Contractors submit bids on five major oil projects in Kuwait
6 October 2025

Register for MEED’s 14-day trial access
Contractors have submitted bids on five major oil projects in Kuwait worth a combined total of $6.55bn, increasing market confidence in activity in the country’s energy sector.
India’s Larsen & Toubro submitted the lowest bid on two contracts, while Spain’s Tecnicas Reunidas submitted the lowest bid on another.
Kuwait’s Combined Group Contracting (CGC) submitted the lowest bids for the remaining two contracts.
The first project focuses on developing two facilities: Separation Gathering Centre 1 (SGC-1) and Water Injection Plant 1 (WIP-1).
Tecnicas Reunidas submitted a low bid worth $2.47bn for this project.
The Spanish company also submitted another bid worth $2.55bn.
One of the prices submitted was its base option and the second was an alternative, according to industry sources.
The full list of bidders for this project was:
SGC-1
- Tecnicas Reunidas – KD754,288,464.875 ($2.47bn)
- Tecnicas Reunidas – KD778,440,100.072 ($2.55bn)
- Larsen & Toubro – KD812,937,222.000 ($2.66bn)
The second project is focused on developing SGC‑3 and WIP‑3; a low bid of $2.48bn was submitted by Larsen & Toubro.
The full list of bidders was:
SGC-3
- Larsen & Toubro – KD757,000,316.000 ($2.48bn)
- Sinopec Luoyang Engineering – KD855,058,903.888 ($2.80bn)
The third project covers the development of effluent water disposal plants for injector wells.
The plants, known as EWDP-1 and EWDP-2, are part of a broader upstream expansion scheme.
Larsen & Toubro is the frontrunner to win this contract with a bid of $1.30bn.
The full list of bidders was:
EWDP
- Larsen & Toubro – KD396700353.000 ($1.30bn)
- Petrofac International – KD414,170,442.000 ($1.36bn)
The fourth project relates to a new network for injecting effluent water in North Kuwait’s Rawdatain region.
CGC submitted a bid of KD23.7m ($77.5m). The scheduled duration of the project is 30 months.
The full list of bidders was:
New North Kuwait Effluent Water Injection Network for the Rawdatain Area
- Combined Group Contracting Company (CGC) – KD23,700,000 ($77.5m)
- Heavy Engineering Industries & Shipbuilding Company (Heisco) – KD28,000,000
- Mechanical Engineering & Contracting Company (MECC) – KD44,000,000
- Megha Engineering & Infrastructure – KD63,900,000
The fifth project is related to a new network for injecting effluent water into northern Kuwait in the Sabriya/Bahra area.
CGC submitted a bid of KD36.0m ($117.7m) for the project, which has a duration of 30 months.
The full list of bidders was:
New North Kuwait Injection Network for SA/BA Area
- CGC – KD36,000,000 ($117.7m)
- Heisco – KD46,100,000
- MECC – KD64,300,000
- Megha Engineering & Infrastructure – KD86,310,000
All five contracts were tendered by Kuwait’s state-owned upstream operator, Kuwait Oil Company (KOC).
Bids were submitted ahead of a deadline on 30 September.
On 19 September, MEED reported that KOC was planning to close bidding for the SGC projects before the end of the month.
Exclusive from Meed
-
Kuwait on track to hit oil production target7 October 2026
-
Al-Yamamah signs Saudi 380kV transmission deals6 October 2026
-
Eagle Hills plans new Syria projects6 October 2026
-
-
Dubai issues PMC tender for four stormwater projects6 October 2026
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Kuwait on track to hit oil production target7 October 2026
Kuwait is on track to meet its target of having 4 million barrels a day (b/d) of oil production capacity by 2035, according to Kuwait Petroleum Corporation (KPC) chief executive Shaikh Nawaf Al-Sabah.
Al-Sabah also said Kuwait is on course to increase non-associated gas production to 2 billion cubic feet a day by 2040.
His comments come amid an ongoing crisis in Kuwait’s oil and gas sector linked to the regional conflict that began when the US and Israel attacked Iran on 28 February.
The subsequent war has significantly disrupted shipping through the Strait of Hormuz, which is a crucial export route for Kuwaiti crude oil.
Kuwait is currently producing around 2 million b/d of oil, down from 2.6 million b/d before the US and Israel attack.
Speaking at a conference in London, Al-Sabah said: “We have the capacity to go back up to our current maximum sustainable capacity of 3 million b/d, if we have the export routes available, and this comes down to the ability to move oil through the Strait.”
KPC is investing $9bn-$10bn a year in capital expenditure to meet its oil and gas production goals, according to Al-Sabah.
He said: “We are doing this because we recognise that it is our hydrocarbons that will be most in demand a decade from now, and two decades from now – in fact, for the rest of our lifetimes.”
Project Seef
KPC is pushing ahead with the Al-Seef project, which focuses on developing three large offshore oil discoveries, Al-Sabah said.
The offshore fields are known as Nokhatha, Julaia and Jazza. The development was first announced in February this year, about two weeks before the US and Israel attack on Iran.
Al-Sabah said KPC is continuing with the project and believes the three fields collectively hold more than 3 billion barrels of recoverable oil.
He said: “We are asking international oil companies to partner with us to develop those resources under an operating services contract.
“So, we’re moving ahead according to the exact same schedule that we had put together even before the war began.”
Al-Sabah did not say which international oil companies KPC has approached to help develop the three offshore fields.
READ THE OCTOBER 2026 MEED BUSINESS REVIEW – click here to view PDFIndustry and logistics drive development at Neom; Saudi Arabia’s investment priorities realign amid conflict; MEED’s 2026 power developer ranking.
Distributed to senior decision-makers in the region and around the world, the October 2026 edition of MEED Business Review includes:
> AGENDA: Oxagon takes centre stage at Neom> MARKET FOCUS: Saudi projects hold steady> INDUSTRY REPORT: MEED’s 2026 GCC power developer ranking> LEADERSHIP: The future city does not need to hang above the groundTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/20315147/main.jpg -
Al-Yamamah signs Saudi 380kV transmission deals6 October 2026
Riyadh-headquartered Al-Yamamah Steel Industries has signed two supply contracts with Algihaz Contracting Company for the construction of 380kV ultra-high-voltage transmission lines in Saudi Arabia’s Western Region.
The contracts cover the supply of steel towers and are worth a combined SR254.28m ($67.8m).
In a disclosure to the Saudi Exchange (Tadawul), the firm said the first contract is valued at SR135.65m ($36.2m), while the second is worth SR118.63m ($31.6m).
Both contracts have a one-year duration, with supply scheduled to begin in March 2027. The financial impact of the contracts is expected to start appearing in Al-Yamamah Steel’s results in the first quarter of 2027.
Algihaz is currently carrying out construction works for several transmission projects, including Saudi Energy’s $206m Bisha 380/132kV BSP connection project, for which it was appointed the main contractor in 2025.
The project involves a double-circuit 380kV overhead transmission line connecting the Bisha PV bulk supply point to the existing bulk supply points in Aseer Province.
The deals also add to a series of steel tower contracts secured by Al-Yamamah Steel for 380kV transmission projects in the Western Region.
In September, the company signed a SR103.14m ($27.5m) contract with the Saudi branch of National Power Construction Corporation to supply steel towers for a 380kV ultra-high-voltage line. Supply under that contract is due to begin in February 2027.
Al-Yamamah Steel also signed a SR176.48m ($47.1m) contract in November 2025 with Arabian Electrical Transmission Line Construction Company to supply steel towers for another 380kV ultra-high-voltage line in the Western Region.
The company has expanded its tower production capacity in recent years to meet expected demand for steel towers used in electricity transmission lines. Its 2024 annual report said it had added production lines and a galvanising plant in Jeddah Industrial City for this purpose.
READ THE OCTOBER 2026 MEED BUSINESS REVIEW – click here to view PDFIndustry and logistics drive development at Neom; Saudi Arabia’s investment priorities realign amid conflict; MEED’s 2026 power developer ranking.
Distributed to senior decision-makers in the region and around the world, the October 2026 edition of MEED Business Review includes:
> AGENDA: Oxagon takes centre stage at Neom> MARKET FOCUS: Saudi projects hold steady> INDUSTRY REPORT: MEED’s 2026 GCC power developer ranking> LEADERSHIP: The future city does not need to hang above the groundTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/20308551/main.jpg -
Eagle Hills plans new Syria projects6 October 2026
Abu Dhabi-based real estate developer Eagle Hills has signed a framework agreement with Syria’s Ministry of Public Works & Housing to develop a series of residential and tourism community projects across several Syrian governorates.
The first phase will include Damascus Heights in the capital and Latakia Yachts & Marina on the Mediterranean coast.
Damascus Heights is planned as a mixed-use community comprising homes, retail, hospitality and business facilities, supported by schools, healthcare services, green areas and resident amenities.
Latakia Yachts & Marina is planned as a waterfront destination anchored by a marina, with homes, hotels, branded residences and leisure offerings.
During development and operation, the projects are expected to support economic activity and tourism, create jobs across construction, hospitality and services, and add new housing, community facilities and tourism infrastructure.
Syrian professionals and businesses are expected to play a central role in both delivery and operations, creating opportunities for contractors, suppliers and service providers, strengthening local supply chains and SMEs, and supporting skills development and knowledge transfer.
Eagle Hills is also inviting applications for investment participation from Syrians in Syria and abroad, with priority for qualified Syrian individuals, businesses and institutions.
Following the signing, both projects will proceed to implementation, with enabling and construction works expected to begin shortly in Damascus and Latakia.
READ THE OCTOBER 2026 MEED BUSINESS REVIEW – click here to view PDFIndustry and logistics drive development at Neom; Saudi Arabia’s investment priorities realign amid conflict; MEED’s 2026 power developer ranking.
Distributed to senior decision-makers in the region and around the world, the October 2026 edition of MEED Business Review includes:
> AGENDA: Oxagon takes centre stage at Neom> MARKET FOCUS: Saudi projects hold steady> INDUSTRY REPORT: MEED’s 2026 GCC power developer ranking> LEADERSHIP: The future city does not need to hang above the groundTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/20308460/main.jpg -
Contractors submit revised bids for Dukhan field facilities upgrade6 October 2026

Contractors have submitted revised proposals to QatarEnergy for a key tender to upgrade facilities at the Dukhan oil field in Qatar, about 80 kilometres west of Doha.
Following the submission of the initial round of bids for the project on 9 August, QatarEnergy requested revised proposals from contractors, which they submitted by 27 September, sources told MEED.
The following local contractors, among others, are understood to be bidding for the DPFU Phase 1B (Part 2) tender, according to information obtained by MEED Projects:
- Doha Petroleum Construction Company (Dopet)
- Galfar Al-Misnad Engineering & Contracting
- Qatar Engineering & Construction Company (Q-con)
QatarEnergy originally stipulated a bond validity of 150 days (until 23 December) and a bid validity of 120 days (until 23 November) for the project.
The engineering, procurement, installation and commissioning scope covers upgrades to 56 oil manifolds, 108 gas-lift manifold slots, chemical injection systems and key pumping facilities, along with associated piping, instrumentation, control, electrical and civil works.
The scope includes the demolition of obsolete equipment, degassing station enhancements, and full testing and handover. It also encompasses additional capacity enhancement works under Part 3, mainly the installation of new oil export and produced-water transfer pumps, along with supporting facility modifications.
The project involves complex interfaces and shutdown-critical activities, requiring expertise in live-plant integration.
QatarEnergy issued the tender for the DPFU Phase 1B (Part 2) project on 8 June and initially set a bid submission deadline of 26 July, later extending it to 9 August.
Dukhan, Qatar’s first and only onshore oil field, was discovered in 1938, with oil production starting in 1939-40. The country currently produces about 1.8 million barrels a day (b/d) of crude, with the Dukhan field accounting for about 350,000 b/d.
The Dukhan oil field covers about 80km by 8km and consists of four reservoirs: Khatiyah, Fahahil, Jaleha and Diyab. The first three are oil reservoirs. The more recently developed Diyab reservoir contains non-associated gas and is estimated to hold around 2 billion barrels of crude oil reserves. Diyab lies on Dukhan’s southern flank.
ALSO READ: QatarEnergy selects contractors for offshore oil field expansion
https://image.digitalinsightresearch.in/uploads/NewsArticle/20306273/main5440.jpg -
Dubai issues PMC tender for four stormwater projects6 October 2026

Dubai Municipality has invited consultants to bid for a contract to provide construction supervision services for four stormwater projects.
The bid submission deadline is 29 October.
All four projects are part of the municipality’s Tasreef programme, intended to increase Dubai’s rainwater drainage capacity by 700% by 2033 and provide capacity for the emirate’s needs for the next 100 years.
The tender for TF-06-S1 Supervision of Stormwater Drainage System Projects – Package 4 was issued on 6 October.
The consultancy covers the following projects:
- TF-06-C1: Construction of a stormwater pond connecting Al-Maktoum Airport and Dubai South
- TF-06-C2: Construction of a stormwater drainage system connecting Al-Maktoum Airport and Dubai South
- TF-07-C1: Construction of a stormwater drainage system on Sheikh Zayed Bin Hamdan Road connecting developers
- TF-24-C1: Connecting developers’ areas to the stormwater networks in Dubailand
In documents seen by MEED, the municipality said it will require a dedicated supervision team for each project.
The consultancy will cover construction supervision, including the deployment of resident engineers, civil engineers, inspectors, quantity surveyors, land surveyors and planning engineers. Mechanical engineers will also be required, along with health and safety personnel and NOC engineers, depending on the project.
TF-07-C1 is the same strategic stormwater drainage project that Dubai Municipality recently tendered for construction, with contractors preparing to submit bids on 22 October.
The project covers more than 100 million square metres between Sheikh Mohammed Bin Zayed Road and Emirates Road, and from Expo Road to Dubailand.
It will provide stormwater infrastructure and service connections for more than 20 private developers and Al-Yalayis 5, as well as supporting major roads in the Jebel Ali area. The construction scope includes a major gravity drainage system with pipeline diameters of up to 3,000mm.
TF-24-C1 is one of three water infrastructure tenders issued by the municipality in August, as reported by MEED. The project will connect developers’ areas in Dubailand to the stormwater network. It includes 18 kilometres (km) of stormwater drainage pipelines with diameters of up to 1,800mm and 3.5km of gravity sewer pipelines with diameters of up to 1,000mm.
Bidding for the engineering, procurement and construction contract was recently extended to 1 October, with Nael Construction & Contracting and Al-Nasr Contracting Company among those expected to make an offer for the project.
READ THE OCTOBER 2026 MEED BUSINESS REVIEW – click here to view PDFIndustry and logistics drive development at Neom; Saudi Arabia’s investment priorities realign amid conflict; MEED’s 2026 power developer ranking.
Distributed to senior decision-makers in the region and around the world, the October 2026 edition of MEED Business Review includes:
> AGENDA: Oxagon takes centre stage at Neom> MARKET FOCUS: Saudi projects hold steady> INDUSTRY REPORT: MEED’s 2026 GCC power developer ranking> LEADERSHIP: The future city does not need to hang above the groundTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/20305174/main.jpg