Bigger is better for construction

23 December 2024

 

Nothing encapsulates a buoyant construction market better than signing a contract to complete the world’s tallest tower. That happened on 2 October 2024, when Saudi Binladin Group (SBG) was awarded a $2bn contract to complete the 1,000-metre-plus Jeddah Tower.

The award was significant in many ways. It was a revival of the tower project, which has been on hold since 2018, and it was also a comeback for SBG after years of financial stress that had led many in the market to think it would never win another major construction deal.

On a macro level, the construction deal confirmed that the region is home to the world’s most daring and challenging construction projects.

More importantly, these projects are more than just aspirations; they are real projects that are being built.

Biggest contracts

While Jeddah Tower was the most symbolic contract award in 2024, at $2bn, it was not the largest. That accolade went to the Italian contractor WeBuild when it was awarded a $4.7bn contract for the construction of the three dams at the Trojena mountain resort at Neom in January. 

Like Jeddah Tower, the project is a challenging one. Time pressure is a key issue. Trojena has been selected to host the 2029 Asian Winter Games, and the reservoir will be used to make the snow for the event. This means the dams must be completed and the reservoir filled well in advance.  

The project is also technically complex. The main dam will have a height of 145 metres and will be 475 metres long at its crest. Inside the reservoir there will be a kidney-shaped dam that will house an attraction known as the Enchanted Forest, which will be connected to the rest of the Trojena development by an underwater tunnel.

WeBuild’s involvement also highlighted that international contractors, after sitting on the sidelines for a number of years, are playing an active role in the Saudi construction market. 

One market segment that has attracted strong interest is building stadiums, which like Trojena have to be completed for football tournaments with fixed dates: the 2027 Asian Games and the 2034 Fifa World Cup. 

In October, Spain’s FCC in joint venture with the local Nesma & Partners secured a $1bn contract to build the Prince Mohammed Bin Salman Stadium at the Qiddiya City development on the outskirts of Riyadh.

Earlier in the year, a joint venture of Belgian contractor Besix and the local Albawani was awarded the contract to build the Aramco football stadium in Al-Khobar, and Beijing-headquartered China Railway Construction Corporation and local contractor Sama Construction for Trading & Contracting won the contract to construct the Jeddah Central stadium project.

Outside of Saudi Arabia, there were only two contract awards valued at over $1bn and both were in the UAE emirate of Abu Dhabi. 

In January, a $1.2bn contract to complete phases two and four at the Saadiyat Lagoons project was awarded to a joint venture of two Abu Dhabi-based contractors, Trojan Construction Group and Arabian Construction Company. 

The other $1bn-plus deal was a $1.4bn contract to complete dredging and marine works for the Nisi Island development, which was awarded to the local NMDC Group. 

These deals were highlights in what was a strong year for the rest of the market. In total, according to regional projects tracker MEED Projects, there were $67.9bn of construction contract awards by the end of October 2024. If the trajectory is maintained until the end of the year, it will result in about $81.4bn of awards, which is lower than the $96.9bn of awards recorded in 2023, but still higher than any of the eight years from 2015 to 2022. 

Market challenges

Replicating the record-breaking performance of 2023 was never going to be easy, especially after Riyadh warned that its spending would be more targeted at the end of 2023. Those comments, made by the finance minister, set the tone for 2024, which proved to be a year with plenty of contract awards, but without the apparent carefree attitude to spending that characterised 2023. 

The other challenge with following on from a bumper year is supply chain constraints. With full order books, contractors and suppliers have lost some of the appetite that they had for new work in 2023. The result of this for project clients has been difficulties in attracting enough bidders, and when bids are submitted, the offers are often not competitively priced.

These challenges have been felt most acutely by projects in the remote regions of Saudi Arabia. The issue is so prevalent at Neom that there is now a phenomenon known as ‘Neom inflation’, which implies that the $500bn gigaproject in the remote northwestern corner of the kingdom has its own unique inflation rate.

These regional issues have added to the international supply chain constraints that have been felt since the Covid-19 pandemic and, more recently, during the conflict in Gaza and threats to shipping lanes in the Red Sea.

Addressing challenges

The market has responded to these challenges. In Saudi Arabia, the Public Investment Fund (PIF) invested in four of the kingdom’s largest general contractors in 2023. Then, in February 2024, the sovereign wealth vehicle announced that it had, together with the National Infrastructure Fund, introduced a new contractor financing programme, designed to strengthen the construction sector’s finances. 

The programme aims to provide contractors with finance solutions to help improve their cash flows.

Developers have also been improving their contract terms and, crucially, working to ensure payments are processed on time – a move that should also help improve contractor cash flows. 

The PIF-backed development companies have also been actively working on attracting new companies to Saudi Arabia. They have been travelling the world on roadshows to attract more contractors and suppliers to projects in the kingdom. 

These roadshows have been highlighting the volume and scale of the opportunities in Saudi Arabia, and have shown that the kingdom offers long-term opportunities for companies that come and invest in the market. 

In the UAE, Abu Dhabi has invested heavily in its construction supply chain. With its government-controlled investment vehicles and a series of interconnected mergers and acquisitions, Abu Dhabi and its ruling family now own the emirate’s key contracting companies and the suppliers of vital raw materials such as cement and steel. 

These national champions shield Abu Dhabi from many, but not all, supply chain challenges that have impacted projects in other markets.

Meanwhile, in Dubai, where the real estate market is driving construction, private sector developers are courting contractors to work on their projects.

As private entities, they are not bound by the procurement regulations that government or government-controlled developers have, so they have been offering directly negotiated deals to help guarantee that their projects are delivered on time.

 

2025 outlook

Unless the market dynamics shift dramatically, the market will likely face many of the same challenges in 2025. 

One of the overriding fears is a sharp slowdown in project spending in Saudi Arabia. This has happened before and is a valid concern, and the market has already shown signs of plateauing in some areas. 

This is most noticeable when contract awards for the five official gigaprojects – Diriyah, Neom, Qiddiya, Red Sea Global and Roshn –  are examined. After a sharp ramp-up in awards from 2020 to 2023, the pace of contract awards levelled off in 2024, which reflects budgetary concerns within the development companies and the PIF, and the market’s ability to take on such large volumes of new work. 

With budgets under pressure, developers in Saudi Arabia are increasingly looking for investment to help fund their projects. The success of these efforts will determine how buoyant the market in the kingdom remains over the long term.  

Even if investment comes in, it will take time, which means there will likely be a degree of conservatism from development companies in 2025. This was signalled in mid-November, when Neom, while announcing the exit of CEO Nadhmi Al-Nasr and the appointment of Aiman Al-Mudaifer as acting CEO, said: “As Neom enters a new phase of delivery, this new leadership will ensure operational continuity, agility and efficiency to match the overall vision and objectives of the project.”

While there may be a pause in spending on some of the Saudi gigaprojects, other schemes continue to underpin the performance of the construction market. 

Oil prices remain supportive of government spending on projects across the Gulf, and for the private sector, in markets such as the UAE, real estate projects continue to move into construction as developers rush to deliver units to investors and capitalise on the ongoing strength of the property market. 

https://image.digitalinsightresearch.in/uploads/NewsArticle/13146583/main.gif
Colin Foreman
Related Articles
  • Hydrom targets hyperscalers in round four

    19 November 2026

     

    Oman’s green hydrogen company Hydrom is turning to domestic demand to support the sector as export markets slow, says managing director Abdulaziz Al-Shidhani.

    Speaking to MEED after Hydrom awarded two projects under its third auction round and launched a fourth round linked to data centres at UN climate change conference Cop31 in Antalya, Al-Shidhani says interest in the third round had been satisfactory but below earlier levels. 

    “There was a good interest, satisfactory to the auction itself, but it was not as big as it was in round one specifically,” he says. “[That is] reflecting the overall market sentiment when it comes to green hydrogen.”

    Hydrom does not disclose the number of auction bids it receives.

    Domestic demand

    According to Al-Shidhani, regulatory slowdowns in Europe and slower progress in markets such as South Korea and Japan prompted Hydrom to look for buyers at home.

    “We decided last year to start exploring each and every avenue domestically to support decarbonising our industries and introducing green solutions for expanding the industrial base within Oman itself,” he says.

    Steel, methanol, mobility, hydrogen-to-power and data centres are among the applications that are under review. A natural gas supply agreement was recently signed for a green direct reduced iron (DRI) plant, which carries a mandate to replace natural gas with green hydrogen in the early 2030s. Hydrom is helping first-round developers in Duqm reach a commercial agreement with the DRI investor.

    Data centres

    The fourth round, the Green-Powered Data Centre Hydrogen Auction, will be held in Dhofar Governorate. The city of Salalah was chosen for its connectivity, cooler climate and seawater cooling.

    Al-Shidhani says the national grid is not yet in a position to supply hyperscalers requiring 100MW or more. The Energy & Minerals Ministry and the Transport, Communications & Information Technology Ministry mandated Hydrom to design a captive power solution.

    “Our work yielded that the best techno-commercial proposition is a blend of renewable electrons supported by batteries and supported by up to 20% firming power through hydrogen gensets,” he says.

    The auction is designed for integrated consortiums covering power, hydrogen and data centre hubs. Hydrom will also offer matchmaking for investors that want a partner to supply the energy.

    Registration for expressions of interest is open until February 2027. Al-Shidhani says a market sounding exercise had given “a very positive signal”. Hydrom plans to issue the request for qualification by the end of the first quarter of 2027, with requests for proposals expected around mid-year.

    Round three

    The awards went to a consortium of Petrogas E&P and Italy’s Bio3Energy, which plans to produce about 625,000 tonnes a year (t/y) of green ammonium nitrate, and a consortium of PLN Indonesia Power Renewables, Alawi Enterprises and HBA Offshore International, which plans to produce about 400,000 t/y of green ammonia. Combined green hydrogen output is expected to reach about 121,000 t/y by 2032.

    The block offered covers 300 square kilometres and could accommodate up to three projects. One winner has an option on a further 100 square kilometres, which would use the full block.

    Al-Shidhani says the land usufruct agreements will be registered with Oman’s Housing Ministry within two to three weeks. Developers then have three and a half years for development work, with a final investment decision expected by the end of year three and financial close six months later. Construction is allotted three and a half years, followed by 40 years of operations.

    He says the 2032 production date does not represent a delay to Oman’s 2030 target. 

    “It is a rolling process,” he says. “The 2030 [projects] were signed in 2023 and 2024. It is a moving target.”

    One of the new projects has opted for solar power only at the outset. Hydrom does not specify generation or electrolyser technology. Project finance remains the most common funding route, although Al-Shidhani says export credit agencies could also play a role.

    This is a demonstration that Oman is able to produce [some of] the lowest-cost hydrogen

    First production

    The first phase of India-based Acme Group’s project in Duqm, which will produce 100,000 t/y of green ammonia, is expected to start production in Q2 2027. Al-Shidhani, who visited the site in October, says major components were almost complete.

    “This is a demonstration that Oman is able to produce [some of] the lowest-cost hydrogen and deliver it competitively to markets, and we are not talking about small quantities,” he says.

    He expects the first export cargo to convince sceptical investors that Oman can produce hydrogen for less than $3 a kilogram. Other first- and second-round developers are still negotiating offtake before moving to front-end engineering and design.

    Further rounds

    Al-Shidhani says the awarded projects use approximately 4% of the land available to Hydrom, and that further auctions are certain. Oman’s strategy targets 8.5 million t/y of green hydrogen by 2050.

    Hydrom paused for almost a year after the second auction round, and the timing of future rounds will depend on the market.

    “It is all about selecting the right time to go to the market,” he says. “In terms of whether there would be round five or round six, the answer is definitely there would be.”  

    https://image.digitalinsightresearch.in/uploads/NewsArticle/21573009/main.gif
    Colin Foreman
  • Contractors submit best offers for Oxagon Highway 55

    19 November 2026

     

    Contractors have submitted their best and final offers for a design-and-build contract to upgrade Highway 55 in Saudi Arabia’s Oxagon region.

    The first phase of the project includes the construction of 14 kilometres of road, with two lanes in each direction, as well as one bridge and three interchanges.

    The project is expected to take 22 months to complete.

    Contractors initially submitted bids on 28 September, as MEED exclusively reported.

    Highway 55 connects the Red Sea coast with the mainland in northwestern Saudi Arabia. It is currently the only road providing north-south connectivity between Duba and the Neom region.

    MEED reported exclusively in August last year that contractors had submitted responses to an expression of interest notice that Neom had issued earlier that month.

    The project is expected to support cargo movement from Duba Port to other parts of the kingdom and the wider region.

    Last year, Neom tested a pilot initiative by handling a shipment that travelled from Cairo via the Port of Safaga, across the Red Sea to the Port of Neom, and then inland to Erbil, Iraq.

    In a statement, Neom said: “The shipment travelled through an intermodal corridor spanning over 900 kilometres, marking a significant milestone in the kingdom’s transformation into a regional and global logistics hub.”


    READ THE NOVEMBER 2026 MEED BUSINESS REVIEW – click here to view PDF

    Gulf projects keep moving amid conflict; UAE's state spending and oil output flexibility cushion Iran war shock; Project finance lenders weigh risk against infrastructure needs.

    Distributed to senior decision-makers in the region and around the world, the November 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/21556022/main.jpg
    Yasir Iqbal
  • Construction starts on Damascus hotel and mall

    19 November 2026

    Construction has started on the Movenpick Hotel and Arab Mall development in the Kafr Sousa district of Damascus.

    Rotana Star Holding and Sankari Holding are backing the project, which Syria’s Ministry of Tourism is developing under its patronage.

    The project marks Accor’s entry into the Syrian market. The France-based hotel group signed an agreement earlier this year to manage the project’s Movenpick Hotel component.

    The integrated development will cover more than 90,000 square metres (sq m) and combine hotel, retail, entertainment and supporting facilities.

    The Movenpick Hotel will occupy more than 25,000 sq m and include 300 accommodation units. Facilities will include event and celebration halls, restaurants with panoramic views, and health and fitness amenities.

    Arab Mall will cover more than 65,000 sq m across seven levels. It will include retail units, entertainment facilities and service areas.

    The developers expect Arab Mall to open in the first quarter of 2028, followed by the hotel in the first quarter of 2029.

    Accor acquired the Swiss-founded Movenpick brand in 2018. Under the management agreement, Accor will operate the hotel and provide access to its global reservation, distribution and marketing platforms.

    The development is expected to create direct and indirect employment across construction, engineering, hospitality, retail and services.

    The project is being advanced as Syria seeks to expand its tourism and hospitality capacity.

    Syria’s Ministry of Tourism has reported that the country received 3.52 million visitors in the first half of 2026, 111% more than in the same period of 2025.

    The ministry said foreign tourist arrivals increased by 448%, while Arab visitor numbers rose by 107%.


    READ THE NOVEMBER 2026 MEED BUSINESS REVIEW – click here to view PDF

    Gulf projects keep moving amid conflict; UAE's state spending and oil output flexibility cushion Iran war shock; Project finance lenders weigh risk against infrastructure needs.

    Distributed to senior decision-makers in the region and around the world, the November 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/21555695/main.jpeg
    Yasir Iqbal
  • Kuwait discusses retender of $7.7bn of oil projects

    19 November 2026

     

    State-owned upstream operator Kuwait Oil Company (KOC) is discussing the retendering of upstream projects worth an estimated $7.7bn, according to industry sources.

    The tender processes for all four contracts were cancelled earlier this year after the lowest bids exceeded the projects’ approved budgets.

    The projects are:

    • Separation Gathering Centre 1 (SGC-I) and Water Injection Plant (WIP-1)
      Previous low bidder: Tecnicas Reunidas (Spain) – $2.47bn
    • Separation Gathering Centre 3 (SGC-3) and Water Injection Plant (WIP-3)
      Previous low bidder: Larsen & Toubro (India) – $2.48bn
    • Installation of Water Injection Plant (WIP-4)
      Previous low bidder: Petrofac (UK) – $1.48bn
    • Effluent Water Disposal Plants 1 & 2 expansion project (EWDP 1&2)
      Previous low bidder: Larsen & Toubro (India) – $1.30bn

    KOC is considering a strategy under which pipeline and network installation work would be removed from the main contract scopes and tendered separately, the sources said.

    The company is also planning to relaunch the four main packages under a build-own-operate model rather than the engineering, procurement and construction (EPC) model used previously.

    KOC is expected to tender the pipeline and network packages on an EPC basis, or under a similar delivery model.

    In addition, KOC is discussing increases to the projects’ approved budgets to enable contractors to submit compliant bids, the sources said.

    Since KOC cancelled the four tenders in January, Kuwait’s oil and gas sector and the wider economy have faced disruption linked to the regional conflict that began after the US and Israel attacked Iran on 28 February.

    The conflict has reduced shipping through the Strait of Hormuz, limiting Kuwait’s ability to export crude oil.


    READ THE NOVEMBER 2026 MEED BUSINESS REVIEW – click here to view PDF

    Gulf projects keep moving amid conflict; UAE's state spending and oil output flexibility cushion Iran war shock; Project finance lenders weigh risk against infrastructure needs.

    Distributed to senior decision-makers in the region and around the world, the November 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/21532374/main.jpg
    Wil Crisp
  • Saudi Arabia cancels more water tenders

    19 November 2026

     

    Two tenders for a major water pipeline project in Saudi Arabia have been cancelled, marking the second major water infrastructure project in the kingdom to have its tender process called off this month.

    The tenders cover Package B and the combined Packages C1 and C3 of the New Water Pipeline to Feed Riyadh City 2 project, being developed by Water Transmission Company (WTCO). 

    A source close to the project told MEED that bidders were notified of the decision earlier in November.

    The three packages have a combined value of about $556m and involve the construction of a long-distance potable-water transmission system to strengthen supplies to Riyadh.

    The wider masterplan includes approximately 136 kilometres of pipeline, with diameters ranging from 64 inches to 100 inches. The scope also includes 10 steel storage tanks with capacities ranging from 100,000 cubic metres to 170,000 cubic metres.

    According to regional tracker MEED Projects, Saudi Services for Electro-Mechanic Works was appointed as the main contractor for Package B in 2025, with a reported contract value of $279.6m. Another local firm, Al-Rawaf Trading & Contracting, was appointed for Packages C1 and C3, with a combined contract value of $276m. Multiple other contractors submitted bids for the three packages.

    As MEED understands, construction was expected to start earlier this year.

    The cancellations follow the withdrawal of a tender for a 300-million-litres-a-day seawater reverse osmosis desalination plant at Yanbu, valued at $272m.

    As reported by MEED on 16 November, Saudi Water Authority cancelled the Yanbu tender despite India’s VA Tech Wabag receiving the contract award in July 2025.

    The contractor disclosed the decision in a filing to Indian stock exchanges, saying the tender was cancelled due to “internal reasons” on the authority’s side.

    It is the second time a tender has been cancelled for the project at the final award stage.

    It is unclear whether the desalination or transmission-pipeline projects will be retendered and, if so, whether their scopes will remain unchanged. MEED has contacted WTCO for comment.


    READ THE NOVEMBER 2026 MEED BUSINESS REVIEW – click here to view PDF

    Gulf projects keep moving amid conflict; UAE's state spending and oil output flexibility cushion Iran war shock; Project finance lenders weigh risk against infrastructure needs.

    Distributed to senior decision-makers in the region and around the world, the November 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/21527730/main.jpg
    Mark Dowdall