Aramco’s recalibrated chemicals goals reflect realism

26 March 2025

 

Saudi Aramco told consultants and contractors last year that it was revisiting its investment strategy and execution approach for its liquids-to-chemicals programme.

The central ambition of the strategic programme is to derive greater economic value from every barrel of crude produced in Saudi Arabia by converting 4 million barrels a day (b/d) of Aramco’s oil production into high-value petrochemicals and chemicals feedstocks by 2030.

Aramco and its subsidiary, Saudi Basic Industries Corporation (Sabic), had been tasked with establishing 10-11 large mixed-feed crackers by 2030. These petrochemicals crackers, which included greenfield developments and expansions of existing facilities, were to be built both in Saudi Arabia and in overseas markets.

Achieving this ambition required Aramco and Sabic – the main stakeholders in the liquids-to-chemicals programme – to invest a sum of up to $100bn. Amid considerable cost pressures and significant overcapacity in the global chemicals sector, pushing forward with such a capital-intensive campaign was hard to justify. 

However, while Aramco may have streamlined the programme’s remit, the primary goal of attaining a liquids-to-chemicals conversion rate of 4 million b/d within its global portfolio remains unchanged.

In a presentation detailing Aramco’s financial performance and operational activities in 2024, president and CEO Amin Nasser stated that the company had achieved 45% of the target of the liquids-to-chemicals programme as of the end of last year. Also, 53% of Aramco’s crude oil production is utilised by the downstream sector.

This has been achieved through “greater capital efficiency with low-equity and a high-placement strategy”, Nasser said in the presentation.

Moreover, large-scale petrochemicals projects undertaken by Aramco’s joint ventures with foreign partners in South Korea and Saudi Arabia, namely the Shaheen and Amiral developments, respectively, will significantly contribute to the liquids-to-chemicals target when they come online in 2026 and 2027.

Key chemical projects advance

Aramco continues to make progress with projects deemed crucial to its long-term petrochemicals objectives. One such project is the expansion of Aramco affiliate, Saudi Aramco Jubail Refinery Company (Sasref), into the petrochemicals sector.

Aramco has brought China-based Rongsheng Petrochemical Company on board as a joint-venture partner for the proposed project, which is part of the liquids-to-chemicals programme.

Their aim is to convert the Sasref refining complex in Jubail into an integrated refinery and petrochemicals complex by adding a mixed-feed cracker. The project also involves building an ethane cracker that will draw feedstock from the Sasref refinery.

The project is in the pre-front-end engineering and design (pre-feed) stage, with Aramco previously saying that the construction of large-scale steam crackers and the integration of associated downstream derivatives into the existing Sasref complex would enhance “its ability to meet growing demand for high-quality petrochemical products”.

Meanwhile, Sabic is in the bid evaluation stage with a major project that involves building an integrated blue ammonia and urea manufacturing complex at the existing facility of its affiliate, Sabic Agri-Nutrients Company, in Jubail. 

The estimated $3bn project, called the low-carbon hydrogen San 6 complex, is part of Sabic’s Horizon-I low-carbon hydrogen (LCH) programme. Contractors submitted bids for the project in March last year.

The San 6 complex will have an output capacity of 3,500 metric tonnes a day, or 1.17 million tonnes a year (t/y), of blue ammonia, and a urea production capacity of 3,850 metric tonnes a day, or 1.28 million t/y.

Carbon dioxide (CO2) from the blue ammonia plant will be utilised for urea production, with surplus CO2 from the ammonia plant and post-combustion carbon capture unit to be exported via a third-party pipeline for subsequent sequestration.

Gas transportation and processing projects

Saudi Arabia was the biggest regional spender on midstream and downstream projects last year. To address incremental volumes of gas entering the grid as Aramco increases its conventional and unconventional gas production, the state enterprise spent more than $17bn on gas processing and transportation projects in 2024.

In April last year, Aramco awarded $7.7bn in engineering, procurement and construction (EPC) contracts for a project to expand the Fadhili gas plant in the Eastern Province of Saudi Arabia. The project is expected to increase the plant’s processing capacity from 2.5 billion cubic feet a day (cf/d) to up to 4 billion cf/d.

In June, Aramco awarded 15 lump-sum turnkey contracts for the third expansion phase of the Master Gas System (MGS-3), worth $8.8bn. Then, in August, the company awarded contracts for the remaining two packages of the MGS-3 project, which were worth $1bn. 

Saudi Aramco divided EPC works on the MGS-3 project into 17 packages. The first two packages involve upgrading existing gas compression systems and installing new gas compressors. The 15 other packages relate to laying gas transport pipelines at various locations in the kingdom.

The Master Gas System expansion will increase the size of the network and raise its total capacity by an additional 3.15 billion cf/d by 2028, with the installation of about 4,000 kilometres of pipelines and 17 new gas compression trains.

So far this year, the Saudi energy giant has selected the main contractor for a major project to develop a large-scale carbon capture and storage (CCS) hub in Jubail Industrial City.

India’s Larsen & Toubro Energy Hydrocarbon has been picked to perform EPC work on the first phase of the project, which is called the Accelerated Carbon Capture and Sequestration (ACCS) scheme, worth $1.5bn.

The aim of the ACCS scheme, which is expected to have nine phases in total, is to capture CO2 from Aramco’s northern gas plants at Wasit, Fadhili and Khursaniyah, as well as from the operations of Sabic and Saudi industrial gases provider Air Products Qudra.

The first phase of the ACCS project will have the capacity to store and sequester up to 9 million t/y of CO2 in the planned CCS hub in Jubail. The main facility that will be built in Jubail will capture streams from the acid gas enrichment units of the Wasit, Fadhili and Khursaniyah plants. The CO2 will be compressed, dried and fed into the collection pipeline system.


MEED’s April 2025 report on Saudi Arabia also includes:

> UPSTREAM: Saudi oil and gas spending to surpass 2024 level
> POWER: Saudi power sector enters busiest year
> WATER: Saudi water contracts set another annual record
> CONSTRUCTION: Reprioritisation underpins Saudi construction
> TRANSPORT: Riyadh pushes ahead with infrastructure development
> BANKING:
 Saudi banks work to keep pace with credit expansion

https://image.digitalinsightresearch.in/uploads/NewsArticle/13477916/main.gif
Indrajit Sen
Related Articles
  • Saudi Arabia battery storage awards provide fresh lift

    24 August 2026

    Commentary
    Mark Dowdall
    Power & water editor

    The latest battery storage awards provide a welcome injection of investment into Saudi Arabia’s power market, which has seen a sharp slowdown in contract awards this year.

    Saudi Power Procurement Company’s four Group 1 storage service agreements, announced last week, are worth more than $1.16bn and cover 2,000MW of capacity.

    That is significant against the wider market. According to regional project tracker MEED Projects, Saudi Arabia recorded $19.7bn in power sector contract awards in the first seven months of 2025, compared with just $2.5bn in new awards in the same period this year.

    The battery energy storage system (bess) awards therefore account for a sizeable share of the activity recorded so far this year and provide a much-needed source of new contracting activity.

    Importantly, this is not a one-off. SPPC issued the request for proposal (RFP) for its second group of bess projects in July, covering six projects with a combined capacity of 3,000MW and 12,000MWh.

    With the Group 1 tender taking around 18 months from RFP to contract award, it is reasonable to expect Group 2 contracts to be signed in 2027.

    At the same time, the awards for six independent renewable plants under Round 7 of Saudi Arabia’s National Renewable Energy Programme (NREP), with a combined capacity of 5,300MW, are also likely to move into next year, with the latest bid deadlines now extending into September.

    Although a substantial pipeline remains in procurement, it is only once these projects move from tender to award and into construction that this pipeline translates into market activity.

    It is important that these tenders continue to progress at the pace established by the early rounds of Saudi Arabia’s renewable energy programme and now also SPPC’s independent storage provider bess scheme.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/18962923/main.jpg
    Mark Dowdall
  • Qatar receives bids for major power grid expansion

    24 August 2026

     

    Qatar General Electricity & Water Corporation (Kahramaa) has received bids for several packages under a major power transmission expansion project tendered in April.

    The project covers new substations at multiple voltage levels, as well as the supply and installation of 400kV extra-high-voltage power cables. The overall scheme is estimated to cost $650m.

    It is being tendered as part of Kahramaa’s 2026 procurement plan, which includes 198 tenders with a total estimated value of QR21.4bn ($5.9bn).

    According to sources, bids were submitted for the following packages on 20 August:

    • Substation packages S1 and S2, covering new 132/11kV substations (estimated cost: $200m)
    • Package S3, covering new 66/11kV substations ($50m)
    • Package S4, including a new 400/220/132kV substation, as well as upgrades and modifications to existing 400kV and 220kV substations ($200m)
    • Package S5, covering new 132/11kV substations and upgrades to existing 132kV and 66kV substations ($100m)
    • Cable packages C1 and C2, covering 400kV cables ($100m)

    Kahramaa previously stated that foreign companies not registered in Qatar would be allowed to participate in the bidding, subject to meeting specified conditions, including registration and certification requirements.

    In June, the electricity and water utility awarded contracts worth more than QR2.2bn ($604m) to expand the electricity transmission network in the country’s western region.

    The engineering, procurement and construction (EPC) works will support the integration of the 2GW Dukhan solar power project into Qatar’s national electricity grid. The scope includes new and upgraded substations, as well as the installation of underground cables and overhead transmission lines.

    Kahramaa said contracts were awarded to local firm Voltage Engineering, Turkiye’s Best & Betas Consortium, India’s Larsen & Toubro and South Korea’s LS Cable.

    Of Kahramaa’s 2026 procurement plan, electricity transmission projects account for QR8.9bn ($2.4bn) and include the construction of new 400/132kV substations in Al-Wukair and Al-Mashaf, as well as the expansion of 400kV substations at Ras Laffan.

    These also cover the installation of 132kV underground cables between Al-Sailiya and Al-Rayyan over a 24-kilometre route, as well as upgrades to the 400kV and 220kV networks.

    Additionally, there are 64 planned electricity distribution projects managed by the Electricity Distribution Department that cover the medium-voltage and low-voltage networks throughout Doha and the regional municipalities. 

    https://image.digitalinsightresearch.in/uploads/NewsArticle/18962223/main.jpg
    Mark Dowdall
  • Maaden closes $1bn term loan and credit facility

    24 August 2026

    Saudi Arabian Mining Company (Maaden) has announced the closing of its inaugural international syndicated term loan and revolving credit facilities, worth a total of $1bn.

    The $500m international term loan facility will support Maaden’s growth agenda and general corporate purposes, including funding growth projects across its portfolio.

    The $500m international revolving credit facility, which is expected to remain undrawn, provides additional committed funding capacity “as Maaden continues to scale its business and execute its long-term growth strategy”.

    The transaction “was met with strong support from the international banking market, attracting participation from a diverse group of leading international banks across key global financial markets”, including the US, Canada, Europe, China and Japan. The facilities were oversubscribed, Maaden said.

    ALSO READ: Maaden and Aramco sign deal to create joint venture

    “The level of demand reflects the global banking community’s confidence in Maaden’s financial strength, strategic direction and ambitious growth plans,” the Saudi state miner said in its statement.

    “The facilities mark another significant milestone in Maaden’s funding journey – further diversifying its sources of funding and broadening its access to global capital providers as the company continues to advance its long-term growth ambitions.

    “Maaden continues to make significant progress across its growth pipeline, expanding production, advancing major projects and accelerating exploration as it builds a world-class mining company at the heart of Saudi Arabia’s economic transformation.”

    https://image.digitalinsightresearch.in/uploads/NewsArticle/18962086/main4516.jpg
    Indrajit Sen
  • Dubai inflation slows to 5.3% in July

    24 August 2026

    Dubai’s annual inflation rate slowed to 5.3% in July, down from 5.7% in June, as a decline in transport costs eased pressure on consumer prices, according to Emirates NBD.

    The bank said the slowdown supported its view that price growth peaked at mid-year, and it expects inflation to continue easing through the rest of 2026. Monthly price growth slowed to 0.1% in July, from 0.4% in June, the weakest pace since February.

    Transport was the clearest sign of the moderation. Annual price growth in the category slowed to 11.9% in July, from 18.1% in June, as transport costs fell 3.7% over the month. Fuel and lubricant inflation eased to 24.1% year on year, from 48.3%, tracking a decline in local petrol prices.

    Petrol remains the main swing factor in the emirate’s inflation. Transport contributed 1.1 percentage points to headline inflation in July, down from 1.7 percentage points in June. Emirates NBD said the relief may prove temporary, with Super 98 petrol prices climbing 5.9% in August to leave them 33.8% higher than a year earlier. The bank expects headline inflation to edge higher in the August figures before easing again later in the year.

    The UAE deregulated petrol and diesel prices in 2015 and reviews them monthly against global prices, meaning changes in global fuel costs pass through to consumers quickly. Transport, which includes fuel, accounts for 9% of Dubai’s consumer price index basket.

    Housing remained the largest contributor to inflation even as its impulse faded. Housing and utilities, which account for about two-fifths of the basket, added 2.8 percentage points to headline inflation. Annual price growth in the category slowed to 7.0%, from 7.4% in January.

    Food inflation edged up to 7.8% year on year, from 7.6% in June, which the bank attributed to lingering supply-chain disruption from the regional conflict. Inflation in restaurants and hotels accelerated to 4.5% year on year, from 1.7% in June.

    Emirates NBD forecasts inflation of 2.9% by year-end but said risks to that projection were tilted to the upside, given lingering pressures in food and housing.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/18961735/main1839.jpg
    Colin Foreman
  • Libya oil project on track for 2027 completion

    24 August 2026

     

    The project to develop a workers’ camp at Libya’s Erawin oil field is on track for completion next year, according to industry sources.

    The project, estimated to be worth about $50m, is being executed by the Libyan oil services company Al-Saraya Al-Hamara, headquartered in the city of Sebha.

    The Libyan company was awarded the contract in February 2025.

    The scope of the project includes:

    • Construction of an accommodation camp
    • Construction of the camp maintenance warehouse
    • Construction of the camp office
    • Construction of a fire brigade shelter
    • Construction of a kitchen and mess hall
    • Construction of a mosque
    • Construction of a laundry room
    • Construction of a clinic
    • Construction of parking facilities
    • Installation of a fire and gas system
    • Installation of a power generator
    • Construction of associated facilities

    The client on the project is Zallaf Libya Oil & Gas Exploration & Production Company.

    Zallaf Libya Oil & Gas Exploration & Production Company was established in Libya in 2013 and is wholly owned by Libya’s state-owned National Oil Corporation.

    The Erawin field development project is located about 800 kilometres south of Tripoli and 100km southwest of the El-Sharara field.

    Libya shipped its first cargo of crude from the Erawin oil field in November 2023.

    The shipment departed from Libya’s Zawiyah port and consisted of 600,000 barrels of crude.

    Australia-based Worley Parsons was appointed as the front-end engineering and design (feed) contractor for the early production facility project in 2019.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/18953632/main.jpg
    Wil Crisp