Aramco awards $7.7bn Fadhili gas plant expansion contracts

2 April 2024

Register for MEED's guest programme 

Saudi Aramco has awarded engineering, procurement and construction (EPC) contracts totalling $7.7bn to expand the Fadhili gas plant in the Eastern Province of Saudi Arabia.

The project is expected to increase the Fadhili gas plant’s processing capacity from 2.5 billion cubic feet a day (cf/d) to up to 4 billion cf/d.

“The additional 1.5 billion cf/d of processing capacity is expected to contribute to the company’s strategy to raise gas production by more than 60% by 2030, compared to 2021 levels,” Aramco said in a statement on 2 April.

The Fadhili gas plant expansion, which is expected to be completed by November 2027, is also anticipated to add 2,300 metric tonnes a day of sulphur production, Aramco added.

MEED recently named frontrunners for the main EPC packages of the project, which will add three processing trains, each with a capacity of 500 million cf/d.

According to sources, the following contractors were in pole position to win the three main EPC works on the Fadhili gas plant expansion project:

  • Package 1 – Gas processing plant expansion – Samsung Engineering (South Korea)
  • Package 2 – Sulphur recovery units (SRUs) – GS Engineering & Construction (South Korea)
  • Package 4 – Utilities and offsites – Samsung Engineering

Aramco’s statement named local contractor Nesma and Partners among the project contract winners. MEED understands the Al Khobar-based contractor has won the contract for package 3, which relates to early civil works on the project.

Aramco declined to respond to MEED’s request for comment on the information at the time.

MEED reported in November that Aramco was preparing to award contracts for the main EPC packages for the Fadhili gas plant expansion project in the first quarter of this year. The Saudi energy giant was previously expected to award the EPC contracts by the end of last year.

Contractors submitted bids for packages 1 and 2 on 16 September, and bids for packages 3 and 4 on 14 October, MEED previously reported.

Aramco issued the tenders for the EPC packages between March and April in 2023 and set 15 July as the initial deadline for submission of proposals, as MEED reported. Aramco organised a site visit for contractors on 15 May.

Four contractors are understood to have been bidding for the Fadhili gas plant expansion project:

  • GS Engineering & Construction (South Korea)
  • Hyundai Engineering & Construction (South Korea)
  • JGC Gulf International (Saudi Arabia subsidiary of Japan-headquartered JGC Corporation)
  • Samsung Engineering (South Korea)

US-headquartered KBR is understood to have executed the project’s front-end engineering and design (feed) works.

Fadhili gas processing complex

The Fadhili gas processing complex, located 30 kilometres southwest of the Khursaniyah gas plant, was commissioned in early 2020 and has the capacity to process 2.5 billion cf/d of natural gas.

EPC works on the $6.5bn Fadhili gas processing complex were completed by the end of 2019.

There were five EPC packages in the project’s first phase, contracts for which were awarded in 2015.

Spanish contractor Tecnicas Reunidas was awarded packages 1 and 2, worth $2bn and $1bn, respectively. The scope of work on the two packages related to building the central gas processing facility and the utilities and interconnecting systems.

UK-based Petrofac won package 3, worth about $1.7bn. The scope included the construction of six sulphur recovery trains with associated facilities for sulphur and heavy-duty oil handling, loading, unloading and storage; sour water stripper, flare system and a wastewater treatment plant.

The fourth EPC package, worth about $450m, was awarded to a consortium of India’s Larsen & Toubro Energy Hydrocarbon, Saudi Arabia’s Arkad Engineering & Construction and local firm Denys Arabia. Package 4 related to constructing a pipeline network connecting the Fadhili gas plant to its feeder oil and gas fields and other gas plants in the Eastern Province.

A fifth package for industrial support facilities at the Fadhili gas plant site was awarded to local firm Al-Muhaidib Contracting.

The UK-headquartered Wood Group carried out the feed work on the Fadhili project and was also the project management consultant.

The Fadhili plant processes sour gas from the offshore Khursaniyah oil field and the offshore Hasbah non-associated gas field.

The Fadhili gas project is vital to Aramco’s goal of nearly doubling its gas production and processing capacity from 12 billion cf/d to 23 billion cf/d by the end of this decade.

ALSO READ: Aramco CEO calls fossil fuel phase out a fantasy

https://image.digitalinsightresearch.in/uploads/NewsArticle/11652087/main0457.jpeg
Indrajit Sen
Related Articles
  • Chinese contractor appointed for 500MW Oman solar plant

    22 July 2026

    China's Shanxi Installation Group has secured an estimated $222m engineering, procurement and construction (EPC) contract for the 500MW Al-Kamil 1 solar independent power project (IPP) in Oman.

    In a filing on the Hong Kong stock exchange, the company said the deal marks its first major project in the Middle East.

    The contract covers the EPC, grid connection, testing and commissioning of the utility-scale solar photovoltaic (PV) plant, as well as 2.5 years of operations and maintenance. 

    A consortium comprising France's EDF Power Solutions, Oman National Engineering & Investment Company and OQ Alternative Energy signed the power purchase agreement for the project with Nama Power & Water Procurement Company (Nama PWP) in June.

    Nama PWP is the sole procurer of new electricity generation capacity in Oman.

    The Al-Kamil 1 solar IPP is EDF Power Solutions' third renewable energy project in Oman, following the 500MW Manah 1 solar PV IPP and the 120MW JBB wind IPP.

    As MEED has previously reported, the Al-Kamil 1 project is part of Nama PWP's renewable energy development pipeline, which also includes the 400MW Sinaw and 280MW Marsa solar IPPs.

    Nama PWP is currently tendering supervisory services for the Marsa IPP, with a bid submission deadline of 26 July.

    The pipeline also comprises the 800MW Mahout and 300MW Duqm 2 wind IPPs, both targeted for commissioning between 2027 and 2029.


    READ THE JULY 2026 MEED BUSINESS REVIEW – click here to view PDF

    Stress test for Gulf aviation; Mixed performance as country outlooks diverge in the Levant; GCC tourism sector pivots from crisis to recovery mode.

    Distributed to senior decision-makers in the region and around the world, the July 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/17725741/main.jpg
    Mark Dowdall
  • Fluor wins feed contract for key Bahrain aromatics facility

    22 July 2026

    Bahrain’s Gulf Petrochemical Industries Company (GPIC) has awarded US-based consultant Fluor a contract for front-end engineering and design (feed) on an aromatics facility in the country.

    The project will be an expansion of GPIC’s existing petrochemicals facility in Bahrain’s downstream complex in Sitra, which produces ammonia, urea and methanol.

    The new aromatics facility will utilise “commercially-proven process technologies” to produce approximately 1.2 million metric tonnes a year (t/y) of paraxylene and 500,000 metric t/y of benzene, Texas-headquartered Fluor said.

    Paraxylene and benzene are critical building blocks for plastics, polyester fibers and packaging materials, supporting global demand for high‑performance consumer and industrial products.

    Founded in 1979, GPIC is a joint venture of Bahraini state energy enterprise Bapco Energies, known at the time as Nogaholding; chemicals giant Saudi Basic Industries Corporation (Sabic); and Petrochemical Industries Company – a subsidiary of state energy conglomerate Kuwait Petroleum Corporation. The three partners hold equal stakes of 33.3% in GPIC.

    GPIC utilises locally available natural gas as feedstock to manufacture high-quality chemicals and fertilisers for domestic consumption and export, including 1,200 metric tonnes a day (t/d) of ammonia, 1,200 metric t/d of methanol and 1,700 metric t/d of granular urea.

    ALSO READ: Bahrain taps consultants for studying use of nuclear power

    READ THE JULY 2026 MEED BUSINESS REVIEW – click here to view PDF

    Stress test for Gulf aviation; Mixed performance as country outlooks diverge in the Levant; GCC tourism sector pivots from crisis to recovery mode.

    Distributed to senior decision-makers in the region and around the world, the July 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/17725737/main1255.jpg
    Indrajit Sen
  • Firms submit bids for second Hassyan SWRO pipeline contract

    22 July 2026

    Dubai Electricity & Water Authority (Dewa) has received bids from three contractors for a second pipeline contract relating to the Hassyan seawater reverse osmosis (SWRO) network expansion.

    Project two requires contractors to supply, install, test and commission glass-reinforced epoxy (GRE) water transmission pipelines and associated works for the plant's phase two network.

    Local firm Tristar Engineering & Construction submitted the lowest offer of AED792.59m ($215.8m), according to tender results published by the state utility.

    Green Oasis General Contracting (UAE) submitted a bid of AED800.02m ($217.8m) and Wade Adams Contracting (UAE) made the other compliant offer of AED989.65m ($269.5m).

    In January, Dewa announced that construction of the 180-million-imperial-gallon-a-day phase one of the Hassyan SWRO independent water project was 90% complete.

    Earlier in July, eight contractors submitted bids for project one of the Hassyan pipeline network expansion.

    Dewa also has a third contract out for tender for GRE water transmission pipeline work related to the Hassyan SWRO phase two network.

    Project three was tendered on 26 January and has a bid submission deadline of 29 July.


    READ THE JULY 2026 MEED BUSINESS REVIEW – click here to view PDF

    Stress test for Gulf aviation; Mixed performance as country outlooks diverge in the Levant; GCC tourism sector pivots from crisis to recovery mode.

    Distributed to senior decision-makers in the region and around the world, the July 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/17723861/main.jpg
    Mark Dowdall
  • Riyadh seeks contractors for Expo Icon structure

    22 July 2026

     

    Expo 2030 Riyadh Company (ERC), which is tasked with delivering the Expo 2030 Riyadh venue, has asked contractors to express interest in the construction of the Icon, one of the key landmarks at the site.

    The structure will be located at the entrance of the Expo 2030 Riyadh site, within the Collaboration Precinct.

    ERC issued the expressions of interest notice on 20 July. The deadline for submissions of interest is 23 July.

    The structure will be connected to the metro station and will serve as a gateway to the event.

    It will be 66 metres tall and will comprise an observation platform, food and beverage outlets and other features.

    The total built-up area will be approximately 16,279 square metres and it will be able to accommodate more than 1,450 visitors an hour during the event.

    The contract duration is 29 months from the start of construction.

    ERC tendered the contract for the construction of the Saudi Arabia pavilion at the site in May.

    The pavilion is a major asset located within the venue's KSA District, on the eastern side of the Expo 2030 Riyadh masterplan, within the Loop of Nations district.

    Construction progress

    The tendering of the pavilion structure followed swift progress on the site’s infrastructure development works.

    In April, ERC awarded two contracts for the next phase of infrastructure works at the site to local firm Al-Yamama Company.

    The scope covered the construction of road networks and infrastructure for water, sewage, electricity, telecommunications and electric vehicle charging.

    These awards followed ERC’s January award of an estimated SR1bn ($267m) contract for initial infrastructure works at the site to local firm Nesma & Partners. That scope covered about 50 kilometres of integrated infrastructure networks, including internal roads and essential utilities such as water, sewage, electrical and communications systems, and electric vehicle charging stations.

    The overall infrastructure works – covering the construction of main utilities and civil works at Expo 2030 Riyadh – are split into three packages:

    • Lot 1 covers the main utilities corridor;
    • Lot 2 includes the northern cluster of the nature corridor;
    • Lot 3 comprises the southern cluster of the nature corridor. 

    The masterplan encompasses an area of 6 square kilometres, making it one of the largest sites ever designated for a World Expo event. Situated to the north of the Saudi capital, the site will be located near the future King Salman International airport and will provide direct access to landmarks within Riyadh.

    The Public Investment Fund, Saudi Arabia’s sovereign wealth vehicle, launched ERC – a wholly owned subsidiary – in June 2025 to build and operate facilities for Expo 2030.


    READ THE JULY 2026 MEED BUSINESS REVIEW – click here to view PDF

    Stress test for Gulf aviation; Mixed performance as country outlooks diverge in the Levant; GCC tourism sector pivots from crisis to recovery mode.

    Distributed to senior decision-makers in the region and around the world, the July 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/17723204/main.jpg
    Yasir Iqbal
  • EtihadWE tenders $150m Ajman substation project

    21 July 2026

    The UAE’s Etihad Water & Electricity (EtihadWE) has tendered a contract to build three new substations in Ajman.

    Estimated to cost $150m, the project involves the construction of three new 132/11kV substations in the Bahya, Rumaila and Liwara districts. It also includes associated 132kV underground cabling works to connect the substations to the existing transmission network.

    The bid submission deadline is 10 August.

    According to tender documents, the project will add distribution capacity to support load growth and improve the security of electricity supply in the emirate.

    The scope of work includes site preparation, construction of three substation buildings and foundations, installation of 132kV GIS/AIS switchgear, 132/11kV power transformers and 11kV switchgear, as well as protection, control, Scada and telecommunications systems.

    Etihad WE is responsible for electricity and water services in Ajman, Umm Al-Quwain, Ras Al-Khaimah, Fujairah and parts of Sharjah. The utility has been investing in new substations and transmission infrastructure as electricity demand continues to increase across the Northern Emirates.

    This includes a 132/33/11kV substation project on Al-Marjan Island in Ras Al-Khaimah. Construction work is ongoing on the project, with Maetal Dubai serving as the main contractor.

    EtihadWE is also finalising a new masterplan that will cover network capacity requirements and expansion priorities for the next 10 to 15 years.

    In June, Abdulla Al-Khemeiri, chief operations officer, told MEED: “We are currently reviewing it, and we need to obtain shareholder approval first. Once it is approved, it will be released, hopefully by the end of the year.” 

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17710661/main.jpg
    Mark Dowdall