Algeria cancels $1.3bn refinery contract and makes new award
6 December 2024
Register for MEED's 14-day trial access
Algerian state energy producer Sonatrach has cancelled its $1.3bn contract with South Korea’s Samsung Engineering for the planned $3.7bn Hassi Messaoud refinery project in Algeria, and replaced it with China’s Sinopec.
Samsung Engineering confirmed the contract’s cancellation on 28 November without specifying the reason.
Sonatrach officially signed the main contract award for the Hassi Messaoud refinery with the consortium of Samsung Engineering and Tecnicas Reunidas in January 2020.
Since then, little progress has been made on the project due to various factors, including the Covid-19 pandemic, which caused significant disruption to the project.
Spanish newspaper CincoDias reported that China’s Sinopec has replaced Samsung Engineering on the project.
Spain’s Tecnicas Reunidas is still participating in the project, according to industry sources.
In August this year, MEED revealed that only some preliminary engineering work had been finished and the project was about 5% complete.
In 2023, Sonatrach restarted talks with the consortium that won the contract to execute the Hassi Messaoud refinery project to get it moving, but they were unsuccessful.
Talks were reinstated in 2024, but these were also unsuccessful.
In August, MEED revealed that Samsung Engineering and Tecnicas Reunidas had asked for amendments to the original deal due to the significant increase in building material prices since the original contracts were signed, which implies the project cannot be completed with the same budget.
At the time, a source said that the consortium wanted more money to account for inflation since 2020, when the contracts were signed.
In July this year, the vice-president of refining and petrochemicals at Sonatrach, Slimane Slimani, said that his company aimed to bring the facility online before the end of 2027.
Industry sources say this target will be difficult to achieve given the extensive delays and disruption that the project has suffered.
Speaking on Radio Algerienne Chaine 3 in July, Slimani said that Sonatrach had officially revived the project, and its execution was aligned with the company’s broader strategy for the country’s downstream sector.
He said the refinery project is estimated to produce an extra 2.7 million tonnes of diesel fuel and 1.2 million tonnes of gasoline a year.
When Sonatrach first announced the project, it was part of Algeria’s $14bn strategic downstream capacity expansion programme, which included the construction of five new refineries.
Under the terms of the original contracts signed in 2020, contractors were required to execute the works on a lump-sum turn-key basis.
Prior to the delays, the work was expected to be completed in about 52 months and conclude in the first quarter of 2025.
The scope of work includes building process and utility units; a crude distillation unit/vacuum distillation unit; a continuous catalytic reforming unit; an isomerisation, naphtha hydro-treating unit; a hydro desulphurisation unit; and a hydrocracker unit, as well as utility systems.
In recent years, Algeria’s $14bn strategic downstream capacity expansion programme has been scaled down and delayed.
Initially, Sonatrach awarded the front-end engineering and design contract for three refineries to London-based Amec Foster Wheeler in 2016.
These three refineries were located in Hassi Messaoud, Biskra and Tiaret.
Under the original $14bn plan, a further two refineries were to be added later.
Budget issues in 2017 put the Biskra refinery on hold so that Sonatrach could focus on moving forward with the Hassi Messaoud and Tiaret refineries.
Then, in 2018, Sonatrach cancelled the tendering process for the Tiaret refinery following a major downstream review.
Exclusive from Meed
-
Egypt approves plans for 869MW wind power plant22 June 2026
-
Local firm signs Jeddah drainage contracts22 June 2026
-
Saudi firm signs Uzbekistan water treatment PPP22 June 2026
-
Qiddiya seeks contractors for indoor arena project22 June 2026
-
Egypt signs gas deal with Harbour Energy22 June 2026
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Egypt approves plans for 869MW wind power plant22 June 2026
Egypt’s Cabinet has approved plans for French renewable energy developer Voltalia to develop an 869MW wind power project.
The scheme will be built on land allocated by the New & Renewable Energy Authority (NREA), according to a statement posted by the Cabinet following its most recent weekly meeting.
Voltalia will make an initial investment of $53m and has committed to achieving commercial operations by December 2028.
Voltalia already operates the 32MW Ra solar plant at the Benban solar complex in Aswan and is expanding its renewable energy portfolio in Egypt.
Previously, in 2024, it signed a framework agreement with Egypt’s Taqa Arabia to develop a green hydrogen and renewable power cluster near the Ain Sokhna port in the Suez Canal Economic Zone.
The green hydrogen development is planned in two phases, each centred on a 500MW electrolyser powered by more than 1.3GW of renewable generation capacity. The project, still in its early stages, is expected to produce up to 350,000 tonnes of green ammonia a year.
Voltalia’s partnership with Taqa Arabia also includes plans for a 3.2GW hybrid wind and solar project to repower the existing 545MW Zafarana wind farm in Suez Governorate. The Cabinet statement did not indicate whether the newly approved 869MW wind project forms part of that proposal.
Meanwhile, the developer won another contract, earlier this year, to develop a 132MW solar power project in Tunisia’s Gabes region.
The project, known as Wadi, marked Voltalia’s third major solar award in the country after the Sagdoud and Menzel Habib projects awarded in 2024.
https://image.digitalinsightresearch.in/uploads/NewsArticle/17376730/main.jpg -
Local firm signs Jeddah drainage contracts22 June 2026
Local contractor Alkhorayef Water & Power Technologies (AWPT) has announced it has signed two contracts with Jeddah Municipality to operate and maintain stormwater and surface water drainage networks across the city.
The contracts have a combined value of SR202.06m ($53.9m), and each will run for five years.
The first contract, valued at SR108.46m ($28.9m), covers the operation and cleaning of stormwater and surface water networks in the South and Al-Malisa sub-municipalities.
The second contract, worth SR93.59m ($25m), covers similar services for the Airport Sub-Municipality.
In March, MEED reported that the firm had won a long-term contract to carry out work in the airport’s sub-municipality area. The agreement was signed on 16 June.
Elsewhere, construction has yet to begin on phases one and two of the King Abdullah Road-Falasteen Road tunnel project, each valued at about $175m.
According to sources, Jeddah Municipality selected Saudi contractor Thrustboring Construction Company to build the large-diameter stormwater drainage tunnels in 2025. However, an official agreement has yet to be signed.
The municipality was also previously planning to rehabilitate the existing Al-Zahra pumping station. Prequalification for the project began in 2020; however, it is understood that the main contact tender was cancelled last year.
https://image.digitalinsightresearch.in/uploads/NewsArticle/17376097/main.jpg -
Saudi firm signs Uzbekistan water treatment PPP22 June 2026
Saudi-listed Miahona has signed a public-private partnership agreement to enhance, operate and maintain Uzbekistan’s Zomin water treatment plant in the country’s Jizzakh region.
The agreement was signed on 18 June with Uzsuvtaminot, the country’s state-owned water utility, the developer said in a filing with the Saudi stock exchange.
Miahona will carry out enhancement works and 25 years of operation and maintenance services for the existing plant, which has a design treatment capacity of 50,000 cubic metres a day
The contract marks the company’s entry into Uzbekistan’s water sector. According to the disclosure, it will enter into force once a project-related governmental decree is issued in accordance with Uzbekistan’s applicable legislation.
The contract is estimated at $105m (SR395m), with a final value to be confirmed following the issuance of the governmental decree.
MEED reported earlier this month that Uzbekistan had stepped up its engagement with Middle Eastern investors, including holding talks with Saudi Arabia’s Acwa and Vision Invest on renewable energy, water management, waste recycling, digital infrastructure and urban utility projects.
The government also recently held discussions with a UAE delegation led by Suhail Mohamed Al-Mazrouei, minister of energy and infrastructure and chairman of Etihad Water & Electricity’s Board of Directors.
At the Tashkent International Investment Forum, it signed a €197m financing package with Germany’s KfW Development Bank to support drinking water supply and wastewater projects in the Surkhandarya and Fergana regions.
The projects will cover Termez and several district centres in Surkhandarya region, as well as Kokand and Margilan in Fergana region.
This includes “the construction and reconstruction of hundreds of kilometres of drinking water and wastewater networks, pumping stations and modern wastewater treatment facilities”, deputy prime minister Jamshid Khodjaev said.
https://image.digitalinsightresearch.in/uploads/NewsArticle/17375811/main.jpg -
Qiddiya seeks contractors for indoor arena project22 June 2026

Register for MEED’s 14-day trial access
Saudi Arabian gigaproject developer Qiddiya Investment Company (QIC) has invited contractors to prequalify for a contract to build an indoor sports arena within its Qiddiya entertainment city project.
The invitation was issued on 21 May, with a submission deadline of 28 June.
The multipurpose arena is designed to International Olympic Committee standards.
It will be located in District 18, in the Uptown South area of Qiddiya.
Once completed, the indoor arena will be capable of hosting a wide range of sports, cultural and entertainment events.
The arena will feature numerous sports courts for basketball, handball, futsal, volleyball, tennis, boxing and gymnastics.
It will have a seating capacity of 18,000 spectators.
The project is scheduled for completion by 2030.
QIC’s other major projects include an e-sports arena, the National Tennis Centre, Prince Mohammed Bin Salman Stadium, a motorsports track, a racecourse, the Dragon Ball and Six Flags theme parks, and Aquarabia.
QIC opened the Six Flags theme park to the public in December last year.
The park covers 320,000 square metres and features 28 rides and attractions, including 10 thrill rides and 18 aimed at families and young children.
The Qiddiya project is a key part of Riyadh’s strategy to boost leisure tourism in the kingdom.
https://image.digitalinsightresearch.in/uploads/NewsArticle/17375504/main.jpg -
Egypt signs gas deal with Harbour Energy22 June 2026
Egypt’s Ministry of Petroleum & Mineral Resources has signed a new agreement with London-headquartered Harbour Energy.
Under the scope of the agreement, Harbour Energy will drill two new exploration wells and carry out maintenance work for one of the existing wells within the Dsouq-1 development contract.
Harbour Energy committed an initial $6m investment and a $1m signing bonus for the Dsouq concession. Total investment could rise to $18m if commercial discoveries are made.
The signing was witnessed by Egypt’s Minister of Petroleum, Karim Badawi.
He said that his ministry is continuing to implement a package of investment measures and incentives aimed at encouraging partners to increase investments and intensify exploration, development and production activities.
The agreement was signed by Syed Saleem, a member of the executive branch of the state-owned Egyptian Natural Gas Holding Company (EGAS), and Samah Sabry, the executive director of Harbour Energy for the Middle East and North Africa region.
Harbour Energy drilled two new wells in Egypt during the fiscal year 2025/2026, resulting in the addition of reserves estimated at 35 billion cubic feet of gas.
The company aims to drill three new exploration wells during the fiscal year 2026/2027.
Egypt is currently pushing to boost the production of both oil and gas in its territory.
Earlier this month, Egypt’s Ministry of Petroleum & Mineral Resources announced that it had fully settled all outstanding arrears owed to oil and gas companies.
Two years ago, in June 2024, the country owed approximately $6.1bn to partners in the oil and gas sector.
READ THE JUNE 2026 MEED BUSINESS REVIEW – click here to view PDFGCC looks beyond the Strait; Iraq’s reform window narrows as fiscal assumptions shatter; MEED Top 100 companies.
Distributed to senior decision-makers in the region and around the world, the June 2026 edition of MEED Business Review includes:
> AGENDA: Gulf races to reroute trade> EXPORT ROUTES: Regional war boosts oil and gas pipeline project activity> CURRENT AFFAIRS: UAE’s Opec departure fulfils multiple ends> MEED TOP 100: Middle East stocks recover unevenly> LEADERSHIP: Building the infrastructure that makes net zero possible> TRADE DEAL: UK-GCC trade deal talks concludeTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/17374536/main4731.jpg
