Borouge awards output capacity expansion contracts

30 April 2025

Abu Dhabi petrochemicals producer Borouge has awarded contracts for projects that will increase its overall production capacity to 6.6 million tonnes a year (t/y) by 2028.

Germany-headquartered Linde Engineering won a contract for front-end engineering and design (feed) services to upgrade Borouge’s second ethane cracker unit (EU2), adding 230,000 t/y of capacity, which is a 15% increase for the EU2 cracker.

Adnoc Gas and Adnoc Refining, subsidiaries of Abu Dhabi National Oil Company (Adnoc Group), will supply ethane feedstock for the EU2 upgrade project, with completion scheduled for 2028-end. 

Separately, Borouge has undertaken a project to expand its PE4 and PE5 polyethylene production units, which will increase their nameplate capacity from 540,000 t/y to 700,000 t/y each.

Abu Dhabi’s Target Engineering Construction Company has won the engineering, procurement and construction contract for this project, which is expected to be completed in the first quarter of 2027. 

Borouge expects the two output capacity expansion projects to contribute between $165m and $200m in annual earnings before interest, taxes, depreciation and amortisation (Ebitda).

ALSO READ: Borouge awards hydrogen extraction project contract

Borouge entered operations in 2001, with a production capacity of 450,000 t/y of polyethylene. The Borouge 2 and Borouge 3 expansion projects took the capacity to 2 million t/y and 4.5 million t/y of polyethylene and polypropylene in 2010 and 2014, respectively. 

When the under-construction Borouge 4 complex enters operations, Borouge’s overall production capacity will increase significantly from 5 million t/y to 6.4 million t/y, making it the world’s largest single-site polyolefins facility.

The upcoming Borouge 4 polyolefins complex will feature two polyethylene plants – each with a capacity of 700,000 t/y – using the third generation of Borealis Borstar technology. These plants will be supplied by an ethane cracker with a capacity of more than 1.5 million t/y of ethylene, as well as associated ethylene derivatives.

Following the signing of a final investment decision agreement worth $6.2bn by Adnoc and Borealis in November 2021, Borouge awarded the main EPC contracts for the Borouge 4 project in December of that year.

The EPC packages, the winning contractors, their estimated contract values and a brief scope of work are as follows:

  • Early works (package one) – Al-Asab General Transport & Contracting (UAE) – site preparation and early civil works
  • Ethane cracker (package two) – Technip Energies (France)/Target Engineering (UAE) – $1.58bn – building an ethane cracker with a manufacturing capacity of 1.5 million t/y of ethylene
  • Polymers production (package three) – Tecnimont (Italy) – $1.35bn – building two new polyethylene manufacturing plants and a unit to produce 1-hexene, a component in the production of high-performance polyethylene
  • Utilities and offsites (package four) – Tecnimont (Italy) – $1.5bn – constructing non-process buildings, roads, infrastructure, internal and external interfaces, tankage systems, flaring systems and utilities, as well as integration of Borouge 4 with the existing facilities
  • Second cross-linkable-polyethylene (XLPE) plant (package five) – Tecnimont (Italy) – $350m – building an XLPE plant with a capacity of 100,000 t/y.

Italian contractor Maire Tecnimont executed the front-end engineering and design works for Borouge 4.

Borouge awarded France-based Axens a contract to provide licensed technologies in January 2020. This covered supplying a methyl tertiary butyl ether unit coupled with a 1-butene production unit and 1-hexene unit for the project.

The new Borouge 4 facility will cover an area equivalent to almost 500 football pitches, or more than three times the size of Al-Maryah Island in Abu Dhabi. It will produce enough polyolefins annually to make pipes to supply water to 35 million households.

Borouge Group International

Borouge is the petrochemicals-producing joint venture of Abu Dhabi National Oil Company (Adnoc) and Austrian energy company Borealis. Adnoc owns the majority 56% stake in Borouge, with Borealis holding a 34% stake. The remaining 10% of shares in Borouge trade on the Abu Dhabi Securities Exchange following an initial public offering in June 2022, from which Adnoc Group earned proceeds of $2bn.

In March, Adnoc and Austrian energy company OMV entered into a binding framework agreement to combine their shareholdings in Borouge and Borealis and take control of a greater share of the global chemicals market.

Adnoc has also entered into a share purchase agreement with Canada-based Nova Chemicals Holdings, an indirectly wholly-owned company of Abu Dhabi’s sovereign wealth institution Mubadala Investment Company, for 100% of Nova Chemicals Corporation (Nova).

Adnoc and OMV have also agreed that upon completion of the planned merger of Borouge and Borealis, the new entity – which will be known as Borouge Group International – will acquire Nova for $13.4bn including debt, further expanding its footprint in North America.

Borouge Group International is intended to be headquartered and domiciled in Austria, with regional headquarters in the UAE. In addition, Borouge Group International will hold corporate hubs in Canada’s Calgary, Pittsburgh in the US and Singapore.

The combination of Borouge and Borealis, and the acquisition of Nova, are expected to complete in the first quarter of 2026, subject to regulatory approvals and other customary conditions, Adnoc said.

The acquisition, together with the contribution of the upcoming Borouge 4 petrochemicals project in Abu Dhabi, will create a major polyolefins producer valued at over $60bn. It will be the world’s fourth-largest by nameplate production, with a potential of 13.6 million metric t/y across 62 plants globally.

https://image.digitalinsightresearch.in/uploads/NewsArticle/13786125/main.jpg
Indrajit Sen
Related Articles
  • Eni completes $1bn Libya gas project

    20 October 2026

    Register for MEED’s 14-day trial access 

    Libya’s Mellitah Oil & Gas Company, a joint venture of Libya’s National Oil Corporation (NOC) and Italian oil and gas company Eni, has achieved mechanical completion on its Bouri gas utilisation project (GUP).

    In a statement, Eni said that start-up procedures are currently under way, enabling the recovery of associated gas produced from the Bouri field, which is located in Libya’s western offshore area.

    The main contract for the project, worth $1bn, was awarded to Italy’s Saipem in August 2023.

    The project involved the construction and installation of the new Bouri gas recovery module and related tie-in infrastructure that enables the recovery and treatment of gas that was previously flared.

    In its statement, Eni said that the project “represents one of the most significant emissions reduction initiatives in Libya’s energy sector”.

    It also said that it would contribute to improving the environmental performance of the country’s production system by reducing greenhouse gas emissions by approximately 1.5 million tonnes of carbon dioxide a year.

    The recovered gas will be supplied to the domestic market, adding about 700 million cubic metres a year and helping meet demand from the power generation sector.

    The project will also support additional gas volumes available for export to Europe through the GreenStream pipeline.

    Eni said: “The start-up of the Bouri GUP confirms the joint commitment of Eni and NOC to the development of Libya’s energy sector through initiatives that combine production growth, operational efficiency and environmental stewardship.

    “The project is part of a broader strategy aimed at enhancing the value of the country’s gas resources while reducing the emissions intensity of upstream activities.”

    Other key projects currently under way in Libya include the A&E Structures Project, which is focused on bringing new offshore gas resources onstream for both the domestic market and exports, as well as initiatives aimed at upgrading and optimising gas production and transportation infrastructures.

    Eni has been present in Libya since 1959, and the company’s equity production in the country in 2025 amounted to approximately 162,000 barrels of oil equivalent a day.

    The Bouri offshore field is part of Libya’s Block NC-41, located 120 kilometres north of the Libyan coast in the Mediterranean Sea.

    It was first discovered in 1976 at a depth of 8,700 feet. It is estimated to contain 4.5 billion barrels in proven recoverable crude oil reserves and 3.5 trillion cubic feet of associated natural gas, with an annual production potential of 6 billion cubic metres.

    The first development phase, costing nearly $2bn, was completed in 1990.

    This was immediately followed by a second development phase, which entailed drilling 55 new wells and constructing three additional platforms. Production began from the oil platforms DP4 and DP3 in August 1998.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/20770288/main3529.jpg
    Wil Crisp
  • Diriyah Company tenders East Wadi bridge

    20 October 2026

     

    Saudi Arabia’s Diriyah Company has invited contractors to bid on the construction of the DG II East Wadi Bridge, a key crossing within Riyadh’s Diriyah master development.  

    The bridge will provide an arterial road connection linking the Diriyah Gate Phase 2 (DG II) Infrastructure Package 1 and Package 2 zones.  

    The project scope involves the construction of a 100-metre clear-span, 44-metre-wide, single-span post-tensioned concrete bridge structure with integrated abutments and four architectural towers.  

    The contract also encompasses approach slabs, access roads, pavements, associated earthworks, architectural finishes and cladding, mechanical, electrical and plumbing installations, utility interfaces, bridge parapets, vehicle restraint systems, waterproofing, testing and commissioning, and associated temporary works.  

    The client will supply the detailed engineering design, and the selected contractor will develop the construction methodology.

    Diriyah Company issued the prequalification tender on 14 September, with submissions due by 10 December.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/20769223/main.png
    Yasir Iqbal
  • Kuwait selects firms for power works at housing projects

    20 October 2026

     

    Kuwait’s Public Authority for Housing Welfare (PAHW) has appointed contractors for works covering the supply and installation of 132kV underground cables at South Sabah Al-Ahmad Residential City.

    The contracts relate to engineering, procurement and construction (EPC) packages for works for 28 main 132/11kV substations across four phases.

    According to sources, Egypt’s Elsewedy Cables has won contracts for phases 1 and 3, while China’s TBEA Shandong Luneng Taishan Cable Company has won contracts for phases 2 and 4 of the development.

    In April, MEED reported that PAHW had received at least five bids for each of the first two packages, with Elsewedy and TBEA offering $44m and $40.5m, respectively.

    The first contract (phase 1) covers seven substations in zones N9, N7 and N5. The second contract (phase 2) covers seven substations in zones N10 and N5.

    PAHW issued two further 132kV underground cable tenders for the South Sabah Al-Ahmad residential development at the end of May, as reported by MEED.

    This included a contract (phase 3) covering the supply, extension and maintenance of 132kV underground cables linked to seven substations serving the N5, N6, N8 and N10 districts. Egytech Cables, a subsidiary of Elsewedy, submitted an offer of $39.95m, the lowest of four bids.

    The other contract (phase 4) covers the supply, extension and maintenance of 132kV underground cables feeding eight main transformer substations serving the N1, N6 and N11 districts. 

    MEED reported in July that TBEA had submitted an offer of $44.06m for the contract.

    South Saad Al-Abdullah 

    Separately, PAHW has appointed contractors for power transmission works at the South Saad Al-Abdullah residential development.

    The local firm Sayed Hamid Behbehani & Sons has won a contract to supply, install and maintain 10 main 132/11kV transformer substations for the development’s third phase. 

    Another local firm, Al-Ahleia Switchgear, has won a contract to supply, install and maintain 10 main 132/11kV transformer substations for the project’s fourth phase. 

    As reported in August, the contractors submitted bids of $104.2m and $103.3m, respectively.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/20761431/main.jpg
    Mark Dowdall
  • Taqa moves forward with Mirfa-Liwa scheme

    20 October 2026

     

    Taqa Transmission and Taqa Distribution are advancing a major water transmission and distribution scheme serving Mirfa, Madinat Zayed and Liwa in Abu Dhabi, sources told MEED.

    The project, originally estimated to cost $775m, has been in procurement for several years. According to sources, a request for proposals has been issued, with bids due on 5 January 2027.

    The initial submission deadline was 11 November, before it was extended.

    The project was previously tendered in December 2024, with contractors submitting bids for transmission and distribution packages in January 2025.  As of August, the bids were still under evaluation. It is unclear whether the latest tender represents a revised procurement process for the same scheme.

    The project comprises a water transmission system from Mirfa, alongside distribution networks serving farms and settlements in the western region.

    According to details seen by MEED, the latest scope includes a pumping station at Mirfa with a capacity of 128 million imperial gallons a day, about 125 kilometres of transmission pipelines to Muzairah, with branches to Madinat Zayed and Liwa Summit, and storage tanks at the three locations.

    The distribution network is divided into four geographic clusters covering Liwa East, Liwa West, Madinat Zayed and Seih Al-Kheir. The works include associated pipelines, pumping stations and storage facilities.

    The earlier procurement was structured as an engineering, procurement and construction scheme, divided between transmission and distribution works.

    As MEED understands, the latest tender is being pursued under a design, build and operate model, which extends the contractor’s responsibilities to operating the infrastructure after construction.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/20758109/main2934.jpg
    Mark Dowdall
  • Contractors prepare prices for Adnoc Onshore field facilities project

    20 October 2026

     

    Contractors are preparing commercial bids for Adnoc Onshore’s project to build on-plot and off-plot facilities at the Rumaitha and Shanayel fields in Abu Dhabi’s North East Bab oil field cluster.

    The project will enhance and sustain crude output at Rumaitha and Shanayel at 45,000 barrels a day (b/d), supporting Adnoc’s Accelerated Integrated Programme 5 (AiP5) drive to lift capacity to 5 million b/d by 2027.

    Adnoc Onshore issued the main tender for engineering, procurement and construction (EPC) works on 19 June. Contractors submitted technical bids by 5 August, sources told MEED.

    The on-plot works include adding a crude processing train, produced water treatment and reinjection systems, surface water pumps, and multi-stage gas compression and dehydration units. Works also include utilities, safety and control systems, modifications to existing Phase 1 units and 220kV power infrastructure.

    The off-plot scope includes installing and tying in new gas-lifted producer and water-injection wells, as well as building and expanding wellhead clusters. Contractors will also lay crude-gathering, water-injection and gas-export pipelines connecting to the Adnoc Gas network and extend 33kV overhead power lines across the fields.

    The tender follows Adnoc Onshore’s shift in strategy for the wider North East Bab development – comprising the Al-Nouf, Rumaitha and Shanayel fields – after scrapping an earlier engineering, procurement and construction management (EPCm) approach. MEED reported in December that the operator had cancelled an off-plot EPCm contract awarded to China Petroleum Engineering & Construction Corporation (CPECC) in October 2024. Adnoc later cancelled a separate on-plot EPCm tender that it received bids for in the second quarter of 2025.

    In addition to the North East cluster, Adnoc Onshore continues to make progress on EPC works for another similar project to build off-plot facilities at the South East cluster of oil fields in Abu Dhabi, which is also integral to Adnoc Group’s AiP5 campaign.

    The South East cluster comprises the Asab, Mender, Qusahwira, Sahil and Shah fields and accounts for approximately a third of Adnoc Onshore’s oil production capacity.

    MEED previously reported that Adnoc Onshore awarded CPECC the EPC works for the South East off-plot facilities project, with the contract value estimated at around $1.2bn.

    CPECC is also performing EPC works on the South East on-plot facilities project in a consortium with Greece-headquartered Archirodon. Adnoc Onshore awarded an estimated $1.5bn contract for that project to the consortium in December 2024, with EPC works scheduled for completion in 2027.

    ALSO READ: Adnoc Onshore seeks bids for Bu Hasa field EOR project

    https://image.digitalinsightresearch.in/uploads/NewsArticle/20757699/main.jpeg
    Indrajit Sen