Aramco extends desulphurisation scheme deadline
16 March 2023

Saudi Aramco has allowed more time for bidders to submit proposals for a major desulphurisation programme to modify sulphur recovery units (SRUs) at key gas processing plants in the kingdom.
Aramco expects third-party investments of up to $2bn in the desulphurisation programme, which entails building a large downstream tail-gas treatment (TGT) facility to collect and process tail gas discharged from SRUs at identified gas plants, MEED reported in December 2021.
According to industry sources, the facility is to be developed on a build, own and operate (BOO) or build-own-operate-transfer (BOOT) basis. This will make it one of Aramco’s initial public-private partnership (PPP) exercises, if not the first, in its main oil and gas business.
Aramco issued the main tender for the TGT facility in May last year, MEED previously reported. The Saudi energy giant has now extended the proposal submission deadline for bidders until 31 March, according to sources.
Bidders were initially required to submit proposals by 30 September last year. The proposal submission deadline was then moved to 15 December, and then extended again to 15 March this year.
Aramco issued expressions of interest (EoI) for the scheme on 18 October 2021 to several entities, sources previously said. Invited companies submitted EoI documents by 30 November of that year.
Among those understood to be bidding for the scheme are:
- Vision Invest (Saudi Arabia) / Mitsui & Co (Japan) / JGC Corporation (Japan)
- Lamar Holding (Saudi Arabia) / Hyundai Engineering & Construction (South Korea) / Korea Overseas Infrastructure & Urban Development Corporation (South Korea)/ Enerflex (Canada)
- Gatti (Italy)/Spetco (Kuwait)/Standardkessel Baumgarte (Germany)/Knauf (Germany)
In a recent interview with MEED, Lamar Holding’s CEO Ramit Jain confirmed that the company was bidding for the TGT scheme in a team comprising South Korean government-owned Korean Overseas Infrastructure & Urban Development Corporation and other entities.
SO2 reduction campaign
The Aramco programme is in line with the regulations for emissions to air from stationary sources set out by Saudi Arabia’s Environment, Water & Agriculture Ministry. These stipulate that sulphur dioxide (SO2) emissions from stationary sources must not exceed 250 parts per million volume (dry and 0 per cent oxygen basis). They must also comply with the SO2 ambient emission limits or ground-level SO2 concentration.
The rollout of the desulphurisation scheme stems from Aramco’s goal to achieve net-zero carbon emissions by 2050 and is part of its environmental, social and governance initiatives, sources previously said.
Seven gas plants in Saudi Arabia’s Eastern Province have been identified from which tail gas needs to be treated for up to 99.9 per cent SO2 removal:
- Berri
- Haradh
- Hawiyah
- Khursaniyah
- Shedgum
- Uthmaniyah
- Wasit
The scope of the scheme has been split into two packages, one source said. The first package covers gas plants in Aramco’s Zone 1 – Berri, Khursaniyah and Wasit – while the second package relates to units in Zone 2 – Haradh, Hawiyah, Shedgum and Uthmaniyah.
Along with fully financing the project, the developer will need to adopt one of the following commercial desulphurisation technologies approved by Aramco for the scheme:
- TGT reduction absorption
- Ammonia-based desulphurisation
- Dry sorbent injection
- Flue gas desulphurisation using gypsum
According to Aramco, the project will cover “the end-to-end application of the approved technologies, including but not limited to required plot space, utilities, market analysis and logistics of feedstock and byproduct, contractual arrangements, risks associated with each technology related to safety, process reliability and SO2 emissions compliance on a continuous basis”.
Aramco expects the common TGT facility to be operational by 2027.
ALSO READ: Aramco prepares to tender carbon capture project
Exclusive from Meed
-
Qatari Diar unveils $30bn Egypt project masterplan21 July 2026
-
-
-
Chinese firm wins Dubai drainage contract20 July 2026
-
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Qatari Diar unveils $30bn Egypt project masterplan21 July 2026
Qatari Diar, the real estate arm of the Qatar Investment Authority, has announced the masterplan for its $30bn Alam Al-Roum project on Egypt’s north coast.
The masterplan was developed by US-based architectural firm Skidmore, Owings & Merrill.
The master-planning team also includes US-based landscape architecture firm SWA; UK-headquartered marina design and operations consultant Marina Projects; and French transport and traffic engineering consultant Setec.
The development will cover more than 20 million square metres and include 7.2 kilometres of private beachfront on the Mediterranean Sea.
The site is about 20 minutes from Marsa Matrouh and 50 minutes from Ras El-Hekma.
According to a statement, the project includes $3.5bn in direct cash investment and is designed as an integrated, year-round Mediterranean destination.
Alam Al-Roum expands Qatari Diar Egypt’s portfolio, which includes CityGate, New Giza and The St Regis Cairo.
Qatari Diar and Egypt’s New Urban Communities Authority signed the project agreement for Alam Al-Roum in November 2025.
The estimated value of the deal to Egypt is $7.5bn. Under the agreement, Cairo will receive an upfront payment of $3.5bn by late December 2025 for the initial land purchase and is expected to receive an in-kind stake in the project, estimated to be worth $1.8bn.
Qatari Diar’s broader investment plans for the area include spending up to $26.2bn in addition to the $3.5bn already allocated for the land purchase.
https://image.digitalinsightresearch.in/uploads/NewsArticle/17707658/main.jpg -
Contractors submit final offers for Global Sports Tower21 July 2026

Contractors submitted their last and final offers in the first week of July for the main construction contract for the Global Sports Tower, located in the Athletics District of the Sports Boulevard development in Riyadh.
The Sports Boulevard Foundation issued the tender for the main works contract on 31 July last year.
The 130-metre-tall Global Sports Tower will cover an area of 84,000 square metres (sq m) and include more than 30 sports facilities.
The tower will feature the world’s tallest indoor climbing wall, at 98 metres, and a 250-metre running track.
Saudi Arabia’s Sports Boulevard Foundation also received bids on 10 June for a contract covering project management consultancy (PMC) services for the Global Sports Tower, as MEED reported.
MEED reported in May 2025 that design work on the tower had been completed. Saudi Arabia’s Crown Prince Mohammed Bin Salman Bin Abdulaziz Al-Saud approved the designs in 2024.
The Sports Boulevard development runs across Riyadh from east to west and, once complete, is set to be the world’s longest park, spanning more than 135 kilometres.
The development will feature several districts, including Wadi Hanifah, the Arts District, Urban Wadi, the Entertainment District, the Athletics District and the Eco District, as well as Sands Sports Park.
The large-scale project aims to transform central Riyadh – currently dominated by major highways – into a recreational corridor.
Sports Boulevard, which will feature 4.4 million sq m of public realm and landmark buildings, will also be home to the Centre for Cinematic Arts and a 2,000-seat amphitheatre.
The development will provide more than 2.3 million sq m of mixed-use commercial, residential and retail assets, along with sports facilities around the park, which will be known as Linear Park.
https://image.digitalinsightresearch.in/uploads/NewsArticle/17707675/main.jpeg -
Consultants submit bids for Saudi Arabia’s GCC rail link20 July 2026

Consultants submitted proposals on 14 July for a contract to provide design consultancy services for the Saudi Arabian section of the GCC railway network, which is intended to link all six member states.
Saudi Arabia Railways (SAR) issued the tender on 7 May, MEED previously reported.
The tender covers the concept, preliminary and issued for construction design stages. SAR requires the selected consultant to review, update and complete the existing preliminary design.
The consultants who submitted bids include:
- Atkins with Khatib & Alami
- DeutscheBahn with ARX
- Egis with Sener
- Idom with Dal Al-Handasah
- Systra
Saudi Arabia’s section of the railway will start at Al-Khafji in the Eastern Province, near the border with Kuwait, and end at Al-Batha, on Saudi Arabia’s border with the UAE. The route length in Saudi Arabia will be about 672 kilometres (km).
The railway will interface with the Kuwait National Rail Road (KNRR) project on the Kuwaiti side. Last year, MEED exclusively reported that the KNRR design contract was awarded to Turkiye’s Proyapi Muhendislik ve Musavirlik Anonim Sirketi.
The KNRR forms part of the wider GCC rail network. GCC railway projects have gained renewed momentum since the six member states signed the Al-Ula Declaration in January 2021.
In October last year, Qatar’s cabinet approved a draft agreement paving the way for a railway link between Qatar and Saudi Arabia as part of the GCC railway network.
GCC railway line
Under the overall plan, the railway will run from Kuwait, pass through Dammam in Saudi Arabia, reach Bahrain via a planned causeway, and continue from Dammam to Qatar, the UAE and, ultimately, Muscat via Sohar in Oman. The railway is reported to span about 2,186km in total.
The route length within each member state is as follows: 684km in the UAE, 672km in Saudi Arabia, 306km in Oman, 283km in Qatar, 145km in Kuwait and 36km in Bahrain.
The railway is designed for passenger trains travelling at 220km/h and freight trains operating at 80-120km/h.
With high levels of project activity, governments in spending mode and renewed cooperation under the Al-Ula Declaration, the latest efforts to restart the GCC railway project may make more progress than previous attempts. If completed, the railway could prove transformational for a region that is globally connected but still divided by national borders.
https://image.digitalinsightresearch.in/uploads/NewsArticle/17705320/main.gif -
Chinese firm wins Dubai drainage contract20 July 2026
China State Construction Engineering Corporation (CSCEC) has announced it has won a contract to deliver a stormwater drainage pipeline package under Dubai Municipality’s Tasreef programme.
The contract is for the TF-15-C2 stormwater drainage network project located along Umm Suqeim Road in the Al-Barsha and Al-Quoz areas of Dubai.
MEED exclusively revealed in May that the contractor had been selected for the engineering, procurement and construction (EPC) contract. The project is estimated to cost $162m.
The scope of work includes the construction of about 20 kilometres of new stormwater pipelines, together with associated inspection and intake manholes. The project is located west of the Dubai Canal and will connect the Al-Quoz 3 and Al-Quoz 4 industrial areas with Al-Quoz 1.
It is being delivered as part of Dubai’s Tasreef strategic plan, which supports the Dubai 2040 Urban Master Plan. Once completed, the new drainage infrastructure is expected to improve the emirate’s stormwater network, increase flood protection and enhance the resilience of Dubai’s infrastructure.
In February, the municipality confirmed it had awarded contracts for five new projects under phase two of the programme to expand and strengthen Dubai’s stormwater drainage network.
These include a separate contract awarded to CSCEC for the TF-11-C1 stormwater drainage project in the Dubailand area.
Also in February, Dubai Municipality invited consultants to qualify for a contract to supervise construction on the TF-15-C2 stormwater drainage projects along with two other projects (TF-13-C1 and TF-16-C1) under the Tasreef programme.
According to a source, a consultant has yet to be appointed.
TF-16-C1 involves upgrading and rehabilitating the stormwater system east of the Dubai Canal, while TF-13-C1 involves building a water pipeline stormwater drainage system at Al-Marmoum, Al-Qudra and Al-Yalayis 2 & 3.
Bids are currently under evaluation for the EPC contracts for both projects.
https://image.digitalinsightresearch.in/uploads/NewsArticle/17705058/main.jpg -
Dubai receives eight bids for Hassyan SWRO pipeline contract20 July 2026
Register for MEED’s 14-day trial access
Eight contractors have made offers for a contract to supply, install, test and commission glass-reinforced epoxy (GRE) water transmission pipelines and associated works for the Hassyan seawater reverse osmosis (SWRO) phase two network in Dubai.
The contract relates to project one of the Hassyan pipeline network expansion being undertaken by state utility Dubai Electricity & Water Authority (Dewa).
Local firm Binladin Contracting Group submitted the lowest offer of AED335.92m ($91.5m), according to results published by the utility.
The other bids were:
- Green Oasis General Contracting (UAE) – AED345.00m ($93.9m)
- Al-Nasr Contracting (UAE) – AED391.54m ($106.6m)
- Wade Adams Contracting (UAE) – AED393.80m ($107.2m)
- RMB Contracting (UAE) – AED437.96m ($119.3m)
- Tristar Engineering & Construction (UAE) – AED441.55m ($120.2m)
- Shapoorji Pallonji Mideast (UAE/India) – AED451.47m ($122.9m)
- Gulf Petrochemical Services Trading (UAE) – AED495.20m ($134.8m)
RMB also submitted a conditional discounted offer of AED427.02m ($116.3m). Three companies submitted regret notices, while one offer was rejected after no valid commercial offer was received.
In January, Dewa announced that construction of the 180-million-imperial-gallon-a-day phase one of the Hassyan SWRO independent water project was 90% complete.
Dewa has two other contracts out for tender for GRE water transmission pipeline work related to the Hassyan SWRO phase two network.
Project two was tendered on 22 January and has a bid submission deadline of 21 July. Project three was tendered on 26 January and has a bid submission deadline of 29 July.
https://image.digitalinsightresearch.in/uploads/NewsArticle/17704940/main.jpg
