Contractors submit bids for next Upper Zakum field expansion
28 November 2025

Register for MEED’s 14-day trial access
Contractors have submitted technical proposals for the next expansion phase of the Upper Zakum offshore field development in Abu Dhabi, aimed at increasing the asset’s oil production potential to 1.5 million barrels a day (b/d).
The offshore oil and gas production business of Abu Dhabi National Oil Company (Adnoc Offshore) is understood to have issued the main tender for engineering, procurement and construction (EPC) works for the UZ 1.5MMBD project in the third quarter of this year, according to sources.
Adnoc Offshore has divided the project's EPC scope of work into three packages, according to sources.
Contractors submitted technical bids for package 1 by 21 November, while proposals for packages 2 and 3 were submitted by 14 November, sources told MEED.
MEED reported last November that Adnoc Offshore had awarded a contract for front-end engineering and design (feed) and pre-feed services on the project to France-headquartered contractor Technip Energies.
A kick-off meeting between Adnoc Offshore and Technip Energies took place on 21 November last year, it was previously reported.
Located 84 kilometres offshore in Abu Dhabi, Upper Zakum is the world’s second-largest offshore oil field and fourth-largest oil field.
The UZ 1.5MMBD project is the latest crude output expansion project that Adnoc Offshore has undertaken at the Upper Zakum field development.
Upper Zakum expansion
The first phase of the programme to raise the Upper Zakum offshore field development’s oil production capacity to 1.2 million b/d was launched in 2019. The initial goal was to increase the field’s output potential to 1 million b/d by 2024, which was later increased to 1.2 million b/d, with the project execution timeline eventually extended.
In April last year, MEED reported that Adnoc Offshore had awarded the main EPC contract for the UZ 1.2MMBD EPC-1 project to UAE-based Target Engineering Construction Company. The value of the contract was estimated to be $825m.
The project’s main scope involved the EPC of several surface facilities and plants at the Upper Zakum offshore development’s four main artificial islands: Al-Ghallan, Umm Al-Anbar, Ettouk and Asseifiya – also known as Central Island, West Island, North Island and South Island, respectively.
Spanish contractor Tecnicas Reunidas won the contract for the feed works on the UZ 1.2MMBD EPC-1 project in 2019. UK-headquartered Wood Group was appointed as the project management consultant for the EPC phase.
In November 2024, MEED reported that Adnoc Offshore had also selected Target for the second phase of the Upper Zakum 1.2 million b/d project (UZ 1.2MMBD EPC-2). The value of the contract was estimated to be about $500m, according to sources.
Target began work on the project in December last year, MEED previously reported.
The scope of work on the UZ 1.2MMBD EPC-2 project covers the EPC of several structures on Assefiya Island.
Adnoc Offshore performed the feed work on the UZ 1.2MMBD EPC-2 project in-house.
Upper Zakum oil production
Adnoc Offshore has committed to a total capital expenditure budget of approximately $30bn, along with its operating partners in the Upper Zakum hydrocarbons concession, Japan Oil Development Company (Jodco) and US-based ExxonMobil.
The strategic objective is to first raise the asset’s oil output from 640,000 b/d to 750,000 b/d through the UZ 750 project, then to 1.2 million b/d through the two phases of the ongoing UZ 1.2MMBD project, and eventually to 1.5 million b/d.
Zakum Development Company (Zadco), which later merged into Adnoc Offshore, awarded EPC contracts for the UZ 750 project in 2012 and early 2013.
The $817m first package was awarded to a consortium of Abu Dhabi’s NMDC Energy (then known as National Petroleum Construction Company) and Technip Energies. Package two, the project’s largest EPC package, worth $3.7bn, was awarded to a consortium of UK-headquartered Petrofac and South Korea’s Daewoo Shipbuilding & Engineering.
EPC work on UZ 750 began in 2014 and was completed in 2022.
In October 2022, Adnoc Group subsidiary Adnoc Drilling set a world record for drilling the longest oil and gas well at the Upper Zakum concession, stretching 50,000 feet.
The extended-reach wells will tap into an undeveloped part of the Upper Zakum reservoir, potentially increasing the field’s production capacity by 15,000 b/d without expanding or building any new infrastructure, Adnoc said.
ALSO READ: Adnoc strives to build long-term upstream potential
Exclusive from Meed
-
Local contractor wins Saudi substation deal3 December 2025
-
SEC signs $347m power works deal for Soudah Peaks3 December 2025
-
Jeddah Economic Company appoints new CEO3 December 2025
-
Saudi Arabia approves 2026 state budget3 December 2025
-
Buro Happold appointed for Riyadh expo masterplan3 December 2025
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Local contractor wins Saudi substation deal3 December 2025
Saudi-based Nesma Infrastructure & Technology has signed a contract with state-owned utility Saudi Electricity Company (Sec) for the replacement of the Jubail Southeast 230/115/34.5kV substation.
The project includes overhead transmission line (OHTL) works and is valued at more than SAR 840m ($224m). It is scheduled to be delivered within 20 months.
The award form part of Sec's ongoing programme to upgrade ageing substations and reinforce network capacity in the Jubail industrial area.
In September, local contractor Al-Fanar Projects was appointed to replace the Jubail South West 230/115KV substation, one of several transmssion assets in the region undergoing phased renewal.
As MEED recently reported, Sec has plans to invest SR220bn ($58.7bn) in power projects by 2030. This includes SR135bn ($36bn) and SR85bn ($22.7bn) for transmission and distribution, respectively.
According to the utility, its planned upgrades will cover 130 high-voltage substations, 135,000 MVA of capacity, 12,900 kilometres of overhead transmission lines and 1,100km of underground cables.
https://image.digitalinsightresearch.in/uploads/NewsArticle/15195824/main.jpg -
SEC signs $347m power works deal for Soudah Peaks3 December 2025
Register for MEED’s 14-day trial access
Saudi Electricity Company (SEC) has announced that its transmission subsidiary, National Grid, has signed a SR1.3bn ($347m) agreement with Soudah Development to deliver the electrical infrastructure for Saudi Arabia’s Soudah Peaks project.
Soudah Peaks is a major high-altitude tourism and real estate development in the Asir mountains, led by Soudah Development, a wholly owned Public Investment Fund (PIF) company.
The $7.7bn project includes hotels, resorts, residential units, entertainment facilities and outdoor activity zones at elevations of up to 3,000 metres. It will be developed over three phases, with full completion scheduled for 2033.
Under the agreement, National Grid will develop a full integrated electrical network to support the project’s phased construction.
The scope includes a central 380/132kV transmission substation with a capacity of 500MVA and two 13.8/132kV substations. The company will also build the electrical interconnection needed to supply all stages of the development.
The first phase of the initiative will see the development of 454 residential units, 1,010 hotel keys and retail space with a gross leasable area of 20,625 square metres by 2027.
The overall project includes the development of six main areas: Red Rock Mountain, Tahlal gateway to Soudah Peaks, Sahab, Sabrah, Jareen and Rijal.
https://image.digitalinsightresearch.in/uploads/NewsArticle/15194632/main.jpg -
Jeddah Economic Company appoints new CEO3 December 2025
Register for MEED’s 14-day trial access
Jeddah Economic Company (JEC), the developer of the world’s tallest tower project, has appointed Fabian Toscano as its new CEO.
In an official statement, JEC said: “Toscano will lead the next phase of development for Jeddah Economic City and the Jeddah Tower. His focus will include accelerating development activity, strengthening global collaborations, and shaping a world-class destination aligned with the ambitions of Saudi Vision 2030.”
Toscano has previously served as the CEO of AlUla Development Company.
Last year, JEC signed an estimated SR8bn, 42-month contract with SBG to resume construction work on the tower. SBG then began engaging with the supply chain to work on the project. SBG awarded Beijing-headquartered Jangho Group a facade works contract that involves engineering design and technical services for the project’s structural glass and adhesive curtain walls.
At the time, Jeddah Tower’s superstructure was about one-third complete, with 63 floors out of a total 157. SBG was the main contractor on the project in the early and mid-2010s. Germany’s Bauer completed the tower’s piling work.
The architect is US-based Adrian Smith & Gordon Gill, and the engineering consultant is Lebanon’s Dar Al-Handasah (Shair & Partners).
Jeddah Tower is the centrepiece of the Jeddah Economic City development. The project’s first phase, which includes the main tower, covers an area of 1.5 million square metres.
https://image.digitalinsightresearch.in/uploads/NewsArticle/15194477/main.gif -
Saudi Arabia approves 2026 state budget3 December 2025
Saudi Arabia has approved a SR1.313tn ($349bn) state budget for fiscal year 2026, maintaining an expansionary spending stance as it pursues its Vision 2030 economic transformation agenda.
The Ministry of Finance’s Final Budget Statement, released on 2 December, projects revenues of SR1.147tn, leaving an estimated deficit of SR165bn, equivalent to about 3.3% of GDP. The figures are broadly in line with the projections set out in October’s pre-budget statement.
Finance Minister Mohammed Aljadaan said the 2026 budget underlines Riyadh’s commitment to sustaining economic diversification and social development while preserving fiscal sustainability over the medium term. He stressed that citizens remain the core focus of spending plans, with continued allocations for education, health and social services, alongside investments in infrastructure and quality-of-life improvements across the kingdom’s regions.
Non-oil activities are expected to remain the main engine of growth. Initial estimates for 2025 point to a 5% expansion in non-oil GDP, supported by higher investment and consumption, while real GDP is forecast to grow by 4.6% in 2026, driven primarily by non-oil sectors.
Public debt is projected to rise to SR1.457tn in 2025 (31.7% of GDP) and SR1.622tn in 2026 (32.7% of GDP). Aljadaan said the debt profile remains sustainable by international standards and confirmed that the government will continue to tap local and international debt markets and alternative financing channels to cover the deficit and refinance maturing obligations.
Government reserves held at the Saudi Central Bank are expected to remain stable at around SR390bn through the end of 2026, supporting the kingdom’s capacity to absorb external shocks. The minister said ongoing structural and fiscal reforms have strengthened public finance management and enhanced the resilience of the Saudi economy amid a challenging and uncertain global environment.
https://image.digitalinsightresearch.in/uploads/NewsArticle/15194673/main.gif -
Buro Happold appointed for Riyadh expo masterplan3 December 2025
Register for MEED’s 14-day trial access
Saudi Arabia’s Expo 2030 Riyadh Company (ERC), which is tasked with delivering the Expo 2030 Riyadh venue, has signed a contract with UK-based engineering firm Buro Happold.
Buro Happold will provide detailed design services for infrastructure works, utilities, the public realm, landscape and engineering, as well as technical support during construction.
According to an official statement published on its website, Buro Happold said that it is coordinating with Expo 2030’s concept master planner, Lava.
The company is also coordinating with other firms working on the project. These include: 9e Global, Barc Solutions, Christine Losecaat MBE, Design Confidence, DPA Lighting, Expo Pavilion Group, Event Planning Group, Gorgeous Group, LAND Italia, LAND Research Lab, Montana, Omrania, Plan A, REDAS, Samantha Cotterell, Schlaich Bergermann Partner, Space Agency, Think Hospitality, Thornton Tomasetti, Transsolar KlimaEngineering, Tricon and Linesight.
The masterplan encompasses an area of 6 square kilometres, making it one of the largest sites designated for a World Expo event. Situated to the north of the Saudi capital, the site will be located near the future King Salman International airport, providing direct access to various landmarks within Riyadh.
Countries participating in Expo 2030 Riyadh will have the option to construct permanent pavilions. This initiative is expected to create opportunities for business and investment growth in the region.
The expo is forecast to attract more than 40 million visitors.
The Public Investment Fund (PIF), Saudi Arabia’s sovereign wealth vehicle, launched ERC in June as a wholly owned subsidiary to build and operate facilities for Expo 2030.
In a statement, the PIF said: “During its construction phases, Expo 2030 Riyadh and its legacy are projected to contribute around $64bn to Saudi GDP and generate approximately 171,000 direct and indirect jobs. Once operational, it is expected to contribute approximately $5.6bn to GDP.”
In November, MEED exclusively reported that contractors submitted commercial bids on 23 November for the tender to undertake the initial infrastructure works at the site.