Aramco awards $7.7bn Fadhili gas plant expansion contracts

2 April 2024

Register for MEED's guest programme 

Saudi Aramco has awarded engineering, procurement and construction (EPC) contracts totalling $7.7bn to expand the Fadhili gas plant in the Eastern Province of Saudi Arabia.

The project is expected to increase the Fadhili gas plant’s processing capacity from 2.5 billion cubic feet a day (cf/d) to up to 4 billion cf/d.

“The additional 1.5 billion cf/d of processing capacity is expected to contribute to the company’s strategy to raise gas production by more than 60% by 2030, compared to 2021 levels,” Aramco said in a statement on 2 April.

The Fadhili gas plant expansion, which is expected to be completed by November 2027, is also anticipated to add 2,300 metric tonnes a day of sulphur production, Aramco added.

MEED recently named frontrunners for the main EPC packages of the project, which will add three processing trains, each with a capacity of 500 million cf/d.

According to sources, the following contractors were in pole position to win the three main EPC works on the Fadhili gas plant expansion project:

  • Package 1 – Gas processing plant expansion – Samsung Engineering (South Korea)
  • Package 2 – Sulphur recovery units (SRUs) – GS Engineering & Construction (South Korea)
  • Package 4 – Utilities and offsites – Samsung Engineering

Aramco’s statement named local contractor Nesma and Partners among the project contract winners. MEED understands the Al Khobar-based contractor has won the contract for package 3, which relates to early civil works on the project.

Aramco declined to respond to MEED’s request for comment on the information at the time.

MEED reported in November that Aramco was preparing to award contracts for the main EPC packages for the Fadhili gas plant expansion project in the first quarter of this year. The Saudi energy giant was previously expected to award the EPC contracts by the end of last year.

Contractors submitted bids for packages 1 and 2 on 16 September, and bids for packages 3 and 4 on 14 October, MEED previously reported.

Aramco issued the tenders for the EPC packages between March and April in 2023 and set 15 July as the initial deadline for submission of proposals, as MEED reported. Aramco organised a site visit for contractors on 15 May.

Four contractors are understood to have been bidding for the Fadhili gas plant expansion project:

  • GS Engineering & Construction (South Korea)
  • Hyundai Engineering & Construction (South Korea)
  • JGC Gulf International (Saudi Arabia subsidiary of Japan-headquartered JGC Corporation)
  • Samsung Engineering (South Korea)

US-headquartered KBR is understood to have executed the project’s front-end engineering and design (feed) works.

Fadhili gas processing complex

The Fadhili gas processing complex, located 30 kilometres southwest of the Khursaniyah gas plant, was commissioned in early 2020 and has the capacity to process 2.5 billion cf/d of natural gas.

EPC works on the $6.5bn Fadhili gas processing complex were completed by the end of 2019.

There were five EPC packages in the project’s first phase, contracts for which were awarded in 2015.

Spanish contractor Tecnicas Reunidas was awarded packages 1 and 2, worth $2bn and $1bn, respectively. The scope of work on the two packages related to building the central gas processing facility and the utilities and interconnecting systems.

UK-based Petrofac won package 3, worth about $1.7bn. The scope included the construction of six sulphur recovery trains with associated facilities for sulphur and heavy-duty oil handling, loading, unloading and storage; sour water stripper, flare system and a wastewater treatment plant.

The fourth EPC package, worth about $450m, was awarded to a consortium of India’s Larsen & Toubro Energy Hydrocarbon, Saudi Arabia’s Arkad Engineering & Construction and local firm Denys Arabia. Package 4 related to constructing a pipeline network connecting the Fadhili gas plant to its feeder oil and gas fields and other gas plants in the Eastern Province.

A fifth package for industrial support facilities at the Fadhili gas plant site was awarded to local firm Al-Muhaidib Contracting.

The UK-headquartered Wood Group carried out the feed work on the Fadhili project and was also the project management consultant.

The Fadhili plant processes sour gas from the offshore Khursaniyah oil field and the offshore Hasbah non-associated gas field.

The Fadhili gas project is vital to Aramco’s goal of nearly doubling its gas production and processing capacity from 12 billion cf/d to 23 billion cf/d by the end of this decade.

ALSO READ: Aramco CEO calls fossil fuel phase out a fantasy

https://image.digitalinsightresearch.in/uploads/NewsArticle/11652087/main0457.jpeg
Indrajit Sen
Related Articles
  • Kuwait halves drilling contractor pool

    22 September 2026

     

    State-owned upstream operator Kuwait Oil Company (KOC) has reduced the number of approved contractors for onshore drilling and shallow-well maintenance from 51 to 24.

    Firms that are no longer qualified include major contractors such as Italy’s Saipem, Oklahoma-based Helmerich & Payne and Houston-based Patterson-UTI Energy.

    The latest list still includes a wide range of Kuwaiti, regional and international companies, according to the latest update on its electronic system, published on 21 September 2026.

    The full list of contractors that are now qualified to participate in tenders is:

    • Burgan Company for Well Drilling, Trading & Maintenance (Kuwait)
    • Kuwait Drilling Company (Kuwait)
    • Sun Drilling Kuwait (Kuwait)
    • TDL Kuwait for Oil Rigs & Natural Gas Extraction Activities, Services and Facilities (Kuwait)
    • United Precision Drilling (Kuwait)
    • Abraj Energy Services (Oman)
    • Adnoc Drilling Company (UAE)
    • Arabian Drilling Company (Saudi Arabia)
    • Anton Oilfield Services (China)
    • China Oilfield Services (China)
    • Egyptian Drilling Company (Egypt)
    • CNPC Bohai Drilling Engineering Company (China)
    • Great Wall Drilling Company (China)
    • John Energy (India)
    • Kerui Oilfield Service (China)
    • KCA Deutag Drilling (Germany)
    • Mohammed Al-Barwani Petroleum Services (Oman)
    • Nabors Drilling International (US)
    • National Drilling & Services Company (Oman)
    • Sea & Land Drilling Contractors (Oman)
    • Sinopec International Petroleum Service Corporation (China)
    • Karamay Jianye Energy (China)
    • Modern Drilling Company (Egypt)
    • Grey Wolf Drilling International (US)

    An earlier list, which was published on 11 February, included 51 qualified companies.

    The reduction in qualified drilling contractors follows KOC’s notice on 27 April this year, informing existing qualified contractors that they would need to reapply.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19863744/main3435.jpg
    Wil Crisp
  • Abu Dhabi expects 45% emissions cut as electricity demand rises

    21 September 2026

    Register for MEED’s 14-day trial access 

    Abu Dhabi-based Emirates Water & Electricity Company (Ewec) expects carbon emissions from power and water production to fall by more than 45% by 2035 as the UAE expands renewable energy and reverse osmosis (RO) desalination.

    The state offtaker's latest long-term system planning forecasts emissions will decline from about 42 million tonnes in 2019 to approximately 23 million tonnes in 2035.

    The reduction is expected despite annual electricity demand that is forecast to rise by about 70% in 2026-33.

    Ewec said the expansion of renewable energy and the shift towards RO desalination will be the principal drivers of the reduction.

    The company plans to increase Abu Dhabi's solar capacity to 14GW by 2030 and more than 35GW by 2035. This will be supported by up to 15GW of battery storage capacity.

    According to regional project tracker MEED Projects, Ewec has over $16bn-worth of power and water projects in the execution stage as part of its long-term procurement programme to increase renewable energy and low-carbon water production capacity.

    This includes a 5.2GW Abu Dhabi solar and battery energy storage system (bess) round-the-clock renewable energy project, as well as three 1.5GW solar photovoltaic independent power projects (IPP): Al-Ajban, Al-Khazna and Al-Zarraf.

    It also comprises the 1GW Al-Dhafra open-cycle gas turbine power plant, the 2.5GW Taweelah C combined-cycle gas turbine (CCGT) plant and a separate 400MW bess IPP.

    As previously reported, it is expected that the developer's agreement for the 3.3GW Al-Nouf 1 CCGT IPP will be signed by the end of the year, while contractors are preparing to submit bids for a separate 2.6GW power plant project in Ajman.

    The expansion of solar and battery storage is expected to reduce the system's reliance on gas-fired generation. However, gas-fired generation will continue to provide flexibility to support the system and balance intermittent renewable power output, according to Ewec. 

    The offtaker also expects RO desalination to account for more than 95% of total water production by 2035, with the procurement programme supporting the Abu Dhabi Department of Energy's Clean Energy Strategic Target 2035 for electricity production and the UAE Net Zero by 2050 Strategy.


    READ THE SEPTEMBER 2026 MEED BUSINESS REVIEW – click here to view PDF

    Nuclear power ambitions gather pace; Kuwait keeps dealmaking alive despite war; Region invests in raising gas processing capacity.

    Distributed to senior decision-makers in the region and around the world, the September 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/19849749/main.jpg
    Mark Dowdall
  • Seven bid for Bahrain highway upgrade

    21 September 2026

    Register for MEED’s 14-day trial access 

    Seven contractors have submitted bids for the next phase of the Sheikh Jaber Al-Ahmed Al-Sabah Highway upgrade project.

    According to results published by the Bahrain Tender Board, the firms that have submitted bids include:

    • Nass Contracting Company
    • Haji Hassan Group
    • Almoayyed Contracting Group
    • Mohammed Abdulmohsen Al-Kharafi & Sons
    • Eastern Asphalt & Concrete Production
    • Cebarco Bahrain
    • Kingdom Asphalt

    The contract scope includes expansion works on 2 kilometres of the highway. It consists of a four-lane dual carriageway with service roads on both sides.

    The scope of works also includes excavation and backfill work, construction of stormwater drainage networks, a pumping station, installation of ducts for future utilities, upgraded street lighting, traffic signs and directional signage.

    The project aims to improve traffic capacity, reduce congestion and enhance safety along the transport corridor linking Manama with industrial zones.

    In April, MEED reported that Bahrain had approved a financing agreement framework to fund the construction of the next phase of the Sheikh Jaber Al-Ahmed Al-Sabah Highway upgrade.

    In March last year, the Kuwait Fund for Arab Economic Development and the Bahraini government signed a KD10m ($32.4m) loan agreement to fund the second phase of the project, which is expected to cost about $404m.

    This was followed in September 2025 by the appointment of US-based Parsons Corporation on a $1.5m contract to provide pre-contract engineering consultancy services for the project.

    According to data from regional project tracker MEED Projects, construction of the first phase was completed in 2020.

    A joint venture of local firm Nass Contracting and Kuwait’s KCC Engineering & Contracting undertook the main construction works.


    READ THE SEPTEMBER 2026 MEED BUSINESS REVIEW – click here to view PDF

    Nuclear power ambitions gather pace; Kuwait keeps dealmaking alive despite war; Region invests in raising gas processing capacity.

    Distributed to senior decision-makers in the region and around the world, the September 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/19847073/main.png
    Yasir Iqbal
  • Teams prepare bids for Oman PPP wastewater project

    21 September 2026

     

    At least three consortiums are preparing bids for a contract to develop and operate two major sewage treatment plants (STPs) in Oman.

    The public-private partnership (PPP) project covers expanding two Muscat-based plants: the Al-Ansab STP (phase three) and the Al-Amerat STP (phase two). It will be delivered under a build-own-operate-transfer model.

    At Al-Ansab, capacity will increase from 125,000 cubic metres a day (cm/d) to 207,000 cm/d. At Al-Amerat, capacity will rise from 18,000 cm/d to 54,000 cm/d.

    According to sources, the bidders for the project include:

    • Etihad Water & Electricity (UAE) / Metito (UAE)
    • Lamar Holding (Bahrain) / Tawzea (Saudi Arabia)
    • Civil Works Company (CWC, Saudi Arabia)  / Suez (France)

    The bid submission deadline is 5 January 2027.

    State-owned Nama Water Services (NWS) issued a request for proposals for the project in July, as exclusively reported by MEED.

    It is understood that Veolia (France), Miahona (Saudi Arabia) and Samsung E&A (South Korea) are also among the firms that prequalified for the project after the request for qualifications was issued last November.

    The project scope includes the design, financing, construction, operation and maintenance of the new facilities, alongside the long-term operation of the existing facilities.

    It has been over a decade since the Al-Ansab STP first entered full operation at a capacity of about 54,000 cm/d. In 2015, South Korea’s Doosan Ennerbility, formerly Doosan Heavy Industries, was awarded the main engineering, procurement, and construction contract for the phase two expansion, which increased the facility’s maximum flow capacity to 125,000 cm/d. This phase was completed in 2017.

    Phase one of the Al-Amerat STP was awarded to a joint venture of France’s Degremont (Suez) and local contractor Al-Ansari Trading Enterprise under a design, build and short-term operation contract valued at about €50m ($58.1m). The plant was developed for Haya Water and commissioned in 2019 as part of the Muscat wastewater scheme.

    Haya Water, the former wastewater utility, was later incorporated into NWS following a government restructuring programme.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19794912/main.jpg
    Mark Dowdall
  • Oman reveals Sohar airport and Salalah Thumrait Road plans

    21 September 2026

    Oman is planning a new passenger terminal at Sohar Airport to expand regional air connectivity and strengthen the airport’s role in the national aviation network.

    According to Said Bin Hamoud Al-Maawali, Oman’s minister of transport, communications and information technology, new routes are expected to be announced before the end of the year. Potential destinations include Dammam in Saudi Arabia, Gwadar in Pakistan, and southern Iran.

    The planned terminal and additional routes will give residents of northern Oman more travel options.

    Al-Maawali also provided an update on the long-delayed Salalah-Thumrait truck road, saying the project will be procured through a conventional tendering model rather than a public-private partnership (PPP).

    In August 2023, Oman shortlisted five of eight prequalified teams to compete for the Salalah-Thumrait truck road project, which was set to be the sultanate’s first PPP road project.

    The 67-kilometre road project is specially designed for heavy vehicles. 

    The road is a key link in Dhofar’s transport network, connecting Thumrait with Salalah and supporting movement between the interior and the governorate’s main urban and economic centre.


    READ THE SEPTEMBER 2026 MEED BUSINESS REVIEW – click here to view PDF

    Nuclear power ambitions gather pace; Kuwait keeps dealmaking alive despite war; Region invests in raising gas processing capacity.

    Distributed to senior decision-makers in the region and around the world, the September 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/19794881/main.jpg
    Yasir Iqbal