Aramco receives bids for three offshore tenders

2 May 2025

Saudi Aramco has received bids from contractors in its Long-Term Agreement (LTA) pool of offshore service providers for three tenders related to the engineering, procurement, construction and installation (EPCI) of structures at several offshore oil and gas fields.

The tenders are numbers 158, 159 and 160 on Aramco’s Contracts Release and Purchase Order (CRPO) system.

Offshore LTA contractors submitted bids for these CRPOs by the deadline of 27 April, sources told MEED.

The Saudi energy giant issued CRPOs 158, 159 and 160 to its offshore LTA contractors in late November and set an initial bid submission deadline of 15 January. The bid submission deadline was extended several times, to 26 January24 February19 March13 April and 20 April.

The scope of work on CRPO 158 covers the EPCI of 11 jackets at several offshore fields, including Abu Safah, Berri and Manifa. Aramco has stipulated that three of the jackets must be fabricated in the kingdom.

CRPO 159 involves the EPCI of three production deck modules at the Abu Safah, Berri and Manifa offshore fields.

CRPO 160 relates to the EPCI of three more production deck modules at the Abu Safah, Berri and Manifa offshore fields.

Aramco’s LTA pool of offshore service providers comprises the following entities:

  • Saipem (Italy)
  • McDermott International (US)
  • Larsen & Toubro Energy Hydrocarbon (LTEH, India) / Subsea7 (UK)
  • NMDC Energy (UAE)
  • Lamprell (UAE/Saudi Arabia)
  • China Offshore Oil Engineering Company (China)
  • Dynamic Industries (US)
  • Sapura Energy (Malaysia)
  • TechnipFMC (France) / MMHE (Malaysia)
  • Hyundai Heavy Industries (South Korea)

Aramco recently renewed LTAs with the following contractors, whose contracts had either lapsed or were close to expiry:

  • Saipem
  • McDermott International
  • Larsen & Toubro Energy Hydrocarbon / Subsea7
  • NMDC Energy
  • Lamprell
  • China Offshore Oil Engineering Company
Robust offshore spending

In January last year, the Saudi Energy Ministry directed Aramco to abandon its campaign to expand its oil production spare capacity from 12 million barrels a day (b/d) to 13 million b/d by 2027. As a direct consequence of that government decision, Aramco cancelled the tendering process for at least 15 tenders involving the EPCI of structures at offshore oil and gas fields.

Since that decision, however, the Saudi energy giant has gone the other way, spending an estimated $5bn in 2024 on offshore EPCI contracts.

Italian contractor Saipem was the biggest beneficiary of Aramco’s robust offshore spending, winning five of the eight CRPOs awarded last year.

In early May, Aramco awarded Saipem the contract for CRPO 143, which involves replacing an oil line between the Berri and Manifa oil fields in the kingdom’s Gulf waters.

Aramco then awarded Saipem the contract for CRPO 138, which involves laying a trunkline at the Abu Safah offshore field. The contract is estimated to be worth $500m.

The Milan-listed contractor then scooped three major CRPOs in August, starting with CRPOs 132 and 139, the combined value of which is estimated to be about $1bn. In early September, Saipem began work on the two contracts, which involve the EPCI of structures to upgrade the Marjan, Zuluf and Safaniya offshore field developments.

Just days after awarding CRPOs 132 and 139 to Saipem, Aramco awarded the Italian contractor CRPO 127, a $2bn contract that involves the EPCI of topsides and jackets for wellhead platforms, a tie-in platform jacket and topside, rigid flowlines, submarine composite cables and fibre optic cables at the Marjan oil and gas field.

In late November, Aramco awarded three CRPOs, worth more than $500m. China Offshore Oil Engineering Company (COOEC) won CRPOs 149 and 152, which are estimated to be valued at $30m and $250m-$300m, respectively. UK-based Subsea7 secured CRPO 153, which is said to be valued at $200m-$250m.

Offshore jobs under bidding

Looking ahead, Aramco is in the bid evaluation and tendering stages for 11 more offshore tenders, including CRPOs 158, 159 and 160.

MEED recently reported that Aramco had requested LTA contractors who submitted bids for CRPO 150 – which involves the installation of structures at its offshore Northern Area Oil Operations – to extend the validity of their bids until the end of June.

Additionally, Aramco is reviewing bids it has received for four CRPOs – numbers 145, 146, 147 and 148 – that represent the further expansion of the Zuluf field development.

Offshore LTA contractors submitted bids for these four tenders, which are estimated to be worth a total of $6bn, in December, with the contract awards due in the second quarter of this year.

Separately, LTA contractors are preparing bids for CRPO 157, which mainly covers the EPCI of a 48-inch trunkline covering a distance of 60 kilometres at the Zuluf field development, along with dredging works onshore.

Aramco has also sought proposals for CRPOs 154, 155 and 156, which cover the next expansion phase of the Safaniya field. Offshore LTA contractors are due to submit bids for these three tenders by 31 July.

https://image.digitalinsightresearch.in/uploads/NewsArticle/13803814/main4158.jpeg
Indrajit Sen
Related Articles
  • What actually slows a gigaproject down

    9 September 2026

     

    Ask anyone delivering a major programme in the GCC what causes delays and sequencing will come up early. Utilities go in too late. Approvals lag behind construction. Stations, depots and access roads are procured as if they belong to different projects rather than one system.

    “None of this is new. The industry has understood these risks for years,” says Alan Caldwell, managing director for transport and infrastructure at WSP Middle East.

    For Caldwell, that is what makes the pattern worth interrogating rather than simply restating.

    “The more important question is why the same issues around interfaces, approvals, stakeholder alignment and delivery sequencing continue to slow major programmes when the risks are already so well understood,” he says.

    The answer, he argues, is not that these programmes are too big or too technically complex. What breaks a schedule is a wider system delivered as a set of disconnected parts; an approval sitting with an authority team with no visibility of the construction sequence downstream; or a station package proceeding without the utilities diversion it depends on.

    “Infrastructure programmes do not struggle because a railway is too large or a highway network is too complex,” Caldwell says. “They encounter difficulties when interconnected elements are delivered in the wrong order.”

    Sequencing decisions are rarely purely technical either, he adds. They are commercial – shaped by which assets need to unlock value first, which phases are tied to funding, and where sales or investment assumptions depend on infrastructure landing in a particular order.

    Approvals sit at the centre of that logic. On many programmes, they become one of the biggest sources of lost time – not because the requirements are unreasonable, but because approvals are not planned, evidenced or owned as part of the delivery logic from day one.

    Caldwell has seen the same pattern across three decades of Gulf delivery, from early work on Palm Jumeirah to today’s region-wide transport programmes.

    “The decisive factor has often been the same: whether interfaces, approvals, responsibilities and delivery sequencing are aligned early enough to prevent complexity becoming delay.”

    Integration needs to be well understood

    “Most programme teams in the region would say they understand the need for integration,” Caldwell says. Fewer are structured to deliver it. “The harder task is turning that understanding into the way projects are actually set up and managed,” he argues.

    Riyadh Metro is the reference point he returns to, precisely because engineering complexity was not the deciding factor in its delivery.

    Coordinating a city-scale transport system meant aligning design, construction, systems, utilities and stakeholder interfaces across every delivery vertical.

    “The lesson for the region today is clear,” Caldwell says. “Ambitious programmes need a delivery model that gives every contributor a shared view of progress, risk, decision-making and the business case driving programme priorities.”

    That shared view, he argues, will be what the next phase of Gulf delivery is judged on.

    Whether clients, consultants, contractors, operators and approval authorities can work to a single delivery logic will be key.

    “This requires more than coordination meetings. It requires integrated ways of working, shared common data environments and governance structures that make risks, decisions and dependencies visible before they become delays,” he says.

    From reporting progress to managing risk before it lands

    Digital tools have a role here, Caldwell says, but not as a headline in themselves.

    Digital twins, programme visualisation and data-led modelling matter only if they help teams identify and address problems before they affect the wider programme.

    “The real value is not technology for its own sake,” he says. “It is the ability to see, in one place, where approvals are outstanding, where interfaces are unresolved, where programme dates are slipping, where clashes are emerging and where decisions need to be escalated."

    None of it works without governance behind it, he cautions. “A dashboard will not resolve a delayed approval if nobody knows who owns the decision, when it needs to be made, or how it should be escalated.”

    Data only has value if the processes and responsibilities around it are clear, which is why Caldwell frames the shift the region needs not as digitisation, but as a move “from programme management as a discipline focused mainly on reporting and coordination, and towards project and programme intelligence”.

    With many of the region’s programmes running for a decade or more, he adds, delivery models also need to flex as funding assumptions, user needs and policy priorities change along the way.

    “The ambition behind the Gulf’s transformation programmes is not in question,” Caldwell says.

    What will determine how much of it is realised on time is whether delivery models evolve at the same pace: earlier integration, clearer approval pathways, shared data environments, and every contributor working to a delivery logic that connects technical sequencing with the funding and operational case behind it.

    “The region’s next challenge is not imagining bigger projects,” he says. “It is changing the way they are delivered, operated and adapted over time.”

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19502016/main.gif
    Yasir Iqbal
  • Jordan tenders advisory for wastewater treatment plant

    9 September 2026

    The Water Authority Jordan (WAJ) has issued an invitation to prequalify for advisory services for the rehabilitation and expansion of the Shallala wastewater treatment plant in Irbid, northern Jordan.

    The Shallala plant was commissioned in 2013 with a design capacity of about 14,000 cubic metres a day (cm/d).

    The rehabilitation and expansion project will increase its treatment capacity to about 30,500 cm/d to meet projected wastewater flows through 2050.

    The PIU Support and Construction Supervision Consultancy Services tender was released on 19 August.

    The submission deadline is 21 September.

    The consultancy will support the project implementation unit and provide construction supervision services for the project. The project has an estimated value of $69m and is being financed by the European Bank for Reconstruction and Development.

    The planned works include rehabilitating the existing activated sludge and treatment units and constructing a new treatment train.

    The scope also includes installing biogas combined heat and power units, improving sludge handling and dewatering systems, and installing odour control and chemical containment systems.

    WAJ is also undertaking the upgrade and expansion of the Ain Ghazal wastewater treatment plant in Amman.

    The existing facility had a capacity of 330,000 cm/d and is being upgraded to 726,712 cm/d to accept and treat expected incoming flows until 2045.

    The local Arab Towers Contracting Company was appointed as the main contractor for the project last year.


    READ THE SEPTEMBER 2026 MEED BUSINESS REVIEW – click here to view PDF

    Nuclear power ambitions gather pace; Kuwait keeps dealmaking alive despite war; Region invests in raising gas processing capacity.

    Distributed to senior decision-makers in the region and around the world, the September 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/19498520/main.jpg
    Mark Dowdall
  • Medina’s KEC signs real estate project development deal

    9 September 2026

    Medina’s Knowledge Economic City (KEC) has signed an agreement with Riyadh-based Kaden Investment Company to develop a mixed-use project in Medina.

    The project will have an estimated gross floor area of about 230,000 square metres (sq m).

    According to a statement filed by KEC with the Saudi Exchange (Tadawul), the project – called Multaqa Al-Madinah 2 – will be built on a 92,000 sq m plot located directly north of the first phase of the Multaqa Al-Madinah development.

    It is expected to include about 1,527 residential units across three residential zones, along with commercial and office space totalling about 31,108 sq m of net leasable area.

    It will also feature parking, recreational and service facilities, landscaping and other supporting infrastructure.

    KEC and Kaden intend to deliver the project through a closed-ended real estate investment fund regulated by Saudi Arabia’s Capital Market Authority.

    Under the proposed structure, KEC will contribute the land as an in-kind contribution and hold 75% of the fund units, while Kaden will contribute cash and hold the remaining 25%.

    Kaden will also serve as the development manager.

    KEC said the land has been initially valued at about SR692.3m ($184.6m), while the total equity required for the project is estimated at around SR833m.

    Once final agreements are signed, KEC expects to receive SR67.7m in cash and fund units valued at approximately SR624.6m.


    READ THE SEPTEMBER 2026 MEED BUSINESS REVIEW – click here to view PDF

    Nuclear power ambitions gather pace; Kuwait keeps dealmaking alive despite war; Region invests in raising gas processing capacity.

    Distributed to senior decision-makers in the region and around the world, the September 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/19492407/main.png
    Yasir Iqbal
  • Morocco signs agreement for synthetic fuel complex

    9 September 2026

    Switzerland-based Synhelion has signed an agreement with the Government of Morocco with the aim of developing a large-scale commercial synthetic fuel plant in the country’s southern Tan-Tan province.

    The memorandum of understanding (MoU) relates to a facility with the capacity to produce 100,000 tonnes a year of fuel, according to a statement released by the company.

    Synhelion has secured land for the project site and established a subsidiary in Morocco to develop the fuel complex.

    Gianluca Ambrosetti, one of Synhelion’s co-chief executives, said: “Morocco’s exceptional renewable energy resources and its clear industrial strategy make it an ideal location for scaling our synthetic fuel technology.

    “With the MoU signed, the land reservation secured and our branch in place, we are moving from evaluation to execution and toward our first commercial-scale plant in the region.”

    Synhelion specialises in producing hydrocarbon fuels using renewable energy. Its products include synthetic jet fuel, gasoline and diesel.


    READ THE SEPTEMBER 2026 MEED BUSINESS REVIEW – click here to view PDF

    Nuclear power ambitions gather pace; Kuwait keeps dealmaking alive despite war; Region invests in raising gas processing capacity.

    Distributed to senior decision-makers in the region and around the world, the September 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/19489903/main.jpg
    Wil Crisp
  • Iraq solar package on track to come online in December

    9 September 2026

     

    The 1,000MW solar photovoltaic project in Artawi – also called Ratawi – in southern Iraq is on track for its second phase to come online on 8 December, according to industry sources.

    This phase has a capacity of 250MW and will bring the project’s total online capacity to 500MW.

    The first phase of the project, also with a capacity of 250MW, came online in March this year.

    The third and fourth phases, each with a capacity of 250MW, are expected to be brought online next year.

    The solar project is part of the broader Gas Growth Integrated Project (GGIP), which has an estimated total value of $27bn and a first phase worth an estimated $10bn.

    The solar project’s ownership differs from the headline GGIP ownership structure, with its ownership equally divided between France’s TotalEnergies and QatarEnergy.

    The wider GGIP consortium includes TotalEnergies, Iraq’s Basra Oil Company and QatarEnergy, which hold stakes of 45%, 30% and 25%, respectively.

    China Energy Engineering Corporation is part of a consortium that is executing the main engineering, procurement and construction contract for the project.

    It announced that the first 250MW of capacity had been connected to the grid on 4 March this year.

    The consortium also includes China Energy Engineering Group Tianjin Electric Power Construction Company and Chengdu-headquartered Southwest Electric Power Design Institute Company.

    The project scope includes:

    • Construction of a substation
    • Installation of a 132kV booster station
    • Installation of solar panels
    • Installation of transformers
    • Laying of transmission lines
    • Construction of related infrastructure

    In February 2025, Basra Investment Commission director Alaa Abdul Hussein said the solar plant had an estimated total value of $820m.

    The GGIP programme is focused on developing four major projects in Iraq:

    • The Common Seawater Supply Project (CSSP)
    • The Ratawi gas processing complex
    • The 1GW solar power project for Iraq’s electricity ministry
    • A field development project at Ratawi, known as the Associated Gas Upstream Project (AGUP)

    All four of these projects are currently under execution, though there have been some delays related to the regional war that started when the US and Israel attacked Iran on 28 February.

    The conflict has caused significant disruption to shipping through the Strait of Hormuz, which Iraq uses to export crude oil and import equipment and materials for projects.


    READ THE SEPTEMBER 2026 MEED BUSINESS REVIEW – click here to view PDF

    Nuclear power ambitions gather pace; Kuwait keeps dealmaking alive despite war; Region invests in raising gas processing capacity.

    Distributed to senior decision-makers in the region and around the world, the September 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/19489818/main.jpg
    Wil Crisp