Algeria cancels $1.3bn refinery contract and makes new award

6 December 2024

Register for MEED's 14-day trial access 

Algerian state energy producer Sonatrach has cancelled its $1.3bn contract with South Korea’s Samsung Engineering for the planned $3.7bn Hassi Messaoud refinery project in Algeria, and replaced it with China’s Sinopec.

Samsung Engineering confirmed the contract’s cancellation on 28 November without specifying the reason.

Sonatrach officially signed the main contract award for the Hassi Messaoud refinery with the consortium of Samsung Engineering and Tecnicas Reunidas in January 2020.

Since then, little progress has been made on the project due to various factors, including the Covid-19 pandemic, which caused significant disruption to the project.

Spanish newspaper CincoDias reported that China’s Sinopec has replaced Samsung Engineering on the project.

Spain’s Tecnicas Reunidas is still participating in the project, according to industry sources.

In August this year, MEED revealed that only some preliminary engineering work had been finished and the project was about 5% complete.

In 2023, Sonatrach restarted talks with the consortium that won the contract to execute the Hassi Messaoud refinery project to get it moving, but they were unsuccessful.

Talks were reinstated in 2024, but these were also unsuccessful.

In August, MEED revealed that Samsung Engineering and Tecnicas Reunidas had asked for amendments to the original deal due to the significant increase in building material prices since the original contracts were signed, which implies the project cannot be completed with the same budget.

At the time, a source said that the consortium wanted more money to account for inflation since 2020, when the contracts were signed.

In July this year, the vice-president of refining and petrochemicals at Sonatrach, Slimane Slimani, said that his company aimed to bring the facility online before the end of 2027.

Industry sources say this target will be difficult to achieve given the extensive delays and disruption that the project has suffered.

Speaking on Radio Algerienne Chaine 3 in July, Slimani said that Sonatrach had officially revived the project, and its execution was aligned with the company’s broader strategy for the country’s downstream sector.

He said the refinery project is estimated to produce an extra 2.7 million tonnes of diesel fuel and 1.2 million tonnes of gasoline a year.

When Sonatrach first announced the project, it was part of Algeria’s $14bn strategic downstream capacity expansion programme, which included the construction of five new refineries.

Under the terms of the original contracts signed in 2020, contractors were required to execute the works on a lump-sum turn-key basis.

Prior to the delays, the work was expected to be completed in about 52 months and conclude in the first quarter of 2025.

The scope of work includes building process and utility units; a crude distillation unit/vacuum distillation unit; a continuous catalytic reforming unit; an isomerisation, naphtha hydro-treating unit; a hydro desulphurisation unit; and a hydrocracker unit, as well as utility systems.

In recent years, Algeria’s $14bn strategic downstream capacity expansion programme has been scaled down and delayed.

Initially, Sonatrach awarded the front-end engineering and design contract for three refineries to London-based Amec Foster Wheeler in 2016.

These three refineries were located in Hassi Messaoud, Biskra and Tiaret.

Under the original $14bn plan, a further two refineries were to be added later.

Budget issues in 2017 put the Biskra refinery on hold so that Sonatrach could focus on moving forward with the Hassi Messaoud and Tiaret refineries.

Then, in 2018, Sonatrach cancelled the tendering process for the Tiaret refinery following a major downstream review.

https://image.digitalinsightresearch.in/uploads/NewsArticle/13072344/main.jpg
Wil Crisp
Related Articles
  • Chinese contractor wins Morocco solar plant deal

    10 August 2026

    China Harbour Engineering Company (CHEC), a subsidiary of China Communications Construction Company (CCCC), has won a contract to build a solar photovoltaic (PV) power plant in Fez in northern Morocco.

    Known as GreenPower Morocco 4 (GPM4), the project is being developed by Moroccan company GPM Holding through its utility-scale solar subsidiary GPM Parks.

    The project covers engineering design, equipment procurement and installation, construction of an operation and maintenance building, grid connection and commissioning. It also includes upgrades to the associated substation.

    According to CHEC, the completed plant will supply electricity to the local grid, although it did not disclose the project’s capacity or contract value. 

    The project is being developed under Law 13-09, which provides Morocco’s framework for private renewable energy generation.

    According to its website, GPM Holding is also developing another solar PV project called GreenPower Morocco 2 (GPM2). This follows the completion of its first solar project, the 34MW project (GPM1) commissioned in Tangier in 2024. 

    GPM1 was developed by Green Power Morocco, a special purpose vehicle owned by GPM Holding and UAE-based Amea Power. The $30m project covers 75 hectares and includes 91,000 PV panels. It is expected to generate about 66,149MWh a year.

    The project has a 25-year power purchase agreement in place with Amendis, a subsidiary of Veolia Morocco. PowerChina was the main engineering, procurement and construction (EPC) contractor.

    Chinese contractors have previously been involved in other projects in Morocco’s renewable energy sector.

    Shandong Electric Power Construction Company (Sepco 3), a subsidiary of PowerChina, was part of the EPC consortium for the 200MW Noor 2 concentrated solar plants and 150MW Noor 3 concentrated solar power projects at the Noor Ouarzazate complex.

    New contract awards have been limited in Morocco in 2026, although six solar PV plants are now in the execution stage under phases one and two of the 305MW Noor Atlas solar PV programme.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/18263680/main.jpg
    Mark Dowdall
  • Aramco puts out fire at Jizan refinery after Houthi strike

    10 August 2026

    Saudi Aramco said it had extinguished a fire that broke out at its Jizan refinery on Saudi Arabia’s Red Sea coast after the facility was hit in drone strikes by Yemen-based Houthi rebels on 9 August.

    The kingdom’s Ministry of Energy said the fire occurred at an Aramco refinery facility in Jizan and that emergency authorities had completed the necessary procedures to deal with the incident.

    The energy ministry did not say what started the fire, saying only that the incident caused no injuries.

    The Houthi rebels later claimed responsibility for the attack.

    The province of Jizan lies close to Saudi Arabia’s border with Yemen and has repeatedly been targeted by the Houthis in attacks on the kingdom’s energy infrastructure.

    The strike on the Jizan refinery was the second attack on the facility by the Houthis in as many weeks. Aramco shut the refinery on 27 July following a similar drone strike, which, according to media reports, damaged the integrated gasification combined-cycle unit and tank farm at the complex.

    On a call with investors to discuss Aramco’s second-quarter results, CEO Amin Nasser said recent attacks on the company’s facilities in the world’s top oil-exporting country had caused some disruption to production, but that he was confident operations could be restored quickly. He said the attacks had had no material operational or financial impact.

    Jizan refinery complex

    Saudi Aramco’s sprawling Jizan refinery complex entered operations in 2021.

    Aramco undertook the estimated $16bn-plus project in late 2010. The scheme consists of a refinery with an output capacity of 400,000 barrels a day (b/d), a major marine terminal and a 4GW combined-cycle power plant in Baish, in Saudi Arabia’s southwestern Jizan region.

    The Jizan refinery covers an area of 12 square kilometres. The complex processes Arabian Heavy and Arabian Medium crude grades to produce 80 million b/d of gasoline, 250 million b/d of diesel and more than 1 million tonnes a year of petrochemical products such as benzene and paraxylene.

    A multiple-pier marine terminal supports the supply of crude oil from oil fields located mainly in the kingdom’s Eastern Province to the refinery, as well as the export of surplus refined products to overseas markets. The terminal has been designed to accommodate very large crude carriers.

    A 4,000MW combined-cycle power plant uses approximately 90,000 b/d of vacuum residue from the refinery to generate electricity, hydrogen and water for the refinery, while conveying excess power to the national grid.

    The hydrocracker unit comprises two parallel trains with a combined capacity of 54,500 b/d. The diesel hydrotreater plant comprises two trains, each with a capacity of 87,500 b/d.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/18262347/main.jpg
    Indrajit Sen
  • Shamal picks Dutco for Dubai Zoo site homes

    10 August 2026

    Dubai-based Shamal Holding has awarded local contractor Dutco Construction the main construction works contract for a low-rise residential project on the site of the former Dubai Zoo in Jumeirah 1.

    The project will comprise 90 low-rise homes and is designed as a residential leasing community that will remain under Shamal’s ownership, with all homes offered for premium leasing.

    The development will retain mature trees from the former zoo and is planned around shared courtyards, landscaped open spaces and a central park. Residents will have access to a clubhouse, wellness area, children’s play area, family pool, lounge and gym.

    The architect is DXB Lab. The local H&H is the development manager for the project.

    Dutco has previously worked with Shamal on infrastructure elements of the Dubai Harbour and Dubai Harbour Marinas developments.

    Shamal’s wider real estate portfolio includes the Naia Island, Dubai Harbour and Nad Al-Sheba Gardens developments. The company also holds hospitality and leisure assets, including partnerships with Jumeirah, Hilton and Baccarat, and operates attractions such as Skydive Dubai and Deep Dive Dubai.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/18262386/main.png
    Colin Foreman
  • WEBINAR: Mena Oil & Gas Projects Market 2026-27

    10 August 2026

    Webinar: Mena Oil & Gas Projects Market 2026-27 
    Thursday 27 August 2026 | 11:00 AM GST  |  Register now


    Agenda:

    • Summary of the Mena oil, gas and petrochemicals projects market 
    • Overview of major megaprojects, including project programmes
    • Analysis of active contracts and spending to date
    • Review of top contracts by work already awarded
    • Long-term capital expenditure outlays and forecasts
    • Key contracts expected to be tendered and awarded over the next 18 months
    • Leading clients, contractors and market participants
    • Spending by segment: oil, gas and petrochemicals (upstream, downstream, onshore and offshore) 
    • Audience Q&A 

    Hosted by: Indrajit Sen, MEED’s oil & gas editor

    Click here to register

    https://image.digitalinsightresearch.in/uploads/NewsArticle/18260597/main.gif
    Indrajit Sen
  • Spanish firm renews Yanbu desalination O&M contract

    10 August 2026

    Spain’s Aqualia has announced it has renewed a contract to operate and maintain three floating desalination plants in Yanbu on Saudi Arabia’s Red Sea coast.

    The contract was awarded by the National Shipping Company of Saudi Arabia (Bahri) and will run until 14 September 2028, with an option to extend for a further two years.

    The three reverse osmosis (RO) plants are mounted on barges and have a combined production capacity of 150,000 cubic metres a day (cm/d). Each plant has a capacity of 50,000 cm/d.

    The three plants were originally deployed at Al-Shuqaiq and are designed to be relocated along Saudi Arabia’s coastline according to water demand. The barges are currently located at Yanbu.

    The $255m floating desalination project was commissioned for the Saudi Water Authority in 2022, with Bahri as the developer and UAE-based Metitio as the main contractor.

    Bahri is publicly listed on the Saudi Exchange but has significant government ownership, with the Public Investment Fund (PIF) holding 22.5% and Saudi Aramco Development Company owning 20% of the company.

    Aqualia is providing operation and maintenance services in Saudi Arabia through its joint venture Haji Abdullah Alireza Integrated Services Company (Haaisco), in which it holds a 51% stake.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/18259350/main.jpg
    Mark Dowdall