Aramco awards $7.7bn Fadhili gas plant expansion contracts
2 April 2024
Register for MEED's guest programme
Saudi Aramco has awarded engineering, procurement and construction (EPC) contracts totalling $7.7bn to expand the Fadhili gas plant in the Eastern Province of Saudi Arabia.
The project is expected to increase the Fadhili gas plant’s processing capacity from 2.5 billion cubic feet a day (cf/d) to up to 4 billion cf/d.
“The additional 1.5 billion cf/d of processing capacity is expected to contribute to the company’s strategy to raise gas production by more than 60% by 2030, compared to 2021 levels,” Aramco said in a statement on 2 April.
The Fadhili gas plant expansion, which is expected to be completed by November 2027, is also anticipated to add 2,300 metric tonnes a day of sulphur production, Aramco added.
MEED recently named frontrunners for the main EPC packages of the project, which will add three processing trains, each with a capacity of 500 million cf/d.
According to sources, the following contractors were in pole position to win the three main EPC works on the Fadhili gas plant expansion project:
- Package 1 – Gas processing plant expansion – Samsung Engineering (South Korea)
- Package 2 – Sulphur recovery units (SRUs) – GS Engineering & Construction (South Korea)
- Package 4 – Utilities and offsites – Samsung Engineering
Aramco’s statement named local contractor Nesma and Partners among the project contract winners. MEED understands the Al Khobar-based contractor has won the contract for package 3, which relates to early civil works on the project.
Aramco declined to respond to MEED’s request for comment on the information at the time.
MEED reported in November that Aramco was preparing to award contracts for the main EPC packages for the Fadhili gas plant expansion project in the first quarter of this year. The Saudi energy giant was previously expected to award the EPC contracts by the end of last year.
Contractors submitted bids for packages 1 and 2 on 16 September, and bids for packages 3 and 4 on 14 October, MEED previously reported.
Aramco issued the tenders for the EPC packages between March and April in 2023 and set 15 July as the initial deadline for submission of proposals, as MEED reported. Aramco organised a site visit for contractors on 15 May.
Four contractors are understood to have been bidding for the Fadhili gas plant expansion project:
- GS Engineering & Construction (South Korea)
- Hyundai Engineering & Construction (South Korea)
- JGC Gulf International (Saudi Arabia subsidiary of Japan-headquartered JGC Corporation)
- Samsung Engineering (South Korea)
US-headquartered KBR is understood to have executed the project’s front-end engineering and design (feed) works.
Fadhili gas processing complex
The Fadhili gas processing complex, located 30 kilometres southwest of the Khursaniyah gas plant, was commissioned in early 2020 and has the capacity to process 2.5 billion cf/d of natural gas.
EPC works on the $6.5bn Fadhili gas processing complex were completed by the end of 2019.
There were five EPC packages in the project’s first phase, contracts for which were awarded in 2015.
Spanish contractor Tecnicas Reunidas was awarded packages 1 and 2, worth $2bn and $1bn, respectively. The scope of work on the two packages related to building the central gas processing facility and the utilities and interconnecting systems.
UK-based Petrofac won package 3, worth about $1.7bn. The scope included the construction of six sulphur recovery trains with associated facilities for sulphur and heavy-duty oil handling, loading, unloading and storage; sour water stripper, flare system and a wastewater treatment plant.
The fourth EPC package, worth about $450m, was awarded to a consortium of India’s Larsen & Toubro Energy Hydrocarbon, Saudi Arabia’s Arkad Engineering & Construction and local firm Denys Arabia. Package 4 related to constructing a pipeline network connecting the Fadhili gas plant to its feeder oil and gas fields and other gas plants in the Eastern Province.
A fifth package for industrial support facilities at the Fadhili gas plant site was awarded to local firm Al-Muhaidib Contracting.
The UK-headquartered Wood Group carried out the feed work on the Fadhili project and was also the project management consultant.
The Fadhili plant processes sour gas from the offshore Khursaniyah oil field and the offshore Hasbah non-associated gas field.
The Fadhili gas project is vital to Aramco’s goal of nearly doubling its gas production and processing capacity from 12 billion cf/d to 23 billion cf/d by the end of this decade.
ALSO READ: Aramco CEO calls fossil fuel phase out a fantasy
Exclusive from Meed
-
Oman tenders three major distribution deals
19 June 2025
-
PIF forms new subsidiary to deliver Expo 2030 Riyadh
19 June 2025
-
Kharafi wins Egypt wastewater deal
19 June 2025
-
Oman receives dams funding
18 June 2025
-
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends

Related Articles
-
Oman tenders three major distribution deals
19 June 2025
Oman Electricity Transmission Company (OETC) has tendered three significant contracts to build new substations in the sultanate.
The first contract, estimated at about $100m, covers the construction of the Majan 400/220/132kV grid station along with an associated 400kV line-in line-out underground cable from Sohar Free Zone to the Sohar Interconnector Station.
The second deal, worth about $35m, covers the construction of the Sultan Haitham City 132/33kV grid station and associated 132kV line-in line-out underground cables running 4 kilometres from Mabella to Mabella Industrial Zone.
The bid submission deadline for both tenders is 3 July.
A tender deadline of 1 July has been set for the construction of the Surab 400/33kV grid station and an associated 400kV line-in line-out cable from the Duqm grid station to the Mahout grid station. Like the Majan substation, the Surab facility has an estimated contract value of about $100m.
In addition, OETC, part of the government-owned Nama Group, is evaluating bids for a number of other major substation construction tenders. These include:
- The 400kV Ras Madraka wind farm grid station
- The 132kV Sadah wind farm grid station
- The 400/132kV Wadi Latham grid station
China Energy Engineering Group Shanxi Electric Power Construction Company recently won the deal to upgrade the 220/132kV Sohar Free Zone grid station, while Oman National Engineering & Investment Company won a contract to build the Mahadha 220kV substation.
In 2024, OETC awarded more than $1.2bn worth of transmission and distribution work. Major signed contracts included:
READ THE JUNE 2025 MEED BUSINESS REVIEW – click here to view PDF
Gulf accelerates AI and data centre strategy; Baghdad keeps up project spending, but fiscal clouds gather; Banking stocks rise despite lower global oil prices
Distributed to senior decision-makers in the region and around the world, the June 2025 edition of MEED Business Review includes:
> AGENDA 1: Data centres churn investments> AGENDA 2: Gulf seizes AI opportunities> MEED TOP 100: Middle East stocks defy lower oil prices> SAUDI ARABIA: Riyadh confirms capital expenditure cuts> INTERVIEW: Mena crucial to Veolia’s growth plan> GULF PROJECTS INDEX: Gulf projects index leaps 4.3%> CONTRACT AWARDS: Region sees third month of weak awards activity> ECONOMIC DATA: Data drives regional projects> OPINION: Dealmaking trumps the Truman DoctrineTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/14100049/main.gif -
PIF forms new subsidiary to deliver Expo 2030 Riyadh
19 June 2025
Register for MEED’s 14-day trial access
Saudi sovereign wealth vehicle the Public Investment Fund (PIF) has launched Expo 2030 Riyadh Company (ERC) as a wholly-owned subsidiary to build and operate facilities for Expo 2030.
In a statement, the PIF said: “During its construction phases, Expo 2030 Riyadh and its legacy are projected to contribute around $64bn to Saudi GDP and generate approximately 171,000 direct and indirect jobs. Once operational, it is expected to contribute approximately $5.6bn to GDP.”
The masterplan for Expo 2030 Riyadh encompasses an area of 6 square kilometres, making it one of the largest sites designated for a World Expo. Situated to the north of the city, the expo site will be located near the future King Salman International airport, providing direct access to various landmarks within the Saudi capital.
Countries participating in Expo 2030 Riyadh will have the option to construct permanent pavilions, contributing to the event's legacy. This initiative is expected to create opportunities for business and investment growth in the region.
The expo is projected to attract over 40 million visitors. After the event concludes, ERC plans to convert the expo's secured area into a global village, to serve as a multicultural centre for retail and dining. This development will also include an international residential community with various amenities, with a focus on sustainable tourism practices.
Expo 2030 Riyadh will run from 1 October 2030 to 31 March 2031.
In mid-May, MEED reported that Riyadh had begun talks with various stakeholders in preparation for the start of the construction works for the event.
The discussions were understood to have been held with the Royal Commission for Riyadh City and the PIF.
German architectural firm Lava Architects and US-based engineering firm Jacobs are assisting with the project masterplan and the design of infrastructure for the site.
READ THE JUNE 2025 MEED BUSINESS REVIEW – click here to view PDF
Gulf accelerates AI and data centre strategy; Baghdad keeps up project spending, but fiscal clouds gather; Banking stocks rise despite lower global oil prices
Distributed to senior decision-makers in the region and around the world, the June 2025 edition of MEED Business Review includes:
> AGENDA 1: Data centres churn investments> AGENDA 2: Gulf seizes AI opportunities> MEED TOP 100: Middle East stocks defy lower oil prices> SAUDI ARABIA: Riyadh confirms capital expenditure cuts> INTERVIEW: Mena crucial to Veolia’s growth plan> GULF PROJECTS INDEX: Gulf projects index leaps 4.3%> CONTRACT AWARDS: Region sees third month of weak awards activity> ECONOMIC DATA: Data drives regional projects> OPINION: Dealmaking trumps the Truman DoctrineTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/14099688/main.jfif -
Kharafi wins Egypt wastewater deal
19 June 2025
Kuwaiti contractor Mohamed Abdulmohsin Al-Kharafi & Sons has won a €69m ($79m) contract to design and build a new wastewater treatment plant (WWTP) in Tanta with a capacity of 100,000 cubic metres a day (cm/d).
Four other international and local contractors bid for the 30-month contract tendered by Gharbia Company for Water & Wastewater.
The aim of the project is to have an installed flow rate of 100,000 cm/d by 2037, expanded under a later phase to 150,000 cm/d by 2057.
The scheme is a core component of the $730m Kitchener Drain Depollution project funded by the European Investment Bank and the European Bank for Reconstruction & Development.
The programme’s aim is to depollute the Kitchener Drain, also called the Main Gharbia Drain, one of the main agricultural drains in the Nile delta. Some 69 kilometres long, the drain is the main source of irrigation water for about 193,000 hectares of agricultural land.
However, it is highly polluted due to poorly or untreated domestic wastewater discharge; uncontrolled municipal solid waste disposal into and along the banks of the drain; industrial wastewater discharges; and agricultural runoff.
Other significant projects under the programme include a $28m contract awarded in March 2024 to rehabilitate the Umm Tahoun, Arbaeen and Al-Suyah canals; a separate $40m deal to rehabilitate bridges across the drain and depollute the Beshbish, Sanbara and Shemy canals; and an estimated $70m contract to build new mechanical and biological treatment facilities with total capacity of 1,800 tonnes a day in the city of Defra, for which tender evaluation is under way.
Tanta is one of many WWTP projects tendered or awarded in Egypt over the past five years. Recently, a general procurement notice was issued for the fourth-phase design-build expansion of the giant Abu Rawash WWTP in Giza, while in late May, a grouping of the local Hassan Allam Construction and UAE-headquartered Metito won an estimated $200m contract to upgrade and expand the Alexandria West WWTP.
The world’s largest WWTP, the 7.5 million cm/d New Delta Irrigation plant, was completed in 2023. It was preceded by the 5 million cm/d Bahr El-Baqr facility commissioned two years earlier.
READ THE JUNE 2025 MEED BUSINESS REVIEW – click here to view PDF
Gulf accelerates AI and data centre strategy; Baghdad keeps up project spending, but fiscal clouds gather; Banking stocks rise despite lower global oil prices
Distributed to senior decision-makers in the region and around the world, the June 2025 edition of MEED Business Review includes:
> AGENDA 1: Data centres churn investments> AGENDA 2: Gulf seizes AI opportunities> MEED TOP 100: Middle East stocks defy lower oil prices> SAUDI ARABIA: Riyadh confirms capital expenditure cuts> INTERVIEW: Mena crucial to Veolia’s growth plan> GULF PROJECTS INDEX: Gulf projects index leaps 4.3%> CONTRACT AWARDS: Region sees third month of weak awards activity> ECONOMIC DATA: Data drives regional projects> OPINION: Dealmaking trumps the Truman DoctrineTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/14098452/main.gif -
Oman receives dams funding
18 June 2025
The Islamic Development Bank (ISDB) has extended a $632m loan to the Ministry of Agricultural, Fisheries Wealth & Water Resources to fund the construction of four major flood protection dams in the sultanate.
The dam projects are:
- The Wadi Al-Khoud Flood Protection Dam (AK01) in Seeb
- The Wadi Rijma Flood Protection Dam (R2A) in Liwa
- The Wadi Majlas Flood Protection Dam in Qurayat
- The Wadi Ahin Flood Protection Dam in Saham North
Each of the dam schemes will be open to bids from both local and international contractors, although it is unclear at this stage when the tenders will be issued.
Separately, contractors are preparing to submit technical and commercial bids by 23 June for the ISDB-funded project to build two flood protection dams at Wadi Al-Ansab, called ANS-02 and ANS-03.
The estimated $80m contract involves the following scope of work for each dam:
- An embankment dam with geomembrane sealing at the upstream face
- A plinth at the upstream toe of the dam and plastic concrete cut-off wall at the foundation
- Curtain/consolidation/contact grouting works along the cut-off wall, plinth at the abutments, spillway ogee structure and bottom outlet
- A reinforced concrete spillway located at the left abutment and composed of approach channel, crest, chute and tailwater channel slabs and walls
- Shotcrete and slope stabilisation works for open excavations
- Bottom outlet system with intake tower, conduit, energy dissipation basin and access bridge to the intake tower
- Bottom outlet control gates
- Dam monitoring system
- Restitution works at the reservoir area
- Providing electricity supply for operation of the gates
- Access road, fencing and access gates
Potential bidders include:
- Strabag Oman
- Arab Contractors (Egypt)
- Serka Taahhut Insaat (Turkiye)
- Khimji Ramdas (local)
- Galfar (local)
- Sarooj Construction Company (local)
- Al-Jafar Contracting Company (Jordan)
READ THE JUNE 2025 MEED BUSINESS REVIEW – click here to view PDF
Gulf accelerates AI and data centre strategy; Baghdad keeps up project spending, but fiscal clouds gather; Banking stocks rise despite lower global oil prices
Distributed to senior decision-makers in the region and around the world, the June 2025 edition of MEED Business Review includes:
> AGENDA 1: Data centres churn investments> AGENDA 2: Gulf seizes AI opportunities> MEED TOP 100: Middle East stocks defy lower oil prices> SAUDI ARABIA: Riyadh confirms capital expenditure cuts> INTERVIEW: Mena crucial to Veolia’s growth plan> GULF PROJECTS INDEX: Gulf projects index leaps 4.3%> CONTRACT AWARDS: Region sees third month of weak awards activity> ECONOMIC DATA: Data drives regional projects> OPINION: Dealmaking trumps the Truman DoctrineTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/14091190/main.gif -
Contractors submit prices for QatarEnergy NGL train project
18 June 2025
Register for MEED’s 14-day trial access
Contractors have submitted commercial bids to QatarEnergy for a project to add a fifth natural gas liquids (NGL) train at its NGL complex in Qatar’s Mesaieed Industrial City.
The objective of the project, which is estimated to be worth $2.5bn, is to build a fifth NGL train (NGL-5) with the capacity to process up to 350 million cubic feet a day of rich associated gas from QatarEnergy’s offshore and onshore oil fields.
Contractors submitted commercial bids for engineering, procurement and construction (EPC) works on the NGL-5 project by the deadline of 15 June, according to sources.
The following contractors are understood to be participating in the project’s main contract tendering process:
- CTCI Corporation (Taiwan)
- Larsen & Toubro Energy Hydrocarbon (India)
- McDermott (US)
- Saipem (Italy)
- Samsung E&A (South Korea)
- Tecnicas Reunidas (Spain)
- Tecnimont (Italy)
QatarEnergy initially set a deadline of the end of May for the submission of prices for the project.
MEED previously reported that QatarEnergy had received technical bids for the project from contractors by the deadline of 13 April.
QatarEnergy issued the expression of interest (EoI) document for the NGL-5 project in early June of last year, with contractors submitting responses by 24 June 2024, MEED previously reported.
QatarEnergy eventually issued the main EPC tender for the NGL-5 project in November 2024.
In the EoI document, QatarEnergy said that it had begun site preparation works for the project in the fourth quarter of 2023 and expected work to be completed in the first quarter of 2025.
Turkish contractor Iris Insaat is performing site preparation work on the project, according to regional projects tracker MEED Projects.
QatarEnergy intends to start operations at the NGL-5 facility by the second quarter of 2028.
Project scope
Associated gas from the PS1, PS2 and PS3 offshore fields and the Dukhan onshore field is processed at existing facilities in the NGL complex at Mesaieed – the FSP, NGL-1 and Qapco ERU units.
The planned NGL-5 facility will replace these three units at the Mesaieed complex and process gas from the PS1, PS2 and Dukhan fields.
The scope of work on the project involves EPC work on units for the following functions:
- Feed gas compression
- Slug handling
- Gas sweetening
- Dehydration
- Mercury removal
- NGL fractionation
- NGL recovery
- Product treatment
- Propane refrigeration
- Acid gas enrichment
- Sulphur recovery
- Anti-flaring
- Utilities
- Boil-off gas recovery
- Drains and collection networks
- Effluent water treatment plant
- Carbon dioxide treatment and sequestration/ export
- Brownfield modifications
- Product rundown pipelines
QatarEnergy is understood to have divided the scope of work on the NGL-5 project into five EPC packages.
ALSO READ: QatarEnergy receives bids for new NGL train project
READ THE JUNE 2025 MEED BUSINESS REVIEW – click here to view PDF
Gulf accelerates AI and data centre strategy; Baghdad keeps up project spending, but fiscal clouds gather; Banking stocks rise despite lower global oil prices
Distributed to senior decision-makers in the region and around the world, the June 2025 edition of MEED Business Review includes:
> AGENDA 1: Data centres churn investments> AGENDA 2: Gulf seizes AI opportunities> MEED TOP 100: Middle East stocks defy lower oil prices> SAUDI ARABIA: Riyadh confirms capital expenditure cuts> INTERVIEW: Mena crucial to Veolia’s growth plan> GULF PROJECTS INDEX: Gulf projects index leaps 4.3%> CONTRACT AWARDS: Region sees third month of weak awards activity> ECONOMIC DATA: Data drives regional projects> OPINION: Dealmaking trumps the Truman DoctrineTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/14089234/main1845.jpg