AI accelerates UAE power generation projects sector

10 April 2025

 

On 3 April, Abu Dhabi National Energy Company (Taqa) and Emirates Water & Electricity Company (Ewec) confirmed for the first time the UAE capital’s energy infrastructure plans to support its artificial intelligence (AI) and net-zero strategies.

The programme will require an investment of AED36bn ($9.8bn), comprising the round-the-clock 5.2GW solar plus 19 gigawatt-hour battery energy storage system (bess) plants announced in January; a 1GW open-cycle gas turbine plant in Dhafra, which Taqa will own, finance and operate; and advanced grid infrastructure.

This development followed several months of speculations concerning the UAE capital’s plans for a power generation portfolio and infrastructure projects supporting its AI strategy.

It came on the heels of the Abu Dhabi government announcing plans to embark on a three-year digital strategy, requiring the deployment of AED13bn in investment, to make it the “first government globally” to fully integrate AI into its digital services by 2027.

The Abu Dhabi Digital 2025-27 Strategy aims to 100% adopt sovereign cloud computing for government operations and digitise and automate 100% of processes “to streamline procedures, enhance productivity and improve operational efficiency”.

“One thing that strikes me about this Ewec and Taqa announcement is the question of how much of a model it can be for enabling solar with additional gas power, which should be what happens in other countries like in the US,” Karen Young, senior research scholar at Columbia University’s Centre on Global Energy Policy, tells MEED.

Young acknowledges that the ability to scale up with state-owned assets and offtake agreements gives the UAE a capacity that other markets will find difficult to replicate.

“It is certainly an advantage and one reason why the UAE is ahead of other regional markets, including Saudi Arabia, but also on a global scale,” she explains.

Staging an aggressive and energy-intensive AI programme while complying with its net-zero aspirations will keep the UAE’s utility stakeholders on their toes over the coming few years.

Robust capacity buildout

In addition to these three major project blocks, separate thermal, renewable energy and battery energy storage projects are in various construction and procurement stages in Abu Dhabi and Dubai.

Somewhat ironically and similar to Saudi Arabia, the UAE’s main utility stakeholders have stepped into what could be their busiest year in terms of capacity buildout, in order to meet their mid-term 2030 energy diversification targets while supporting the government’s industrial and economic expansion programmes.

According to MEED Projects data, the UAE power sector let an estimated $5.2bn-worth of contracts in 2024, up 70% from the previous full year.

Last year, the UAE awarded four generation contracts representing the full spectrum of fuel, except nuclear. These were the 1.5GW Al-Ajban solar independent power project (IPP), the Dhafra waste-to-energy project, the Ruwais cogeneration and utility package in Abu Dhabi, and the contract to complete the third phase of the Jebel Ali K power station in Dubai.

Expectations that Abu Dhabi Future Energy Company (Masdar) will sign the engineering, procurement and construction (EPC) contracts for the estimated $6bn round-the-clock solar plus battery facility this year, in addition to the 1GW Dhafra open-cycle gas turbine (OCGT) project, for which a contract was already awarded in April, guarantee that contract awards in the UAE’s power projects sector will further accelerate.

Upcoming projects

According to MEED Projects data, as of early April, an estimated $7.2bn-worth of generation and $1bn of transmission and distribution contracts were in the bid and bid evaluation stages across the UAE.

These include six major generation projects in Abu Dhabi that are expected to be awarded this year. These are the 2.5GW Taweelah C combined-cycle gas turbine scheme, Madinat Zayed OCGT IPP, Al-Khazna and Al-Zarraf solar photovoltaic (PV), Al-Sila wind and Bess 1.

The prequalification proceedings are under way for generation projects worth $7.2bn and transmission projects worth $180m.

The 3.3GW Al-Nouf combined-cycle gas turbine (CCGT) scheme in Abu Dhabi and phase seven of Dubai’s Mohammed Bin Rashid Solar Park are the main projects in the prequalification stage.

Last year, there were indications that Abu Dhabi could start initiating the procurement process for the next phase of the Barakah nuclear power plant this year. However, more recent developments indicate that this process could be delayed by a year or two, depending on multiple factors, including demand growth and costs.

Including the next phase of Barakah in the upcoming projects pipeline takes the estimated total value of planned and unawarded generation projects in the UAE to roughly $47bn.

Battery

The deployment of substantial battery energy storage capacity is crucial in ensuring grid flexibility as the UAE’s electricity grids take on an increasing amount of renewable power.

Ewec received two bids for the contract to develop Bess 1, which will be built in two locations with a total capacity of 400MW.

The project will closely follow Abu Dhabi’s IPP model, in which developers enter into a long-term energy storage agreement with Ewec as the sole procurer.

The first plant will be in Al-Bihouth, about 45 kilometres (km) southwest of Abu Dhabi, and the second plant will be in Madinat Zayed, about 160km southwest of the city.

According to industry sources, the companies that submitted bids for the contract in March include:

  • EDF Renewables (France)
  • Engie (France) / Saudi Electricity Company (SEC, Saudi Arabia) / Hajj Abdullah Alireza Company (Haaco, Saudi Arabia)
  • Jinko Power (China) / Alghanim International (Kuwait)

In Dubai, the prequalification process is under way for the seventh phase of the MBR Solar Park, which will include a solar PV plant with a capacity of 1.6GW and a 1GW bess plant intended to produce six hours of storage capacity.

The $6bn round-the-clock solar plus bess project in Abu Dhabi boasts 19GWh of battery storage capacity, which is envisaged to enable renewable power to be dispatched similar to a baseload capacity, which gas or nuclear plants typically supply.

Fittingly, the UAE’s Minister of Industry and Advanced Technology Sultan Al-Jaber described the project as Abu Dhabi’s response to the “moonshot challenge of our time”, which is the intermittency of renewables.

Masdar has already selected the preferred EPC, solar PV and battery technology subcontractors for the project.

India’s Larsen & Toubro and Beijing-headquartered PowerChina will undertake the project’s EPC contracts, while Shanghai-based Jinko Solar and Beijing-headquartered JA Solar will supply solar PV modules. 

Another Chinese firm, Fujian-based Contemporary Amperex Technology Company), will supply its Tener product line for the bess plant.

The project will be structured as a classic public-private partnership (PPP), funded by equity and syndicated debt.

It is being deployed on a fast-track basis, with financial close expected by the second quarter of this year and commercial operations set for 2027.

https://image.digitalinsightresearch.in/uploads/NewsArticle/13655568/main.jpg
Jennifer Aguinaldo
Related Articles
  • Saudi Arabia battery storage awards provide fresh lift

    24 August 2026

    Commentary
    Mark Dowdall
    Power & water editor

    The latest battery storage awards provide a welcome injection of investment into Saudi Arabia’s power market, which has seen a sharp slowdown in contract awards this year.

    Saudi Power Procurement Company’s four Group 1 storage service agreements, announced last week, are worth more than $1.16bn and cover 2,000MW of capacity.

    That is significant against the wider market. According to regional project tracker MEED Projects, Saudi Arabia recorded $19.7bn in power sector contract awards in the first seven months of 2025, compared with just $2.5bn in new awards in the same period this year.

    The battery energy storage system (bess) awards therefore account for a sizeable share of the activity recorded so far this year and provide a much-needed source of new contracting activity.

    Importantly, this is not a one-off. SPPC issued the request for proposal (RFP) for its second group of bess projects in July, covering six projects with a combined capacity of 3,000MW and 12,000MWh.

    With the Group 1 tender taking around 18 months from RFP to contract award, it is reasonable to expect Group 2 contracts to be signed in 2027.

    At the same time, the awards for six independent renewable plants under Round 7 of Saudi Arabia’s National Renewable Energy Programme (NREP), with a combined capacity of 5,300MW, are also likely to move into next year, with the latest bid deadlines now extending into September.

    Although a substantial pipeline remains in procurement, it is only once these projects move from tender to award and into construction that this pipeline translates into market activity.

    It is important that these tenders continue to progress at the pace established by the early rounds of Saudi Arabia’s renewable energy programme and now also SPPC’s independent storage provider bess scheme.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/18962923/main.jpg
    Mark Dowdall
  • Qatar receives bids for major power grid expansion

    24 August 2026

     

    Qatar General Electricity & Water Corporation (Kahramaa) has received bids for several packages under a major power transmission expansion project tendered in April.

    The project covers new substations at multiple voltage levels, as well as the supply and installation of 400kV extra-high-voltage power cables. The overall scheme is estimated to cost $650m.

    It is being tendered as part of Kahramaa’s 2026 procurement plan, which includes 198 tenders with a total estimated value of QR21.4bn ($5.9bn).

    According to sources, bids were submitted for the following packages on 20 August:

    • Substation packages S1 and S2, covering new 132/11kV substations (estimated cost: $200m)
    • Package S3, covering new 66/11kV substations ($50m)
    • Package S4, including a new 400/220/132kV substation, as well as upgrades and modifications to existing 400kV and 220kV substations ($200m)
    • Package S5, covering new 132/11kV substations and upgrades to existing 132kV and 66kV substations ($100m)
    • Cable packages C1 and C2, covering 400kV cables ($100m)

    Kahramaa previously stated that foreign companies not registered in Qatar would be allowed to participate in the bidding, subject to meeting specified conditions, including registration and certification requirements.

    In June, the electricity and water utility awarded contracts worth more than QR2.2bn ($604m) to expand the electricity transmission network in the country’s western region.

    The engineering, procurement and construction (EPC) works will support the integration of the 2GW Dukhan solar power project into Qatar’s national electricity grid. The scope includes new and upgraded substations, as well as the installation of underground cables and overhead transmission lines.

    Kahramaa said contracts were awarded to local firm Voltage Engineering, Turkiye’s Best & Betas Consortium, India’s Larsen & Toubro and South Korea’s LS Cable.

    Of Kahramaa’s 2026 procurement plan, electricity transmission projects account for QR8.9bn ($2.4bn) and include the construction of new 400/132kV substations in Al-Wukair and Al-Mashaf, as well as the expansion of 400kV substations at Ras Laffan.

    These also cover the installation of 132kV underground cables between Al-Sailiya and Al-Rayyan over a 24-kilometre route, as well as upgrades to the 400kV and 220kV networks.

    Additionally, there are 64 planned electricity distribution projects managed by the Electricity Distribution Department that cover the medium-voltage and low-voltage networks throughout Doha and the regional municipalities. 

    https://image.digitalinsightresearch.in/uploads/NewsArticle/18962223/main.jpg
    Mark Dowdall
  • Maaden closes $1bn term loan and credit facility

    24 August 2026

    Saudi Arabian Mining Company (Maaden) has announced the closing of its inaugural international syndicated term loan and revolving credit facilities, worth a total of $1bn.

    The $500m international term loan facility will support Maaden’s growth agenda and general corporate purposes, including funding growth projects across its portfolio.

    The $500m international revolving credit facility, which is expected to remain undrawn, provides additional committed funding capacity “as Maaden continues to scale its business and execute its long-term growth strategy”.

    The transaction “was met with strong support from the international banking market, attracting participation from a diverse group of leading international banks across key global financial markets”, including the US, Canada, Europe, China and Japan. The facilities were oversubscribed, Maaden said.

    ALSO READ: Maaden and Aramco sign deal to create joint venture

    “The level of demand reflects the global banking community’s confidence in Maaden’s financial strength, strategic direction and ambitious growth plans,” the Saudi state miner said in its statement.

    “The facilities mark another significant milestone in Maaden’s funding journey – further diversifying its sources of funding and broadening its access to global capital providers as the company continues to advance its long-term growth ambitions.

    “Maaden continues to make significant progress across its growth pipeline, expanding production, advancing major projects and accelerating exploration as it builds a world-class mining company at the heart of Saudi Arabia’s economic transformation.”

    https://image.digitalinsightresearch.in/uploads/NewsArticle/18962086/main4516.jpg
    Indrajit Sen
  • Dubai inflation slows to 5.3% in July

    24 August 2026

    Dubai’s annual inflation rate slowed to 5.3% in July, down from 5.7% in June, as a decline in transport costs eased pressure on consumer prices, according to Emirates NBD.

    The bank said the slowdown supported its view that price growth peaked at mid-year, and it expects inflation to continue easing through the rest of 2026. Monthly price growth slowed to 0.1% in July, from 0.4% in June, the weakest pace since February.

    Transport was the clearest sign of the moderation. Annual price growth in the category slowed to 11.9% in July, from 18.1% in June, as transport costs fell 3.7% over the month. Fuel and lubricant inflation eased to 24.1% year on year, from 48.3%, tracking a decline in local petrol prices.

    Petrol remains the main swing factor in the emirate’s inflation. Transport contributed 1.1 percentage points to headline inflation in July, down from 1.7 percentage points in June. Emirates NBD said the relief may prove temporary, with Super 98 petrol prices climbing 5.9% in August to leave them 33.8% higher than a year earlier. The bank expects headline inflation to edge higher in the August figures before easing again later in the year.

    The UAE deregulated petrol and diesel prices in 2015 and reviews them monthly against global prices, meaning changes in global fuel costs pass through to consumers quickly. Transport, which includes fuel, accounts for 9% of Dubai’s consumer price index basket.

    Housing remained the largest contributor to inflation even as its impulse faded. Housing and utilities, which account for about two-fifths of the basket, added 2.8 percentage points to headline inflation. Annual price growth in the category slowed to 7.0%, from 7.4% in January.

    Food inflation edged up to 7.8% year on year, from 7.6% in June, which the bank attributed to lingering supply-chain disruption from the regional conflict. Inflation in restaurants and hotels accelerated to 4.5% year on year, from 1.7% in June.

    Emirates NBD forecasts inflation of 2.9% by year-end but said risks to that projection were tilted to the upside, given lingering pressures in food and housing.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/18961735/main1839.jpg
    Colin Foreman
  • Libya oil project on track for 2027 completion

    24 August 2026

     

    The project to develop a workers’ camp at Libya’s Erawin oil field is on track for completion next year, according to industry sources.

    The project, estimated to be worth about $50m, is being executed by the Libyan oil services company Al-Saraya Al-Hamara, headquartered in the city of Sebha.

    The Libyan company was awarded the contract in February 2025.

    The scope of the project includes:

    • Construction of an accommodation camp
    • Construction of the camp maintenance warehouse
    • Construction of the camp office
    • Construction of a fire brigade shelter
    • Construction of a kitchen and mess hall
    • Construction of a mosque
    • Construction of a laundry room
    • Construction of a clinic
    • Construction of parking facilities
    • Installation of a fire and gas system
    • Installation of a power generator
    • Construction of associated facilities

    The client on the project is Zallaf Libya Oil & Gas Exploration & Production Company.

    Zallaf Libya Oil & Gas Exploration & Production Company was established in Libya in 2013 and is wholly owned by Libya’s state-owned National Oil Corporation.

    The Erawin field development project is located about 800 kilometres south of Tripoli and 100km southwest of the El-Sharara field.

    Libya shipped its first cargo of crude from the Erawin oil field in November 2023.

    The shipment departed from Libya’s Zawiyah port and consisted of 600,000 barrels of crude.

    Australia-based Worley Parsons was appointed as the front-end engineering and design (feed) contractor for the early production facility project in 2019.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/18953632/main.jpg
    Wil Crisp