Capacity building spurs upstream spending
27 April 2023

The Middle East and North Africa (Mena) region, where a third of the world’s crude oil and about a quarter of its natural gas is produced, is increasing its hydrocarbons production potential.
There are an estimated $113.6bn-worth of upstream oil and gas projects in the engineering, procurement and construction (EPC) execution stage in the Mena region, according to data from regional projects tracker MEED Projects.
Most of these schemes are set to be commissioned between this year and 2025, helping the region to consolidate its position as the largest producer of crude oil, natural gas and liquefied natural gas (LNG).
With the world still heavily reliant on hydrocarbons, and green energy sources falling short of meeting global energy needs, oil and gas producers in the region see more merit in investing in building upstream production potential.
Regional oil and gas industry leaders have been making the case for increasing spending on boosting hydrocarbons output capacity. Their purpose has been to draw the world’s attention to the role of fossil fuels as a bridge to achieving a clean energy transition, as well as to justify their major upstream capital expenditure (capex) programmes.
Saudi Arabia dominates
Saudi Aramco tops MEED’s ranking of state energy enterprises in the Mena region by the volume of upstream oil and gas projects under EPC execution, with nearly $41bn-worth of project value.
Aramco aims to increase its maximum oil output spare capacity to 13 million barrels a day (b/d) by 2027 from about 12 million b/d currently. It also plans to raise gas production by 50 per cent by the end of this decade.
With a large portion of its under-execution projects expected to come online by the middle of this decade, the Saudi energy giant appears to be on track to meet its strategic output goals.
The largest Saudi Aramco project under execution is the $3bn-plus Berri increment programme, which was awarded to Italian contractor Saipem in July 2019. Through the project, Aramco plans to add 250,000 b/d of Arabian light crude from the offshore oil and gas field.
The planned facilities will include a new gas oil separation plant (GOSP) on Abu Ali Island to process 500,000 b/d of Arabian light crude and additional processing facilities at the Khursaniyah gas plant to process 40,000 b/d of associated hydrocarbons condensates.
The Berri increment programme will complement Saudi Aramco’s $15bn Marjan field development programme, EPC contracts for which were also awarded in July 2019. The scheme is an integrated project for oil, associated gas, non-associated gas and cap gas from the Marjan offshore oil and gas field.
The Marjan development plan includes provision of a new offshore GOSP and 24 offshore oil, gas and water injection platforms. The contract for the main GOSP, which is worth $3bn and is the first EPC package of the project, was awarded to McDermott International. The US contractor also won offshore package four, which involves the building of offshore gas facilities and is valued at about $1.5bn.
The offshore development project aims to increase the production of the Marjan field by 300,000 b/d of Arabian medium crude oil, process 2.5 billion cubic feet a day (cf/d) of gas and produce an additional 360,000 b/d of ethane and natural gas liquids.
Looking ahead, Aramco expects capital expenditure in 2023 to be $45bn-$55bn, including external investments. This projected spending is at least 20 per cent higher than the company’s $37.6bn capex in 2022.
Qatar’s LNG expansion
With the goal of consolidating its position as the world’s largest supplier of gas, QatarEnergy continues to progress with its North Field LNG expansion programme. The project, which is estimated to be worth about $30bn, will increase Qatar’s LNG production to 126 million tonnes a year (t/y) in two phases by 2027.
The two-stage North Field Production Sustainability (NFPS) programme will run in parallel, to help maintain gas production from the offshore reserve in order to match the feedstock requirements of the LNG expansion scheme.
QatarEnergy led spending on upstream projects in 2022 for the second year in a row, accounting for more than a third of the $18.9bn EPC contract awards in the Mena region. The firm’s overall value of EPC projects under execution stands at $27.3bn, putting it in second place in MEED’s ranking of the biggest national oil companies by volume of under-execution projects.
Launched in 2017, the North Field East (NFE) project constitutes the first phase of QatarEnergy’s North Field LNG expansion project. As well as an LNG output of 32 million t/y, NFE will produce 4,000 tonnes a day (t/d) of ethane as feedstock for future petrochemicals developments, 260,000 b/d of condensates, 11,000 t/d of liquefied petroleum gas (LPG) and 20 t/d of helium.
The EPC works on QatarEnergy’s NFE project were divided into six packages – four onshore and two offshore – and are currently progressing.
QatarEnergy awarded a $13bn contract for NFE package one to a consortium of Chiyoda and TechnipEnergies in February 2021. The package covers the EPC of four LNG trains, each planned to have an output capacity of about 8 million t/y.
QatarEnergy’s largest award in 2022 was a $4.5bn EPC contract that was won by Saipem for the building and installation of two gas compression facilities as part of the second development phase of its NFPS project. The gas compression complexes covered in the package known as EPCI 2 will weigh 62,000 tonnes and 63,000 tonnes and will be the largest fixed steel jacket compression platforms ever built.
Abu Dhabi ambitions
Abu Dhabi National Oil Company (Adnoc) adopted a five-year business plan in November last year that covers a capex budget of $150bn for 2023-27. The budget also sets the target of achieving its oil production capacity goal of 5 million b/d by 2027 rather than 2030.
The oil production increment projects that it has under execution are expected to play a key role in enabling the Abu Dhabi major to attain its accelerated oil capacity target.
The largest of Adnoc’s under execution projects is a $1.4bn EPC contract awarded to Spanish contractor Tecnicas Reunidas in late 2018 for upgrading the Bu Hasa onshore oil field development. Through this project, Adnoc plans to increase the Bu Hasa field’s production from 500,000 b/d to 650,000 b/d.
On the gas production front – a core priority for Adnoc – $1.5bn-worth of EPC contracts were awarded to Abu Dhabi’s National Petroleum Construction Company (NPCC) and Tecnicas Reunidas in November 2021 for the offshore and onshore packages, respectively, of the Dalma sour gas field development project.
When completed in 2025, the project will enable the Dalma field to produce about 340 million cf/d of natural gas.
The Abu Dhabi energy giant further intends to raise its total gas output by 3 billion cf/d in the next few years. The Hail and Ghasha offshore sour gas production project will be central to achieving this goal.
In January, Adnoc signed pre-construction services agreements (PCSAs) with France-headquartered Technip Energies, South Korean contractor Samsung Engineering and Italy’s Tecnimont for the Hail and Ghasha onshore package. Saipem, NPCC and state-owned China Petroleum Engineering & Construction Company secured a PCSA for the offshore package.
While the onshore and offshore PCSAs awarded to the two consortiums by Adnoc are valued at $80m and $60m, respectively, the EPC packages are estimated to be worth $5.5bn and $5bn.
As part of the PCSAs, the contractors are required to perform initial detailed engineering and procurement for important long-lead items.
Based on proposals to be submitted later this year, Adnoc is expected to award the same contractors the contracts for the main EPC works on the Hail and Ghasha project.
Production from the Ghasha concession, where the Dalma and Hail and Ghasha fields are located, is expected to start in 2025, ramping up to more than 1.5 billion cf/d before the end of this decade.
Main image: Saudi Aramco tops the ranking of state energy enterprises in the Mena region with almost $41bn-worth of projects under execution. Credit: Aramco
Exclusive from Meed
-
SLB passes evaluation for Kuwait upstream project12 December 2025
-
SAR to tender new phosphate rail track section in January12 December 2025
-
Contract award nears for Saudi Defence Ministry headquarters10 December 2025
-
Firms prepare Riyadh government office PPP bids10 December 2025
-
Municipality seeks consultants for Dubailand drainage project10 December 2025
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
SLB passes evaluation for Kuwait upstream project12 December 2025
The US-based oilfield services company SLB, formerly Schlumberger, has passed the technical bid evaluation for a major project to develop Kuwait’s Mutriba oil field.
The Houston-headquartered company was the only bidder to pass the technical evaluation for the Mutriba integrated project management (IPM) contract.
The minimum passing technical evaluation score was 75%.
The full list of bidders was:
- SLB (US): 97%
- Halliburton (US): 72%
- Weatherford (US): 61.5%
The decision was finalised at a meeting of the Higher Purchase Committee (HPC) of state-owned Kuwait Petroleum Corporation (KPC) on 20 November 2025.
According to a document published earlier this year by KOC, the IPM tender for the Mutriba field aims to “accelerate production through a comprehensive study that includes economic feasibility evaluation, well planning and long-term sustainability strategies”.
The field was originally discovered in 2009.
Commercial production from the Mutriba field started earlier this year, on 15 June, after several wells were connected to production facilities.
The field is located in a relatively undeveloped area in northwest Kuwait and spans more than 230 square kilometres.
The oil at the Mutriba field has unusually high hydrogen sulfide content, which can be as much as 40%.
This presents operational challenges requiring specialised technologies and safety measures.
In order to start producing oil at the field, KOC deployed multiphase pumps to increase hydrocarbon pressure and enable transportation to the nearest Jurassic production facilities in north Kuwait.
The company also built long-distance pipelines stretching 50 to 70 kilometres, using high-grade corrosion-resistant materials engineered to withstand the high hydrogen sulfide levels and ensure long-term reliability.
KOC also commissioned the Mutriba long-term testing facility in northwest Kuwait, with a nameplate capacity of around 5,000 barrels of oil a day (b/d) and 5 million standard cubic feet of gas a day (mmscf/d).
Once this facility was commissioned, production stabilised at 5,000 b/d and 7 mmscf/d.
In documents published earlier this year, KOC said that starting production from the field had “laid a solid foundation” for the IPM contract by generating essential reservoir and surface data that will guide future development.
Future output from the field is expected to range between 80,000 and 120,000 b/d, in addition to approximately 150 mmscf/d of gas.
https://image.digitalinsightresearch.in/uploads/NewsArticle/15235579/main.png -
SAR to tender new phosphate rail track section in January12 December 2025

Saudi Arabian Railways (SAR) is expected to float another multibillion-riyal tender to double the tracks on the existing phosphate railway network, connecting the Waad Al-Shamal mines to Ras Al-Khair in the Eastern Province.
MEED understands that the new tender – covering the second section of the track-doubling works, spanning more than 150 kilometres (km) – will be issued in January.
The new tender follows SAR’s issuance of the tender for the project's first phase in November, which spans about 100km from the AZ1/Nariyah Yard to Ras Al-Khair.
The scope includes track doubling, alignment modifications, new utility bridges, culvert widening and hydrological structures, as well as the conversion of the AZ1 siding into a mainline track.
The scope also covers support for signalling and telecommunication systems.
The tender notice was issued in late November, with a bid submission deadline of 20 January.
Switzerland-based engineering firm ARX is the project consultant.
MEED understands that these two packages are the first of four that SAR is expected to tender for the phosphate railway line.
The other packages expected to be tendered shortly include the depot and the systems package.
In 2023, MEED reported that SAR was planning two projects to increase its freight capacity, including an estimated SR4.2bn ($1.1bn) project to install a second track along the North Train Freight Line and construct three new freight yards.
Formerly known as the North-South Railway, the North Train is a 1,550km-long freight line running from the phosphate and bauxite mines in the far north of the kingdom to the Al-Baithah junction. There, it diverges into a line southward to Riyadh and a second line running east to downstream fertiliser production and alumina refining facilities at Ras Al-Khair on the Gulf coast.
Adding a second track and the freight yards will significantly increase the network’s cargo-carrying capacity and facilitate increased industrial production. Project implementation is expected to take four years.
State-owned SAR is also considering increasing the localisation of railway materials and equipment, including the construction of a cement sleeper manufacturing facility.
https://image.digitalinsightresearch.in/uploads/NewsArticle/15229624/main.jpg -
Contract award nears for Saudi Defence Ministry headquarters10 December 2025

Saudi Arabia’s Defence Ministry (MoD) is preparing to award the contract to build a new headquarters building, as part of its P-563 programme in Riyadh.
MEED understands that bid evaluation has reached advanced stages and the contract award is imminent.
The MoD issued the tender in April. The commercial bids were submitted in September, as MEED reported.
Located to the northwest of Riyadh, the P-563 programme includes the development of facilities and infrastructure to support the MoD’s broader initiatives under the kingdom’s Vision 2030 strategy.
It covers the construction of:
- A new military city featuring the MoD headquarters, support and logistics facilities, a residential and commercial community and space for future command centres
- A National Defence University with a library, conference centre and academic buildings
- A self-sustaining Joint Forces Command compound located approximately 50 kilometres from the military city
The budget for the entire programme is expected to be $10bn-$12bn.
In September 2023, MEED reported that Spain-headquartered Typsa had won two contracts for the project.
The first contract, worth $11.4m, included data management, geographic information systems management, geotechnical reporting and the preparation of the phase one final traffic report. The contract duration was 270 days from the notice to proceed.
The second contract, valued at $10.8m, involved preparing four conceptual masterplans for the P-563 site. It was set to last 255 days from the notice to proceed.
These followed a $290m consultancy contract awarded to Typsa in March of the same year. The single-award task order covered a three-year base period, with an optional two-year extension.
Typsa’s scope of work included programme management planning, communications, change and quality management and cost and schedule tracking.
It also included design requirements, codes, standards and submission requirements, programme guidance, study integration, risk analysis and management, design reviews and a programme-of-work breakdown plan.
READ THE DECEMBER 2025 MEED BUSINESS REVIEW – click here to view PDFProspects widen as Middle East rail projects are delivered; India’s L&T storms up MEED’s EPC contractor ranking; Manama balances growth with fiscal challenges
Distributed to senior decision-makers in the region and around the world, the December 2025 edition of MEED Business Review includes:
> AGENDA 1: Regional rail construction surges ahead> INDUSTRY REPORT 1: Larsen & Toubro climbs EPC contractor ranking> INDUSTRY REPORT 2: Chinese firms expand oil and gas presence> CONSTRUCTION: Aramco Stadium races towards completion> RENEWABLES: UAE moves ahead with $6bn solar and storage project> INTERVIEW: Engie pivots towards renewables projects> BAHRAIN MARKET FOCUS: Manama pursues reform amid strainTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/15222401/main.gif -
Firms prepare Riyadh government office PPP bids10 December 2025

Firms are preparing to submit bids for a contract covering the construction of the Riyadh administrative office for Defence Ministry (MoD) personnel.
The clients have asked firms to submit their bids by 26 March 2026.
The MoD is developing the project in collaboration with Saudi Arabia's National Centre for Privatisation & PPP (NCP).
The project will be implemented under a design, build, finance and maintain contract with a term of 27.5 years.
The administrative complex, located in the north of Riyadh, will cover about 52,793 square metres. It will accommodate 4,500 employees and provide 3,200 parking spaces.
In September, the NCP announced the prequalified bidders for the project. These include:
- Tamasuk / Alghanim International (local/Kuwait)
- Mota-Engil / Tatweer Buildings Company / Alternative Resources Investments (Portugal/local/UAE)
- Albawani / Areic (local/local)
- Bonyan Real Estate Investment / Artar (local/local)
- FCC / IHCC (Spain/local)
- Vision Invest (local)
- Own Real Estate (local)
- Alfanar (local)
- Lamar Holding (local)
- Alyamama (local)
- El-Seif Engineering Contracting (local)
- Al-Kifah Holding Company (local)
- Alargan (Kuwait)
- Asyad (Oman)
The NCP and MoD started the expression of interest and request for qualification process for the project in May, as MEED reported.
According to an official statement, "the selected private-sector partner will be responsible for the design, construction and long-term maintenance of the facilities and supporting infrastructure, as well as coordination with stakeholders and obtaining all necessary permits".
The value of public-private partnership (PPP) contracts in Saudi Arabia has risen sharply over the past few years as the government seeks to develop projects through the private sector and diversify funding sources.
PPPs have been used in Saudi Arabia and the wider GCC region for over two decades, but have been mainly limited to power generation and water desalination plants, where the developer benefits from guaranteed take-or-pay power-purchase agreements that eliminate demand risk.
However, in the past three years, the government has successfully implemented PPPs in several new sectors, including education and healthcare, to finance, build and operate schools and hospitals. Forthcoming PPP projects include the estimated $2.5bn Asir-Jizan highway, which would be the first road concession in the GCC; the multibillion-dollar contract to develop the expansion of Abha International airport; and the Qiddiya high-speed rail scheme.
Outside the utilities sector, the NCP has more than 170 PPPs in the pipeline, covering long-term concession agreements in projects as diverse as municipal laboratories, television and radio tower infrastructure, court complexes and logistics zones.
As capital expenditure continues to increase, the NCP is expected to add dozens more PPPs to its future pipeline to relieve the state’s financial burden and to stimulate the private sector’s involvement in the local projects market.
READ THE DECEMBER 2025 MEED BUSINESS REVIEW – click here to view PDFProspects widen as Middle East rail projects are delivered; India’s L&T storms up MEED’s EPC contractor ranking; Manama balances growth with fiscal challenges
Distributed to senior decision-makers in the region and around the world, the December 2025 edition of MEED Business Review includes:
> AGENDA 1: Regional rail construction surges ahead> INDUSTRY REPORT 1: Larsen & Toubro climbs EPC contractor ranking> INDUSTRY REPORT 2: Chinese firms expand oil and gas presence> CONSTRUCTION: Aramco Stadium races towards completion> RENEWABLES: UAE moves ahead with $6bn solar and storage project> INTERVIEW: Engie pivots towards renewables projects> BAHRAIN MARKET FOCUS: Manama pursues reform amid strainTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/15222216/main.jpg -
Municipality seeks consultants for Dubailand drainage project10 December 2025
Register for MEED’s 14-day trial access
Dubai Municipality has invited consultants to prequalify for a contract to provide supervision services on a major drainage infrastructure project serving developed communities in Dubailand.
The sewerage and stormwater drainage project, listed under the code DS-204-S1, is being procured through the government’s Sewerage and Recycled Water Projects Department (SRPD).
The bid submission deadline is 8 January.
The consultancy contract follows the issuance in November of the related construction package, DS-204-C1, for which the municipality invited contractors to prequalify.
The scope includes sewage gravity pipelines with diameters of up to 2,200mm, a sewage lift station with a capacity of three cubic metres a second, and a 1,400mm-diameter sewage rising main that will take pumped sewage from the lift station to the main sewer network.
The bid submission deadline for the construction package is also 8 January 2026.
The tenders form part of Dubai’s wider investment in sewerage expansion, including the $8bn Tasreef programme, for which several projects have moved into the execution phase in recent months.
Once completed, the Tasreef system is expected to increase Dubai’s overall drainage capacity by about 700% and provide daily stormwater treatment capacity exceeding 20 million cubic metres.
READ THE DECEMBER 2025 MEED BUSINESS REVIEW – click here to view PDFProspects widen as Middle East rail projects are delivered; India’s L&T storms up MEED’s EPC contractor ranking; Manama balances growth with fiscal challenges
Distributed to senior decision-makers in the region and around the world, the December 2025 edition of MEED Business Review includes:
> AGENDA 1: Regional rail construction surges ahead> INDUSTRY REPORT 1: Larsen & Toubro climbs EPC contractor ranking> INDUSTRY REPORT 2: Chinese firms expand oil and gas presence> CONSTRUCTION: Aramco Stadium races towards completion> RENEWABLES: UAE moves ahead with $6bn solar and storage project> INTERVIEW: Engie pivots towards renewables projects> BAHRAIN MARKET FOCUS: Manama pursues reform amid strainTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/15218750/main.jpg

