Capacity building spurs upstream spending
27 April 2023

The Middle East and North Africa (Mena) region, where a third of the world’s crude oil and about a quarter of its natural gas is produced, is increasing its hydrocarbons production potential.
There are an estimated $113.6bn-worth of upstream oil and gas projects in the engineering, procurement and construction (EPC) execution stage in the Mena region, according to data from regional projects tracker MEED Projects.
Most of these schemes are set to be commissioned between this year and 2025, helping the region to consolidate its position as the largest producer of crude oil, natural gas and liquefied natural gas (LNG).
With the world still heavily reliant on hydrocarbons, and green energy sources falling short of meeting global energy needs, oil and gas producers in the region see more merit in investing in building upstream production potential.
Regional oil and gas industry leaders have been making the case for increasing spending on boosting hydrocarbons output capacity. Their purpose has been to draw the world’s attention to the role of fossil fuels as a bridge to achieving a clean energy transition, as well as to justify their major upstream capital expenditure (capex) programmes.
Saudi Arabia dominates
Saudi Aramco tops MEED’s ranking of state energy enterprises in the Mena region by the volume of upstream oil and gas projects under EPC execution, with nearly $41bn-worth of project value.
Aramco aims to increase its maximum oil output spare capacity to 13 million barrels a day (b/d) by 2027 from about 12 million b/d currently. It also plans to raise gas production by 50 per cent by the end of this decade.
With a large portion of its under-execution projects expected to come online by the middle of this decade, the Saudi energy giant appears to be on track to meet its strategic output goals.
The largest Saudi Aramco project under execution is the $3bn-plus Berri increment programme, which was awarded to Italian contractor Saipem in July 2019. Through the project, Aramco plans to add 250,000 b/d of Arabian light crude from the offshore oil and gas field.
The planned facilities will include a new gas oil separation plant (GOSP) on Abu Ali Island to process 500,000 b/d of Arabian light crude and additional processing facilities at the Khursaniyah gas plant to process 40,000 b/d of associated hydrocarbons condensates.
The Berri increment programme will complement Saudi Aramco’s $15bn Marjan field development programme, EPC contracts for which were also awarded in July 2019. The scheme is an integrated project for oil, associated gas, non-associated gas and cap gas from the Marjan offshore oil and gas field.
The Marjan development plan includes provision of a new offshore GOSP and 24 offshore oil, gas and water injection platforms. The contract for the main GOSP, which is worth $3bn and is the first EPC package of the project, was awarded to McDermott International. The US contractor also won offshore package four, which involves the building of offshore gas facilities and is valued at about $1.5bn.
The offshore development project aims to increase the production of the Marjan field by 300,000 b/d of Arabian medium crude oil, process 2.5 billion cubic feet a day (cf/d) of gas and produce an additional 360,000 b/d of ethane and natural gas liquids.
Looking ahead, Aramco expects capital expenditure in 2023 to be $45bn-$55bn, including external investments. This projected spending is at least 20 per cent higher than the company’s $37.6bn capex in 2022.
Qatar’s LNG expansion
With the goal of consolidating its position as the world’s largest supplier of gas, QatarEnergy continues to progress with its North Field LNG expansion programme. The project, which is estimated to be worth about $30bn, will increase Qatar’s LNG production to 126 million tonnes a year (t/y) in two phases by 2027.
The two-stage North Field Production Sustainability (NFPS) programme will run in parallel, to help maintain gas production from the offshore reserve in order to match the feedstock requirements of the LNG expansion scheme.
QatarEnergy led spending on upstream projects in 2022 for the second year in a row, accounting for more than a third of the $18.9bn EPC contract awards in the Mena region. The firm’s overall value of EPC projects under execution stands at $27.3bn, putting it in second place in MEED’s ranking of the biggest national oil companies by volume of under-execution projects.
Launched in 2017, the North Field East (NFE) project constitutes the first phase of QatarEnergy’s North Field LNG expansion project. As well as an LNG output of 32 million t/y, NFE will produce 4,000 tonnes a day (t/d) of ethane as feedstock for future petrochemicals developments, 260,000 b/d of condensates, 11,000 t/d of liquefied petroleum gas (LPG) and 20 t/d of helium.
The EPC works on QatarEnergy’s NFE project were divided into six packages – four onshore and two offshore – and are currently progressing.
QatarEnergy awarded a $13bn contract for NFE package one to a consortium of Chiyoda and TechnipEnergies in February 2021. The package covers the EPC of four LNG trains, each planned to have an output capacity of about 8 million t/y.
QatarEnergy’s largest award in 2022 was a $4.5bn EPC contract that was won by Saipem for the building and installation of two gas compression facilities as part of the second development phase of its NFPS project. The gas compression complexes covered in the package known as EPCI 2 will weigh 62,000 tonnes and 63,000 tonnes and will be the largest fixed steel jacket compression platforms ever built.
Abu Dhabi ambitions
Abu Dhabi National Oil Company (Adnoc) adopted a five-year business plan in November last year that covers a capex budget of $150bn for 2023-27. The budget also sets the target of achieving its oil production capacity goal of 5 million b/d by 2027 rather than 2030.
The oil production increment projects that it has under execution are expected to play a key role in enabling the Abu Dhabi major to attain its accelerated oil capacity target.
The largest of Adnoc’s under execution projects is a $1.4bn EPC contract awarded to Spanish contractor Tecnicas Reunidas in late 2018 for upgrading the Bu Hasa onshore oil field development. Through this project, Adnoc plans to increase the Bu Hasa field’s production from 500,000 b/d to 650,000 b/d.
On the gas production front – a core priority for Adnoc – $1.5bn-worth of EPC contracts were awarded to Abu Dhabi’s National Petroleum Construction Company (NPCC) and Tecnicas Reunidas in November 2021 for the offshore and onshore packages, respectively, of the Dalma sour gas field development project.
When completed in 2025, the project will enable the Dalma field to produce about 340 million cf/d of natural gas.
The Abu Dhabi energy giant further intends to raise its total gas output by 3 billion cf/d in the next few years. The Hail and Ghasha offshore sour gas production project will be central to achieving this goal.
In January, Adnoc signed pre-construction services agreements (PCSAs) with France-headquartered Technip Energies, South Korean contractor Samsung Engineering and Italy’s Tecnimont for the Hail and Ghasha onshore package. Saipem, NPCC and state-owned China Petroleum Engineering & Construction Company secured a PCSA for the offshore package.
While the onshore and offshore PCSAs awarded to the two consortiums by Adnoc are valued at $80m and $60m, respectively, the EPC packages are estimated to be worth $5.5bn and $5bn.
As part of the PCSAs, the contractors are required to perform initial detailed engineering and procurement for important long-lead items.
Based on proposals to be submitted later this year, Adnoc is expected to award the same contractors the contracts for the main EPC works on the Hail and Ghasha project.
Production from the Ghasha concession, where the Dalma and Hail and Ghasha fields are located, is expected to start in 2025, ramping up to more than 1.5 billion cf/d before the end of this decade.
Main image: Saudi Aramco tops the ranking of state energy enterprises in the Mena region with almost $41bn-worth of projects under execution. Credit: Aramco
Exclusive from Meed
-
Qiddiya plans $7bn theme park hub near Paris25 August 2026
-
Masdar shelves Abu Dhabi green hydrogen project25 August 2026
-
Oman invites bids for Musandam renewables study25 August 2026
-
US launches sanctions campaign against Iran25 August 2026
-
Kuwait tenders $3.3bn gas processing facility25 August 2026
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Qiddiya plans $7bn theme park hub near Paris25 August 2026
Saudi Arabia’s Qiddiya Investment Company plans to develop a mixed-use leisure destination worth about €6bn ($7bn) at Cergy-Pontoise in the Ile-de-France region, in one of the largest Saudi investments in French tourism infrastructure to date.
The plan was set out in a joint statement issued on 24 August at the close of a state visit to France by Crown Prince and Prime Minister Mohammed Bin Salman Bin Abdulaziz Al-Saud. France and Saudi Arabia signed a memorandum of understanding (MoU) covering the project during the two-day visit.
The destination will bring together entertainment, leisure, hospitality, culture and sport, according to the joint statement. Current plans envisage up to three major entertainment anchors, hotels and complementary leisure experiences, with the €6bn figure covering the full development lifecycle.
One of the three parks is expected to be manga-themed, according to the French presidency. The themes of the other two have not been disclosed. The parks will be built and opened in stages, with construction expected to take several years. No opening date has been given.
The parks are expected to create about 22,000 direct jobs, according to the French presidency, compared with about 20,000 at Disneyland Paris. Cergy-Pontoise lies about 30 kilometres northwest of Paris.
Qiddiya is a subsidiary of the Public Investment Fund, Saudi Arabia’s sovereign wealth fund. Its flagship project is a giga-scale entertainment, sports and cultural city on the outskirts of Riyadh, one of several gigaprojects under Vision 2030.
The theme park plan was among a wider set of agreements reached during the visit. Both sides welcomed the announcement of 21 agreements and MoUs at a French-Saudi investment roundtable, spanning energy, industry, financial services, transport and logistics, health, culture, tourism and artificial intelligence. Bilateral trade reached about $11.8bn in 2025.
It is not the first time Saudi capital has backed a French theme park. Kingdom Holding Company was a longstanding investor in the operator of Disneyland Paris, first taking a stake in 1994 and participating in successive recapitalisations before Walt Disney Company moved to near-full ownership in 2017.
https://image.digitalinsightresearch.in/uploads/NewsArticle/18987274/main.png -
Masdar shelves Abu Dhabi green hydrogen project25 August 2026

Abu Dhabi Future Energy Company (Masdar) has decided to cancel a planned project to build a green hydrogen plant in Abu Dhabi that would have supplied up to 100MW of renewable hydrogen to local steelmaker Emsteel for green steel production.
After contractors submitted bids for the project last year, Masdar asked bidders in the first quarter of this year to extend the validity of their proposals until the end of August to allow “more time to study and evaluate bids”, according to one source.
However, Masdar issued a notification to all bidders on 1 August stating that it had decided to cancel the project, sources told MEED.
Contractors that submitted bids for the Masdar green hydrogen project included:
- Envision (China)
- Larsen & Toubro (India)
- PowerChina (China)
- Samsung E&A (South Korea)
- Sinopec (China)
Masdar did not respond to MEED’s request for comment on the information.
In its current steelmaking process, Emsteel uses hydrogen produced by steam reforming of natural gas as a reducing agent to extract iron from iron ore. The core objective of Masdar’s planned project was to install a 100MW electrolyser at Emsteel’s main manufacturing hub in Musaffah, Abu Dhabi, to supply green hydrogen for future clean steel production.
Masdar initiated work on the project in 2024 by awarding a front-end engineering and design (feed) contract to locally based NT Energies, a joint venture of Abu Dhabi’s NMDC Energy and France-based Technip Energies.
Masdar then sought proposals last year for engineering, procurement, construction, demolition (if needed for brownfield activities), pre-commissioning, commissioning, start-up, and two years of operations and maintenance (extendable up to 20 years) at the planned facility.
Contractors submitted bids by the end of the year, according to sources.
The project involved green hydrogen production using alkaline water electrolysis, with a total installed electrolyser capacity of 100MW.
The scope of work involved building electrolyser stacks and modules, hydrogen separation and compression units, associated utilities and storage systems, and electrical, instrumentation and control systems.
It also included tie-ins to pre-defined interface points, including (but not limited to):
- a grid power supply connection to the MOSF substation in Musaffah that exists within the Emsteel complex and is operated by Taqa Transmission
- a water supply connection to a nearby Taqa Distribution network
Supporting infrastructure included a substation, a motor control centre, and ancillary plant buildings and facilities.
Masdar’s planned 100MW electrolyser project at the Emsteel facility would have represented a step up from a previous pilot project by the two Abu Dhabi-owned companies.
The partners inaugurated a pilot green hydrogen plant at Emsteel’s manufacturing complex in Musaffah in October 2024. It incorporates a 2.1MW electrolyser and is designed to support the production of up to 5,000 tonnes of green steel a year.
This made Emsteel the only steelmaker in the Middle East to use green hydrogen to produce green steel on a pilot basis.
“Sustainability is central to Emsteel’s innovation, competitiveness and long-term growth. Today, approximately 89% of our steel business electricity consumption comes from clean sources, and our steel carbon emissions intensity is around 40% lower than the World Steel Association global average,” Michael Rion, chief commercial officer of Emirates Steel, part of Emsteel Group, told MEED in a recent interview.
READ THE AUGUST 2026 MEED BUSINESS REVIEW – click here to view PDFSaudi Arabia builds for the global stage; Rising uncertainty creates fresh set of challenges in the Maghreb; Gulf banks remain robust in the face of geopolitical tensions.
Distributed to senior decision-makers in the region and around the world, the August 2026 edition of MEED Business Review includes:
> WORLD CUP: What the 2026 World Cup means for Saudi Arabia 2034> MARKET FOCUS: Maghreb fortunes diverge> INDUSTRY REPORT: GCC banks prove resilient amid turmoil> LEADERSHIP: Private capital and the GCC infrastructure inflection> INTERVIEW: Developers look beyond standalone solarTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/18911651/main0611.jpg -
Oman invites bids for Musandam renewables study25 August 2026
Oman’s Nama Power & Water Procurement Company (PWP) has issued a request for proposals (RFP) for techno-economic consultancy services to assess the feasibility of renewable energy options in Musandam Governorate.
The study will examine solar photovoltaic (PV), wind and hybrid renewable energy configurations. It will also assess battery energy storage systems (bess) and other renewable energy and energy storage technologies.
The consultant will be required to determine which technologies are technically and economically justified for the governorate.
The bid submission deadline is 24 September.
The Musandam power system is served primarily by the 123MW Musandam independent power plant (IPP), which began operating in 2017. The governorate has historically relied on small diesel-fired units, but has been seeking to move away from diesel-fired power generation for several years.
Nama PWP has previously said it was exploring renewable energy options in Musandam to meet future additional capacity requirements.
Its latest seven-year statement, released in March, forecasts peak electricity demand in Musandam to rise from 91MW in 2024 to 130MW in 2031, an average annual increase of 5%. Average demand is forecast to rise from 52MW to 73MW over the same period.
The plan says demand growth is being driven by distribution-level load and projects aimed at boosting tourism, economic and commercial activity.
Separately, the utility recently invited bids for financial and commercial consultancy services covering three 1GW solar IPPs targeted for commercial operation by the second quarter of 2030.
The bid submissions deadline is 10 September.
The three projects covered by the financial and commercial consultancy tender are understood to also be part of the 4GW programme, for which a technical advisory tender was issued on 15 July.
Bidding for this tender closes on 26 August.
READ THE AUGUST 2026 MEED BUSINESS REVIEW – click here to view PDFSaudi Arabia builds for the global stage; Rising uncertainty creates fresh set of challenges in the Maghreb; Gulf banks remain robust in the face of geopolitical tensions.
Distributed to senior decision-makers in the region and around the world, the August 2026 edition of MEED Business Review includes:
> WORLD CUP: What the 2026 World Cup means for Saudi Arabia 2034> MARKET FOCUS: Maghreb fortunes diverge> INDUSTRY REPORT: GCC banks prove resilient amid turmoil> LEADERSHIP: Private capital and the GCC infrastructure inflection> INTERVIEW: Developers look beyond standalone solarTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/18983679/main.jpg -
US launches sanctions campaign against Iran25 August 2026
The US has launched a sweeping sanctions campaign against Iran and the entities that trade with it, imposing measures on almost 60 individuals, companies and vessels while expanding the reach of secondary sanctions across five sectors of the Iranian economy.
The campaign, named Operation Economic Outcast, was announced on 24 August by US treasury secretary Scott Bessent, who described it as an economic D-Day for Iran. He said Washington’s objective was to sever every economic lifeline sustaining the Iranian regime.
The treasury’s Office of Foreign Assets Control (Ofac) issued five sectoral sanctions determinations under Executive Order 13902, covering digital assets, technology, gold, aviation and shipping. The determinations allow Ofac to sanction any person operating in those sectors, regardless of location. Washington said Iran uses cryptocurrency for sanctions evasion, seeks advanced technology for its weapons programmes, uses gold to stabilise the rial, and relies on commercial aviation and shipping networks to move fighters, weapons and oil revenue.
The measures build on earlier determinations targeting Iran’s financial, petroleum and petrochemical sectors.
Ofac also sanctioned close to 60 entities, individuals and vessels across multiple jurisdictions, including UAE-based entities, over alleged involvement in nuclear and missile procurement, cyber operations and oil revenue networks. The designations named a network of brokers, companies and shadow fleet vessels operating across the UAE, Hong Kong, China, Singapore, Switzerland and other regions to transport Iranian oil and channel revenue to the Islamic Revolutionary Guard Corps.
Among those designated were shipping brokers and bunkering firms based in the UAE that Washington said facilitated Iranian oil shipments and provided services to sanctioned vessels. The treasury also identified several shadow fleet tankers as blocked property, saying they had moved millions of barrels of Iranian crude and petroleum products, mainly to China.
Separately, the treasury targeted a procurement network spanning the Middle East and East Asia that it said supported Iran’s acquisition of proliferation-sensitive equipment, along with a cyber group directed by Iran’s Ministry of Intelligence & Security.
Bessent said Washington was pressing governments to shut down Iran-related activity within defined timelines, warning that entities facilitating money laundering or sanctions evasion for Iran risked being cut off from the US financial system. He declined to name specific countries.
The campaign follows the UAE’s own move against Tehran. On 19 August, the UAE suspended all trade, commercial exchanges and financial transactions with Iran with immediate effect, citing regional escalation. The UAE has historically been one of Iran’s most significant trading partners, with much of the relationship built on re-export trade routed through Dubai.
https://image.digitalinsightresearch.in/uploads/NewsArticle/18983152/main.jpg -
Kuwait tenders $3.3bn gas processing facility25 August 2026

State-owned Kuwait Gulf Oil Company (KGOC) has issued the tender for the development of an onshore gas plant next to the Al-Zour refinery, according to industry sources.
The project budget is estimated at $3.3bn, and the bid deadline is 29 December, with a meeting for contractors scheduled for 14 September.
The tender was issued on 23 August.
The proposed plant will have the capacity to process up to 632 million cubic feet a day of gas and 60,000 b/d a day of condensates from the Dorra offshore field, located in Gulf waters in the Saudi-Kuwait Neutral Zone.
In February, MEED reported that at least seven companies had shown interest in participating in the tender.
Contractors that sent representatives to previous meetings to discuss the project include:
- Samsung E&A (South Korea)
- Larsen & Toubro (India)
- Tecnicas Reunidas (Spain)
- Saipem (Italy)
- Hyundai Engineering & Construction (South Korea)
- Hyundai Engineering Company (South Korea)
- JGC (Japan)
The tender process is using a fast-track model, which means that Kuwait’s Central Agency for Public Tenders (Capt) will not be involved in the tender process.
Capt typically reviews the technical and commercial evaluations of bids and verifies that the bidding process is competitive.
It is understood that not requiring Capt to approve this tender is expected to speed up the tender process.
Iran disputes ownership of the field, referring to it as Arash.
Iran claims the field partially extends into Iranian territory and asserts that Tehran should be a stakeholder in its development.
The Dorra field’s close proximity to Iran could make development difficult due to current security concerns.
The offshore elements of the wider Dorra field development project are expected to be especially difficult to protect from attacks from Iran.
Earlier this month, MEED revealed that Al-Khafji Joint Operations (KJO) had selected contractors for two major offshore packages under the Dorra field facilities development project.
KJO, which is jointly owned by Aramco subsidiary Aramco Gulf Operations Company and Kuwait Petroleum Corporation subsidiary KGOC, has divided the engineering, procurement and construction (EPC) scope for the Dorra gas production project into four packages: three offshore and one onshore.
US-based McDermott International has secured offshore package 2A, valued at about $1.5bn, according to sources.
A consortium of India’s Larsen & Toubro Energy Hydrocarbon (LTEH) and Italian contractor Saipem has secured package 2B, sources told MEED.
Estimated at about $3.7bn, package 2B is the largest of the three offshore EPC packages under the Dorra field facilities project.
MEED reported in March that the LTEH/Saipem consortium had emerged as the lowest bidder for offshore package 2B.
Contractors submitted bids for offshore packages 2A and 2B by the 9 March deadline, MEED previously reported. Bid validity was understood to expire on 15 August, prompting KJO to issue letters of intent to the selected contractors earlier this month, sources said.
https://image.digitalinsightresearch.in/uploads/NewsArticle/18964461/main.png