Capacity building spurs upstream spending

27 April 2023

 

The Middle East and North Africa (Mena) region, where a third of the world’s crude oil and about a quarter of its natural gas is produced, is increasing its hydrocarbons production potential.

There are an estimated $113.6bn-worth of upstream oil and gas projects in the engineering, procurement and construction (EPC) execution stage in the Mena region, according to data from regional projects tracker MEED Projects. 

Most of these schemes are set to be commissioned between this year and 2025, helping the region to consolidate its position as the largest producer of crude oil, natural gas and liquefied natural gas (LNG).

With the world still heavily reliant on hydrocarbons, and green energy sources falling short of meeting global energy needs, oil and gas producers in the region see more merit in investing in building upstream production potential.

Regional oil and gas industry leaders have been making the case for increasing spending on boosting hydrocarbons output capacity. Their purpose has been to draw the world’s attention to the role of fossil fuels as a bridge to achieving a clean energy transition, as well as to justify their major upstream capital expenditure (capex) programmes.

Saudi Arabia dominates

Saudi Aramco tops MEED’s ranking of state energy enterprises in the Mena region by the volume of upstream oil and gas projects under EPC execution, with nearly $41bn-worth of project value.

Aramco aims to increase its maximum oil output spare capacity to 13 million barrels a day (b/d) by 2027 from about 12 million b/d currently. It also plans to raise gas production by 50 per cent by the end of this decade. 

With a large portion of its under-execution projects expected to come online by the middle of this decade, the Saudi energy giant appears to be on track to meet its strategic output goals.

The largest Saudi Aramco project under execution is the $3bn-plus Berri increment programme, which was awarded to Italian contractor Saipem in July 2019. Through the project, Aramco plans to add 250,000 b/d of Arabian light crude from the offshore oil and gas field.

The planned facilities will include a new gas oil separation plant (GOSP) on Abu Ali Island to process 500,000 b/d of Arabian light crude and additional processing facilities at the Khursaniyah gas plant to process 40,000 b/d of associated hydrocarbons condensates.

The Berri increment programme will complement Saudi Aramco’s $15bn Marjan field development programme, EPC contracts for which were also awarded in July 2019. The scheme is an integrated project for oil, associated gas, non-associated gas and cap gas from the Marjan offshore oil and gas field.

The Marjan development plan includes provision of a new offshore GOSP and 24 offshore oil, gas and water injection platforms. The contract for the main GOSP, which is worth $3bn and is the first EPC package of the project, was awarded to McDermott International. The US contractor also won offshore package four, which involves the building of offshore gas facilities and is valued at about $1.5bn.

The offshore development project aims to increase the production of the Marjan field by 300,000 b/d of Arabian medium crude oil, process 2.5 billion cubic feet a day (cf/d) of gas and produce an additional 360,000 b/d of ethane and natural gas liquids.

Looking ahead, Aramco expects capital expenditure in 2023 to be $45bn-$55bn, including external investments. This projected spending is at least 20 per cent higher than the company’s $37.6bn capex in 2022.

Qatar’s LNG expansion

With the goal of consolidating its position as the world’s largest supplier of gas, QatarEnergy continues to progress with its North Field LNG expansion programme. The project, which is estimated to be worth about $30bn, will increase Qatar’s LNG production to 126 million tonnes a year (t/y) in two phases by 2027.

The two-stage North Field Production Sustainability (NFPS) programme will run in parallel, to help maintain gas production from the offshore reserve in order to match the feedstock requirements of the LNG expansion scheme.

QatarEnergy led spending on upstream projects in 2022 for the second year in a row, accounting for more than a third of the $18.9bn EPC contract awards in the Mena region. The firm’s overall value of EPC projects under execution stands at $27.3bn, putting it in second place in MEED’s ranking of the biggest national oil companies by volume of under-execution projects.

Launched in 2017, the North Field East (NFE) project constitutes the first phase of QatarEnergy’s North Field LNG expansion project. As well as an LNG output of 32 million t/y, NFE will produce 4,000 tonnes a day (t/d) of ethane as feedstock for future petrochemicals developments, 260,000 b/d of condensates, 11,000 t/d of liquefied petroleum gas (LPG) and 20 t/d of helium.

The EPC works on QatarEnergy’s NFE project were divided into six packages – four onshore and two offshore – and are currently progressing. 

QatarEnergy awarded a $13bn contract for NFE package one to a consortium of Chiyoda and TechnipEnergies in February 2021. The package covers the EPC of four LNG trains, each planned to have an output capacity of about 8 million t/y. 

QatarEnergy’s largest award in 2022 was a $4.5bn EPC contract that was won by Saipem for the building and installation of two gas compression facilities as part of the second development phase of its NFPS project. The gas compression complexes covered in the package known as EPCI 2 will weigh 62,000 tonnes and 63,000 tonnes and will be the largest fixed steel jacket compression platforms ever built.

Abu Dhabi ambitions

Abu Dhabi National Oil Company (Adnoc) adopted a five-year business plan in November last year that covers a capex budget of $150bn for 2023-27. The budget also sets the target of achieving its oil production capacity goal of 5 million b/d by 2027 rather than 2030.

The oil production increment projects that it has under execution are expected to play a key role in enabling the Abu Dhabi major to attain its accelerated oil capacity target.

The largest of Adnoc’s under execution projects is a $1.4bn EPC contract awarded to Spanish contractor Tecnicas Reunidas in late 2018 for upgrading the Bu Hasa onshore oil field development. Through this project, Adnoc plans to increase the Bu Hasa field’s production from 500,000 b/d to 650,000 b/d. 

On the gas production front – a core priority for Adnoc – $1.5bn-worth of EPC contracts were awarded to Abu Dhabi’s National Petroleum Construction Company (NPCC) and Tecnicas Reunidas in November 2021 for the offshore and onshore packages, respectively, of the Dalma sour gas field development project.

When completed in 2025, the project will enable the Dalma field to produce about 340 million cf/d of natural gas.

The Abu Dhabi energy giant further intends to raise its total gas output by 3 billion cf/d in the next few years. The Hail and Ghasha offshore sour gas production project will be central to achieving this goal.

In January, Adnoc signed pre-construction services agreements (PCSAs) with France-headquartered Technip Energies, South Korean contractor Samsung Engineering and Italy’s Tecnimont for the Hail and Ghasha onshore package. Saipem, NPCC and state-owned China Petroleum Engineering & Construction Company secured a PCSA for the offshore package.

While the onshore and offshore PCSAs awarded to the two consortiums by Adnoc are valued at $80m and $60m, respectively, the EPC packages are estimated to be worth $5.5bn and $5bn.

As part of the PCSAs, the contractors are required to perform initial detailed engineering and procurement for important long-lead items. 

Based on proposals to be submitted later this year, Adnoc is expected to award the same contractors the contracts for the main EPC works on the Hail and Ghasha project.

Production from the Ghasha concession, where the Dalma and Hail and Ghasha fields are located, is expected to start in 2025, ramping up to more than 1.5 billion cf/d before the end of this decade. 


Main image: Saudi Aramco tops the ranking of state energy enterprises in the Mena region with almost $41bn-worth of projects under execution. Credit: Aramco

https://image.digitalinsightresearch.in/uploads/NewsArticle/10791190/main.gif
Indrajit Sen
Related Articles
  • Firms announce 129MW Dubai data centre

    24 April 2026

    Dubai’s Integrated Economic Zones Authority (DIEZ) has signed a joint-venture agreement with Netherlands-headquartered data centre developer Volt to build a new artificial intelligence (AI)-ready data centre in the emirate.

    Planned for Dubai Silicon Oasis, the development will take the form of a campus covering up to 60,000 square metres.

    The project will be delivered in two phases, starting with 29MW of immediately available capacity, followed by a second phase adding a further 100MW of committed power.

    Under the arrangement, DIEZ will supply the land and essential infrastructure, while Volt will finance and develop the project, lead construction, and manage the design, leasing, implementation and day-to-day operations.

    French firm Schneider Electric, which has its regional headquarters in Dubai Silicon Oasis, will support the development by supplying advanced electrical systems, power distribution capabilities and smart data centre infrastructure.

    The GCC currently has more than 174 active data centre projects, representing over $93bn in investment, led by international players such as AWS, Google and Huawei, alongside regional developers including Khazna and Moro, supported by government-led localisation strategies.

    More than a dozen large-scale facilities valued at over $100m each are currently under tender, with further packages expected to reach the market over the next six to 12 months.

    The UAE is one of the leading data centre markets, with hyperscale campuses, sovereign cloud initiatives and edge data centre deployments underway.

    Data centre development is closely aligned with the UAE’s digital economy and AI roadmap, as well as the wider smart city programme.

    Priorities include hyperscale and colocation facilities to support cloud service providers; edge data centres to reduce latency and enable 5G and IoT use cases; energy-efficient designs using advanced cooling, modular construction and renewables; and strategic partnerships between global hyperscalers, local developers and utilities.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16548972/main.JPG
    Yasir Iqbal
  • Iraq signs upstream oil contract

    24 April 2026

    State-owned Iraqi Drilling Company (IDC) has signed a contract with China’s EBS Petroleum for a project to drill 17 horizontal wells in the southeastern portion of the East Baghdad field.

    Mohamed Hantoush, the general manager of IDC, said the contract signing came after a “series of successful achievements” by the company at the field.

    The achievements included the completion of a project to drill 27 horizontal wells and another project to drill 18 horizontal wells, according to a statement released by Iraq’s Ministry of Oil.

    In January, Iraq’s Midland Oil Company (MOC), in collaboration with EBS Petroleum, completed the country’s longest horizontal oil well in the southern part of the East Baghdad field.

    The well, which was called EBMK-8-1H, reached a total depth of 6,320 metres, and had a 3,535-metre horizontal section, making it the country’s largest horizontal well ever drilled.

    Senior officials from the Iraqi Oil Ministry and representatives of EBS Petroleum attended the well’s completion ceremony.

    EBS Petroleum is a subsidiary of China’s ZhenHua Oil, which is focused on Iraq.

    ZhenHua Oil is the operator of the field and is working with Iraqi partners to oversee the field’s development.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16543675/main4942.jpg
    Wil Crisp
  • Jordan tenders oil and gas terminal project

    24 April 2026

     

    Jordan’s Aqaba Development Corporation (ADC) has tendered a project for the development of the facilities at the Aqaba Oil and Gas Terminal.

    The project has been divided into two packages, and a bid deadline has been set for 15 June 2026.

    The oil and gas terminal is located south of the city of Aqaba in Jordan’s Southern Industrial Zone.

    The scope of Package 1 includes:

    • Rehabilitation of petroleum product pipelines of various sizes and their accessories (such as supports, structures and valves), including rectification of painting defects
    • Inspection and repair of pipe welds
    • Rectification and overall maintenance of the product booster pump
    • Inspection, maintenance, testing and commissioning of liquefied petroleum gas (LPG) booster pumps
    • Rectification of two overhead cranes
    • Rectification and calibration of instrumentation, including pressure indicators and valves

    The scope of Package 2 includes:

    • Rehabilitation of control rooms and security rooms, replacing them with concrete control rooms, including infrastructure works and all required services
    • Removal of unused tanks and equipment previously used for exporting crude oil
    • Rehabilitation of the existing gate in order to improve safety and security with the installation of a tire killer
    • Carrying out maintenance and repairs for the oil berth dolphins and trestle with inspection
    • Maintenance, repair and reinstallation of oil berth concrete slabs
    • Removal and extension of the jetty platform
    • Installation of a lighting system at pipelines beside booster pumps
    • Installation of stripping pumps at the LPG terminal
    • Replacement of drain line path for slop tank of LPG booster pumps
    • Rehabilitation of the existing closed drain drum
    • Rectification of cone sealing issue of all truck loading arms
    • Conversion of manual valves to motor-operated valves
    • Remote operation of shut-off valves on the main pipeline alongside and near the entrance gate
    • Upgrading of the firefighting system

    The last date for questions and clarifications related to the project will be 13 May 2026.

    The Aquaba Oil and Gas Terminal was built to meet demand for petroleum products and LPG imports into Jordan.

    It is operated by state-owned Jordan Oil Terminals Company (JOTC), which was established in 2015 as a private shareholding company.

    Earlier this year, Abu Dhabi’s AD Ports Group signed an agreement with ADC to manage and operate the Aqaba multipurpose port.

    AD Ports is managing and operating the port under a 30-year concession agreement.

    Under the agreement, AD Ports and ADC will establish a joint venture to oversee port operations.

    AD Ports will hold a 70% stake in the joint venture, with the remaining 30% held by ADC.

    AD Ports Group will also invest AED141m ($38.4m) in the joint venture.

    The signing ceremony was held at the Aqaba Special Economic Zone Authority headquarters in Aqaba on 5 February.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16543632/main.jpg
    Wil Crisp
  • Decision imminent on Dubai sewerage tunnel contracts

    24 April 2026

     

    A final decision on the first two packages of the flagship Dubai Strategic Sewerage Tunnels (DSST) project is imminent, with two remaining bidders having submitted best and final offers. 

    The AED80bn ($22bn) public-private partnership (PPP) scheme comprises three packages: J, W and Links.

    According to a source, two consortiums led by Etihad Water & Electricity (UAE) and Vision Invest (Saudi Arabia) were recently invited to submit final bids for packages J and W, which were tendered last November.

    The winning consortium is expected to be formally confirmed in the coming weeks once the required approval process is completed, the source said.

    MEED had previously reported that three consortiums were bidding for the project, which is being procured by Dubai Municipality’s sewerage and recycled water projects department.

    These included:

    • Consortium 1: Led by Plenary Group (Australia) alongside Itochu (Japan) and Infrastructure Holding (UAE) 
    • Consortium 2: Led by Vision Invest (Saudi Arabia) alongside Suez Water Company (France)
    • Consortium 3: Led by Etihad Water & Electricity (UAE) alongside Tamasuk Holding (Saudi Arabia) and Alkhorayef Water & Power (Saudi Arabia)

    It is understood that the consortium led by Pleneray Group has since been dropped from consideration for the contract.

    As MEED previously reported, the bid packages include equity partners, an appointed operator and a construction contractor.

    Of the bidders still in contention, MEED understands that Vision Invest plans to act as operator for that consortium, while Suez will lead construction.

    In the other consortium, EtihadWE plans to take the operator role, with construction led by France’s Veolia.

    Large-scale sewerage network

    The DSST masterplan project covers the construction of two sets of deep tunnels terminating at pump stations at Warsan and Jebel Ali Sewage Treatment Plants (STPs). It also includes over 200 kilometres of sewer links.

    Construction work was previously categorised in multiple packages under the Warsan Strategic Tunnel Scheme (Package W) and the Jebel Ali Strategic Sewerage Scheme (J1 North, J2 South, J3 Jebel Ali Links).

    These packages have now been restructured and renamed.

    The bid submission deadline for the third 'Phase 2 Links' package, meanwhile, was recently extended.

    The new deadline is June 30. 

    The three packages are being procured under 30-year design, build, finance, operate and maintain concession models.

    The DSST project aims to convert Dubai’s sewerage system from a pumped network to a gravity-based system, enabling the emirate to replace existing sewage pumping stations and meet long-term capacity needs.

    The programme also marks the first time the municipality will implement In-Country Value (ICV), a local content programme that promotes economic benefits.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16536060/main.jpg
    Mark Dowdall
  • Dubai scales up its metro ambitions

    23 April 2026

     

    Dubai’s rail sector has rarely seen such a concentrated burst of procurement activity as it has in the past year.

    Within the space of a few months, Dubai’s Roads & Transport Authority (RTA) has moved simultaneously on three distinct fronts: tendering design consultancy for the Route 2020 extension that will connect the Expo 2020 metro station to Al-Maktoum International airport; inviting study-and-design bids for a 55-kilometre Airport Express Line linking Dubai International airport to Al-Maktoum International airport; and culminating in Dubai Ruler Sheikh Mohammed Bin Rashid Al-Maktoum’s approval of the AED34bn ($9.2bn) Gold Line, a 42km fully underground route that the emirate is calling the largest transportation project in its history.

    These projects form a key part of the Dubai Rail Network Plan 2032, which outlines the development of six public transportation schemes comprising a mix of metro, passenger and high-speed rail lines.

    The most prominent feature of the plan is the addition of new lines to Dubai Metro’s existing network, representing a systematic effort to support the shift of Dubai’s economic centre of gravity towards Dubai South and the vast development corridors in between.

    The city is also seeking to stay ahead of the curve by investing heavily in infrastructure. Data from regional projects tracker MEED Projects shows that the emirate has awarded over $14bn-worth of transport projects in the past two years alone, with several other multibillion-dollar schemes still moving through the planning stages.

    All of this work is being carried out in line with the Dubai 2040 Urban Master Plan, which forecasts the emirate’s population will reach 5.8 million by 2040 – a clear indication of the scale of daily movement the city must accommodate.

    Project progress

    Dubai Metro Gold Line

    On 21 April, Sheikh Mohammed officially announced the launch of the new AED34bn ($9.2bn) Gold Line project.

    The line will be a fully underground network spanning over 42 kilometres, with 18 stations.

    It will run from Al-Ghubaiba in Bur Dubai to Jumeirah Golf Estates.

    The Gold Line will connect with Dubai Metro’s existing Red and Green lines and integrate with the Etihad Rail passenger network.

    In October last year, MEED exclusively reported that the RTA had selected US-based engineering firm Aecom to provide consultancy services for the project.

    Stage one covers concept design; stage two, preliminary design; stage three, preparation of tender documents; stage four, construction supervision; and stage five, the defects liability period.

    Airport Express Line

    Procurement has started for another metro line extending from Dubai International airport (DXB) in Al-Garhoud to Al-Maktoum International airport (DWC) in Jebel Ali.

    Earlier this month, the RTA invited consultants to bid for a contract to study and design what is referred to as the Airport Express Line.

    The proposed line will stretch about 55km and include five stations that will provide passengers with facilities such as remote airline check-in, baggage drop-off and security screening.

    The new line will run from the Red Line metro station at DXB through Al-Jaddaf, along Al-Khail Road to a new station at Jumeirah Village Circle (JVC), before continuing on to DWC.

    There will be two spur lines. The first will run from the new JVC station to Al-Fardan Exchange metro station at Emirates Golf Club, while the second will branch toward Business Bay, where another station will be built.

    Expo 2020 route extension

    Dubai is also undertaking the Route 2020 extension of its metro system, which will start from the Expo 2020 metro station and connect with Al-Maktoum International airport’s West Terminal.

    Consultants submitted their bids earlier this month for the design contract.

    The extension will run for about 3km and feature two stations.

    The existing Route 2020 metro link is a 15km line that branches off the Red Line at Jebel Ali metro station. The line comprises 11.8km of elevated tracks and 3.2km of tunnels, and has five elevated stations and two underground stations.

    Dubai Metro Blue Line extension

    Construction progress on the Dubai Metro Blue Line extension is expected to reach 30% by the end of 2026, according to official accounts.

    In December 2024, the RTA awarded a AED20.5bn ($5.5bn) main contract for the construction of the project.

    The contract was awarded to a consortium of Turkiye’s Limak Holding, Mapa Group, also of Turkiye, and the Hong Kong office of China Railway Rolling Stock Corporation (CRRC).

    The Blue Line will connect the existing Red and Green lines. It will be 30km long, with 15.5km underground and 14.5km above ground.

    The line will have 14 stations, seven of which will be elevated. There will be five underground stations, including one interchange station, and two elevated transfer stations connected to the existing Centrepoint and Creek stations.

    The project is scheduled for completion in September 2029.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16534887/main.png
    Yasir Iqbal