Adnoc Gas to rally UAE downstream project spending

7 April 2026

 

Despite the impact of recent Iranian attacks on its assets, the gas processing business of Abu Dhabi National Oil Company (Adnoc Gas) is on course to emerge as the largest spending entity in the UAE’s downstream oil and gas sector this year.

Adnoc Group created Adnoc Gas, which began operating as a commercial entity in 2023, through the merger of its former subsidiaries Adnoc Gas Processing and Adnoc LNG. The consolidation of Adnoc’s gas processing and liquefied natural gas (LNG) operations formed one of the world’s largest gas processing entities, with a capacity of about 10 billion standard cubic feet a day (cf/d) across eight onshore and offshore sites, including Asab, Bab, Bu Hasa, Habshan and Ruwais.

The scale of its infrastructure – particularly its 3,250-kilometre pipeline network, which is being expanded under the $3bn Estidama project – positions Adnoc Gas as a critical enabler of both domestic industrial growth and export competitiveness.

Resilience amid geopolitical risk

The recent drone-related disruptions highlight the growing exposure of Gulf energy infrastructure to regional conflict. However, the limited operational impact reported by Adnoc Gas suggests a high degree of system redundancy and resilience, supported by networked infrastructure and diversified processing capacity.

This resilience is crucial as the company pushes ahead with its $20bn-$28bn capital programme for 2023-29. Continued investment despite security risks signals confidence in both project economics and the UAE’s ability to safeguard critical assets.

Rich Gas Development

At the core of Adnoc Gas’ expansion strategy is the Rich Gas Development (RGD) programme, which aims to increase processing capacity by 30% by 2030.

The RGD project will enable the development of new gas reservoirs, helping to boost gas liquids exports, support UAE gas self-sufficiency and provide feedstock to the country’s growing petrochemicals sector, Adnoc Gas says.

The first phase of the RGD project is under construction. Adnoc Gas awarded $5bn-worth of engineering, procurement and construction management (EPCm) contracts in three tranches for phase one last June – its largest-ever capital investment.

The contracts cover the expansion of key gas processing plants to increase throughput and improve operational efficiency across four facilities: Asab, Bu Hasa, Habshan (onshore) and the Das Island liquefaction facility (offshore).

The first tranche, valued at $2.8bn, was awarded to UK-headquartered Wood for the Habshan facility. The company said the contract value includes pass-through revenue and that it expects to recognise about $400m in EPCm revenue.

Wood’s scope includes upgrades and debottlenecking of the Habshan and Habshan 5 gas processing complexes and pipelines, including brownfield modifications and the installation of new facilities.

The remaining two tranches – $1.2bn for the Das Island liquefaction facility and $1.1bn for the Asab and Bu Hasa facilities – were awarded to UAE-based Petrofac and Dubai-based Kent, respectively.

Petrofac, separately, said it will provide EPCm services and oversee procurement and construction contracts for a new inlet facility; two gas dehydration and compression trains, each with a capacity of 420 million cf/d; and associated infrastructure at Das Island. The company will also upgrade existing facilities to increase capacity for collecting and transporting raw gas.

RGD growth phases

Adnoc Gas’ capital expenditure commitment of $20bn for the 2023-29 period is expected to rise to about $28bn as it targets final investment decisions (FIDs) on the second and third phases of the RGD programme in the first quarter of 2026.

These phases involve building a natural gas liquids (NGL) fractionation train at the Ruwais facility and a new gas processing train at Habshan. Adnoc Gas has selected main contractors for EPC works on both projects, although official contract awards are pending.

Italy’s Tecnimont has been selected for the Ruwais NGL Train 5 project, which will have a capacity of 22,000 tonnes a day, or about 8 million tonnes a year.

China-based Wison Engineering has been selected for the Habshan 7 gas processing train. The Habshan complex is one of the largest in the UAE and the wider Middle East and North Africa region, with a capacity of 6.1 billion cf/d across five trains and 14 processing units.

With Adnoc Group advancing its P5 programme to raise oil production capacity to 5 million barrels a day by 2027, higher volumes of associated gas are set to enter the grid. The new train at Habshan, scheduled for commissioning in 2029, will help process these additional volumes.

Bab Gas Cap development

As part of its upstream expansion plans, Adnoc Group is working to extract gas from four underdeveloped gas cap reservoirs at the Bab onshore field: Thammama A, B, F and H. The Thammama A, B and H reservoirs are expected to produce a combined 1.45 billion cf/d, while Thammama F is projected to produce 396 million cf/d.

Existing processing capacity at Habshan will be insufficient to handle these volumes. As a result, Adnoc Gas plans to build new facilities to process up to 1.85 billion cf/d of additional gas.

The company is planning a new gas processing plant in the Bab area, about 170 kilometres from Abu Dhabi, along with associated pipelines and supporting infrastructure, as part of the broader Bab gas cap development project.

Adnoc Gas has divided the EPC scope into four packages. It completed contractor prequalification in February and is expected to issue main EPC tenders in the second quarter.

The company’s capital expenditure commitment could exceed $30bn once it reaches FID on the Bab gas cap development, which is expected later this year.

https://image.digitalinsightresearch.in/uploads/NewsArticle/16281839/main.gif
Indrajit Sen
Related Articles
  • Chinese firms win $290m Algeria data centre deal

    18 November 2026

     

    Algeria’s High Commission for Digitalisation has awarded a AD39.8bn ($290m) contract for the study, construction, supply of equipment and commissioning of a national disaster recovery data centre.

    The contract was awarded to a joint venture of Chinese firms including China Railway Construction Corporation (CRCC) and Huawei Group.

    The contract is split into two lots:

    • Lot 1 – Civil engineering and infrastructure: The CRCC-Huawei Group submitted a bid of $67m, including VAT, for a nine-month delivery period
    • Lot 2 – Disaster recovery site: The group submitted a bid of $223m, including VAT, with a six-month completion period

    The CRCC-Huawei Group comprises CRCC International, CRCC Algeria and Huawei Telecommunication Algeria.

    The High Commission for Digitalisation said the group scored 100 out of 100 on both lots, meeting the tender requirements.

    The project will provide a national disaster recovery site intended to maintain the availability and recovery of digital systems and data if a disruption affects a primary data centre or IT system.

    The scope includes the physical data centre infrastructure under the first lot and the disaster recovery site equipment and systems under the second lot.

    The planned facility forms part of Algeria’s wider digitalisation programme, which includes expanding public sector digital services and the supporting infrastructure required to host, secure and protect government data and applications.


    READ THE NOVEMBER 2026 MEED BUSINESS REVIEW – click here to view PDF

    Gulf projects keep moving amid conflict; UAE's state spending and oil output flexibility cushion Iran war shock; Project finance lenders weigh risk against infrastructure needs.

    Distributed to senior decision-makers in the region and around the world, the November 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/21515726/main.gif
    Yasir Iqbal
  • Projects market holds firm

    18 November 2026

    Commentary
    Colin Foreman
    Editor

    After eight months of conflict in the Gulf, the region’s economies are sustaining heavy damage. The IMF’s October World Economic Outlook forecasts contraction in every GCC state except Oman in 2026. Kuwait’s economy is projected to shrink by 16.7% and Qatar’s by 15.6% as disruption in the Strait of Hormuz cuts energy exports.

    The projects market has held up far better. Data from MEED Projects shows the UAE leading the region for a second consecutive year, with contract awards 6.1% higher than in the same period of 2025. Abu Dhabi has been the standout, with awards up 35% on the back of a sharp rise in public capital spending. Saudi Arabia has awarded $68.8bn of contracts so far this year, 13% less than in 2025.

    Two key drivers are shaping the market in 2026. First, private developers, faced with declining off-plan sales, are focusing on project completion to unlock cash from investors who have already purchased property. Second, government and state-related entities have accelerated activity, pushing ahead with large-scale public infrastructure schemes alongside more commercially oriented developments.

    Abu Dhabi has been the standout, with awards up 35% on last year

    Warning signs remain beneath the headline totals. Tendering has slowed since hostilities resumed after the April ceasefire, and Dubai’s residential market has weakened, marked by a steep year-on-year drop in Q3 transactions. The effect on contract awards is likely to become clearer in the coming months.

    The conflict is also generating new demand. Saudi Arabia and the UAE are prioritising ports, pipelines and transport links that bypass Hormuz, and reconstruction and repair work will follow once the fighting ends.

    The central question for the final quarter is whether the Q3 slowdown marks a temporary pause or the start of a sustained decline. 

    Much will depend on when the strait reopens.


    READ THE NOVEMBER 2026 MEED BUSINESS REVIEW – click here to view PDF

    Gulf projects keep moving amid conflict; UAE's state spending and oil output flexibility cushion Iran war shock; Project finance lenders weigh risk against infrastructure needs.

    Distributed to senior decision-makers in the region and around the world, the November 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/21514495/main.gif
    Colin Foreman
  • EBRD takes stake in Egypt desalination platform

    18 November 2026

    The European Bank for Reconstruction & Development (EBRD) has finalised an agreement to invest up to $31m in Egypt’s RWD Investments BV, a water development and investment arm of Hassan Allam Utilities (HAU).

    Under the agreement, EBRD will acquire a 30% equity stake in RWD. HAU is contributing up to $61m towards the platform’s overall $92m equity funding.

    The proceeds will support RWD’s near- and medium-term expansion plans, including the development of future large-scale desalination and wastewater projects through public-private partnerships (PPPs). The agreement follows EBRD board approval of the proposed investment in July.

    RWD plans to add up to 15,000 cubic metres a day (cm/d) of new desalination capacity annually through 2030. The additional capacity will increase water supplies to businesses in coastal areas that are not connected to municipal networks.

    The company will also rehabilitate existing desalination facilities to reduce energy consumption and improve operating efficiency.

    Demand for alternative water sources is increasing in Egypt’s coastal areas, where tourism, industrial and other private developments often cannot rely on municipal water networks. The government has also restricted further extensions of Nile-sourced water infrastructure to coastal tourism developments.

    Established in 2019, RWD operates in Egypt through Ridgewood for Water Desalination, Sinai for Environmental Services and Ridgewood Egypt for Infrastructure Projects.

    The group owns and operates 79 desalination facilities across Egypt’s coastal cities, with a combined design capacity of about 96,340 cm/d as of December 2025.

    In October, the Higher Committee for Public-Private Partnership approved the tendering of four industrial wastewater treatment plants in Alexandria, Giza, Beheira and Port Said. The facilities will serve the Amreya, Abu Rawash, Wadi El-Natrun and El-Raswa industrial zones, with capacities of 15,000-35,000 cm/d.

    Two further desalination projects were approved for tendering, including a 900,000 cm/d plant in Port Said and a 1 million cm/d plant in Suez.


    READ THE NOVEMBER 2026 MEED BUSINESS REVIEW – click here to view PDF

    Gulf projects keep moving amid conflict; UAE's state spending and oil output flexibility cushion Iran war shock; Project finance lenders weigh risk against infrastructure needs.

    Distributed to senior decision-makers in the region and around the world, the November 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/21513812/main.jpg
    Mark Dowdall
  • Bahrain appoints Northern Link Road transaction adviser

    18 November 2026

     

    Bahrain's Ministry of Works has awarded Ernst & Young a BD2.26m ($6m) contract to provide transaction advisory services on the Bahrain Northern Link Road (BNLR), a highway the government intends to deliver on a public-private partnership (PPP) basis.

    The Bahrain Tender Board opened the financial proposals on 6 August. Local units of KPMG, PriceWaterhouseCoopers (PwC) and Ernst & Young (EY) submitted bids, all of which were accepted.

    EY will provide financial, technical and legal advisory services, including feasibility studies, project structuring and bid documentation, along with support through tendering, evaluation and negotiation, and assistance up to financial close.

    The 29.5-kilometre highway will run from North Manama Causeway Bridge to Suhaila Island and onwards to King Hamad Causeway. The project is intended to serve as a parallel east-west corridor to Sheikh Isa Bin Salman Highway and to support traffic flow between Khalifa Bin Salman Port and Saudi Arabia.

    Causeway connection

    The BNLR will connect to the planned King Hamad Causeway. Earlier project plans, drawn up in 2016, included an arterial road with six or eight lanes that could run alongside a light rail or rapid bus transit system.

    In October 2019, King Fahd Causeway Authority appointed a consortium to provide transaction advisory services for King Hamad Causeway. The $8.9m consultancy agreement was signed with a consortium of Netherlands-headquartered KPMG, US-based Aecom and UK-based CMS. The plan was to fund the project through tolls, as with the existing King Fahd Causeway.

    The King Fahd Causeway opened in 1986 and extends for 25km. The bridge cost an estimated $1.2bn to construct and serves about 45,000 vehicles a day on average, rising to about 60,000 at weekends. It has been undergoing an expansion to ease severe congestion during peak periods.


    READ THE NOVEMBER 2026 MEED BUSINESS REVIEW – click here to view PDF

    Gulf projects keep moving amid conflict; UAE’s state spending and oil output flexibility cushion Iran war shock; Project finance lenders weigh risk against infrastructure needs.

    Distributed to senior decision-makers in the region and around the world, the November 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/21511012/main.jpg
    Yasir Iqbal
  • OMV to drill Libya oil and gas exploration well

    18 November 2026

    Austrian oil and gas company OMV is planning to start drilling an exploration well in Libya’s Marwa concession before the end of this month, according to a statement from the North African country’s National Oil Corporation (NOC).

    In its statement, NOC said that it held an “extensive technical meeting” with officials from OMV to discuss the company’s plans and contractual obligations.

    ​The meeting reviewed activities carried out throughout 2026 alongside programmes scheduled for 2027.

    NOC said: “Officials also addressed ways to overcome challenges hindering the completion of remaining work, including seismic surveys and exploration well drilling.”

    During the meeting, OMV confirmed that preparations are under way to drill its first exploration well at the Marwa concession in Contract Area 103/3 (NC74B) by the end of November, targeting a depth of approximately 6,500 feet.

    NOC’s Exploration Department said that intensifying oil and gas exploration is a key strategic priority for the organisation.

    In June, NOC announced a capacity target of 2 million barrels of oil a day by 2030.

    Earlier this month, Libya’s Audit Bureau said it had held a meeting with NOC to discuss tendering a project to rehabilitate and develop Libya’s Dahra oil field.

    The head of the Audit Bureau, Khaled Shakshak, met with NOC head Masoud Suleiman on 15 November.

    During the meeting, they discussed options for tendering the Dahra oil field development project, previously estimated at $1bn and expected to significantly increase the field’s oil production.

    The oil field in central Libya has suffered from years of poor maintenance and was sabotaged by Islamic State militants in 2015.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/21479617/main.jpg
    Wil Crisp