Capacity building spurs upstream spending
27 April 2023

The Middle East and North Africa (Mena) region, where a third of the world’s crude oil and about a quarter of its natural gas is produced, is increasing its hydrocarbons production potential.
There are an estimated $113.6bn-worth of upstream oil and gas projects in the engineering, procurement and construction (EPC) execution stage in the Mena region, according to data from regional projects tracker MEED Projects.
Most of these schemes are set to be commissioned between this year and 2025, helping the region to consolidate its position as the largest producer of crude oil, natural gas and liquefied natural gas (LNG).
With the world still heavily reliant on hydrocarbons, and green energy sources falling short of meeting global energy needs, oil and gas producers in the region see more merit in investing in building upstream production potential.
Regional oil and gas industry leaders have been making the case for increasing spending on boosting hydrocarbons output capacity. Their purpose has been to draw the world’s attention to the role of fossil fuels as a bridge to achieving a clean energy transition, as well as to justify their major upstream capital expenditure (capex) programmes.
Saudi Arabia dominates
Saudi Aramco tops MEED’s ranking of state energy enterprises in the Mena region by the volume of upstream oil and gas projects under EPC execution, with nearly $41bn-worth of project value.
Aramco aims to increase its maximum oil output spare capacity to 13 million barrels a day (b/d) by 2027 from about 12 million b/d currently. It also plans to raise gas production by 50 per cent by the end of this decade.
With a large portion of its under-execution projects expected to come online by the middle of this decade, the Saudi energy giant appears to be on track to meet its strategic output goals.
The largest Saudi Aramco project under execution is the $3bn-plus Berri increment programme, which was awarded to Italian contractor Saipem in July 2019. Through the project, Aramco plans to add 250,000 b/d of Arabian light crude from the offshore oil and gas field.
The planned facilities will include a new gas oil separation plant (GOSP) on Abu Ali Island to process 500,000 b/d of Arabian light crude and additional processing facilities at the Khursaniyah gas plant to process 40,000 b/d of associated hydrocarbons condensates.
The Berri increment programme will complement Saudi Aramco’s $15bn Marjan field development programme, EPC contracts for which were also awarded in July 2019. The scheme is an integrated project for oil, associated gas, non-associated gas and cap gas from the Marjan offshore oil and gas field.
The Marjan development plan includes provision of a new offshore GOSP and 24 offshore oil, gas and water injection platforms. The contract for the main GOSP, which is worth $3bn and is the first EPC package of the project, was awarded to McDermott International. The US contractor also won offshore package four, which involves the building of offshore gas facilities and is valued at about $1.5bn.
The offshore development project aims to increase the production of the Marjan field by 300,000 b/d of Arabian medium crude oil, process 2.5 billion cubic feet a day (cf/d) of gas and produce an additional 360,000 b/d of ethane and natural gas liquids.
Looking ahead, Aramco expects capital expenditure in 2023 to be $45bn-$55bn, including external investments. This projected spending is at least 20 per cent higher than the company’s $37.6bn capex in 2022.
Qatar’s LNG expansion
With the goal of consolidating its position as the world’s largest supplier of gas, QatarEnergy continues to progress with its North Field LNG expansion programme. The project, which is estimated to be worth about $30bn, will increase Qatar’s LNG production to 126 million tonnes a year (t/y) in two phases by 2027.
The two-stage North Field Production Sustainability (NFPS) programme will run in parallel, to help maintain gas production from the offshore reserve in order to match the feedstock requirements of the LNG expansion scheme.
QatarEnergy led spending on upstream projects in 2022 for the second year in a row, accounting for more than a third of the $18.9bn EPC contract awards in the Mena region. The firm’s overall value of EPC projects under execution stands at $27.3bn, putting it in second place in MEED’s ranking of the biggest national oil companies by volume of under-execution projects.
Launched in 2017, the North Field East (NFE) project constitutes the first phase of QatarEnergy’s North Field LNG expansion project. As well as an LNG output of 32 million t/y, NFE will produce 4,000 tonnes a day (t/d) of ethane as feedstock for future petrochemicals developments, 260,000 b/d of condensates, 11,000 t/d of liquefied petroleum gas (LPG) and 20 t/d of helium.
The EPC works on QatarEnergy’s NFE project were divided into six packages – four onshore and two offshore – and are currently progressing.
QatarEnergy awarded a $13bn contract for NFE package one to a consortium of Chiyoda and TechnipEnergies in February 2021. The package covers the EPC of four LNG trains, each planned to have an output capacity of about 8 million t/y.
QatarEnergy’s largest award in 2022 was a $4.5bn EPC contract that was won by Saipem for the building and installation of two gas compression facilities as part of the second development phase of its NFPS project. The gas compression complexes covered in the package known as EPCI 2 will weigh 62,000 tonnes and 63,000 tonnes and will be the largest fixed steel jacket compression platforms ever built.
Abu Dhabi ambitions
Abu Dhabi National Oil Company (Adnoc) adopted a five-year business plan in November last year that covers a capex budget of $150bn for 2023-27. The budget also sets the target of achieving its oil production capacity goal of 5 million b/d by 2027 rather than 2030.
The oil production increment projects that it has under execution are expected to play a key role in enabling the Abu Dhabi major to attain its accelerated oil capacity target.
The largest of Adnoc’s under execution projects is a $1.4bn EPC contract awarded to Spanish contractor Tecnicas Reunidas in late 2018 for upgrading the Bu Hasa onshore oil field development. Through this project, Adnoc plans to increase the Bu Hasa field’s production from 500,000 b/d to 650,000 b/d.
On the gas production front – a core priority for Adnoc – $1.5bn-worth of EPC contracts were awarded to Abu Dhabi’s National Petroleum Construction Company (NPCC) and Tecnicas Reunidas in November 2021 for the offshore and onshore packages, respectively, of the Dalma sour gas field development project.
When completed in 2025, the project will enable the Dalma field to produce about 340 million cf/d of natural gas.
The Abu Dhabi energy giant further intends to raise its total gas output by 3 billion cf/d in the next few years. The Hail and Ghasha offshore sour gas production project will be central to achieving this goal.
In January, Adnoc signed pre-construction services agreements (PCSAs) with France-headquartered Technip Energies, South Korean contractor Samsung Engineering and Italy’s Tecnimont for the Hail and Ghasha onshore package. Saipem, NPCC and state-owned China Petroleum Engineering & Construction Company secured a PCSA for the offshore package.
While the onshore and offshore PCSAs awarded to the two consortiums by Adnoc are valued at $80m and $60m, respectively, the EPC packages are estimated to be worth $5.5bn and $5bn.
As part of the PCSAs, the contractors are required to perform initial detailed engineering and procurement for important long-lead items.
Based on proposals to be submitted later this year, Adnoc is expected to award the same contractors the contracts for the main EPC works on the Hail and Ghasha project.
Production from the Ghasha concession, where the Dalma and Hail and Ghasha fields are located, is expected to start in 2025, ramping up to more than 1.5 billion cf/d before the end of this decade.
Main image: Saudi Aramco tops the ranking of state energy enterprises in the Mena region with almost $41bn-worth of projects under execution. Credit: Aramco
Exclusive from Meed
-
Oil prices rise above $100 a barrel as conflict escalates9 September 2026
-
What actually slows a gigaproject down9 September 2026
-
Qatari firm wins $221m Qiddiya stadium MEP deal9 September 2026
-
Jordan tenders advisory for wastewater treatment plant9 September 2026
-
Consultants bid for Abu Dhabi light rail project management9 September 2026
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Oil prices rise above $100 a barrel as conflict escalates9 September 2026
Register for MEED’s 14-day trial access
Oil prices rose above $100 a barrel on 9 September for the first time since July as the US-Iran conflict escalated and Iran-backed Houthi forces attacked Saudi energy infrastructure.
Brent crude futures reached $100.95 a barrel, while US benchmark West Texas Intermediate (WTI) rose to $95.60. Brent had last traded above $100 on 24 July.
The latest escalation has heightened concerns about oil supplies from the region, with shipping through both the Strait of Hormuz and the Red Sea facing disruption.
Flows through the Strait of Hormuz had fallen below 2 million barrels a day (b/d) from about 8-9 million b/d before the latest escalation, according to Rystad Energy.
At the same time, Houthi attacks on Saudi Arabia threaten another important route for oil exports, with the group targeting energy infrastructure and shipping in and around the Red Sea.
US strikes on Iranian tankers
US forces destroyed five Iranian crude oil carriers on 8 September after Iran’s Islamic Revolutionary Guard Corps (IRGC) targeted a US Navy warship with ballistic missiles.
The US Central Command (Centcom) said the warship successfully evaded two Iranian attacks and that no US personnel were harmed.
Four of the Iranian vessels – Kaviz, Charminar, Horizon 1 and Riesco – were struck in the Gulf of Oman, while the Derya was attacked near Kharg Island, Iran’s main crude export hub.
The M/T Riesco subsequently sank in the Gulf of Oman, according to Centcom.
Iran responded by launching ballistic missiles towards Jordan. Jordan’s armed forces said 18 of 20 missiles were intercepted, with the remaining two falling in unpopulated areas.
Iran’s IRGC also said it had attacked two US naval vessels, eight oil tankers and 10 other vessels in the Gulf, although it did not identify the vessels or provide evidence of the attacks.
The latest exchanges mark a further escalation in the US-Iran conflict, which began on 28 February.
Houthi attacks raise supply concerns
The conflict has also widened into a renewed confrontation between Saudi Arabia and Yemen’s Iran-backed Houthi movement.
On 8 September, Saudi authorities said Houthi attacks had targeted civilian and economic sites in Abha, Khamis Mushait, Jazan and Najran in the south of the kingdom, injuring 73 people.
Saudi Arabia’s Ministry of Energy said several energy sector facilities and installations had been targeted, causing fires and forcing a temporary halt to some operations.
The Houthis said their attacks were in response to Saudi military action in Yemen, including what they described as attacks on Houthi positions and a Saudi blockade of ports and airports.
Riyadh condemns attacks
Saudi Arabia has strongly condemned the Houthi attacks and warned that it would take measures to defend its territory and national assets.
In a statement on 8 September, the Ministry of Energy said authorities were working to address the impact of the attacks and ensure the safety of facilities and personnel while maintaining operations in accordance with approved plans.
Saudi Arabia’s Ministry of Foreign Affairs also condemned the attacks and said the kingdom had the right to take measures to defend its sovereignty and protect its citizens, residents and national assets.
https://image.digitalinsightresearch.in/uploads/NewsArticle/19505512/main0138.jpg -
What actually slows a gigaproject down9 September 2026

Ask anyone delivering a major programme in the GCC what causes delays and sequencing will come up early. Utilities go in too late. Approvals lag behind construction. Stations, depots and access roads are procured as if they belong to different projects rather than one system.
“None of this is new. The industry has understood these risks for years,” says Alan Caldwell, managing director for transport and infrastructure at WSP Middle East.
For Caldwell, that is what makes the pattern worth interrogating rather than simply restating.
“The more important question is why the same issues around interfaces, approvals, stakeholder alignment and delivery sequencing continue to slow major programmes when the risks are already so well understood,” he says.
The answer, he argues, is not that these programmes are too big or too technically complex. What breaks a schedule is a wider system delivered as a set of disconnected parts; an approval sitting with an authority team with no visibility of the construction sequence downstream; or a station package proceeding without the utilities diversion it depends on.
“Infrastructure programmes do not struggle because a railway is too large or a highway network is too complex,” Caldwell says. “They encounter difficulties when interconnected elements are delivered in the wrong order.”
Sequencing decisions are rarely purely technical either, he adds. They are commercial – shaped by which assets need to unlock value first, which phases are tied to funding, and where sales or investment assumptions depend on infrastructure landing in a particular order.
Approvals sit at the centre of that logic. On many programmes, they become one of the biggest sources of lost time – not because the requirements are unreasonable, but because approvals are not planned, evidenced or owned as part of the delivery logic from day one.
Caldwell has seen the same pattern across three decades of Gulf delivery, from early work on Palm Jumeirah to today’s region-wide transport programmes.
“The decisive factor has often been the same: whether interfaces, approvals, responsibilities and delivery sequencing are aligned early enough to prevent complexity becoming delay.”
Integration needs to be well understood
“Most programme teams in the region would say they understand the need for integration,” Caldwell says. Fewer are structured to deliver it. “The harder task is turning that understanding into the way projects are actually set up and managed,” he argues.
Riyadh Metro is the reference point he returns to, precisely because engineering complexity was not the deciding factor in its delivery.
Coordinating a city-scale transport system meant aligning design, construction, systems, utilities and stakeholder interfaces across every delivery vertical.
“The lesson for the region today is clear,” Caldwell says. “Ambitious programmes need a delivery model that gives every contributor a shared view of progress, risk, decision-making and the business case driving programme priorities.”
That shared view, he argues, will be what the next phase of Gulf delivery is judged on.
Whether clients, consultants, contractors, operators and approval authorities can work to a single delivery logic will be key.
“This requires more than coordination meetings. It requires integrated ways of working, shared common data environments and governance structures that make risks, decisions and dependencies visible before they become delays,” he says.
From reporting progress to managing risk before it lands
Digital tools have a role here, Caldwell says, but not as a headline in themselves.
Digital twins, programme visualisation and data-led modelling matter only if they help teams identify and address problems before they affect the wider programme.
“The real value is not technology for its own sake,” he says. “It is the ability to see, in one place, where approvals are outstanding, where interfaces are unresolved, where programme dates are slipping, where clashes are emerging and where decisions need to be escalated."
None of it works without governance behind it, he cautions. “A dashboard will not resolve a delayed approval if nobody knows who owns the decision, when it needs to be made, or how it should be escalated.”
Data only has value if the processes and responsibilities around it are clear, which is why Caldwell frames the shift the region needs not as digitisation, but as a move “from programme management as a discipline focused mainly on reporting and coordination, and towards project and programme intelligence”.
With many of the region’s programmes running for a decade or more, he adds, delivery models also need to flex as funding assumptions, user needs and policy priorities change along the way.
“The ambition behind the Gulf’s transformation programmes is not in question,” Caldwell says.
What will determine how much of it is realised on time is whether delivery models evolve at the same pace: earlier integration, clearer approval pathways, shared data environments, and every contributor working to a delivery logic that connects technical sequencing with the funding and operational case behind it.
“The region’s next challenge is not imagining bigger projects,” he says. “It is changing the way they are delivered, operated and adapted over time.”
https://image.digitalinsightresearch.in/uploads/NewsArticle/19502016/main.gif -
Qatari firm wins $221m Qiddiya stadium MEP deal9 September 2026

Register for MEED’s 14-day trial access
Qatari contractor Elegancia MEP, part of Estithmar Holding, has won a SR829m ($221m) mechanical package contract for the Prince Mohammed Bin Salman Stadium in Qiddiya, Saudi Arabia.
The contract covers full mechanical, electrical and plumbing (MEP) works for the stadium, and is Elegancia MEP’s largest award in Saudi Arabia to date.
The 45,000-seat stadium will feature a fully combined retractable pitch, roof and LED wall.
The stadium’s main construction works are being undertaken by a joint venture of Spanish firm FCC Construction and local firm Nesma & Partners.
Saudi gigaproject developer Qiddiya Investment Company awarded an estimated SR15bn ($4bn) deal to build the stadium in October 2024, as MEED exclusively reported.
The contract covered the construction of a multipurpose stadium on top of the 200-metre-high Tuwaiq cliff in the new sports and entertainment district of Qiddiya City.
Once completed, the stadium will be the home ground for Saudi Pro League football clubs Al-Nassr and Al-Hilal.
US-based architect Populous is the project consultant.
The stadium is one of the venues for the kingdom’s 2034 Fifa World Cup bid and will host events such as the Saudi King Cup, the Asian Cup and the 2034 Asian Games.
https://image.digitalinsightresearch.in/uploads/NewsArticle/19501493/main.jpg -
Jordan tenders advisory for wastewater treatment plant9 September 2026
The Water Authority Jordan (WAJ) has issued an invitation to prequalify for advisory services for the rehabilitation and expansion of the Shallala wastewater treatment plant in Irbid, northern Jordan.
The Shallala plant was commissioned in 2013 with a design capacity of about 14,000 cubic metres a day (cm/d).
The rehabilitation and expansion project will increase its treatment capacity to about 30,500 cm/d to meet projected wastewater flows through 2050.
The PIU Support and Construction Supervision Consultancy Services tender was released on 19 August.
The submission deadline is 21 September.
The consultancy will support the project implementation unit and provide construction supervision services for the project. The project has an estimated value of $69m and is being financed by the European Bank for Reconstruction and Development.
The planned works include rehabilitating the existing activated sludge and treatment units and constructing a new treatment train.
The scope also includes installing biogas combined heat and power units, improving sludge handling and dewatering systems, and installing odour control and chemical containment systems.
WAJ is also undertaking the upgrade and expansion of the Ain Ghazal wastewater treatment plant in Amman.
The existing facility had a capacity of 330,000 cm/d and is being upgraded to 726,712 cm/d to accept and treat expected incoming flows until 2045.
The local Arab Towers Contracting Company was appointed as the main contractor for the project last year.
READ THE SEPTEMBER 2026 MEED BUSINESS REVIEW – click here to view PDFNuclear power ambitions gather pace; Kuwait keeps dealmaking alive despite war; Region invests in raising gas processing capacity.
Distributed to senior decision-makers in the region and around the world, the September 2026 edition of MEED Business Review includes:
> AGENDA: Gulf nuclear revival takes shape> MARKET FOCUS: Kuwait keeps dealmaking alive under fire> INDUSTRY REPORT: Gas processing takes centre stage in Mena regionTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/19498520/main.jpg -
Consultants bid for Abu Dhabi light rail project management9 September 2026

Register for MEED’s 14-day trial access
Abu Dhabi Transport Company (ADTC) has issued a request for prequalification (RFQ) notice to consultants for a contract for project management engineering consultancy services for the first phase of the light rail transit network, also known as ADT4.
The notice was issued on 7 September, with a submission deadline of 9 November.
The project’s first phase will span 19 kilometres (km) and include 23 stations, connecting Zayed International airport (AUH) with nearby areas, including Yas Island, Al‑Raha Beach and Khalifa City.
The key sections of the tram are:
AUH to Yas Island: The tram will start from Terminal A at AUH and run through the Yas tunnel to Yas Gateway Park. It will serve areas including Yas Bay, Media Zone, Yas Plaza, Yas Drive, Yas Mall, Sea World and Water Edge.
This section covers 13km and includes 13 at-grade stations and one underground station.
Al-Raha: This section will stretch for 4.3km and run along Al-Raha Street. It will serve areas including Al-Zeina, Al-Muneera and Al-Bandar, towards the Aldar head office. The section will include seven at-grade stations.
Etihad Plaza: This section will pass the Etihad Aviation Training Centre and span about 1.7km. It will feature a main depot near the Etihad Airways headquarters, along with two at-grade stations.
The tender also covers the procurement of 25 trams, each with a capacity of 270 people, along with associated systems.
The project was officially launched at the GlobalRail exhibition in Abu Dhabi in October last year.
Referred to as Abu Dhabi Tram Line 4, the project will be delivered in three phases.
Construction of the first phase is expected to start next year. The tram is slated to begin operations by 2030.
Future phases will extend towards Khalifa City and serve additional destinations across Yas Island.
The project forms a key part of the recently announced AED170bn ($46bn) package of national transport and road projects to be implemented by 2030.
https://image.digitalinsightresearch.in/uploads/NewsArticle/19493532/main.jpg