Aramco nears decision on Jafurah fourth expansion phase
21 April 2026

Saudi Aramco is closing in on a final investment decision (FID) and main contract award for engineering, procurement and construction (EPC) works on the fourth expansion phase of the Jafurah unconventional gas development in Saudi Arabia.
The main scope of work on the Jafurah fourth expansion phase project involves the EPC of three gas compression trains at the giant gas basin in the kingdom’s Eastern Province. Each plant will be able to process up to 200 million cubic feet a day (cf/d).
Based on technical and commercial evaluation of bids, and several rounds of discussion and negotiations, Indian contractor Larsen & Toubro Energy Hydrocarbon is understood to have emerged as the favourite to win the main EPC contract for the Jafurah fourth expansion phase, according to sources.
Contractors submitted proposals for the Jafurah fourth expansion phase project by the deadline of 15 January 2025, MEED previously reported. Following the submission of bids, Aramco initially requested that contractors extend the validity of their bids until the end of September, as it needed more time to evaluate the proposals.
The Saudi energy giant then asked contractors to extend the validity of their base proposals until February this year, and the bidders complied, MEED earlier reported.
Along with requesting bidders for a second bid validity extension, Aramco also sought an alternative set of commercial proposals from contractors, as per sources. Bidders submitted the second price option to the client in December, they added.
The following contractors are among those that are understood to have submitted bids for the Jafurah fourth expansion phase project:
- China Petroleum Engineering and Construction
- Larsen & Toubro Energy Hydrocarbon (India)
- Samsung E&A (South Korea)
- Tecnicas Reunidas (Spain) / Sinopec Group (China)
Aramco issued the main tender for the estimated $2bn-$2.5bn contract in July 2024. Contractors invited to bid for the contract were initially set a deadline of 15 October that year to submit technical bids and their In-Kingdom Total Value Add (IKTVA) credentials. Commercial bids were due to be submitted by 31 October, with the deadline extended to 31 December, then to 15 January, 2025.
The detailed scope of work on the Jafurah fourth expansion phase involves the EPC of the following process and utilities units at the south field of the Jafurah reserve:
- Three gas compression trains of 200 million cf/d capacity each, measuring 400 by 400 metres
- Gas compression plant inlet area
- Gas compression plant condensate and produced-water handling
- Instrumentation and plant air unit
- Nitrogen generation unit
- Raw/potable/water utilities
- Chemical injection systems
- Diesel systems
- Flare and flare gas recovery systems
- Gas compression plant burn pit
- Closed drain system
- Oily water system
- Sanitary water system
- Stormwater system
- Firewater system
- Fire and gas protection system
- All buildings located within the gas compression plant, excluding security buildings
- Outside battery limit buildings
Aramco is moving towards a decision on the main contract award for the Jafurah fourth expansion phase project, as it advances the main EPC tendering exercise for the fifth expansion phase of the mammoth Jafurah unconventional gas development programme.
Aramco completed the solicitation of interest process with contractors for the main EPC tendering round for the Jafurah fifth expansion phase project in November, MEED previously reported.
Dubai-headquartered Wood Group has carried out the front-end engineering and design (feed) on the fifth expansion phase.
Jafurah gas development phases
The Jafurah basin is the largest liquid-rich shale gas play in the Middle East, spanning around 17,000 square kilometres. The reserve is estimated to contain 229 trillion cubic feet of gas and 75 billion stock-tank barrels of condensate.
Aramco, in early December, brought the greenfield Jafurah gas processing plant online, with a production capacity of 450 million cf/d, marking the commissioning of the first phase of its $100bn capital expenditure programme to produce gas from the unconventional resource base.
The Saudi oil behemoth had earlier stated it expected to start gas production at Jafurah in 2025, with the intention of progressively ramping up to 2 billion cf/d of sales gas, 420 million cf/d of ethane and 630,000 barrels a day (b/d) of high-value liquids by 2030.
Aramco has said that, at peak production, its unconventional gas programme is expected to generate electricity equivalent to displacing 500,000 b/d of oil.
Progress on the fourth and fifth expansion phases of the Jafurah unconventional gas development programme continues, as EPC work on the third phase advances.
In July 2024, Aramco issued a non-binding letter of intent to a consortium of Tecnicas Reunidas and Sinopec Group for the EPC contract for the Jafurah third expansion phase. The value of the contract is estimated to be $2.24bn.
The objective of the third expansion phase of Jafurah is similar to that of the fourth phase of development. The main scope of work involves the EPC of three gas compression plants, each with a capacity of 200 million cf/d.
The third phase’s scope of work also includes building a 230kV substation to power the new gas compression plants and installing other utilities units, piping systems and safety equipment.
The selection of contractors for the third expansion phase of the Jafurah development came within weeks of Aramco officially awarding EPC contracts for the second expansion phase, which aims to raise its processing potential to up to 2 billion cf/d of raw gas produced from the Jafurah field.
Aramco awarded 16 contracts, worth a combined total of about $12.4bn, for the second expansion phase on 30 June 2024.
The EPC scope of work on the project involves the construction of gas compression facilities and associated pipelines and the expansion of the Jafurah gas plant, including the construction of gas processing trains, utilities, sulphur and export facilities, Aramco said in a statement.
The main EPC packages of the Jafurah second expansion phase project, their estimated values and the selected contractors are:
- Package 1 – gas processing plant and main process units – $2.9bn: Larsen & Toubro Energy Hydrocarbon (India)
- Package 2 – utilities and offsites – $2.4bn: Hyundai Engineering (South Korea)
- Package 3 – gas compression units – $1bn: Larsen & Toubro Energy Hydrocarbon
- Riyas natural gas liquids (NGL) package 1 – NGL fractionation trains – $1bn: Tecnicas Reunidas / Refining & Chemical Engineering Group (part of China’s Sinopec Group)
- Riyas NGL package 2 – utilities, storage and export facilities – $2.2bn: Tecnicas Reunidas/Refining & Chemical Engineering Group
- Riyas NGL package 6 – site preparation works – $107m: Mofarreh Alharbi & Partners (Saudi Arabia)
- Riyas NGL package 9 – temporary construction facilities – $80m: Mofarreh Alharbi & Partners
Aramco kickstarted EPC works on the first phase of the programme in November 2021 by awarding $10bn-worth of subsurface and EPC contracts.
In February 2020, Aramco received a capital expenditure grant of $110bn from the Saudi government for the long-term phased development of the Jafurah unconventional gas resource base.
The Jafurah unconventional gas development programme is central to Aramco’s goal of increasing gas production capacity. The target has recently been raised to 80%, with 2021 as the baseline, up from 60%, to meet rising domestic and global demand. The company expects life-cycle investment in Jafurah to exceed $100bn.
Prior to the commissioning of the Jafurah gas plant in the last quarter of this year, Aramco completed an $11bn lease-and-leaseback deal in late October for gas processing facilities at the Jafurah unconventional gas reserve with a consortium led by funds managed by Global Infrastructure Partners (GIP), part of US asset manager BlackRock.
Under the transaction, which Aramco started in August, a newly formed subsidiary – Jafurah Midstream Gas Company (JMGC) – will lease development and usage rights to the Jafurah field gas processing plant and the Riyas natural gas liquids (NGL) fractionation facility.
After 20 years, JMGC will lease the assets back to Aramco. JMGC will collect a tariff payable by Aramco in exchange for granting Aramco the exclusive right to receive, process and treat raw gas from the Jafurah resource base.
Aramco will hold a 51% majority stake in JMGC, while the GIP-led consortium will hold the remaining 49%. Investors participating in the GIP-led consortium include Hassana Investment Company, The Arab Energy Fund (TAEF) and Aberdeen Investcorp Infrastructure Partners, as well as other institutional investors from North and Southeast Asia and the Middle East.
Exclusive from Meed
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Qatar seeks to establish new industrial area in Mesaieed16 July 2026
Qatar’s Ministry of Commerce & Industry and state enterprise QatarEnergy have signed an agreement to cooperate on evaluating and allocating hydrocarbon-derived resources to support the establishment of a new medium industries area in Mesaieed Industrial City.
Under the terms of reference signed between the parties, QatarEnergy will implement a governance mechanism for the allocation of hydrocarbon-derived feedstock to qualifying industrial investment opportunities for the proposed new medium industries area in Mesaieed Industrial City.
“The agreed terms of reference stipulate the evaluation and allocation of hydrocarbon-derived resources, natural gas, power and related natural resources to downstream derivative industrial investment opportunities,” QatarEnergy said in a statement.
“It will also ensure the optimal use of national resources and enhance the added value of the industrial sector by establishing a joint governance framework to evaluate and allocate resources required by qualified industrial investment opportunities,” it added.
QatarEnergy currently operates crude oil refining facilities, including natural gas liquids units, as well as petrochemical production complexes and other units in the hydrocarbon value chain, in Mesaieed Industrial City, situated around 45 kilometres south of Doha.
https://image.digitalinsightresearch.in/uploads/NewsArticle/17688383/main.jpg -
Bahri signs deal for two offshore vessels with Dubai shipyard16 July 2026
Bahri Logistics, a division of Saudi Arabia’s national shipping company Bahri, has placed an order for the construction of two advanced offshore support vessels with Dubai-based Grandweld Shipyard.
Grandweld will custom-build the two vessels to meet Bahri’s operational requirements for offshore activities at Ras Tanura port in Saudi Arabia, one of the world’s busiest oil and gas bunkering and export hubs.
The vessels will be built at Grandweld’s shipyard in Dubai Maritime City and are expected to be delivered in August, following a 12-month building period.
The vessels will feature the latest navigation and safety technologies. They are designed to perform multiple offshore support functions, including vessel clearance, crew changes and emergency response, while adhering to international maritime standards.
The newbuild agreement with Grandweld aligns with Bahri’s broader strategy “to modernise its fleet, enhance technical capabilities, and adopt more energy-efficient and environmentally responsible designs”.
“Through continued investments in technology, infrastructure and fleet diversification, Bahri Logistics aims to deliver smarter, more sustainable logistics solutions that contribute to the Saudi Green Initiative and the kingdom’s long-term economic diversification goals,” the Saudi Stock Exchange-listed (Tadawul) company said in a statement.
https://image.digitalinsightresearch.in/uploads/NewsArticle/17687877/main.jpg -
Egypt intensifies efforts to create petroleum stockpile16 July 2026
Egypt is intensifying its efforts to secure and maintain a sufficient strategic stockpile of petroleum products, according to a statement from the country’s cabinet and its Ministry of Petroleum & Mineral Resources.
The Egyptian government is closely monitoring regional developments and their potential repercussions on the energy sector, according to the statement.
Egyptian Prime Minister Mostafa Madbouly said that the government is implementing flexible plans and looking at alternative scenarios so that it can respond quickly to emergencies while ensuring the uninterrupted supply of fuel to citizens and key industrial sectors.
Egypt is intensifying its efforts to build up strategic stockpiles amid heightened uncertainty about future global oil and gas supplies.
Since the US and Israel attacked Iran on 28 February, there has been significant disruption to shipping through the Strait of Hormuz, which is a key transit route for oil and gas exports from the Middle East.
On top of this, the regional war has involved multiple direct attacks on refineries in the GCC, increasing uncertainty about the future availability of refined products.
Aside from Motafa Madbouly, the meeting was also attended by Hassan Abdullah, who is governor of the Central Bank, Minister of Finance Ahmed Koguk and Minister of Petroleum and Minerals Karim Badawi.
During the meeting, Badawi gave a presentation on the available quantities of different petroleum products and explained the details of the procedures currently being implemented to increase the strategic stock of petroleum products.
A review of the coordination framework and joint work between the Ministry of Finance and the Central Bank also took place during the meeting.
This was in order to ensure the management of financial tools needed to strengthen the country’s strategic inventory, according to the statement.
https://image.digitalinsightresearch.in/uploads/NewsArticle/17685719/main.jpg -
Tunisia orders $86m of trainsets from Chinese supplier16 July 2026
Tunisian public transport operator Transtu has finalised an $86m agreement with China’s CRRC Nanjing Puzhen.
CRRC will supply 18 new electric trainsets for the capital’s northern suburban rail network, which links Tunis to La Goulette and La Marsa.
Each new trainset will be air-conditioned and capable of carrying up to 400 passengers, including 90 seated riders, with a top speed of 100 km/h. Once operational, the trains are expected to run at six-minute intervals during rush hour and every 12 minutes during off-peak hours.
The deal forms part of a broader fleet renewal effort by Transtu, which has struggled in recent years with operational setbacks that have taken a toll on the quality of public transport across Greater Tunis.
The acquisition is designed to boost capacity on the heavily used line as ridership continues to grow, while also enhancing safety standards and overall service quality.
Funding for the project comes jointly from the European Bank for Reconstruction & Development and the European Investment Bank.
Beyond the trainsets, the contract includes five years of maintenance coverage, a supply of spare parts and maintenance equipment, and an underfloor wheel lathe aimed at improving long-term fleet reliability.
This latest investment fits into Tunisia’s larger railway modernisation strategy, under which the government plans to invest $12bn by 2040 to expand and upgrade the country’s rail infrastructure.
https://image.digitalinsightresearch.in/uploads/NewsArticle/17683957/main.jpg -
PIF developer tenders 365-metre Mecca residential tower16 July 2026

Rua Al-Haram Al-Makki has tendered the main construction package for the Ajyad residential tower, a 365-metre high-rise development in Mecca’s central area, close to the grand mosque.
The bid submission deadline is 30 September.
Rua Al-Haram Al-Makki Company was established in October 2017 and is a wholly owned subsidiary of Saudi Arabia’s Public Investment Fund.
The project team includes US-based Marriott International as residential operator, Hanmi Global Saudi as project management consultant, Saudi Diyar Consultants as construction supervision consultant, and PLP Architecture as lead design consultant and construction-stage design guardian.
The tower rises 84 floors with four basement levels. It comprises a total of 212 units, including 82 three-bedroom apartments, 85 four-bedroom units, 29 penthouses and 16 duplex villas.
The scheme has a gross floor area of 209,231 square metres (sq m) and a built-up area of 242,976 sq m.
The site is currently being cleared by a demolition contractor, with the existing mat foundation and retaining walls to be handed over to the main contractor, who will build the new superstructure on the retained raft.
https://image.digitalinsightresearch.in/uploads/NewsArticle/17683664/main.jpg