Adnoc spurs downstream gas expansions

13 October 2023

This package on the UAEs downstream sector also includes: 

Adnoc Gas picks site for planned LNG terminal
Adnoc Gas receives prices for Estidama package
> Adnoc and Dusup sign key gas supply agreement

Adnoc receives bids for gas pipeline packages
> Adnoc receives prices for sales gas pipeline packages
Adnoc Gas awards $3.6bn Project Meram contract


 

Demand for natural gas has risen exponentially in this decade, with its share in the global energy mix set to grow further in the decades to come.

Regional energy producers are deploying major capital expenditure programmes to increase their gas production and processing capabilities to cater to growing demand.

The UAE is striving to achieve self-sufficiency in gas production by 2030. With this objective in mind, Abu Dhabi National Oil Company (Adnoc) has committed significant investment towards expanding its midstream and downstream gas capabilities.

These projects seek to increase the availability of gas for utility providers and industrial customers in the UAE and ramp up ethane output to grow the country’s petrochemical sector and its derivatives ecosystem.

Hail and Ghasha galvanises UAE upstream market

Ruwais LNG project

Adnoc Gas, the gas processing business of Adnoc, has finalised the location for its planned liquefied natural gas (LNG) export terminal. The facility will have the capacity to produce about 9.6 million tonnes a year (t/y) of LNG from two processing trains, each with a capacity of 4.8 million t/y.

The overall value of the planned project is estimated to be upwards of $4.5bn, based on capital expenditure by operators on similar schemes worldwide.

Adnoc Gas received technical bids from contractors in May for the engineering, procurement and construction (EPC) works on the project, which will be built in Ruwais Industrial City in Abu Dhabi’s Al-Dhafrah region.

Adnoc Gas had originally planned to build the LNG terminal in the UAE emirate of Fujairah, which sits outside the Strait of Hormuz on the coast of the Gulf of Oman. In early May, however, the company announced it was shifting the location of the project from Fujairah to Ruwais, Abu Dhabi.

Sales gas pipeline network

Adnoc Gas is progressing the Estidama project, which is crucial to enhancing Adnoc’s sales gas pipeline network across the UAE. The project aims to cater to rising demand for gas from industrial consumers across the UAE, particularly in the Northern Emirates.

Contractors submitted commercial bids in August for combined package numbers 4 and 7. The combined package involves laying a new pipeline from the Al-Shuwaib pig launcher and pig receiver station to the Sajaa gas facility in Sharjah.

The scope also covers building a new gas pipeline between BVS-2/KP28.7 in Abu Dhabi to Dubai’s Margham gas facility to meet increased gas demand from Adnoc Gas’ customer Dubai Supply Authority (Dusup).

EPC works on the estimated $2bn-plus Estidama project have been divided into seven packages. Abu Dhabi-based contractor Integrated Specialised General Contracting Company (Iscco) won package 1, understood to have a contract value of $18m, in December 2021.

In early July, Adnoc Gas awarded contracts worth a combined $1.34bn for two other packages of the Estidama project. UK-headquartered Petrofac was awarded the EPC contract for package 2 of the Estidama project, estimated to be worth $720m.

A consortium of Abu Dhabi’s National Petroleum Construction Company (NPCC) and Lebanon-headquartered CAT Group won Estidama package 3, which is valued at about $630m.

Contractors submitted technical bids for package 6 in August 2022 and commercial bids by 21 November. Work on package 6 entails the installation of a 52-inch, 74-kilometre pipeline from Sweihan to Al-Shuwaib in Abu Dhabi and building two block valve stations.

Package 5 is expected to be tendered separately to contractors as part of a planned second phase of the sales gas pipeline upgrade project.

As per the original project schedule, EPC works on the Estidama project are due to be completed in 2025.

Ramping up ethane output

Adnoc Gas is in charge of one of the world’s largest gas processing complexes in Abu Dhabi, with the capacity to process about 8 billion cubic feet a day from its Asab, Bab, Bu Hasa, Habshan and Ruwais plants.

Increased volumes of ethane production will allow the company to commercialise it to supply feedstock to Borouge for its under-construction Borouge 4 petrochemicals complex, as well as to derivatives plants in the upcoming Taziz complex. Adnoc Gas intends to achieve this through the Maximise Ethane Recovery & Monetisation (Meram) project.

Adnoc Gas awarded a $3.6bn contract for Project Meram to a consortium of NPCC and Spanish contractor Tecnicas Reunidas in early August, with EPC work on the project starting later that month. The scope of work on the contract includes commissioning new gas processing facilities to enable an optimised supply to the Ruwais industrial complex, Adnoc Group said.

The strategic Meram project aims to achieve dual objectives, Adnoc stated.

The first goal is to increase ethane extraction by 35 to 40 per cent from Adnoc Gas’ existing onshore facilities in the Habshan gas processing complex by constructing new gas processing facilities.

The second goal is to unlock further value from existing feedstock and deliver it to Ruwais via a 120km natural gas liquids (NGL) pipeline.


LATEST NEWS FROM THE UAE's CHEMICALS SECTOR:
Lummus seeks to expand Abu Dhabi office
Firms express interest for Abu Dhabi methanol project
> Borouge and Borealis launch recycled products range
Fertiglobe makes $84m profit in second quarter
> Borouge announces $231m profit in second quarter
Adnoc opens formal chemicals integration talks with OMV


Taziz chemicals complex

Meanwhile, investors in the Taziz petrochemicals derivatives-producing industrial complex in Ruwais are pushing ahead with their projects.

Taziz – a 60:40 joint venture (JV) of Adnoc and Abu Dhabi’s industrial holding company ADQ – is overseeing the development of the sprawling industrial complex, which will mainly draw ethylene feedstock from the Borouge 4 facility to produce several in-demand chemicals.

A JV of UAE-based Fertiglobe, South Korea’s GS Energy and Japanese investment firm Mitsui awarded Italian contractor Tecnimont the main EPC contract for its planned blue ammonia project in the Taziz Industrial Chemicals Zone in February.

The JV has appointed KBR to provide the technology licence, basic engineering design, proprietary equipment and catalyst for the low-carbon ammonia plant, which will have a capacity of 1 million t/y.

India’s Reliance Industries is also an investor in the Taziz complex, having forged a partnership with Taziz and Abu Dhabi-based Shaheen Chem Holdings Investment to invest $2bn in developing three chemical plants producing chlor-alkali (940,000 t/y), ethylene dichloride (1.1 million t/y) and polyvinyl chloride (360,000 t/y).

Switzerland-based Proman has committed to building the UAE’s first methanol plant at Taziz, with a planned production capacity of 1.8 million t/y. The Proman-Taziz JV completed the contractor prequalification process for the EPC tendering round for the methanol production project in August. The operator is expected to issue the main EPC tender later this year.

As projects in the first phase of the chemicals complex move forward, Taziz is also understood to be gearing up for a second phase to more than double the number of chemicals produced at the derivatives hub.

https://image.digitalinsightresearch.in/uploads/NewsArticle/11214144/main.jpg
Indrajit Sen
Related Articles
  • Focus shifts to delivery of Iraq utilities expansion

    12 May 2026

     

    Iraq’s power and water sector recorded its largest year of investment on record in 2025, with more than $17bn in combined contract awards.

    Several long-planned water infrastructure schemes finally reached contract award stage amid mounting supply pressures in the south of the country and a growing reliance on new desalination projects.

    Iraq awarded $10bn-worth of water infrastructure contracts between January 2025 and May 2026, according to regional projects tracker MEED Projects.

    This compares with just $1.8bn in total awards across 2022, 2023 and 2024, when only one seawater desalination plant reached the contract award stage.

    Desalination projects

    Attention is now turning to the delivery phase of new plants led by a series of major desalination and water treatment projects in Basra governorate.

    In February, Iraqi officials said the flagship $2.42bn Basra seawater desalination plant could be financed through the Iraqi-Chinese Fund, weeks after the main engineering, procurement and construction (EPC) contract was awarded to PowerChina.

    Located on the Arabian Gulf coast in Al-Faw, the plant is designed to produce 1 million cubic metres a day (cm/d) of potable water. The project also includes a water transmission network supplying 11 cities and a dedicated 300MW power plant.

    Baghdad had earlier announced plans for four additional desalination plants across the province in July 2025. These include the Shatt Al-Arab plant, planned to produce 120,000 cm/d of desalinated water, and the Al-Faw and Al-Siba plants, each with a capacity of 72,000 cm/d.

    The joint venture of Baghdad-headquartered Al-Rida Investment Group and PowerChina has been appointed as the main contractor for each project, with construction expected to begin in the third quarter of 2026.

    Additional schemes include the $72m Safwan desalination plant and the $70m Abu Flous desalination project. Abu Flous is being undertaken by the Ministry of Water Resources and is designed to have a capacity of 72,000 cm/d.

    The push to advance new projects follows warnings issued last year by Iraq’s High Commission for Human Rights about a worsening humanitarian situation linked to declining river flows and rising salinity levels in the Shatt Al-Arab waterway.

    Alongside municipal water projects, Iraq is also advancing large industrial water infrastructure schemes tied to the energy sector. Last August, Iraq approved the award of the Common Seawater Supply Project package for the Artawi oil field to South Korea’s Hyundai Engineering & Construction.

    The estimated $3.16bn contract covers the engineering, procurement, supply, construction, commissioning and operation of a major seawater treatment facility. Construction is expected to begin in 2026, further reflecting the scale of projects now in the execution stage.

    Power expansion

    In parallel, Iraq’s power sector is undergoing one of its largest expansion programmes in decades as the government attempts to address chronic electricity shortages, diversify fuel sources and strengthen regional grid connectivity. Over $40bn-worth of projects are under execution, following $4.2bn in new contracts last year.

    In August 2025, the Iraqi cabinet approved five major power generation schemes with a combined capacity exceeding 10GW. The projects represent one of the country’s largest-ever single rounds of power project approvals.

    The centrepiece of the programme is three independent power producer (IPP) combined-cycle plants at Al-Faw, Abu Ghraib and Kirkuk, with a total capacity of 7,500MW.

    The largest schemes are the 3,000MW Al-Faw plant in southern Iraq, with US-based General Electric as the EPC contractor, and the 3,000MW Abu Ghraib facility near Baghdad. Both projects will be implemented under 25-year build-own-operate models.

    A 1,500MW combined-cycle plant in Kirkuk will also be developed under long-term power purchase agreements backed by sovereign guarantees from the Finance Ministry. US-based GE Vernova is the technology provider for all three projects.

    Furthermore, the government has approved two thermal power plants in Najaf and Youssifiyah, with planned capacities of 1,500MW and 1,800MW, respectively.

    This is part of a wider 20-year electricity strategy unveiled last year in partnership with Siemens Energy and GE Vernova. The programme aims to add 57GW of new generation capacity through a mix of gas-fired, thermal and renewable energy projects.

    Electricity shortfall

    The scale of the challenge means timely project execution will be critical. Iraq currently produces about 28GW of electricity, according to the Electricity Ministry, but demand during peak summer periods is estimated at more than 50GW. The shortfall continues to result in widespread outages and pressure on the national grid.

    The fragility of the system was exposed again in March, when Iraq suffered nationwide electricity blackouts after a sudden drop in gas supplies to the Rumaila power plant in Basra. The disruption led to the loss of about 1,900MW of generation capacity and triggered a nationwide grid collapse.

    The incident highlighted Iraq’s continued dependence on associated gas production from the oil sector. With regional geopolitical tensions affecting oil exports and production, gas availability for power generation has become increasingly vulnerable.

    Solar plants

    As part of a strategy to diversify energy sources, the country inaugurated the first phase of the 300MW Karbala solar IPP plant in September 2025, marking Iraq’s first utility-scale solar scheme connected to the national grid.

    Developed by a consortium of Norway’s Scatec, Egypt’s Orascom Construction and Iraq’s Al-Bilal Group, the project forms part of the government’s target to add 10GW of solar energy by 2030.

    These plans also include the 1GW solar IPP in Najaf, now under construction and scheduled for commissioning in 2028.

    Looking further ahead, the Iraqi government announced in February that it has allocated more than 140 sites for new solar power plants, following a six-month identification process. The locations are distributed across several regions, including the outskirts of Baghdad and areas such as Nahrawan, Al-Nasr, Al-Salam, Al-Hamamiyat, Taji and Al-Husseiniya.

    Meanwhile, regional interconnection projects are also becoming increasingly important. Iraq is progressing with plans to integrate into the GCC electricity grid through a new 400kV transmission link between Kuwait’s Al-Wafra station and Iraq’s Al-Faw station.

    The first phase of the project will allow 500MW of electricity imports into Iraq, rising to 1,800MW over time. Iraq is targeting full integration of the GCC-Iraq grid by the end of 2026.


    MEED’s June 2026 report on Iraq also includes:

    > OVERVIEW: Iraq enters era of resilience, reform and rising risks
    > OIL & GAS: Iraqi oil and gas sector in crisis

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16797622/main.gif
    Mark Dowdall
  • Abu Dhabi announces $15bn infrastructure PPP projects

    12 May 2026

    The Abu Dhabi Investment Office and the Abu Dhabi Projects and Infrastructure Centre have launched a AED55bn ($15bn) public-private partnership (PPP) pipeline of 24 projects to be tendered in 2026 and 2027.

    The projects will be tendered across the transport, infrastructure and social sectors.

    According to a statement published by the Abu Dhabi Media Office, the transport sector accounts for 11 road projects, with AED35bn ($9.5bn) of construction capex, covering more than 300 kilometres of new and upgraded roads, tunnels, intersections and related network works.

    The infrastructure pipeline includes five projects budgeted at AED11bn ($3bn), covering dams, water storage, flood control, stormwater upgrades and urban landscaping.

    Social infrastructure includes eight projects budgeted at AED9bn ($2.5bn), covering sports facilities, specialist healthcare assets, schools and university campuses.

    The statement added that the pipeline forms part of Abu Dhabi’s infrastructure delivery plan and will be executed through PPP structures.

    It is also intended to support company establishment in the emirate, local content objectives, and supply-chain and industrial capacity.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16793904/main.jpg
    Yasir Iqbal
  • Saudi Arabia tenders GCC rail link from Kuwait to UAE border

    12 May 2026

     

    Saudi Arabia has begun the procurement process to deliver its portion of the GCC railway, which will connect all six member states.

    Saudi Arabia Railways (SAR) issued a tender for design consultancy services for the project on 7 May, with a bid submission deadline of 30 June.

    It includes the concept design, preliminary design and Issued for Construction (IFC) design stages of the network.

    SAR requires the selected consultant to review, update and complete the existing preliminary design of the network.

    The kingdom’s section of the railway will start at Al-Khafji in the Eastern Province, near the border with Kuwait, and end at Al-Batha, at Saudi Arabia’s border with the UAE. The route length in Saudi Arabia will be about 672 kilometres (km).

    The railway will interface with the Kuwait National Rail Road (KNRR) project on the Kuwaiti side. Last year, MEED exclusively reported that the KNRR design contract was awarded to Türkiye’s Proyapi Muhendislik ve Musavirlik Anonim Sirketi.

    The KNRR forms part of the wider GCC rail network. GCC railway projects have been progressing with renewed impetus since the six member states signed the Al-Ula Declaration in January 2021.

    In October last year, the Qatari cabinet approved a draft agreement paving the way for a railway link between Qatar and Saudi Arabia as part of the GCC railway network.

    GCC railway line

    Under the overall plan, the railway will span 2,186 kilometres, beginning in Kuwait, passing through Dammam in Saudi Arabia, reaching Bahrain via a planned causeway, and continuing from Dammam to Qatar, the UAE and, ultimately, Muscat via Sohar in Oman.

    The network’s route length within each member state is as follows: 684km in the UAE, 672km in Saudi Arabia, 306km in Oman, 283km in Qatar, 145km in Kuwait and 36km in Bahrain.

    The railway is designed for passenger trains travelling at 220 kilometres an hour (km/h) and freight trains operating at 80-120km/h.

    With high levels of project activity, governments in spending mode and renewed cooperation under the Al-Ula Declaration, the latest efforts to restart the GCC railway project may make more progress than previous attempts. If completed, the railway could prove transformational for a region that is globally connected but divided between its constituent parts.

    > Be recognised among the best in the industry at the MEED Projects Awards 2026 …

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16793841/main.jpg
    Yasir Iqbal
  • Kuwait tenders upstream oil project

    12 May 2026

    State-owned upstream operator Kuwait Oil Company (KOC) has tendered a contract to develop power infrastructure to provide electricity to the country’s Bahra oil field.

    The project focuses on constructing an 11kV, 72MW main intake in the Bahra-A area.

    It also includes the development of 11kV, 20MW substations in the Bahra-A2 area, and the conversion of a substation in the Bahra-A1 area in northern Kuwait.

    An initial meeting for the project is scheduled for 7 June, and bids are due by 9 August.

    Kuwait’s oil and gas sector has been severely impacted by the blockade of the Strait of Hormuz, through which all of its crude exports are normally shipped.

    The country recorded zero crude oil exports in April for the first time since the end of the Gulf War in 1991, according to shipping monitor TankerTrackers.com.


    READ THE MAY 2026 MEED BUSINESS REVIEW – click here to view PDF

    Global energy sector forced to recalibrate; Conflict hits debt issuance and listings activity; UAE’s non-oil sector faces unclear recovery period amid disruption.

    Distributed to senior decision-makers in the region and around the world, the May 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/16792080/main.png
    Wil Crisp
  • Chinese company signs deal to develop Syria cement plant

    12 May 2026

    China’s Jiangsu Pengfei Group has signed a deal with Damascus-based Al-Hasan Holding Group (HHG) to develop a cement plant in Syria’s Raqa governorate.

    The “strategic agreement” was signed on 29 April, according to a statement from HHG.

    The clinker production line will have a capacity of 5,000 tonnes a day (t/d).

    Syria is seeking to expand cement production capacity to meet demand from the domestic construction sector.

    HHG is an integrated investment conglomerate headquartered in Damascus with a portfolio of companies across sectors including industry, trade, energy, construction, tourism and services.

    It was founded by the Syrian businessman Hassan Kamel Al-Hasan.

    Jiangsu Pengfei Group is a manufacturer of rotary kiln and grinding equipment.

    The company is involved in the design, manufacture and service of equipment in the fields of building materials, metallurgy and the chemical industry.

    It is also an engineering, procurement and construction service provider that has completed more than 100 cement production line projects.


    READ THE MAY 2026 MEED BUSINESS REVIEW – click here to view PDF

    Global energy sector forced to recalibrate; Conflict hits debt issuance and listings activity; UAE’s non-oil sector faces unclear recovery period amid disruption.

    Distributed to senior decision-makers in the region and around the world, the May 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/16792079/main.jpg
    Wil Crisp