Completing infrastructure ahead of time
10 December 2024

In late December 2023, Bahrain opened the Al-Fateh Highway project to traffic five months ahead of schedule. The highway connects key areas in Bahrain, including Manama, Mina Salman, Sitra, Muharraq, Bahrain Bay and Juffair, and opening the scheme promptly has significantly improved traffic in one of the most congested areas of the country.
“The secret to success was implementing the project in stages, combined with excellent traffic management,” says Minister of Works Ibrahim Bin Hassan Al-Hawaj.
The successful completion of the Al-Fateh Highway project comes at an important time for Bahrain, as it continues to upgrade its road network.
“The lessons we learned from Al-Fateh Highway are being utilised on other projects. We are working on the Muharraq Ring Road project, and that is also going to be open for traffic well ahead of time,” says Al-Hawaj.
Like Al-Fateh Highway, the Muharraq Ring Road project connects key commercial and residential areas in Bahrain, including North Muharraq, Diyar Al-Muharraq and Dilmunia.
Multifaceted approach
These projects are part of Bahrain’s comprehensive approach to alleviating road traffic.
“In 2016, we launched a study that identified projects that could help ease congestion. It proposed a multifaceted approach that covers many things, including public transport and an intelligent transport system, which introduces automation,” explains Al-Hawaj.
“We have not implemented everything in the study, but we are working through it gradually with the Traffic Council, headed by his excellency the minister of interior, and including the Ministry of Works, Ministry of Transportation and Ministry of Housing & Urban Planning. We have regular meetings to identify challenges and then put forward suitable projects to solve them,” says Al-Hawaj.
The Ministry of Works is responsible for maintaining, improving and expanding the road network. Its projects are split into four categories.
The first two categories are the major projects. The first is building new roads, while the second is improving the existing road network, either by widening roads or upgrading intersections.
Then there are the other two categories. These are maintaining the existing road network – which is a challenging task with existing traffic – and a fourth category that is known as ‘quick wins’. These small, tactical-level projects can be completed quickly to ease specific traffic black spots.
“We have about 60 projects under implementation, valued at BD172m ($456.2m), and among these are 14 strategic projects that amount to BD117m,” says Al-Hawaj.
Upcoming schemes
The pipeline of projects under execution will soon be expanded with the addition of a fourth crossing connecting Busaiteen with Bahrain Bay. The Bahrain Tender Board opened prices for the contract to build the signature bridge crossing in late November.
“The fourth crossing project is going to start in 2025,” says Al-Hawaj.
Looking further ahead, more road contracts will be awarded. “There are more than BD200m of future projects approved, and they will go to tender in the coming two years,” says Al-Hawaj.
There are more than BD200m of future projects approved, and they will go to tender in the coming two years
One of the roads that suffers from high traffic volumes is Sheikh Jaber Ahmed Al-Sabah Highway, from Umm Al-Hassam to the Alba intersection.
“This is our biggest project in the future. There will be four lanes in each direction, and all the intersections will be free-flowing traffic either by underpass or flyovers. We will get rid of all the traffic lights,” says Al-Hawaj.
The project will move into the construction phase next year with preparation works.
“One of the main lessons from the Al-Fateh Highway project is to free the construction zone from any services before construction starts. It will take some time to redirect the existing utilities, and then we will immediately go into construction,” says Al-Hawaj.
Another upcoming major scheme is the Bahrain Northern Link Road (BNLR) project that will run along the northern coast of Manama from the Bahrain Bay area in the east to Madinat Salman in the west. Initial estimates suggest that the scheme, which will have sections onshore and offshore, could cost BD500m to deliver.
Together with the fourth crossing project and the Northern Muharraq Ring Road, the BNLR scheme will create a new road corridor along the northern edge of Bahrain.
Unlike other road projects in Bahrain, the BNLR will be delivered as a public-private partnership project. Dar Al-Handasah was selected for the project’s feasibility study in 2022.
Away from roads, another major area of responsibility for the Ministry of Works is sanitation. At present, 86% of premises in Bahrain are connected to the sanitation network and sewage treatment plants (STPs), and there are plans to connect the remaining 14%.
STP capacity is also increasing. The capacity of Bahrain’s largest plant at Tubli is being doubled, and there is an expansion under way for the STP at Muharraq. The Sitra STP is also being upgraded, using technology from UK company Bluewater, which allows for capacity to increase without adding to the footprint of the site.
A greenfield project is also planned. “We have a new plant coming soon at Khalifa City,” says Al-Hawaj.
“We are finalising the drawings, and a tender is expected to be issued in the first quarter of 2025. We will start with 20,000 cubic metres a day, but the ultimate capacity will be 40,000 cubic metres a day.”
Exclusive from Meed
-
Saudi Arabia battery storage awards provide fresh lift24 August 2026
-
Qatar receives bids for major power grid expansion24 August 2026
-
Maaden closes $1bn term loan and credit facility24 August 2026
-
Dubai inflation slows to 5.3% in July24 August 2026
-
Libya oil project on track for 2027 completion24 August 2026
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Saudi Arabia battery storage awards provide fresh lift24 August 2026
Commentary
Mark Dowdall
Power & water editorThe latest battery storage awards provide a welcome injection of investment into Saudi Arabia’s power market, which has seen a sharp slowdown in contract awards this year.
Saudi Power Procurement Company’s four Group 1 storage service agreements, announced last week, are worth more than $1.16bn and cover 2,000MW of capacity.
That is significant against the wider market. According to regional project tracker MEED Projects, Saudi Arabia recorded $19.7bn in power sector contract awards in the first seven months of 2025, compared with just $2.5bn in new awards in the same period this year.
The battery energy storage system (bess) awards therefore account for a sizeable share of the activity recorded so far this year and provide a much-needed source of new contracting activity.
Importantly, this is not a one-off. SPPC issued the request for proposal (RFP) for its second group of bess projects in July, covering six projects with a combined capacity of 3,000MW and 12,000MWh.
With the Group 1 tender taking around 18 months from RFP to contract award, it is reasonable to expect Group 2 contracts to be signed in 2027.
At the same time, the awards for six independent renewable plants under Round 7 of Saudi Arabia’s National Renewable Energy Programme (NREP), with a combined capacity of 5,300MW, are also likely to move into next year, with the latest bid deadlines now extending into September.
Although a substantial pipeline remains in procurement, it is only once these projects move from tender to award and into construction that this pipeline translates into market activity.
It is important that these tenders continue to progress at the pace established by the early rounds of Saudi Arabia’s renewable energy programme and now also SPPC’s independent storage provider bess scheme.
https://image.digitalinsightresearch.in/uploads/NewsArticle/18962923/main.jpg -
Qatar receives bids for major power grid expansion24 August 2026

Qatar General Electricity & Water Corporation (Kahramaa) has received bids for several packages under a major power transmission expansion project tendered in April.
The project covers new substations at multiple voltage levels, as well as the supply and installation of 400kV extra-high-voltage power cables. The overall scheme is estimated to cost $650m.
It is being tendered as part of Kahramaa’s 2026 procurement plan, which includes 198 tenders with a total estimated value of QR21.4bn ($5.9bn).
According to sources, bids were submitted for the following packages on 20 August:
- Substation packages S1 and S2, covering new 132/11kV substations (estimated cost: $200m)
- Package S3, covering new 66/11kV substations ($50m)
- Package S4, including a new 400/220/132kV substation, as well as upgrades and modifications to existing 400kV and 220kV substations ($200m)
- Package S5, covering new 132/11kV substations and upgrades to existing 132kV and 66kV substations ($100m)
- Cable packages C1 and C2, covering 400kV cables ($100m)
Kahramaa previously stated that foreign companies not registered in Qatar would be allowed to participate in the bidding, subject to meeting specified conditions, including registration and certification requirements.
In June, the electricity and water utility awarded contracts worth more than QR2.2bn ($604m) to expand the electricity transmission network in the country’s western region.
The engineering, procurement and construction (EPC) works will support the integration of the 2GW Dukhan solar power project into Qatar’s national electricity grid. The scope includes new and upgraded substations, as well as the installation of underground cables and overhead transmission lines.
Kahramaa said contracts were awarded to local firm Voltage Engineering, Turkiye’s Best & Betas Consortium, India’s Larsen & Toubro and South Korea’s LS Cable.
Of Kahramaa’s 2026 procurement plan, electricity transmission projects account for QR8.9bn ($2.4bn) and include the construction of new 400/132kV substations in Al-Wukair and Al-Mashaf, as well as the expansion of 400kV substations at Ras Laffan.
These also cover the installation of 132kV underground cables between Al-Sailiya and Al-Rayyan over a 24-kilometre route, as well as upgrades to the 400kV and 220kV networks.
Additionally, there are 64 planned electricity distribution projects managed by the Electricity Distribution Department that cover the medium-voltage and low-voltage networks throughout Doha and the regional municipalities.
https://image.digitalinsightresearch.in/uploads/NewsArticle/18962223/main.jpg -
Maaden closes $1bn term loan and credit facility24 August 2026
Saudi Arabian Mining Company (Maaden) has announced the closing of its inaugural international syndicated term loan and revolving credit facilities, worth a total of $1bn.
The $500m international term loan facility will support Maaden’s growth agenda and general corporate purposes, including funding growth projects across its portfolio.
The $500m international revolving credit facility, which is expected to remain undrawn, provides additional committed funding capacity “as Maaden continues to scale its business and execute its long-term growth strategy”.
The transaction “was met with strong support from the international banking market, attracting participation from a diverse group of leading international banks across key global financial markets”, including the US, Canada, Europe, China and Japan. The facilities were oversubscribed, Maaden said.
ALSO READ: Maaden and Aramco sign deal to create joint venture
“The level of demand reflects the global banking community’s confidence in Maaden’s financial strength, strategic direction and ambitious growth plans,” the Saudi state miner said in its statement.
“The facilities mark another significant milestone in Maaden’s funding journey – further diversifying its sources of funding and broadening its access to global capital providers as the company continues to advance its long-term growth ambitions.
“Maaden continues to make significant progress across its growth pipeline, expanding production, advancing major projects and accelerating exploration as it builds a world-class mining company at the heart of Saudi Arabia’s economic transformation.”
https://image.digitalinsightresearch.in/uploads/NewsArticle/18962086/main4516.jpg -
Dubai inflation slows to 5.3% in July24 August 2026
Dubai’s annual inflation rate slowed to 5.3% in July, down from 5.7% in June, as a decline in transport costs eased pressure on consumer prices, according to Emirates NBD.
The bank said the slowdown supported its view that price growth peaked at mid-year, and it expects inflation to continue easing through the rest of 2026. Monthly price growth slowed to 0.1% in July, from 0.4% in June, the weakest pace since February.
Transport was the clearest sign of the moderation. Annual price growth in the category slowed to 11.9% in July, from 18.1% in June, as transport costs fell 3.7% over the month. Fuel and lubricant inflation eased to 24.1% year on year, from 48.3%, tracking a decline in local petrol prices.
Petrol remains the main swing factor in the emirate’s inflation. Transport contributed 1.1 percentage points to headline inflation in July, down from 1.7 percentage points in June. Emirates NBD said the relief may prove temporary, with Super 98 petrol prices climbing 5.9% in August to leave them 33.8% higher than a year earlier. The bank expects headline inflation to edge higher in the August figures before easing again later in the year.
The UAE deregulated petrol and diesel prices in 2015 and reviews them monthly against global prices, meaning changes in global fuel costs pass through to consumers quickly. Transport, which includes fuel, accounts for 9% of Dubai’s consumer price index basket.
Housing remained the largest contributor to inflation even as its impulse faded. Housing and utilities, which account for about two-fifths of the basket, added 2.8 percentage points to headline inflation. Annual price growth in the category slowed to 7.0%, from 7.4% in January.
Food inflation edged up to 7.8% year on year, from 7.6% in June, which the bank attributed to lingering supply-chain disruption from the regional conflict. Inflation in restaurants and hotels accelerated to 4.5% year on year, from 1.7% in June.
Emirates NBD forecasts inflation of 2.9% by year-end but said risks to that projection were tilted to the upside, given lingering pressures in food and housing.
https://image.digitalinsightresearch.in/uploads/NewsArticle/18961735/main1839.jpg -
Libya oil project on track for 2027 completion24 August 2026

The project to develop a workers’ camp at Libya’s Erawin oil field is on track for completion next year, according to industry sources.
The project, estimated to be worth about $50m, is being executed by the Libyan oil services company Al-Saraya Al-Hamara, headquartered in the city of Sebha.
The Libyan company was awarded the contract in February 2025.
The scope of the project includes:
- Construction of an accommodation camp
- Construction of the camp maintenance warehouse
- Construction of the camp office
- Construction of a fire brigade shelter
- Construction of a kitchen and mess hall
- Construction of a mosque
- Construction of a laundry room
- Construction of a clinic
- Construction of parking facilities
- Installation of a fire and gas system
- Installation of a power generator
- Construction of associated facilities
The client on the project is Zallaf Libya Oil & Gas Exploration & Production Company.
Zallaf Libya Oil & Gas Exploration & Production Company was established in Libya in 2013 and is wholly owned by Libya’s state-owned National Oil Corporation.
The Erawin field development project is located about 800 kilometres south of Tripoli and 100km southwest of the El-Sharara field.
Libya shipped its first cargo of crude from the Erawin oil field in November 2023.
The shipment departed from Libya’s Zawiyah port and consisted of 600,000 barrels of crude.
Australia-based Worley Parsons was appointed as the front-end engineering and design (feed) contractor for the early production facility project in 2019.
https://image.digitalinsightresearch.in/uploads/NewsArticle/18953632/main.jpg