Chinese firm to take over Duro Felguera project in Algeria

22 April 2025

Spain's Duro Felguera and Algeria's Sonelgaz Production d'Electricite have signed a memorandum of understanding (MoU) for the amicable termination of a contract for the construction of the Djelfa power plant in Algeria, which they signed in 2014.

In a statement, the Spanish engineering, procurement and construction (EPC) contractor said the agreement includes assigning the contract "in favour of a group of companies" led by China Power Engineering Consulting Group (CPECC) and the final and amicable resolution of all disputes and litigation between Duro Felguera and Sonelgaz Production d'Electricite.

The Spanish firm said the "MoU has been signed by China Power Engineering & Consulting Group International Engineering Company, in its capacity as assignee of the contract, and by GE Energy Products France, in its capacity as manufacturer of the equipment".

The MoU ensures the completion of the construction of the Djelfa power plant through the assignment of the contract from Duro Felguera to the Chinese contracting firms, as well as the termination of all existing claims and litigation between Duro Felguera and Sonelgaz, with the withdrawal by the parties from the arbitrations in progress.

The Spanish company is understood to have stopped construction work on the gas-fired power plant, which has a planned installed capacity of 1,262MW, in June 2024.

The scope of the project includes engineering design, partial equipment procurement, installation and trial operation.

MEED understands that the project is part of the Algerian Electricity & Gas Company's strategy to enhance national power production.

Once completed, the project will meet the electricity needs of residents and enterprises in Algeria's Djelfa region and promote regional economic development.

It is not the first power plant project won by Duro Felguera in the region that has suffered delays and undergone arbitration proceedings.

Related read: K station highlights risks of part-finished schemes

The Spanish firm won the AED802m ($219m) EPC contract to build the expansion of the Jebel Ali K Station power plant in Dubai in 2017.

The project included the supply, installation, testing and launch of two F-type gas turbines from Siemens AG that would produce 590MW at 50 degrees centigrade. The turbines were planned to be operational by the second quarter of 2020, taking the capacity of K Station to 1,538MW.

However, it is understood that the contract with the Spanish contractor was terminated in 2020.

In its 2021 annual report, the Madrid-headquartered EPC contractor said that Dubai Electricity & Water Authority (Dewa) had submitted claims of AED975.8m ($266m) and it had issued counterclaims of AED603.8m. It said at the time that the arbitration process was going through the Dubai courts.

https://image.digitalinsightresearch.in/uploads/NewsArticle/13731125/main1407.gif
Jennifer Aguinaldo
Related Articles
  • Construction advances on Riyadh King Salman airport

    19 May 2026

    King Salman International Airport (KSIA) is advancing airside infrastructure works under its long-term expansion programme in Riyadh, including the delivery of a third runway and new private aviation facilities.

    Construction activity on the central runway programme is progressing across several operational zones, with works covering excavation, grading, site preparation and taxiway-enabling infrastructure to support upcoming phases.

    The third runway is intended to increase airfield capacity and cater to the airport’s future operational requirements.

    In a separate development, KSIA has completed initial landside works for the private aviation apron, marking a milestone in the rollout of its executive aviation infrastructure.

    The completed scope includes pavement markings, waterproofing systems, firefighting infrastructure chambers and final operational inspections to support readiness for the next stages.

    KSIA has also secured General Authority of Civil Aviation (GACA) approval for phase one airside works, which includes the planned connection of Taxiway Alpha to the private aviation facilities, strengthening operational integration between executive aviation assets and airfield movement areas.

    The packages form part of the wider KSIA masterplan, which covers about 57 square kilometres and supports Saudi Arabia’s objective of positioning Riyadh as a global aviation and logistics hub.

    The airport aims to accommodate up to 100 million passengers by 2030.

    Saudi Arabia plans to invest $100bn in its aviation sector. The Saudi Aviation Strategy, announced by GACA, aims to triple annual passenger traffic to 330 million travellers by 2030. It also targets air cargo growth to 4.5 million tonnes and an increase in total air connections to more than 250 destinations.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16906496/main.jpeg
    Yasir Iqbal
  • Aldar launches Al-Ghadeer Gardens project

    19 May 2026

    Abu Dhabi-based real estate developer Aldar Properties has launched the Al-Ghadeer Gardens project, located on the Abu Dhabi-Dubai border.

    The new residential development will feature 437 villas and townhouses, offering two-, three- and four-bedroom homes.

    Al-Ghadeer Gardens will include more than 30,000 square metres of landscaped open space, supporting a pedestrian-friendly layout and outdoor-focused living.

    As part of its sustainability and wellbeing approach, the project is targeting Estidama Pearl 2 and Fitwel 2-star certifications.

    Earlier this month, Aldar announced its Q1 financial results, reporting a 20% year-on-year increase in net profit after tax to AED2.3bn ($626m).

    Aldar Development recorded a 14% year-on-year rise in revenue to $1.7bn, while earnings before interest, taxes, depreciation and amortisation (Ebitda) increased 23% to $599m.

    UAE revenue backlog rose to $17bn at the end of March from $16.6bn at the end of December, with an average duration of 29 months.

    The group attributed its performance to revenue from its development backlog and steady income from its investment properties.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16906154/main.jpg
    Yasir Iqbal
  • Iraq trucks oil from the south to Kurdish pipeline

    19 May 2026

     

    Iraq is trucking crude from Basra to the north of the country to be exported via the Iraq-Turkiye Pipeline (ITP), according to industry sources.

    The oil is being loaded into trucks at fields in Basra before being driven to the north, where it is injected into the pipeline network at Khurmala Dome, in the northern section of the Kirkuk field.

    Once it has entered the network at Khurmala Dome, it is transported to the main ITP export pipeline and eventually to the port of Ceyhan in Turkiye, where it can be loaded onto ships.

    The volumes of crude being transported using trucks have surged in Iraq since the US and Israel attacked Iran on 28 February, starting a regional conflict that has disrupted shipping through the Strait of Hormuz.

    One source said: “Most of the crude that is being trucked out of Iraqi oil fields at the moment is going to Syria, but some is being trucked to the north where it is being funnelled through the pipeline.”

    Even with the additional volumes being trucked from the south, Iraq is struggling to boost exports using the ITP.

    At the end of March, Amer Khalil, the director-general of Iraq’s state-run North Oil Company, said that Iraq was exporting 200,000 barrels a day (b/d) through the ITP.

    At the time, he said that the pipeline, which runs from Kirkuk in Iraqi Kurdistan to the port of Ceyhan in Turkiye, was expected to start transporting 300,000 b/d “in the near future”.

    As of early May, the pipeline was still exporting about 200,000 b/d, despite having a nameplate capacity of 1.4 million b/d.

    One of the factors said to be stopping increased volumes from being shipped through the pipeline is that several key oil fields in northern Iraq evacuated staff and stopped production after the US and Israel started their war with Iran.

    Another factor is that Iraq has not invested in domestic pipeline infrastructure to pipe production from Basra to Kurdistan, where it could be exported via the Kurdish ITP route.


    READ THE MAY 2026 MEED BUSINESS REVIEW – click here to view PDF

    Global energy sector forced to recalibrate; Conflict hits debt issuance and listings activity; UAE’s non-oil sector faces unclear recovery period amid disruption.

    Distributed to senior decision-makers in the region and around the world, the May 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/16902345/main1824.jpg
    Wil Crisp
  • Kuwaiti oil services company secures credit facility

    19 May 2026

    The Kuwaiti drilling and oilfield services provider Action Energy Company (AEC) has secured a new credit facility and renewed and expanded an existing facility in order to support the company’s rig fleet expansion.

    The new facility and the expansion were obtained from two Kuwaiti banks and had a combined value of KD40.9m ($132.8m).

    In its statement, AEC said that the facilities support the financing and deployment of new rigs linked to contract awards previously announced with the state-owned upstream operator Kuwait Oil Company (KOC).

    The company added: “They further reinforce AEC’s financing structure and strengthen its ability to execute its contracted fleet expansion plan through 2026 and beyond, while maintaining a disciplined approach to capital allocation.”

    The new credit facility was obtained from Kuwait International Bank (KIB).

    It is worth KD7.3m ($23.7m) and will finance two new 750-horsepower (HP) rigs.

    The renewal and expansion of the existing facility is worth KD33.6m ($109.1m) and was obtained from Commercial Bank of Kuwait (CBK) to finance four new 1,500 HP rigs and one 1,000 HP rig, in addition to the renewal of the existing facilities.

    AEC announced its financial and operational performance for the first quarter earlier this month.

    The company reported a net profit of KD2.2m ($7.1m).

    The company’s revenue grew by 69.2% year-on-year, primarily driven by the expansion of the operating rig fleet from 13 rigs in the first quarter of 2025 to 20 rigs in the first quarter of 2026, including the full-quarter contribution of 10 new rigs deployed during 2025.

    The company is benefitting from a substantial multi-year contracted backlog with KOC.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16902234/main.jpg
    Wil Crisp
  • Emirates awards $5bn engineering complex deal

    18 May 2026

    Register for MEED’s 14-day trial access 

    Emirates Airline has awarded a AED19bn ($5bn) contract to build one of the world's largest engineering complexes in Dubai South.

    The contract was awarded to Beijing-headquartered China Railway Construction Corporation (CRCC).

    CRCC is being supported by French firm Artelia, as the project consultant.

    The complex will cover over 1 million square metres (sq m).

    It will comprise 77,000 sq m of dedicated workshop space for maintenance and repairs, 380,000 sq m of storage and logistics capacity, a 50,000 sq m administrative building for Emirates Engineering and 15,000 sq m of training facilities.

    It will be the world's only complex with a capacity to service 28 wide-body aircraft simultaneously.

    The airline officially broke ground on the project on 18 May. 

    The groundbreaking ceremony was attended by Sheikh Ahmed Bin Saeed Al-Maktoum, chairman and CEO of Emirates Group; Tim Clark, president of Emirates Airline; Khalifa Al-Zaffin, executive chairman of Dubai Aviation City Corporation and Dubai South; and Dai Hegen, chairman of CRCC.

    The facility will enable large-scale retrofits, cabin redesigns and structural modifications to be performed in-house, thereby reducing turnaround times.

    The engineering complex is scheduled for completion in 2030 and will be located at Al-Maktoum International airport.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16895218/main.jpg
    Yasir Iqbal