Completing infrastructure ahead of time
10 December 2024

In late December 2023, Bahrain opened the Al-Fateh Highway project to traffic five months ahead of schedule. The highway connects key areas in Bahrain, including Manama, Mina Salman, Sitra, Muharraq, Bahrain Bay and Juffair, and opening the scheme promptly has significantly improved traffic in one of the most congested areas of the country.
“The secret to success was implementing the project in stages, combined with excellent traffic management,” says Minister of Works Ibrahim Bin Hassan Al-Hawaj.
The successful completion of the Al-Fateh Highway project comes at an important time for Bahrain, as it continues to upgrade its road network.
“The lessons we learned from Al-Fateh Highway are being utilised on other projects. We are working on the Muharraq Ring Road project, and that is also going to be open for traffic well ahead of time,” says Al-Hawaj.
Like Al-Fateh Highway, the Muharraq Ring Road project connects key commercial and residential areas in Bahrain, including North Muharraq, Diyar Al-Muharraq and Dilmunia.
Multifaceted approach
These projects are part of Bahrain’s comprehensive approach to alleviating road traffic.
“In 2016, we launched a study that identified projects that could help ease congestion. It proposed a multifaceted approach that covers many things, including public transport and an intelligent transport system, which introduces automation,” explains Al-Hawaj.
“We have not implemented everything in the study, but we are working through it gradually with the Traffic Council, headed by his excellency the minister of interior, and including the Ministry of Works, Ministry of Transportation and Ministry of Housing & Urban Planning. We have regular meetings to identify challenges and then put forward suitable projects to solve them,” says Al-Hawaj.
The Ministry of Works is responsible for maintaining, improving and expanding the road network. Its projects are split into four categories.
The first two categories are the major projects. The first is building new roads, while the second is improving the existing road network, either by widening roads or upgrading intersections.
Then there are the other two categories. These are maintaining the existing road network – which is a challenging task with existing traffic – and a fourth category that is known as ‘quick wins’. These small, tactical-level projects can be completed quickly to ease specific traffic black spots.
“We have about 60 projects under implementation, valued at BD172m ($456.2m), and among these are 14 strategic projects that amount to BD117m,” says Al-Hawaj.
Upcoming schemes
The pipeline of projects under execution will soon be expanded with the addition of a fourth crossing connecting Busaiteen with Bahrain Bay. The Bahrain Tender Board opened prices for the contract to build the signature bridge crossing in late November.
“The fourth crossing project is going to start in 2025,” says Al-Hawaj.
Looking further ahead, more road contracts will be awarded. “There are more than BD200m of future projects approved, and they will go to tender in the coming two years,” says Al-Hawaj.
There are more than BD200m of future projects approved, and they will go to tender in the coming two years
One of the roads that suffers from high traffic volumes is Sheikh Jaber Ahmed Al-Sabah Highway, from Umm Al-Hassam to the Alba intersection.
“This is our biggest project in the future. There will be four lanes in each direction, and all the intersections will be free-flowing traffic either by underpass or flyovers. We will get rid of all the traffic lights,” says Al-Hawaj.
The project will move into the construction phase next year with preparation works.
“One of the main lessons from the Al-Fateh Highway project is to free the construction zone from any services before construction starts. It will take some time to redirect the existing utilities, and then we will immediately go into construction,” says Al-Hawaj.
Another upcoming major scheme is the Bahrain Northern Link Road (BNLR) project that will run along the northern coast of Manama from the Bahrain Bay area in the east to Madinat Salman in the west. Initial estimates suggest that the scheme, which will have sections onshore and offshore, could cost BD500m to deliver.
Together with the fourth crossing project and the Northern Muharraq Ring Road, the BNLR scheme will create a new road corridor along the northern edge of Bahrain.
Unlike other road projects in Bahrain, the BNLR will be delivered as a public-private partnership project. Dar Al-Handasah was selected for the project’s feasibility study in 2022.
Away from roads, another major area of responsibility for the Ministry of Works is sanitation. At present, 86% of premises in Bahrain are connected to the sanitation network and sewage treatment plants (STPs), and there are plans to connect the remaining 14%.
STP capacity is also increasing. The capacity of Bahrain’s largest plant at Tubli is being doubled, and there is an expansion under way for the STP at Muharraq. The Sitra STP is also being upgraded, using technology from UK company Bluewater, which allows for capacity to increase without adding to the footprint of the site.
A greenfield project is also planned. “We have a new plant coming soon at Khalifa City,” says Al-Hawaj.
“We are finalising the drawings, and a tender is expected to be issued in the first quarter of 2025. We will start with 20,000 cubic metres a day, but the ultimate capacity will be 40,000 cubic metres a day.”
Exclusive from Meed
-
UAE rail momentum grows as trade routes face strain6 April 2026
-
War casts shadow over UAE construction boom6 April 2026
-
Acwa solar plants face power output restrictions6 April 2026
-
Kuwait reports attacks on power and water plants6 April 2026
-
RCRC opens Riyadh Metro Line 7 bids6 April 2026
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
UAE rail momentum grows as trade routes face strain6 April 2026

Rail has shifted from a long-term diversification play to an immediate strategic imperative for the UAE. The regional conflict and its ripple effects on risk premiums, insurance costs and schedule reliability have highlighted the vulnerability of traditional logistics routes and maritime chokepoints.
Against this backdrop, the country’s infrastructure pipeline – particularly rail – now serves as both an economic enabler and a resilience strategy. On the freight side, Abu Dhabi’s Hafeet Rail and the expanding Etihad Rail network are laying the groundwork for higher-capacity, lower-volatility overland transport, reducing reliance on sea-based supply chains.
Inland connectivity is already being prioritised to counter supply chain disruption, including the recent opening of a green corridor with Oman to accelerate cross-border flows.
The importance of the programme is equally evident in passenger mobility. Projects such as the Etihad high-speed rail and Dubai Metro’s Blue Line signal a parallel effort to reshape commuting patterns, strengthen labour-market connectivity and support transit-oriented development.
Network integration
The next step is to transform these corridors into a fully integrated system. This includes linking rail and road networks with industrial zones, logistics parks and inland terminals, while strengthening redundancy through connections to strategic gateways such as Fujairah Port, which, due to its east coast location, provides an alternative route that reduces exposure to disruption around the Strait of Hormuz.
Together, freight and passenger rail – combined with planned investments in airports and road network upgrades – are becoming the backbone of the UAE’s next infrastructure cycle. This integrated system not only expands capacity but also strengthens economic resilience, helping to keep trade and urban movement functioning during periods of disruption.
Pipeline outlook
According to data from regional projects tracker MEED Projects, the UAE has an infrastructure pipeline valued at about $63bn, covering airports, railways and road schemes.
In November last year, the UAE’s Minister of Energy and Infrastructure, Suhail Al-Mazrouei, announced a AED170bn ($46bn) package of national transport and road projects to be delivered by 2030.
Speaking at the UAE Government Annual Meetings in Abu Dhabi on 5 November, Al-Mazrouei said the projects form part of a national strategy to ease congestion and enhance mobility. Initiatives include road expansions, public transport upgrades, and the development of high-speed and light rail systems.
Key road projects include adding six lanes (three in each direction) to Etihad Road, increasing capacity by 60% to a total of 12 lanes. Emirates Road will be expanded to 10 lanes along its full length, boosting capacity by 65% and reducing travel time by 45%. Sheikh Mohammed Bin Zayed Road will also be widened to 10 lanes, increasing capacity by 45%.
The plan also includes a study for a fourth federal highway, extending 120 kilometres with 12 lanes and a capacity of up to 360,000 trips a day.
Work has already begun on the AED750m Emirates Road upgrade, which is expected to be completed within two years.
Rail progress
Etihad Rail remains on track to launch passenger services by 2026 and has awarded multibillion-dollar design-and-build contracts for the civil works and station packages of the high-speed rail (HSR) line connecting Abu Dhabi and Dubai.
Trains on the UAE’s HSR network are designed for speeds of up to 350km/h, with an operating speed of 320km/h. The programme will be delivered in four phases, gradually extending connectivity across the country.
Procurement is also progressing for the Abu Dhabi Tram Line 4 project. The first phase, announced by Abu Dhabi Transport Company in October last year, will connect Zayed International airport with nearby areas including Yas Island, Al-Raha Beach and Khalifa City. Prequalification has been completed, and the tender is expected to be issued soon.
In Dubai, the most significant infrastructure project is the first-phase expansion of Al Maktoum International airport. Dubai Aviation Engineering Projects received contractor proposals on 31 March for three superstructure packages. A contractor was selected last year for the substructure works.
Dubai is also planning to connect Al-Maktoum International airport to the metro network. In March, consultants submitted proposals for the design of the Route 2020 extension, which will link the Expo 2020 station to the airport’s West Terminal.
Another major project is the Dubai Metro Gold Line. In October last year, Dubai’s Roads & Transport Authority appointed US-based engineering firm Aecom to provide consultancy services for the scheme.
https://image.digitalinsightresearch.in/uploads/NewsArticle/16267919/main.gif -
War casts shadow over UAE construction boom6 April 2026

The UAE’s construction sector entered the year in a position of strength. According to regional projects tracker MEED Projects, contract awards reached $59bn in 2025, a record that surpassed the $53bn awarded in 2024.
With market conditions expected to remain buoyant, 2026 was forecast to be another strong year. However, the Iran conflict that began on 28 February is set to change that narrative.
In the short term, the construction sector proved resilient during the first weeks of the conflict. With the exception of a few sites in high-risk zones, construction activity across the UAE has largely continued uninterrupted.
Cost pressures
Despite continued activity on the ground, the industry is bracing for cost escalation. Brent crude prices have risen well above the $100-a-barrel mark. For the construction sector, the impact was felt most acutely on 1 April, when the UAE adjusted its domestic fuel prices.
Diesel surged to AED4.69 a litre, up sharply from AED2.72 in March. This nearly 72% increase has immediate and far-reaching implications for project overheads, affecting heavy machinery operations, site power generation, and the transport of bulk materials such as sand, steel and cement.
For projects signed under fixed-price contracts during the lower-inflation environment of 2024 and 2025, these increases pose a significant threat to contractor margins and potentially to overall project viability.
Supply disruption
These inflationary pressures are compounded by logistical challenges stemming from instability in the Strait of Hormuz. As a critical artery for regional imports, any disruption has ripple effects across the construction supply chain – particularly for long-lead items such as specialised façade systems, high-end finishing materials and key MEP components.
While the UAE has leveraged overland routes to mitigate some of these bottlenecks, the shift is unlikely to be cost-neutral or time-neutral.
Insurance gaps
Legal and contractual frameworks governing projects are now under increased scrutiny. A key concern is the limitation of standard insurance policies. Many contractor all-risk and logistics policies exclude coverage for losses arising from active conflict, creating a significant gap for goods in transit.
As freight is rerouted to alternative ports and transported over longer distances by road, insurers are becoming increasingly reluctant to provide cover for these extended journeys.
Contractors are being advised to adopt a more disciplined approach. To recover costs linked to these disruptions, the industry is being urged to move away from the broad claims that have historically characterised regional disputes.
Employers are unlikely to accept claims that do not clearly distinguish conflict-related impacts from pre-existing project delays. Instead, contractors must precisely document separate heads of claim, including supply chain cost increases, on-site stoppages, and new health and safety requirements.
Market outlook
In the longer term, the sector is in a wait-and-see phase. The market’s trajectory will depend heavily on the government’s ability to manage public finances following a period of significant, unforeseen expenditure.
The cost of defence, combined with reduced tourism revenue, lower oil exports and weaker consumer spending, has created a complex and as yet undetermined fiscal challenge.
Although construction is likely to be used as a tool for economic stimulus once the conflict subsides, the availability of capital for major new projects remains unknown. Government spending priorities will likely shift towards resilience, including accelerated infrastructure development on the UAE’s east coast.
Fujairah and the Sharjah enclave of Khor Fakkan – both located outside the Strait of Hormuz – are expected to play an increasingly central role in strategic infrastructure planning. Over the next decade, investment may focus on strengthening the logistics and industrial capacity of these ports to better shield the federation from future geopolitical shocks.
For the private real estate sector, the outlook depends on whether the attacks that began on 28 February have permanently altered the UAE’s reputation as a secure, low-tax safe haven. While the conflict is testing investor confidence, the country’s operational resilience may still compare favourably with challenges in other global markets.
If the risks are viewed as manageable, investment could rebound quickly. However, prolonged uncertainty would result in a slower recovery. By early April, warning signs had already emerged, with some developers facing cashflow pressures due to slowing sales.
https://image.digitalinsightresearch.in/uploads/NewsArticle/16267286/main.gif -
Acwa solar plants face power output restrictions6 April 2026
Acwa has announced that two of its solar independent power producer (IPP) plants in Saudi Arabia have been subject to temporary power dispatch limitations following instructions from the grid operator.
According to the developer, the grid operator cited alleged reactive power fluctuations affecting grid stability. Acwa said both project companies deny the allegations.
The affected assets are the 1,425MW Al-Kahfah solar photovoltaic (PV) IPP and the 2,000MW Ar Rass 2 solar PV IPP.
Saudi Arabia’s Water & Electricity Holding Company (Badeel) and Acwa, formerly Acwa Power, signed power-purchase agreements with Saudi Power Procurement Company (SPPC) for the development and operation of the plants in 2023.
Ishaa Energy Renewable Company and Nawwar Renewable Energy Company are the project companies specially set up to manage the Al-Kahfah and Ar Rass 2 projects, respectively. Both were set up as joint ventures between Acwa and Badeel.
Al-Kahfah received its commercial operation certificate in November 2025. The plant has been under dispatch limitation since 12 December 2025, with partial dispatch permitted since 11 February 2026.
The accumulated estimated revenue challenged by the principal buyer at Al-Kahfah up to the end of March is approximately SR95m ($25.3m).
Ar Rass 2 received its initial commercial operation certificate in September 2025. It has been under dispatch limitation since 16 January 2026, with partial dispatch permitted since 8 March 2026.
The accumulated estimated revenue challenged by the principal buyer at Ar Rass 2 up to the end of March is approximately SR73m ($19.7m).
Acwa said both project companies have challenged the matter and are conducting detailed technical assessments, including independent third-party analysis. The company said it is also coordinating with the relevant authorities to enable the full restoration of plant operations.
https://image.digitalinsightresearch.in/uploads/NewsArticle/16267226/main.jpg -
Kuwait reports attacks on power and water plants6 April 2026
Two power generation and water desalination plants in Kuwait were damaged in a drone attack on 5 April, according to the Ministry of Electricity, Water & Renewable Energy (MEWRE).
In an official statement, the ministry said the facilities were targeted by “hostile drones as part of the Iranian aggression”, forcing the shutdown of two electricity generation units due to “significant material damage”.
No injuries were reported.
The ministry said technical and emergency teams began work immediately in line with approved contingency plans.
It added that coordination was under way with the relevant authorities to ensure the safety and stability of Kuwait’s electricity and water systems, which it said remained a top priority.
The announcement came amid a broader series of reported attacks on key infrastructure in Kuwait on the same day.
Kuwait Petroleum Corporation separately said fires broke out at operating units following a drone strike, causing “severe material damage”, although no injuries were reported.
MEWRE had previously confirmed that a service building at one of the country’s power generation and water desalination plants was damaged in an attack on the evening of 29 March.
The incident led to the death of one worker of Indian nationality and caused significant material damage to the building.
In a separate statement over the weekend, the ministry said it had restored operations at the main transformer station serving the Jahra area after a technical fault caused a temporary power outage.
Electricity supply was restored to all affected customers following the completion of emergency works, the ministry said.
https://image.digitalinsightresearch.in/uploads/NewsArticle/16267204/main.jpg -
Sharjah reports fire at Khor Fakkan port6 April 2026
Sharjah has reported that a fire broke out at its Khor Fakkan port after debris fell on the facility due to the interception of an unidentified object on Sunday 5 April.
In a social media post on X, the Sharjah media office reported that the incident resulted in several casualties, including one person of Nepalese nationality and three individuals of Pakistani nationality.
في إطار المتابعة المستمرة للحادث الذي تم الإبلاغ عنه سابقاً في ميناء خورفكان اليوم الأحد 5 أبريل، والناجم عن سقوط شظايا بعد اعتراض ناجح من قبل أنظمة الدفاع الجوي؛ تؤكد الجهات المختصة اندلاع حريق في الموقع وقد باشرت فرق الاستجابة للطوارئ التعامل معه بسرعة وكفاءة عالية، وتمت…
— sharjahmedia (@sharjahmedia) April 5, 2026
Last week, Sharjah reported a drone attack targeting the administrative building of Thuraya Telecommunications Company in the emirate’s Central Region.
No injuries were reported during that attack.
Meanwhile, the latest data from the UAE Ministry of Defence, released on 5 April, showed that air defence systems had engaged 50 unmanned aerial vehicles (UAVs), nine ballistic missiles and one cruise missile.
الدفاعات الجوية الإماراتية تتعامل مع الصواريخ الباليستية والجوالة والمسيرات الإيرانية.
UAE Air Defences engaged Iranian
Ballistic and Cruise Missiles and UAVs Attacks#وزارة_الدفاع #وزارة_الدفاع_الإماراتية#MOD#UAEMinistryOfDefence pic.twitter.com/UUIIE5o8MD— وزارة الدفاع |MOD UAE (@modgovae) April 5, 2026
Cumulatively, authorities said 2,191 drones, 24 cruise missiles and 507 ballistic missiles have been intercepted since the onset of the war on 28 February.
https://image.digitalinsightresearch.in/uploads/NewsArticle/16267175/main.jpg
