Aramco negotiates with gas plants PPP bidders

18 July 2023

Register for MEED's guest programme 

Saudi Aramco is negotiating with two consortiums of bidders competing for one of the first public-private partnership (PPP) deals in its main oil and gas business.

The project involves modifying and upgrading sulphur recovery units (SRUs) at Aramco's gas processing plants located in the kingdom's Eastern Province.

Two consortiums submitted proposals by the deadline of 30 April for the scheme, which involves building tail-gas treatment (TGT) facilities at seven gas processing plants in the kingdom:

  • Vision Invest (Saudi Arabia) / Larsen & Toubro Energy Hydrocarbon (India)
  • Lamar Holding (Saudi Arabia) / Hyundai Engineering (South Korea) / Korea Overseas Infrastructure & Urban Development Corporation (South Korea) / Enerflex (Canada) / Brookfield (Canada) / Export-Import Bank of China (China)

The facilities are to be developed on a build, own and operate (BOO) or build-own-operate-transfer (BOOT) basis. This will make it one of Aramco’s first PPP projects in its main oil and gas business, if not the first.

Under the desulphurisation programme, Aramco expects third-party investors to build large downstream TGT units to collect and process tail gas discharged from SRUs at seven identified gas plants, MEED reported in December 2021.

Based on Aramco's initial evaluation of proposals, the consortium led by Lamar Holding pulled ahead in the race to win the contract to become the sole developer of the desulphurisation facilities, sources told MEED.

The Lamar-led consortium has submitted “considerably lower prices” than the other group being headed by Vision Invest, for both Zone I and II gas plants, according to sources.

“Lamar is the lowest bidder for both packages [Zones I and II], but Aramco is still in negotiations with the other consortium,” one source said.

“It remains to be seen whether one consortium wins both packages or Aramco chooses to divide them between the two groups,” another source said.

Aramco issued expressions of interest (EoI) for the scheme on 18 October 2021 and received EoI documents on 30 November that year. The Saudi energy giant then issued the main tender for the PPP project in May last year, as MEED reported.

Bidders were initially required to submit proposals by 30 September last year. The proposal submission deadline was moved to 15 December, then to 15 March this year, and again extended it to 31 March. Bids were eventually submitted on 30 April.

SO2 reduction campaign

The Aramco programme is in line with the regulations for emissions to air from stationary sources set out by Saudi Arabia’s Environment, Water & Agriculture Ministry. These stipulate that sulphur dioxide (SO2) emissions from stationary sources must not exceed 250 parts per million volume (dry and 0 per cent oxygen basis). They must also comply with the SO2 ambient emission limits or ground-level SO2 concentration.

The rollout of the desulphurisation scheme stems from Aramco’s goal to achieve net-zero carbon emissions by 2050 and is part of its environmental, social and governance initiatives, sources previously said.

Seven gas plants in Saudi Arabia’s Eastern Province have been identified from which tail gas needs to be treated for up to 99.9 per cent SO2 removal:

  • Berri
  • Haradh
  • Hawiyah
  • Khursaniyah
  • Shedgum
  • Uthmaniyah
  • Wasit

The scope of the scheme has been split into two packages, one source said. The first package covers gas plants in Aramco’s Zone 1 – Berri, Khursaniyah and Wasit – while the second package relates to units in Zone 2 – Haradh, Hawiyah, Shedgum and Uthmaniyah.

Along with fully financing the project, the developer will need to adopt one of the following commercial desulphurisation technologies approved by Aramco for the scheme:

  • TGT reduction absorption
  • Ammonia-based desulphurisation
  • Dry sorbent injection
  • Flue gas desulphurisation using gypsum

According to Aramco, the project will cover “the end-to-end application of the approved technologies, including but not limited to required plot space, utilities, market analysis and logistics of feedstock and byproduct, contractual arrangements, risks associated with each technology related to safety, process reliability and SO2 emissions compliance on a continuous basis”.

Aramco expects the common TGT facility to be operational by 2027.

https://image.digitalinsightresearch.in/uploads/NewsArticle/11010795/main3124.jpg
Indrajit Sen
Related Articles
  • Iranian missiles hit Qatari and Kuwaiti fuel tankers

    1 April 2026

    Iranian missiles have struck fuel tankers in Gulf waters belonging to Qatar and Kuwait, as Tehran continues to target energy, industrial and logistical assets in GCC countries.

    A fuel oil tanker chartered by QatarEnergy, named Aqua 1, was struck by missiles in Qatar’s northern territorial waters in the early hours of 1 April, the company said in a statement.

    “None of the crew members on board were injured, and there is no impact on the environment as a result of this incident,” QatarEnergy said.

    Earlier, on 31 March,  said one of its very large crude carriers, Al-Salmi, caught fire after being hit by an Iranian missile while anchored in UAE waters just outside Dubai.

    The vessel’s crew, with support from UAE authorities, extinguished the fire by 04:26 Kuwait time on 31 March, KPC said. It added that all 24 crew members were safe and that no oil spill or environmental damage occurred.

    “KPC is continuing to assess the damage in coordination with relevant authorities,” the Kuwaiti state energy conglomerate said.

    ALSO READ: Iran strikes Gulf aluminium assets after hits on its steel sector
    https://image.digitalinsightresearch.in/uploads/NewsArticle/16217670/main4010.jpg
    Indrajit Sen
  • One killed and one injured in drone attacks on the UAE

    1 April 2026

    Debris falling from Iranian drones intercepted by the UAE’s air defence systems has killed one person in the emirate of Fujairah and injured another in Umm Al-Quwain in two separate incidents on 1 April.

    A successful interception of a drone by UAE air defence forces resulted in debris falling on a farm in Fujairah, leading to the death of a Bangladeshi national.

    The latest fatality brings the total death toll in the UAE since the start of the US-Israel-Iran war to 12. Most of the deaths have been caused by falling debris following interceptions. Among the deceased are two members of the UAE armed forces who died while performing their duties, as well as a Moroccan civilian contracted by the armed forces.

    The remaining victims were of Bangladeshi, Indian, Nepali, Pakistani and Palestinian nationalities.

    Hours after the Fujairah incident, authorities in Umm Al-Quwain confirmed that an Indian national was injured when debris from an intercepted drone fell in the emirate.

    In a statement posted on its official social media channels, the Umm Al-Quwain government media office said the incident occurred near an industrial facility in the Umm Al-Thuoob area, after air defence systems successfully intercepted an unmanned aerial vehicle (UAV).

    Meanwhile, the latest data from the UAE Ministry of Defence, released on 31 March, showed that air defence systems had engaged 36 UAVs, four cruise missiles and eight ballistic missiles in the previous 24 hours. Cumulatively, authorities said 1,977 drones, 19 cruise missiles and 433 ballistic missiles have been intercepted since the onset of the war on 28 February.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16218126/main.jpg
    Indrajit Sen
  • Contractors submit Al-Maktoum airport superstructure bids

    1 April 2026

     

    Dubai Aviation Engineering Projects (DAEP) received proposals on 31 March from contractors for three packages covering superstructure works for the first phase of the expansion of Al-Maktoum International airport.

    MEED understands that the selected contractor will undertake superstructure works on three packages:

    • West Terminal and concourse one
    • Concourse two
    • Concourse three

    Construction on these packages began in November last year, when DAEP formally selected a contractor to deliver the substructure works.

    According to an official description on DAEP’s website, the expanded airport’s West Terminal will be a seven-level, 800,000-square-metre facility with an annual capacity of 45 million passengers.

    It will be the second of three terminals at Al-Maktoum International airport, linked to the airside by a 14-station automated people-mover (APM) system.

    In August last year, MEED exclusively reported that DAEP had received bids from firms to build the APM at the airport. 

    The system will run under the apron of the entire airfield and the airport’s terminals. It will consist of several tracks, taking passengers from the terminals to the concourses.

    Four underground stations will be built as part of the first phase. The overall plan includes 14 stations across the airport.

    The airport’s construction is planned to be undertaken in three phases. The airport will cover an area of 70 square kilometres (sq km) south of Dubai and will have five parallel runways, five terminal buildings and 400 aircraft gates.

    It will be five times the size of the existing Dubai International airport and will have the world’s largest passenger-handling capacity of 260 million passengers a year. For cargo, it will have the capacity to handle 12 million tonnes a year.

    Construction progress

    Construction on the first phase has already begun. In May last year, MEED exclusively reported that DAEP had awarded a AED1bn ($272m) deal to UAE firm Binladin Contracting Group to construct the second runway at the airport.

    The enabling works on the terminal are also ongoing and are being undertaken by Abu Dhabi-based Tristar E&C.

    Construction on the project’s first phase is expected to be completed by 2032.

    The government approved the updated designs and timelines for its largest construction project in April 2024.

    In a statement, the authorities said the plan is for all operations from Dubai International airport to be transferred to Al-Maktoum International within 10 years.

    The statement added that the project will create housing demand for 1 million people around the airport.

    In September 2024, MEED exclusively reported that a team comprising Austria’s Coop Himmelb(l)au and Lebanon’s Dar Al-Handasah had been confirmed as the lead masterplanning and design consultants on the expansion of Al-Maktoum airport.

    Project history

    The expansion of Al-Maktoum International, also known as Dubai World Central (DWC), is a long-standing project. It was officially launched in 2014, with a different design from the one approved in April 2024. At that time, it involved building the biggest airport in the world by 2050, with the capacity to handle 255 million passengers a year.

    An initial phase, due to be completed in 2030, involved increasing the airport’s capacity to 130 million passengers a year. The development was to cover an area of 56 sq km.

    Progress on the project slipped as the region grappled with the impact of lower oil prices and Dubai focused on developing the Expo 2020 site. Tendering for work on the project then stalled with the onset of the Covid-19 pandemic in early 2020.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16215664/main.jpg
    Yasir Iqbal
  • Drone strikes Kuwait International airport

    1 April 2026

    Register for MEED’s 14-day trial access 

    Kuwait International airport was hit by further drone attacks on Wednesday, with strikes on fuel tanks sparking a major fire.

    Kuwait’s state news agency Kuna said the attack caused significant damage to fuel tanks belonging to Kuwait Aviation Fuelling Company. No casualties were reported.

    This was the second reported incident at the airport in recent days. Local media reported that the airport was attacked on 28 March by multiple drones, causing significant damage to its radar system.

    The airport is currently undergoing expansion works that are expected to be completed by 2027, as MEED reported previously.

    Project execution of the second terminal began in 2017, with the completion date pushed back from the original 2022 target.

    The second terminal project consists of three packages.

    These are:

    • Package 1: Main works – $4,329m
    • Package 2: Multistorey car park building, connection roads, bridges and landscaping works – $550m
    • Package 3: Aircraft parking, runways and service buildings – $950m

    Turkiye’s Limak Holding is executing the main works.

    The terminal building was designed by Foster+Partners and Gulf Consult.

    Spanish firm Ineco is providing the project management services for the new terminal building and the airfield.

    The scope of the main package includes the new terminal building, a building for cooling and electricity supply facilities, and a building for the water supply and the future Automatic People Mover (APM) connection to the satellite building.

    The terminal building will be three times the size of the original building and will have 36 boarding gates.

    The building will cover more than 700,000 square metres and have five floors, one of which will be underground.

    It will have the capacity, at maximum service level, for 25 million passengers a year once the first phase has been completed and up to 50 million passengers after further phases are completed.

    The second package of works includes a new car park with approximately 5,000 parking spaces, connected to the new passenger terminal.

    It also includes all new access roads to the airport and landscaping.

    The scope of the third package comprises the main platform, new taxiways and several tunnels, including one under the platform between the terminal building and the future cargo area of the airport.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16216797/main.png
    Yasir Iqbal
  • Saudi Arabia’s Sadara halts chemical production

    1 April 2026

    Register for MEED’s 14-day trial access 

    Sadara Chemical Company (Sadara), the Saudi Aramco-Dow Chemical joint venture producing petrochemicals and specialty chemicals, has announced a temporary shutdown of production, citing ongoing supply chain disruptions.

    Sadara operates a sprawling chemical production complex in Jubail in Saudi Arabia’s Eastern Province, with a total output capacity of more than 3 million metric tonnes a year. Aramco and Dow established the Sadara petrochemicals complex – estimated to have cost $13bn – in 2016.

    The suspension was announced in a filing on the Saudi Exchange (Tadawul) by Sadara Basic ​Services, which issues sukuk, or Islamic bonds, ​for its parent. “The shutdown was successfully completed in accordance with Sadara’s high safety standards and in a manner that safeguards operations and reduces risk,” the entity said in its filing on 31 March

    “Sadara cannot provide, at the present ‌time, ⁠an estimate for the return to production, as this is contingent on domestic and international factors,” it said, ​adding ​the shutdown ⁠is expected to impact this year’s financial results.

    The month-long war between Israel, the US and Iran has spread across the Middle East, disrupting energy supplies and threatening the global economy, as Tehran has responded to US and Israeli attacks by targeting regional energy and industrial infrastructure, as well as shipping.

    ALSO READ: Sultan Al-Jaber calls Strait of Hormuz blockade “economic terrorism”

    Separately, Sadara, in another Tadawul filing on 31 March, announced a net loss of SR5,793bn ($1.54bn) for the full year 2025, a further decline of about 40% compared to 2024. The company’s revenue in 2025 fell by about 15% year-on-year to $2.63bn.

    The chemicals producer attributed the deepening of its losses in 2025 to a reduction in sales volumes, “which resulted from unplanned operational events and extended maintenance activities that temporarily impacted production availability”.

    Sadara also pinned its augmented losses to “margin compression, and higher fixed costs associated with unplanned operational events and extended maintenance activities.

    “In addition, the company experienced lower average selling prices across certain portfolio lines, which further contributed to the overall decrease in revenue,” Sadara said in the disclosure.

    In addition, “the net loss for 2025 increased compared to 2024, mainly due to an accounting adjustment related to a debt modification that had a favourable impact on the prior year’s results,” the company added.

    ALSO READ: Sabic registers $6.87bn net loss in 2025

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16215635/main2446.jpg
    Indrajit Sen