Aramco nears decision on Jafurah fourth expansion phase
21 April 2026

Saudi Aramco is closing in on a final investment decision (FID) and main contract award for engineering, procurement and construction (EPC) works on the fourth expansion phase of the Jafurah unconventional gas development in Saudi Arabia.
The main scope of work on the Jafurah fourth expansion phase project involves the EPC of three gas compression trains at the giant gas basin in the kingdom’s Eastern Province. Each plant will be able to process up to 200 million cubic feet a day (cf/d).
Based on technical and commercial evaluation of bids, and several rounds of discussion and negotiations, Indian contractor Larsen & Toubro Energy Hydrocarbon is understood to have emerged as the favourite to win the main EPC contract for the Jafurah fourth expansion phase, according to sources.
Contractors submitted proposals for the Jafurah fourth expansion phase project by the deadline of 15 January 2025, MEED previously reported. Following the submission of bids, Aramco initially requested that contractors extend the validity of their bids until the end of September, as it needed more time to evaluate the proposals.
The Saudi energy giant then asked contractors to extend the validity of their base proposals until February this year, and the bidders complied, MEED earlier reported.
Along with requesting bidders for a second bid validity extension, Aramco also sought an alternative set of commercial proposals from contractors, as per sources. Bidders submitted the second price option to the client in December, they added.
The following contractors are among those that are understood to have submitted bids for the Jafurah fourth expansion phase project:
- China Petroleum Engineering and Construction
- Larsen & Toubro Energy Hydrocarbon (India)
- Samsung E&A (South Korea)
- Tecnicas Reunidas (Spain) / Sinopec Group (China)
Aramco issued the main tender for the estimated $2bn-$2.5bn contract in July 2024. Contractors invited to bid for the contract were initially set a deadline of 15 October that year to submit technical bids and their In-Kingdom Total Value Add (IKTVA) credentials. Commercial bids were due to be submitted by 31 October, with the deadline extended to 31 December, then to 15 January, 2025.
The detailed scope of work on the Jafurah fourth expansion phase involves the EPC of the following process and utilities units at the south field of the Jafurah reserve:
- Three gas compression trains of 200 million cf/d capacity each, measuring 400 by 400 metres
- Gas compression plant inlet area
- Gas compression plant condensate and produced-water handling
- Instrumentation and plant air unit
- Nitrogen generation unit
- Raw/potable/water utilities
- Chemical injection systems
- Diesel systems
- Flare and flare gas recovery systems
- Gas compression plant burn pit
- Closed drain system
- Oily water system
- Sanitary water system
- Stormwater system
- Firewater system
- Fire and gas protection system
- All buildings located within the gas compression plant, excluding security buildings
- Outside battery limit buildings
Aramco is moving towards a decision on the main contract award for the Jafurah fourth expansion phase project, as it advances the main EPC tendering exercise for the fifth expansion phase of the mammoth Jafurah unconventional gas development programme.
Aramco completed the solicitation of interest process with contractors for the main EPC tendering round for the Jafurah fifth expansion phase project in November, MEED previously reported.
Dubai-headquartered Wood Group has carried out the front-end engineering and design (feed) on the fifth expansion phase.
Jafurah gas development phases
The Jafurah basin is the largest liquid-rich shale gas play in the Middle East, spanning around 17,000 square kilometres. The reserve is estimated to contain 229 trillion cubic feet of gas and 75 billion stock-tank barrels of condensate.
Aramco, in early December, brought the greenfield Jafurah gas processing plant online, with a production capacity of 450 million cf/d, marking the commissioning of the first phase of its $100bn capital expenditure programme to produce gas from the unconventional resource base.
The Saudi oil behemoth had earlier stated it expected to start gas production at Jafurah in 2025, with the intention of progressively ramping up to 2 billion cf/d of sales gas, 420 million cf/d of ethane and 630,000 barrels a day (b/d) of high-value liquids by 2030.
Aramco has said that, at peak production, its unconventional gas programme is expected to generate electricity equivalent to displacing 500,000 b/d of oil.
Progress on the fourth and fifth expansion phases of the Jafurah unconventional gas development programme continues, as EPC work on the third phase advances.
In July 2024, Aramco issued a non-binding letter of intent to a consortium of Tecnicas Reunidas and Sinopec Group for the EPC contract for the Jafurah third expansion phase. The value of the contract is estimated to be $2.24bn.
The objective of the third expansion phase of Jafurah is similar to that of the fourth phase of development. The main scope of work involves the EPC of three gas compression plants, each with a capacity of 200 million cf/d.
The third phase’s scope of work also includes building a 230kV substation to power the new gas compression plants and installing other utilities units, piping systems and safety equipment.
The selection of contractors for the third expansion phase of the Jafurah development came within weeks of Aramco officially awarding EPC contracts for the second expansion phase, which aims to raise its processing potential to up to 2 billion cf/d of raw gas produced from the Jafurah field.
Aramco awarded 16 contracts, worth a combined total of about $12.4bn, for the second expansion phase on 30 June 2024.
The EPC scope of work on the project involves the construction of gas compression facilities and associated pipelines and the expansion of the Jafurah gas plant, including the construction of gas processing trains, utilities, sulphur and export facilities, Aramco said in a statement.
The main EPC packages of the Jafurah second expansion phase project, their estimated values and the selected contractors are:
- Package 1 – gas processing plant and main process units – $2.9bn: Larsen & Toubro Energy Hydrocarbon (India)
- Package 2 – utilities and offsites – $2.4bn: Hyundai Engineering (South Korea)
- Package 3 – gas compression units – $1bn: Larsen & Toubro Energy Hydrocarbon
- Riyas natural gas liquids (NGL) package 1 – NGL fractionation trains – $1bn: Tecnicas Reunidas / Refining & Chemical Engineering Group (part of China’s Sinopec Group)
- Riyas NGL package 2 – utilities, storage and export facilities – $2.2bn: Tecnicas Reunidas/Refining & Chemical Engineering Group
- Riyas NGL package 6 – site preparation works – $107m: Mofarreh Alharbi & Partners (Saudi Arabia)
- Riyas NGL package 9 – temporary construction facilities – $80m: Mofarreh Alharbi & Partners
Aramco kickstarted EPC works on the first phase of the programme in November 2021 by awarding $10bn-worth of subsurface and EPC contracts.
In February 2020, Aramco received a capital expenditure grant of $110bn from the Saudi government for the long-term phased development of the Jafurah unconventional gas resource base.
The Jafurah unconventional gas development programme is central to Aramco’s goal of increasing gas production capacity. The target has recently been raised to 80%, with 2021 as the baseline, up from 60%, to meet rising domestic and global demand. The company expects life-cycle investment in Jafurah to exceed $100bn.
Prior to the commissioning of the Jafurah gas plant in the last quarter of this year, Aramco completed an $11bn lease-and-leaseback deal in late October for gas processing facilities at the Jafurah unconventional gas reserve with a consortium led by funds managed by Global Infrastructure Partners (GIP), part of US asset manager BlackRock.
Under the transaction, which Aramco started in August, a newly formed subsidiary – Jafurah Midstream Gas Company (JMGC) – will lease development and usage rights to the Jafurah field gas processing plant and the Riyas natural gas liquids (NGL) fractionation facility.
After 20 years, JMGC will lease the assets back to Aramco. JMGC will collect a tariff payable by Aramco in exchange for granting Aramco the exclusive right to receive, process and treat raw gas from the Jafurah resource base.
Aramco will hold a 51% majority stake in JMGC, while the GIP-led consortium will hold the remaining 49%. Investors participating in the GIP-led consortium include Hassana Investment Company, The Arab Energy Fund (TAEF) and Aberdeen Investcorp Infrastructure Partners, as well as other institutional investors from North and Southeast Asia and the Middle East.
Exclusive from Meed
-
Consultant wins Jeddah metro design22 May 2026
-
-
-
Eni makes oil and gas discovery in Egypt22 May 2026
-
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Consultant wins Jeddah metro design22 May 2026

French engineering firm Egis has been appointed to undertake the preliminary design consultancy for the Jeddah Metro Blue Line project.
The project client, Jeddah Development Authority, issued the tender in early January, when MEED exclusively reported that Saudi Arabia had restarted plans to build the Jeddah Metro.
Engineering consulting firms submitted bids in April, as MEED reported.
The Blue Line will run from King Abdulaziz International airport and connect to the Haramain high-speed railway station.
The line will be 35 kilometres (km) long and will include 15 stations.
Project history
Plans for the Jeddah Metro were first publicly floated in the early 2010s and were formally packaged into a wider Jeddah public transport programme around 2013-14.
In 2014, French engineering firm Systra was appointed to complete preliminary engineering for the Jeddah Metro, as MEED reported at the time.
In the same year, US-based engineering firm Aecom was awarded a SR276m ($74m) contract to provide pre-programme management consultancy services.
Under its 18-month contract, Aecom was expected to provide staff to support preliminary planning and design work for various phases of the metro project.
This was followed by the appointment of UK-based architectural firm Foster + Partners in 2015 to design the metro stations.
The project then stalled as government spending priorities were reset and major capital programmes were reviewed following the fall in oil prices in 2015, with the metro’s scope, cost and delivery model coming under reassessment.
Early concept designs envisaged a multi-line network integrated with buses and, later, other city-wide mobility upgrades.
Route details
According to Jeddah Transport Company’s website, the scheme comprises 81 stations and 197 trains serving more than 161km. The network will have four lines:
- Orange Line: a 44.8km line running along Al-Madinah Road and Old Makkah Road, with 29 stops including one at Obhur Bridge
- Blue Line: a 35km line running from King Abdulaziz International airport to the Haramain high-speed railway station, with 15 stations
- Green Line: a 17km line running through the city centre, from the downtown area to the Haramain railway station, with nine stops
- Red Line: A 59.7km line running from King Abdullah Stadium north to Old Makkah Street through King Abdulaziz Road and King Abdullah Road, with 25 stops
> Be recognised among the best in the industry at the MEED Projects Awards 2026 …
https://image.digitalinsightresearch.in/uploads/NewsArticle/16949416/main.jpg -
Egypt signs gas deal with QatarEnergy and Exxon Mobil22 May 2026
Egypt’s Ministry of Petroleum & Mineral Resources has signed a preliminary gas agreement with state-owned QatarEnergy and US-based Exxon Mobil.
The memorandum of understanding (MoU) focuses on cooperation in the development of natural gas discoveries in Cyprus.
The plan involves transporting gas from offshore discoveries in Cypriot waters to Egypt via pipelines.
In a statement, Egypt’s Ministry of Petroleum & Mineral Resources said that the deal would strengthen the North African country’s status as a regional hub for natural gas trading.
The agreement was witnessed by Egypt’s Prime Minister Mustafa Madbouli.
It was signed by Muhammad Al-Bajouri, from the legal affairs department of the Ministry of Petroleum & Minerals, and Kanan Nariman, vice-president for the development of liquefied natural gas (LNG) at Exxon Mobil.
It was also signed by Ali Immunae, director of international exploration and production at QatarEnergy.
Commenting on the MoU signing, Saad Sherida Al-Kaabi, the minister of state for energy affairs, and president and chief executive of QatarEnergy, said: “This MoU represents an important step in advancing regional energy cooperation across the Eastern Mediterranean through unlocking the long-term commercial potential of natural gas resources across that region.”
Egypt’s Ministry of Petroleum & Mineral Resources said the agreement paved the way for QatarEnergy and Exxon to take advantage of existing Egyptian infrastructure in the gas sector, especially the country’s existing LNG export terminals.
Under the terms of the agreement, a study will be conducted to analyse the feasibility of linking the gas discoveries in Cyprus to Egypt’s gas facilities.
The signatories will also establish a commercial framework aimed at achieving “the maximum possible benefit from natural gas resources in both Egypt and Cyprus”.
Egypt’s Minister of Oil and Gas Karim Badawi said the ministry has been working with ExxonMobil to explore cooperation on the development of gas discoveries in Cyprus.
He said the partnership with Egypt would help QatarEnergy and Exxon reduce the cost of developing the discoveries while allowing Egypt to achieve an economic return.
READ THE MAY 2026 MEED BUSINESS REVIEW – click here to view PDFGlobal energy sector forced to recalibrate; Conflict hits debt issuance and listings activity; UAE’s non-oil sector faces unclear recovery period amid disruption.
Distributed to senior decision-makers in the region and around the world, the May 2026 edition of MEED Business Review includes:
> REGIONAL LNG: War undermines business case for Middle East LNG> CAPITAL MARKETS: Damage avoidance frames debt issuance> MARKET FOCUS: Conflict tests UAE diversificationTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/16944918/main.jpg -
Kuwait’s Heisco working on active projects worth $3.5bn22 May 2026

Kuwait’s Heavy Engineering Industries & Shipbuilding Company (Heisco) is in a strong position to weather challenges in the country’s project market, with active projects worth $3.5bn, according to documents seen by MEED.
The company also has active maintenance and service contracts that are worth $843m.
Heisco’s projects span the oil, gas, power, water, construction, transport and industrial sectors.
The company’s biggest active project contract is the $576m project to upgrade Kuwait’s Doha West power station.
This contract was awarded to Heisco by Kuwait’s Ministry of Electricity, Water & Renewable Energy (MEW) in July 2024.
The company’s second-biggest active project is focused on the construction of crude oil pipelines and associated works in North Kuwait.
This $565m contract was awarded to Heisco by Kuwait’s state-owned upstream operator Kuwait Oil Company (KOC) in February this year.
Other major project contracts include a $442m MEW contract for the rehabilitation of the Az-Zour South power and water distillation station and a $223m KOC contract for the construction of flowlines and associated works in the West Kuwait Area.
Heisco’s biggest active maintenance contract is worth $295m and is focused on providing mechanical maintenance services at Kuwait’s Mina Abdullah Refinery.
This contract was awarded by the state-owned downstream operator Kuwait National Petroleum Company (KNPC) in July 2023 and it officially started in September that year.
The contract is currently due to conclude in November 2028.
Heisco’s second-biggest active maintenance contract is worth $95m and was awarded by Wafra Joint Operations (WJO) for work in the Divided Zone, which is shared by Kuwait and Saudi Arabia.
WJO’s onshore operations cover an area of about 5,000 square kilometres in the Divided Zone.
Saudi Arabian Chevron and Kuwait Gulf Oil Company are equal shareholders in WJO.
Six major fields have been discovered in the WJO area to date: Wafra, South Fuwaris, South Umm-Gudair, Humma, Arq and North Wafra.
Heisco’s Wafra maintenance contract was awarded in October last year and officially started in November the same year.
The contract is expected to conclude in May 2031 and its scope is focused on the maintenance of tanks and vessels as well as the provision of welding services.
Market headwinds
Kuwait’s oil and gas sector has been severely impacted by the blockade of the Strait of Hormuz, through which all of its crude exports are normally shipped.
The country recorded zero crude oil exports in April for the first time since the end of the Gulf War in 1991, according to shipping monitor TankerTrackers.com.
While the closure of the Strait of Hormuz is expected to have a significant impact on Kuwait’s project sector for some time, Heisco’s strong project pipeline is likely to help it weather the challenging economic environment.
READ THE MAY 2026 MEED BUSINESS REVIEW – click here to view PDFGlobal energy sector forced to recalibrate; Conflict hits debt issuance and listings activity; UAE’s non-oil sector faces unclear recovery period amid disruption.
Distributed to senior decision-makers in the region and around the world, the May 2026 edition of MEED Business Review includes:
> REGIONAL LNG: War undermines business case for Middle East LNG> CAPITAL MARKETS: Damage avoidance frames debt issuance> MARKET FOCUS: Conflict tests UAE diversificationTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/16792105/main.png -
Eni makes oil and gas discovery in Egypt22 May 2026
A joint venture of Italy’s Eni and state-owned Egyptian General Petroleum Corporation (EGPC) has made a major oil and gas discovery in Egypt’s Western Desert region.
The partnership, known as Agiba Petroleum Company, made the discovery with an exploratory well drilled in the Bustan South block.
Initial estimates indicate the presence of approximately 330 billion cubic feet of gas and 10 million barrels of condensate and crude oil.
Together, this is a total of 70 million barrels of oil equivalent (boe), making the discovery Agiba Petroleum Company’s biggest in 15 years.
The new discovery is located only 10 kilometres from existing facilities and infrastructure, which should enable rapid development and connection to production.
The well revealed several sandstone and limestone reservoirs, according to a statement from Egypt’s Ministry of Petroleum & Mineral Resources.
The ministry said: “This new discovery reflects the success of the Ministry of Petroleum & Mineral Resources’ efforts and the incentives it offered to partners to intensify exploration activities in areas adjacent to existing fields.
“This facilitates new discoveries near existing infrastructure and production facilities without the need for new infrastructure development.
“This contributes to reducing the cost of producing a barrel, accelerating the integration of discoveries into the production map, and encouraging partners to implement the latest data collection and analysis technologies to increase the chances of successful exploration.”
Egypt is seeing increased interest in its oil and gas resources due to disruptions to shipping through the Strait of Hormuz, which have significantly reduced oil and gas exports from the GCC and Iraq.
READ THE MAY 2026 MEED BUSINESS REVIEW – click here to view PDFGlobal energy sector forced to recalibrate; Conflict hits debt issuance and listings activity; UAE’s non-oil sector faces unclear recovery period amid disruption.
Distributed to senior decision-makers in the region and around the world, the May 2026 edition of MEED Business Review includes:
> REGIONAL LNG: War undermines business case for Middle East LNG> CAPITAL MARKETS: Damage avoidance frames debt issuance> MARKET FOCUS: Conflict tests UAE diversificationTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/16944815/main.jpg -
King Salman airport selects three contractors for apron ECI21 May 2026

Saudi Arabia’s King Salman International Airport Development Company (KSIADC) has selected three groups to deliver the Terminal 6 apron, taxiways and other airfield infrastructure at King Salman International airport (KSIA) in Riyadh.
KSIADC, which is backed by Saudi sovereign wealth vehicle the Public Investment Fund, will initially deliver the project on an early contractor involvement (ECI) basis.
The selected groups are:
- Nesma & Partners / Limak / Samsung C&T / Alayuni Investment & Contracting (local/Turkiye/South Korea/local)
- Saudi Arabian Trading & Construction Company / Top International Engineering Corporation (local/China)
- Al-Rashid Trading & Contracting Company / IC Ictas (local/Turkiye)
The ECI process requires selected contractors to submit methodologies for the project and a design proposal. One team will then be selected for the construction.
MEED understands that the total package could be worth upto $800m.
In March, MEED exclusively reported that KSIADC had selected three groups for the construction of Terminal 6 at KSIA in Riyadh.
In November last year, MEED exclusively reported that KSIADC was targeting mid-2026 to award the contract for the construction of Terminal 6.
MEED reported in May 2025 that US firm Bechtel Corporation had been appointed as the delivery partner for the terminals at KSIA.
According to local media reports, KSIADC’s acting CEO, Marco Mejia, said the project developer had completed the project’s masterplan.
The reports added that Terminal 6 will boost the airport’s capacity by 40 million passengers.
The project is expected to be delivered before the start of Expo 2030 Riyadh.
MEED’s April 2026 report on Saudi Arabia includes:
> COMMENT: Risk accelerates Saudi spending shift
> GVT &: ECONOMY: Riyadh navigates a changed landscape
> BANKING: Testing times for Saudi banks
> UPSTREAM: Offshore oil and gas projects to dominate Aramco capex in 2026
> DOWNSTREAM: Saudi downstream projects market enters lean period
> POWER: Wind power gathers pace in Saudi Arabia
> WATER: Sharakat plan signals next phase of Saudi water expansion
> CONSTRUCTION: Saudi construction enters a period of strategic readjustment
> TRANSPORT: Rail expansion powers Saudi Arabia’s infrastructure pushTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/16937556/main.jpg