Delivering priority event-driven projects in Saudi Arabia

16 May 2025

 

As Saudi Arabia accelerates preparations to host a series of landmark global events, including the 2027 AFC Asian Cup, the 2029 Asian Winter Games in Trojena, Expo 2030 in Riyadh and the Fifa World Cup in 2034, momentum is building across the kingdom’s construction sector to chart out strategies to deliver event-driven projects.

Earlier this week, MEED hosted a panel discussion on the sidelines of the MEED 2025 Saudi Gigaprojects summit in Riyadh that brought together senior stakeholders from fields including architecture, project management, ESG and contracting to address how to deliver event-driven construction schemes.

The session explored how the kingdom can balance ambition with execution, manage complexity, and promote Saudi Arabia as a global hub for international sports and entertainment events.

The consensus was that the success of these large-scale, complex projects depends on early, sustained and transparent collaboration between all stakeholders – from clients and designers to contractors, operators and regulators.

You simply can’t deliver something as complex and time-sensitive as a stadium or expo venue if people are working in silos
Chris Seymour, Mace

Serious coordination is non-negotiable

“Big projects live or die by early engagement,” said Chris Seymour, managing director – Middle East and Africa at Mace, a global consultancy involved in many of the region’s most ambitious schemes.

“You simply can’t deliver something as complex and time-sensitive as a stadium or expo venue if people are working in silos. The earlier you bring the ecosystem together, the more agile and successful the project becomes.”

Seymour highlighted that the challenge is not just scale, but the dynamic and high-pressure environment in which these projects operate.

“Engagement on these megaprojects is difficult to create and maintain, especially when integrating new technologies or fast-tracking delivery. You need to pre-empt issues, adapt quickly and build trust early,” he said, citing hospitality projects as an example of early coordination leading to better performance.

Delivering a venue such as the Prince Mohammed Bin Salman Stadium in Qiddiya demands intense, sustained collaboration across all project layers
Fatemeh Hosseini, Populous

Overcoming the delivery challenges of architecturally complex schemes

"The stadiums designed for Saudi Arabia represent the next generation of sports venues globally, and are architectural statements which will leave a lasting impression on the global stage," said Fatemeh Hosseini, associate at leading global design firm Populous, who spoke about the architectural ambition behind these developments.

“These schemes are extremely large in scale, with highly complex design and engineering requirements,” she said.

“Take the Prince Mohammed Bin Salman Stadium in Qiddiya – its architectural vision is bold, iconic and layered with advanced technology and fan experiences. Delivering such a venue demands intense, sustained collaboration across all project layers.”

Hosseini noted that while Vision 2030 sets a clear ambition, translating that into buildable, operational venues in time for global events is an enormous challenge.

“We need a shared vision and a collaborative delivery model from day one – not just between consultants and contractors, but with operators, planners and city authorities,” she added.

Green buildings don’t just reduce carbon – they also command higher values, improve tenant appeal and future-proof assets
Wesley Thomson, Knight Frank

Sustainability as a strategic imperative

Alongside design excellence and timely delivery, sustainability emerged as a critical theme in the panel discussion. Saudi Arabia’s commitment to environmental responsibility is growing, and mega-events provide an opportunity to demonstrate leadership in green building practices.

“Sustainability is increasingly becoming a value driver in the built environment,” said Wesley Thomson, partner and head of ESG at UK-headquartered firm Knight Frank.

“Green buildings don’t just reduce carbon – they also command higher values, improve tenant appeal and future-proof assets. If we get this right now, it’s a long-term win for Saudi Arabia.”

However, Thomson stressed that the kingdom needs a more robust regulatory framework to meet sustainability goals across the project lifecycle.

“There’s a real need to enhance and enforce green building codes and ESG reporting structures in the kingdom,” he said.

“Coordination and communication on sustainability must be centralised, especially for large, time-critical projects that could easily miss the mark if not carefully managed.”

When contractors are engaged early, they can feed real-world constraints and opportunities into the design process
Michael Al-Kurdi, Albawani

Early contractor involvement is key to success

From a construction delivery perspective, one message rang loud and clear: contractors must be brought to the table early to avoid late-stage risks and costly redesigns.

“When contractors are engaged early, they can feed real-world constraints and opportunities into the design process,” said Mikhael Al-Kurdi, business development and relationship manager at Albawani, one of Saudi Arabia’s leading construction firms.

“Early contractor involvement (ECI) unlocks true collaboration and ensures harmony between vision and feasibility.”

Al-Kurdi noted that early involvement allows contractors to prepare the supply chain more effectively and anticipate delivery risks well in advance.

“It’s not just about feasibility – it’s about preparedness. These are huge, fast-moving projects, and the more aligned the stakeholders are from the outset, the smoother the execution phase will be.”

The panellists agreed that Saudi Arabia has a rare opportunity to reshape its global image through these sporting and cultural mega-events. But with tight deadlines and high global expectations, success will hinge not only on design and engineering innovation but also on collaboration, coordination and clarity of vision.

“We have an opportunity to lead the world – not just in the scale of what we’re building, but in how we build it,” Seymour said. 

“That means doing things differently: being open, integrated and agile. If we can embed that mindset into every stadium, arena and event venue we build, we’ll not just meet the deadlines – we’ll set a new global benchmark.”

https://image.digitalinsightresearch.in/uploads/NewsArticle/13886718/main3604.jpg
Yasir Iqbal
Related Articles
  • Algeria opens bidding for water treatment plant

    15 April 2026

     

    State-owned Cosider Pipelines, part of Algeria’s public infrastructure group Cosider, has issued a tender for the construction of a demineralisation plant in In Salah in Algeria.

    The contract covers the design, supply, installation, testing and commissioning of a plant with a treatment capacity of 62,000 cubic metres a day (cm/d).

    The tender is open to local and international companies specialising in the design and construction of demineralisation and reverse osmosis desalination plants.

    The bid submission deadline is 26 April.

    The project will be located at In Salah, a key industrial area in southern Algeria, where treated water supply is important for both municipal and industrial use.

    Cosider said that individual bidders must demonstrate that they have completed at least one reverse osmosis demineralisation or desalination plant with a capacity of 20,000 cubic metres a day or more.

    They must also show an average annual turnover of at least AD1bn ($7.7m) for their five best years over the past decade.

    For consortium bids, all partners must share full responsibility for the contract, while the lead company must meet the technical and financial requirements.

    Recent projects

    In 2023, MEED reported that Riyadh-based water utility developer Wetico had won two contracts to develop water desalination plants in Algeria.

    Societe Algerienne de Realisation de Projects Industriels (Sarpi) awarded the contract for the El-Tarf desalination plant, while Entreprise Nationale de Canalisations (Enac) is the client for the Bejaja facility.

    Both plants were commissioned in 2025, each with a production capacity of 300,000 cm/d.

    Separately, Wetico was the main contractor on a third plant commissioned last year. The Cap Dijinet 2 seawater desalination plant in Boumerdes province covers 18 hectares and also has a capacity of 300,000 cm/d.

    Like many countries, Algeria is facing pressure on resources due to longer and more frequent droughts. Seawater desalination is seen as a key driver of the government’s strategy to guarantee drinking water supply.

    According to previous reports, the government is planning to build up to six additional plants by 2030.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16404325/main.jpg
    Mark Dowdall
  • WEBINAR: UAE Projects Market 2026

    15 April 2026

    Webinar: UAE Projects Market 2026
    Tuesday, 28 April 2026 | 11:00 GST  |  Register now


    Agenda:

    • Overview of the UAE projects market landscape
    • 2025 projects market performance
    • Value of work awarded 2026 YTD
    • Impact of the Iran conflict on the projects market and real estate, assessing supply chain disruptions, material cost inflation and war risk premiums
    • Key drivers, challenges and opportunities
    • Size of future pipeline by sector and status
    • Ranking of the top contractors and clients
    • Summary of key current and future projects
    • Short and long-term market outlook
    • Audience Q&A

    Hosted by: Colin Foreman, editor of MEED 

    Colin Foreman is editor and a specialist construction journalist for news and analysis on MEED.com and the MEED Business Review magazine. He has been reporting on the region since 2003, specialising in the construction sector and its impact on the broader economy. He has reported exclusively on a wide range of projects across the region including Dubai Metro, the Burj Khalifa, Jeddah Airport, Doha Metro, Hamad International airport and Yas Island. Before joining MEED, Colin reported on the construction sector in Hong Kong.

    Click here to register

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16401868/main.gif
    Colin Foreman
  • Saudi Landbridge finds its moment in Gulf turmoil

    15 April 2026

    Commentary
    Yasir Iqbal
    Construction writer

    The strategic case for the Saudi Landbridge has never been more urgent. SAR’s appointment of Spain’s Typsa as lead design consultant, reported by MEED this week, is more than a procurement milestone. After two decades of delays, it reflects how the long-deferred project has become a strategic necessity.

    The conflict reshaping the Middle East has made that necessity more immediate. Red Sea transits are costly and unpredictable. The Strait of Hormuz carries risk no insurer can fully price. Saudi Arabia’s most valuable exports, including crude oil, refined products, petrochemicals and industrial goods, move almost entirely by sea through routes that are no longer reliably secure.

    The kingdom sits between two coastlines with no rail link connecting them. That gap is now an economic exposure.

    The $27bn project addresses it directly. More than 1,500 kilometres of track, anchored by a 900km railway between Riyadh and Jeddah, will provide direct freight access from King Abdullah Port on the Red Sea, with upgrades to the Riyadh-Dammam line and a new connection to Yanbu.

    Together, they create what Saudi Arabia has never had: a continuous land corridor linking Gulf industrial ports to Red Sea export terminals, entirely within its own borders.

    The commercial implications are substantial. Aramco’s downstream output, Sabic’s chemicals, and the manufacturing clusters of Jubail and Yanbu gain flexible access to both coasts.

    Exporters targeting Europe and the Americas load at Jeddah; those serving Asia pivot east to Dammam by rail, on demand, without Hormuz risk or Red Sea freight surcharges.

    No neighbouring economy has that optionality. The network also underpins a broader economic ambition. Connecting Jeddah, Riyadh, Dammam, Jubail, Yanbu, King Abdullah port and King Khalid airport by rail positions the kingdom as a genuine logistics corridor between East and West. 

    With design now under way and construction tenders expected imminently, the Landbridge is closer to reality than at any point in its troubled history. Regional disruption did not create this project. But it has made the argument for it unanswerable.


    MEED’s April 2026 report on Saudi Arabia includes:

    > COMMENT: Risk accelerates Saudi spending shift
    > GVT &: ECONOMY: Riyadh navigates a changed landscape
    > BANKING: Testing times for Saudi banks
    > UPSTREAM: Offshore oil and gas projects to dominate Aramco capex in 2026
    > DOWNSTREAM: Saudi downstream projects market enters lean period
    > POWER: Wind power gathers pace in Saudi Arabia

    > WATER: Sharakat plan signals next phase of Saudi water expansion
    > CONSTRUCTION: Saudi construction enters a period of strategic readjustment
    > TRANSPORT: Rail expansion powers Saudi Arabia’s infrastructure push

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/16401567/main.png
    Yasir Iqbal
  • Indian firm selected for Saudi sewage treatment project

    15 April 2026

     

    Saudi Arabia’s National Water Company is understood to have recently selected Indian contractor VA Tech Wabag as its preferred bidder for a contract to expand a sewage treatment plant (STP) in Al-Majmaah in Riyadh Province.

    The engineering, procurement and construction (EPC) package for the Al-Majmaah STP has an estimated value of $65m.

    The scope includes the construction of sewage treatment plant units, a pumping station and an effluent surplus line. It also covers the installation of a Scada system, supervisory control systems and associated facilities.

    As MEED understands, six bids were submitted last year, including from local firms Alkhorayef Water & Power Technologies, Al-Rafia Contracting, Civil Works Company, Saudi Sdn Water & Energy and Washnah Trading & Contracting.

    The project forms part of Saudi Arabia’s broader push to expand treatment and reuse infrastructure under Vision 2030, particularly across the Riyadh region.

    MEED recently revealed that NWC had awarded an EPC contract for the latest phase of its long-term operations and maintenance sewage treatment programme.

    The contract to build and upgrade sewage treatment plants with a combined capacity of about 440,000 cubic metres a day was awarded to a consortium led by China’s Jiangsu United Water Technology.

    Elsewhere, a joint venture of Kuwait-based Heavy Engineering Industries & Shipbuilding and Wabag is awaiting the formal contract award for phase two of Kuwait’s Doha seawater desalination plant project.

    The firms submitted the lowest bid of $373.2m for the project last year.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16401155/main.jpg
    Mark Dowdall
  • SAR extends phosphate rail track deadline

    15 April 2026

     

    Saudi Arabian Railways (SAR) has extended the bid submission deadline to 26 April for a multibillion-riyal tender to double the tracks on the existing phosphate transport railway network connecting the Waad Al-Shamal mines to Ras Al-Khair in the kingdom’s Eastern Province.

    The new tender – covering the second section of the track-doubling works and spanning more than 150 kilometres (km) – was issued on 9 February. The previous bid submission deadline was 15 April.

    The new tender follows SAR receiving bids from contractors on 1 February for the project’s first phase, which spans about 100km from the AZ1/Nariyah Yard to Ras Al-Khair.

    The scope includes track doubling, alignment modifications, new utility bridges, culvert widening and hydrological structures, as well as the conversion of the AZ1 siding into a mainline track. It also includes support for signalling and telecommunications systems.

    The tender notice was issued in late November, with a bid submission deadline of 20 January 2026.

    Switzerland-based engineering firm ARX is the project consultant.

    MEED understands that these two packages are the first of four that SAR is expected to tender for the phosphate railway line. Other packages expected to be tendered shortly include the depot and systems packages.

    In 2023, MEED reported that SAR was planning two projects to increase its freight capacity, including an estimated SR4.2bn ($1.1bn) project to install a second track along the North Train Freight Line and construct three new freight yards.

    Formerly known as the North-South Railway, the North Train is a 1,550km-long freight line running from the phosphate and bauxite mines in the far north of the kingdom to the Al-Baithah junction. There, it diverges into a line southward to Riyadh and a second line running east to downstream fertiliser production and alumina refining facilities at Ras Al-Khair on the Gulf coast.

    Adding a second track and the freight yards will significantly increase the network’s cargo-carrying capacity and facilitate increased industrial production. Project implementation is expected to take four years.

    State-owned SAR is also considering increasing the localisation of railway materials and equipment, including the construction of a cement sleeper manufacturing facility.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16400986/main.jpg
    Yasir Iqbal