Bridging the infrastructure capacity gap

2 April 2024

 

The Middle East and North Africa (Mena) region faces a massive infrastructure gap, with estimates of the shortfall ranging from $75bn to $100bn annually. 

This translates to a cumulative need for $2-2.5tn in infrastructure investment alone by 2050. Bridging this funding gap will require a drastic increase in the level of investment.

In 2020, the World Bank stated that Mena countries needed to spend at least 8.2% of GDP to meet their infrastructure goals through to 2030. However, it had been averaging a spend of just 3% over the prior decade – mostly from public sector funds, alongside multilateral and bilateral debt financing. 

In the intervening years, the additional fiscal constraints imposed by the pandemic and global economic shocks, such as food price inflation, have further hindered regional public spending on infrastructure.

In 2023, the ICD-Refinitiv OIC Infrastructure Outlook valued the region’s outstanding funding gap for infrastructure development at $994bn. The gaps included a $685bn shortfall in investment in road infrastructure; a $111bn funding gap in the water sector; a $65bn gap in telecoms; $47bn in rail; $34bn in port infrastructure; $27bn in electricity network investment; and $25bn in airport infrastructure investment.

This funding gap has real, material impacts on economic prosperity and the prospects for economic growth. The shortfall in investment in road infrastructure, for example, is estimated to cost the Mena region a staggering 5.5% in GDP a year due to inefficiency and accidents, according to the World Bank.

A 2020 study in the Review of Middle East Economics and Finance found that manufacturing firms in the Mena region faced the most severe durations of power outages a month of any region, at 64 hours a month. The perceived value of the business losses due to these power outages was estimated to be around 4.8% of total sales.

Meeting the region’s annual investment needs could generate about 2 million direct jobs and 2.5 million direct, indirect and induced infrastructure-related jobs, according to the OECD. 

This is critical when half of the region’s population is under 24 years old, and 29% are not in employment, education or training, as per the OECD figures. 

Another very tangible infrastructure gap is water capacity. The current annual water shortage in the Mena region is about 42 cubic kilometres, but by 2050, this is projected to grow fivefold to 199 cubic kilometres a year under average climate scenarios and potentially up to 283 cubic kilometres a year under drier conditions. 

These examples highlight the need for substantial investments to bridge the infrastructure deficiencies, ensure the conditions for economic growth, and enhance overall sustainability in the Mena region.

To address the challenges, a comprehensive and multi-faceted approach is needed to incentivise the private sector to support regional infrastructure investments. This includes governments establishing clear policy directions and regulatory frameworks to attract private capital mobilisation.

This funding gap has real, material impacts on economic prosperity and the prospects for economic growth

Technological adaptation

In parallel with the need for governments to proactively improve the conditions for investment, the delivery of future infrastructure requirements also anticipates the adoption of emerging technology.

The goal of many countries to achieve net zero by 2050 also layers further complexity onto existing infrastructure challenges. Regional efforts such as the Middle East Green Initiative and the Circular Carbon Economy framework nevertheless demonstrate the region’s commitment to achieving its net-zero targets.

Reaching net zero will entail building infrastructure that is not just bigger and better, but smarter. At the Global Infrastructure Initiative Summit hosted by McKinsey in Dubai in February, disruptive thinking and technology were identified as vital to the industry’s evolution to meet the needs of a net-zero future. 

Industry leaders called for a nuts-and-bolts overhaul of the industry from the bottom up, with more sustainable alternatives to even centuries-old staples such as Portland cement and rebar. The digitalisation of the industry and the advent of machine-learning and AI also hold huge potential for cutting waste and designing more organic, efficient structures.

The summit highlighted that solving future infrastructure requirements will also likely necessitate overcoming technology hurdles and bringing costs down through research and development, much like the costs of solar power or reverse osmosis desalination have come down in the region. 

Alistair Green, a senior partner in McKinsey’s global infrastructure practice, pointed to the technologies that “are not at conviction, yet: the technology hasn’t even really been proven outside of the lab – like flow batteries, which are an alternative to lithium-ion batteries that can be used for grid-scale storage of long duration, energy storage. This is a technology problem that we’re actively investing in researching in order to bring the costs down.”

Strategy& and engineering consultancy Dar recently reported that sustainable construction technologies can potentially reduce lifecycle emissions from the Mena region’s $2tn construction pipeline through to 2035 by 50%-60% for planned projects. Simple changes can be highly effective, such as incorporating dynamic facades into building designs, which can deliver energy savings of up to 55% in hot countries.

The key is the level of innovation, not the level of technology. In the right application, a low-tech solution may be more efficient. If a low-tech solution is scalable, it is also likely to be more cost-efficient.

In the arid Ait Baamrane region of Morocco, a 2015 project by the NGO Dar Si Hmad has created the world’s largest operational fog-harvesting system, providing potable water using a system of shore-side nets that capture and condense the fog rolling in off the ocean. Launched after a decade of research, the system yields approximately 22 litres of water a day for each square metre of net. It demonstrates that infrastructure does not need to be expensive or complex to have a positive sustainability outcome.

The most pressing need for the Mena region is to improve the attractiveness of its infrastructure investment opportunities

Accessing finance

Without sufficient finance, the effectiveness of infrastructure development, including technological innovation within the sector, will be throttled. The most pressing need for the Mena region is to improve the attractiveness of its infrastructure investment opportunities.

Many governments, especially in the Gulf, have been focused on encouraging the private sector through better and wider public-private partnership (PPP) arrangements, with mixed results. Some countries have struggled to deliver PPP frameworks with sufficient commercial appeal and bankability, a problem usually linked to unattractive risk allocations on the private sector side.

Nevertheless, the mobilisation of PPPs and the creation of more transparent and efficient regulatory frameworks around them are routinely identified as vital for attracting and mobilising private capital.

The delivery of more sustainable infrastructure with a view to net-zero targets also brings the potential to tap into green finance, including green bonds and sharia-compliant sukuk. Projects targeted towards carbon neutrality open themselves up to more diverse avenues of potential finance, including international climate mitigation and adaptation funds.

Multilateral development banks, such as the Asian Infrastructure Investment Bank, support initiatives like the Catalyst Mena Climate Fund 2, which works to mobilise private capital for infrastructure projects focused on renewable energy, sustainable utility schemes and green hydrogen capacity.

Governments in the region are also taking steps to mobilise climate finance by issuing green sovereign bonds and sukuk to fund clean transportation, waste management and green building schemes.

The UAE’s infrastructure development is guided by the Green Agenda 2030 policy framework. Under this aegis, UAE banks, including Mashreq Bank and First Abu Dhabi Bank, have pledged to mobilise $270bn in green financing by 2030 for environmentally impactful projects.

Infrastructure financing schemes are an important step towards drawing more private sector liquidity into the infrastructure industry, but it is also just a start compared to what will be required to deliver the region’s infrastructure needs.

Deep regional inequality also needs to be addressed. While countries such as Saudi Arabia and the UAE may currently be meeting the World Bank’s 8.2% of GDP infrastructure spending targets, the region’s hydrocarbon importers will likely need far more outside assistance.

For the region as a whole to thrive, countries will also need to work together and synergistically to deliver holistic infrastructure roadmaps. Just as the GCC is working together to deliver the Gulf Railway, the Levant and North Africa must work together to develop their shared infrastructure.

Only through cooperation and joint initiatives will the Mena region stand to bridge its infrastructure gap.

Gulf construction holds huge emissions savings potential 

https://image.digitalinsightresearch.in/uploads/NewsArticle/11650914/main.gif
John Bambridge
Related Articles
  • Adnoc Distribution signs deal to enter South Africa

    14 July 2026

    Adnoc Distribution, the fuel retailing business of Abu Dhabi National Oil Company (Adnoc Group), has entered into a definitive agreement to acquire 100% of the share capital of UK energy major Shell’s downstream unit in South Africa.

    The proposed acquisition is estimated to have an enterprise value of approximately $1bn for 100% of the share capital of Shell Downstream South Africa (SDSA), part of Shell South Africa Holdings, prior to adjustment for net debt and working capital.

    The transaction is expected to close in 2027, subject to customary regulatory conditions, other conditions precedent and closing conditions, Abu Dhabi Securities Exchange-listed Adnoc Distribution said.

    Additionally, Adnoc Distribution intends to sell a 28% stake in SDSA to a local empowerment partner and employee stock option plan following completion of the acquisition.

    Furthermore, Adnoc Distribution will enter into a long-term brand licensing agreement upon completion of the acquisition, to retain the Shell brand for retail service stations and lubricants businesses in South Africa.

    BofA Securities acted as the sole financial advisor. A&O Shearman and ENS provided legal counsel to Adnoc Distribution on the transaction.

    SDSA represents Shell’s downstream business in South Africa, including a network of 580 company- and dealer-owned mobility and convenience sites, as well as lubricants, commercial fuels, aviation and marine businesses. The brand had fuel volumes of approximately 3.5 billion litres and operated 360 convenience stores as of 2025.

    The proposed acquisition will mark a step forward in Adnoc Distribution’s international expansion, as well as in its drive to grow its fuel retail presence in Africa.

    South Africa is the fourth country where Adnoc Distribution will operate and follows its acquisition of a 50% stake in TotalEnergies Marketing Egypt in 2023 and the 2018 launch of its retail fuel stations in Saudi Arabia.

    Established in 1973, Adnoc Distribution has 1,032 service stations – 568 in the UAE, 219 in Saudi Arabia and 245 in Egypt, as of 31 March this year.

    As a non-fuel retail leader in the UAE, it operates 386 Adnoc Oasis convenience stores, 37 vehicle inspection centres and other services such as car wash and lube change, and has 400 electric vehicle charging points installed under the E2Go brand in the UAE.

    The company is also a marketer and distributor of fuels to commercial, industrial and government customers throughout the UAE.


    READ THE JULY 2026 MEED BUSINESS REVIEW – click here to view PDF

    Stress test for Gulf aviation; Mixed performance as country outlooks diverge in the Levant; GCC tourism sector pivots from crisis to recovery mode.

    Distributed to senior decision-makers in the region and around the world, the July 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/17664769/main4804.jpg
    Indrajit Sen
  • Expo 2030 Riyadh construction gathers pace

    14 July 2026

     

    Construction activity at the Expo 2030 Riyadh site is accelerating, with Expo Riyadh 2030 Company (ERC) moving to award its first major vertical contracts and advancing infrastructure works across a programme that will eventually require between 50,000 and 70,000 workers at peak.

    Saudi Arabia’s first World Expo runs from 1 October 2030 to 31 March 2031. Riyadh was awarded the hosting rights in November 2023, winning the vote in the first round, and the event is projected to attract more than 40 million visits over its six months. Beyond the event itself, the project carries significant economic weight: ERC, wholly owned by the Public Investment Fund (PIF), expects the construction phase and legacy development to contribute around $64bn to Saudi GDP and generate approximately 171,000 direct and indirect jobs, with the live event contributing a further $5.6bn.

    The masterplan covers 6 million square metres to the north of Riyadh, adjacent to the future King Salman International airport. After the event closes, ERC plans to transform the site into a global village combining retail, food and beverage and an international residential community – meaning every asset being built now is being designed with its post-Expo purpose in mind.

    Infrastructure works under way

    The earliest works on site – bulk earthworks including cut, fill and levelling – have been completed by local contractor Binyah, with millions of cubic metres of material moved to bring the site to design level.

    The programme has now moved into utility infrastructure, which has been split into two packages. Nesma is constructing the primary utility networks – the main corridor running around the site carrying high-voltage power lines, water mains, sewerage and communications – while Al-Yamama is delivering the secondary networks that bring services into the central event area, with construction expected to commence this month.

    Power has been a priority. ERC has worked with the Saudi electricity sector since 2025 to develop the site’s demand profile, and an agreement for permanent supply has been signed. Design and procurement of the main substation and primary power infrastructure are under way, with a contract award expected within weeks and full permanent power – at a capacity of 400MW – targeted approximately 18 months ahead of the event.

    An initial 25MW supply to power site operations and support testing and commissioning is already installed and ready to be energised.

    On water, ERC is finalising an agreement with the Royal Commission for Riyadh City (RCRC), the Saudi Water Authority and the National Water Company, with an announcement expected in Q3 and construction targeted to start in 2027.

    Transport and connectivity

    With more than 42 million visits anticipated over the six-month event, transport connectivity is treated as central to the project’s success. ERC is working with RCRC on a mobility plan that covers several modes. Two road enhancement projects around the airport and along King Salman Road are expected to be announced shortly, increasing capacity on the main arteries approaching the site.

    A dedicated Expo metro station on Riyadh Metro Line 4 – which connects the airport to the city centre – will be built within the site boundary, forming the first stop from the airport towards Riyadh, and providing a direct link for international arrivals.

    A park-and-ride programme using dedicated bus lanes will serve domestic visitors parking at locations across the city.

    A hotel within the fenced Expo site is also nearing contract, with a design agreement close to signature. ERC says the intention is to give guests staying on site “the full experience from early morning when the gates open until late at night when the gates close” – an offer it expects will prove particularly popular with international visitors.

    Pavilions and vertical assets

    The Expo's masterplan is organised around five districts, each echoing one of the event’s sub-themes under its overarching theme of Foresight for Tomorrow: planet, people, technology, collaboration and culture. ERC is responsible for delivering a signature pavilion in each district, plus an iconic structure in the Global Collaboration district and a convention centre intended to serve both the event and Riyadh’s long-term conference market.

    The Kingdom of Saudi Arabia (KSA) Pavilion, one of the centrepieces of the event, is also under ERC’s delivery responsibility. Design work is progressing across all these assets with engineering firms taking concepts through to schematic and detailed design.

    For international participating countries, this edition of the Expo marks a significant departure from previous editions. Rather than grouping lower-income countries into shared halls, all participants will have their own national pavilion.

    “In this edition, we are following the ‘one nation, one pavilion’ model, whereby each country has its own pavilion, and we have a dedicated budget to help up to 100 eligible countries deliver those pavilions,” says Murad Al-Sayed, ERC’s chief delivery officer.

    Contracting strategy

    The contracting approach for vertical assets is being calibrated to the complexity of each building. Less complex assets will be procured on a design-and-build basis.

    For the most complex – the KSA Pavilion and the iconic structure – ERC is using a two-stage model, separating enabling works and substructure from the main contract. This allows construction to begin on site while the main package is finalised and brings contractors into the design process earlier.

    “We are adopting different contracting strategies depending on the asset – its size, complexity and anticipated construction duration,” Al-Sayed says.

    For the KSA Pavilion, enabling and substructure works are already in the market, with an award targeted in Q3, allowing construction to start before the main contract – for which nine tier-one contractors, local and international, have been invited to bid – is awarded towards the end of the year. Packages for the remaining signature pavilions are expected to follow later this year and into 2027.

    On commercial terms, ERC is favouring lump-sum contracts where design maturity allows, with provisional sum or remeasurement provisions used where elements remain in development. A final public realm package, covering site-wide finishing works, remains under design and is expected to be tendered in 2026, sequenced deliberately to be installed last and once only ahead of the event.

    Bidding appetite from the market has been strong. ERC says all tenders issued to date have attracted healthy numbers of qualified bids, reflecting a contracting market that has eased over the past 18 months as several gigaprojects elsewhere in the kingdom have reached completion or had their timelines revised.

    Programme and supply chain

    ERC is targeting completion of major construction by the end of 2029, leaving six to nine months for finishing, snagging and operational testing. To ease the build programme for international participants, ERC is making plots available up to 36 months before the event – around nine to 12 months longer than the industry norm – giving countries more schedule float to complete their pavilions.

    On the supply chain, ERC is leaning heavily on local manufacturers for current infrastructure work, covering piping, cabling, electrical equipment and bulk materials. As construction moves above ground and international participants begin work on their pavilions from 2027 onwards, ERC will make its database of prequalified local contractors, suppliers and consultants available to them through a dedicated one-stop shop – a registration exercise already under way and expected to remain open until the event itself.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17664502/main.gif
    Colin Foreman
  • Masdar reaches financial close on world-first 24/7 solar project

    14 July 2026

    Abu Dhabi Future Energy Company (Masdar) has reached financial close on the world's first gigascale round-the-clock renewable energy project, securing a $5.1bn financing package from a consortium of 13 international and local banks.

    The project, being developed in Abu Dhabi with state offtaker Emirates Water & Electricity Company (Ewec), represents a total capital investment of $6.1bn, with Masdar providing $1bn of equity. It integrates a 5.2GW solar photovoltaic (PV) plant with a 19 gigawatt-hour battery energy storage system, which Masdar says is the largest of its kind in the world.

    The 13 lenders providing the financing are Abu Dhabi Commercial Bank, Abu Dhabi Islamic Bank, France's BNP Paribas, Bank of China, France's Credit Agricole Corporate & Investment Bank, Dubai Islamic Bank, First Abu Dhabi Bank, UK-based HSBC, Germany's KfW Ipex-Bank, France's Natixis, Japan's Sumitomo Mitsui Banking Corporation, UK-based Standard Chartered Bank and France's Societe Generale.

    The independent power project is designed to deliver 1GW of baseload power around the clock, addressing the challenge of solar intermittency by pairing large-scale generation with battery storage. It is intended to serve large energy users requiring 24/7 clean electricity, including data centre operators and technology firms driving artificial intelligence deployment in the region.

    Ewec will act as offtaker under a long-term power purchase agreement, while private offtakers such as data centres will access electricity through back-to-back arrangements.

    India's Larsen & Toubro and Beijing-headquartered PowerChina are handling engineering, procurement and construction works, with PwC Middle East advising Ewec on financial structuring. China's CATL will supply the battery storage system, while Jinko Solar and JA Solar will each provide 2.6GW of PV modules.

    Masdar broke ground on the project in October 2025, and it is expected to be operational in 2027. The scheme will avoid 5.7 million tonnes of carbon dioxide emissions a year and provide enough clean energy to power nearly half a million homes.

    The developer has a diversified portfolio of more than 65GW and has set a target of reaching 100GW of renewable energy capacity by 2030.


    READ THE JULY 2026 MEED BUSINESS REVIEW – click here to view PDF

    Stress test for Gulf aviation; Mixed performance as country outlooks diverge in the Levant; GCC tourism sector pivots from crisis to recovery mode.

    Distributed to senior decision-makers in the region and around the world, the July 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/17664609/main.jpg
    Colin Foreman
  • Jordan tenders IPP8 power project

    14 July 2026

    Jordan’s National Electric Power Company (Nepco) has issued a tender for a contract to develop the 700MW combined-cycle gas turbine (CCGT) power project known as independent power project 8 (IPP8).

    Companies understood to have prequalified include France’s EDF, Saudi Arabia’s Acwa and Egypt’s Orascom Construction. Bids are due in July, although the market expects the closing date may be extended.

    MEED reported in November last year that Nepco had invited developers to submit prequalification documents for IPP8. The project will be developed on a build, own and operate (BOO) basis and will supply power to the national grid under a 25-year agreement.

    Natural gas will serve as the primary fuel, with light distillate as backup. The facility will be connected to Nepco’s 132kV/400kV transmission infrastructure, which will be built separately.

    In April, MEED reported that Nepco had signed an agreement to establish a natural gas supply point for the 700MW IPP7. The agreement was signed with Fajr Jordanian-Egyptian for Natural Gas Transmission and Supply to support fuel provision for the CCGT plant.

    The plant will be developed in partnership with Etihad Development Company, a subsidiary of the UAE’s Etihad Water & Electricity (EtihadWE), following recent approval by the Ministry of Energy & Mineral Resources.

    The IPP7 plant is expected to meet about 10% of Jordan’s electricity demand once operational. It is also intended to enhance the reliability and efficiency of the national power system.

    The project is scheduled to become operational between 2027 and 2028.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17662814/main.jpg
    Colin Foreman
  • Indian firm wins Oman’s Al-Dhahirah economic zone deal

    14 July 2026

    Oman Shapoorji Company, the local branch of India's Shapoorji Pallonji, has won an estimated $67m contract to construct an administrative and commercial buildings complex within the Economic Zone at Al-Dhahirah (Ezad).

    The scope of work includes the construction of an administration building, a commercial centre, a hotel and a health centre.

    The scope also covers the construction of roads, sewers and water, irrigation and landscaping works.

    Oman’s Public Authority for Special Economic Zones & Free Zones (Opaz) tendered the contract.

    In July last year, MEED reported that Opaz had signed seven agreements and memorandums of understanding (MoUs) for the first phase of development of Ezad.

    The zone is located in Al-Dhahirah Governorate in northwestern Oman, on the sultanate’s borders with Saudi Arabia and the UAE. Oman’s Finance Ministry and the Saudi Fund for Development signed an MoU in February 2023 to jointly invest $320m in developing Ezad.

    Among the agreements was a contract awarded by Opaz for the construction of main roads and the surface water drainage system at Ezad, valued at $58m. A consortium of Omani and Saudi contractors won the contract, which had a duration of 24 months.

    Opaz awarded two further contracts for engineering consultancy work to Oman-based Al-Watanyiah United Engineering and Saudi Arabia’s Dar Al-Riyadh. As part of their contracts, both firms were to prepare architectural, structural and infrastructure designs for projects in Ezad; provide technical advice; perform feasibility studies; and assist with approvals.

    Opaz intends to develop 20 square kilometres (sq km) of the total land area allocated to Ezad as part of the first phase of development, with 7.5 sq km of that earmarked for fast-track development.


    READ THE JULY 2026 MEED BUSINESS REVIEW – click here to view PDF

    Stress test for Gulf aviation; Mixed performance as country outlooks diverge in the Levant; GCC tourism sector pivots from crisis to recovery mode.

    Distributed to senior decision-makers in the region and around the world, the July 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/17661726/main.gif
    Yasir Iqbal