Aramco extends desulphurisation scheme deadline

16 March 2023

Saudi Aramco has allowed more time for bidders to submit proposals for a major desulphurisation programme to modify sulphur recovery units (SRUs) at key gas processing plants in the kingdom.

Aramco expects third-party investments of up to $2bn in the desulphurisation programme, which entails building a large downstream tail-gas treatment (TGT) facility to collect and process tail gas discharged from SRUs at identified gas plants, MEED reported in December 2021.

According to industry sources, the facility is to be developed on a build, own and operate (BOO) or build-own-operate-transfer (BOOT) basis. This will make it one of Aramco’s initial public-private partnership (PPP) exercises, if not the first, in its main oil and gas business.

Aramco issued the main tender for the TGT facility in May last year, MEED previously reported. The Saudi energy giant has now extended the proposal submission deadline for bidders until 31 March, according to sources.

Bidders were initially required to submit proposals by 30 September last year. The proposal submission deadline was then moved to 15 December, and then extended again to 15 March this year.

Aramco issued expressions of interest (EoI) for the scheme on 18 October 2021 to several entities, sources previously said. Invited companies submitted EoI documents by 30 November of that year.

Among those understood to be bidding for the scheme are:

  • Vision Invest (Saudi Arabia) / Mitsui & Co (Japan) / JGC Corporation (Japan)
  • Lamar Holding (Saudi Arabia) / Hyundai Engineering & Construction (South Korea) / Korea Overseas Infrastructure & Urban Development Corporation (South Korea)/ Enerflex (Canada)
  • Gatti (Italy)/Spetco (Kuwait)/Standardkessel Baumgarte (Germany)/Knauf (Germany)

In a recent interview with MEED, Lamar Holding’s CEO Ramit Jain confirmed that the company was bidding for the TGT scheme in a team comprising South Korean government-owned Korean Overseas Infrastructure & Urban Development Corporation and other entities.

SO2 reduction campaign

The Aramco programme is in line with the regulations for emissions to air from stationary sources set out by Saudi Arabia’s Environment, Water & Agriculture Ministry. These stipulate that sulphur dioxide (SO2) emissions from stationary sources must not exceed 250 parts per million volume (dry and 0 per cent oxygen basis). They must also comply with the SO2 ambient emission limits or ground-level SO2 concentration.

The rollout of the desulphurisation scheme stems from Aramco’s goal to achieve net-zero carbon emissions by 2050 and is part of its environmental, social and governance initiatives, sources previously said.

Seven gas plants in Saudi Arabia’s Eastern Province have been identified from which tail gas needs to be treated for up to 99.9 per cent SO2 removal:

  • Berri
  • Haradh
  • Hawiyah
  • Khursaniyah
  • Shedgum
  • Uthmaniyah
  • Wasit

The scope of the scheme has been split into two packages, one source said. The first package covers gas plants in Aramco’s Zone 1 – Berri, Khursaniyah and Wasit – while the second package relates to units in Zone 2 – Haradh, Hawiyah, Shedgum and Uthmaniyah.

Along with fully financing the project, the developer will need to adopt one of the following commercial desulphurisation technologies approved by Aramco for the scheme:

  • TGT reduction absorption
  • Ammonia-based desulphurisation
  • Dry sorbent injection
  • Flue gas desulphurisation using gypsum

According to Aramco, the project will cover “the end-to-end application of the approved technologies, including but not limited to required plot space, utilities, market analysis and logistics of feedstock and byproduct, contractual arrangements, risks associated with each technology related to safety, process reliability and SO2 emissions compliance on a continuous basis”.

Aramco expects the common TGT facility to be operational by 2027.

ALSO READ: Aramco prepares to tender carbon capture project

https://image.digitalinsightresearch.in/uploads/NewsArticle/10680003/main3437.jpg
Indrajit Sen
Related Articles
  • Consultant wins Dubai Al-Maktoum airport metro link

    11 September 2026

     

    Register for MEED’s 14-day trial access 

    US-based engineering firm Aecom has won a design contract for the Route 2020 extension, which will start from the Expo 2020 metro station and connect with Al-Maktoum International airport’s West Terminal.

    Dubai’s Roads & Transport Authority (RTA) awarded the contract.

    The extension will run about 3 kilometres (km) and include two stations.

    MEED understands the invitation to bid was issued in January, with a submission deadline in mid-March.

    The existing Route 2020 metro link is a 15km-long line that branches off the Red Line at Jebel Ali metro station. The line comprises 11.8km of elevated tracks and 3.2km of tunnels, and has five elevated stations and two underground stations.

    The RTA awarded the AED10.6bn ($2.9bn) design-and-build contract for the project to a consortium of Spain’s Acciona, Turkiye’s Gulermak and France’s Alstom in 2016.

    The RTA also selected Aecom to provide consultancy services for the upcoming Dubai Metro Gold Line project, also known as Metro Line 4, in October last year, as MEED reported.

    The Gold Line will start at Al-Ghubaiba in Bur Dubai. It will run parallel to – and alleviate pressure on – the existing Red Line, before heading inland to Business Bay, Meydan, Global Village and residential developments in Dubailand.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19571676/main.jpg
    Yasir Iqbal
  • Saudi Arabia sets October deadline for Mecca metro design

    11 September 2026

     

    The Royal Commission for Makkah City & Holy Sites (RCMC) has set a deadline of 14 October for a contract covering the initial design studies for its long-planned metro network in the holy city.

    The scope includes reviewing existing studies, preparing a concept design, conducting land acquisition studies, developing an integration concept for future phases and other related studies.

    The notice was issued in May, with an initial submission deadline of 5 August, as MEED reported.

    In September last year, RCMC invited contractors to attend an early market engagement meeting for the project.

    In an explanatory document inviting companies to attend the event, the RCMC’s General Transport Centre said it was seeking to gauge market interest in the multibillion-dollar project and obtain feedback on its proposed procurement approach.

    MEED exclusively reported in June last year that the project was restarting. Current plans envisage a four-line network, named lines A-D, with 89 stations and three depots, to be implemented over three phases between 2032 and 2045.

    Project scope

    Stage 1 focuses on lines B and C, involving 2.4 kilometres of tunnelling under the Masar project and integration with the existing Mashaer line.

    The network will run just over 62km and comprise 31 stations, 21 of which will be underground, including three iconic stations. A total of 19.5km will run through tunnels, while 41.2km will be elevated, with the remainder at grade.

    The 66 required trainsets are projected to provide a daily passenger capacity of about 450,000, equating to annual ridership of 171 million.

    The 84.7km-long second phase, due to be operational by 2038, will extend the two lines towards the outskirts of Mecca and includes construction of the initial inner and central segments of lines A and D.

    Comprising 61.1km elevated and 18.6km underground, Phase 2 is planned to add 45 stations serving the two new lines, as well as two depots and a potential interconnection with the planned Saudi Landbridge. The 59 trainsets for Phase 2 will increase the network’s projected total annual passenger capacity to more than 500 million.

    Phase 3 covers the elevated 36km extension of lines A and D and involves procurement of a further 72 trainsets, increasing the network’s ultimate passenger capacity to 1.2 million daily and 642 million annually by completion in 2045.

    Associated development

    The metro plan also envisages several transit-oriented developments (TODs) at different points on the route. These will typically comprise commercial, residential and retail elements to maximise the investment case.

    The client’s proposed procurement approach involves three distinct packages: civil and systems works, TODs, and operations and maintenance.

    The initial concept calls for some of the project to be delivered on a public-private partnership (PPP) basis, wherein the private sector, through special purpose vehicles, will part-finance, build, operate and then transfer commercially viable elements of the scheme.

    The then-called Mecca Mass Rail Transit Company (MMRTC) first launched the metro project in 2013; however, the scheme has faltered for more than a decade due to funding issues, land acquisition challenges and scope changes.

    The relaunch of the procurement process raises hopes that the project will now come to fruition, although it is likely to be at least 18 months before any definitive works start.

    Mecca is home to Saudi Arabia’s first metro, the nine-station, 18km-long Mashaer line, which opened in 2010. It operates only seven days a year during Hajj, but carries more than 2 million pilgrims during that time.

    Some 30 million pilgrims visit the city each year, with this number set to grow. A known, quantifiable and growing demand base will help facilitate the use of a PPP mechanism if the framework is adopted.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19569659/main.jpg
    Yasir Iqbal
  • Consortiums submit bids for Sadara cogeneration plant

    11 September 2026

     

    Register for MEED’s 14-day trial access 

    At least three consortiums have submitted bids for the contract to develop and operate a cogeneration steam and power plant catering to the Sadara petrochemicals complex in Saudi Arabia.

    The planned independent steam and power plant (ISPP) project will have a capacity for 400MW-450MW of combined-cycle electricity generation and 550-700 tonnes an hour of steam.

    According to sources, bids were submitted for the contract at the end of August.

    The consortium bidders include: 

    • Abu Dhabi National Energy Company (Taqa) / Samsung C&T (South Korea)
    • Al-Jomaih Energy & Water (Saudi Arabia) / Albawani (Saudi Arabia) / Sepco 3 (China)
    • Acwa (Saudi Arabia), Korea Electric Power Corporation (Kepco) / Doosan Enerbility (South Korea)

    Sadara Chemical Company (Sadara) is the project client. It is the downstream joint venture of Saudi Aramco and US-headquartered Dow Chemical.

    The estimated $500m project includes construction of a power plant, substations, a seawater intake system and associated switchyards and switchgear.

    The project will also include gas turbines and a back-pressure steam turbine, as well as facilities for steam production.

    In 2024, MEED exclusively reported that Sadara had prequalified potential bidders for the project. It is understood that the request for proposals was issued towards the end of last year.

    The first units at the $20bn Sadara petrochemicals complex in Jubail began production in 2016, and the complex became operational in 2017.

    The Sadara complex is designed to produce more than 3 million tonnes a year (t/y) of chemicals and performance plastics, including polyurethanes, propylene oxide, propylene glycol, elastomers, polyethylene, glycol ethers and amines.

    Construction is also continuing on the Najim cogeneration facility, which will supply the Amiral petrochemicals complex with up to 475MW of power and approximately 452 tonnes an hour of steam.

    Previously known as the Amiral cogeneration independent steam and power plant, the project is being developed by a team comprising Abu Dhabi National Energy Company (Taqa) and Japanese power generation company Jera.

    South Korean contractor Samsung C&T is the engineering, procurement and construction contractor for the project.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19567716/main.jpg
    Mark Dowdall
  • UAE plans 150km Boring Company tunnel network

    11 September 2026

    The UAE plans to build more than 150 kilometres of underground tunnel with US tunnelling firm The Boring Company, in a programme backed by a $3bn funding round the UAE led.

    The Series D round values the Boring Company at $23bn, about four times the $5.7bn it was worth after a 2022 funding round. The UAE and affiliated investment entities led the round, which will accelerate a partnership to deploy underground infrastructure across the UAE, the firm said.

    The 150km target marks a substantial expansion of the company’s footprint in the country, extending work already committed through the Dubai Loop project. It contrasts sharply with what has been contracted so far. The Boring Company has signed a construction contract with Dubai’s Roads & Transport Authority (RTA) for the pilot phase of Dubai Loop, covering a 6.4km route and four stations linking Dubai International Financial Centre (DIFC) and Dubai Mall. The pilot is expected to cost about AED565m ($154m), with tunnelling due to begin in the second half of this year.

    The 150km figure therefore represents an ambition for the wider partnership rather than a contracted volume, with the bulk of the network yet to be tendered, designed or awarded. No timeframe has been attached to the target.

    A second Dubai Loop phase will connect Dubai World Trade Centre and DIFC with Business Bay, extending the tunnels to 22km across 19 stations. The total cost across both phases is expected to be about AED2bn ($545m), with completion scheduled within three years. The pilot route is projected to carry about 13,000 passengers a day, rising to about 30,000 a day across the full route.

    Other investors in the round include Human Capital, Vy Capital, Valor Equity Partners, Sequoia Capital, Andreessen Horowitz, Temasek, Shamal Holding and Baron Capital. The proceeds will also fund hiring, the scaling of the company’s Loop transit systems in the US cities of Las Vegas and Nashville, and further development of its Prufrock tunnel-boring machines, which it says can operate in both soft ground and hard rock.

    The RTA and the Boring Company signed a memorandum of understanding in February last year to explore developing the Dubai Loop, and the construction contract followed in February this year. In May, US engineering firm Parsons was appointed as programme manager for the pilot phase, with a scope covering independent design verification, permitting and multidisciplinary design reviews.

    The appointment comes amid a broader shift towards underground construction across the Gulf, as metro, sewerage and highway works in the UAE, Saudi Arabia and Qatar increasingly default to tunnelling.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19567623/main.jpg
    Yasir Iqbal
  • Heisco wins $359m oil contract in Kuwait

    11 September 2026

    Kuwait-based Heavy Engineering Industries & Shipbuilding Company (Heisco) has been awarded a contract worth KD111.05m ($359m) to develop storage tanks for Kuwait’s Jurassic Light Oil (JLO) export facilities, according to a stock market filing.

    The scope of the contract includes civil, mechanical, electrical and instrumentation works, as well as engineering, procurement and construction (EPC) services for the tanks.

    The contract was awarded by India’s Larsen & Toubro (L&T), the main contractor for a broader project to develop JLO storage and export facilities in Kuwait, as well as upgrade Kuwait Oil Company’s (KOC’s) existing export network.

    The $979.2m main contract for this broader project was awarded to L&T on 15 July.

    The contract for Heisco’s scope of work has a time period of 42 months, according to its stock market filing.

    Oil crisis

    Kuwait’s oil and gas sector is currently in crisis due to the regional war that started after the US and Israel attacked Iran on 28 February.

    The war has severely disrupted exports through the Strait of Hormuz, which Kuwait relies on in order to ship crude exports.

    It has also disrupted imports of equipment and materials for projects, raising project costs.

    Sheikh Nawaf Saud Al-Sabah, deputy chairman and CEO of Kuwait Petroleum Corporation (KPC), the country’s national oil company, has described the current conflict as the biggest oil crisis the country has faced since Iraq’s 1990 invasion.

    Despite the significant reduction in crude exports, Kuwait’s state-owned oil companies have continued to tender some projects.

    Export facilities

    The scope of work under the contract awarded to L&T in July includes the EPC of six new crude oil storage tanks, each with an operating capacity of 618,000 barrels, along with associated facilities, the Mumbai-headquartered company said on 29 July.

    The project also involves “the installation of new pipelines and comprehensive upgrades to Kuwait’s existing crude loading and export network, to seamlessly accommodate increased production and enhance the country’s crude handling capabilities”, the Bombay Stock Exchange-listed company said.

    L&T also said that the contract will be executed on a lump-sum turnkey basis.

    Only two companies submitted bids for the contract in October last year:

    • L&T (India): KD303.5m ($988m)
    • Petrofac (UK): KD310.6m ($1.01bn)

    Following bid submission, KPC discussed the potential cancellation of the tender due to bids coming in significantly over budget and Petrofac becoming ineligible to win contracts in Kuwait.

    The contractor was temporarily barred from participating in tenders in Kuwait’s oil and gas sector in December last year.

    Petrofac received the ban after the company announced it had applied to appoint administrators, a move that potentially put thousands of jobs at risk and increased uncertainty for projects worth billions of dollars in the Middle East and North Africa region.

    Despite discussions about cancelling the tender, KPC ultimately decided to proceed with the award process because it considered the project a high priority.

    One source previously told MEED: “Around the same time, projects worth around $8bn were cancelled because of bids coming in over budget, but this one has gone ahead because KPC sees it as an essential project.”

    The project was originally tendered in November 2024, with a bid deadline of 1 December the same year. The bid deadline was extended several times before bids were ultimately submitted.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19556019/main.png
    Wil Crisp