Algeria cancels $1.3bn refinery contract and makes new award

6 December 2024

Register for MEED's 14-day trial access 

Algerian state energy producer Sonatrach has cancelled its $1.3bn contract with South Korea’s Samsung Engineering for the planned $3.7bn Hassi Messaoud refinery project in Algeria, and replaced it with China’s Sinopec.

Samsung Engineering confirmed the contract’s cancellation on 28 November without specifying the reason.

Sonatrach officially signed the main contract award for the Hassi Messaoud refinery with the consortium of Samsung Engineering and Tecnicas Reunidas in January 2020.

Since then, little progress has been made on the project due to various factors, including the Covid-19 pandemic, which caused significant disruption to the project.

Spanish newspaper CincoDias reported that China’s Sinopec has replaced Samsung Engineering on the project.

Spain’s Tecnicas Reunidas is still participating in the project, according to industry sources.

In August this year, MEED revealed that only some preliminary engineering work had been finished and the project was about 5% complete.

In 2023, Sonatrach restarted talks with the consortium that won the contract to execute the Hassi Messaoud refinery project to get it moving, but they were unsuccessful.

Talks were reinstated in 2024, but these were also unsuccessful.

In August, MEED revealed that Samsung Engineering and Tecnicas Reunidas had asked for amendments to the original deal due to the significant increase in building material prices since the original contracts were signed, which implies the project cannot be completed with the same budget.

At the time, a source said that the consortium wanted more money to account for inflation since 2020, when the contracts were signed.

In July this year, the vice-president of refining and petrochemicals at Sonatrach, Slimane Slimani, said that his company aimed to bring the facility online before the end of 2027.

Industry sources say this target will be difficult to achieve given the extensive delays and disruption that the project has suffered.

Speaking on Radio Algerienne Chaine 3 in July, Slimani said that Sonatrach had officially revived the project, and its execution was aligned with the company’s broader strategy for the country’s downstream sector.

He said the refinery project is estimated to produce an extra 2.7 million tonnes of diesel fuel and 1.2 million tonnes of gasoline a year.

When Sonatrach first announced the project, it was part of Algeria’s $14bn strategic downstream capacity expansion programme, which included the construction of five new refineries.

Under the terms of the original contracts signed in 2020, contractors were required to execute the works on a lump-sum turn-key basis.

Prior to the delays, the work was expected to be completed in about 52 months and conclude in the first quarter of 2025.

The scope of work includes building process and utility units; a crude distillation unit/vacuum distillation unit; a continuous catalytic reforming unit; an isomerisation, naphtha hydro-treating unit; a hydro desulphurisation unit; and a hydrocracker unit, as well as utility systems.

In recent years, Algeria’s $14bn strategic downstream capacity expansion programme has been scaled down and delayed.

Initially, Sonatrach awarded the front-end engineering and design contract for three refineries to London-based Amec Foster Wheeler in 2016.

These three refineries were located in Hassi Messaoud, Biskra and Tiaret.

Under the original $14bn plan, a further two refineries were to be added later.

Budget issues in 2017 put the Biskra refinery on hold so that Sonatrach could focus on moving forward with the Hassi Messaoud and Tiaret refineries.

Then, in 2018, Sonatrach cancelled the tendering process for the Tiaret refinery following a major downstream review.

https://image.digitalinsightresearch.in/uploads/NewsArticle/13072344/main.jpg
Wil Crisp
Related Articles
  • Oman receives Misfah and Duqm applications

    4 April 2025

    Oman's Nama Power & Water Procurement Company (Nama PWP) has received statements of qualifications (SOQs) from 12 firms for a competitive tender to develop a gas-fired independent power producer (IPP) project in the sultanate.

    The Misfah and Duqm combined-cycle gas turbine plants will have a capacity of 2,400MW and will be tendered as one contract, a source close to the project previously told MEED. 

    Nama PWP invited interested firms to submit their prequalification applications for the project in January, with a 13 March deadline.

    The utility developers that submitted their SOQs include:

    • Acwa Power (Saudi Arabia)
    • Korea Western Power Company (Kowepo, South Korea)
    • Marubeni Corporation (Japan)
    • Nebras Power (Qatar)
    • Alghanim International (Kuwait)
    • Etihad Water & Electricity (UAE)
    • Reliance Power (India)
    • Samsung C&T Corporation (South Korea)
    • Sembcorp Utilities (Singapore)
    • Shenzhen Energy Group Company (China)
    • Sumitomo Corporation (Japan)
    • Al-Jomaih Energy & Water (Saudi Arabia)

    In December, the project client invited companies to express interest in the project, which will be implemented on a build, own and operate (BOO) basis.

    At the time, Nama PWP said it expected to issue the tender in the first quarter of 2025 and award the BOO contract by Q4.

    The company also said it expects early power in Q2 2028, with full commercial operation set for Q2 2029.

    US/India-based Synergy Consulting is the client's financial adviser.

    The new project represents a u-turn on a previous announcement that Oman would not build any new gas-fired power generation plants, which local media reported in 2022.

    In May last year, Nama PWP announced the award of renewed contracts for four gas-fired independent power and water projects (IWPPs) in the sultanate.

    The agreements collectively secured over 1,500MW of electricity and 200,000 cubic metres a day of desalinated water for up to nine years.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/13616470/main.jpg
    Jennifer Aguinaldo
  • Trump tariffs hit 13 Mena states

    4 April 2025

    Over a  dozen Mena countries face between 10% and 41% of US President Donald Trump's reciprocal tariffs effective 5 April.

    Trump announced an executive order on 2 April in line with "regulating imports with a reciprocal tariff to rectify trade practices that contribute to large and persistent annual US goods trade deficits".

    Six of these countries, including Egypt, Kuwait, Morocco, Qatar, Saudi Arabia and the UAE face 10% of tariffs, which is the minimum rate – or universal tariff –  that has been imposed on US trading partners.

    Goods originating from Syria and Iraq face the highest tariff rates of  41% and 39%, followed by Libya and Algeria, which each face tariffs of 31% and 30%, respectively.

    The executive order imposes 28% tariffs on goods originating from Tunisia, 20% from Jordan, and 17% from Israel.

    The impact of the new tariffs on regional businesses is less clear compared to their impact on US consumers, who will have to bear the brunt of increased prices of imported products.

    US media outlets report that goods included in the reciprocal tariff regime include electronics, automobiles, clothing and shoes, wine and spirits, furniture, coffee and chocolates.

    Dubai-based global ports operator DP World said that businesses will face significant adjustments in response to the tariffs, according to a report by the UAE's The National.

    'With tariffs increasingly shaping policy, we recognise that businesses are facing significant adjustments. As supply chains realign, new manufacturing and trading hubs may emerge in response to shifting cost structures and market access considerations," DP World was quoted as saying.

    The firm added that they are working closely "with our customers to navigate these complexities – helping them maintain continuity, find efficiencies and build resilience in an evolving global landscape".

    Photo credit: Pixabay, fo illustrative purposes only

    https://image.digitalinsightresearch.in/uploads/NewsArticle/13616433/main.jpg
    Jennifer Aguinaldo
  • Bahrain receives solar IPP consultancy bids

    4 April 2025

    Three firms have submitted proposals for a consultancy services contract for a new solar independent power project (IPP) in Bahrain.

    Bahrain’s Electricity & Water Authority (EWA) plans to procure the solar IPP project located at Belaj Al-Jazaer area in the kingdom's Southern Governorate.

    According to an industry source, the planned solar IPP will have a capacity of between 160MW and 200MW.

    As in most IPPs, a financial adviser will lead the project's consultancy services team.

    KPMG Fakhro, a subsidiary of the UK-based consultancy services firm, submitted the lowest bid of BD506,000 ($1.3m). 

    Deloitte & Touche Middle East offered BD589,480 for the contract, while EY Middle East offered BD770,510.

    In January, EWA received proposals from 10 firms for a contract to establish a 44MW solar power plant at the University of Bahrain premises.

    The project will be implemented on a turnkey basis, which includes engineering, designing, manufacturing, installing and commissioning the project. The proposed project is expected to generate approximately 75 gigawatt-hours of electricity annually.

    The construction of solar power plants supports Bahrain’s 2060 net-zero carbon emissions target.

    In July last year, EWA received a single bid for a contract to design and build solar power stations in the Al-Dur area in the kingdom’s Southern Governorate. The project is expected to have a capacity of between 90MW and 100MW.

    In August 2023, EWA awarded Deft Contractors a contract to build, own, operate and maintain grid-tied solar photovoltaic (PV) power panels with a minimum capacity of 72MW in Sakhir in the south of the kingdom.

    EWA also recently prequalified bidders for one thermal independent water and power project and an independent water project. 

    https://image.digitalinsightresearch.in/uploads/NewsArticle/13616351/main.jpg
    Jennifer Aguinaldo
  • First Siemens Energy turbine reaches Qassim 2

    4 April 2025

    The first combined-cycle gas turbine (CCGT) has arrived at the Qasssim 2 independent power producer (IPP) project site in Saudi Arabia.

    According to one of the project owners, France's EDF, the first turbine has arrived at their Qassim 2 CCGT site in Saudi Arabia, marking a key milestone in the construction of the 1,800MW "decarbonised combined-cycle gas turbine project with provision for carbon capture, utilisation and storage".

    The first and the next two turbines to power the Qassim 2 CCGT plant are understood to be made in Saudi Arabia, EDF Renewables Middle East said in a social media post.

    Germany's Siemens Energy confirmed winning the contract, worth a total of $1.5bn, to supply gas turbines and other equipment to the Qassim 2, as well as another CCGT plant, Taiba 2, in June 2024

    Siemens Energy´s HL-class gas turbines, in combination with steam turbines and generators, will generate approximately 2,000MW of electricity at each site.

    A utility developer team led by the local Al-Jomaih Energy & Water Company (Jenwa) reached financial close for the contract to develop and operate the Taiba 2 and Qassim 2 IPPs in July 2024.

    The developer team, which includes EDF and the local Buhur for Investment, signed a 25-year power-purchase agreement with the principal buyer, Saudi Power Procurement Company (SPPC), for the projects in November 2023.

    The team subsequently appointed an EPC team, led by China Energy International Group, to work on the project.

    The EPC contractor awarded the contract to supply the project with gas turbines and other related equipment to Siemens Energy.

    Siemens Energy said last year that  Taiba 2 and Qassim 2 power plants will be initially connected to the grid in simple cycle mode in 2026 and will be permanently operated as a combined cycle power plant one year later.

    The new plants are expected to save up to 60% of carbon dioxide (CO2) emissions compared with oil-fueled power plants.

    They will also be compatible with Saudi Arabia's energy strategy, which calls for the construction of CO2 capture and storage facilities in the medium term, to enable a carbon-neutral energy supply.

    Photo credit: EDF Renewables Middle East

    https://image.digitalinsightresearch.in/uploads/NewsArticle/13616061/main.gif
    Jennifer Aguinaldo
  • Tadweer and Tribe seek nod for $1.5bn Australia project

    4 April 2025

    The first project to emerge from the Comprehensive Economic Partnership Agreement (Cepa) signed between the UAE and Australia in November 2024 is progressing well. 

    The Parkes Energy Recovery (PER) project will convert waste to electricity to power homes, businesses and industries across New South Wales (NSW) on Australia’s east coast.

    According to Fahad Obaid Al-Taffaq, UAE ambassador to Australia, Parkes Energy Recovery, led by Australia-headquartered Tribe Infrastructure Group and Abu Dhabi’s Tadweer Group, is kicking off its consultation process to engage with stakeholders and secure approvals for the $1.5bn energy-from-waste facility.

    “This project, a key development after signing the UAE-Australia Cepa, will power 80,000 homes, create jobs and foster long-term, sustainable growth,” Al-Taffaq said in a social media post in March.

    The proposed facility will divert an estimated 600,000 tonnes of waste annually from landfill and generate at least 60MW of energy.

    The anticipated capital investment of $1.5bn makes the project the “largest single investment in the history of Parkes”, the Parkes Shire Council website said in March.

    MEED understands that councillors and the council’s Executive Management Team met with representatives from Parkes Energy Recovery on 18 March to discuss the proposed project.

    The project is expected to tap “proven technology” from Zurich-headquartered Kanadevia Inova, formerly Hitachi Zosen Inova, to turn waste into electricity.

    Parkes Energy Recovery comprises Tribe, Tadweer, Australian waste solutions firm HiQ and Kanadevia Inova.

    The Regional Growth NSW Development Corporation (RGDC) selected the team following a “market process to identify a developer, which included scrutinising the consortium and the technology offered”.

    The Parkes Shire Council said in March that the consortium “will now begin the process of wide community engagement and the planning and environmental approvals process for the facility that it will design, fund, own and operate on land leased from RGDC”.

    The process will include rigorous planning and environmental approvals with the NSW Environment Protection Authority (EPA) and the Department of Planning, Housing and Infrastructure (DPHI).

    Cepa objectives

    According to a legal note by UK-based law firm Watson, Farley & Williams (WFW), the Cepa free trade agreement offers major benefits to Australian businesses. These include the elimination of tariffs on over 99% of exports from Australia to the UAE by value and guaranteed market access in over 120 service sectors and subsectors.

    WFW also notes that Australia and the UAE have agreed on five memoranda of understanding highlighting sectors that the two countries intend to work on to facilitate and enhance their investment relationship. These are green and renewable energy, data centres and artificial intelligence (AI) projects, the minerals sector, food and agriculture, and infrastructure development.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/13613963/main.jpg
    Jennifer Aguinaldo