Aramco’s recalibrated chemicals goals reflect realism

26 March 2025

 

Saudi Aramco told consultants and contractors last year that it was revisiting its investment strategy and execution approach for its liquids-to-chemicals programme.

The central ambition of the strategic programme is to derive greater economic value from every barrel of crude produced in Saudi Arabia by converting 4 million barrels a day (b/d) of Aramco’s oil production into high-value petrochemicals and chemicals feedstocks by 2030.

Aramco and its subsidiary, Saudi Basic Industries Corporation (Sabic), had been tasked with establishing 10-11 large mixed-feed crackers by 2030. These petrochemicals crackers, which included greenfield developments and expansions of existing facilities, were to be built both in Saudi Arabia and in overseas markets.

Achieving this ambition required Aramco and Sabic – the main stakeholders in the liquids-to-chemicals programme – to invest a sum of up to $100bn. Amid considerable cost pressures and significant overcapacity in the global chemicals sector, pushing forward with such a capital-intensive campaign was hard to justify. 

However, while Aramco may have streamlined the programme’s remit, the primary goal of attaining a liquids-to-chemicals conversion rate of 4 million b/d within its global portfolio remains unchanged.

In a presentation detailing Aramco’s financial performance and operational activities in 2024, president and CEO Amin Nasser stated that the company had achieved 45% of the target of the liquids-to-chemicals programme as of the end of last year. Also, 53% of Aramco’s crude oil production is utilised by the downstream sector.

This has been achieved through “greater capital efficiency with low-equity and a high-placement strategy”, Nasser said in the presentation.

Moreover, large-scale petrochemicals projects undertaken by Aramco’s joint ventures with foreign partners in South Korea and Saudi Arabia, namely the Shaheen and Amiral developments, respectively, will significantly contribute to the liquids-to-chemicals target when they come online in 2026 and 2027.

Key chemical projects advance

Aramco continues to make progress with projects deemed crucial to its long-term petrochemicals objectives. One such project is the expansion of Aramco affiliate, Saudi Aramco Jubail Refinery Company (Sasref), into the petrochemicals sector.

Aramco has brought China-based Rongsheng Petrochemical Company on board as a joint-venture partner for the proposed project, which is part of the liquids-to-chemicals programme.

Their aim is to convert the Sasref refining complex in Jubail into an integrated refinery and petrochemicals complex by adding a mixed-feed cracker. The project also involves building an ethane cracker that will draw feedstock from the Sasref refinery.

The project is in the pre-front-end engineering and design (pre-feed) stage, with Aramco previously saying that the construction of large-scale steam crackers and the integration of associated downstream derivatives into the existing Sasref complex would enhance “its ability to meet growing demand for high-quality petrochemical products”.

Meanwhile, Sabic is in the bid evaluation stage with a major project that involves building an integrated blue ammonia and urea manufacturing complex at the existing facility of its affiliate, Sabic Agri-Nutrients Company, in Jubail. 

The estimated $3bn project, called the low-carbon hydrogen San 6 complex, is part of Sabic’s Horizon-I low-carbon hydrogen (LCH) programme. Contractors submitted bids for the project in March last year.

The San 6 complex will have an output capacity of 3,500 metric tonnes a day, or 1.17 million tonnes a year (t/y), of blue ammonia, and a urea production capacity of 3,850 metric tonnes a day, or 1.28 million t/y.

Carbon dioxide (CO2) from the blue ammonia plant will be utilised for urea production, with surplus CO2 from the ammonia plant and post-combustion carbon capture unit to be exported via a third-party pipeline for subsequent sequestration.

Gas transportation and processing projects

Saudi Arabia was the biggest regional spender on midstream and downstream projects last year. To address incremental volumes of gas entering the grid as Aramco increases its conventional and unconventional gas production, the state enterprise spent more than $17bn on gas processing and transportation projects in 2024.

In April last year, Aramco awarded $7.7bn in engineering, procurement and construction (EPC) contracts for a project to expand the Fadhili gas plant in the Eastern Province of Saudi Arabia. The project is expected to increase the plant’s processing capacity from 2.5 billion cubic feet a day (cf/d) to up to 4 billion cf/d.

In June, Aramco awarded 15 lump-sum turnkey contracts for the third expansion phase of the Master Gas System (MGS-3), worth $8.8bn. Then, in August, the company awarded contracts for the remaining two packages of the MGS-3 project, which were worth $1bn. 

Saudi Aramco divided EPC works on the MGS-3 project into 17 packages. The first two packages involve upgrading existing gas compression systems and installing new gas compressors. The 15 other packages relate to laying gas transport pipelines at various locations in the kingdom.

The Master Gas System expansion will increase the size of the network and raise its total capacity by an additional 3.15 billion cf/d by 2028, with the installation of about 4,000 kilometres of pipelines and 17 new gas compression trains.

So far this year, the Saudi energy giant has selected the main contractor for a major project to develop a large-scale carbon capture and storage (CCS) hub in Jubail Industrial City.

India’s Larsen & Toubro Energy Hydrocarbon has been picked to perform EPC work on the first phase of the project, which is called the Accelerated Carbon Capture and Sequestration (ACCS) scheme, worth $1.5bn.

The aim of the ACCS scheme, which is expected to have nine phases in total, is to capture CO2 from Aramco’s northern gas plants at Wasit, Fadhili and Khursaniyah, as well as from the operations of Sabic and Saudi industrial gases provider Air Products Qudra.

The first phase of the ACCS project will have the capacity to store and sequester up to 9 million t/y of CO2 in the planned CCS hub in Jubail. The main facility that will be built in Jubail will capture streams from the acid gas enrichment units of the Wasit, Fadhili and Khursaniyah plants. The CO2 will be compressed, dried and fed into the collection pipeline system.


MEED’s April 2025 report on Saudi Arabia also includes:

> UPSTREAM: Saudi oil and gas spending to surpass 2024 level
> POWER: Saudi power sector enters busiest year
> WATER: Saudi water contracts set another annual record
> CONSTRUCTION: Reprioritisation underpins Saudi construction
> TRANSPORT: Riyadh pushes ahead with infrastructure development
> BANKING:
 Saudi banks work to keep pace with credit expansion

https://image.digitalinsightresearch.in/uploads/NewsArticle/13477916/main.gif
Indrajit Sen
Related Articles
  • Oil prices rise above $100 a barrel as conflict escalates

    9 September 2026

    Register for MEED’s 14-day trial access 

    Oil prices rose above $100 a barrel on 9 September for the first time since July as the US-Iran conflict escalated and Iran-backed Houthi forces attacked Saudi energy infrastructure.

    Brent crude futures reached $100.95 a barrel, while US benchmark West Texas Intermediate (WTI) rose to $95.60. Brent had last traded above $100 on 24 July.

    The latest escalation has heightened concerns about oil supplies from the region, with shipping through both the Strait of Hormuz and the Red Sea facing disruption.

    Flows through the Strait of Hormuz had fallen below 2 million barrels a day (b/d) from about 8-9 million b/d before the latest escalation, according to Rystad Energy.

    At the same time, Houthi attacks on Saudi Arabia threaten another important route for oil exports, with the group targeting energy infrastructure and shipping in and around the Red Sea.

    US strikes on Iranian tankers

    US forces destroyed five Iranian crude oil carriers on 8 September after Iran’s Islamic Revolutionary Guard Corps (IRGC) targeted a US Navy warship with ballistic missiles.

    The US Central Command (Centcom) said the warship successfully evaded two Iranian attacks and that no US personnel were harmed.

    Four of the Iranian vessels – Kaviz, Charminar, Horizon 1 and Riesco – were struck in the Gulf of Oman, while the Derya was attacked near Kharg Island, Iran’s main crude export hub.

    The M/T Riesco subsequently sank in the Gulf of Oman, according to Centcom.

    Iran responded by launching ballistic missiles towards Jordan. Jordan’s armed forces said 18 of 20 missiles were intercepted, with the remaining two falling in unpopulated areas.

    Iran’s IRGC also said it had attacked two US naval vessels, eight oil tankers and 10 other vessels in the Gulf, although it did not identify the vessels or provide evidence of the attacks.

    The latest exchanges mark a further escalation in the US-Iran conflict, which began on 28 February.

    Houthi attacks raise supply concerns

    The conflict has also widened into a renewed confrontation between Saudi Arabia and Yemen’s Iran-backed Houthi movement.

    On 8 September, Saudi authorities said Houthi attacks had targeted civilian and economic sites in Abha, Khamis Mushait, Jazan and Najran in the south of the kingdom, injuring 73 people.

    Saudi Arabia’s Ministry of Energy said several energy sector facilities and installations had been targeted, causing fires and forcing a temporary halt to some operations.

    The Houthis said their attacks were in response to Saudi military action in Yemen, including what they described as attacks on Houthi positions and a Saudi blockade of ports and airports.

    Riyadh condemns attacks

    Saudi Arabia has strongly condemned the Houthi attacks and warned that it would take measures to defend its territory and national assets.

    In a statement on 8 September, the Ministry of Energy said authorities were working to address the impact of the attacks and ensure the safety of facilities and personnel while maintaining operations in accordance with approved plans.

    Saudi Arabia’s Ministry of Foreign Affairs also condemned the attacks and said the kingdom had the right to take measures to defend its sovereignty and protect its citizens, residents and national assets.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19505512/main0138.jpg
    Indrajit Sen
  • What actually slows a gigaproject down

    9 September 2026

     

    Ask anyone delivering a major programme in the GCC what causes delays and sequencing will come up early. Utilities go in too late. Approvals lag behind construction. Stations, depots and access roads are procured as if they belong to different projects rather than one system.

    “None of this is new. The industry has understood these risks for years,” says Alan Caldwell, managing director for transport and infrastructure at WSP Middle East.

    For Caldwell, that is what makes the pattern worth interrogating rather than simply restating.

    “The more important question is why the same issues around interfaces, approvals, stakeholder alignment and delivery sequencing continue to slow major programmes when the risks are already so well understood,” he says.

    The answer, he argues, is not that these programmes are too big or too technically complex. What breaks a schedule is a wider system delivered as a set of disconnected parts; an approval sitting with an authority team with no visibility of the construction sequence downstream; or a station package proceeding without the utilities diversion it depends on.

    “Infrastructure programmes do not struggle because a railway is too large or a highway network is too complex,” Caldwell says. “They encounter difficulties when interconnected elements are delivered in the wrong order.”

    Sequencing decisions are rarely purely technical either, he adds. They are commercial – shaped by which assets need to unlock value first, which phases are tied to funding, and where sales or investment assumptions depend on infrastructure landing in a particular order.

    Approvals sit at the centre of that logic. On many programmes, they become one of the biggest sources of lost time – not because the requirements are unreasonable, but because approvals are not planned, evidenced or owned as part of the delivery logic from day one.

    Caldwell has seen the same pattern across three decades of Gulf delivery, from early work on Palm Jumeirah to today’s region-wide transport programmes.

    “The decisive factor has often been the same: whether interfaces, approvals, responsibilities and delivery sequencing are aligned early enough to prevent complexity becoming delay.”

    Integration needs to be well understood

    “Most programme teams in the region would say they understand the need for integration,” Caldwell says. Fewer are structured to deliver it. “The harder task is turning that understanding into the way projects are actually set up and managed,” he argues.

    Riyadh Metro is the reference point he returns to, precisely because engineering complexity was not the deciding factor in its delivery.

    Coordinating a city-scale transport system meant aligning design, construction, systems, utilities and stakeholder interfaces across every delivery vertical.

    “The lesson for the region today is clear,” Caldwell says. “Ambitious programmes need a delivery model that gives every contributor a shared view of progress, risk, decision-making and the business case driving programme priorities.”

    That shared view, he argues, will be what the next phase of Gulf delivery is judged on.

    Whether clients, consultants, contractors, operators and approval authorities can work to a single delivery logic will be key.

    “This requires more than coordination meetings. It requires integrated ways of working, shared common data environments and governance structures that make risks, decisions and dependencies visible before they become delays,” he says.

    From reporting progress to managing risk before it lands

    Digital tools have a role here, Caldwell says, but not as a headline in themselves.

    Digital twins, programme visualisation and data-led modelling matter only if they help teams identify and address problems before they affect the wider programme.

    “The real value is not technology for its own sake,” he says. “It is the ability to see, in one place, where approvals are outstanding, where interfaces are unresolved, where programme dates are slipping, where clashes are emerging and where decisions need to be escalated."

    None of it works without governance behind it, he cautions. “A dashboard will not resolve a delayed approval if nobody knows who owns the decision, when it needs to be made, or how it should be escalated.”

    Data only has value if the processes and responsibilities around it are clear, which is why Caldwell frames the shift the region needs not as digitisation, but as a move “from programme management as a discipline focused mainly on reporting and coordination, and towards project and programme intelligence”.

    With many of the region’s programmes running for a decade or more, he adds, delivery models also need to flex as funding assumptions, user needs and policy priorities change along the way.

    “The ambition behind the Gulf’s transformation programmes is not in question,” Caldwell says.

    What will determine how much of it is realised on time is whether delivery models evolve at the same pace: earlier integration, clearer approval pathways, shared data environments, and every contributor working to a delivery logic that connects technical sequencing with the funding and operational case behind it.

    “The region’s next challenge is not imagining bigger projects,” he says. “It is changing the way they are delivered, operated and adapted over time.”

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19502016/main.gif
    Yasir Iqbal
  • Qatari firm wins $221m Qiddiya stadium MEP deal

    9 September 2026

     

    Register for MEED’s 14-day trial access 

    Qatari contractor Elegancia MEP, part of Estithmar Holding, has won a SR829m ($221m) mechanical package contract for the Prince Mohammed Bin Salman Stadium in Qiddiya, Saudi Arabia.

    The contract covers full mechanical, electrical and plumbing (MEP) works for the stadium, and is Elegancia MEP’s largest award in Saudi Arabia to date.

    The 45,000-seat stadium will feature a fully combined retractable pitch, roof and LED wall.

    The stadium’s main construction works are being undertaken by a joint venture of Spanish firm FCC Construction and local firm Nesma & Partners.

    Saudi gigaproject developer Qiddiya Investment Company awarded an estimated SR15bn ($4bn) deal to build the stadium in October 2024, as MEED exclusively reported.

    The contract covered the construction of a multipurpose stadium on top of the 200-metre-high Tuwaiq cliff in the new sports and entertainment district of Qiddiya City.

    Once completed, the stadium will be the home ground for Saudi Pro League football clubs Al-Nassr and Al-Hilal.

    US-based architect Populous is the project consultant.

    The stadium is one of the venues for the kingdom’s 2034 Fifa World Cup bid and will host events such as the Saudi King Cup, the Asian Cup and the 2034 Asian Games.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19501493/main.jpg
    Yasir Iqbal
  • Jordan tenders advisory for wastewater treatment plant

    9 September 2026

    The Water Authority Jordan (WAJ) has issued an invitation to prequalify for advisory services for the rehabilitation and expansion of the Shallala wastewater treatment plant in Irbid, northern Jordan.

    The Shallala plant was commissioned in 2013 with a design capacity of about 14,000 cubic metres a day (cm/d).

    The rehabilitation and expansion project will increase its treatment capacity to about 30,500 cm/d to meet projected wastewater flows through 2050.

    The PIU Support and Construction Supervision Consultancy Services tender was released on 19 August.

    The submission deadline is 21 September.

    The consultancy will support the project implementation unit and provide construction supervision services for the project. The project has an estimated value of $69m and is being financed by the European Bank for Reconstruction and Development.

    The planned works include rehabilitating the existing activated sludge and treatment units and constructing a new treatment train.

    The scope also includes installing biogas combined heat and power units, improving sludge handling and dewatering systems, and installing odour control and chemical containment systems.

    WAJ is also undertaking the upgrade and expansion of the Ain Ghazal wastewater treatment plant in Amman.

    The existing facility had a capacity of 330,000 cm/d and is being upgraded to 726,712 cm/d to accept and treat expected incoming flows until 2045.

    The local Arab Towers Contracting Company was appointed as the main contractor for the project last year.


    READ THE SEPTEMBER 2026 MEED BUSINESS REVIEW – click here to view PDF

    Nuclear power ambitions gather pace; Kuwait keeps dealmaking alive despite war; Region invests in raising gas processing capacity.

    Distributed to senior decision-makers in the region and around the world, the September 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/19498520/main.jpg
    Mark Dowdall
  • Consultants bid for Abu Dhabi light rail project management

    9 September 2026

     

    Register for MEED’s 14-day trial access 

    Abu Dhabi Transport Company (ADTC) has issued a request for prequalification (RFQ) notice to consultants for a contract for project management engineering consultancy services for the first phase of the light rail transit network, also known as ADT4.

    The notice was issued on 7 September, with a submission deadline of 9 November.

    The project’s first phase will span 19 kilometres (km) and include 23 stations, connecting Zayed International airport (AUH) with nearby areas, including Yas Island, Al‑Raha Beach and Khalifa City.

    The key sections of the tram are:

    AUH to Yas Island: The tram will start from Terminal A at AUH and run through the Yas tunnel to Yas Gateway Park. It will serve areas including Yas Bay, Media Zone, Yas Plaza, Yas Drive, Yas Mall, Sea World and Water Edge.

    This section covers 13km and includes 13 at-grade stations and one underground station.

    Al-Raha: This section will stretch for 4.3km and run along Al-Raha Street. It will serve areas including Al-Zeina, Al-Muneera and Al-Bandar, towards the Aldar head office. The section will include seven at-grade stations.

    Etihad Plaza: This section will pass the Etihad Aviation Training Centre and span about 1.7km. It will feature a main depot near the Etihad Airways headquarters, along with two at-grade stations.

    The tender also covers the procurement of 25 trams, each with a capacity of 270 people, along with associated systems.

    The project was officially launched at the GlobalRail exhibition in Abu Dhabi in October last year.

    Referred to as Abu Dhabi Tram Line 4, the project will be delivered in three phases.

    Construction of the first phase is expected to start next year. The tram is slated to begin operations by 2030.

    Future phases will extend towards Khalifa City and serve additional destinations across Yas Island.

    The project forms a key part of the recently announced AED170bn ($46bn) package of national transport and road projects to be implemented by 2030.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19493532/main.jpg
    Yasir Iqbal