Companies confirm Saudi gigaproject slowdown

11 September 2024

 

Companies working on Saudi Arabia’s gigaprojects have expressed concerns about the pace of development in the kingdom despite increased levels of contract awards this year. 

The concerns demonstrate how Saudi Arabia’s gigaprojects programme and the marketing hype it has generated risks falling short of market expectations in spite of delivering solid progress with contract awards. 

Companies in Saudi Arabia have reported a noticeable slowdown in activity on the kingdom’s gigaprojects programme this year. 

During MEED’s webinar on Saudi Arabia’s projects market in late August, attendees were asked: “Have you seen a noticeable slowdown in activity on the gigaprojects programme this year?”. Of the 362 respondents, 72% reported a slowdown, 19% said that activity levels are roughly the same, and 10% reported an increase in activity. 

The poll results reflect a significant change in sentiment towards the Saudi market since the start of this year. In January, attendees of another MEED webinar on the Saudi projects market were asked if they anticipated more contract awards in 2024 than in 2023. Over 92% answered that they expected more awards in 2024, building on the record numbers registered in 2023, when there were $44.5bn of contract awards in the kingdom across all sectors. 

Since January, there have been reports on how the delivery of The Line at Neom will be phased, as well as rephasing exercises for other projects as budgets come under strain. These exercises followed comments from the Finance Ministry at the end of last year, which admitted that some projects will be slowed down as the government manages its finances more tightly.

The perceived slowdown in activity on the gigaprojects expressed in August is also reflected by data from regional projects tracker MEED Projects. During August this year, no contract awards were recorded on the kingdom’s five official gigaprojects: Diriyah, Neom, Qiddiya, Roshn and the projects being developed by Red Sea Global.

The total value of contracts awarded by the gigaproject developers in August 2023 was $587m, which suggests the performance in August this year was not just a result of a typical seasonal summer slowdown. 

The lack of contract awards for the gigaprojects in August bucks the otherwise positive trend for the year. By the end of August, there had been $14bn of contract awards in 2024 compared to $9bn during the same period in 2023, representing a 55% increase on last year. The total registered by the end of August this year is close to achieving the $15.8bn total registered for the full 12 months of 2023.

Major awards this year have included the $4.7bn contract to build dams at Trojena that was won by Italy’s WeBuild and a $2bn contract won by a joint venture of local firm Albawani and Qatari contractor Urbacon Trading & Contracting for the construction of assets in the Wadi Safar development of the Diriyah project in Riyadh. An estimated $1bn design-and-build contract was also secured by a joint venture of local firm El-Seif Engineering Contracting, Egyptian contractor Hassan Allam Construction and Beijing-headquartered China Harbour Engineering Company to deliver infrastructure and building works for Terminal 1 of the port at the Oxagon industrial city development in Neom.

Wider market

The broader Saudi projects market has followed a similar trajectory. By the end of August this year, there had been $72bn of contract awards compared to $44.5bn of contract awards during the same period of 2023. During August 2024, there were $14bn of contract awards, and if the market replicates this performance again, it will have already outperformed the $86bn total recorded for all of 2023. 

Major highlights include the National Housing Company (NHC) signing an agreement with Beijing-headquartered China Machinery Engineering Corporation (CMEC) to construct 20,000 housing units for projects being developed by NHC. Another major signing was the Royal Commission for Riyadh City (RCRC) awarding a SR4bn ($1bn) design-and-build contract to upgrade the Wadi Laban cable bridge to the joint venture of Turkish contracting firm IC Ictas and Riyadh-based Al-Rashid Trading & Contracting Company.

Outside of the construction sector, Saudi Aramco has awarded billions of dollars worth of contracts for major projects such as the third phase of the kingdom’s Master Gas System and the Fadhili gas plant. 

For some contractors, it is not the volume of work being awarded that is the main issue but rather the pace at which contracts are awarded.

“We were rushed to submit bids for a major project before the end of last year. There have been changes to the scope and clarifications, but ultimately, there is still no decision on a contract award,” says an international contractor working in Saudi Arabia. 

Payments are another perennial concern for companies working on projects in Saudi Arabia and the rest of the GCC. Despite the buoyant market conditions, most companies still say that getting paid on time is a problem. During the MEED webinar in August, attendees were asked if their companies were being paid on time for work on projects in the GCC. Of the 382 respondents, 64% said they were not being paid on time, while 36% said they were being paid on time. 

While contractors remain optimistic about the volume of work planned in Saudi Arabia, the slowdown in spending is forcing a shift in contractors’ bidding strategies.

“Saudi Arabia is booming,” says an international contractor working in the kingdom. “A lot of oil and gas projects are moving forward, but for the civil construction, we have noticed a slowdown and some challenges with cashflow. We expect this trend to continue, and to avoid these problems, we will focus our efforts on the revenue-generating projects.”

https://image.digitalinsightresearch.in/uploads/NewsArticle/12499188/main.gif
Colin Foreman
Related Articles
  • Kuwait awards $381m oil project

    23 September 2026

    Register for MEED’s 14-day trial access 

    State-owned upstream operator Kuwait Oil Company (KOC) has awarded an oil project contract worth KD117m ($381m) to India’s Megha Engineering & Infrastructure (Meil).

    The Supreme Purchasing Committee for Kuwait Petroleum Corporation (KPC) approved the contract last month, paving the way for the official award.

    The project focuses on a water separation unit at the Al-Rawdatain facility in Kuwait.

    The water separation facility will be developed at Gathering Centre 25 (GC-25), along with a pumping facility at GC-30.

    The project will deliver a wide-ranging upgrade of processing and utility infrastructure, including new low-pressure separation and gas-handling equipment such as a three-phase wet separator package, a gas knock-out drum and associated low-pressure gas pipelines, as well as a high-integrity pressure protection system and a high-pressure flare.

    Meil will develop the new three-phase low-pressure wet separation facility at GC-25.

    The main process equipment will include two wet separator packages, each with a capacity of 150,000 barrels of liquid a day, and a low-pressure gas knock-out drum with a capacity of 53 million standard cubic feet a day, together with associated gas-handling facilities.

    The facility will also incorporate an effluent water treatment and transfer system, including an effluent water balance tank equipped with microbubble flotation and induced gas flotation systems, as well as transfer pumps.

    Additional GC-25 facilities will include fuel gas treatment, chemical injection, oil recovery and flare connections, along with firewater and deluge systems.

    The scope also covers control and safety systems, substations, and associated civil, structural, mechanical, electrical and instrumentation works.

    At GC-30, the project will focus on treated-water filtration and high-pressure injection infrastructure.

    The scope includes nutshell filters and associated feed pumps with a combined capacity of approximately 500,000 barrels of water a day.

    Booster and injection pumps will transfer treated effluent water to designated injection wells.

    Additional facilities at GC-30 will include fuel gas treatment, sludge collection and disposal systems, oil recovery systems, control and safety systems, substations, laboratory and workshop facilities, and associated civil, structural, piping, mechanical, electrical and instrumentation works.

    The project also includes transfer pipelines connecting GC-25, GC-15 and GC-30.

    Meil will carry out modifications to existing tanks at GC-30, as well as process and utility tie-ins, electrical and instrumentation modifications and other infrastructure required to integrate the new facilities with KOC’s existing assets.

    Meil’s responsibilities cover the project lifecycle from design and engineering through procurement, construction, testing, pre-commissioning, commissioning, start-up and performance testing.

    The contract also includes operation, maintenance, repair and insurance responsibilities for the designated facilities during the applicable operations and maintenance period.

    Seven companies submitted bids for the project last November.

    The full list of bids was:

    • Meil (India) – KD117m ($381m)
    • Mechanical Engineering & Contracting Company (Kuwait) – KD130m
    • Spetco (Kuwait) – KD158m
    • Al-Kharafi (Kuwait) – KD164m
    • China Oil HBP Science & Technology (China) – KD169m
    • Alghanim International (Kuwait) – KD169m
    • Jereh Oil & Gas Engineering (China) – KD191m

    In October last year, KOC awarded Meil a separate contract for a project to develop a gas sweetening and recovery facility in west Kuwait.

    Meil submitted the lowest bid for that tender, at KD69.2m ($225.5m), in February 2025.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19911322/main.jpg
    Wil Crisp
  • Kuwait refinery project on track for year-end completion

    23 September 2026

     

    A $65m project to replace a substation at the Mina Al-Ahmadi (MAA) refinery is on schedule to be mechanically complete before the end of the year, according to industry sources.

    The project is being executed by India’s Larsen & Toubro (L&T), which was awarded the contract in October 2024.

    One source said: “This project is approaching completion and is currently on schedule to be completed before the end of the year, although it could still see delays related to the ongoing regional conflict.”

    The client is state-owned downstream operator Kuwait National Petroleum Company (KNPC).

    Kuwait’s Ministry of Electricity, Water & Renewable Energy (MEW) is also involved in the project and will provide final approvals and sign-off.

    The scope of the project includes:

    • Construction of a substation
    • Installation of transformers
    • Installation of medium-voltage switchgear
    • Installation of low-voltage auxiliary systems
    • Installation of network protection systems
    • Installation of disconnecting switches
    • Installation of surge arrestors
    • Installation of feeder breakers and cubicles
    • Installation of low-voltage A/C and D/C equipment
    • Installation of battery banks and battery chargers
    • Installation of related relay and control panel boards
    • Installation of fire alarm and fire protection equipment
    • Installation of a SCADA system
    • Installation of cables
    • Civil works
    • Associated facilities

    The current project to replace a substation at the MAA refinery closely resembles another project tendered by KNPC more than a decade ago, which L&T also won.

    On 18 May 2015, KNPC signed a contract with L&T to build a new 240MW substation at the MAA refinery, valued at KD21.866m.

    The new substation, known as M20, was designed to replace an existing substation that was considered old and obsolete.

    Mohammed Al-Mutairi, who was KNPC’s chief executive at the time, said the substation building would be explosion-proof and use state-of-the-art control systems.

    He said the station’s capacity would increase from 180MW to 240MW, supplying most of the refinery’s electricity needs.

    Given the similarities between the two projects, L&T has been able to reuse some designs, creating efficiencies, according to industry sources.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19911319/main.jpg
    Wil Crisp
  • Contractor wins $208m Almoosa hospital MEP contract

    23 September 2026

    Register for MEED’s 14-day trial access 

    Riyadh-based construction firm BEC Arabia has won a SR781m ($208m) contract for the mechanical, electrical and plumbing (MEP) works at Almoosa Hospital in Al-Khobar.

    Saudi Arabia’s Almoosa Health Company awarded the contract.

    The hospital complex consists of two towers: a 24-storey in-patient tower with 380 beds, and an 11-storey tower with 224 clinics and 113 additional treatment spaces.

    It will be built on a 45,000-square-metre site.

    A podium spanning the ninth and 10th floors will connect the two towers.

    The hospital will also include parking for 1,700 cars.

    BEC Arabia won the SR656m ($175m) main construction contract for the hospital in November last year.

    In August 2025, MEED reported that Almoosa Health Company had announced it had secured a sharia-compliant credit facility worth SR650m ($173m) from Banque Saudi Fransi.

    In a statement published on the Saudi stock exchange (Tadawul), the company said the seven-year facility would be used to support its expansion and growth strategy.

    Lebanon’s Dar, US-based Perkins&Will and French design firm Pierre-Yves Rochon designed the project.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19910889/main.jpg
    Yasir Iqbal
  • UAE to develop integrated waste-to-resource pilot

    23 September 2026

    Emirates Biotech and United Arab Emirates University (UAEU) have launched a pilot project in Al-Ain that could provide a model for larger waste-to-resource facilities.

    The project involves developing the UAE’s first integrated organic-waste valorisation pilot plant, which will test whether food waste and compostable packaging can be processed together to recover resources and reduce waste sent to landfill.

    Located near the UAEU campus, the 40kg-a-day facility will process organic waste to produce renewable biogas and nutrient-rich compost. The project is intended to generate technical and operating data that could support the development of larger-scale facilities.

    Emirates Biotech and UAEU will design, build and operate the pilot plant as part of a two-year research project running from August 2026 to August 2028. Installation and commissioning are expected to be completed by August 2027.

    The plant will combine anaerobic digestion and composting. Anaerobic digestion will convert the organic waste into renewable biogas, while the resulting digestate will be composted to produce nutrient-rich compost.

    A laboratory-scale assessment will also examine the potential to convert the biogas into renewable hydrogen.

    Food waste accounts for nearly 40% of daily municipal solid waste in the UAE, according to Emirates Biotech, and much of it is currently disposed of in landfills.

    The pilot will therefore assess the technical and operational feasibility of recovering value from two waste streams through a single integrated process.

    If successfully scaled, Emirates Biotech says an integrated organic-waste valorisation plant could reduce CO₂ emissions by 89% compared with landfilling.

    The project is expected to provide a scalable and modular model for converting food waste and compostable packaging into renewable biogas and compost, with the findings intended to inform the development of larger waste-to-resource facilities.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19908972/main.jpg
    Mark Dowdall
  • Contractors prepare Oxagon Highway 55 bids

    23 September 2026

     

    Contractors are preparing to submit bids on 28 September for a design-and-build contract for permanent upgrade works on Highway 55 in the kingdom’s Oxagon region.

    The first phase of the project includes constructing 14 kilometres of road, with two lanes in each direction. It also includes one bridge and three interchanges.

    The project duration is 22 months.

    Highway 55 connects the Red Sea coast with the mainland in northwestern Saudi Arabia. It is currently the only road providing north-south connectivity between Duba and the Neom region.

    MEED reported exclusively in August 2025 that contractors had submitted responses to an expression of interest notice that Neom had issued earlier that month.

    The project is expected to support cargo movement from Duba Port to other parts of the kingdom and the wider region.

    Last year, Neom tested a pilot initiative by handling a shipment that travelled from Cairo via the Port of Safaga, across the Red Sea to the Port of Neom, and then inland to Erbil, Iraq.

    In a statement, Neom said: “The shipment travelled through an intermodal corridor spanning over 900 kilometres, marking a significant milestone in the kingdom’s transformation into a regional and global logistics hub.”

    The Port of Neom is located on the Red Sea near the Arar border, a key entry point into Iraq.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19907876/main.jpg
    Yasir Iqbal