Bigger is better for construction
23 December 2024

Nothing encapsulates a buoyant construction market better than signing a contract to complete the world’s tallest tower. That happened on 2 October 2024, when Saudi Binladin Group (SBG) was awarded a $2bn contract to complete the 1,000-metre-plus Jeddah Tower.
The award was significant in many ways. It was a revival of the tower project, which has been on hold since 2018, and it was also a comeback for SBG after years of financial stress that had led many in the market to think it would never win another major construction deal.
On a macro level, the construction deal confirmed that the region is home to the world’s most daring and challenging construction projects.
More importantly, these projects are more than just aspirations; they are real projects that are being built.
Biggest contracts
While Jeddah Tower was the most symbolic contract award in 2024, at $2bn, it was not the largest. That accolade went to the Italian contractor WeBuild when it was awarded a $4.7bn contract for the construction of the three dams at the Trojena mountain resort at Neom in January.
Like Jeddah Tower, the project is a challenging one. Time pressure is a key issue. Trojena has been selected to host the 2029 Asian Winter Games, and the reservoir will be used to make the snow for the event. This means the dams must be completed and the reservoir filled well in advance.
The project is also technically complex. The main dam will have a height of 145 metres and will be 475 metres long at its crest. Inside the reservoir there will be a kidney-shaped dam that will house an attraction known as the Enchanted Forest, which will be connected to the rest of the Trojena development by an underwater tunnel.
WeBuild’s involvement also highlighted that international contractors, after sitting on the sidelines for a number of years, are playing an active role in the Saudi construction market.
One market segment that has attracted strong interest is building stadiums, which like Trojena have to be completed for football tournaments with fixed dates: the 2027 Asian Games and the 2034 Fifa World Cup.
In October, Spain’s FCC in joint venture with the local Nesma & Partners secured a $1bn contract to build the Prince Mohammed Bin Salman Stadium at the Qiddiya City development on the outskirts of Riyadh.
Earlier in the year, a joint venture of Belgian contractor Besix and the local Albawani was awarded the contract to build the Aramco football stadium in Al-Khobar, and Beijing-headquartered China Railway Construction Corporation and local contractor Sama Construction for Trading & Contracting won the contract to construct the Jeddah Central stadium project.
Outside of Saudi Arabia, there were only two contract awards valued at over $1bn and both were in the UAE emirate of Abu Dhabi.
In January, a $1.2bn contract to complete phases two and four at the Saadiyat Lagoons project was awarded to a joint venture of two Abu Dhabi-based contractors, Trojan Construction Group and Arabian Construction Company.
The other $1bn-plus deal was a $1.4bn contract to complete dredging and marine works for the Nisi Island development, which was awarded to the local NMDC Group.
These deals were highlights in what was a strong year for the rest of the market. In total, according to regional projects tracker MEED Projects, there were $67.9bn of construction contract awards by the end of October 2024. If the trajectory is maintained until the end of the year, it will result in about $81.4bn of awards, which is lower than the $96.9bn of awards recorded in 2023, but still higher than any of the eight years from 2015 to 2022.
Market challenges
Replicating the record-breaking performance of 2023 was never going to be easy, especially after Riyadh warned that its spending would be more targeted at the end of 2023. Those comments, made by the finance minister, set the tone for 2024, which proved to be a year with plenty of contract awards, but without the apparent carefree attitude to spending that characterised 2023.
The other challenge with following on from a bumper year is supply chain constraints. With full order books, contractors and suppliers have lost some of the appetite that they had for new work in 2023. The result of this for project clients has been difficulties in attracting enough bidders, and when bids are submitted, the offers are often not competitively priced.
These challenges have been felt most acutely by projects in the remote regions of Saudi Arabia. The issue is so prevalent at Neom that there is now a phenomenon known as ‘Neom inflation’, which implies that the $500bn gigaproject in the remote northwestern corner of the kingdom has its own unique inflation rate.
These regional issues have added to the international supply chain constraints that have been felt since the Covid-19 pandemic and, more recently, during the conflict in Gaza and threats to shipping lanes in the Red Sea.
Addressing challenges
The market has responded to these challenges. In Saudi Arabia, the Public Investment Fund (PIF) invested in four of the kingdom’s largest general contractors in 2023. Then, in February 2024, the sovereign wealth vehicle announced that it had, together with the National Infrastructure Fund, introduced a new contractor financing programme, designed to strengthen the construction sector’s finances.
The programme aims to provide contractors with finance solutions to help improve their cash flows.
Developers have also been improving their contract terms and, crucially, working to ensure payments are processed on time – a move that should also help improve contractor cash flows.
The PIF-backed development companies have also been actively working on attracting new companies to Saudi Arabia. They have been travelling the world on roadshows to attract more contractors and suppliers to projects in the kingdom.
These roadshows have been highlighting the volume and scale of the opportunities in Saudi Arabia, and have shown that the kingdom offers long-term opportunities for companies that come and invest in the market.
In the UAE, Abu Dhabi has invested heavily in its construction supply chain. With its government-controlled investment vehicles and a series of interconnected mergers and acquisitions, Abu Dhabi and its ruling family now own the emirate’s key contracting companies and the suppliers of vital raw materials such as cement and steel.
These national champions shield Abu Dhabi from many, but not all, supply chain challenges that have impacted projects in other markets.
Meanwhile, in Dubai, where the real estate market is driving construction, private sector developers are courting contractors to work on their projects.
As private entities, they are not bound by the procurement regulations that government or government-controlled developers have, so they have been offering directly negotiated deals to help guarantee that their projects are delivered on time.
2025 outlook
Unless the market dynamics shift dramatically, the market will likely face many of the same challenges in 2025.
One of the overriding fears is a sharp slowdown in project spending in Saudi Arabia. This has happened before and is a valid concern, and the market has already shown signs of plateauing in some areas.
This is most noticeable when contract awards for the five official gigaprojects – Diriyah, Neom, Qiddiya, Red Sea Global and Roshn – are examined. After a sharp ramp-up in awards from 2020 to 2023, the pace of contract awards levelled off in 2024, which reflects budgetary concerns within the development companies and the PIF, and the market’s ability to take on such large volumes of new work.
With budgets under pressure, developers in Saudi Arabia are increasingly looking for investment to help fund their projects. The success of these efforts will determine how buoyant the market in the kingdom remains over the long term.
Even if investment comes in, it will take time, which means there will likely be a degree of conservatism from development companies in 2025. This was signalled in mid-November, when Neom, while announcing the exit of CEO Nadhmi Al-Nasr and the appointment of Aiman Al-Mudaifer as acting CEO, said: “As Neom enters a new phase of delivery, this new leadership will ensure operational continuity, agility and efficiency to match the overall vision and objectives of the project.”
While there may be a pause in spending on some of the Saudi gigaprojects, other schemes continue to underpin the performance of the construction market.
Oil prices remain supportive of government spending on projects across the Gulf, and for the private sector, in markets such as the UAE, real estate projects continue to move into construction as developers rush to deliver units to investors and capitalise on the ongoing strength of the property market.
Exclusive from Meed
-
Riyadh tenders Expo 2030 Adaptation and Innovation Pavilion21 October 2026
-
Mubadala Bio lands Lilly logistics deal21 October 2026
-
Chinese/local joint venture wins Qiddiya stadium facade21 October 2026
-
Zamil Steel wins $82m Qiddiya tennis centre contract21 October 2026
-
Eni starts to bring gas processing facility online in Egypt21 October 2026
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Riyadh tenders Expo 2030 Adaptation and Innovation Pavilion21 October 2026

Register for MEED’s 14-day trial access
Expo 2030 Riyadh has tendered the design-and-build main contract for the Adaptation and Innovation Pavilion in the exhibition’s Technology District.
The pavilion will be built on a plot of at least 12,710 square metres and will feature a two-level basement, ground-level public areas, an elevated skywalk, visitor experience areas, food and beverage outlets, retail space, VIP facilities, offices, back-of-house areas, exhibition spaces, an amphitheatre and a resonance hall.
The facility is being designed to accommodate a minimum of 20,000 visitors a day at peak periods, with an anticipated average of about 15,000 visitors a day. The project targets LEED Gold certification.
The tender was issued on 1 October, with bids due on 6 January 2027.
The design-and-build contractor will be responsible for completing, reviewing, verifying, coordinating and technically integrating the design, including specialist contractor design portions and coordination with the novated lead design consultant.
The scope includes completing early works and substructure activities, including grading, bulk earthworks, excavation, cut and fill, soil improvement, raft foundations, reinforced-concrete basement walls, basement columns through to the ground-floor slab, waterproofing, mechanical, electrical and plumbing (MEP) provisions, and backfilling.
The contractor will also deliver the superstructure and building envelope, including structural works, facade engineering and installation, roofs, waterproofing, external finishes, and permanent facade access and maintenance systems. The internal works will cover front-of-house and back-of-house areas, public and core spaces, internal finishes, fixtures, fixed fittings, joinery, circulation areas, lobbies, stairs, toilets, storage, waste areas and associated builder’s works.
The building services package includes MEP systems, information and communications technology, extra-low-voltage systems, building management systems, security, fire and life safety systems, specialist lighting and vertical transportation.
The contract also covers the visitor experience package, including procurement, installation, integration, testing, commissioning and handover of visitor-facing environments, media, immersive and audiovisual technologies, interactive elements, experiential lighting, digital content, interpretive and wayfinding systems, controls and supporting infrastructure.
Within-plot infrastructure and utilities, landscaping, public realm works, paving, planting, irrigation, signage, street furniture, drainage, stormwater systems, external lighting, security, and fire and life safety systems are also included.
The contractor will be responsible for procurement, off-site fabrication, construction, testing and commissioning, performance verification, training, operations and maintenance documentation, operational readiness, handover, defects rectification and close-out.
The main works tender is based on a 60% RIBA Stage 3 design, with the Stage 3 design to be completed to 100% through an addendum.
Early works and substructure works, as well as the lead design consultant, will be novated to the contractor. Visitor experience works are included as a provisional sum.
https://image.digitalinsightresearch.in/uploads/NewsArticle/20801465/main.jpeg -
Mubadala Bio lands Lilly logistics deal21 October 2026
Mubadala Bio, the life sciences subsidiary of Abu Dhabi state investor Mubadala Investment Company, has signed an agreement with US drugmaker Eli Lilly to localise the packaging and logistics of Lilly’s glucagon-like peptide-1 (GLP-1) medicines in Abu Dhabi.
The work will take place at a 125,000-square-metre site in Khalifa Economic Zones Abu Dhabi (Kezad), which includes packaging and warehousing facilities. Mubadala Bio said the facilities would strengthen its pharmaceutical contract manufacturing, packaging and logistics capabilities and its ability to serve international clients from the UAE.
The packaging and logistics activities will be introduced in phases and will be subject to technical, quality and regulatory requirements. The companies did not disclose the value of the agreement or a timeline for the first phase.
The Emirates Drug Establishment approved Lilly’s oral GLP-1 drug Foundayo (orforglipron) for chronic weight management in April. The companies said this made the UAE the second country in the world to register the medicine.
In Abu Dhabi, the treatment is available to eligible patients under a weight management programme launched by the Abu Dhabi Department of Health and the Abu Dhabi Public Health Centre in June 2025. The UAE was also an early launch market for Lilly’s injectable treatment Mounjaro (tirzepatide) in August 2022.
Mubadala launched Mubadala Bio in 2025 to expand domestic drug manufacturing and distribution, with a focus on national drug security. It is one of Mubadala’s designated national champions, set up to support strategic sectors. At launch, its combined facilities covered 110,000 square metres, with an annual capacity of more than 2.5 billion tablets and capsules and 120 million intravenous and injectable units.
https://image.digitalinsightresearch.in/uploads/NewsArticle/20801279/main.jpg -
Chinese/local joint venture wins Qiddiya stadium facade21 October 2026
Register for MEED’s 14-day trial access
A joint venture of China’s Fangda Group and Saudi Arabia’s IKK Group has secured a SR1.15bn ($306m) contract to deliver curtain wall facade works for the Prince Mohammed Bin Salman Stadium in Qiddiya City, Riyadh.
The contract was awarded by the joint venture of Spain’s FCC Construccion and local contractor Nesma & Partners, which is building the stadium under an estimated SR15bn ($4bn) main contract awarded by Qiddiya Investment Company (QIC) in October 2024.
The IKK-Fangda joint venture will design, supply and install curtain wall façade systems for the main stadium (Lot 1), as well as for the museum and ancillary buildings (Lot 3).
The contract has an execution period of 863 days.
The stadium will seat about 47,000 spectators and will be the home ground for Saudi Pro League clubs Al-Nassr and Al-Hilal.
The facade award follows the appointment of Elegancia Arabia, a subsidiary of Qatar-based Elegancia MEP and Estithmar Holding, to deliver the stadium’s mechanical, electrical and plumbing works.
The SR829m ($221m) contract is Elegancia Arabia’s largest award in Saudi Arabia to date.
The project is being designed by US-based consultant Populous.
It is among the venues planned for the 2034 Fifa World Cup and will also host the Saudi King Cup, the AFC Asian Cup and the 2034 Asian Games.
https://image.digitalinsightresearch.in/uploads/NewsArticle/20799367/main.jpg -
Zamil Steel wins $82m Qiddiya tennis centre contract21 October 2026
Advanced Building Industries Company (Senaat) has announced that its subsidiary, Zamil Structural Steel Company (Zamil Steel), has secured a SR308m ($82m) contract for the National Tennis Centre in Qiddiya City, Riyadh.
The 19-month contract was awarded by the joint venture of France’s Bouygues Batiment International and local contractor Almabani General Contractors Company.
Zamil Steel’s scope includes the fabrication, supply and installation of structural steel and external facades for the scheme.
MEED reported in June that the Bouygues Batiment International-Almabani joint venture had started construction of the National Tennis Centre.
The development will include 30 tennis courts, comprising 28 hard courts and two clay courts. The main Centre Court will seat 15,000 spectators and feature a retractable roof.
The facility is being designed to meet standards set by the Association of Tennis Professionals, the Women’s Tennis Association and the International Tennis Federation.
The development will also include an 8,000-seat multipurpose arena with a retractable roof, known as Court 3. Other facilities include a 5,000-seat Court 1, a 2,000-seat Court 2, six competition courts, six indoor courts and 14 practice courts. Each outdoor match court will provide 450 seats.
Total seating capacity across the complex will be 33,000. US-based architect Populous designed the project.
Qiddiya Investment Company officially announced the project on 15 June. The developer has said the centre will be the region’s largest tennis complex and will host international tennis events.
https://image.digitalinsightresearch.in/uploads/NewsArticle/20799055/main.jpg -
Eni starts to bring gas processing facility online in Egypt21 October 2026
Register for MEED’s 14-day trial access
Italy’s Eni has started to bring its Meleiha Phase 2 (MP2) project online in Egypt’s Western Desert, according to statements from the company and Egypt’s Ministry of Petroleum & Mineral Resources.
The project includes a new gas processing facility designed to process up to 100 million standard cubic feet of gas a day.
Eni is a part owner of the project through Agiba Petroleum Company, a joint venture of Eni and state-owned Egyptian General Petroleum Corporation (EGPC)
The main contract for the project was awarded to the Egyptian engineering, procurement and construction (EPC) company Petrojet.
The scope of the project included:
- Laying 200 kilometres of pipeline
- Drilling 28 wells
- Construction of a gas sweetening unit
- Construction of a gas recovery unit
- Installation of gas purification and liquids separation units
- Installation of utilities and supporting infrastructure
- Construction of natural gas processing plant
- Construction of associated facilities
In its statement, Eni said: “The project represents a key milestone in the development of a new gas hub within the Merged Meleiha concession and will significantly increase the gas processing capacity for production from the area’s fields, supporting the growth of domestic gas output and the valorisation of Egypt’s energy resources.”
The Meleiha and Meleiha Deep concessions were combined into a single concession known as the Merged Meleiha concession in 2021.
Eni said that the new facilities “will ensure the connection of new production to Egypt’s existing gas infrastructure, enabling the rapid monetisation of resources and enhanced operational efficiency”.
It added: “The launch of the project confirms Eni’s role as a strategic partner of Egypt and reaffirms the company’s long-standing commitment to contributing to the country’s energy security through the development and valorisation of the Western Desert’s diversified resource base, one of the most promising areas of Egypt’s energy sector.”
Eni has been present in Egypt since 1954 and produced approximately 242,000 barrels of oil equivalent a day in the country on an equity basis in 2025.
https://image.digitalinsightresearch.in/uploads/NewsArticle/20788394/main.gif