Construction step change boosts order books
29 April 2024
Using data from regional projects tracker MEED Projects, the region’s most active contractor is Nesma & Partners, with $14.7bn of work at the execution stage. In 2023, the Saudi Arabia-based contractor topped the ranking with $5.3bn of work in execution, a total that would not even make the top 10 this year. Dubai-based Alec ranks 10th this year with $6bn of work under execution.
Five Saudi-based contractors are in the top 10, reflecting the volume of construction work under way in the kingdom. Four of them are the contractors that the Public Investment Fund (PIF) invested in – Al Bawani, Almabani, El Seif and Nesma. The other is Shibh Al Jazira Contracting.
Two UAE-based companies, Trojan General Contracting and Alec, are in the top 10. While not as active as Saudi Arabia, the UAE market remains a crucial construction market, even though it is increasingly dominated by contractors with government or government-related shareholders.
The other three contractors are Turkiye’s Limak, which is working extensively in Kuwait; Italy’s Webuild, which has won a series of major orders in Saudi Arabia in the past three years; and Beijing-based China State Construction Engineering Corporation (CSCEC), which works across the GCC and is the world’s third most active contractor, according to GlobalData’s ranking of global construction companies.
Volume of work
With a clear shift in the volume of work being undertaken, only five of the companies from 2023 remain in the top 10 this year. They are Nesma, Limak, Almabani, Webuild and CSCEC. Dropping out the top 10 are Saudi Arabia’s Alfanar Construction, Saudi Binladin Group – which was consistently the region’s most active contractor for many years – India’s Shapooorji Pallonji, Beijing-based China Harbour Engineering Corporation and Saudi Arabian Baytur.
With large contracts still being tendered in Saudi Arabia, it is likely that there will also be significant changes to next year’s ranking. The four contractors that the PIF invested in will likely continue to dominate, while other players will also look to take advantage of the work available in the kingdom and move up the rankings.
With large contracts still being tendered in Saudi Arabia, it is likely that there will also be significant changes to next year’s ranking
This will include other local players, as Shibh Al Jazira has demonstrated in 2024, and international companies that are looking to build their order books – just as Webuild has done in recent years.
As contractors pick up more work, there are nascent concerns that you can have too much of a good thing. Companies that grow rapidly become more difficult to manage and experience has shown that when markets correct, organisations that tempered their ambitions are more manageable and resilient, and are the ones more likely to survive.
Bahrain
Bahrain’s contractor ranking has remained largely static this year. The top two contractors have not changed and only one company has joined the top 10 this year.
China Machinery Engineering Corporation maintains its lead position with $698m of work in the execution phase, thanks to its contract to build the East Sitra development for the housing ministry. Al Hamad Building Contracting is in second place, with $560m-worth of projects in the execution phase.
Nass Contracting is in third place, having moved up from fifth last year. Kooheji Contractor, which was ranked third last year, is now fourth.
The rest of the ranking remains largely the same, with Saleh Abdullah Al Muhanna & Partners replacing Al Taitoon Contracting in the top 10.
The relative lack of change to the Bahraini ranking reflects the quiet market conditions in the country when compared to the larger GCC markets.
This is largely due to major projects such as the new terminal building at Bahrain International airport having been completed and tendering and contract awards not yet having started for major new projects, including the first phase of the Bahrain metro network and the second causeway connecting to Saudi Arabia.
Kuwait
Turkiye’s Limak Holding has strengthened its position at the top of Kuwait’s ranking this year. The contractor has $5.6bn of construction work at the execution stage, according to MEED Projects. This is about $600m more than the $5bn it had when it headed the 2023 ranking.
Limak’s work in execution was boosted last year when the Public Works Ministry awarded it more construction work at Kuwait International airport. It secured a contract for package three of the expansion of Terminal 2, which covers the construction of aircraft parking aprons, taxiways and service buildings.
In joint second place is Shapoorji Pallonji with $1.4bn of work at the execution stage. The Indian contractor is working on two healthcare projects and one education scheme in a joint venture with the local Al Sager General Trading & Contracting, which is also working on $1.4bn of projects at the execution stage.
The only other non-Kuwaiti contractor in the top 10 is China Gezhouba Group Corporation, which is in fourth place with $1.3bn of projects at the execution stage. Its largest project is the infrastructure works at South Saad Al Abdullah Residential City.
Oman
The local Galfar Engineering & Contracting remains at the top of the Oman ranking in 2024, with about $900m of construction and transport projects at the execution stage, according to MEED Projects. The contractor’s total is slightly less than the $1.1bn it recorded last year.
Several key changes have occurred in the Omani top 10 this year. Local contractor Saif Salim Essa Al Harasi & Company has moved into fourth place thanks to several major contract awards.
In December last year, it secured a $118m contract for the construction of a hospital, and in October it was awarded a design-and-build contract for a cultural complex. The cultural complex was won as part of a joint venture with Turkish contractor Sembol Construction, which has also moved into the top 10 in seventh position.
Another contractor that has moved into Oman’s top 10 is China Communications Construction Company. In January, it secured a marine works contract at the Yiti Sustainable City project.
Qatar
Two contractors top the Qatar ranking in 2024 with $1.4bn of ongoing projects each. Turkish contractor TAV Construction and the local Midmac Contracting Company both lead, largely due to their ongoing work at Hamad International airport.
Closely behind, in third position, is the local Generic Engineering Technologies, which is working on several projects in Qatar, including the upgrade of the Lusail Formula 1 and MotoGP race circuit.
Urbacon Trading & Contracting, which topped last year’s ranking with $1.8bn of projects at the execution stage, is in fifth place this year with $1.2bn of projects. The contractor has taken significant strides in the past year to win work in other markets, including Saudi Arabia.
Saudi Arabia
There has been a major shift in the level of construction activity undertaken by the 10 most active contractors in Saudi Arabia in 2024.
This year, the total value of projects undertaken by the top 10 contractors is $71.5bn, more than a 130% increase from the $31bn recorded by the top 10 in 2023.
The local Nesma & Partners tops the Saudi ranking again this year with $14.7bn-worth of projects at the execution stage. The total, which is about 50% more than that of the second-ranked contractor, highlights Nesma’s leading position in the Saudi market, and the scale of the opportunities that the kingdom’s projects sector now offers.
In second position is Italy’s Webuild with just short of $10bn of projects at the execution stage. Earlier this year, it secured a $4.7bn contract to construct dams at the Trojena mountain resort in Neom, adding to other major orders at Neom and Diriyah.
The four contractors that received investment from the PIF in 2023 now occupy four out of the top six positions in the
Saudi Ranking. They are Nesma, El Seif, Al Bawani and Almabani.
UAE
The UAE’s construction market has grown strongly over the past year, and this is reflected in the 2024 contractor ranking. Like Saudi Arabia, the top 10 UAE contractors have more than doubled the total value of projects they have at the execution stage. This year, the top 10 have $27.6bn of work, which is a 123% increase from the $12.4bn last year.
The top-ranked contractor in the UAE this year is Trojan General Contracting, which is part of Alpha Dhabi. In April, Alpha Dhabi Holding agreed to sell a 49% stake in its construction subsidiary Alpha Dhabi Construction Holding (ADCH) to local investment firm ADQ. Trojan is part of ADCH.
With $6.2bn of projects at the execution stage, Trojan is ahead of National Marine Dredging Company (NMDC), which has $3.1bn of work. NMDC topped last year’s ranking with $2.3bn of projects.
In third place is UK-headquartered Innovo, with $3bn of projects, followed by Dubai-based Alec with $2.6bn.
Contractors need to grow quickly to maintain their rankings. Al Amry Transport & General Contracting has moved down to fifth place from fourth, even though it more than doubled the value of its projects at the execution stage. China State Construction Engineering Corporation has also dropped in the ranking, from third to sixth place, despite increasing its value of projects to $2.4bn from $1.6bn.
Exclusive from Meed
-
Algeria extends bid deadline for stalled power plant30 April 2026
-
Dewa announces new record for power reliability30 April 2026
-
Riyadh tenders PMC deal for major sports arena30 April 2026
-
-
Iraq sets up commission for $5bn pipeline project30 April 2026
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Algeria extends bid deadline for stalled power plant30 April 2026
Algeria’s state-owned electricity and gas utility Sonelgaz has extended a deadline for contractors to submit expressions of interest for the construction of the 1.2GW Djelfa combined-cycle power plant.
The project is being procured through Sonelgaz’s power generation subsidiary, Societe Algerienne de l’Electricite et du Gaz – Production de l’Electricite (SPE).
In March, MEED reported that the utility was seeking contractors to complete works at the existing Djelfa plant, including the remaining construction, the supply of missing equipment and the assessment of installed equipment.
The original bid submission deadline for prequalification was 7 April. The new deadline is 5 May.
The tender is open to both local and international companies, and will be conducted in three phases: prequalification, preliminary technical assessment, and final technical and financial submission.
The retender follows earlier plans to complete the project through a Chinese consortium comprising China Energy Engineering Group Company, Northwest Electric Power Design Institute and Anhui Electric Power Construction Company.
This proposal was made after Spanish contractor Duro Felguera halted work on the project in June 2024.
According to MEED Projects, construction works had progressed to 72% at the time of the suspension.
It is understood that an agreement in principle was then reached to transfer the remaining works to the Chinese group after the Spanish firm entered a pre-bankruptcy phase in December 2024.
A company statement at the time said: “The Chinese group is committed to completing the plant construction, with commissioning scheduled to start in the ninth month following the final agreement.”
However, in October 2025, it was revealed that the attempt to transfer the project to a consortium of Chinese companies had failed, leaving the Spanish firm with an official demand to pay €413m in compensation to Sonelgaz.
This was revealed via a lengthy report containing a restructuring plan sent by Duro Felguera to creditors in Spain and the Madrid Financial Markets Authority.
Gas-fired power plants
Located in Djelfa province, the project remains a key part of Algeria’s power generation expansion plans.
Sonelgaz has been seeking contractors to build a separate 1.2GW combined-cycle gas-fired power plant in Aldrar since last April.
The most recent deadline extension was 29 April.
According to recent reports, Algeria has also begun construction of a power generation plant in El-Aouinet, with a total installed capacity of 1,406MW.
The combined-cycle gas turbine plant is being developed in partnership with China National Electric Engineering Company.
Gas-fired combined-cycle plants continue to account for the majority of Algeria’s electricity generation capacity. Data from MEED Projects indicates that more than 5,000MW of oil- and gas-fired power capacity is currently in the execution phase.
https://image.digitalinsightresearch.in/uploads/NewsArticle/16623787/main.jpg -
Dewa announces new record for power reliability30 April 2026
Dubai Electricity & Water Authority (Dewa) has announced that it set a new world record for the lowest electricity customer minutes lost (CML), at 0.82 minutes a year in 2025.
The figure is equivalent to about 49 seconds of annual outage per customer. It improves on the utility’s previous record of 0.94 minutes in 2024, a reduction of around 13%.
Dewa said it has reduced CML in Dubai from 6.88 minutes a year in 2012 to 0.82 minutes in 2025, significantly lower than the average of about 15 minutes recorded by leading electricity utilities in the European Union.
The smart grid is a central component of Dewa’s strategy to improve reliability and efficiency. The programme is being implemented with total investments of AED7bn up to 2035.
One of the key initiatives of the programme is the Automatic Smart Grid Restoration System, which enables remote, round-the-clock control and monitoring.
Dewa currently has tenders out for several power and water infrastructure projects in the emirate. These include at least four Glass Reinforced Epoxy (GRE) water transmission pipeline projects.
According to regional projects tracker MEED Projects, Dewa awarded $1.1bn-worth of new power and water contracts in 2025. Contract awards had previously reached $2.6bn in 2024, and $4bn in 2024.
https://image.digitalinsightresearch.in/uploads/NewsArticle/16623721/main.jpg -
Riyadh tenders PMC deal for major sports arena30 April 2026

Saudi Arabia’s Sports Boulevard Foundation has tendered a contract inviting firms to bid for project management consultancy (PMC) services for the Global Sports Tower in the Athletics District of the Sports Boulevard development in Riyadh.
The tender was issued on 8 April, with a bid submission deadline of 10 May.
The 130-metre-tall Global Sports Tower will cover an area of 84,000 square metres and will include more than 30 sports facilities. The tower will feature the world’s tallest indoor climbing wall at 98 metres and a 250-metre running track.
Earlier this week, MEED reported that the Sports Boulevard Foundation is preparing to award the main construction contract for the Global Sports Tower. MEED understands that bid evaluation has reached an advanced stage and the contract is likely to be awarded by the end of May.
MEED reported in May last year that design work on the tower had been completed. Saudi Arabia’s Crown Prince Mohammed Bin Salman Bin Abdulaziz Al-Saud approved the designs in 2024.
The Sports Boulevard development runs across Riyadh from east to west and, once complete, is set to be the world’s longest park spanning more than 135 kilometres.
The development will be spread across several districts, including Wadi Hanifah, Arts, Urban Wadi, Entertainment, Athletics and Eco, as well as Sands Sports Park.
The large-scale project aims to transform central Riyadh – currently dominated by major highways – into a recreational corridor.
Sports Boulevard, which will feature 4.4 million sq m of public realm and landmark buildings, will also be home to the Centre for Cinematic Arts and a 2,000-seat amphitheatre.
The development will provide more than 2.3 million sq m of mixed-use commercial, residential, and retail assets, along with sports facilities around the park, known as Linear Park.
https://image.digitalinsightresearch.in/uploads/NewsArticle/16622287/main.jpeg -
Contractors submit Saudi Arabia phosphate rail track bids30 April 2026

Saudi Arabian Railways (SAR) received bids from contractors on 27 April for a multibillion-riyal tender to double the tracks on the existing phosphate transport railway network connecting the Waad Al-Shamal mines to Ras Al-Khair in the kingdom’s Eastern Province.
The tender – covering the second section of the track-doubling works and spanning more than 150 kilometres (km) – was issued on 9 February.
This follows SAR receiving bids on 1 February for the project’s first phase, which spans about 100km from the AZ1/Nariyah Yard to Ras Al-Khair.
The scope includes track doubling, alignment modifications, new utility bridges, culvert widening and hydrological structures, as well as the conversion of the AZ1 siding into a mainline track. It also includes support for signalling and telecommunications systems.
The tender notice was issued in late November.
Switzerland-based engineering firm ARX is the project consultant.
MEED understands that these two packages are the first of four that SAR is expected to tender for the phosphate railway line. Other packages anticipated to be tendered shortly include the depot and systems packages.
In 2023, MEED reported that SAR was planning two projects to increase its freight capacity, including an estimated SR4.2bn ($1.1bn) project to install a second track along the North Train Freight Line and construct three new freight yards.
Formerly known as the North-South Railway, the North Train is a 1,550km-long freight line running from the phosphate and bauxite mines in the far north of the kingdom to the Al-Baithah junction. There, it diverges into a line southward to Riyadh and a second line running east to downstream fertiliser production and alumina refining facilities at Ras Al-Khair on the Gulf coast.
Adding a second track and the freight yards will significantly increase the network’s cargo-carrying capacity and facilitate increased industrial production. Project implementation is expected to take four years.
State-owned SAR is also considering increasing the localisation of railway materials and equipment, including the construction of a cement sleeper manufacturing facility.
https://image.digitalinsightresearch.in/uploads/NewsArticle/16622526/main.jpg -
Iraq sets up commission for $5bn pipeline project30 April 2026
Iraq is setting up a high-level commission to oversee the development of the planned $5bn Basra-Haditha crude oil pipeline project.
The decision was made at a meeting held on 26 April, attended by Prime Minister Mohammed Shia Al-Sudani and the Minister of Petroleum Hayyan Abdul Ghani Al-Sawad, as well as other officials and consultants.
The commission will be chaired by the undersecretary of the Oil Ministry and include advisers to the prime minister, along with director-generals from the Oil Ministry and the Industry & Minerals Ministry.
Al-Sudani said the pipeline project will increase flexibility in transporting crude oil to the Turkish port of Ceyhan, as well as the Syrian port of Baniyas and Jordan’s port of Aqaba.
The pipeline is also expected to strengthen supply to refineries in central and northern Iraq and support higher domestic refining output.
The meeting also approved allocating $1.5bn to the project this year, with funding provided through the Iraq-China oil-for-infrastructure mechanism, according to a statement issued by the Petroleum Ministry.
Earlier this month, Iraq’s Council of Ministers approved amendments allowing the Oil Ministry to directly invite specialised companies to bid for the 685-kilometre pipeline.
The pipeline is expected to have a capacity of up to 2.25 million barrels a day.
https://image.digitalinsightresearch.in/uploads/NewsArticle/16621546/main.jpg
.gif)