Capacity building spurs upstream spending

27 April 2023

 

The Middle East and North Africa (Mena) region, where a third of the world’s crude oil and about a quarter of its natural gas is produced, is increasing its hydrocarbons production potential.

There are an estimated $113.6bn-worth of upstream oil and gas projects in the engineering, procurement and construction (EPC) execution stage in the Mena region, according to data from regional projects tracker MEED Projects. 

Most of these schemes are set to be commissioned between this year and 2025, helping the region to consolidate its position as the largest producer of crude oil, natural gas and liquefied natural gas (LNG).

With the world still heavily reliant on hydrocarbons, and green energy sources falling short of meeting global energy needs, oil and gas producers in the region see more merit in investing in building upstream production potential.

Regional oil and gas industry leaders have been making the case for increasing spending on boosting hydrocarbons output capacity. Their purpose has been to draw the world’s attention to the role of fossil fuels as a bridge to achieving a clean energy transition, as well as to justify their major upstream capital expenditure (capex) programmes.

Saudi Arabia dominates

Saudi Aramco tops MEED’s ranking of state energy enterprises in the Mena region by the volume of upstream oil and gas projects under EPC execution, with nearly $41bn-worth of project value.

Aramco aims to increase its maximum oil output spare capacity to 13 million barrels a day (b/d) by 2027 from about 12 million b/d currently. It also plans to raise gas production by 50 per cent by the end of this decade. 

With a large portion of its under-execution projects expected to come online by the middle of this decade, the Saudi energy giant appears to be on track to meet its strategic output goals.

The largest Saudi Aramco project under execution is the $3bn-plus Berri increment programme, which was awarded to Italian contractor Saipem in July 2019. Through the project, Aramco plans to add 250,000 b/d of Arabian light crude from the offshore oil and gas field.

The planned facilities will include a new gas oil separation plant (GOSP) on Abu Ali Island to process 500,000 b/d of Arabian light crude and additional processing facilities at the Khursaniyah gas plant to process 40,000 b/d of associated hydrocarbons condensates.

The Berri increment programme will complement Saudi Aramco’s $15bn Marjan field development programme, EPC contracts for which were also awarded in July 2019. The scheme is an integrated project for oil, associated gas, non-associated gas and cap gas from the Marjan offshore oil and gas field.

The Marjan development plan includes provision of a new offshore GOSP and 24 offshore oil, gas and water injection platforms. The contract for the main GOSP, which is worth $3bn and is the first EPC package of the project, was awarded to McDermott International. The US contractor also won offshore package four, which involves the building of offshore gas facilities and is valued at about $1.5bn.

The offshore development project aims to increase the production of the Marjan field by 300,000 b/d of Arabian medium crude oil, process 2.5 billion cubic feet a day (cf/d) of gas and produce an additional 360,000 b/d of ethane and natural gas liquids.

Looking ahead, Aramco expects capital expenditure in 2023 to be $45bn-$55bn, including external investments. This projected spending is at least 20 per cent higher than the company’s $37.6bn capex in 2022.

Qatar’s LNG expansion

With the goal of consolidating its position as the world’s largest supplier of gas, QatarEnergy continues to progress with its North Field LNG expansion programme. The project, which is estimated to be worth about $30bn, will increase Qatar’s LNG production to 126 million tonnes a year (t/y) in two phases by 2027.

The two-stage North Field Production Sustainability (NFPS) programme will run in parallel, to help maintain gas production from the offshore reserve in order to match the feedstock requirements of the LNG expansion scheme.

QatarEnergy led spending on upstream projects in 2022 for the second year in a row, accounting for more than a third of the $18.9bn EPC contract awards in the Mena region. The firm’s overall value of EPC projects under execution stands at $27.3bn, putting it in second place in MEED’s ranking of the biggest national oil companies by volume of under-execution projects.

Launched in 2017, the North Field East (NFE) project constitutes the first phase of QatarEnergy’s North Field LNG expansion project. As well as an LNG output of 32 million t/y, NFE will produce 4,000 tonnes a day (t/d) of ethane as feedstock for future petrochemicals developments, 260,000 b/d of condensates, 11,000 t/d of liquefied petroleum gas (LPG) and 20 t/d of helium.

The EPC works on QatarEnergy’s NFE project were divided into six packages – four onshore and two offshore – and are currently progressing. 

QatarEnergy awarded a $13bn contract for NFE package one to a consortium of Chiyoda and TechnipEnergies in February 2021. The package covers the EPC of four LNG trains, each planned to have an output capacity of about 8 million t/y. 

QatarEnergy’s largest award in 2022 was a $4.5bn EPC contract that was won by Saipem for the building and installation of two gas compression facilities as part of the second development phase of its NFPS project. The gas compression complexes covered in the package known as EPCI 2 will weigh 62,000 tonnes and 63,000 tonnes and will be the largest fixed steel jacket compression platforms ever built.

Abu Dhabi ambitions

Abu Dhabi National Oil Company (Adnoc) adopted a five-year business plan in November last year that covers a capex budget of $150bn for 2023-27. The budget also sets the target of achieving its oil production capacity goal of 5 million b/d by 2027 rather than 2030.

The oil production increment projects that it has under execution are expected to play a key role in enabling the Abu Dhabi major to attain its accelerated oil capacity target.

The largest of Adnoc’s under execution projects is a $1.4bn EPC contract awarded to Spanish contractor Tecnicas Reunidas in late 2018 for upgrading the Bu Hasa onshore oil field development. Through this project, Adnoc plans to increase the Bu Hasa field’s production from 500,000 b/d to 650,000 b/d. 

On the gas production front – a core priority for Adnoc – $1.5bn-worth of EPC contracts were awarded to Abu Dhabi’s National Petroleum Construction Company (NPCC) and Tecnicas Reunidas in November 2021 for the offshore and onshore packages, respectively, of the Dalma sour gas field development project.

When completed in 2025, the project will enable the Dalma field to produce about 340 million cf/d of natural gas.

The Abu Dhabi energy giant further intends to raise its total gas output by 3 billion cf/d in the next few years. The Hail and Ghasha offshore sour gas production project will be central to achieving this goal.

In January, Adnoc signed pre-construction services agreements (PCSAs) with France-headquartered Technip Energies, South Korean contractor Samsung Engineering and Italy’s Tecnimont for the Hail and Ghasha onshore package. Saipem, NPCC and state-owned China Petroleum Engineering & Construction Company secured a PCSA for the offshore package.

While the onshore and offshore PCSAs awarded to the two consortiums by Adnoc are valued at $80m and $60m, respectively, the EPC packages are estimated to be worth $5.5bn and $5bn.

As part of the PCSAs, the contractors are required to perform initial detailed engineering and procurement for important long-lead items. 

Based on proposals to be submitted later this year, Adnoc is expected to award the same contractors the contracts for the main EPC works on the Hail and Ghasha project.

Production from the Ghasha concession, where the Dalma and Hail and Ghasha fields are located, is expected to start in 2025, ramping up to more than 1.5 billion cf/d before the end of this decade. 


Main image: Saudi Aramco tops the ranking of state energy enterprises in the Mena region with almost $41bn-worth of projects under execution. Credit: Aramco

https://image.digitalinsightresearch.in/uploads/NewsArticle/10791190/main.gif
Indrajit Sen
Related Articles
  • Contractors submit bids for next phase of Duba port

    2 June 2023

    Contractors have submitted bids for the next phase of the Duba port expansion at Oxagon industrial city.

    The bidders are Belgium’s Deme with Greece’s Archirodon; Van Oord of the Netherlands with South Korea’s Hyundai Engineering & Construction; a Belgian joint venture of Jan de Nul and Besix; Netherlands-based Boskalis with France’s Soletanche Bachy; South Korea’s Daewoo; and China Harbour Engineering Company.

    The tender for the project’s second phase follows the award of a contract to deliver the first phase of the port expansion. A team of Boskalis, Besix and the local Modern Building Leaders (MBL) was awarded that estimated SR3bn ($800m) contract in mid-January.

    The scope of the Duba port expansion package includes excavation and dredging, revetments for channel widening, demolition, container terminal quay expansion and earthworks, in addition to the development of a flexible quay, a roll-on/roll-off (RoRo) berth and quay walls to a marine services berth and a coast guard facility.

    Jacobs is the main design consultant, with Moffatt & Nichol, IGO and Trent as the main sub-consultants.

    Contractors are preparing to submit bids in June for a contract to build tunnels connecting the offshore elements of the Oxagon industrial city at Neom to the mainland.

    The design-and-build contract involves digging a 6.5-metre-diameter tunnel using a tunnel boring machine (TBM) under the sea that will link the Neom Connector with the offshore elements of Oxagon port. It will house utilities including water pipelines, fibre optic cables and electricity cables.

    Crown Prince Mohammed bin Salman launched Oxagon in late 2021. It will include onshore elements as well as floating structures offshore. Construction works on the 48 square-kilometre, eight-sided industrial city have already started.

    An expanded Duba port is a critical component of Oxagon and the broader Neom development, as it will allow greater volumes of materials to be imported for the project. With an expected investment value of $500bn, Neom is the largest programme of construction work in the world.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/10909320/main.jpeg
    Colin Foreman
  • Egypt makes steady progress on Assiut refinery

    2 June 2023

    Egypt is making steady progress on the $2bn hydrocracking complex package that forms part of the wider Assuit oil refinery upgrade project, according to industry sources.

    Assiut Oil Refining Company (ASORC), a subsidiary of state-owned Egyptian General Petroleum Corporation (EGPC), is the project operator.

    “Work on the main units is continuing with no significant issues,” said one source.

    During 2021, the project faced disruption due to issues related to the Covid-19 pandemic.

    In 2023, many projects in Egypt’s oil and gas sector have been disrupted by currency issues due to the declining value of the Egyptian pound.

    Most of the projects that the currency issues have significantly impacted have been in their early stages, with the problems related to the procurement of materials and equipment.

    France’s Technip Energies is the main contractor performing engineering, procurement and construction (EPC) works on the Assiut hydrocracking complex, as part of a $2bn contract it was awarded by ASORC in February 2020.

    In April 2021, Switzerland-based Burckhardt Compression announced being selected by Technip Energies as the gas compressor supplier for the hydrocracker package.

    ASORC held a kick-off meeting for the project in September 2020.

    Egyptian contractors Enppi and Petrojet are supporting Technip Energies on the project. Enppi has undertaken the engineering work, while Petrojet is carrying out construction work.

    In 2021, contractors completed the construction of a $450m high-octane gasoline complex in the Assiut governorate as part of the broader $3.8bn Assuit oil refinery upgrade project.

    Assiut refinery

    The Assiut hydrocracking complex will be one of Egypt’s major strategic refineries, and will help meet growing local demand for cleaner products.

    The project will also become the largest oil refining facility to be implemented in Upper Egypt so far.

    Once completed, the project will transform lower-value petroleum by-products, such as mazut, into cleaner, higher-value products.

    It is expected to have an output of about 2.8 million tonnes a year of Euro-5 diesel, in addition to other petroleum products.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/10908534/main3340.jpg
    Wil Crisp
  • Mawani implements $950m of Saudi port projects

    2 June 2023

    Saudi Ports Authority (Mawani) is implementing a series of projects over the coming 18 months as part of its efforts to improve and expand infrastructure at ports and increase their utilisation rates.

    The programme, worth about SR3.5bn ($950m), comprises just over 150 projects, of which 48 are strategic in nature, 90 infrastructure-focused and 14 targeting security enhancements.

    The most significant projects are:

    At Jeddah Islamic Port

    • A four-year contract to build a new road, interchanges and flyovers to link Gate 9 with the Al-Khumrah integrated logistics park.
    • Deepening over three years of the north basin approach channel to 14 metres and the construction of a bull nose dike

    At Ras al-Khair Port

    • Increasing the draft depth of berths 11 and 12 to 16 metres
    • A three-year job to widen and dredge the approach channel from 300 metres to 500 metres and deepen it by 3 metres to 19 metres

    Other key investments include installing integrated security systems at Jeddah Islamic Port and King Abdulaziz Port in Dammam and constructing a new 40MVA substation at King Fahd Port in Yanbu.

    The contracts are expected to be tendered and awarded by the end of 2024.

    Mawani’s planned investment comes on the back of several major contracts awarded over the past 12 months, including an agreement with DP World to set up the Al-Khumrah logistics park, the reconstruction and expansion of the first and second container terminals at King Abdulaziz Port, and the upgrade of berth infrastructure and draft depths at Jeddah Islamic Port and King Fahd Port.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/10909176/main.jpg
    Edward James
  • Dubai unveils new masterplan for Palm Jebel Ali

    1 June 2023

    Dubai has released details of the new masterplan for Palm Jebel Ali, an artificial island located south of Jebel Ali Freezone.

    Double the size of Palm Jumeirah, Palm Jebel Ali will have 110 kilometres of shoreline and extensive green spaces. The development will feature over 80 hotels and resorts, along with a diverse range of entertainment and leisure facilities.

    Strategic masterplan

    The unveiling of the masterplan aligns with Dubai's commitment to doubling the size of its economy by 2033, as outlined in the Dubai Economic Agenda.

    The project, approved by Sheikh Mohammed bin Rashid al-Maktoum, Vice President and Prime Minister of the UAE and Ruler of Dubai, includes seven connected islands, catering to approximately 35,000 families. The development also emphasises sustainability, with 30 per cent of public facilities powered by renewable energy.

     

    MEED reported in January that local developer Nakheel had approached contractors to complete the reclamation works for Palm Jebel Ali.

    As with Palm Jumeirah, it is estimated that it could take around 20 years for Palm Jebel Ali to reach its full development potential. Nakheel has previously secured AED17bn ($4.6bn) in funding to expedite the development of various projects, including the Dubai Islands and other waterfront schemes.

    The upcoming dredging contract for Palm Jebel Ali is anticipated to involve 5-6 million cubic metres of material, contributing to the completion of the man-made offshore island.

    While reclamation work for Palm Jebel Ali is mostly finished, the project was put on hold in 2009. Nakheel had made some progress with infrastructure development, including the construction of bridges on the island by Samsung C+T.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/10906519/main.jpg
    Colin Foreman
  • Swedish firm to deliver apartments for Neom

    1 June 2023

    Swedish modular home manufacturer SIBS has been awarded a contract to deliver 2,174 apartments for Neom.

    The engineered equipment supply contract involves SIBS constructing 35 buildings within Neom’s primary staff accommodation and office cluster.

    The apartments will cater to professionals involved in the planning, engineering and construction of Neom. The entire project is expected to be delivered and commissioned by the third quarter of 2024.

    The $500bn Neom development in northwestern Saudi Arabia is the region’s largest construction project and employs thousands of staff.

    Elements of the project that have been officially launched so far are The Line, Oxagon, Trojena and Sindalah. There are also plans for an international airport and a coastal strip of hotels known as the Gulf of Aqaba.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/10905700/main.gif
    Colin Foreman