Algeria cancels $1.3bn refinery contract and makes new award
6 December 2024
Register for MEED's 14-day trial access
Algerian state energy producer Sonatrach has cancelled its $1.3bn contract with South Korea’s Samsung Engineering for the planned $3.7bn Hassi Messaoud refinery project in Algeria, and replaced it with China’s Sinopec.
Samsung Engineering confirmed the contract’s cancellation on 28 November without specifying the reason.
Sonatrach officially signed the main contract award for the Hassi Messaoud refinery with the consortium of Samsung Engineering and Tecnicas Reunidas in January 2020.
Since then, little progress has been made on the project due to various factors, including the Covid-19 pandemic, which caused significant disruption to the project.
Spanish newspaper CincoDias reported that China’s Sinopec has replaced Samsung Engineering on the project.
Spain’s Tecnicas Reunidas is still participating in the project, according to industry sources.
In August this year, MEED revealed that only some preliminary engineering work had been finished and the project was about 5% complete.
In 2023, Sonatrach restarted talks with the consortium that won the contract to execute the Hassi Messaoud refinery project to get it moving, but they were unsuccessful.
Talks were reinstated in 2024, but these were also unsuccessful.
In August, MEED revealed that Samsung Engineering and Tecnicas Reunidas had asked for amendments to the original deal due to the significant increase in building material prices since the original contracts were signed, which implies the project cannot be completed with the same budget.
At the time, a source said that the consortium wanted more money to account for inflation since 2020, when the contracts were signed.
In July this year, the vice-president of refining and petrochemicals at Sonatrach, Slimane Slimani, said that his company aimed to bring the facility online before the end of 2027.
Industry sources say this target will be difficult to achieve given the extensive delays and disruption that the project has suffered.
Speaking on Radio Algerienne Chaine 3 in July, Slimani said that Sonatrach had officially revived the project, and its execution was aligned with the company’s broader strategy for the country’s downstream sector.
He said the refinery project is estimated to produce an extra 2.7 million tonnes of diesel fuel and 1.2 million tonnes of gasoline a year.
When Sonatrach first announced the project, it was part of Algeria’s $14bn strategic downstream capacity expansion programme, which included the construction of five new refineries.
Under the terms of the original contracts signed in 2020, contractors were required to execute the works on a lump-sum turn-key basis.
Prior to the delays, the work was expected to be completed in about 52 months and conclude in the first quarter of 2025.
The scope of work includes building process and utility units; a crude distillation unit/vacuum distillation unit; a continuous catalytic reforming unit; an isomerisation, naphtha hydro-treating unit; a hydro desulphurisation unit; and a hydrocracker unit, as well as utility systems.
In recent years, Algeria’s $14bn strategic downstream capacity expansion programme has been scaled down and delayed.
Initially, Sonatrach awarded the front-end engineering and design contract for three refineries to London-based Amec Foster Wheeler in 2016.
These three refineries were located in Hassi Messaoud, Biskra and Tiaret.
Under the original $14bn plan, a further two refineries were to be added later.
Budget issues in 2017 put the Biskra refinery on hold so that Sonatrach could focus on moving forward with the Hassi Messaoud and Tiaret refineries.
Then, in 2018, Sonatrach cancelled the tendering process for the Tiaret refinery following a major downstream review.
Exclusive from Meed
-
-
Consortium signs PPA for Taweelah C power plant3 June 2026
-
-
Syria to tender gas plant contract3 June 2026
-
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Iranian drones hit Kuwait International airport’s Terminal 13 June 2026
Kuwait International airport was struck by a fresh wave of hostile drone attacks on 3 June. The drones caused significant structural damage to Terminal 1 and wounded several individuals.
Brigadier General Saud Abdulaziz Al-Otaibi, official spokesman for the Ministry of Defence, blamed the strikes on “criminal Iranian aggression”. He confirmed that the injured had been evacuated for medical care and stated that the armed forces remain in a state of complete readiness to secure the state.
The incident is the third major drone strike on the hub in recent months. On 1 April, a drone strike hit fuel tanks managed by Kuwait Aviation Fuelling Company, sparking massive fires. On March 28, another multi-drone raid severely damaged the airport’s primary radar systems.
The airport is being expanded with the construction of a new terminal, and works on the project are expected to be completed by 2027. It consists of three packages.
These are:
- Package 1: Main works – $4,329m
- Package 2: Multistorey car park building, connection roads, bridges and landscaping works – $550m
- Package 3: Aircraft parking, runways and service buildings – $950m
Turkiye’s Limak Holding is executing the main works.
The terminal building was designed by Foster+Partners and Gulf Consult.
https://image.digitalinsightresearch.in/uploads/NewsArticle/17089683/main.gif -
Consortium signs PPA for Taweelah C power plant3 June 2026
Emirates Water & Electricity Company (Ewec) has confirmed it has signed a power-purchase agreement (PPA) with a developer consortium for the Taweelah C independent power producer (IPP) project.
The agreement, which will run through to 2050, was signed with Abu Dhabi National Energy Company (Taqa), Al-Jomaih Energy & Water Company (Saudi Arabia) and Sembcorp Industries (Singapore), the utility said in a statement.
Taqa will own a 60% stake in the project, with the international consortium holding 40%. The ADX-listed company will also own 40% of the project’s operations and maintenance company, while the international consortium will own 60%.
Last month, MEED exclusively revealed that the winning consortium had been selected for the project, with the PPA initially expected to be signed in mid-May.
It is understood that China Energy Engineering Corporation (CEEC) will be the engineering, procurement and construction contractor.
The combined-cycle gas turbine plant will have a capacity of about 2.5GW. It will be located at the Al-Taweelah power and desalination complex, about 50 kilometres northeast of Abu Dhabi city.
Taweelah C is part of Ewec’s wider programme to support the UAE’s Net Zero by 2050 Strategic Initiative and the Abu Dhabi Department of Energy’s Clean Energy Strategic Target 2035.
Ewec plans to raise solar power capacity to 18GW and wind capacity to 2.6GW by 2035, while reducing the carbon intensity of its power generation by more than half compared with 2019.
The Taweelah C IPP is now expected to start commercial operations in 2029. The facility had previously been scheduled to begin commercial operations in the fourth quarter of 2028.
https://image.digitalinsightresearch.in/uploads/NewsArticle/17089163/main.jpg -
Local contractor wins Oman water transmission contract3 June 2026

Local contractor Al-Jesr United has won the main engineering, procurement and construction contract to reinforce Oman’s Sur water transmission system.
The contract, awarded by state-owned utility Nama Water Services (NWS), forms part of a project to improve the reliability of potable water supply to Sur, a coastal city about 200 kilometres southeast of Muscat.
The scheme, estimated to cost $80m, is designed to strengthen the network’s resilience during peak-demand periods and emergencies.
The scope of work includes upgrading the pumps at the Sur DP Pump Station with variable frequency drive units and replacing ductile iron pipes and fittings within the facility. It also covers about 17km of new transmission pipelines.
According to regional projects tracker MEED Projects, at least five local firms submitted commercial bids for the contract, which was tendered in August 2025.
These include:
- Al-Jesr United
- Al-Rafaa Trading & Contracting
- Gulf Petrochemical Services & Trading
- Professionals Trading
- Sarooj Construction Company
In June 2024, NWS awarded a $1.3m contract for the project’s design and construction supervision to Muscat-headquartered Ibn Khaldun Almadaen Engineering Consultants.
Sur is home to one of the sultanate’s key desalination plants, which supplies potable water to communities across eastern Oman.
The water transmission project will support network expansion in areas such as Al-Aigah and Ahiae, as the existing ductile iron pipeline serving Wilayat Sur is no longer sufficient to meet current and future demand.
Construction is expected to start in the third quarter of 2026 and take about two years to complete.
https://image.digitalinsightresearch.in/uploads/NewsArticle/17088454/main.jpg -
Syria to tender gas plant contract3 June 2026

Syria is preparing to tender a project to rehabilitate the Conoco gas plant in Deir ez-Zor province in the east of the country within the next 10 weeks, according to a document published by the US-Syria Business Council.
The gas plant was reclaimed by Syria’s military during an offensive in January this year.
It is Syria’s largest gas plant, but is severely damaged and cannot be operated in its current condition.
Before the country’s civil war, it processed 13 million cubic metres of gas a day.
The US-based companies ConocoPhillips and Novaterra signed a memorandum of understanding with the state-owned Syria Petroleum Company (SPC) to restore the facility in November last year.
Syria is currently in the midst of a push to ramp up oil and gas production and establish itself as a regional energy hub.
Earlier this year, Yousef Qiblawy, chief executive of SPC, said that his organisation was aiming to double national oil production before 2027 and boost output to 800,000 barrels a day by the end of 2029, not including offshore production.
https://image.digitalinsightresearch.in/uploads/NewsArticle/17088320/main.jpg -
AD Ports enters South America with $835m Brazil deal3 June 2026
Abu Dhabi-listed AD Ports Group has entered the South American market by agreeing to acquire a majority stake in Corredor Logística e Infraestrutura (CLI), Brazil’s leading independent agri-bulk port terminal operator, for an enterprise value of $835m.
The transaction represents AD Ports’ largest acquisition to date, surpassing its $720m purchase of Spain’s Noatum in 2023, and its $510m purchase of a 51% stake in Dubai-based Global Feeder Shipping in early 2024.
Under the terms of the agreement, AD Ports will acquire CLI from joint owners Macquarie Asset Management and IG4 Capital. CLI operates two major agri-bulk export terminals under long-term concessions: CLI Norte at the Port of Itaqui, which is 100% owned by CLI, and CLI Sul at the Port of Santos, which is 80% owned. In 2025, CLI handled 17 million tonnes of cargo, generating $178m in revenue and profits of $98m.
The deal, expected to close in the second half of 2026, subject to regulatory approvals, aligns with AD Ports’ strategy to expand its agrifood vertical. The group has recently secured similar international assets, including a 30-year concession at Jordan’s Aqaba multipurpose port, a $30m investment in Kazakhstan’s Sarzha Grain Terminal, and a clean bulk facility development at Pakistan’s Karachi Port.
The acquisition also reflects broader economic ties between the UAE and Brazil, where UAE investments total about $5bn. The UAE is currently negotiating a Comprehensive Economic Partnership Agreement (CEPA) with the Mercosur trading bloc, which includes Brazil.
The major capital deployment follows a period of significant financial growth and international expansion for the Abu Dhabi operator, which is 75.42% owned by sovereign wealth fund ADQ. AD Ports reported record results for 2025, with revenue rising 20% year-on-year to AED20.77bn ($5.66bn) and net profit increasing 16% to AED2.07bn.
According to its 2025 annual report, the group plans to invest AED2.45bn in port infrastructure development during 2026 alone, alongside AED1.3bn for liquefied petroleum gas and liquefied natural gas storage terminals between 2026 and 2028. To fund higher-return projects and optimise its balance sheet, AD Ports launched an asset monetisation programme in late 2025 targeting the recycling of AED4.6bn of capital.
https://image.digitalinsightresearch.in/uploads/NewsArticle/17087945/main.jpg