Borouge awards output capacity expansion contracts
30 April 2025
Abu Dhabi petrochemicals producer Borouge has awarded contracts for projects that will increase its overall production capacity to 6.6 million tonnes a year (t/y) by 2028.
Germany-headquartered Linde Engineering won a contract for front-end engineering and design (feed) services to upgrade Borouge’s second ethane cracker unit (EU2), adding 230,000 t/y of capacity, which is a 15% increase for the EU2 cracker.
Adnoc Gas and Adnoc Refining, subsidiaries of Abu Dhabi National Oil Company (Adnoc Group), will supply ethane feedstock for the EU2 upgrade project, with completion scheduled for 2028-end.
Separately, Borouge has undertaken a project to expand its PE4 and PE5 polyethylene production units, which will increase their nameplate capacity from 540,000 t/y to 700,000 t/y each.
Abu Dhabi’s Target Engineering Construction Company has won the engineering, procurement and construction contract for this project, which is expected to be completed in the first quarter of 2027.
Borouge expects the two output capacity expansion projects to contribute between $165m and $200m in annual earnings before interest, taxes, depreciation and amortisation (Ebitda).
ALSO READ: Borouge awards hydrogen extraction project contract
Borouge entered operations in 2001, with a production capacity of 450,000 t/y of polyethylene. The Borouge 2 and Borouge 3 expansion projects took the capacity to 2 million t/y and 4.5 million t/y of polyethylene and polypropylene in 2010 and 2014, respectively.
When the under-construction Borouge 4 complex enters operations, Borouge’s overall production capacity will increase significantly from 5 million t/y to 6.4 million t/y, making it the world’s largest single-site polyolefins facility.
The upcoming Borouge 4 polyolefins complex will feature two polyethylene plants – each with a capacity of 700,000 t/y – using the third generation of Borealis Borstar technology. These plants will be supplied by an ethane cracker with a capacity of more than 1.5 million t/y of ethylene, as well as associated ethylene derivatives.
Following the signing of a final investment decision agreement worth $6.2bn by Adnoc and Borealis in November 2021, Borouge awarded the main EPC contracts for the Borouge 4 project in December of that year.
The EPC packages, the winning contractors, their estimated contract values and a brief scope of work are as follows:
- Early works (package one) – Al-Asab General Transport & Contracting (UAE) – site preparation and early civil works
- Ethane cracker (package two) – Technip Energies (France)/Target Engineering (UAE) – $1.58bn – building an ethane cracker with a manufacturing capacity of 1.5 million t/y of ethylene
- Polymers production (package three) – Tecnimont (Italy) – $1.35bn – building two new polyethylene manufacturing plants and a unit to produce 1-hexene, a component in the production of high-performance polyethylene
- Utilities and offsites (package four) – Tecnimont (Italy) – $1.5bn – constructing non-process buildings, roads, infrastructure, internal and external interfaces, tankage systems, flaring systems and utilities, as well as integration of Borouge 4 with the existing facilities
- Second cross-linkable-polyethylene (XLPE) plant (package five) – Tecnimont (Italy) – $350m – building an XLPE plant with a capacity of 100,000 t/y.
Italian contractor Maire Tecnimont executed the front-end engineering and design works for Borouge 4.
Borouge awarded France-based Axens a contract to provide licensed technologies in January 2020. This covered supplying a methyl tertiary butyl ether unit coupled with a 1-butene production unit and 1-hexene unit for the project.
The new Borouge 4 facility will cover an area equivalent to almost 500 football pitches, or more than three times the size of Al-Maryah Island in Abu Dhabi. It will produce enough polyolefins annually to make pipes to supply water to 35 million households.
Borouge Group International
Borouge is the petrochemicals-producing joint venture of Abu Dhabi National Oil Company (Adnoc) and Austrian energy company Borealis. Adnoc owns the majority 56% stake in Borouge, with Borealis holding a 34% stake. The remaining 10% of shares in Borouge trade on the Abu Dhabi Securities Exchange following an initial public offering in June 2022, from which Adnoc Group earned proceeds of $2bn.
In March, Adnoc and Austrian energy company OMV entered into a binding framework agreement to combine their shareholdings in Borouge and Borealis and take control of a greater share of the global chemicals market.
Adnoc has also entered into a share purchase agreement with Canada-based Nova Chemicals Holdings, an indirectly wholly-owned company of Abu Dhabi’s sovereign wealth institution Mubadala Investment Company, for 100% of Nova Chemicals Corporation (Nova).
Adnoc and OMV have also agreed that upon completion of the planned merger of Borouge and Borealis, the new entity – which will be known as Borouge Group International – will acquire Nova for $13.4bn including debt, further expanding its footprint in North America.
Borouge Group International is intended to be headquartered and domiciled in Austria, with regional headquarters in the UAE. In addition, Borouge Group International will hold corporate hubs in Canada’s Calgary, Pittsburgh in the US and Singapore.
The combination of Borouge and Borealis, and the acquisition of Nova, are expected to complete in the first quarter of 2026, subject to regulatory approvals and other customary conditions, Adnoc said.
The acquisition, together with the contribution of the upcoming Borouge 4 petrochemicals project in Abu Dhabi, will create a major polyolefins producer valued at over $60bn. It will be the world’s fourth-largest by nameplate production, with a potential of 13.6 million metric t/y across 62 plants globally.
Exclusive from Meed
-
-
-
Kuwait awards oil services contract16 June 2026
-
-
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Dubai to award $15bn of Al-Maktoum airport contracts this year16 June 2026
Dubai Aviation Engineering Projects (DAEP) will award contracts worth over AED55bn ($15bn) by the end of this year for construction works at Al-Maktoum International airport.
According to a statement published by the Emirates News Agency (Wam), the projects slated for contract awards include “the substructure works for the Western Passenger Terminal, the fourth aircraft concourse building, the automated people mover (APM) system and the baggage handling system, in addition to the superstructure works for the Western Passenger Terminal and the first, second and third aircraft concourses”.
“The packages also encompass the long-span structural frameworks for buildings covering an area of about 1.5 million square metres (sq m), infrastructure works for the southern airfield area, as well as power generation and district cooling plants supporting the construction programme,” the statement added.
“The award of facade and roofing packages is also planned during the course of this year,” said Suzanne Al-Anani, CEO of DAEP.
DAEP has already awarded contracts valued at about AED13bn, with construction works currently under way on several airport packages. These include enabling works, the second runway, and the initial structural foundations for passenger terminals and gates.
Construction progress
In May last year, MEED exclusively reported that DAEP had awarded a AED1bn ($272m) deal to UAE firm Binladin Contracting Group to construct the second runway at the airport.
The enabling works on the terminal are also ongoing and are being undertaken by Abu Dhabi-based Tristar E&C.
Construction on the project’s first phase is expected to be completed by 2032.
Construction on substructure works began in November last year, when DAEP formally selected a contractor to deliver the package.
The government approved the updated designs and timelines for its largest construction project in April 2024.
In a statement, the authorities said the plan is for all operations from Dubai International airport to be transferred to Al-Maktoum International within 10 years.
According to an official description on DAEP’s website, the expanded airport’s West Terminal will be a seven-level, 800,000-square-metre facility with an annual capacity of 45 million passengers.
It will be the second of three terminals at Al-Maktoum International airport, linked to the airside by a 14-station APM system.
In September 2024, MEED exclusively reported that a team comprising Austria’s Coop Himmelb(l)au and Lebanon’s Dar Al-Handasah had been confirmed as the lead masterplanning and design consultants on the expansion of Al-Maktoum airport.
The airport’s construction is planned to be undertaken in three phases. The airport will cover an area of 70 square kilometres (sq km) south of Dubai and will have five parallel runways, two terminal buildings, seven concourses and 430 aircraft gates
It will be five times the size of the existing Dubai International airport and will have the world’s largest passenger-handling capacity of 260 million passengers a year. For cargo, it will have the capacity to handle 12 million tonnes a year.
https://image.digitalinsightresearch.in/uploads/NewsArticle/17289093/main.jpg -
Eleven contractors bid for Yanbu seawater cooling project16 June 2026

Eleven contractors have submitted bids for a contract to build a seawater cooling system in Yanbu Industrial City, Saudi Arabia.
The estimated $70m project is being developed by the Royal Commission for Jubail & Yanbu (RCJY).
The project involves the construction of a seawater supply and re-cooling pipeline system serving industrial operations in the petrochemical area. The scheme is intended to reduce the need for individual cooling facilities at separate sites.
The engineering, procurement and construction (EPC) contract was tendered on 8 March, and bids were submitted on 9 June.
The bidders include:
- Al-Fateh International Company for Water & Electricity (Saudi Arabia)
- Al-Yamama Company (Saudi Arabia)
- Alsaad General Contracting (Saudi Arabia)
- Aqua Arabia Water Company (Saudi Arabia)
- China Harbour Engineering Company (China)
- Masco Group (Saudi Arabia)
- Mofarreh Alharbi & Partners (Saudi Arabia)
- Saad Ali Al-Essa Group (Saudi Arabia)
- Saudi Services for Electro Mechanic Works (Saudi Arabia)
- Sayegh Group of Companies (Saudi Arabia)
- Union General Contractor (Saudi Arabia)
The scope of work includes seawater intake structures and screening facilities, a pumping station, manholes and valves, a control building, seawater pumps, strainers and inlet and outlet headers.
The contract also covers the installation of cooling water supply and return transmission pipelines, as well as a discharge outfall and diffuser system.
According to MEED Projects, RCJY has awarded construction contracts for three seawater cooling projects in 2026.
Mofarreh Alharbi & Partners secured a $40m seawater cooling system project in Jubail 2, while China Geo-Engineering Corporation won a contract to upgrade the seawater cooling network in Ras Al-Khair Industrial City.
Local firm Bin Jarallah Group of Companies was also awarded a contract to expand the seawater cooling network in Jubail’s Plaschem Area.
Meanwhile, Beijing-headquartered China Harbour Engineering Corporation is continuing construction on another project for RCJY.
The project comprises a seawater cooling system catering to Jizan City for Primary & Downstream Industries. Commissioning is expected later this year.
https://image.digitalinsightresearch.in/uploads/NewsArticle/17288985/main.gif -
Kuwait awards oil services contract16 June 2026
National Petroleum Services Company (Napesco) has secured a contract worth KD11.94m ($38.8m) to provide cementing and associated services for drilling and workover operations on unconventional wells in Kuwait.
The contract has been awarded by the state-owned upstream operator Kuwait Oil Company (KOC) and has a five-year term, according to a statement from Napesco.
Under the agreement, Napesco will provide integrated cementing solutions designed to support well integrity, optimise drilling performance, and enhance operational efficiency across the client’s unconventional exploration and production programme.
Kuwait’s oil and gas sector is currently in the midst of a major crisis as disruption to shipping through the Strait of Hormuz has dramatically reduced the volume of exported crude oil.
The disruption to shipping is also creating significant challenges to construction projects in the oil and gas sector, which normally import equipment and materials through the Strait of Hormuz.
https://image.digitalinsightresearch.in/uploads/NewsArticle/17218811/main1619.jpg -
HKN Energy starts to operate Syria’s Rmeilan oil fields16 June 2026

Register for MEED’s 14-day trial access
US-based HKN Energy is starting operations on the ground at Syria’s Rmeilan fields in Al-Hasakah Governorate, according to industry sources.
The development comes as Syria is trying to fast-track the conversion of memorandums of understanding (MoUs) signed with oil companies to concrete contracts.
Speaking at a conference in Washington on 9 June, the chief executive of state-owned Syria Petroleum Company (SPC), Youssef Qablawi, said that HKN had recently converted an MoU into a finalised deal and was preparing to start operations in Syria.
Qablawi did not mention which assets HKN would be operating in Syria, but sources say it is starting operations on the ground at the Rmeilan fields.
Some work related to the company’s activities in Syria is currently being carried out in HKN’s office in Erbil, in the Kurdish region of Iraq, sources said.
The Syrian government took control of the Rmeilan oil fields earlier this year after a military operation.
The group of fields is considered to be one of Syria’s largest oil assets and contains more than 1,300 oil wells.
The field is said to have produced up to 120,000 barrels a day (b/d) before civil war broke out in Syria in 2011.
Output later fell by nearly 85% after hundreds of wells went offline, either due to war damage or lack of maintenance.
Prior to the military operation by Syria’s army earlier this year, the field was held and administered by the Kurdish-led Syrian Democratic Forces (SDF).
Foreign interest in Syria’s oil and gas sector is growing as the government moves to revive the industry and elevated global energy prices improve the economics of new developments.
A series of agreements signed in recent months has attracted some of the world’s largest energy companies, raising expectations that investment and production could accelerate.
New deals
Speaking at the conference in Washington earlier this month, Qablawi said he was planning to sign a contract with ConocoPhillips today, 16 June.
He said it would be the largest contract signed by SPC since its establishment in October last year.
Qablawi also said he hoped to convert an MoU with the US-based oil company Chevron into a signed contract before the end of July.
Qablawi said the country was forecasting increases in both oil and gas production and predicted it would produce 1 million b/d by 2030.
The chief executive said that previously unexplored blocks in the country held “huge” reserves that could be developed.
Chevron is interested in making investments in onshore production in the country, according to Qablawi.
Downstream projects
Syria is planning several downstream projects.
Under current plans, the country’s Baniyas refinery will be shut down for major maintenance in July.
The maintenance will dramatically increase the refinery’s capacity to 130,000 b/d, according to Qablawi.
Currently, it is operating at a rate of 90,000-95,000 b/d.
The refinery is expected to be brought back online in October this year.
Syria is also planning to develop a new refinery, which will produce more than 200,000 b/d, and is expected by SPC to come online within four years.
Under current plans, the front-end engineering and design (feed) for the new refinery will start in the fourth quarter of this year.
“Syria will be exporting refined products within three years [of starting the feed],” Qablawi said. “After we have finished the construction of the new refinery.”
Gas development
In April, SPC signed a formal contract with Saudi Arabia’s ADES to increase gas production in central Syria.
The contract is focused on developing five central gas fields:
- Abu Rabah
- Qamqam
- North Al-Faydh
- Al-Tiyas
- Zumlat Al-Mahar
The deal aims to increase Syria’s domestic gas production by up to 50% within a year.
Speaking on 9 June, Qablawi said that ADES was mobilising for that project.
Pipeline planning
Syria is involved in several major pipeline projects, including plans to restore the pipeline from Kirkuk in Iraq to Baniyas in Syria.
Qablawi said that under current plans, the contracts for this pipeline would be tendered using the build-operate-transfer (BOT) contract model.
“We are going to pick the best company for Syria to construct this pipeline,” he said.
Syria has awarded an engineering, procurement and construction contract for an extension to the existing Arab Gas Pipeline.
The new section extends 185 kilometres from Aleppo to Homs and is being fully funded by SPC.
https://image.digitalinsightresearch.in/uploads/NewsArticle/17218785/main.jpg -
Dubai extends deadlines for Jebel Ali sewage treatment plants16 June 2026

Dubai Municipality has extended the deadlines for two major water infrastructure projects at Jebel Ali, according to sources.
The first involves the expansion of the Jebel Ali sewage treatment plant (STP) phases one and two, which is being delivered under an engineering, procurement and construction (EPC) model.
Contractors have been given until 25 June to submit offers to design, build and commission an upgraded facility, estimated to cost $300m.
The facility will be capable of treating an additional sewage flow of 100,000 cubic metres a day (cm/d). The previous deadline was 11 June.
Located on a 670-hectare site in Jebel Ali, the original wastewater facility has a treatment capacity of about 675,000 cm/d following the completion of phase two in 2019, combining approximately 300,000 cm/d from phase one and 375,000 cm/d from phase two.
The main element of the expansion involves modifications to the secondary treatment process at Jebel Ali STP phase two.
UK-headquartered KPMG and UAE-based Tribe Infrastructure are serving as financial advisers on the project.
Phase 3 PPP
The second and larger of the two projects involves the Jebel Ali STP expansion – phase 3.
The DS150/3 project will be delivered under a public-private partnership (PPP) model on a design, build, finance, own, operate and transfer basis.
Dubai Municipality issued a request for qualifications in May, with an initial deadline of June 18. That deadline has been extended to 16 July, a source said.
The project involves the development of a new water resource recovery facility with a treatment capacity of up to 1 million cm/d.
It is being procured through Dubai Municipality’s Sewerage and Recycled Water Projects Department and will be delivered through a two-stage operational approach over a 30-year concession period.
UK-headquartered Deloitte is acting as financial adviser, Aecom as technical adviser and CMS as legal adviser.
Dubai Municipality said the project will also include additional land uses and community-focused amenities as part of broader sustainability and urban integration objectives.
https://image.digitalinsightresearch.in/uploads/NewsArticle/17212607/main.jpg