Bridging the infrastructure capacity gap
2 April 2024

The Middle East and North Africa (Mena) region faces a massive infrastructure gap, with estimates of the shortfall ranging from $75bn to $100bn annually.
This translates to a cumulative need for $2-2.5tn in infrastructure investment alone by 2050. Bridging this funding gap will require a drastic increase in the level of investment.
In 2020, the World Bank stated that Mena countries needed to spend at least 8.2% of GDP to meet their infrastructure goals through to 2030. However, it had been averaging a spend of just 3% over the prior decade – mostly from public sector funds, alongside multilateral and bilateral debt financing.
In the intervening years, the additional fiscal constraints imposed by the pandemic and global economic shocks, such as food price inflation, have further hindered regional public spending on infrastructure.
In 2023, the ICD-Refinitiv OIC Infrastructure Outlook valued the region’s outstanding funding gap for infrastructure development at $994bn. The gaps included a $685bn shortfall in investment in road infrastructure; a $111bn funding gap in the water sector; a $65bn gap in telecoms; $47bn in rail; $34bn in port infrastructure; $27bn in electricity network investment; and $25bn in airport infrastructure investment.
This funding gap has real, material impacts on economic prosperity and the prospects for economic growth. The shortfall in investment in road infrastructure, for example, is estimated to cost the Mena region a staggering 5.5% in GDP a year due to inefficiency and accidents, according to the World Bank.
A 2020 study in the Review of Middle East Economics and Finance found that manufacturing firms in the Mena region faced the most severe durations of power outages a month of any region, at 64 hours a month. The perceived value of the business losses due to these power outages was estimated to be around 4.8% of total sales.
Meeting the region’s annual investment needs could generate about 2 million direct jobs and 2.5 million direct, indirect and induced infrastructure-related jobs, according to the OECD.
This is critical when half of the region’s population is under 24 years old, and 29% are not in employment, education or training, as per the OECD figures.
Another very tangible infrastructure gap is water capacity. The current annual water shortage in the Mena region is about 42 cubic kilometres, but by 2050, this is projected to grow fivefold to 199 cubic kilometres a year under average climate scenarios and potentially up to 283 cubic kilometres a year under drier conditions.
These examples highlight the need for substantial investments to bridge the infrastructure deficiencies, ensure the conditions for economic growth, and enhance overall sustainability in the Mena region.
To address the challenges, a comprehensive and multi-faceted approach is needed to incentivise the private sector to support regional infrastructure investments. This includes governments establishing clear policy directions and regulatory frameworks to attract private capital mobilisation.
This funding gap has real, material impacts on economic prosperity and the prospects for economic growth
Technological adaptation
In parallel with the need for governments to proactively improve the conditions for investment, the delivery of future infrastructure requirements also anticipates the adoption of emerging technology.
The goal of many countries to achieve net zero by 2050 also layers further complexity onto existing infrastructure challenges. Regional efforts such as the Middle East Green Initiative and the Circular Carbon Economy framework nevertheless demonstrate the region’s commitment to achieving its net-zero targets.
Reaching net zero will entail building infrastructure that is not just bigger and better, but smarter. At the Global Infrastructure Initiative Summit hosted by McKinsey in Dubai in February, disruptive thinking and technology were identified as vital to the industry’s evolution to meet the needs of a net-zero future.
Industry leaders called for a nuts-and-bolts overhaul of the industry from the bottom up, with more sustainable alternatives to even centuries-old staples such as Portland cement and rebar. The digitalisation of the industry and the advent of machine-learning and AI also hold huge potential for cutting waste and designing more organic, efficient structures.
The summit highlighted that solving future infrastructure requirements will also likely necessitate overcoming technology hurdles and bringing costs down through research and development, much like the costs of solar power or reverse osmosis desalination have come down in the region.
Alistair Green, a senior partner in McKinsey’s global infrastructure practice, pointed to the technologies that “are not at conviction, yet: the technology hasn’t even really been proven outside of the lab – like flow batteries, which are an alternative to lithium-ion batteries that can be used for grid-scale storage of long duration, energy storage. This is a technology problem that we’re actively investing in researching in order to bring the costs down.”
Strategy& and engineering consultancy Dar recently reported that sustainable construction technologies can potentially reduce lifecycle emissions from the Mena region’s $2tn construction pipeline through to 2035 by 50%-60% for planned projects. Simple changes can be highly effective, such as incorporating dynamic facades into building designs, which can deliver energy savings of up to 55% in hot countries.
The key is the level of innovation, not the level of technology. In the right application, a low-tech solution may be more efficient. If a low-tech solution is scalable, it is also likely to be more cost-efficient.
In the arid Ait Baamrane region of Morocco, a 2015 project by the NGO Dar Si Hmad has created the world’s largest operational fog-harvesting system, providing potable water using a system of shore-side nets that capture and condense the fog rolling in off the ocean. Launched after a decade of research, the system yields approximately 22 litres of water a day for each square metre of net. It demonstrates that infrastructure does not need to be expensive or complex to have a positive sustainability outcome.
The most pressing need for the Mena region is to improve the attractiveness of its infrastructure investment opportunities
Accessing finance
Without sufficient finance, the effectiveness of infrastructure development, including technological innovation within the sector, will be throttled. The most pressing need for the Mena region is to improve the attractiveness of its infrastructure investment opportunities.
Many governments, especially in the Gulf, have been focused on encouraging the private sector through better and wider public-private partnership (PPP) arrangements, with mixed results. Some countries have struggled to deliver PPP frameworks with sufficient commercial appeal and bankability, a problem usually linked to unattractive risk allocations on the private sector side.
Nevertheless, the mobilisation of PPPs and the creation of more transparent and efficient regulatory frameworks around them are routinely identified as vital for attracting and mobilising private capital.
The delivery of more sustainable infrastructure with a view to net-zero targets also brings the potential to tap into green finance, including green bonds and sharia-compliant sukuk. Projects targeted towards carbon neutrality open themselves up to more diverse avenues of potential finance, including international climate mitigation and adaptation funds.
Multilateral development banks, such as the Asian Infrastructure Investment Bank, support initiatives like the Catalyst Mena Climate Fund 2, which works to mobilise private capital for infrastructure projects focused on renewable energy, sustainable utility schemes and green hydrogen capacity.
Governments in the region are also taking steps to mobilise climate finance by issuing green sovereign bonds and sukuk to fund clean transportation, waste management and green building schemes.
The UAE’s infrastructure development is guided by the Green Agenda 2030 policy framework. Under this aegis, UAE banks, including Mashreq Bank and First Abu Dhabi Bank, have pledged to mobilise $270bn in green financing by 2030 for environmentally impactful projects.
Infrastructure financing schemes are an important step towards drawing more private sector liquidity into the infrastructure industry, but it is also just a start compared to what will be required to deliver the region’s infrastructure needs.
Deep regional inequality also needs to be addressed. While countries such as Saudi Arabia and the UAE may currently be meeting the World Bank’s 8.2% of GDP infrastructure spending targets, the region’s hydrocarbon importers will likely need far more outside assistance.
For the region as a whole to thrive, countries will also need to work together and synergistically to deliver holistic infrastructure roadmaps. Just as the GCC is working together to deliver the Gulf Railway, the Levant and North Africa must work together to develop their shared infrastructure.
Only through cooperation and joint initiatives will the Mena region stand to bridge its infrastructure gap.
Exclusive from Meed
-
December 2025: Data drives regional projects23 December 2025
-
Local firm bids lowest for Kuwait substation deal22 December 2025
-
Saudi-Dutch JV awards ‘supercentre’ metals reclamation project22 December 2025
-
QatarEnergy LNG awards $4bn gas project package22 December 2025
-
Managing risk in the GCC construction market19 December 2025
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
December 2025: Data drives regional projects23 December 2025
Click here to download the PDF
Includes: Top inward FDI locations by project volume | Brent spot price | Construction output
MEED’s January 2026 report on Oman includes:
> COMMENT: Oman steadies growth with strategic restraint
> ECONOMY: Oman pursues diversification amid regional concerns
> BANKING: Oman banks feel impact of stronger economy
> OIL & GAS: LNG goals galvanise Oman’s oil and gas sector
> POWER & WATER: Oman prepares for a wave of IPP awards
> CONSTRUCTION: Momentum builds in construction sectorTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/15306140/main.gif -
Local firm bids lowest for Kuwait substation deal22 December 2025
The local Al-Ahleia Switchgear Company has submitted the lowest price of KD33.9m ($110.3m) for a contract to build a 400/132/11 kV substation at the South Surra township for Kuwait’s Public Authority for Housing Welfare (PAHW).
The bid was marginally lower than the two other offers of KD35.1m and KD35.5m submitted respectively by Saudi Arabia’s National Contracting Company (NCC) and India’s Larsen & Toubro.
PAHW is expected to take about three months to evaluate the prices before selecting the successful contractor.
The project is one of several transmission and distribution projects either out to bid or recently awarded by Kuwait’s main affordable housing client.
This year alone, it has awarded two contracts worth more than $100m for cable works at its 1Z, 2Z, 3Z and 4Z 400kV substations at Al-Istiqlal City, and two deals totalling just under $280m for the construction of seven 132/11kV substations in the same township.
Most recently, it has tendered two contracts to build seven 132/11kV main substations at its affordable housing project, west of Kuwait City. The bid deadline for the two deals covering the MS-01 through to MS-08 substations is 8 January.
https://image.digitalinsightresearch.in/uploads/NewsArticle/15305745/main.gif -
Saudi-Dutch JV awards ‘supercentre’ metals reclamation project22 December 2025
The local Advanced Circular Materials Company (ACMC), a joint venture of the Netherlands-based Shell & AMG Recycling BV (SARBV) and local firm United Company for Industry (UCI), has awarded the engineering, procurement and construction (EPC) contract for the first phase of its $500m-plus metals reclamation complex in Jubail.
The contract, estimated to be worth in excess of $200m, was won by China TianChen Engineering Corporation (TCC), a subsidiary of China National Chemical Engineering Company (CNCEC), following the issue of the tender in July 2024.
Under the terms of the deal, TCC will process gasification ash generated at Saudi Aramco’s Jizan refining complex on the Red Sea coast to produce battery-grade vanadium oxide and vanadium electrolyte for vanadium redox flow batteries. AMG will provide the licensed technology required for the production process.
The works are the first of four planned phases at the catalyst and gasification ash recycling ‘Supercentre’, which is located at the PlasChem Park in Jubail Industrial City 2 alongside the Sadara integrated refining and petrochemical complex.
Phase 2 will expand the facility to process spent catalysts from heavy oil upgrading facilities to produce ferrovanadium for the steel industry and/or additional battery-grade vanadium oxide.
Phase 3 involves installing a manufacturing facility for residue-upgrading catalysts.
In the fourth phase, a vanadium electrolyte production plant will be developed.
The developers expect a total reduction of 3.6 million metric tonnes of carbon dioxide emissions a year when the four phases of the project are commissioned.
SARBV first announced its intention to build a metal reclamation and catalyst manufacturing facility in Saudi Arabia in November 2019. The kingdom’s Ministry of Investment, then known as the Saudi Arabian General Investment Authority (Sagia), supported the project.
In July 2022, SARBV and UCI signed the agreement to formalise their joint venture and build the proposed facility.
The project has received support from Saudi Aramco’s Namaat industrial investment programme. Aramco, at the time, also signed an agreement with the joint venture to offtake vanadium-bearing gasification ash from its Jizan refining complex.
Photo credit: SARBV
https://image.digitalinsightresearch.in/uploads/NewsArticle/15305326/main.gif -
QatarEnergy LNG awards $4bn gas project package22 December 2025
QatarEnergy LNG, a subsidiary of state-owned QatarEnergy, has awarded the main engineering, procurement, construction and installation (EPCI) contract for a major package for the second phase of its North Field Production Sustainability (NFPS) project.A consortium comprising the Italian contractor Saipem and state-owned China Offshore Oil Engineering Company (COOEC) has secured the EPCI contract for the COMP5 package. The contract value is $4bn, with Saipem declaring its share to be worth $3.1bn.
Milan-headquartered Saipem said the contract will run for about five years. The scope of work comprises engineering, procurement, fabrication and installation of two compression complexes, each including a compression platform, a living quarters platform, a flare platform supporting the gas combustion system, and the related interconnecting bridges. Each complex will have a total weight of about 68,000 tonnes.
Offshore installation operations will be carried out by Saipem’s De He construction vessel in 2029 and 2030.
MEED previously reported that the following contractors submitted bids for the NFPS phase two COMP5 package:
- Larsen & Toubro Energy Hydrocarbon (India)
- McDermott (US)
- Saipem/China Offshore Oil Engineering Company (Italy/China)
QatarEnergy LNG, formerly Qatargas, is said to have issued the tender for the NFPS phase two COMP5 package in the first quarter of the year.
Contractors submitted technical bids for the COMP5 package in late June, while commercial bids were submitted by 8 October, as per sources.
Based upon initial evaluation of bids by QatarEnergy LNG, L&TEH has emerged as the lowest bidder for the COMP5 package, followed by McDermott, with the consortium of Saipem and COOEC in third place, MEED reported in late October.
In the weeks following that, the project operator is said to have engaged all bidders for a final round of negotiations, during which the consortium of Saipem and COOEC is believed to have “clinched the deal”, according to sources.
The detailed scope of work on the COMP5 package covers the EPCI work on the following:
- Two gas compression platforms, each weighing 30,000-35,000 tonnes, plus jacket
- Two living quarters platforms, plus jacket
- Two gas flare platforms, plus jacket
- Brownfield modification work at two complexes
NFPS scheme
QatarEnergy’s North Field liquefied natural gas (LNG) expansion programme requires the state enterprise to pump large volumes of gas from the North Field offshore reserve to feed the three phases of the estimated $40bn-plus programme.
QatarEnergy has already invested billions of dollars in engineering, procurement and construction works on the two phases of the NFPS project, which aims to maintain steady gas feedstock for the North Field LNG expansion phases.
The second NFPS phase will mainly involve building gas compression facilities to sustain and gradually increase gas production from Qatar’s offshore North Field gas reserve over the long term.
Saipem has been the most successful contractor on the second NFPS phase, securing work worth a total of $8.5bn.
QatarEnergy LNG awarded Saipem a $4.5bn order in October 2022 to build and install gas compression facilities. The main scope of work on the package, which is known as EPCI 2, covers two large gas compression complexes that will comprise decks, jackets, topsides, interconnecting bridges, flare platforms, living quarters and interface modules.
The gas compression complexes – CP65 and CP75 – will weigh 62,000 tonnes and 63,000 tonnes, respectively, and will be the largest fixed steel jacket compression platforms ever built.
Following that, Saipem won combined packages COMP3A and COMP3B of the NFPS project’s second phase in September last year.
The scope of work on the combined packages encompasses the EPCI of a total of six platforms, approximately 100 kilometres (km) of corrosion resistance alloy rigid subsea pipelines of 28-inches and 24-inches diameter, 100km of subsea composite cables, 150km of fibre optic cables and several other subsea units.
Separately, QatarEnergy LNG awarded McDermott the contract for the NFPS second phase package known as EPCI 1, or COMP1, in July 2023. The scope of work on the estimated $1bn-plus contract is to install a subsea gas pipeline network at the North Field gas development.
In March this year, India’s Larsen & Toubro Energy Hydrocarbon (LTEH) won the main contract for the combined 4A and 4B package, which is the fourth package of the second phase of the NFPS project and is estimated to be valued at $4bn-$5bn.
The main scope of work on the package is the EPCI of two large gas compression systems that will be known as CP8S and CP4N, each weighing 25,000-35,000 tonnes. The contract scope also includes compression platforms, flare gas platforms and other associated structures.
LTHE sub-contracted detailed engineering and design works on the combined 4A and 4B package to French contractor Technip Energies.
NFPS first phase
Saipem is also executing the EPCI works on the entire first phase of the NFPS project, which consists of two main packages.
Through the first phase of the NFPS scheme, QatarEnergy LNG aims to increase the early gas field production capacity of the North Field offshore development to 110 million tonnes a year.
QatarEnergy LNG awarded Saipem the contract for the EPCI package in February 2021. The package is the larger of the two NFPS phase one packages and has a value of $1.7bn.
Saipem’s scope of work on the EPCI package encompasses building several offshore facilities for extracting and transporting natural gas, including platforms, supporting and connecting structures, subsea cables and anti-corrosion internally clad pipelines.
The scope of work also includes decommissioning a pipeline and other significant modifications to existing offshore facilities.
In addition, in April 2021, QatarEnergy LNG awarded Saipem two options for additional work within the EPCI package, worth about $350m.
QatarEnergy LNG awarded Saipem the second package of the NFPS phase one project, estimated to be worth $1bn, in March 2021.
Saipem’s scope of work on the package, which is known as EPCL, mainly covers installing three offshore export trunklines running almost 300km from their respective offshore platforms to the QatarEnergy LNG north and south plants located in Ras Laffan Industrial City.
Saipem performed the front-end engineering and design work on the main production package of the first phase of the NFPS as part of a $20m contract that it was awarded in January 2019. This provided a competitive advantage to the Italian contractor in its bid to win the package.
https://image.digitalinsightresearch.in/uploads/NewsArticle/15305330/main2239.jpg -
Managing risk in the GCC construction market19 December 2025

The scale and complexity of construction projects under way in the GCC region has attracted global attention. And while large-scale project announcements continue to dominate the headlines, the underlying risks – insufficient financing, harsh contract clauses and a tendency to delay dispute resolution – are often overlooked.
Around the region, many contractors are experiencing difficulties once projects have started because they mistakenly believe they have the necessary in-house skillsets to navigate these complex issues.
MEED has convened a panel of construction consultants and specialists to develop a checklist to help contractors and subcontractors operating in the region to navigate the market’s challenges as the sector moves into 2026.
The proactive steps are aimed at positioning a company so that it can maximise recovery and mitigate threats posed by unresolved claims and poor commercial or contractual administration.
Systemic risk
The regional market is characterised by several systemic issues that amplify risks for contractors.
The fundamental problem is finance. Projects frequently suffer because they are not fully financed from the start, which places financial strain on contractors. This problem is then compounded by the region’s traditional contractual environment, which means disputes are typically not finalised until well after jobs have been completed, creating cash flow problems for contractors, particularly near the end of such projects.
Further financial strain is created by unconditional performance guarantees and retention. The combined requirement for advance payment bonds, a 10% performance bond and sometimes 5%-10% retention represents a significant draw on contractors’ cash flow. The growing tendency of employers to pull bonds further exacerbates the situation.
Many contractors sign up to one-sided contracts so as to secure more work, rather than challenging their employers. Key contractual issues include:
> Unrealistic timelines: Contractors set themselves up to fail by accepting unrealistic timescales on projects, despite the knowledge that the work often takes twice as long.
> Deficient design: A major risk, particularly on high-profile projects, is a lack of specification and design progress. Many contracts, such as the heavily modified Silver Book – a standard contract published by the International Federation of Consulting Engineers (Fidic) for turnkey engineering, procurement and construction projects – presuppose that the contractor has sufficient information to design, build and deliver, even when there is substantive information missing, which renders lump-sum pricing obsolete and inevitably leads to dispute.
> Lowest-bid mentality: Contractors often fail to factor necessary commercial support from legal and claims specialists into their tender figures, making their bid appear more competitive but leaving them without a budget to seek help until it is too late. As a result, projects are managed with budgets that are barely sufficient, rather than being run properly to a successful conclusion.

Supply-chain erosion
The quality and capacity of the subcontractor market, particularly in the mechanical, electrical and plumbing (MEP) field, has eroded significantly.
Some major MEP players have closed or left the market due to underpricing, prompting contractors to call in their performance bonds. This means the region is receiving progressively lower quality for increasingly higher costs, further straining the delivery phase for main contractors.
The risk of subcontractor insolvency is increasing and must now be considered a primary project risk. Contractors should monitor financial health, diversify subcontractor dependencies, challenge allocated resources and secure step-in rights wherever possible.
Many Silver Book contracts in the GCC now include heavily amended, employer-friendly clauses that push design and ground-risk even further onto the contractor – often beyond what Fidic intended. These amendments require careful review and firm pushback.
The GCC remains a market of opportunity, but success in 2026 will belong to contractors that combine disciplined tendering, transparent commercial governance and early issue resolution. Optimism is not a strategy; preparation is.
A 10-point checklist for contractors in 2026
1. Mandate contractual due diligence: Invest time and money into a thorough contract review before signing. Be prepared to challenge harsh clauses, particularly those unfairly allocating risk, such as unknown conditions and full design responsibility. Assume that bespoke rather than standard amendments govern your entitlement. Treat the special conditions as the real contract.
2. Factor commercial support into the budget: Do not omit the cost of essential commercial support from the tender, such as quantity surveyor teams, quantum and delay specialists, legal review and claims preparation. Even if not visible in the front-line figures, this cost – which could be as low as 0.01% of the project value – must be factored in to ensure a budget for early and continuous engagement.
3. Prepare a realistic baseline programme: Stop committing to programmes just to fit the tender. Develop a realistic programme from the start, identifying risks and including necessary code books to track delays early. Consider commissioning an independent programme review at the tender stage – this is common internationally and reduces later arguments about logic, durations and sequencing.
4. Confirm project funding: Ensure that the project financing is fully in position before starting work. Many problems stem from projects that are only partially financed, leading to cash running out near completion. Gone are the days of not asking employers for greater transparency when it comes to funding projects.
5. Establish a strong commercial and claims function: This is where commercial management starts. Set up systems to ensure contractual compliance, including seven-day claim notifications. Variations are inevitable, and proper substantiation is required to secure entitlement – if it is not recorded, it cannot be recovered. Diaries, cost records and notice logs remain the foundation of entitlement.
6. Seek early specialist engagement: Prevention is better than a cure. Bring in specialists early to examine time and cost issues before problems arise. Consultants can provide advice, help set up the correct commercial systems and prevent the escalation of unresolved issues.
7. Adopt an old-school approach to claims management: Technology is useful, but nothing beats resolving issues face to face. Engage directly with the employer’s team regularly to negotiate and agree claims early. This manages the client’s expectations when it comes to budgeting and allows the contractor to secure cash flow sooner. A simple early-warning culture – even when not contractually required – prevents surprises and builds trust with the client.
8. Avoid wasting resources: Focus claims efforts only on events that are actually recoverable and demonstrably critical. Contractors often waste time chasing things that will not be recoverable. Prioritise issues that are both time-critical and clearly fall under the employer’s risk – everything else should be logged but not pursued aggressively.
9. Upskill internal teams: Use specialist involvement as an opportunity to upskill your in-house commercial team. Have them sit alongside specialist consultants to learn proper commercial and contractual administration processes, creating a lasting work-culture benefit.
10. Push for faster dispute resolution: When a dispute arises, advocate for a swift resolution mechanism like adjudication, mediation or expert determination to temporarily resolve cash flow issues. Dispute adjudication boards are intended to give quick, interim decisions. However, if not set up from the start of the project, the process becomes protracted – sometimes taking many months – so fails to provide the cash-flow relief contractors urgently need. Where clients resist adjudication, propose interim binding mediation or expert determinations, or failing this, milestone-based dispute workshops – anything that accelerates getting cash back on site. MEED would like to thank Refki El-Mujtahed of REM Consultant Services (refki@rem-consultant.com; www.rem-consultant.com) for facilitating this article, as well as the following co-contributors:
Aevum Consult | Lawrence Baker | lawrence.baker@aevumconsult.com | www.aevumconsult.com
Decerno Consultancy | Lee Sporle | leesporle@decernoconsultancy.com | www.decernoconsultancy.com
Desimone Consulting | Mark Winrow | Mark.Winrow@de-simone.com | www.de-simone.com
Forttas | Derek O’Reilly & Martin Hall | derek.oreilly@forttas.com & martin.hall@forttas.com | www.forttas.com
IDH Consult | Ian Hedderick | ian.hedderick@idhconsult.com | www.idhconsult.com
White Consulting | Nigel White | nigelwhite@whiteconsulting-me.com | www.whiteconsulting-me.com
https://image.digitalinsightresearch.in/uploads/NewsArticle/15289183/main.gif
Gulf construction holds huge emissions savings potential