Aramco PPP project proposals submitted
1 May 2023

Saudi Aramco has received proposals from bidders for a major desulphurisation programme to modify and upgrade sulphur recovery units (SRUs) at its key gas processing plants in the kingdom.
Two consortiums of contractors submitted proposals by the deadline of 30 April for the scheme, which involves building tail-gas treatment (TGT) facilities at seven gas processing plants.
Aramco expects third-party investments of up to $2bn in the desulphurisation programme, which entails building large downstream TGT units to collect and process tail gas discharged from SRUs at the identified gas plants, MEED reported in December 2021.
The facilities are to be developed either on a build, own and operate (BOO) or build-own-operate-transfer (BOOT) basis. This will make it one of Aramco’s initial public-private partnership (PPP) exercises in its main oil and gas business, if not the first.
Aramco issued expressions of interest (EoI) for the scheme on 18 October 2021 and received EoI documents on 30 November that year. The Saudi energy giant then issued the main tender for the PPP project in May last year, as MEED reported.
Bidders were initially required to submit proposals by 30 September last year. The proposal submission deadline was moved to 15 December and then extended to 15 March this year. The latest bid submission date was set for 31 March.
The two parties that are understood to have submitted bids for the scheme are:
- Vision Invest (Saudi Arabia) / Larsen & Toubro Energy Hydrocarbon (India)
- Lamar Holding (Saudi Arabia) / Hyundai Engineering (South Korea) / Korea Overseas Infrastructure & Urban Development Corporation (South Korea) / Enerflex (Canada)
In an interview with MEED earlier this year, Lamar Holding’s chief operating officer Ramit Jain confirmed that the company was bidding for the TGT scheme in a team comprising South Korean government-owned Korean Overseas Infrastructure & Urban Development Corporation and other entities.
SO2 reduction campaign
The Aramco programme is in line with the regulations for emissions to air from stationary sources set out by Saudi Arabia’s Environment, Water & Agriculture Ministry. These stipulate that sulphur dioxide (SO2) emissions from stationary sources must not exceed 250 parts per million volume (dry and 0 per cent oxygen basis). They must also comply with the SO2 ambient emission limits or ground-level SO2 concentration.
The rollout of the desulphurisation scheme stems from Aramco’s goal to achieve net-zero carbon emissions by 2050 and is part of its environmental, social and governance initiatives, sources previously said.
Seven gas plants in Saudi Arabia’s Eastern Province have been identified from which tail gas needs to be treated for up to 99.9 per cent SO2 removal:
- Berri
- Haradh
- Hawiyah
- Khursaniyah
- Shedgum
- Uthmaniyah
- Wasit
The scope of the scheme has been split into two packages, one source said. The first package covers gas plants in Aramco’s Zone 1 – Berri, Khursaniyah and Wasit – while the second package relates to units in Zone 2 – Haradh, Hawiyah, Shedgum and Uthmaniyah.
Along with fully financing the project, the developer will need to adopt one of the following commercial desulphurisation technologies approved by Aramco for the scheme:
- TGT reduction absorption
- Ammonia-based desulphurisation
- Dry sorbent injection
- Flue gas desulphurisation using gypsum
According to Aramco, the project will cover “the end-to-end application of the approved technologies, including but not limited to required plot space, utilities, market analysis and logistics of feedstock and byproduct, contractual arrangements, risks associated with each technology related to safety, process reliability and SO2 emissions compliance on a continuous basis”.
Aramco expects the common TGT facility to be operational by 2027.
Exclusive from Meed
-
UAE water investment broadens beyond desalination8 April 2026
-
UAE banks ready to weather the storm8 April 2026
-
-
-
PDO awards Oman gas plant expansion project8 April 2026
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
UAE water investment broadens beyond desalination8 April 2026

Desalination investment slowed in the UAE last year as awards in the segment fell to $400m, their lowest annual total since 2021.
Although overall market activity remained strong, reaching $3.4bn in total water sector awards, the only major desalination award in 2025 was the Saadiyat seawater reverse osmosis (SWRO) independent water plant (IWP) being developed by Spain’s Acciona.
This project accounted for 12% of total awards, reflecting a gradual decline in desalination investment over the past few years.
In 2024, the segment accounted for 22% of total water infrastructure awards. That figure was 25% in 2023 and 35% in 2022.
Tasreef programme
Beyond desalination, the market has been driven largely by transmission infrastructure over the past 12 months, most notably Dubai Municipality’s AED30bn ($8.1bn) Tasreef programme, which aims to strengthen stormwater drainage systems across the emirate for the next century.
In February, the municipality confirmed it had awarded contracts for five new projects under phase two of the programme to expand and strengthen Dubai’s stormwater drainage network.
These include two contracts awarded to local firm DeTech Contracting and one to China State Construction Engineering Corporation for stormwater drainage infrastructure. In addition, two consultancy contracts were awarded for the study and design of drainage systems in selected areas across the emirate.
Cumulatively valued at AED2.5bn, the new projects will serve 30 vital areas, spanning approximately 430 million square metres and supporting an estimated population of three million residents by 2040.
The latest deals build on an earlier package of projects awarded in April 2025 under phase one of the Tasreef programme. The overall masterplan aims to expand Dubai’s rainwater drainage capacity by 700% by 2033.
Sewage treatment
While 2025 was a quiet year for sewage treatment contract awards, 2026 began with a key milestone as Ras Al-Khaimah awarded its first sewage treatment project under a public-private partnership (PPP).
The contract was awarded to a consortium of Abu Dhabi National Energy Company (Taqa), Saur (France) and Etihad Water & Electricity (UAE).
The $120m project involves developing a wastewater treatment plant with a capacity of 60,000 cubic metres a day (cm/d), expandable to 150,000 cm/d.
The deal is seen as significant not just because it adds capacity, but because it establishes a repeatable template for future private sector participation in municipal infrastructure, a segment that has historically been harder to structure than power or desalination.
Cooling
According to MEED Projects, four cooling contracts were awarded last year, with total investment rising from $161m in 2024 to $205m in 2025.
The segment continues to be led by Empower, which holds more than 80% of Dubai’s district cooling market and operates at least 88 plants across the emirate.
Dubai Electricity & Water Authority (Dewa) now owns 80% of the company, having recently increased its stake in a $1.4bn deal.
In February, Empower announced it had begun the design of its fifth district cooling plant in Dubai’s Business Bay, as part of a wider scheme in the area with a total planned capacity of 451,540 refrigeration tonnes (RT).
The wider Business Bay development comprises nine plants, of which four are already operational and two are currently at the design stage.
Separately, last August, Empower signed a contract to design a $200m district cooling plant at Dubai Science Park, with a total capacity of 47,000 RT serving 80 buildings.
Project pipeline
Looking ahead, the tender pipeline points to sustained market activity, particularly in transmission and wastewater infrastructure.
A key near-term project is the Dubai Strategic Sewerage Tunnels (DSST) PPP, one of the emirate’s largest planned infrastructure schemes. Contracts for three packages are expected to be awarded in the coming months.
The masterplan covers the construction of two deep tunnel systems terminating at pump stations serving the Warsan and Jebel Ali sewage treatment plants (STPs). The scheme will convert Dubai’s sewerage network from a pumped system to a gravity-based system, helping the emirate replace ageing pumping stations and meet long-term capacity requirements.
The main contracts for the J and W packages are expected to be awarded first, with three consortiums in the running, while the Phase 2 Links package is currently under tender, with bids due on 30 June.
Transmission continues to dominate procurement, led by the tunnels scheme, accounting for $21.7bn under bid evaluation and $2.5bn at main contract bidding stage.
The wider pipeline also shows growing momentum in treatment, cooling and storage, underlining how investment is increasingly spread across the broader water infrastructure value chain.
This includes a major dam rehabilitation project in Hatta, covering four dams at Hatta, Ghabra, Al-Khattem and Suhaila, as well as the expansion of the Jebel Ali STP, which will add 100,000 cm/d of treatment capacity.
Dubai Municipality is also preparing to tender the main construction package for the Warsan STP later this year. While previously expected to be procured as a PPP, the project is now set to move forward as an engineering, procurement and construction (EPC) contract.
The focus of desalination activity, meanwhile, is on two upcoming projects being procured by Etihad Water & Electricity (EtihadWE). The first of these involves the construction of a $200m SWRO plant in Ras Al-Khaimah, which has already been put out to tender.
The second involves a $200m SWRO plant in Fujairah, estimated to cost $400m. The request for qualification (RFQ) documents were submitted last year, with the project expected to advance through procurement in the coming months.
Several desalination projects are also moving through construction, with the Shuweihat 4 IWP due to come online soon with a capacity of 318,225 cm/d, while at least three more plants are scheduled for commissioning next year.
https://image.digitalinsightresearch.in/uploads/NewsArticle/16300198/main.gif -
UAE banks ready to weather the storm8 April 2026

Amid unprecedented turbulent geopolitics, Emirati lenders are putting on a confident face. More than one month in from the Iran conflict, Dubai’s largest bank, Emirates NBD, raised $2.25bn in long-term financing – obtaining, it said, the tightest pricing in the bank’s history for a syndicated loan, which aims to strengthen the bank’s liquidity position.
Bankers view this as a token of the sector’s resilience. “Strong oversubscription from international lenders, together with tight pricing, reflects continued market confidence in the UAE’s financial sector,” said Shayne Nelson, Emirates NBD’s CEO.
UAE banks entered the crisis in a strong position. Capital and liquidity buffers are robust, with an aggregate capital adequacy ratio of 17.1% in Q4 2025 – well ahead of the minimum 10.5% level. The loan-to-deposit ratio stood at 77.7%, another metric indicating its latitude to extend ample credit to the economy.
Performance levels last year were impressive. Total assets in the UAE banking system rose 17% in year-on-year terms to AED5,340bn ($1.45bn) by end-2025. Asset quality ratios improved, supported by a 16.2% reduction in non-performing loans (NPLs). Large banks revealed strong profits. The largest Emirati lender, First Abu Dhabi Bank, reported a 24% increase in net income to AED21.11bn ($5.7bn), while Abu Dhabi Commercial Bank similarly saw full-year pre-tax profits rise by 21% to AED12.8bn.
Analysts paint a picture of a broadly healthy banking system, at least pre-conflict. “In 2025, we saw some margin pressure, as competition for liquidity increased. UAE banks’ profitability metrics declined a bit. But banks entered this crisis in the best shape for the last 10 years. Take the NPL ratio; at around 3%, it’s been on a declining trend for the last five years,” says Anton Lopatin, senior director, financial institutions at Fitch Ratings.
Support package
The events since 28 February have clearly ruffled the surface calm, although the UAE Central Bank has stepped in to provide additional support, announcing on 19 March a resilience package mainly made up of precautionary support measures focused on liquidity and forbearance. This comes amid reports of a sharp decline in liquidity in the banking system.
The package allows lenders to access liquidity and to use capital buffers to support the economy. Banks enjoy enhanced access to reserve balances up to 30% of the cash reserve requirement.
“The central bank has a strong ability to support banks in the UAE, as it has AED1tn ($270bn) in external reserves. It means that it is able to provide support if needed, backed by these reserves,” says Lopatin.
According to Lopatin, overnight deposits at the Central Bank have declined slightly since the conflict escalated, but nothing too severe. “Judging by liquidity indicators at the sector level, it’s under pressure, but it’s still healthy,” he says.
Ongoing risks
Nonetheless, a protracted conflict would raise asset quality concerns, given the likely impact on companies in sectors such as infrastructure, real estate, tourism and aviation – those most exposed to war-related effects. In the UAE, hospitality, tourism and real estate also have weaker links to the sovereign.
Disruption to air traffic and tourist inflows is likely to have only a small direct impact on UAE banks, whose lending to the transport (mostly aviation) and tourism sectors is limited. Fitch estimates the two combined accounted for less than 3% of total loans at end-2025.
“The UAE has always been sensitive to the real estate market performance. It has recovered strongly since Covid, with prices up by 60%. But if there is less economic activity, and less belief in Dubai as a safe jurisdiction, real estate would be among the first sectors to suffer,” says Lopatin.
Corporate real estate accounted for 13% of gross loans at end-2025, down from 20% at end-2021, and this sector is likely to be the main source of new Stage 3 loans if the conflict is prolonged, warned Fitch in a rating note issued on 2nd April.
Some banks still have high concentrations in their loan books, namely Sharjah Islamic Bank (29%), Ajman Bank (28%), Commercial Bank International (CBI; 41%), Commercial Bank of Dubai (20%) and United Arab Bank (UAB; 20%). Their asset-quality metrics could weaken, said Fitch, adding profitability pressures, if the real estate price correction exceeds its pre-conflict expectations.
Already, two Dubai property developers have seen their sukuk (Islamic debt securities) fall into distressed territory, as investor concerns about credit quality and refinancing risks start to register. In mid-March, Fitch Ratings placed Dubai real estate firm Binghatti on a negative rating watch, signalling a potential downgrade.
Too early to assess
Yet analysts caution against reading too much into this at this stage. “UAE banks’ total exposure to real estate is not so significant,” he says. “Currently, it’s less than 15%, the lowest level in 10-15 years. Any impact on banks will be gradual, but it will be under pressure, so banks will be under pressure too. Some smaller UAE banks entered this crisis with less cushioning and higher NPLs and therefore could be affected more.”
Refinancing risk may also affect the government-related entity (GRE) sector, with these anticipating around $11.5bn in debt maturing this year, according to estimates from Capital Economics, a consultancy.
If the refinancing of GRE debt proves too expensive, then UAE banks may have to step into the breach with new credit facilities.
“The longer the conflict lasts, refinancing becomes a point of stress,” says Lopatin.
The capacity of the likes of Emirates NBD to raise finance in the most trying conditions suggests a wider resilience that may stave off worst-case scenarios for UAE banks. The next weeks and months will doubtless be testing for them, and the possibility of cash flow problems yielding a worsened loan quality position is one that will be taken seriously.
However, the capital and liquidity buffers painstakingly built up since the Covid pandemic mean banks are ready to weather the storm.
https://image.digitalinsightresearch.in/uploads/NewsArticle/16251184/main.gif -
Dubai extends bid deadline for Jebel Ali STP expansion8 April 2026

Dubai Municipality has extended the deadline for contractors to submit bids for a contract covering the expansion of the Jebel Ali sewage treatment plant (STP) phases one and two.
The upgraded facility will be capable of treating an additional sewage flow of 100,000 cubic metres a day (cm/d), with the expansion estimated to cost $300m.
The scope includes the design, construction and commissioning of infrastructure and systems required to support the increased capacity.
The new bid submission deadline is 30 April. The original deadline was 2 April.
Located on a 670-hectare site in Jebel Ali, the original wastewater facility has a treatment capacity of about 675,000 cm/d following the completion of phase two in 2019, combining approximately 300,000 cm/d from phase one and 375,000 cm/d from phase two.
The main element of the expansion involves modifications to the secondary treatment process at Jebel Ali STP phase two.
UK-headquartered KPMG and UAE-based Tribe Infrastructure are serving as financial advisers on the project.
It is understood that the project is part of long-term plans to treat about 1.05 million cm/d once all future phases are completed.
MEED recently revealed that the municipality is preparing to tender the main construction package for the Warsan STP by the end of the year.
As MEED understands, the Warsan STP had previously been expected to be procured as a public-private partnership scheme.
However, the main construction package will now be procured as an engineering, procurement and construction contract.
The project involves the construction of a sewage treatment plant with a capacity of about 175,000 cm/d, including treatment units, sludge handling systems and associated infrastructure.
https://image.digitalinsightresearch.in/uploads/NewsArticle/16298710/main.jpg -
Prequalification begins for King Salman Stadium early works8 April 2026
Saudi Arabia’s Sports Ministry has invited companies to prequalify for a contract covering early works at the King Salman International Stadium in Riyadh.
The notice was issued on 8 April, with a prequalification deadline of 28 April.
The stadium will cover about 660,000 square metres (sq m) and have a seating capacity of 92,000. Facilities will include a 150-seat royal suite, 120 hospitality suites, 300 VIP seats and 2,200 dignitary seats.
The wider development will include sports facilities covering more than 360,000 sq m, including two training fields and fan zones, a closed sports hall, an Olympic-sized swimming pool, an athletics track, and outdoor courts for volleyball, basketball and padel.
The stadium is set to host the final of the 2034 Fifa World Cup and will serve as the Saudi national football team’s main base.
US-based architectural firm Populous is the lead architect for the stadium.
Construction of the stadium is expected to be completed by 2029.
The stadium will be located next to King Abdulaziz Park.
Firms submitted prequalification statements for the main design-and-build contract in February.
Saudi Arabia stadium plans
In August 2024, MEED reported that Saudi Arabia plans to build 11 new stadiums and refurbish four facilities for the 2034 Fifa World Cup.
Eight stadiums will be located in Riyadh, four in Jeddah and one each in Al-Khobar, Abha and Neom.
A further 10 cities will host training bases: Al-Baha, Jazan, Taif, Medina, Alula, Umluj, Tabuk, Hail, Al-Ahsa and Buraidah.
There are expected to be 134 training sites across the kingdom, including 61 existing facilities and 73 new venues.
Saudi Arabia was officially selected to host the 2034 Fifa World Cup during an online convention of Fifa member associations at the Fifa Congress on 11 December 2024.
https://image.digitalinsightresearch.in/uploads/NewsArticle/16298708/main.jpg -
PDO awards Oman gas plant expansion project8 April 2026

Petroleum Development Oman (PDO) has awarded the main contract for a major project to expand the Birba gas station in the Dhofar governorate in southern Oman.
Known as the Budour-Northeast Birba integrated project, PDO intends to execute engineering, procurement, construction (EPC) and commissioning of units to process additional volumes of sour gas.
Egypt’s Engineering for the Petroleum & Process Industries (Enppi) has won the contract to perform EPC works on the project, according to sources.
The value of the contract awarded by PDO to Enppi is unknown. The Budour-Northeast Birba integrated project was earlier estimated to be worth about $300m.
MEED reported last year on the two-way fight between Enppi and India-based Larsen & Toubro Energy Hydrocarbon (L&TEH) for the project’s main EPC contract.
MEED previously reported that contractors submitted technical bids for the project by the deadline of 30 January 2025. Aside from Enppi and L&TEH, Greece/Lebanon-headquartered Consolidated Contractors Company (CCC) and Abu Dhabi’s NMDC Energy were understood to have submitted technical bids, but are thought to have later withdrawn from the race.
Enppi and L&THE submitted commercial bids for the project by the 11 June deadline, MEED previously reported.
After receiving prices, however, PDO appeared to slow down the bid evaluation process for the project’s contract award. The majority state-owned oil and gas producer engaged bidders for discussions and negotiations in the meantime, eventually asking them to extend the validity of their bids until April, one source said.
The greenfield and brownfield scope of work on the project covers the following:
- New separator train at the Birba gas station to perform three-stage separation
- New gas dehydration unit
- Two new gas injection compressors
- New gas recovery compressor
- New gas booster compressor
- Installation of utility units, such as electrical infrastructure, flare system, drainage, etc
- New high-pressure flare
- New instrumentation air package
- New nitrogen system
- New drainage vessel
- Debottlenecking of AP flare header by increasing the flare header size
- Modification inside existing 33kV gas-insulated switchgear in Birba gas station substation
- Modification of existing 6.6kV switchboard
- Interfaces with existing control room
- Civil and piping interfaces within the Birba gas station facility
In December, PDO achieved a final investment decision on another major project to build an integrated facility to produce natural gas from the Budour and Tayseer fields in Oman.
Kuwait‑based Spetco International Petroleum Company (Spetco) won the main design, build, own, operate and maintain (DBOOM) contract for the combined Budour-Tayseer sour gas processing facility project. The value of the contract won by Spetco is $683m.
PDO awarded Spetco the 15-year contract in September, as MEED reported, with the official signing between the parties taking place in December.
The project aims to expand the capacity of the existing gas production and processing facility at Tayseer. It represents the second development phase of the gas field. Through the project, PDO is also seeking to appraise, produce and process sweet gas from the Budour field, located about 50 kilometres west of the Tayseer field.
ALSO READ:
https://image.digitalinsightresearch.in/uploads/NewsArticle/16298603/main0506.jpg

