Adnoc spurs downstream gas expansions
13 October 2023
This package on the UAE’s downstream sector also includes:
> Adnoc Gas picks site for planned LNG terminal
> Adnoc Gas receives prices for Estidama package
> Adnoc and Dusup sign key gas supply agreement
> Adnoc receives bids for gas pipeline packages
> Adnoc receives prices for sales gas pipeline packages
> Adnoc Gas awards $3.6bn Project Meram contract

Demand for natural gas has risen exponentially in this decade, with its share in the global energy mix set to grow further in the decades to come.
Regional energy producers are deploying major capital expenditure programmes to increase their gas production and processing capabilities to cater to growing demand.
The UAE is striving to achieve self-sufficiency in gas production by 2030. With this objective in mind, Abu Dhabi National Oil Company (Adnoc) has committed significant investment towards expanding its midstream and downstream gas capabilities.
These projects seek to increase the availability of gas for utility providers and industrial customers in the UAE and ramp up ethane output to grow the country’s petrochemical sector and its derivatives ecosystem.
Hail and Ghasha galvanises UAE upstream market
Ruwais LNG project
Adnoc Gas, the gas processing business of Adnoc, has finalised the location for its planned liquefied natural gas (LNG) export terminal. The facility will have the capacity to produce about 9.6 million tonnes a year (t/y) of LNG from two processing trains, each with a capacity of 4.8 million t/y.
The overall value of the planned project is estimated to be upwards of $4.5bn, based on capital expenditure by operators on similar schemes worldwide.
Adnoc Gas received technical bids from contractors in May for the engineering, procurement and construction (EPC) works on the project, which will be built in Ruwais Industrial City in Abu Dhabi’s Al-Dhafrah region.
Adnoc Gas had originally planned to build the LNG terminal in the UAE emirate of Fujairah, which sits outside the Strait of Hormuz on the coast of the Gulf of Oman. In early May, however, the company announced it was shifting the location of the project from Fujairah to Ruwais, Abu Dhabi.
Sales gas pipeline network
Adnoc Gas is progressing the Estidama project, which is crucial to enhancing Adnoc’s sales gas pipeline network across the UAE. The project aims to cater to rising demand for gas from industrial consumers across the UAE, particularly in the Northern Emirates.
Contractors submitted commercial bids in August for combined package numbers 4 and 7. The combined package involves laying a new pipeline from the Al-Shuwaib pig launcher and pig receiver station to the Sajaa gas facility in Sharjah.
The scope also covers building a new gas pipeline between BVS-2/KP28.7 in Abu Dhabi to Dubai’s Margham gas facility to meet increased gas demand from Adnoc Gas’ customer Dubai Supply Authority (Dusup).
EPC works on the estimated $2bn-plus Estidama project have been divided into seven packages. Abu Dhabi-based contractor Integrated Specialised General Contracting Company (Iscco) won package 1, understood to have a contract value of $18m, in December 2021.
In early July, Adnoc Gas awarded contracts worth a combined $1.34bn for two other packages of the Estidama project. UK-headquartered Petrofac was awarded the EPC contract for package 2 of the Estidama project, estimated to be worth $720m.
A consortium of Abu Dhabi’s National Petroleum Construction Company (NPCC) and Lebanon-headquartered CAT Group won Estidama package 3, which is valued at about $630m.
Contractors submitted technical bids for package 6 in August 2022 and commercial bids by 21 November. Work on package 6 entails the installation of a 52-inch, 74-kilometre pipeline from Sweihan to Al-Shuwaib in Abu Dhabi and building two block valve stations.
Package 5 is expected to be tendered separately to contractors as part of a planned second phase of the sales gas pipeline upgrade project.
As per the original project schedule, EPC works on the Estidama project are due to be completed in 2025.
Ramping up ethane output
Adnoc Gas is in charge of one of the world’s largest gas processing complexes in Abu Dhabi, with the capacity to process about 8 billion cubic feet a day from its Asab, Bab, Bu Hasa, Habshan and Ruwais plants.
Increased volumes of ethane production will allow the company to commercialise it to supply feedstock to Borouge for its under-construction Borouge 4 petrochemicals complex, as well as to derivatives plants in the upcoming Taziz complex. Adnoc Gas intends to achieve this through the Maximise Ethane Recovery & Monetisation (Meram) project.
Adnoc Gas awarded a $3.6bn contract for Project Meram to a consortium of NPCC and Spanish contractor Tecnicas Reunidas in early August, with EPC work on the project starting later that month. The scope of work on the contract includes commissioning new gas processing facilities to enable an optimised supply to the Ruwais industrial complex, Adnoc Group said.
The strategic Meram project aims to achieve dual objectives, Adnoc stated.
The first goal is to increase ethane extraction by 35 to 40 per cent from Adnoc Gas’ existing onshore facilities in the Habshan gas processing complex by constructing new gas processing facilities.
The second goal is to unlock further value from existing feedstock and deliver it to Ruwais via a 120km natural gas liquids (NGL) pipeline.
LATEST NEWS FROM THE UAE's CHEMICALS SECTOR:
> Lummus seeks to expand Abu Dhabi office
> Firms express interest for Abu Dhabi methanol project
> Borouge and Borealis launch recycled products range
> Fertiglobe makes $84m profit in second quarter
> Borouge announces $231m profit in second quarter
> Adnoc opens formal chemicals integration talks with OMV
Taziz chemicals complex
Meanwhile, investors in the Taziz petrochemicals derivatives-producing industrial complex in Ruwais are pushing ahead with their projects.
Taziz – a 60:40 joint venture (JV) of Adnoc and Abu Dhabi’s industrial holding company ADQ – is overseeing the development of the sprawling industrial complex, which will mainly draw ethylene feedstock from the Borouge 4 facility to produce several in-demand chemicals.
A JV of UAE-based Fertiglobe, South Korea’s GS Energy and Japanese investment firm Mitsui awarded Italian contractor Tecnimont the main EPC contract for its planned blue ammonia project in the Taziz Industrial Chemicals Zone in February.
The JV has appointed KBR to provide the technology licence, basic engineering design, proprietary equipment and catalyst for the low-carbon ammonia plant, which will have a capacity of 1 million t/y.
India’s Reliance Industries is also an investor in the Taziz complex, having forged a partnership with Taziz and Abu Dhabi-based Shaheen Chem Holdings Investment to invest $2bn in developing three chemical plants producing chlor-alkali (940,000 t/y), ethylene dichloride (1.1 million t/y) and polyvinyl chloride (360,000 t/y).
Switzerland-based Proman has committed to building the UAE’s first methanol plant at Taziz, with a planned production capacity of 1.8 million t/y. The Proman-Taziz JV completed the contractor prequalification process for the EPC tendering round for the methanol production project in August. The operator is expected to issue the main EPC tender later this year.
As projects in the first phase of the chemicals complex move forward, Taziz is also understood to be gearing up for a second phase to more than double the number of chemicals produced at the derivatives hub.
Exclusive from Meed
-
Eni completes $1bn Libya gas project20 October 2026
-
Diriyah Company tenders East Wadi bridge20 October 2026
-
Kuwait selects firms for power works at housing projects20 October 2026
-
Taqa moves forward with Mirfa-Liwa scheme20 October 2026
-
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Eni completes $1bn Libya gas project20 October 2026
Libya’s Mellitah Oil & Gas Company, a joint venture of Libya’s National Oil Corporation (NOC) and Italian oil and gas company Eni, has achieved mechanical completion on its Bouri gas utilisation project (GUP).
In a statement, Eni said that start-up procedures are currently under way, enabling the recovery of associated gas produced from the Bouri field, which is located in Libya’s western offshore area.
The main contract for the project, worth $1bn, was awarded to Italy’s Saipem in August 2023.
The project involved the construction and installation of the new Bouri gas recovery module and related tie-in infrastructure that enables the recovery and treatment of gas that was previously flared.
In its statement, Eni said that the project “represents one of the most significant emissions reduction initiatives in Libya’s energy sector”.
It also said that it would contribute to improving the environmental performance of the country’s production system by reducing greenhouse gas emissions by approximately 1.5 million tonnes of carbon dioxide a year.
The recovered gas will be supplied to the domestic market, adding about 700 million cubic metres a year and helping meet demand from the power generation sector.
The project will also support additional gas volumes available for export to Europe through the GreenStream pipeline.
Eni said: “The start-up of the Bouri GUP confirms the joint commitment of Eni and NOC to the development of Libya’s energy sector through initiatives that combine production growth, operational efficiency and environmental stewardship.
“The project is part of a broader strategy aimed at enhancing the value of the country’s gas resources while reducing the emissions intensity of upstream activities.”
Other key projects currently under way in Libya include the A&E Structures Project, which is focused on bringing new offshore gas resources onstream for both the domestic market and exports, as well as initiatives aimed at upgrading and optimising gas production and transportation infrastructures.
Eni has been present in Libya since 1959, and the company’s equity production in the country in 2025 amounted to approximately 162,000 barrels of oil equivalent a day.
The Bouri offshore field is part of Libya’s Block NC-41, located 120 kilometres north of the Libyan coast in the Mediterranean Sea.
It was first discovered in 1976 at a depth of 8,700 feet. It is estimated to contain 4.5 billion barrels in proven recoverable crude oil reserves and 3.5 trillion cubic feet of associated natural gas, with an annual production potential of 6 billion cubic metres.
The first development phase, costing nearly $2bn, was completed in 1990.
This was immediately followed by a second development phase, which entailed drilling 55 new wells and constructing three additional platforms. Production began from the oil platforms DP4 and DP3 in August 1998.
https://image.digitalinsightresearch.in/uploads/NewsArticle/20770288/main3529.jpg -
Diriyah Company tenders East Wadi bridge20 October 2026

Saudi Arabia’s Diriyah Company has invited contractors to bid on the construction of the DG II East Wadi Bridge, a key crossing within Riyadh’s Diriyah master development.
The bridge will provide an arterial road connection linking the Diriyah Gate Phase 2 (DG II) Infrastructure Package 1 and Package 2 zones.
The project scope involves the construction of a 100-metre clear-span, 44-metre-wide, single-span post-tensioned concrete bridge structure with integrated abutments and four architectural towers.
The contract also encompasses approach slabs, access roads, pavements, associated earthworks, architectural finishes and cladding, mechanical, electrical and plumbing installations, utility interfaces, bridge parapets, vehicle restraint systems, waterproofing, testing and commissioning, and associated temporary works.
The client will supply the detailed engineering design, and the selected contractor will develop the construction methodology.
Diriyah Company issued the prequalification tender on 14 September, with submissions due by 10 December.
https://image.digitalinsightresearch.in/uploads/NewsArticle/20769223/main.png -
Kuwait selects firms for power works at housing projects20 October 2026

Kuwait’s Public Authority for Housing Welfare (PAHW) has appointed contractors for works covering the supply and installation of 132kV underground cables at South Sabah Al-Ahmad Residential City.
The contracts relate to engineering, procurement and construction (EPC) packages for works for 28 main 132/11kV substations across four phases.
According to sources, Egypt’s Elsewedy Cables has won contracts for phases 1 and 3, while China’s TBEA Shandong Luneng Taishan Cable Company has won contracts for phases 2 and 4 of the development.
In April, MEED reported that PAHW had received at least five bids for each of the first two packages, with Elsewedy and TBEA offering $44m and $40.5m, respectively.
The first contract (phase 1) covers seven substations in zones N9, N7 and N5. The second contract (phase 2) covers seven substations in zones N10 and N5.
PAHW issued two further 132kV underground cable tenders for the South Sabah Al-Ahmad residential development at the end of May, as reported by MEED.
This included a contract (phase 3) covering the supply, extension and maintenance of 132kV underground cables linked to seven substations serving the N5, N6, N8 and N10 districts. Egytech Cables, a subsidiary of Elsewedy, submitted an offer of $39.95m, the lowest of four bids.
The other contract (phase 4) covers the supply, extension and maintenance of 132kV underground cables feeding eight main transformer substations serving the N1, N6 and N11 districts.
MEED reported in July that TBEA had submitted an offer of $44.06m for the contract.
South Saad Al-Abdullah
Separately, PAHW has appointed contractors for power transmission works at the South Saad Al-Abdullah residential development.
The local firm Sayed Hamid Behbehani & Sons has won a contract to supply, install and maintain 10 main 132/11kV transformer substations for the development’s third phase.
Another local firm, Al-Ahleia Switchgear, has won a contract to supply, install and maintain 10 main 132/11kV transformer substations for the project’s fourth phase.
As reported in August, the contractors submitted bids of $104.2m and $103.3m, respectively.
https://image.digitalinsightresearch.in/uploads/NewsArticle/20761431/main.jpg -
Taqa moves forward with Mirfa-Liwa scheme20 October 2026

Taqa Transmission and Taqa Distribution are advancing a major water transmission and distribution scheme serving Mirfa, Madinat Zayed and Liwa in Abu Dhabi, sources told MEED.
The project, originally estimated to cost $775m, has been in procurement for several years. According to sources, a request for proposals has been issued, with bids due on 5 January 2027.
The initial submission deadline was 11 November, before it was extended.
The project was previously tendered in December 2024, with contractors submitting bids for transmission and distribution packages in January 2025. As of August, the bids were still under evaluation. It is unclear whether the latest tender represents a revised procurement process for the same scheme.
The project comprises a water transmission system from Mirfa, alongside distribution networks serving farms and settlements in the western region.
According to details seen by MEED, the latest scope includes a pumping station at Mirfa with a capacity of 128 million imperial gallons a day, about 125 kilometres of transmission pipelines to Muzairah, with branches to Madinat Zayed and Liwa Summit, and storage tanks at the three locations.
The distribution network is divided into four geographic clusters covering Liwa East, Liwa West, Madinat Zayed and Seih Al-Kheir. The works include associated pipelines, pumping stations and storage facilities.
The earlier procurement was structured as an engineering, procurement and construction scheme, divided between transmission and distribution works.
As MEED understands, the latest tender is being pursued under a design, build and operate model, which extends the contractor’s responsibilities to operating the infrastructure after construction.
https://image.digitalinsightresearch.in/uploads/NewsArticle/20758109/main2934.jpg -
Contractors prepare prices for Adnoc Onshore field facilities project20 October 2026

Contractors are preparing commercial bids for Adnoc Onshore’s project to build on-plot and off-plot facilities at the Rumaitha and Shanayel fields in Abu Dhabi’s North East Bab oil field cluster.
The project will enhance and sustain crude output at Rumaitha and Shanayel at 45,000 barrels a day (b/d), supporting Adnoc’s Accelerated Integrated Programme 5 (AiP5) drive to lift capacity to 5 million b/d by 2027.
Adnoc Onshore issued the main tender for engineering, procurement and construction (EPC) works on 19 June. Contractors submitted technical bids by 5 August, sources told MEED.
The on-plot works include adding a crude processing train, produced water treatment and reinjection systems, surface water pumps, and multi-stage gas compression and dehydration units. Works also include utilities, safety and control systems, modifications to existing Phase 1 units and 220kV power infrastructure.
The off-plot scope includes installing and tying in new gas-lifted producer and water-injection wells, as well as building and expanding wellhead clusters. Contractors will also lay crude-gathering, water-injection and gas-export pipelines connecting to the Adnoc Gas network and extend 33kV overhead power lines across the fields.
The tender follows Adnoc Onshore’s shift in strategy for the wider North East Bab development – comprising the Al-Nouf, Rumaitha and Shanayel fields – after scrapping an earlier engineering, procurement and construction management (EPCm) approach. MEED reported in December that the operator had cancelled an off-plot EPCm contract awarded to China Petroleum Engineering & Construction Corporation (CPECC) in October 2024. Adnoc later cancelled a separate on-plot EPCm tender that it received bids for in the second quarter of 2025.
In addition to the North East cluster, Adnoc Onshore continues to make progress on EPC works for another similar project to build off-plot facilities at the South East cluster of oil fields in Abu Dhabi, which is also integral to Adnoc Group’s AiP5 campaign.
The South East cluster comprises the Asab, Mender, Qusahwira, Sahil and Shah fields and accounts for approximately a third of Adnoc Onshore’s oil production capacity.
MEED previously reported that Adnoc Onshore awarded CPECC the EPC works for the South East off-plot facilities project, with the contract value estimated at around $1.2bn.
CPECC is also performing EPC works on the South East on-plot facilities project in a consortium with Greece-headquartered Archirodon. Adnoc Onshore awarded an estimated $1.5bn contract for that project to the consortium in December 2024, with EPC works scheduled for completion in 2027.
ALSO READ: Adnoc Onshore seeks bids for Bu Hasa field EOR project
https://image.digitalinsightresearch.in/uploads/NewsArticle/20757699/main.jpeg
