Adnoc spurs downstream gas expansions
13 October 2023
This package on the UAE’s downstream sector also includes:
> Adnoc Gas picks site for planned LNG terminal
> Adnoc Gas receives prices for Estidama package
> Adnoc and Dusup sign key gas supply agreement
> Adnoc receives bids for gas pipeline packages
> Adnoc receives prices for sales gas pipeline packages
> Adnoc Gas awards $3.6bn Project Meram contract
Demand for natural gas has risen exponentially in this decade, with its share in the global energy mix set to grow further in the decades to come.
Regional energy producers are deploying major capital expenditure programmes to increase their gas production and processing capabilities to cater to growing demand.
The UAE is striving to achieve self-sufficiency in gas production by 2030. With this objective in mind, Abu Dhabi National Oil Company (Adnoc) has committed significant investment towards expanding its midstream and downstream gas capabilities.
These projects seek to increase the availability of gas for utility providers and industrial customers in the UAE and ramp up ethane output to grow the country’s petrochemical sector and its derivatives ecosystem.
Hail and Ghasha galvanises UAE upstream market
Ruwais LNG project
Adnoc Gas, the gas processing business of Adnoc, has finalised the location for its planned liquefied natural gas (LNG) export terminal. The facility will have the capacity to produce about 9.6 million tonnes a year (t/y) of LNG from two processing trains, each with a capacity of 4.8 million t/y.
The overall value of the planned project is estimated to be upwards of $4.5bn, based on capital expenditure by operators on similar schemes worldwide.
Adnoc Gas received technical bids from contractors in May for the engineering, procurement and construction (EPC) works on the project, which will be built in Ruwais Industrial City in Abu Dhabi’s Al-Dhafrah region.
Adnoc Gas had originally planned to build the LNG terminal in the UAE emirate of Fujairah, which sits outside the Strait of Hormuz on the coast of the Gulf of Oman. In early May, however, the company announced it was shifting the location of the project from Fujairah to Ruwais, Abu Dhabi.
Sales gas pipeline network
Adnoc Gas is progressing the Estidama project, which is crucial to enhancing Adnoc’s sales gas pipeline network across the UAE. The project aims to cater to rising demand for gas from industrial consumers across the UAE, particularly in the Northern Emirates.
Contractors submitted commercial bids in August for combined package numbers 4 and 7. The combined package involves laying a new pipeline from the Al-Shuwaib pig launcher and pig receiver station to the Sajaa gas facility in Sharjah.
The scope also covers building a new gas pipeline between BVS-2/KP28.7 in Abu Dhabi to Dubai’s Margham gas facility to meet increased gas demand from Adnoc Gas’ customer Dubai Supply Authority (Dusup).
EPC works on the estimated $2bn-plus Estidama project have been divided into seven packages. Abu Dhabi-based contractor Integrated Specialised General Contracting Company (Iscco) won package 1, understood to have a contract value of $18m, in December 2021.
In early July, Adnoc Gas awarded contracts worth a combined $1.34bn for two other packages of the Estidama project. UK-headquartered Petrofac was awarded the EPC contract for package 2 of the Estidama project, estimated to be worth $720m.
A consortium of Abu Dhabi’s National Petroleum Construction Company (NPCC) and Lebanon-headquartered CAT Group won Estidama package 3, which is valued at about $630m.
Contractors submitted technical bids for package 6 in August 2022 and commercial bids by 21 November. Work on package 6 entails the installation of a 52-inch, 74-kilometre pipeline from Sweihan to Al-Shuwaib in Abu Dhabi and building two block valve stations.
Package 5 is expected to be tendered separately to contractors as part of a planned second phase of the sales gas pipeline upgrade project.
As per the original project schedule, EPC works on the Estidama project are due to be completed in 2025.
Ramping up ethane output
Adnoc Gas is in charge of one of the world’s largest gas processing complexes in Abu Dhabi, with the capacity to process about 8 billion cubic feet a day from its Asab, Bab, Bu Hasa, Habshan and Ruwais plants.
Increased volumes of ethane production will allow the company to commercialise it to supply feedstock to Borouge for its under-construction Borouge 4 petrochemicals complex, as well as to derivatives plants in the upcoming Taziz complex. Adnoc Gas intends to achieve this through the Maximise Ethane Recovery & Monetisation (Meram) project.
Adnoc Gas awarded a $3.6bn contract for Project Meram to a consortium of NPCC and Spanish contractor Tecnicas Reunidas in early August, with EPC work on the project starting later that month. The scope of work on the contract includes commissioning new gas processing facilities to enable an optimised supply to the Ruwais industrial complex, Adnoc Group said.
The strategic Meram project aims to achieve dual objectives, Adnoc stated.
The first goal is to increase ethane extraction by 35 to 40 per cent from Adnoc Gas’ existing onshore facilities in the Habshan gas processing complex by constructing new gas processing facilities.
The second goal is to unlock further value from existing feedstock and deliver it to Ruwais via a 120km natural gas liquids (NGL) pipeline.
LATEST NEWS FROM THE UAE's CHEMICALS SECTOR:
> Lummus seeks to expand Abu Dhabi office
> Firms express interest for Abu Dhabi methanol project
> Borouge and Borealis launch recycled products range
> Fertiglobe makes $84m profit in second quarter
> Borouge announces $231m profit in second quarter
> Adnoc opens formal chemicals integration talks with OMV
Taziz chemicals complex
Meanwhile, investors in the Taziz petrochemicals derivatives-producing industrial complex in Ruwais are pushing ahead with their projects.
Taziz – a 60:40 joint venture (JV) of Adnoc and Abu Dhabi’s industrial holding company ADQ – is overseeing the development of the sprawling industrial complex, which will mainly draw ethylene feedstock from the Borouge 4 facility to produce several in-demand chemicals.
A JV of UAE-based Fertiglobe, South Korea’s GS Energy and Japanese investment firm Mitsui awarded Italian contractor Tecnimont the main EPC contract for its planned blue ammonia project in the Taziz Industrial Chemicals Zone in February.
The JV has appointed KBR to provide the technology licence, basic engineering design, proprietary equipment and catalyst for the low-carbon ammonia plant, which will have a capacity of 1 million t/y.
India’s Reliance Industries is also an investor in the Taziz complex, having forged a partnership with Taziz and Abu Dhabi-based Shaheen Chem Holdings Investment to invest $2bn in developing three chemical plants producing chlor-alkali (940,000 t/y), ethylene dichloride (1.1 million t/y) and polyvinyl chloride (360,000 t/y).
Switzerland-based Proman has committed to building the UAE’s first methanol plant at Taziz, with a planned production capacity of 1.8 million t/y. The Proman-Taziz JV completed the contractor prequalification process for the EPC tendering round for the methanol production project in August. The operator is expected to issue the main EPC tender later this year.
As projects in the first phase of the chemicals complex move forward, Taziz is also understood to be gearing up for a second phase to more than double the number of chemicals produced at the derivatives hub.
Exclusive from Meed
-
Emaar appoints contractor for Dubai Creek Harbour tower
22 August 2025
-
Kuwait to meet with UN for oil project approvals
22 August 2025
-
Frontrunner emerges for Dorra gas project offshore package
21 August 2025
-
Project manager confirmed for Riyadh Metro Line 2 extension
21 August 2025
-
Turner & Townsend to manage Abu Dhabi plant decommissioning
20 August 2025
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends

Related Articles
-
Emaar appoints contractor for Dubai Creek Harbour tower
22 August 2025
Register for MEED’s 14-day trial access
UAE firm Engineering Contracting Company has won a contract to build the Palace Residences Creek Blue residential development at Dubai Creek Harbour.
The 50-storey tower is located in the second phase of the development's Bridge District and covers an area of over 98,000 square metres.
The contract was awarded by Dubai-based real estate developer Emaar Properties.
Dubai-headquartered Mirage is the project consultant.
Construction work has started, with local firm Dutch Foundation carrying out the enabling works.
The project is scheduled for completion by 2028.
In March, MEED reported that Emaar Properties was set to relaunch its efforts to build Dubai Creek Tower – which was once touted to become the world’s tallest tower – along with a mall in Dubai’s Creek Harbour area.
According to local media reports, the firm has earmarked a budget of about AED14bn ($3.81bn) to develop both projects.
The developments are fundamental to Emaar’s plans to spend about AED65bn ($18bn) over the next five years.
Dubai’s heightened real estate activity has led to record-breaking announcements from several UAE-based real estate firms.
In February, Emaar reported a total revenue of AED19.1bn ($5.2bn) in 2024, a 61% increase from 2023. It said it recorded a net profit before tax of about AED10.2bn ($2.8bn), a 20% rise compared to 2023.
According to a report published by Emirates News Agency (Wam) earlier this year, the total value of real estate transactions reached AED893bn, with over 331,300 transactions recorded in the UAE last year.
UK analytics firm GlobalData forecasts that the UAE construction industry will register an annual growth of 3.9% in 2025-27, supported by investments in infrastructure, renewable energy, oil and gas, housing, industrial and tourism projects.
https://image.digitalinsightresearch.in/uploads/NewsArticle/14521666/main.png -
Kuwait to meet with UN for oil project approvals
22 August 2025
Register for MEED’s 14-day trial access
State-owned upstream operator Kuwait Oil Company (KOC) has scheduled a meeting with the UN in the second week of September as it seeks approvals to extend two oil remediation projects.
The contractors involved will be given an additional volume of polluted soil to clean and an extra 18 months in which to complete processing, according to industry sources.
The two Kuwait-based contractors that have been provisionally awarded contract extensions are Khalid Ali Al-Kharafi & Brothers Company and Heisco.
The contract extensions are each worth about $30m and have already been approved by KOC.
They also need approval from the UN as the project is being funded through money that was awarded to Kuwait by the UN Compensation Commission (UNCC) to allow Kuwait to address ecological damage resulting from the 1990-91 Gulf War.
The contract extensions are for contracts that were awarded though the Kuwait Environmental Remediation Programme (Kerp) in 2021.
Kerp is the world’s biggest project to clean up oil pollution.
More than 30 years after the UNCC was created to ensure restitution for Kuwait following the Iraqi invasion of 1990, the reparations body announced in February 2022 that it had processed its final claim, amounting to $52.4bn in total.
Kerp itself is understood to be deploying about $3.5bn of the reparation funds, cleaning up the damage caused by oil spills related to the war.
The project to clean up all of the crude that was spilled as a result of the war stalled for decades due to the unique challenges that the clean-up project poses, but in recent years there has been a surge in activity, with major tenders and contract awards.
The project has been divided into three main project areas, which are known as North Kuwait Excavation Transportation Remediation (NKETR), South Kuwait Excavation Transportation Remediation (SKETR) and South Kuwait Excavation Transportation Remediation 2 (SKETR-2).
The original contracts that were awarded to Khalid Ali Al-Kharafi & Brothers Company and Heisco were:
- NKETR A – Sabria: Kharafi (Kuwait)/Lamor (Finland) – $194m
- SKETR A – Greater Burgan: Kharafi/Lamor – $197m
- SKETR B – Greater Burgan: Heisco (Kuwait) / Zaopin Hangzhou (China) – $185m
The extensions are being added to existing contracts after additional volumes of polluted soil were discovered by Kuwait last year.
In October 2024, MEED revealed that KOC had discovered an extra 5 million tons of contaminated soil.
https://image.digitalinsightresearch.in/uploads/NewsArticle/14519954/main.jpg -
Frontrunner emerges for Dorra gas project offshore package
21 August 2025
Based on an initial evaluation of bids by Al-Khafji Joint Operations (KJO), a frontrunner to win the main contract for an offshore engineering, procurement and construction (EPC) package of the Dorra gas field facilities project has emerged.
KJO has divided the scope of work on the project into four EPC packages – three offshore and one onshore.
The scope of work on offshore package one covers the EPC of seven offshore jackets and laying of intra-field lines.
Contractors submitted bids for the first offshore package by a deadline of 2 June, it was previously reported.
Indian contractor Larsen & Toubro Energy Hydrocarbon (L&TEH) has pulled ahead in the race to win the contract for package one of the Dorra project, according to sources.
L&TEH has emerged as the favourite based on “early bid evaluation”, and the situation could change “in the coming days” as KJO engages in further discussions and negotiations with the bidders, one source said.
KJO is expected to select a contractor for the package by the end of August, another source said.
The following contractors are understood to be among those bidding for the three offshore packages of the Dorra gas field offshore and onshore facilities project:
- Lamprell (Saudi Arabia/UAE)
- Larsen & Toubro Energy Hydrocarbon (India)
- McDermott (US)
- NMDC Energy (UAE)
- Saipem (Italy)
MEED reported in March that KJO was pushing forward with a major project to produce gas from the Dorra offshore field, located in Gulf waters in the Neutral Zone shared by Saudi Arabia and Kuwait.
Contractors are currently working towards a bid submission deadline of 15 September for the project's other three EPC packages, offshore packages 2A and 2B and onshore package three, according to sources.
The previous bid submission deadlines for the three packages were 30 June, 31 July and 25 August.
The EPC scope of work on the packages of the Dorra gas field offshore and onshore facilities project is as follows:
Package 2A – Dorra gas field wellhead topsides, flowlines and umbilicals
- Seven gas wellhead platforms or topsides, with production routed to the central gathering platform
- Corrosion-resistant, alloy-lined intra-field flowlines and umbilicals connecting the gas wellhead platforms to the central gathering platform and the auxiliary platform
Package 2B: Dorra central gathering platform complex, export pipelines and cables
- Central gathering platform
- Auxiliary platform
- Dorra accommodation platform
- Flare platform
- Bridge platform
- Pipelines for gas and condensate transmission to each shareholder
- Produced water pipeline from the central gathering platform to Al-Khafji field and from the planned onshore processing facility next to the Al-Zour refinery in Kuwait to Al-Khafji field
- Recovered monoethylene glycol (MEG) pipeline from Al-Khafji field to the central gathering platform
- Control and power system linking Al-Khafji onshore facilities to offshore units
- Offshore central control room at Dorra accommodation platform
Package 3: Onshore gas processing facilities
- Buildings to be constructed as part of KJO’s Dorra project onshore package include:
- Dorra control building
- Operator building
- Operations, maintenance and engineering building
- Process interface building
- Onshore 115/69kV substation
- Two gas insulated substations
- Warehouse
- Maintenance building
- Mosque
- Telecommunications tower radio building
- Beach valve substation at the planned onshore processing facility next to the Al-Zour refinery in Kuwait
- Processing facilities for KJO's onshore package:
- Produced water receiving and treatment
- Sour water stripping and treated water system
- Rich MEG storage tank
- MEG regeneration and reclamation
- Recovered hydrocarbons system
- Lean MEG storage and supply
- Fresh MEG storage and supply
- Beach valve stations at Al-Khafji and Al-Zour
- Utilities:
- Instrument and plant air system
- Nitrogen generation system
- Diesel storage and distribution system
- Fuel gas system
- Closed drain and slop tank system
- Hazardous area open drains system
- Industrial water system
- Drinking water system
- Flare gas recovery system and a low-pressure flare system
- Fire water system
- Emergency diesel generator
- Sewage treatment
The Dorra field is estimated to hold 20 trillion cubic metres of gas and 310 million barrels of oil.
Kuwait and Saudi Arabia have been working together to develop the offshore field since it was discovered in 1965. The two sides expect to produce about 1 billion cubic feet a day of gas from the asset and have agreed to split the gas output equally.
A geopolitical tussle over ownership of the asset has hampered progress.
Iran, which calls the field Arash, claims that it partially extends into its territory and that Tehran should be a stakeholder in any development project.
Kuwait and Saudi Arabia maintain that the Dorra field lies entirely in the waters of their shared territory, known as the Neutral Zone or Divided Zone, and that Iran has no legal basis for its claim.
In February 2024, Kuwait and Saudi Arabia reiterated their claim to the Dorra field in a joint statement issued during an official meeting in Riyadh between Kuwaiti Emir Sheikh Mishal Al-Ahmad Al-Jaber Al-Sabah and Saudi Crown Prince and Prime Minister Mohammed Bin Salman Bin Abdulaziz Al-Saud.
KJO, which is jointly owned by Saudi Aramco subsidiary Aramco Gulf Operations Company and Kuwait Gulf Oil Company, a subsidiary of state-owned Kuwait Petroleum Corporation (KPC), is understood to have issued the tenders for the project in August 2024.
MEED reported in September 2023 that Aramco and KPC had selected France’s Technip Energies to carry out front-end engineering and design (feed) and pre-feed work on the Dorra offshore field development project.
The original feed work for a project to develop the field was performed more than a decade ago. However, due to changes in technology, the engineering design needed to be updated before the project could reach a final investment decision.
ALSO READ: Saudi Arabia and Kuwait announce Neutral Zone oil discovery
https://image.digitalinsightresearch.in/uploads/NewsArticle/14513682/main.jpg -
Project manager confirmed for Riyadh Metro Line 2 extension
21 August 2025
Register for MEED’s 14-day trial access
Riyadh Metro Transit Consultants (RMTC), a joint venture of US-based Parsons and French engineering firms Egis and Systra, has been confirmed as the project management and construction supervision consultant for the recently awarded Riyadh Metro Line 2 extension.
RMTC previously served as the project management and construction supervision consultant for lines one, two and three of the Riyadh Metro scheme.
The Line 2 extension is 8.4 kilometres (km) long, of which 1.3km is elevated and 7.1km is underground. It includes five stations – two elevated and three underground.
The extension will run from the current Line 2 terminus at King Saud University (KSU), continuing to new stations at KSU Medical City, KSU West, Diriyah East, Diriyah Central – where it will interchange with the planned Line 7 – and finally Diriyah South.
In July, MEED exclusively reported that Saudi Arabia’s Royal Commission for Riyadh City (RCRC) had awarded an estimated $800m–$900m contract for the next phase of the Riyadh Metro project.
The contract was awarded to the Arriyadh New Mobility Consortium.
According to the consortium’s official website, its members include Italy’s Webuild, India’s Larsen & Toubro, Saudi firm Nesma & Partners, Japan’s Hitachi, Italy’s Ansaldo STS, Canada’s Bombardier, Spain’s Idom and Australia’s WorleyParsons.
In 2013, the Arriyadh New Mobility Consortium secured the Line 3 contract for $5.21bn.
Line 3, also known as the Orange Line, runs east to west from Jeddah Road to the Second Eastern Ring Road, covering 41km.
Riyadh Metro
Riyadh Metro’s first phase features six lines with 84 stations.
The RCRC completed the phased rollout of the Riyadh Metro network with the launch of the Orange Line on 5 January.
In December last year, the RCRC started operating the Red Line and Green Line.
The Red Line, also known as Line 2, stretches 25.1km from the east of Riyadh to the west, via King Abdullah Road, connecting King Fahd Sports City and King Saud University. It has a total of 15 stations.
The Green Line, also known as Line 5, extends 13.3km from King Abdullah Road to the National Museum. With 12 stations, it serves several ministries and government agencies, including the Defence Ministry, the Finance Ministry and the Commerce Ministry, as well as other areas.
In December, the RCRC started operating the Blue Line (Line 1), Yellow Line (Line 4) and Purple Line (Line 6).
The Blue Line connects Olaya Street to Batha; the Yellow Line runs along King Khalid International Airport Road; while the Purple Line connects Abdul Rahman Bin Awf Road with Al-Sheikh Hassan Bin Hussain Road.
King Salman Bin Abdulaziz Al-Saud inaugurated the Riyadh Metro on 27 November last year.
The network spans 176km. Four of the stations have been designed by signature architects.
The metro is part of the Riyadh Public Transport Project, which encompasses metro and bus systems. The project aims to relieve traffic congestion.
The $23bn project was scheduled to open in 2018, but construction activity slowed due to disputes over prolongation and the disruption caused by the Covid-19 pandemic.
The RCRC awarded the main construction packages for the scheme on 28 July 2013.
In November 2022, the RCRC struck a deal with three contracting consortiums working on the Riyadh Metro scheme regarding the completion of the project’s remaining works.
The Fast consortium won lines 4, 5 and 6, reportedly valued at $7.82bn. The Bacs consortium was awarded lines 1 and 2 for $9.45bn, while Arriyadh New Mobility secured Line 3 for $5.21bn.
US firm Bechtel leads the Bacs consortium. Italian firm Ansaldo STS is the leader of the Arriyadh New Mobility group, and Spanish firm FCC Construccion heads the Fast consortium.
AtkinsRealis has delivered programme management and supervision services for the operations and maintenance of the Riyadh Metro scheme.
https://image.digitalinsightresearch.in/uploads/NewsArticle/14512676/main.jpg -
Turner & Townsend to manage Abu Dhabi plant decommissioning
20 August 2025
Register for MEED’s 14-day trial access
Turner & Townsend has been appointed by Taqa Transmission to provide programme management consultancy services for the retirement of a power-generating plant in Abu Dhabi.
The existing plant, located in the east of Abu Dhabi, has a capacity of 1,640MW and 1,200 megavolt-amperes reactive (MVAr), and is scheduled for decommissioning in 2029. An upgraded, energy-efficient plant will be developed in its place, with a focus on integrating solar and nuclear power into the network to support decarbonisation.
Turner & Townsend said in a statemet that it will establish a programme management office and provide strategic support to expand and facilitate the upgrade of the region’s power transmission and distribution infrastructure.
This work will enable the construction of new grid and switching stations and substations, cable corridors and cable works, capacitor banks and high-voltage overhead lines.
Earlier this month, the UK-based firm announced its appointment to provide project and cost management services for a hyperscale data centre project in Dubai.
The facility is being developed by Dubai-based Emirates Integrated Telecommunications Company (Du) on a 20,000-square-metre site in the emirate.
https://image.digitalinsightresearch.in/uploads/NewsArticle/14504637/main1637.jpg