Bankability remains hydrogen’s unbreakable challenge

6 February 2025

Commentary
Jennifer Aguinaldo
Energy & technology editor

There is some indication that green hydrogen as an industry has arrived at the valley of disillusionment if the Gartner hype cycle is anything to go by.

This is evident with the dwindling number of attendees and absence of offtakers – global commodity trading companies that are expected to buy premium green hydrogen and derivative products – at previously well-attended green hydrogen summits in major cities in the Gulf.

Following frenzied announcements of multibillion-dollar integrated green hydrogen and ammonia plants in the Middle East and North Africa region, particularly Egypt, Morocco, Oman and the UAE, between 2021 and 2023, it appears that key stakeholders have started coming to grips with reality.

Of the close to 80 green hydrogen projects that MEED and MEED Projects track, only three have so far signed an offtake agreement, and only one has managed to reach financial close.

The $8.4bn Neom green hydrogen project in Saudi Arabia reached financial close in March 2023, nearly two years after it was announced.

The project, the largest of its kind requiring over 4GW of renewable energy and 2GW of electrolyser capacity, managed to reach financial close based on one of the three co-developers, the US’ Air Products, assuming the full offtake and construction risks for the project, note some experts.

A project’s bankability ultimately relies on suitable stakeholders taking on the risks for every aspect of the project, from construction to operations.

Currently, the risks or threats include evolving global regulations related to consumption and carbon emissions pricing; lack of technology maturity; supply and demand uncertainty; and the lack of mainstream demand, according to Wael Almazeedi, chief executive at Abu Dhabi-based International Renewable Energy Certification (I-rec) certified firm Avance Energy.

Almazeedi said these risks “need to be mitigated to the satisfaction of project lenders” if the planned green hydrogen projects in the region are to secure financing and reach the construction phase.

The challenges do not necessarily mean all projects will fail, however.

Similar to predecessors such as solar and electrification technologies, the hope is for the planned green hydrogen projects to eventually emerge out of the realm of disillusionment and reach the so-called enlightenment slope and, ultimately, plateaus of productivity, using Gartner’s hype cycle model.

Government support in terms of regulatory frameworks, inevitably including some form of subsidies to bridge the so-called green premium, as well as global certification standards, are at the top of suppliers’ agendas. 

Across the key aspiring Mena clean hydrogen hubs, like the UAE in particular, clearer regulatory frameworks have started to emerge, which could encourage more cohesive cooperation and enable projects to get off the ground.

Key EU countries also appear to remain committed to clean and green hydrogen imports as part of the green deal, while at least one power plant in Japan has completed a three-month trial of co-firing green ammonia with coal “with positive results”.  

But until all these come together to ensure an unencumbered global supply chain, offtakers and project financing deals will likely remain elusive. 

Related reads:


READ THE FEBRUARY MEED BUSINESS REVIEW

Trump unleashes tech opportunities; Doha achieves diplomatic prowess and economic resilience; GCC water developers eye uptick in award activity in 2025.

Published on 1 February 2025 and distributed to senior decision-makers in the region and around the world, the February MEED Business Review includes:

> WATER & WASTEWATER: Water projects require innovation
https://image.digitalinsightresearch.in/uploads/NewsArticle/13370135/main.gif
Jennifer Aguinaldo
Related Articles
  • Houthi truce collapse widens Gulf risk map

    15 July 2026

    Register for MEED’s 14-day trial access 

    The Houthis’ declaration ending the de facto truce with Saudi Arabia has significantly increased the likelihood of renewed attacks on Red Sea shipping and regional infrastructure, broadening the threat environment beyond the Strait of Hormuz.

    S&P Global Market Intelligence says the 13 July exchange is best understood as a potential widening of the renewed US-Iran escalation cycle into the Yemen and Red Sea theatres.

    Houthi claims that Saudi Arabia was responsible for a strike on Sanaa International airport have not been independently confirmed. Saudi Arabia had not formally commented at the time the analysis was written.

    The Yemeni militant group is likely to use the incident as a trigger that allows it to justify renewed military action while aligning with Iran’s wider effort to impose costs on US and Gulf interests, according to the research firm.

    The decision to declare an end to de-escalation with Riyadh materially increases the likelihood of further missile and unmanned aerial vehicle (UAV) activity against infrastructure near the Yemen-Saudi border, as well as renewed pressure on maritime routes in the Red Sea and Bab Al-Mandab.

    Aviation exposure

    The resumption of direct hostilities broadens the range of vessels and ports likely to be subject to Houthi targeting, and presents severe risk to airports and stationary aircraft, S&P Global Market Intelligence says.

    While the Houthis would probably not intentionally down civilian aircraft, there is a significant risk to aircraft in flight, particularly at lower altitudes close to airports, due to incoming UAVs and missiles and interceptor activity.

    The broader risk is to regional logistics rather than any single target set, the analysis says.

    If escalation around the Strait of Hormuz coincides with renewed Houthi activity in the southern Red Sea, Bab Al-Mandab and the Gulf of Aden, commercial operators face a more complex dual-chokepoint environment, with the added likelihood that the Houthis will seek to target Hormuz bypass infrastructure across the Gulf.

    That would raise the likelihood of shipping delays, higher insurance costs, more conservative routing decisions and greater interest in alternative corridors or bypass routes.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17680608/main.jpg
    Colin Foreman
  • Saudi Downtown awards Al-Khobar infrastructure deal

    15 July 2026

    Register for MEED’s 14-day trial access 

    Saudi Downtown Company, a wholly owned subsidiary of the Public Investment Fund (PIF), has awarded a contract for infrastructure works in downtown Al-Khobar.

    The contract was awarded to local contractor Ansab General Contracting Company.

    The scope of work includes the design and development of overall infrastructure, road networks and street lighting for the downtown Al-Khobar project.

    Saudi Downtown Company was officially launched in 2022 by Saudi Crown Prince Mohammed Bin Salman Bin Abdulaziz Al-Saud, who is also chairman of PIF.

    At the time, the company announced plans to develop downtown areas in 12 cities across the kingdom: Medina, Al-Khobar, Al-Ahsa, Buraidah, Najran, Jizan, Hail, Al-Baha, Arar, Taif, Dumat Al-Jandal and Tabuk.

    SDC’s mandate is to develop more than 10 million square metres of land across its projects

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17677176/main.jpg
    Yasir Iqbal
  • Saudi Arabia opens third round of gas-fired IPPs

    15 July 2026

    Register for MEED’s 14-day trial access 

    Principal buyer Saudi Power Procurement Company (SPPC) has opened the qualification process for the third round of conventional independent power projects (IPPs) using combined-cycle gas turbine (CCGT) technology.

    The round is being tendered under the supervision of the Ministry of Energy. Each plant will be built with provision for carbon capture unit readiness, allowing the technology to be deployed at a later stage.

    Each project will be developed on a build-own-operate (BOO) basis, with the winning consortium taking 100% equity in a special purpose vehicle (SPV) set up to develop and operate the plant.

    Each SPV will sign a power purchase agreement with SPPC, which is licensed by the Saudi Electricity Regulatory Authority (SERA) to prepare preliminary studies, tender and award IPPs, and purchase electricity from energy projects in the kingdom.

    The programme forms part of Saudi Arabia’s Circular Carbon Economy approach, which underpins the energy sector element of the Vision 2030 strategy. Riyadh is displacing liquid fuels with natural gas in power generation to cut emissions intensity, while designing new plants so that carbon capture equipment can be retrofitted in support of national emissions targets.

    In April, Acwa and Saudi Energy (formerly Saudi Electricity Company) signed a 31-year power purchase agreement (PPA) with SPPC for the Rabigh 2 IPP expansion.

    The project involves the development of a CCGT plant in the Mecca region. It will have a total capacity of 2,313.5MW.

    The contract is valued at SR11.5bn ($3.07bn), the companies said in separate stock exchange filings.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17676286/main.jpg
    Colin Foreman
  • Dubai selects contractor for Al-Maktoum airport people mover

    15 July 2026

     

    Register for MEED’s 14-day trial access 

    Dubai Aviation Engineering Projects (DAEP) has selected a contractor to deliver the automated people-mover system as part of the first phase of the $35bn expansion of Al-Maktoum International airport.

    A team of Japan’s Mitsubishi Corporation and Indian contractor Larsen & Toubro is the selected contractor.

    The automated people-mover system will serve as a critical facility for operations at Al-Maktoum International airport. The system will run under the apron of the entire airfield and the airport’s terminals. It will consist of multiple tracks, taking passengers from the terminals to the concourses.

    Four underground stations will be built as part of the first phase. The overall plan includes 14 stations across the airport.

    The firms submitted the bids for the project in July last year, as MEED exclusively reported.

    The contract is the latest in a series of awards signed by DAEP recently. DAEP has awarded contracts valued at about AED13bn, with construction works currently under way on several airport packages.

    These include enabling works, the second runway, and the initial structural foundations for passenger terminals and gates.

    Upcoming awards

    In June, DAEP said that it will award contracts worth over AED55bn ($15bn) by the end of this year for construction works at Al-Maktoum International airport.

    The projects slated for contract awards include the substructure works for the Western Passenger Terminal, the fourth aircraft concourse building and the baggage handling system, in addition to the superstructure works for the Western Passenger Terminal and the first, second and third aircraft concourses.

    The packages also encompass long-span structural frameworks for buildings covering about 1.5 million square metres (sq m), infrastructure works for the southern airfield area, and power generation and district cooling plants supporting the construction programme.

    The award of the facade and roofing packages is also planned for this year.

    Construction progress

    In May last year, MEED exclusively reported that DAEP had awarded a AED1bn ($272m) deal to UAE firm Binladin Contracting Group to construct the second runway at the airport.

    The enabling works on the terminal were awarded to Abu Dhabi-based Tristar E&C.

    Construction on the project’s first phase is expected to be completed by 2032.

    Construction on substructure works began in November last year, when DAEP formally selected a contractor to deliver the package.

    The government approved the updated designs and timelines for its largest construction project in April 2024.

    In a statement, the authorities said the plan is for all operations from Dubai International airport to be transferred to Al-Maktoum International within 10 years.

    According to an official description on DAEP’s website, the expanded airport’s West Terminal will be a seven-level, 800,000 sq m facility with an annual capacity of 45 million passengers.

    It will be the second of three terminals at Al-Maktoum International airport.

    In September 2024, MEED exclusively reported that a team comprising Austria’s Coop Himmelb(l)au and Lebanon’s Dar Al-Handasah had been confirmed as the lead masterplanning and design consultants on the expansion of Al-Maktoum airport.

    The airport’s construction is planned to be undertaken in three phases. The airport will cover an area of 70 square kilometres south of Dubai and will have five parallel runways and 430 aircraft gates.

    It will be five times the size of the existing Dubai International airport and will have the world’s largest passenger-handling capacity of 260 million passengers a year. For cargo, it will have the capacity to handle 12 million tonnes a year.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17674721/main.png
    Yasir Iqbal
  • Chinese contractor wins Kuwait investment authority HQ

    15 July 2026

    Register for MEED’s 14-day trial access 

    Beijing-headquartered China State Construction Engineering Corporation (CSCEC) has won a contract to build the permanent headquarters of the Kuwait Direct Investment Promotion Authority (KDIPA).

    The contract covers the construction of a 275-metre, 55-storey office tower located in Kuwait City’s Sharq district. The project is expected to be completed by 2028.

    According to results published on the Kuwait Central Agency for Public Tenders (Capt) website, the firm initially submitted a bid of $233m, as MEED reported in January. The tender was issued on 19 October 2025 and bids were submitted on 18 November, MEED reported.

    The contract is the latest in a series of high-profile projects signed by CSCEC in the GCC region this year. Last month, it won a contract to deliver the Janadriyah cultural district at Qiddiya entertainment city on the outskirts of Riyadh. The contract was awarded by gigaproject developer Qiddiya Investment Company (QIC).

    The scope covers the construction of six structures, including a heritage building, a gateway hotel, a wadi hotel, a creative hub, a community centre and an open-air market.

    In June, MEED exclusively reported that QIC had awarded CSCEC a contract to build a new transport hub at Qiddiya entertainment city.

    The project is located within the resort core zone of the development.

    Kuwait market overview

    UK analytics firm GlobalData expects Kuwait’s construction industry to average annual growth of 4.9% in 2026-29, supported by government investment in renewable energy and transport infrastructure.

    In September 2025, Kuwait’s government allocated KD1.3bn ($4.2bn) for 141 projects, as part of its capital spending during the fiscal year 2025-26. This allocation was intended for 162 current projects and 17 new projects.

    According to government data, as of September 2025, the country had around 300 active projects, valued at about KD35.3bn ($115bn), with large infrastructure projects making up nearly half of that total.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17674440/main.jpg
    Yasir Iqbal