Companies confirm Saudi gigaproject slowdown
11 September 2024

Companies working on Saudi Arabia’s gigaprojects have expressed concerns about the pace of development in the kingdom despite increased levels of contract awards this year.
The concerns demonstrate how Saudi Arabia’s gigaprojects programme and the marketing hype it has generated risks falling short of market expectations in spite of delivering solid progress with contract awards.
Companies in Saudi Arabia have reported a noticeable slowdown in activity on the kingdom’s gigaprojects programme this year.
During MEED’s webinar on Saudi Arabia’s projects market in late August, attendees were asked: “Have you seen a noticeable slowdown in activity on the gigaprojects programme this year?”. Of the 362 respondents, 72% reported a slowdown, 19% said that activity levels are roughly the same, and 10% reported an increase in activity.
The poll results reflect a significant change in sentiment towards the Saudi market since the start of this year. In January, attendees of another MEED webinar on the Saudi projects market were asked if they anticipated more contract awards in 2024 than in 2023. Over 92% answered that they expected more awards in 2024, building on the record numbers registered in 2023, when there were $44.5bn of contract awards in the kingdom across all sectors.
Since January, there have been reports on how the delivery of The Line at Neom will be phased, as well as rephasing exercises for other projects as budgets come under strain. These exercises followed comments from the Finance Ministry at the end of last year, which admitted that some projects will be slowed down as the government manages its finances more tightly.
The perceived slowdown in activity on the gigaprojects expressed in August is also reflected by data from regional projects tracker MEED Projects. During August this year, no contract awards were recorded on the kingdom’s five official gigaprojects: Diriyah, Neom, Qiddiya, Roshn and the projects being developed by Red Sea Global.
The total value of contracts awarded by the gigaproject developers in August 2023 was $587m, which suggests the performance in August this year was not just a result of a typical seasonal summer slowdown.
The lack of contract awards for the gigaprojects in August bucks the otherwise positive trend for the year. By the end of August, there had been $14bn of contract awards in 2024 compared to $9bn during the same period in 2023, representing a 55% increase on last year. The total registered by the end of August this year is close to achieving the $15.8bn total registered for the full 12 months of 2023.
Major awards this year have included the $4.7bn contract to build dams at Trojena that was won by Italy’s WeBuild and a $2bn contract won by a joint venture of local firm Albawani and Qatari contractor Urbacon Trading & Contracting for the construction of assets in the Wadi Safar development of the Diriyah project in Riyadh. An estimated $1bn design-and-build contract was also secured by a joint venture of local firm El-Seif Engineering Contracting, Egyptian contractor Hassan Allam Construction and Beijing-headquartered China Harbour Engineering Company to deliver infrastructure and building works for Terminal 1 of the port at the Oxagon industrial city development in Neom.
Wider market
The broader Saudi projects market has followed a similar trajectory. By the end of August this year, there had been $72bn of contract awards compared to $44.5bn of contract awards during the same period of 2023. During August 2024, there were $14bn of contract awards, and if the market replicates this performance again, it will have already outperformed the $86bn total recorded for all of 2023.
Major highlights include the National Housing Company (NHC) signing an agreement with Beijing-headquartered China Machinery Engineering Corporation (CMEC) to construct 20,000 housing units for projects being developed by NHC. Another major signing was the Royal Commission for Riyadh City (RCRC) awarding a SR4bn ($1bn) design-and-build contract to upgrade the Wadi Laban cable bridge to the joint venture of Turkish contracting firm IC Ictas and Riyadh-based Al-Rashid Trading & Contracting Company.
Outside of the construction sector, Saudi Aramco has awarded billions of dollars worth of contracts for major projects such as the third phase of the kingdom’s Master Gas System and the Fadhili gas plant.
For some contractors, it is not the volume of work being awarded that is the main issue but rather the pace at which contracts are awarded.
“We were rushed to submit bids for a major project before the end of last year. There have been changes to the scope and clarifications, but ultimately, there is still no decision on a contract award,” says an international contractor working in Saudi Arabia.
Payments are another perennial concern for companies working on projects in Saudi Arabia and the rest of the GCC. Despite the buoyant market conditions, most companies still say that getting paid on time is a problem. During the MEED webinar in August, attendees were asked if their companies were being paid on time for work on projects in the GCC. Of the 382 respondents, 64% said they were not being paid on time, while 36% said they were being paid on time.
While contractors remain optimistic about the volume of work planned in Saudi Arabia, the slowdown in spending is forcing a shift in contractors’ bidding strategies.
“Saudi Arabia is booming,” says an international contractor working in the kingdom. “A lot of oil and gas projects are moving forward, but for the civil construction, we have noticed a slowdown and some challenges with cashflow. We expect this trend to continue, and to avoid these problems, we will focus our efforts on the revenue-generating projects.”
Exclusive from Meed
-
Saudi Arabia battery storage awards provide fresh lift24 August 2026
-
Qatar receives bids for major power grid expansion24 August 2026
-
Maaden closes $1bn term loan and credit facility24 August 2026
-
Dubai inflation slows to 5.3% in July24 August 2026
-
Libya oil project on track for 2027 completion24 August 2026
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Saudi Arabia battery storage awards provide fresh lift24 August 2026
Commentary
Mark Dowdall
Power & water editorThe latest battery storage awards provide a welcome injection of investment into Saudi Arabia’s power market, which has seen a sharp slowdown in contract awards this year.
Saudi Power Procurement Company’s four Group 1 storage service agreements, announced last week, are worth more than $1.16bn and cover 2,000MW of capacity.
That is significant against the wider market. According to regional project tracker MEED Projects, Saudi Arabia recorded $19.7bn in power sector contract awards in the first seven months of 2025, compared with just $2.5bn in new awards in the same period this year.
The battery energy storage system (bess) awards therefore account for a sizeable share of the activity recorded so far this year and provide a much-needed source of new contracting activity.
Importantly, this is not a one-off. SPPC issued the request for proposal (RFP) for its second group of bess projects in July, covering six projects with a combined capacity of 3,000MW and 12,000MWh.
With the Group 1 tender taking around 18 months from RFP to contract award, it is reasonable to expect Group 2 contracts to be signed in 2027.
At the same time, the awards for six independent renewable plants under Round 7 of Saudi Arabia’s National Renewable Energy Programme (NREP), with a combined capacity of 5,300MW, are also likely to move into next year, with the latest bid deadlines now extending into September.
Although a substantial pipeline remains in procurement, it is only once these projects move from tender to award and into construction that this pipeline translates into market activity.
It is important that these tenders continue to progress at the pace established by the early rounds of Saudi Arabia’s renewable energy programme and now also SPPC’s independent storage provider bess scheme.
https://image.digitalinsightresearch.in/uploads/NewsArticle/18962923/main.jpg -
Qatar receives bids for major power grid expansion24 August 2026

Qatar General Electricity & Water Corporation (Kahramaa) has received bids for several packages under a major power transmission expansion project tendered in April.
The project covers new substations at multiple voltage levels, as well as the supply and installation of 400kV extra-high-voltage power cables. The overall scheme is estimated to cost $650m.
It is being tendered as part of Kahramaa’s 2026 procurement plan, which includes 198 tenders with a total estimated value of QR21.4bn ($5.9bn).
According to sources, bids were submitted for the following packages on 20 August:
- Substation packages S1 and S2, covering new 132/11kV substations (estimated cost: $200m)
- Package S3, covering new 66/11kV substations ($50m)
- Package S4, including a new 400/220/132kV substation, as well as upgrades and modifications to existing 400kV and 220kV substations ($200m)
- Package S5, covering new 132/11kV substations and upgrades to existing 132kV and 66kV substations ($100m)
- Cable packages C1 and C2, covering 400kV cables ($100m)
Kahramaa previously stated that foreign companies not registered in Qatar would be allowed to participate in the bidding, subject to meeting specified conditions, including registration and certification requirements.
In June, the electricity and water utility awarded contracts worth more than QR2.2bn ($604m) to expand the electricity transmission network in the country’s western region.
The engineering, procurement and construction (EPC) works will support the integration of the 2GW Dukhan solar power project into Qatar’s national electricity grid. The scope includes new and upgraded substations, as well as the installation of underground cables and overhead transmission lines.
Kahramaa said contracts were awarded to local firm Voltage Engineering, Turkiye’s Best & Betas Consortium, India’s Larsen & Toubro and South Korea’s LS Cable.
Of Kahramaa’s 2026 procurement plan, electricity transmission projects account for QR8.9bn ($2.4bn) and include the construction of new 400/132kV substations in Al-Wukair and Al-Mashaf, as well as the expansion of 400kV substations at Ras Laffan.
These also cover the installation of 132kV underground cables between Al-Sailiya and Al-Rayyan over a 24-kilometre route, as well as upgrades to the 400kV and 220kV networks.
Additionally, there are 64 planned electricity distribution projects managed by the Electricity Distribution Department that cover the medium-voltage and low-voltage networks throughout Doha and the regional municipalities.
https://image.digitalinsightresearch.in/uploads/NewsArticle/18962223/main.jpg -
Maaden closes $1bn term loan and credit facility24 August 2026
Saudi Arabian Mining Company (Maaden) has announced the closing of its inaugural international syndicated term loan and revolving credit facilities, worth a total of $1bn.
The $500m international term loan facility will support Maaden’s growth agenda and general corporate purposes, including funding growth projects across its portfolio.
The $500m international revolving credit facility, which is expected to remain undrawn, provides additional committed funding capacity “as Maaden continues to scale its business and execute its long-term growth strategy”.
The transaction “was met with strong support from the international banking market, attracting participation from a diverse group of leading international banks across key global financial markets”, including the US, Canada, Europe, China and Japan. The facilities were oversubscribed, Maaden said.
ALSO READ: Maaden and Aramco sign deal to create joint venture
“The level of demand reflects the global banking community’s confidence in Maaden’s financial strength, strategic direction and ambitious growth plans,” the Saudi state miner said in its statement.
“The facilities mark another significant milestone in Maaden’s funding journey – further diversifying its sources of funding and broadening its access to global capital providers as the company continues to advance its long-term growth ambitions.
“Maaden continues to make significant progress across its growth pipeline, expanding production, advancing major projects and accelerating exploration as it builds a world-class mining company at the heart of Saudi Arabia’s economic transformation.”
https://image.digitalinsightresearch.in/uploads/NewsArticle/18962086/main4516.jpg -
Dubai inflation slows to 5.3% in July24 August 2026
Dubai’s annual inflation rate slowed to 5.3% in July, down from 5.7% in June, as a decline in transport costs eased pressure on consumer prices, according to Emirates NBD.
The bank said the slowdown supported its view that price growth peaked at mid-year, and it expects inflation to continue easing through the rest of 2026. Monthly price growth slowed to 0.1% in July, from 0.4% in June, the weakest pace since February.
Transport was the clearest sign of the moderation. Annual price growth in the category slowed to 11.9% in July, from 18.1% in June, as transport costs fell 3.7% over the month. Fuel and lubricant inflation eased to 24.1% year on year, from 48.3%, tracking a decline in local petrol prices.
Petrol remains the main swing factor in the emirate’s inflation. Transport contributed 1.1 percentage points to headline inflation in July, down from 1.7 percentage points in June. Emirates NBD said the relief may prove temporary, with Super 98 petrol prices climbing 5.9% in August to leave them 33.8% higher than a year earlier. The bank expects headline inflation to edge higher in the August figures before easing again later in the year.
The UAE deregulated petrol and diesel prices in 2015 and reviews them monthly against global prices, meaning changes in global fuel costs pass through to consumers quickly. Transport, which includes fuel, accounts for 9% of Dubai’s consumer price index basket.
Housing remained the largest contributor to inflation even as its impulse faded. Housing and utilities, which account for about two-fifths of the basket, added 2.8 percentage points to headline inflation. Annual price growth in the category slowed to 7.0%, from 7.4% in January.
Food inflation edged up to 7.8% year on year, from 7.6% in June, which the bank attributed to lingering supply-chain disruption from the regional conflict. Inflation in restaurants and hotels accelerated to 4.5% year on year, from 1.7% in June.
Emirates NBD forecasts inflation of 2.9% by year-end but said risks to that projection were tilted to the upside, given lingering pressures in food and housing.
https://image.digitalinsightresearch.in/uploads/NewsArticle/18961735/main1839.jpg -
Libya oil project on track for 2027 completion24 August 2026

The project to develop a workers’ camp at Libya’s Erawin oil field is on track for completion next year, according to industry sources.
The project, estimated to be worth about $50m, is being executed by the Libyan oil services company Al-Saraya Al-Hamara, headquartered in the city of Sebha.
The Libyan company was awarded the contract in February 2025.
The scope of the project includes:
- Construction of an accommodation camp
- Construction of the camp maintenance warehouse
- Construction of the camp office
- Construction of a fire brigade shelter
- Construction of a kitchen and mess hall
- Construction of a mosque
- Construction of a laundry room
- Construction of a clinic
- Construction of parking facilities
- Installation of a fire and gas system
- Installation of a power generator
- Construction of associated facilities
The client on the project is Zallaf Libya Oil & Gas Exploration & Production Company.
Zallaf Libya Oil & Gas Exploration & Production Company was established in Libya in 2013 and is wholly owned by Libya’s state-owned National Oil Corporation.
The Erawin field development project is located about 800 kilometres south of Tripoli and 100km southwest of the El-Sharara field.
Libya shipped its first cargo of crude from the Erawin oil field in November 2023.
The shipment departed from Libya’s Zawiyah port and consisted of 600,000 barrels of crude.
Australia-based Worley Parsons was appointed as the front-end engineering and design (feed) contractor for the early production facility project in 2019.
https://image.digitalinsightresearch.in/uploads/NewsArticle/18953632/main.jpg