Completing infrastructure ahead of time
10 December 2024

In late December 2023, Bahrain opened the Al-Fateh Highway project to traffic five months ahead of schedule. The highway connects key areas in Bahrain, including Manama, Mina Salman, Sitra, Muharraq, Bahrain Bay and Juffair, and opening the scheme promptly has significantly improved traffic in one of the most congested areas of the country.
“The secret to success was implementing the project in stages, combined with excellent traffic management,” says Minister of Works Ibrahim Bin Hassan Al-Hawaj.
The successful completion of the Al-Fateh Highway project comes at an important time for Bahrain, as it continues to upgrade its road network.
“The lessons we learned from Al-Fateh Highway are being utilised on other projects. We are working on the Muharraq Ring Road project, and that is also going to be open for traffic well ahead of time,” says Al-Hawaj.
Like Al-Fateh Highway, the Muharraq Ring Road project connects key commercial and residential areas in Bahrain, including North Muharraq, Diyar Al-Muharraq and Dilmunia.
Multifaceted approach
These projects are part of Bahrain’s comprehensive approach to alleviating road traffic.
“In 2016, we launched a study that identified projects that could help ease congestion. It proposed a multifaceted approach that covers many things, including public transport and an intelligent transport system, which introduces automation,” explains Al-Hawaj.
“We have not implemented everything in the study, but we are working through it gradually with the Traffic Council, headed by his excellency the minister of interior, and including the Ministry of Works, Ministry of Transportation and Ministry of Housing & Urban Planning. We have regular meetings to identify challenges and then put forward suitable projects to solve them,” says Al-Hawaj.
The Ministry of Works is responsible for maintaining, improving and expanding the road network. Its projects are split into four categories.
The first two categories are the major projects. The first is building new roads, while the second is improving the existing road network, either by widening roads or upgrading intersections.
Then there are the other two categories. These are maintaining the existing road network – which is a challenging task with existing traffic – and a fourth category that is known as ‘quick wins’. These small, tactical-level projects can be completed quickly to ease specific traffic black spots.
“We have about 60 projects under implementation, valued at BD172m ($456.2m), and among these are 14 strategic projects that amount to BD117m,” says Al-Hawaj.
Upcoming schemes
The pipeline of projects under execution will soon be expanded with the addition of a fourth crossing connecting Busaiteen with Bahrain Bay. The Bahrain Tender Board opened prices for the contract to build the signature bridge crossing in late November.
“The fourth crossing project is going to start in 2025,” says Al-Hawaj.
Looking further ahead, more road contracts will be awarded. “There are more than BD200m of future projects approved, and they will go to tender in the coming two years,” says Al-Hawaj.
There are more than BD200m of future projects approved, and they will go to tender in the coming two years
One of the roads that suffers from high traffic volumes is Sheikh Jaber Ahmed Al-Sabah Highway, from Umm Al-Hassam to the Alba intersection.
“This is our biggest project in the future. There will be four lanes in each direction, and all the intersections will be free-flowing traffic either by underpass or flyovers. We will get rid of all the traffic lights,” says Al-Hawaj.
The project will move into the construction phase next year with preparation works.
“One of the main lessons from the Al-Fateh Highway project is to free the construction zone from any services before construction starts. It will take some time to redirect the existing utilities, and then we will immediately go into construction,” says Al-Hawaj.
Another upcoming major scheme is the Bahrain Northern Link Road (BNLR) project that will run along the northern coast of Manama from the Bahrain Bay area in the east to Madinat Salman in the west. Initial estimates suggest that the scheme, which will have sections onshore and offshore, could cost BD500m to deliver.
Together with the fourth crossing project and the Northern Muharraq Ring Road, the BNLR scheme will create a new road corridor along the northern edge of Bahrain.
Unlike other road projects in Bahrain, the BNLR will be delivered as a public-private partnership project. Dar Al-Handasah was selected for the project’s feasibility study in 2022.
Away from roads, another major area of responsibility for the Ministry of Works is sanitation. At present, 86% of premises in Bahrain are connected to the sanitation network and sewage treatment plants (STPs), and there are plans to connect the remaining 14%.
STP capacity is also increasing. The capacity of Bahrain’s largest plant at Tubli is being doubled, and there is an expansion under way for the STP at Muharraq. The Sitra STP is also being upgraded, using technology from UK company Bluewater, which allows for capacity to increase without adding to the footprint of the site.
A greenfield project is also planned. “We have a new plant coming soon at Khalifa City,” says Al-Hawaj.
“We are finalising the drawings, and a tender is expected to be issued in the first quarter of 2025. We will start with 20,000 cubic metres a day, but the ultimate capacity will be 40,000 cubic metres a day.”
Exclusive from Meed
-
Kuwait awards $381m oil project23 September 2026
-
Kuwait refinery project on track for year-end completion23 September 2026
-
Contractor wins $208m Almoosa hospital MEP contract23 September 2026
-
UAE to develop integrated waste-to-resource pilot23 September 2026
-
Contractors prepare Oxagon Highway 55 bids23 September 2026
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Kuwait awards $381m oil project23 September 2026
Register for MEED’s 14-day trial access
State-owned upstream operator Kuwait Oil Company (KOC) has awarded an oil project contract worth KD117m ($381m) to India’s Megha Engineering & Infrastructure (Meil).
The Supreme Purchasing Committee for Kuwait Petroleum Corporation (KPC) approved the contract last month, paving the way for the official award.
The project focuses on a water separation unit at the Al-Rawdatain facility in Kuwait.
The water separation facility will be developed at Gathering Centre 25 (GC-25), along with a pumping facility at GC-30.
The project will deliver a wide-ranging upgrade of processing and utility infrastructure, including new low-pressure separation and gas-handling equipment such as a three-phase wet separator package, a gas knock-out drum and associated low-pressure gas pipelines, as well as a high-integrity pressure protection system and a high-pressure flare.
Meil will develop the new three-phase low-pressure wet separation facility at GC-25.
The main process equipment will include two wet separator packages, each with a capacity of 150,000 barrels of liquid a day, and a low-pressure gas knock-out drum with a capacity of 53 million standard cubic feet a day, together with associated gas-handling facilities.
The facility will also incorporate an effluent water treatment and transfer system, including an effluent water balance tank equipped with microbubble flotation and induced gas flotation systems, as well as transfer pumps.
Additional GC-25 facilities will include fuel gas treatment, chemical injection, oil recovery and flare connections, along with firewater and deluge systems.
The scope also covers control and safety systems, substations, and associated civil, structural, mechanical, electrical and instrumentation works.
At GC-30, the project will focus on treated-water filtration and high-pressure injection infrastructure.
The scope includes nutshell filters and associated feed pumps with a combined capacity of approximately 500,000 barrels of water a day.
Booster and injection pumps will transfer treated effluent water to designated injection wells.
Additional facilities at GC-30 will include fuel gas treatment, sludge collection and disposal systems, oil recovery systems, control and safety systems, substations, laboratory and workshop facilities, and associated civil, structural, piping, mechanical, electrical and instrumentation works.
The project also includes transfer pipelines connecting GC-25, GC-15 and GC-30.
Meil will carry out modifications to existing tanks at GC-30, as well as process and utility tie-ins, electrical and instrumentation modifications and other infrastructure required to integrate the new facilities with KOC’s existing assets.
Meil’s responsibilities cover the project lifecycle from design and engineering through procurement, construction, testing, pre-commissioning, commissioning, start-up and performance testing.
The contract also includes operation, maintenance, repair and insurance responsibilities for the designated facilities during the applicable operations and maintenance period.
Seven companies submitted bids for the project last November.
The full list of bids was:
- Meil (India) – KD117m ($381m)
- Mechanical Engineering & Contracting Company (Kuwait) – KD130m
- Spetco (Kuwait) – KD158m
- Al-Kharafi (Kuwait) – KD164m
- China Oil HBP Science & Technology (China) – KD169m
- Alghanim International (Kuwait) – KD169m
- Jereh Oil & Gas Engineering (China) – KD191m
In October last year, KOC awarded Meil a separate contract for a project to develop a gas sweetening and recovery facility in west Kuwait.
Meil submitted the lowest bid for that tender, at KD69.2m ($225.5m), in February 2025.
https://image.digitalinsightresearch.in/uploads/NewsArticle/19911322/main.jpg -
Kuwait refinery project on track for year-end completion23 September 2026

A $65m project to replace a substation at the Mina Al-Ahmadi (MAA) refinery is on schedule to be mechanically complete before the end of the year, according to industry sources.
The project is being executed by India’s Larsen & Toubro (L&T), which was awarded the contract in October 2024.
One source said: “This project is approaching completion and is currently on schedule to be completed before the end of the year, although it could still see delays related to the ongoing regional conflict.”
The client is state-owned downstream operator Kuwait National Petroleum Company (KNPC).
Kuwait’s Ministry of Electricity, Water & Renewable Energy (MEW) is also involved in the project and will provide final approvals and sign-off.
The scope of the project includes:
- Construction of a substation
- Installation of transformers
- Installation of medium-voltage switchgear
- Installation of low-voltage auxiliary systems
- Installation of network protection systems
- Installation of disconnecting switches
- Installation of surge arrestors
- Installation of feeder breakers and cubicles
- Installation of low-voltage A/C and D/C equipment
- Installation of battery banks and battery chargers
- Installation of related relay and control panel boards
- Installation of fire alarm and fire protection equipment
- Installation of a SCADA system
- Installation of cables
- Civil works
- Associated facilities
The current project to replace a substation at the MAA refinery closely resembles another project tendered by KNPC more than a decade ago, which L&T also won.
On 18 May 2015, KNPC signed a contract with L&T to build a new 240MW substation at the MAA refinery, valued at KD21.866m.
The new substation, known as M20, was designed to replace an existing substation that was considered old and obsolete.
Mohammed Al-Mutairi, who was KNPC’s chief executive at the time, said the substation building would be explosion-proof and use state-of-the-art control systems.
He said the station’s capacity would increase from 180MW to 240MW, supplying most of the refinery’s electricity needs.
Given the similarities between the two projects, L&T has been able to reuse some designs, creating efficiencies, according to industry sources.
https://image.digitalinsightresearch.in/uploads/NewsArticle/19911319/main.jpg -
Contractor wins $208m Almoosa hospital MEP contract23 September 2026
Register for MEED’s 14-day trial access
Riyadh-based construction firm BEC Arabia has won a SR781m ($208m) contract for the mechanical, electrical and plumbing (MEP) works at Almoosa Hospital in Al-Khobar.
Saudi Arabia’s Almoosa Health Company awarded the contract.
The hospital complex consists of two towers: a 24-storey in-patient tower with 380 beds, and an 11-storey tower with 224 clinics and 113 additional treatment spaces.
It will be built on a 45,000-square-metre site.
A podium spanning the ninth and 10th floors will connect the two towers.
The hospital will also include parking for 1,700 cars.
BEC Arabia won the SR656m ($175m) main construction contract for the hospital in November last year.
In August 2025, MEED reported that Almoosa Health Company had announced it had secured a sharia-compliant credit facility worth SR650m ($173m) from Banque Saudi Fransi.
In a statement published on the Saudi stock exchange (Tadawul), the company said the seven-year facility would be used to support its expansion and growth strategy.
Lebanon’s Dar, US-based Perkins&Will and French design firm Pierre-Yves Rochon designed the project.
https://image.digitalinsightresearch.in/uploads/NewsArticle/19910889/main.jpg -
UAE to develop integrated waste-to-resource pilot23 September 2026
Emirates Biotech and United Arab Emirates University (UAEU) have launched a pilot project in Al-Ain that could provide a model for larger waste-to-resource facilities.
The project involves developing the UAE’s first integrated organic-waste valorisation pilot plant, which will test whether food waste and compostable packaging can be processed together to recover resources and reduce waste sent to landfill.
Located near the UAEU campus, the 40kg-a-day facility will process organic waste to produce renewable biogas and nutrient-rich compost. The project is intended to generate technical and operating data that could support the development of larger-scale facilities.
Emirates Biotech and UAEU will design, build and operate the pilot plant as part of a two-year research project running from August 2026 to August 2028. Installation and commissioning are expected to be completed by August 2027.
The plant will combine anaerobic digestion and composting. Anaerobic digestion will convert the organic waste into renewable biogas, while the resulting digestate will be composted to produce nutrient-rich compost.
A laboratory-scale assessment will also examine the potential to convert the biogas into renewable hydrogen.
Food waste accounts for nearly 40% of daily municipal solid waste in the UAE, according to Emirates Biotech, and much of it is currently disposed of in landfills.
The pilot will therefore assess the technical and operational feasibility of recovering value from two waste streams through a single integrated process.
If successfully scaled, Emirates Biotech says an integrated organic-waste valorisation plant could reduce CO₂ emissions by 89% compared with landfilling.
The project is expected to provide a scalable and modular model for converting food waste and compostable packaging into renewable biogas and compost, with the findings intended to inform the development of larger waste-to-resource facilities.
https://image.digitalinsightresearch.in/uploads/NewsArticle/19908972/main.jpg -
Contractors prepare Oxagon Highway 55 bids23 September 2026

Contractors are preparing to submit bids on 28 September for a design-and-build contract for permanent upgrade works on Highway 55 in the kingdom’s Oxagon region.
The first phase of the project includes constructing 14 kilometres of road, with two lanes in each direction. It also includes one bridge and three interchanges.
The project duration is 22 months.
Highway 55 connects the Red Sea coast with the mainland in northwestern Saudi Arabia. It is currently the only road providing north-south connectivity between Duba and the Neom region.
MEED reported exclusively in August 2025 that contractors had submitted responses to an expression of interest notice that Neom had issued earlier that month.
The project is expected to support cargo movement from Duba Port to other parts of the kingdom and the wider region.
Last year, Neom tested a pilot initiative by handling a shipment that travelled from Cairo via the Port of Safaga, across the Red Sea to the Port of Neom, and then inland to Erbil, Iraq.
In a statement, Neom said: “The shipment travelled through an intermodal corridor spanning over 900 kilometres, marking a significant milestone in the kingdom’s transformation into a regional and global logistics hub.”
The Port of Neom is located on the Red Sea near the Arar border, a key entry point into Iraq.
https://image.digitalinsightresearch.in/uploads/NewsArticle/19907876/main.jpg