Algeria cancels $1.3bn refinery contract and makes new award
6 December 2024
Register for MEED's 14-day trial access
Algerian state energy producer Sonatrach has cancelled its $1.3bn contract with South Korea’s Samsung Engineering for the planned $3.7bn Hassi Messaoud refinery project in Algeria, and replaced it with China’s Sinopec.
Samsung Engineering confirmed the contract’s cancellation on 28 November without specifying the reason.
Sonatrach officially signed the main contract award for the Hassi Messaoud refinery with the consortium of Samsung Engineering and Tecnicas Reunidas in January 2020.
Since then, little progress has been made on the project due to various factors, including the Covid-19 pandemic, which caused significant disruption to the project.
Spanish newspaper CincoDias reported that China’s Sinopec has replaced Samsung Engineering on the project.
Spain’s Tecnicas Reunidas is still participating in the project, according to industry sources.
In August this year, MEED revealed that only some preliminary engineering work had been finished and the project was about 5% complete.
In 2023, Sonatrach restarted talks with the consortium that won the contract to execute the Hassi Messaoud refinery project to get it moving, but they were unsuccessful.
Talks were reinstated in 2024, but these were also unsuccessful.
In August, MEED revealed that Samsung Engineering and Tecnicas Reunidas had asked for amendments to the original deal due to the significant increase in building material prices since the original contracts were signed, which implies the project cannot be completed with the same budget.
At the time, a source said that the consortium wanted more money to account for inflation since 2020, when the contracts were signed.
In July this year, the vice-president of refining and petrochemicals at Sonatrach, Slimane Slimani, said that his company aimed to bring the facility online before the end of 2027.
Industry sources say this target will be difficult to achieve given the extensive delays and disruption that the project has suffered.
Speaking on Radio Algerienne Chaine 3 in July, Slimani said that Sonatrach had officially revived the project, and its execution was aligned with the company’s broader strategy for the country’s downstream sector.
He said the refinery project is estimated to produce an extra 2.7 million tonnes of diesel fuel and 1.2 million tonnes of gasoline a year.
When Sonatrach first announced the project, it was part of Algeria’s $14bn strategic downstream capacity expansion programme, which included the construction of five new refineries.
Under the terms of the original contracts signed in 2020, contractors were required to execute the works on a lump-sum turn-key basis.
Prior to the delays, the work was expected to be completed in about 52 months and conclude in the first quarter of 2025.
The scope of work includes building process and utility units; a crude distillation unit/vacuum distillation unit; a continuous catalytic reforming unit; an isomerisation, naphtha hydro-treating unit; a hydro desulphurisation unit; and a hydrocracker unit, as well as utility systems.
In recent years, Algeria’s $14bn strategic downstream capacity expansion programme has been scaled down and delayed.
Initially, Sonatrach awarded the front-end engineering and design contract for three refineries to London-based Amec Foster Wheeler in 2016.
These three refineries were located in Hassi Messaoud, Biskra and Tiaret.
Under the original $14bn plan, a further two refineries were to be added later.
Budget issues in 2017 put the Biskra refinery on hold so that Sonatrach could focus on moving forward with the Hassi Messaoud and Tiaret refineries.
Then, in 2018, Sonatrach cancelled the tendering process for the Tiaret refinery following a major downstream review.
Exclusive from Meed
-
Saudi Arabia signs $403m Syria infrastructure loans9 November 2026
-
Frontrunners emerge for Saudi substation projects9 November 2026
-
Contractor wins $197m Doha infrastructure works6 November 2026
-
Stakeholders aim to sign Iraq pipeline deal by year end6 November 2026
-
Taqa shortlists 17 contractors for Mirfa-Liwa scheme6 November 2026
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Saudi Arabia signs $403m Syria infrastructure loans9 November 2026
The Saudi Fund for Development (SFD) has signed six concessional loan agreements worth more than $403m to support power, water, healthcare, housing and other infrastructure projects in Syria.
The agreements include a $90m project to rehabilitate generating units at the Aleppo thermal power plant. The project is expected to benefit about 5 million people by restoring power-generation capacity and strengthening the stability of the national electricity grid.
The Aleppo thermal power plant has five generating units and an installed capacity of approximately 1,100MW. It is understood that at least three of the five generating units are out of operation and require rehabilitation. According to local media reports, rehabilitating these three units is estimated to take 18-24 months.
A further $30m will be allocated to upgrading Syria’s drinking water metering system. The project involves supplying and installing 300,000 smart water meters across several governorates, benefiting approximately 1.5 million people.
The remaining agreements cover civil defence, housing, healthcare and public finance.
A $105m loan will support the construction, rehabilitation and equipping of 25 civil defence centres across several governorates. The project is expected to benefit more than 7 million people and strengthen emergency response and disaster management capabilities.
A further $60m will finance the rehabilitation of up to 10,000 damaged housing units in various areas of the country.
The healthcare sector will receive $100m to rehabilitate, construct and equip hospitals and health centres. The funding will support restoring essential and specialised healthcare services and expanding access to medical facilities.
The final agreement, worth more than $18m, will support the digital transformation and institutional development of Syria’s Ministry of Finance by implementing an integrated financial services system.
The agreements were signed by SFD CEO Sultan Al-Marshad and Syrian Finance Minister Mohammed Yisr Barnieh in Riyadh on 5 November.
The financing is part of Saudi Arabia’s wider support for Syria’s recovery. In September 2025, the kingdom provided two grants to Syria to supply crude oil and cover part of government employees’ salaries for three months.
That same month, Saudi Arabia’s Acwa and Water Transmission Company (WTCO) signed a technical services agreement with Syria’s Ministry of Energy and German engineering group Fichtner to study the country’s water resources and identify future desalination and water transmission projects.
The work will examine the potential for desalination and water transmission capacity of up to 1.2 million cubic metres a day. WTCO has said the proposed transmission network could extend for about 400 kilometres.
https://image.digitalinsightresearch.in/uploads/NewsArticle/21211540/main0549.jpg -
Frontrunners emerge for Saudi substation projects9 November 2026

China’s TBEA Shandong Luneng Taishan Cable Company (TBEA) and Egypt’s Elsewedy have submitted the lowest bids for two substation projects in Riyadh Province, estimated to cost a combined $100m, sources have confirmed to MEED.
The $50m Qiddiya 2 Bulk Supply Point (BSP) project will provide a new bulk supply point to meet electricity demand in the Qiddiya development area. The scope includes constructing a main substation building and outdoor electrical yard, along with power transformers, high- and medium-voltage switchgear, protection and control systems, and supervisory control and data acquisition links.
The $50m Thadeq photovoltaic (PV) substation project will support grid connections and power exports from the Thadeq solar PV development. The scope includes a control building, outdoor switchyard, power transformers, switchgear, protection systems and Scada integration.
It is understood that both projects involve the construction of 380kV BSP substations.
Saudi Energy is the client for both projects.
The two tenders were issued earlier this year, with bids submitted in August and November for the Thadeq PV and Qiddiya 2 BSPs, respectively.
At Qiddiya, the additional infrastructure will support the development of entertainment, tourism, sports and residential facilities. Trading & Development Partnership is also developing a separate 380/132kV substation, known as BSP #9078, at Qiddiya.
The Thadeq project is part of the infrastructure required to connect new solar generation capacity to the national grid.
Saudi Energy has tendered several other 380kV substations and associated transmission lines this year, including projects serving planned solar and wind developments in the kingdom’s central, western and southern regions.
Bids were recently submitted for a separate BSP expansion project at Qurayyat in Al-Jawf Province, involving the construction of a 400kV substation to support higher power demand and improve grid reliability in the area.
https://image.digitalinsightresearch.in/uploads/NewsArticle/21210408/main.jpg -
Contractor wins $197m Doha infrastructure works6 November 2026

Register for MEED’s 14-day trial access
Qatar’s Public Works Authority (Ashghal) has awarded an estimated QR722m ($197m) contract to develop roads and infrastructure north of Al-Rifaa Street in Doha.
The contract was awarded to local firm Tadmur Contracting Company.
Six other contractors submitted bids:
- Qatar Trading & Contracting Group ($244m)
- Iris Construction Tourism Industry & Trade ($259m)
- Lotus Trading & Contracting ($260m)
- Generic Engineering Technologies & Contracting ($261m)
- Alghanim International / National Industrial Contracting ($268m)
- Hamad Bin Khalid Contracting Company ($281m)
The scope of work covers the construction of more than 34 kilometres of roads, dedicated plot developments, site clearance, backfill and earthworks.
The package also requires the installation of surface and groundwater drainage systems, a foul-water drainage network and treated sewage effluent lines.
In addition, the contractor will deliver a dedicated pumping station, an emergency flood area pond, 3,735 car parking spaces, road cross-sectional elements and verge parking bays.
Secondary infrastructure works include electrical distribution, water mains, utility lines, manholes, gully pots and house connections, along with kerbing, road pavement works, landscaping, street lighting, road markings and directional signage.
https://image.digitalinsightresearch.in/uploads/NewsArticle/21204827/main.jpg -
Stakeholders aim to sign Iraq pipeline deal by year end6 November 2026

Stakeholders expect a key contract to be signed before the end of the year for the development of a major oil export pipeline network in Iraq, according to industry sources.
Iraq and Syria’s governments, state-owned oil companies and a consortium led by Qatar’s UCC are currently discussing the terms.
If all parties agree to the proposed deal, the UCC-led coalition will become the selected developer responsible for tendering engineering, procurement and construction (EPC) contracts for the project.
The consortium includes US-based Chevron, the investment company TI Capital and France’s TotalEnergies.
The proposed plan will use a fast-track framework to bring the pipelines online as quickly as possible.
One source said: “The plan that is being discussed is highly unusual, because it is such a large-scale pipeline project and it would be brought online in a relatively short timeframe.”
A team from UCC is currently in Iraq for meetings with government officials to discuss the project, one source said.
The project will be focused on four pipeline packages:
- Basra to Najaf
- Najaf to Haditha
- Haditha to Fish Khapour
- Haditha to Banias Port in Syria
In July, Iraq’s cabinet approved state-owned Basra Oil Company signing a ​heads of agreement and a non-disclosure agreement with the UCC-led consortium to explore possible future oil pipeline projects.
Under the terms of the agreement, the consortium is preparing technical and financial feasibility studies for strategic export pipeline projects.
Also in July, US-based KBR was awarded a consultancy contract for the section of pipeline due to extend from Basra to Haditha.
In April, Iraq announced the allocation of $1.5bn for the Basra-Haditha route, while the larger scheme is estimated at around $5bn.
https://image.digitalinsightresearch.in/uploads/NewsArticle/21181262/main.jpg -
Taqa shortlists 17 contractors for Mirfa-Liwa scheme6 November 2026

Up to 17 contractors have been invited to submit bids for a major water transmission and distribution scheme serving Mirfa, Madinat Zayed and Liwa in Abu Dhabi, a source close to the project has confirmed to MEED.
The project, originally estimated to cost $775m, comprises a water transmission system from Mirfa, alongside distribution networks serving farms and settlements in Abu Dhabi’s western region.
In October, MEED exclusively reported that a request for proposals had been issued, with bids due on 5 January 2027, following an extension from the initial deadline of 11 November 2026.
The Mirfa-Liwa scheme has been in procurement for several years and was previously tendered in December 2024 as an engineering, procurement and construction scheme, divided between transmission and distribution works.
As MEED understands, it was recently re-tendered under a design, build and operate model, extending the contractor’s responsibilities to operating the infrastructure after construction.
According to sources, the full list of contractors invited to bid for the tender includes:
- Afcons Infrastructure (India)
- Alkhorayef Water & Power Technologies (Saudi Arabia)
- China Machinery Engineering Corporation (China)
- China National Chemical Engineering (China)
- China Tiesiju Civil Engineering Group (China)
- Danway Electrical & Mechanical Engineering (UAE)
- Emarat Aloula Contracting (UAE)
- FCC Aqualia (Spain)
- Gulf Contractors Company (UAE)
- Hydropower Energy & General Construction (UAE)
- Jereh Oil & Gas Engineering Corporation (China)
- Mapa (Turkiye)
- Nesma & Partners Contracting Company (Saudi Arabia)
- Orascom Construction (Egypt)
- Power Construction Corporation of China (China)
- Tecton Engineering & Construction (UAE)
- Tristar Engineering & Construction (UAE)
According to details seen by MEED, the scope includes a pumping station at Mirfa with a capacity of 128 million imperial gallons a day, approximately 125 kilometres of transmission pipelines to Muzairah, with branches to Madinat Zayed and Liwa Summit, and storage tanks at the three locations.
The distribution network is divided into four geographic clusters covering Liwa East, Liwa West, Madinat Zayed and Seih Al-Kheir. The works include associated pipelines, pumping stations and storage facilities.
https://image.digitalinsightresearch.in/uploads/NewsArticle/21181223/main.jpg