Contractors extend bid validity for Jafurah fourth expansion phase

6 January 2026

 

Contractors have extended the validity of their bids submitted to Saudi Aramco for engineering, procurement and construction (EPC) works on the fourth expansion phase of the Jafurah unconventional gas development in Saudi Arabia until the end of February this year.

The main scope of work on the Jafurah fourth expansion phase project involves the EPC of three gas compression plants at the giant gas basin in the kingdom’s Eastern Province. Each plant will be able to process up to 200 million cubic feet a day (cf/d).

Contractors submitted proposals for the Jafurah fourth expansion phase project by the deadline of 15 January last year, MEED previously reported. Following the submission of bids, Aramco initially requested contractors to extend the validity of their bids until the end of September as it needed more time to evaluate those proposals, it was earlier reported.

The Saudi energy giant then asked contractors to extend the validity of their base proposals until February, with the bidders complying with that request, according to sources.

Along with requesting bidders for a bid validity extension for a second time, Aramco also sought an alternate set of commercial proposals from contractors, as per sources. Bidders submitted the second price option to the client in December, they added.

According to sources, the following contractors are among those that are understood to have submitted bids for the project:

  • Larsen & Toubro Energy Hydrocarbon (India) / China Petroleum Engineering and Construction
  • Samsung E&A (South Korea)
  • Tecnicas Reunidas (Spain) / Sinopec Group (China)

Aramco issued the main tender for the estimated $2bn-$2.5bn contract in July 2024, MEED previously reported.

Contractors invited to bid for the contract were initially set a deadline of 15 October that year for submission of technical bids and their In-Kingdom Total Value Add (IKTVA) credentials. Commercial bids were due to be submitted by 31 October, with the deadline extended until 31 December, and then until 15 January, 2025.

The detailed scope of work on the Jafurah fourth expansion phase involves the EPC of the following process and utilities units at the south field of the Jafurah reserve:

  • Three gas compression trains of 200 million cf/d capacity each, measuring 400 by 400 metres
  • Gas compression plant inlet area
  • Gas compression plant condensate and produced-water handling
  • Instrumentation and plant air unit
  • Nitrogen generation unit
  • Raw/potable/water utilities
  • Chemical injection systems
  • Diesel systems
  • Flare and flare gas recovery systems
  • Gas compression plant burn pit
  • Closed drain system
  • Oily water system
  • Sanitary water system
  • Stormwater system
  • Firewater system
  • Fire and gas protection system
  • All buildings located within the gas compression plant, excluding security buildings
  • Outside battery limit buildings

The bid evaluation process for the Jafurah fourth expansion phase project is taking place as Aramco prepares to issue the main tender for EPC works on the fifth expansion phase of the mammoth Jafurah unconventional gas development programme.

Aramco completed the solicitation of interest process with contractors for the main EPC tendering round for the Jafurah fifth expansion phase project in November, MEED recently reported.

UK-headquartered Wood Group has carried out the front-end engineering and design (feed) on the fifth expansion phase.

Jafurah gas development phases

The Jafurah basin is the largest liquid-rich shale gas play in the Middle East, spanning around 17,000 square kilometres. The reserve is estimated to contain 229 trillion cubic feet of gas and 75 billion stock-tank barrels of condensate.

Aramco, in early December, brought the greenfield Jafurah gas processing plant online, with a production capacity of 450 million cf/d, marking the commissioning of the first phase of its $100bn capital expenditure programme to produce gas from the unconventional resource base.

The Saudi oil behemoth had earlier stated it expected to start gas production at Jafurah in 2025, with the intention of progressively ramping up to 2 billion cf/d of sales gas, 420 million cf/d of ethane, and 630,000 barrels a day (b/d) of high-value liquids by 2030.

Aramco has said its unconventional gas programme at peak production is expected to generate electricity equivalent to displacing 500,000 b/d of oil.

Progress on the fourth and fifth expansion phases of the Jafurah unconventional gas development programme continues, as EPC work on the third phase advances.

In July 2024, Aramco issued a non-binding letter of intent to a consortium of Tecnicas Reunidas and Sinopec Group for the EPC contract for the Jafurah third expansion phase. The value of the contract is estimated to be $2.24bn.

The objective of the third expansion phase of Jafurah is similar to that of the fourth phase of development. The main scope of work involves the EPC of three gas compression plants, each with a capacity of 200 million cf/d.

The third phase’s scope of work also includes building a 230kV substation to power the new gas compression plants and installing other utilities units, piping systems and safety equipment.

The selection of contractors for the third expansion phase of the Jafurah development came within weeks of Aramco officially awarding EPC contracts for the second expansion phase, which aims to raise its processing potential to up to 2 billion cf/d of raw gas produced from the Jafurah field.

Aramco awarded 16 contracts, worth a combined total of about $12.4bn, for the second expansion phase on 30 June 2024.

The EPC scope of work on the project involves the construction of gas compression facilities and associated pipelines and the expansion of the Jafurah gas plant, including the construction of gas processing trains, utilities, sulphur and export facilities, Aramco said in a statement.

The main EPC packages of the Jafurah second expansion phase project, their estimated values and the selected contractors are:

  • Package 1 – gas processing plant and main process units – $2.9bn: Larsen & Toubro Energy Hydrocarbon (India)
  • Package 2 – utilities and offsites – $2.4bn: Hyundai Engineering (South Korea)
  • Package 3 – gas compression units – $1bn: Larsen & Toubro Energy Hydrocarbon
  • Riyas natural gas liquids (NGL) package 1 – NGL fractionation trains – $1bn: Tecnicas Reunidas / Refining & Chemical Engineering Group (part of China’s Sinopec Group)
  • Riyas NGL package 2 – utilities, storage and export facilities – $2.2bn: Tecnicas Reunidas/Refining & Chemical Engineering Group
  • Riyas NGL package 6 – site preparation works – $107mMofarreh Alharbi & Partners (Saudi Arabia)
  • Riyas NGL package 9 – temporary construction facilities – $80mMofarreh Alharbi & Partners

Aramco kickstarted EPC works on the first phase of the programme in November 2021 by awarding $10bn-worth of subsurface and EPC contracts.

In February 2020, Aramco received a capital expenditure grant of $110bn from the Saudi government for the long-term phased development of the Jafurah unconventional gas resource base.

The Jafurah unconventional gas development programme is central to Aramco’s goal of increasing gas production capacity. The target has recently been raised to 80%, with 2021 as the baseline, up from 60%, to meet rising domestic and global demand. The company expects life-cycle investment in Jafurah to exceed $100bn.

Prior to the commissioning of the Jafurah gas plant in the last quarter of this year, Aramco completed an $11bn lease-and-leaseback deal in late October for gas processing facilities at the Jafurah unconventional gas reserve with a consortium led by funds managed by Global Infrastructure Partners (GIP), part of US asset manager BlackRock.

Under the transaction, which Aramco started in August, a newly formed subsidiary – Jafurah Midstream Gas Company (JMGC) – will lease development and usage rights to the Jafurah field gas processing plant and the Riyas natural gas liquids (NGL) fractionation facility.

After 20 years, JMGC will lease the assets back to Aramco. JMGC will collect a tariff payable by Aramco in exchange for granting Aramco the exclusive right to receive, process and treat raw gas from the Jafurah resource base.

Aramco will hold a 51% majority stake in JMGC, while the GIP-led consortium will hold the remaining 49%. Investors participating in the GIP-led consortium include Hassana Investment Company, The Arab Energy Fund (TAEF) and Aberdeen Investcorp Infrastructure Partners, as well as other institutional investors from North and Southeast Asia and the Middle East.

https://image.digitalinsightresearch.in/uploads/NewsArticle/15372909/main3958.jpg
Indrajit Sen
Related Articles
  • Executive briefing: US-Israel-Iran conflict

    6 March 2026

    Download the briefing

    In this executive briefing, Ed James and Colin Foreman from MEED outline the key developments in the US-Israel-Iran conflict and examine the potential economic, infrastructure and market impacts across the Middle East.

    Drawing on regional data and analysis, the briefing explores the drivers behind the escalation, the scale of attacks across GCC states, and the possible short- and long-term implications for energy markets, shipping, aviation and regional investment.

    For ongoing updates and verified reporting as events unfold, follow MEED’s mega thread here.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/15890483/main.gif
    MEED Editorial
  • Kuwait extends bid deadline for Al-Khairan phase one IWPP

    6 March 2026

     

    Kuwait has extended bidding for the first phase of the Al-Khairan independent water and power producer (IWPP) project.

    The project is being procured by the Kuwait Authority for Partnership Projects (Kapp) and the Ministry of Electricity, Water & Renewable Energy (MEWRE).

    The facility will have a capacity of 1,800MW and 33 million imperial gallons a day (MIGD) of desalinated water.

    It will be located at Al-Khairan, adjacent to the Al-Zour South thermal plant.

    The new deadline is 30 April.

    The main contract was tendered last September, and the deadline had already been extended once, most recently until 4 March.

    Three consortiums and two individual companies were previously prequalified to participate.

    These include:

    • Abu Dhabi National Energy Company (Taqa) / A H Al-Sagar & Brothers (Saudi Arabia) / Jera (Japan)
    • Acwa (Saudi Arabia) / Gulf Investment Corporation (Kuwait)
    • China Power / Malakoff International (Malaysia) / Abdul Aziz Al-Ajlan Sons (Saudi Arabia)
    • Nebras Power (Qatar)                                                                                                                                        
    • Sumitomo Corporation (Japan)

    The Al-Khairan IWPP project is part of Kuwait’s long-term plan to expand power and water production capacity through public-private partnerships (PPPs).

    The winning bidder will sign a set of PPP agreements covering financing, design, construction, operation and transfer of the project.

    The energy conversion and water purchase agreement is expected to cover a 25-year supply period.

    Kapp extended another deadline recently for a contract to develop zone two of the third phase of the Al-Dibdibah power and Al-Shagaya renewable energy project.

    The PPP authority is procuring the 500MW solar photovoltaic independent power project (IPP) in partnership with the ministry.

    The bid submission deadline was moved to the end of April, a source close to the project told MEED.

    According to the MEWRE, the total generation capacity currently offered under partnership projects has reached 6,100MW, equivalent to about 30% of Kuwait’s existing power capacity.

    The ministry and Kapp are also preparing to tender the main contract for the 3,600MW Nuwaiseeb power and water desalination plant after plans were approved by Kuwait’s Council of Ministers last November.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/15889101/main.jpg
    Mark Dowdall
  • UAE utilities say services stable amid tensions

    6 March 2026

    Register for MEED’s 14-day trial access 

    Abu Dhabi National Energy Company (Taqa) and Etihad Water & Electricity (EtihadWE) have confirmed that water and electricity services in the UAE are operating normally amid ongoing regional tensions.

    In a statement, Taqa said it had activated its risk management frameworks and “power generation, water desalination, transmission, distribution and wastewater services are operating safely and without interruption”.

    According to Etihad WE, services are being delivered with “approved response plans” and “precautionary operational procedures” amid the current regional circumstances.

    Taqa is one of the UAE’s largest integrated utilities, with assets including the Taweelah B independent power and water (IWPP) plant and the 2,400MW Fujairah F3 combined-cycle power plant.

    EtihadWE operates electricity and water distribution networks across the Northern Emirates, supplying more than two million residents.

    Iran’s recent missile attacks on energy infrastructure across the GCC in retaliation for US-Israel attacks have drawn renewed attention to the importance of the region’s utilities sector.

    While power and water assets have largely avoided damage, there have been some incidents affecting broader energy infrastructure.

    Saudi Aramco had shut down its Ras Tanura refinery following a drone strike, while US cloud provider Amazon Web Services reported service outages after incidents at two data centres in the UAE.

    In January, Taqa and Etihad won a contract alongside France’s Saur to develop and operate a major wastewater treatment plant in the UAE’s northern emirate of Ras Al-Khaimah.

    The Rakwa wastewater infrastructure project is RAK’s first public-private partnership for a sewage treatment plant.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/15888121/main.jpg
    Mark Dowdall
  • Drawn-out conflict may shift planning priorities

    6 March 2026

    Commentary
    Mark Dowdall
    Power & water editor

    Across the GCC, power and water networks have largely been planned around steadily rising consumption, driven by population growth and cooling demand.

    A drawn-out conflict in the region may begin to change how planners think about these systems – particularly how they can keep operating if parts of the network are disrupted.

    On Thursday, Iran’s Energy Minister Abbas Aliabadi said that US-Israeli attacks had damaged water and electricity supply facilities in several parts of the country, while urging the public to be careful with water and electricity consumption.

    So far, major power and water infrastructure in the GCC has largely avoided damage. In the case of desalination, plants of this scale supply drinking water to millions of people, so striking them would immediately affect civilian populations and represent a significant escalation.

    There is also an element of mutual vulnerability. Iran relies on its own electricity and water infrastructure, and Aliabadi’s comments this week suggest those systems are already under pressure. Targeting desalination plants in the GCC could invite similar disruptions at home.

    However, if infrastructure disruption becomes a recurring risk in the region, the question may gradually shift from how to produce more water and electricity to how to reduce immediate reliance on continuous supply.

    Some elements of that thinking are already visible in the project pipeline. In Saudi Arabia, for example, total reservoir storage capacity has reached about 25.1 million cubic metres, with roughly 44% located in the Mecca region and 31% in Riyadh. This provides a buffer that can sustain supply temporarily if desalination production is disrupted.

    Additionally, the kingdom has about $8bn-worth of water storage projects in early study or feed stages. As regional tensions persist, schemes like this may move higher up the priority list.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/15887101/main.jpg
    Mark Dowdall
  • US oil companies to profit while Middle East exports are curtailed

    6 March 2026

    While the oil and gas operations of the Middle East’s biggest producers are being dramatically curtailed by the conflict sparked by the US and Israel’s attack on Iran, US producers are likely to see windfall profits.

    So far, the list of oil and gas assets in the Mena region disrupted by the conflict is long and includes facilities in all GCC nations, as well as Iraq and Iran itself.

    In addition to oil fields and refineries that have been shut – either due to direct Iranian attacks or concerns over further strikes – about 20 million barrels a day (b/d) of production has been removed from the global market by the effective closure of the Strait of Hormuz.

    Oil price

    The disruption to global oil and gas supplies caused by the Iran conflict has pushed oil prices up by around 15%, with Brent briefly rising above $85 a barrel on 3 March – its highest level since July 2024.

    This has boosted investor optimism about the outlook for US oil companies.

    Texas-headquartered ExxonMobil made $56bn in profit in 2022 after Russia’s invasion of Ukraine created a sustained period of higher oil prices. It was a record year for the company, and it could see a similar bump this year if oil prices remain high.

    Shale response

    US shale producers are ramping up production to capitalise on higher oil prices, according to the Paris-based International Energy Agency (IEA).

    Recently drilled shale wells could add around 240,000 b/d of supply in May, and an additional 400,000 b/d could be added in the second half of the year, according to an IEA document cited by the Financial Times.

    Gas impact

    The impact of the Iran conflict on liquefied natural gas (LNG) prices has been even more pronounced than on oil, with several gas benchmarks hitting multi-year highs.

    The Dutch Title Transfer Facility rose by 55%, reaching its highest level since fuel markets spiked after Russia’s 2022 invasion of Ukraine.

    One of the key factors driving prices higher was Qatar – the world’s second-biggest LNG producer – halting exports on 2 March after Iranian attacks on several facilities.

    Qatar is expected to take at least several weeks to restart exports from its liquefaction terminals.

    Not only will time be required to ensure the export route through the Strait of Hormuz  is secure, but restarting LNG export terminals is also a gradual process. They require a slow restart to avoid damaging cryogenic equipment, which cools natural gas to around -160°C.

    In addition, LNG trains must be brought back online sequentially; Qatar’s Ras Laffan hub has 14 trains.

    US advantage

    While the world’s second-biggest LNG producer is likely to be offline for some time, the US – the world’s biggest LNG producer – is already operating near full capacity and is benefiting from the higher-price environment.

    Cheniere and Venture Global, the two biggest US LNG producers, have both seen their share prices rise amid the conflict.

    Cheniere shares are up 18% since the start of February, while Venture Global’s share price has risen 12% over the same period.

    The scale of additional revenues earned by US companies – and the revenue losses suffered in the Middle East’s oil and gas sector – will largely depend on how long the disruption linked to the Iran conflict continues.

    If the disruption persists and significant long-term damage is done to Middle East oil and gas infrastructure, US-based oil and gas companies could record another year of record profits.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/15886759/main.png
    Wil Crisp