Aramco nears decision on Jafurah fourth expansion phase

21 April 2026

 

Saudi Aramco is closing in on a final investment decision (FID) and main contract award for engineering, procurement and construction (EPC) works on the fourth expansion phase of the Jafurah unconventional gas development in Saudi Arabia.

The main scope of work on the Jafurah fourth expansion phase project involves the EPC of three gas compression trains at the giant gas basin in the kingdom’s Eastern Province. Each plant will be able to process up to 200 million cubic feet a day (cf/d).

Based on technical and commercial evaluation of bids, and several rounds of discussion and negotiations, Indian contractor Larsen & Toubro Energy Hydrocarbon is understood to have emerged as the favourite to win the main EPC contract for the Jafurah fourth expansion phase, according to sources.

Contractors submitted proposals for the Jafurah fourth expansion phase project by the deadline of 15 January 2025, MEED previously reported. Following the submission of bids, Aramco initially requested that contractors extend the validity of their bids until the end of September, as it needed more time to evaluate the proposals.

The Saudi energy giant then asked contractors to extend the validity of their base proposals until February this year, and the bidders complied, MEED earlier reported.

Along with requesting bidders for a second bid validity extension, Aramco also sought an alternative set of commercial proposals from contractors, as per sources. Bidders submitted the second price option to the client in December, they added.

The following contractors are among those that are understood to have submitted bids for the Jafurah fourth expansion phase project:

  • China Petroleum Engineering and Construction
  • Larsen & Toubro Energy Hydrocarbon (India)
  • Samsung E&A (South Korea)
  • Tecnicas Reunidas (Spain) / Sinopec Group (China)

Aramco issued the main tender for the estimated $2bn-$2.5bn contract in July 2024. Contractors invited to bid for the contract were initially set a deadline of 15 October that year to submit technical bids and their In-Kingdom Total Value Add (IKTVA) credentials. Commercial bids were due to be submitted by 31 October, with the deadline extended to 31 December, then to 15 January, 2025.

The detailed scope of work on the Jafurah fourth expansion phase involves the EPC of the following process and utilities units at the south field of the Jafurah reserve:

  • Three gas compression trains of 200 million cf/d capacity each, measuring 400 by 400 metres
  • Gas compression plant inlet area
  • Gas compression plant condensate and produced-water handling
  • Instrumentation and plant air unit
  • Nitrogen generation unit
  • Raw/potable/water utilities
  • Chemical injection systems
  • Diesel systems
  • Flare and flare gas recovery systems
  • Gas compression plant burn pit
  • Closed drain system
  • Oily water system
  • Sanitary water system
  • Stormwater system
  • Firewater system
  • Fire and gas protection system
  • All buildings located within the gas compression plant, excluding security buildings
  • Outside battery limit buildings

Aramco is moving towards a decision on the main contract award for the Jafurah fourth expansion phase project, as it advances the main EPC tendering exercise for the fifth expansion phase of the mammoth Jafurah unconventional gas development programme.

Aramco completed the solicitation of interest process with contractors for the main EPC tendering round for the Jafurah fifth expansion phase project in November, MEED previously reported.

Dubai-headquartered Wood Group has carried out the front-end engineering and design (feed) on the fifth expansion phase.

Jafurah gas development phases

The Jafurah basin is the largest liquid-rich shale gas play in the Middle East, spanning around 17,000 square kilometres. The reserve is estimated to contain 229 trillion cubic feet of gas and 75 billion stock-tank barrels of condensate.

Aramco, in early December, brought the greenfield Jafurah gas processing plant online, with a production capacity of 450 million cf/d, marking the commissioning of the first phase of its $100bn capital expenditure programme to produce gas from the unconventional resource base.

The Saudi oil behemoth had earlier stated it expected to start gas production at Jafurah in 2025, with the intention of progressively ramping up to 2 billion cf/d of sales gas, 420 million cf/d of ethane and 630,000 barrels a day (b/d) of high-value liquids by 2030.

Aramco has said that, at peak production, its unconventional gas programme is expected to generate electricity equivalent to displacing 500,000 b/d of oil.

Progress on the fourth and fifth expansion phases of the Jafurah unconventional gas development programme continues, as EPC work on the third phase advances.

In July 2024, Aramco issued a non-binding letter of intent to a consortium of Tecnicas Reunidas and Sinopec Group for the EPC contract for the Jafurah third expansion phase. The value of the contract is estimated to be $2.24bn.

The objective of the third expansion phase of Jafurah is similar to that of the fourth phase of development. The main scope of work involves the EPC of three gas compression plants, each with a capacity of 200 million cf/d.

The third phase’s scope of work also includes building a 230kV substation to power the new gas compression plants and installing other utilities units, piping systems and safety equipment.

The selection of contractors for the third expansion phase of the Jafurah development came within weeks of Aramco officially awarding EPC contracts for the second expansion phase, which aims to raise its processing potential to up to 2 billion cf/d of raw gas produced from the Jafurah field.

Aramco awarded 16 contracts, worth a combined total of about $12.4bn, for the second expansion phase on 30 June 2024.

The EPC scope of work on the project involves the construction of gas compression facilities and associated pipelines and the expansion of the Jafurah gas plant, including the construction of gas processing trains, utilities, sulphur and export facilities, Aramco said in a statement.

The main EPC packages of the Jafurah second expansion phase project, their estimated values and the selected contractors are:

  • Package 1 – gas processing plant and main process units – $2.9bn: Larsen & Toubro Energy Hydrocarbon (India)
  • Package 2 – utilities and offsites – $2.4bn: Hyundai Engineering (South Korea)
  • Package 3 – gas compression units – $1bn: Larsen & Toubro Energy Hydrocarbon
  • Riyas natural gas liquids (NGL) package 1 – NGL fractionation trains – $1bn: Tecnicas Reunidas / Refining & Chemical Engineering Group (part of China’s Sinopec Group)
  • Riyas NGL package 2 – utilities, storage and export facilities – $2.2bn: Tecnicas Reunidas/Refining & Chemical Engineering Group
  • Riyas NGL package 6 – site preparation works – $107m: Mofarreh Alharbi & Partners (Saudi Arabia)
  • Riyas NGL package 9 – temporary construction facilities – $80m: Mofarreh Alharbi & Partners

Aramco kickstarted EPC works on the first phase of the programme in November 2021 by awarding $10bn-worth of subsurface and EPC contracts.

In February 2020, Aramco received a capital expenditure grant of $110bn from the Saudi government for the long-term phased development of the Jafurah unconventional gas resource base.

The Jafurah unconventional gas development programme is central to Aramco’s goal of increasing gas production capacity. The target has recently been raised to 80%, with 2021 as the baseline, up from 60%, to meet rising domestic and global demand. The company expects life-cycle investment in Jafurah to exceed $100bn.

Prior to the commissioning of the Jafurah gas plant in the last quarter of this year, Aramco completed an $11bn lease-and-leaseback deal in late October for gas processing facilities at the Jafurah unconventional gas reserve with a consortium led by funds managed by Global Infrastructure Partners (GIP), part of US asset manager BlackRock.

Under the transaction, which Aramco started in August, a newly formed subsidiary – Jafurah Midstream Gas Company (JMGC) – will lease development and usage rights to the Jafurah field gas processing plant and the Riyas natural gas liquids (NGL) fractionation facility.

After 20 years, JMGC will lease the assets back to Aramco. JMGC will collect a tariff payable by Aramco in exchange for granting Aramco the exclusive right to receive, process and treat raw gas from the Jafurah resource base.

Aramco will hold a 51% majority stake in JMGC, while the GIP-led consortium will hold the remaining 49%. Investors participating in the GIP-led consortium include Hassana Investment Company, The Arab Energy Fund (TAEF) and Aberdeen Investcorp Infrastructure Partners, as well as other institutional investors from North and Southeast Asia and the Middle East.

https://image.digitalinsightresearch.in/uploads/NewsArticle/16487753/main23093906.jpg
Indrajit Sen
Related Articles
  • Adnoc secures Thailand LNG supply deal

    9 October 2026

    Abu Dhabi National Oil Company (Adnoc) has secured a deal with Thailand-based energy and infrastructure company Gulf Group to supply 2 million tonnes a year of liquefied natural gas (LNG), with deliveries starting in 2027.

    The multi-year sale and purchase agreement (SPA), whose exact duration Adnoc did not disclose, builds on an initial LNG supply deal agreed between the two companies last year. The transaction was arranged through Adnoc’s integrated LNG marketing and trading platform, which was established in July within Abu Dhabi Global Market.

    The hub integrates the marketing operations of Adnoc subsidiaries Adnoc Gas and XRG with the trading activities of Adnoc Trading. It targets a combined portfolio of 47 million t/y of marketable LNG by 2035. Adnoc Trading has developed an active third-party trading portfolio over the past four years, operating from commercial offices in Abu Dhabi, Singapore and Geneva.

    ALSO READ: Adnoc signs energy agreements with Japan and South Korea

    Separately, Adnoc has secured offtake commitments covering approximately 90% of the 9.6 million-t/y capacity planned for its low-carbon Ruwais LNG project.

    In July, Adnoc signed a 15-year SPA with Japan’s Inpex Corporation for the supply of up to 1 million t/y from Ruwais. That contract marked Adnoc’s third long-term Ruwais supply agreement with a Japanese buyer, following deals with Osaka Gas and Mitsui & Co in March and April 2025, respectively. Together, the agreements with the three Japanese firms account for 2.4 million t/y – one-quarter of the terminal’s total capacity, which will be delivered across two 4.8 million-t/y liquefaction trains.

    Adnoc has also secured long-term Ruwais LNG supply agreements with Malaysia’s Petronas, Germany’s EnBW Energie Baden-Wurttemberg and SEFE (Securing Energy for Europe), China’s ENN Natural Gas, UK-based Shell and Indian Oil Corporation.

    Currently under construction in Ruwais Industrial City, Abu Dhabi, the facility is scheduled to begin commercial operations in 2028. Its commissioning will more than double Adnoc’s LNG production capacity to approximately 15 million t/y.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/20421415/main4048.jpg
    Indrajit Sen
  • Fibrex wins $217m Abu Dhabi Seamont residences contract

    9 October 2026

    Register for MEED’s 14-day trial access 

    Abu Dhabi-based contractor Fibrex Construction Group has won an AED800m ($217m) contract to build the Seamont Autograph Collection Residences project, located on Al-Reem Island in the UAE capital.

    Abu Dhabi-based real estate developer Royal Development Holding, a subsidiary of Emirates Stallion Group, and local firm Saas Properties awarded the contract.

    The development comprises two 22-storey towers offering 497 residences, ranging from one- to four-bedroom apartments.

    The construction programme is scheduled to run for 27 months, with completion due in December 2028.

    Fibrex will begin mobilisation immediately, following the completion of enabling works this month, which were undertaken by Sharjah-based Swiss Pro Foundations.

    Dubai-based architectural firm Dewan Architects & Engineers is the project consultant.

    The contract marks another major win for the contractor. Last year, Dubai-based developer Nakheel awarded Fibrex a AED2.6bn ($708m) contract to build the Bay Villas project at Dubai Islands.

    That contract includes the construction of 636 villas.


    READ THE OCTOBER 2026 MEED BUSINESS REVIEW – click here to view PDF

    Industry and logistics drive development at Neom; Saudi Arabia’s investment priorities realign amid conflict; MEED’s 2026 power developer ranking.

    Distributed to senior decision-makers in the region and around the world, the October 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/20420509/main.jpg
    Yasir Iqbal
  • Dubai picks contractor for Al-Maktoum airport terminal

    9 October 2026

     

    Dubai Aviation Engineering Projects (DAEP) has selected a contractor for an estimated AED10bn ($2.7bn) substructure package for the West Terminal, as part of the first phase of the $35bn expansion of Al-Maktoum International airport.

    A joint venture of Beijing-headquartered China Civil Engineering Construction Corporation (CCECC) and Abu Dhabi-based Tristar Engineering & Construction will execute the contract.

    According to a description on DAEP’s website, the expanded airport’s West Terminal will be a seven-level facility spanning 800,000 square metres, with annual capacity for 45 million passengers.

    The terminal will be the second of three planned terminals at Al-Maktoum International airport. It will connect to the airside via a 14-station automated people-mover (APM) system.

    In July, MEED exclusively reported that DAEP had awarded an estimated $1.5bn contract to a joint venture of Japan’s Mitsubishi Corporation and Indian contractor Larsen & Toubro for the APM system.

    The APM will run beneath the apron and terminal areas, using multiple tracks to transport passengers between terminals and concourses. Four underground stations are planned in the first phase, while the full airport development is expected to include 14 stations.

    The latest awards form part of a wider programme of contracts recently signed by DAEP, covering enabling works, the second runway, initial structural foundations for passenger terminals and concourse substructures.

    Upcoming awards

    In June 2026, DAEP said it will award construction contracts worth over AED55bn ($15bn) for Al-Maktoum International airport by the end of the year.

    At the time, DAEP said the planned awards included substructure works for the West Terminal, the fourth aircraft concourse and the baggage-handling system. The programme also included superstructure works for the West Terminal and the first, second and third aircraft concourses.

    The packages are expected to include long-span structural frameworks for buildings covering about 1.5 million square metres, infrastructure works for the southern airfield area, and power-generation and district-cooling plants supporting the construction programme.

    DAEP also plans to award façade and roofing packages in 2026.

    The Dubai Government approved updated designs and timelines for its largest construction project in April 2024. In September 2024, MEED exclusively reported that a team comprising Austria’s Coop Himmelb(l)au and Lebanon’s Dar Al-Handasah had been confirmed as lead masterplanning and design consultants for the Al-Maktoum International airport expansion.

    Construction of the airport is planned in three phases. Once complete, the airport will cover 70 square kilometres south of Dubai and include five parallel runways and 430 aircraft gates.

    It will be five times the size of Dubai International airport and is planned to have a passenger-handling capacity of 260 million passengers a year – the largest in the world. For cargo, it is planned to have the capacity to handle 12 million tonnes a year.


    READ THE OCTOBER 2026 MEED BUSINESS REVIEW – click here to view PDF

    Industry and logistics drive development at Neom; Saudi Arabia’s investment priorities realign amid conflict; MEED’s 2026 power developer ranking.

    Distributed to senior decision-makers in the region and around the world, the October 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/20417755/main.jpg
    Yasir Iqbal
  • Nakheel awards Dubai Islands marine works contract

    9 October 2026

    Dubai-based developer Nakheel, part of Dubai Holding Real Estate, has awarded local firm Mar Marine & Building Contracting a contract for marine and beach works on Island B at Dubai Islands.

    The scope includes constructing breakwaters, removing existing rock revetments and forming a new 320-metre beach near the Bay Villas development.

    The contractor will also refurbish existing beach areas and undertake remedial works along approximately 3 kilometres of the island’s western shoreline.

    The works are scheduled for completion in the fourth quarter of 2027.

    The package supports the Bay Villas project, which comprises 636 villas and townhouses on Island B. Nakheel awarded Fibrex Contracting an AED2.6bn ($708m) construction contract for the residential development in August 2025.

    The marine works award follows Nakheel’s AED527m primary infrastructure and utilities contract for Island B, which was awarded to Al-Nasr Contracting Company in April 2026.

    In September, Nakheel awarded a main construction contract worth more than AED800m ($218m) for phases one and three of Bay Grove Residences at Dubai Islands. The contract was awarded to local firm Metac General Contracting Company.

    The contract covers the construction of 537 apartments, comprising one- to four-bedroom units, across seven residential buildings. Phase one includes 296 units in four buildings, while phase three comprises 241 units across three buildings.


    READ THE OCTOBER 2026 MEED BUSINESS REVIEW – click here to view PDF

    Industry and logistics drive development at Neom; Saudi Arabia’s investment priorities realign amid conflict; MEED’s 2026 power developer ranking.

    Distributed to senior decision-makers in the region and around the world, the October 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/20418469/main.jpg
    Yasir Iqbal
  • Iraq refinery project given regional approval

    9 October 2026

    Plans to establish a 70,000-barrel-a-day (b/d) refinery in the Iraqi town of Qayyarah have been approved by the Nineveh Provincial Council, which has called for the project to be referred to Iraq’s Council of Ministers. The council also recommended that Duhok-based Karband Company, an industrial manufacturer of asphalt products and lubricating oils, be involved in the project.

    The council’s vote follows a meeting held in September between Iraq’s Oil Ministry and Angola’s Sonangol on potentially jointly developing the Qayyarah refinery.

    The planned refinery would allow more of the crude produced in Qayyarah to be processed locally, increasing supplies of petroleum products and reducing the need to transport locally produced crude south for export via the Strait of Hormuz.

    Iraq awarded the Qayyarah oil field to Sonangol in its second licensing round in 2009, with an initial target of around 120,000 b/d.

    A new upstream expansion phase began in January 2025, when Sonangol contracted the Iraqi Drilling Company to drill 10 wells, with an option for three additional appraisal wells.

    An existing refinery in Qayyarah, built in 1955, has a capacity of 20,000 b/d.

    Progress on the new facility has stalled in recent years, with little movement since 2021, when Iraq signed a memorandum of understanding with Sweden’s SEAB and Turkiye’s Limak on developing the refinery.

    Previously, Iraq’s Oil Ministry said the project would include modern units and complex refining technology to produce products meeting Euro 5 standards

    The scope of the project is expected to include:

    • Processing units
    • Storage tanks
    • Distillation units
    • Associated facilities

    The project was first announced in 2018 and has encountered several delays due to funding problems.


    READ THE OCTOBER 2026 MEED BUSINESS REVIEW – click here to view PDF

    Industry and logistics drive development at Neom; Saudi Arabia’s investment priorities realign amid conflict; MEED’s 2026 power developer ranking.

    Distributed to senior decision-makers in the region and around the world, the October 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/20413126/main.png
    Wil Crisp