Aramco awards $7.7bn Fadhili gas plant expansion contracts

2 April 2024

Register for MEED's guest programme 

Saudi Aramco has awarded engineering, procurement and construction (EPC) contracts totalling $7.7bn to expand the Fadhili gas plant in the Eastern Province of Saudi Arabia.

The project is expected to increase the Fadhili gas plant’s processing capacity from 2.5 billion cubic feet a day (cf/d) to up to 4 billion cf/d.

“The additional 1.5 billion cf/d of processing capacity is expected to contribute to the company’s strategy to raise gas production by more than 60% by 2030, compared to 2021 levels,” Aramco said in a statement on 2 April.

The Fadhili gas plant expansion, which is expected to be completed by November 2027, is also anticipated to add 2,300 metric tonnes a day of sulphur production, Aramco added.

MEED recently named frontrunners for the main EPC packages of the project, which will add three processing trains, each with a capacity of 500 million cf/d.

According to sources, the following contractors were in pole position to win the three main EPC works on the Fadhili gas plant expansion project:

  • Package 1 – Gas processing plant expansion – Samsung Engineering (South Korea)
  • Package 2 – Sulphur recovery units (SRUs) – GS Engineering & Construction (South Korea)
  • Package 4 – Utilities and offsites – Samsung Engineering

Aramco’s statement named local contractor Nesma and Partners among the project contract winners. MEED understands the Al Khobar-based contractor has won the contract for package 3, which relates to early civil works on the project.

Aramco declined to respond to MEED’s request for comment on the information at the time.

MEED reported in November that Aramco was preparing to award contracts for the main EPC packages for the Fadhili gas plant expansion project in the first quarter of this year. The Saudi energy giant was previously expected to award the EPC contracts by the end of last year.

Contractors submitted bids for packages 1 and 2 on 16 September, and bids for packages 3 and 4 on 14 October, MEED previously reported.

Aramco issued the tenders for the EPC packages between March and April in 2023 and set 15 July as the initial deadline for submission of proposals, as MEED reported. Aramco organised a site visit for contractors on 15 May.

Four contractors are understood to have been bidding for the Fadhili gas plant expansion project:

  • GS Engineering & Construction (South Korea)
  • Hyundai Engineering & Construction (South Korea)
  • JGC Gulf International (Saudi Arabia subsidiary of Japan-headquartered JGC Corporation)
  • Samsung Engineering (South Korea)

US-headquartered KBR is understood to have executed the project’s front-end engineering and design (feed) works.

Fadhili gas processing complex

The Fadhili gas processing complex, located 30 kilometres southwest of the Khursaniyah gas plant, was commissioned in early 2020 and has the capacity to process 2.5 billion cf/d of natural gas.

EPC works on the $6.5bn Fadhili gas processing complex were completed by the end of 2019.

There were five EPC packages in the project’s first phase, contracts for which were awarded in 2015.

Spanish contractor Tecnicas Reunidas was awarded packages 1 and 2, worth $2bn and $1bn, respectively. The scope of work on the two packages related to building the central gas processing facility and the utilities and interconnecting systems.

UK-based Petrofac won package 3, worth about $1.7bn. The scope included the construction of six sulphur recovery trains with associated facilities for sulphur and heavy-duty oil handling, loading, unloading and storage; sour water stripper, flare system and a wastewater treatment plant.

The fourth EPC package, worth about $450m, was awarded to a consortium of India’s Larsen & Toubro Energy Hydrocarbon, Saudi Arabia’s Arkad Engineering & Construction and local firm Denys Arabia. Package 4 related to constructing a pipeline network connecting the Fadhili gas plant to its feeder oil and gas fields and other gas plants in the Eastern Province.

A fifth package for industrial support facilities at the Fadhili gas plant site was awarded to local firm Al-Muhaidib Contracting.

The UK-headquartered Wood Group carried out the feed work on the Fadhili project and was also the project management consultant.

The Fadhili plant processes sour gas from the offshore Khursaniyah oil field and the offshore Hasbah non-associated gas field.

The Fadhili gas project is vital to Aramco’s goal of nearly doubling its gas production and processing capacity from 12 billion cf/d to 23 billion cf/d by the end of this decade.

ALSO READ: Aramco CEO calls fossil fuel phase out a fantasy

https://image.digitalinsightresearch.in/uploads/NewsArticle/11652087/main0457.jpeg
Indrajit Sen
Related Articles
  • Facility E nears 25 July bid deadline

    19 July 2024

     

    The tender closing date of 25 July remains unchanged for the contract to develop and operate Qatar’s Facility E independent water and power producer (IWPP) project.

    At least one developer team is highly likely to submit a proposal to develop the gas-fired plant, sources close to the project tell MEED.

    Qatar state utility General Electricity & Water Corporation (Kahramaa) had previously extended the tender closing date for the contract in response to developers’ requests, as MEED reported.

    The Facility E IWPP scheme will have a power generation capacity of 2,300MW and a water desalination capacity of 100 million imperial gallons a day (MIGD).

    “We hear that at least one consortium is being formed … others are preparing proposals, but appear unsure if they will ultimately submit them or not,” a source close to the project told MEED in November last year. 

    Kahramaa initially expected to receive bids on 14 December 2023.

    The contract to develop the Facility E IWPP was first tendered in 2019. The three teams that submitted bids for the contract in August 2020 were:   

    • Engie (France) / Mitsui (Japan) / Yonden (Shikoku Electric, Japan)
    • Sumitomo / Kansai Electric (Japan)
    • Marubeni / Kyushu Electric (Japan)

    The original plan was for the Facility E IWPP to have a power generation capacity of about 2,300MW and a desalination component of 100MIGD once fully operational.

    However, the project owner revised the power plant’s design capacity to 2,600MW and sought alternative prices from bidders. 

    Kahramaa eventually cancelled and reissued the tender in September 2023. The current tender entails a power generation plant with the same capacity as initially tendered in 2019.

    MEED understands that the new target commercial operation date for the Facility E IWPP project has been moved to 2027. 

    The state utility’s transaction advisory team includes UK-headquartered PwC and Clyde & Co as financial and legal advisers, respectively, led by Belgrade-headquartered Energoprojekt as technical adviser.

    Facility E is Qatar’s fifth IWPP scheme. Completed and operational IWPPs include three projects in Ras Laffan – known as Facilities A, B and C – and Facility D in Umm Al-Houl.

    Awarded in 2015 and completed in 2018, Facility D was developed by a Japanese consortium of Mitsubishi Corporation and Tokyo Electric Power Company (Tepco). South Korea's Samsung C&T was the engineering, procurement and construction contractor.  

    https://image.digitalinsightresearch.in/uploads/NewsArticle/12177605/main.jpg
    Jennifer Aguinaldo
  • Masdar’s second bond issue raises $1bn

    19 July 2024

    Abu Dhabi Future Energy Company (Masdar) has raised $1bn through its second bond issuance under its Green Finance Framework.

    The announcement comes one year after the company’s first successful issuance of $750m on the International Securities Market of the London Stock Exchange.

    Masdar said the issuance comprises dual tranches of $500m each, with tenors of five and 10 years and coupons of 4.875% and 5.25%, respectively.

    It said there was strong appetite from regional and international investors, with the order book peaking at $4.6bn – 4.6 times oversubscribed.

    The company finalised the allocation with an average split of 70% to international investors and 30% to Middle East and North Africa investors.

    The $1bn proceeds from the issuance will be deployed to fund Masdar’s equity commitments on new greenfield projects, including several in developing economies, as the company pursues a target portfolio capacity of 100GW by 2030.

    In line with Masdar’s corporate credit ratings, the second issuance was rated AA- by Fitch and A2 by Moody’s.

    First Abu Dhabi Bank, Abu Dhabi Commercial Bank, Citibank, HSBC, Standard Chartered, Credit Agricole CIB, Natixis and MUFG were the lead managers and bookrunners on the issuance.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/12177600/main.jpg
    Jennifer Aguinaldo
  • Firms seek to prequalify for 12 Saudi water projects

    18 July 2024

     

    Local and international utility developers have submitted their statements of qualifications (SOQs) for the contracts to develop and operate 12 water public-private partnership (PPP) projects in Saudi Arabia. 

    State-backed offtaker Saudi Water Partnership Company (SWPC) received separate responses from companies for five independent water projects (IWPs) and seven independent sewage treatment plant (ISTP) projects by 4 July, industry sources tell MEED.

    Local and regional companies, in addition to Japanese, Spanish, French and Chinese utility developers, are understood to have sought to prequalify to bid for the contracts, which are set to be tendered in 2024-26. 

    SWPC's shift from a single-project to a multiple-project prequalification process saves time and resources, according to one of the companies that submitted an SOQ.

    "This is particularly true for international developers, which need to allocate resources across various geographies," the source said.

    Another source said he believes SWPC will prequalify companies for lead and technical roles, among others, and then allow these companies to form teams at a later stage.  

    The client previously said that the programme "will provide the opportunity to local and international developers to obtain pre-qualification approval and receive the request for proposal documents for its future projects … without the need to submit a separate qualification application for each project".

    The five IWP schemes have a total combined capacity of 1.7 million cubic metres a day (cm/d). The seven ISTP projects have a total combined capacity of 700,000 cm/d.

    The kingdom's water sector has been undergoing a restructuring programme, with the capacity procurement process linked to the National Water Strategy being undertaken by three other clients: Saline Water Conversion Company, which has been renamed Saudi Water Authority; Water Transmission & Technologies Company; and the National Water Company.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/12167522/main.gif
    Jennifer Aguinaldo
  • Nama appoints 2027-29 procurement advisers

    18 July 2024

     

    Oman's Nama Power & Water Procurement (Nama PWP) has appointed a transaction advisory team to support its 2027-29 power and water procurement strategy.

    According to an industry source, the team comprises UK-headquartered Deloitte as lead transaction and financial adviser, Canada-based engineering consultancy WSP as technical adviser, and US firm CMS as legal adviser.

    The scope of work won by the advisory team includes preparing the overall procurement strategy, extending existing contracts expiring between 2027 and 2029, and undertaking procurement for new-build plants.

    The contracts for three independent power projects (IPPs) in Oman with a total combined capacity of 3,518MW are expiring between 2028 and 2029, according to the state offtaker's latest Seven-Year Planning Statement, which covers the years 2023 to 2029.

    These gas-fired plants and their power generation capacities are:

    • Barka 3 IPP: 750MW (2028)
    • Sohar 3 IPP: 750MW (2028)
    • Sur IPP: 2,018MW (2029)

    Phoenix Power Company, the project company for the 2,018MW Sur IPP, comprises Japan's Marubeni Corporation and Jera and Qatar's Nebras Power. 

    Shinas Generating Company – owned by Saudi Arabia's Acwa Power, Japan's Mitsui and China's Didic – is the project company for Sohar 3.

    Al-Suwaidi Power is the project company for Barka 3. It comprises France's Engie, Japan's Shikoku Electric and the local Suhail Bahwan Group.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/12166689/main1708.jpg
    Jennifer Aguinaldo
  • UAE keen to start next nuclear plant phase

    18 July 2024

    The UAE government could start the tendering process this year for the state's next nuclear power plant, located in Abu Dhabi, according to a Reuters report citing a senior UAE government official.

    According to the report, Hamad Alkaabi, the UAE's permanent representative to the Austria-based International Atomic Energy Agency, said: "The government is looking at this option. No final decision has been made in terms of the tender process but I can tell you that the government is actively exploring this option."

    The government has yet to budget for a second power plant or decide on the size or location of such a project, but Alkaabi said it is possible a tender could be issued this year, the report added.

    A significant increase in electricity use over the next decade, driven by population growth and an expanding industrial sector, underpins the plan to proceed with the next phase of the state's civilian nuclear power programme.

    Any new power plant would likely consist of two or four reactors, said Alkaabi, who also serves as the deputy chairman of the board of management of the UAE's Federal Authority for Nuclear Regulation.

    The next phase of the Barakah power plant, comprising reactors five to eight, has been in the planning stage since 2019, according to regional projects tracker MEED Projects.

    The UAE became the first Arab state to operate a nuclear power plant when the first of the four reactors at Abu Dhabi’s Barakah nuclear power plant became operational in 2021.

    Each of the four reactors at the Barakah nuclear power plant can produce 1,400MW of electricity.

    Three of the plant’s four reactors are operational. Emirates Nuclear Energy Corporation's operating and maintenance subsidiary, Nawah Energy Company, completed the loading of fuel assemblies into Unit 4 in December 2023. 

    Unit 4 will raise the Barakah plant’s total clean electricity generation capacity to 5,600MW, equivalent to 25% of the UAE’s electricity needs.

    Korea Power Corporation is the prime contractor for the $24.4bn first phase of the Barakah nuclear power plant.

    GlobalData expects nuclear power capacity in the Middle East and North Africa region to grow from zero in 2020 to an estimated 7.1GW by 2030, mainly thanks to Abu Dhabi’s Barakah nuclear energy plant and the first reactors of Egypt’s El-Dabaa nuclear power plant.

    The UAE is one of more than 20 countries that committed to tripling global nuclear energy capacity by 2050 at the UN climate change summit Cop28, which was held in Dubai in late 2023.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/12165779/main1220.jpg
    Jennifer Aguinaldo