Adnoc Gas to increase capacity by 20% in five years

12 August 2024

Register for MEED's 14-day trial access 

Adnoc Gas has announced it is making progress on core growth projects that are expected to increase the company’s natural gas processing capacity by 20% within the next five years.

The subsidiary of Abu Dhabi National Oil Company (Adnoc Group) has made significant investments in those growth projects, the largest of which is the liquefied natural gas (LNG) export terminal facility in Ruwais, Abu Dhabi.

Peter van Driel, chief financial officer at Adnoc Gas, provided updates on some of these projects during a press conference held to discuss the company’s financial results for the second quarter of 2024.

Adnoc Gas announced an adjusted net income of $1.19bn in the first quarter of 2024, a year-on-year growth of 21%. Revenues for the second quarter were registered at $6.076bn, a year-on-year increase of 13%, the company said on 12 August.

Ruwais LNG facility

Adnoc Gas expects to commission the upcoming Ruwais LNG export terminal in 2028. The company awarded the full engineering, procurement and construction (EPC) contract and achieved the final investment decision (FID) for the project in June.

A consortium of France’s Technip Energies, Japan-based JGC Corporation and Abu Dhabi-owned NMDC Energy was awarded the EPC contract, worth $5.5bn, Adnoc announced on 12 June.

The LNG export terminal in Ruwais will have the capacity to produce about 9.6 million tonnes a year (t/y) of LNG from two processing trains, each with a capacity of 4.8 million t/y. When the project is commissioned, Adnoc’s LNG production capacity will more than double to about 15 million t/y.

Estidama advances

Adnoc Gas said it expects EPC works on its project to expand its sales gas pipeline network across the UAE, also known as Estidama, to complete in the third quarter of 2025.

Through the Estidama scheme, Adnoc Gas aims to extend the existing 3,200-kilometre pipeline network to over 3,500km, enabling the transportation of higher volumes of natural gas to customers across the UAE. EPC works on the estimated $2bn-plus Estidama project have been divided into seven packages.

Adnoc Gas, in July, awarded contracts worth a total of $550m for two EPC packages of the Estidama project.

The combined packages 4+7 of the Estidama project were awarded to the UAE unit of Oman's Galfar Engineering & Contracting, valued at $295m. Abu Dhabi’s NMDC Energy won package 6, which is worth $255m.

Habshan CO2 recovery project

Adnoc Gas awarded UK-headquartered Petrofac the main EPC contract, valued at $615m, for the Habshan carbon dioxide (CO2) recovery project in October last year. The planned Habshan carbon capture, utilisation and storage (CCUS) facility will have the capacity to capture and permanently store 1.5 million t/y of CO2 within geological formations deep underground.

In its presentation to journalists on 12 August, Adnoc Gas said it expects the Habshan CO2 recovery project to be commissioned in the first quarter of 2026.

Project Meram

Adnoc Gas anticipates EPC work on its Maximise Ethane Recovery & Monetisation (Meram) project to finish in the last quarter of 2025.

The company awarded a $3.6bn contract for Project Meram to a consortium of Abu Dhabi’s NMDC Energy and Spanish contractor Tecnicas Reunidas in August 2023. The consortium began execution of EPC work on the project in the same month, as MEED previously reported.

The strategic Meram project aims to achieve dual objectives, Adnoc stated. The first goal is to increase ethane extraction by 35%-40% from Adnoc Gas’ existing onshore facilities in the Habshan gas processing complex by constructing new gas processing facilities. The second goal is to unlock further value from existing feedstock and deliver it to Ruwais via a 120km natural gas liquids (NGL) pipeline.

Other growth projects

Regarding its other core growth projects, Adnoc Gas said it intends to complete its P5 projects in 2027. Adnoc Gas’ P5 projects are aligned with supporting its parent company's target of achieving an oil production potential of 5 million barrels a day (b/d) by 2027.

“P5 is a set of activities to accommodate the 5 million b/d [Adnoc Group target],” Van Driel told journalists.

Separately, Adnoc Gas said it now expects EPC work on the second phase of its integrated gas development expansion project (IGD-E2) to complete in the first quarter of 2025.

A consortium of Tecnicas Reunidas and Abu Dhabi’s Target Engineering Construction Company is executing EPC works on the IGD-E2 project, which is estimated to be worth about $1.4bn. The project will allow Adnoc Gas’ Habshan plant to process an additional 200 to 400 million cubic feet a day (cf/d) of offshore gas. Its output currently stands at 1.4 billion cf/d.

The Bab Gas Cap development project, which has seen delays since being initiated a few years ago, is expected to complete in 2028, Adnoc Gas said.

Lastly, Adnoc Gas also expects its LNG2.0 project, through which it plans to increase ethane output and reduce greenhouse gas emissions from its LNG production complex on Das Island, to complete in 2028.

Italian contractor Saipem and France-based Technip Energies are participating in a feed-to-EPC contest for the project, MEED previously reported. Adnoc Gas will select the contractor that submits the most competitive front-end engineering and design (feed) proposal for executing EPC works. This constitutes the basic method of a feed-to-EPC competition.

https://image.digitalinsightresearch.in/uploads/NewsArticle/12325521/main.png
Indrajit Sen
Related Articles
  • What actually slows a gigaproject down

    9 September 2026

     

    Ask anyone delivering a major programme in the GCC what causes delays and sequencing will come up early. Utilities go in too late. Approvals lag behind construction. Stations, depots and access roads are procured as if they belong to different projects rather than one system.

    “None of this is new. The industry has understood these risks for years,” says Alan Caldwell, managing director for transport and infrastructure at WSP Middle East.

    For Caldwell, that is what makes the pattern worth interrogating rather than simply restating.

    “The more important question is why the same issues around interfaces, approvals, stakeholder alignment and delivery sequencing continue to slow major programmes when the risks are already so well understood,” he says.

    The answer, he argues, is not that these programmes are too big or too technically complex. What breaks a schedule is a wider system delivered as a set of disconnected parts; an approval sitting with an authority team with no visibility of the construction sequence downstream; or a station package proceeding without the utilities diversion it depends on.

    “Infrastructure programmes do not struggle because a railway is too large or a highway network is too complex,” Caldwell says. “They encounter difficulties when interconnected elements are delivered in the wrong order.”

    Sequencing decisions are rarely purely technical either, he adds. They are commercial – shaped by which assets need to unlock value first, which phases are tied to funding, and where sales or investment assumptions depend on infrastructure landing in a particular order.

    Approvals sit at the centre of that logic. On many programmes, they become one of the biggest sources of lost time – not because the requirements are unreasonable, but because approvals are not planned, evidenced or owned as part of the delivery logic from day one.

    Caldwell has seen the same pattern across three decades of Gulf delivery, from early work on Palm Jumeirah to today’s region-wide transport programmes.

    “The decisive factor has often been the same: whether interfaces, approvals, responsibilities and delivery sequencing are aligned early enough to prevent complexity becoming delay.”

    Integration needs to be well understood

    “Most programme teams in the region would say they understand the need for integration,” Caldwell says. Fewer are structured to deliver it. “The harder task is turning that understanding into the way projects are actually set up and managed,” he argues.

    Riyadh Metro is the reference point he returns to, precisely because engineering complexity was not the deciding factor in its delivery.

    Coordinating a city-scale transport system meant aligning design, construction, systems, utilities and stakeholder interfaces across every delivery vertical.

    “The lesson for the region today is clear,” Caldwell says. “Ambitious programmes need a delivery model that gives every contributor a shared view of progress, risk, decision-making and the business case driving programme priorities.”

    That shared view, he argues, will be what the next phase of Gulf delivery is judged on.

    Whether clients, consultants, contractors, operators and approval authorities can work to a single delivery logic will be key.

    “This requires more than coordination meetings. It requires integrated ways of working, shared common data environments and governance structures that make risks, decisions and dependencies visible before they become delays,” he says.

    From reporting progress to managing risk before it lands

    Digital tools have a role here, Caldwell says, but not as a headline in themselves.

    Digital twins, programme visualisation and data-led modelling matter only if they help teams identify and address problems before they affect the wider programme.

    “The real value is not technology for its own sake,” he says. “It is the ability to see, in one place, where approvals are outstanding, where interfaces are unresolved, where programme dates are slipping, where clashes are emerging and where decisions need to be escalated."

    None of it works without governance behind it, he cautions. “A dashboard will not resolve a delayed approval if nobody knows who owns the decision, when it needs to be made, or how it should be escalated.”

    Data only has value if the processes and responsibilities around it are clear, which is why Caldwell frames the shift the region needs not as digitisation, but as a move “from programme management as a discipline focused mainly on reporting and coordination, and towards project and programme intelligence”.

    With many of the region’s programmes running for a decade or more, he adds, delivery models also need to flex as funding assumptions, user needs and policy priorities change along the way.

    “The ambition behind the Gulf’s transformation programmes is not in question,” Caldwell says.

    What will determine how much of it is realised on time is whether delivery models evolve at the same pace: earlier integration, clearer approval pathways, shared data environments, and every contributor working to a delivery logic that connects technical sequencing with the funding and operational case behind it.

    “The region’s next challenge is not imagining bigger projects,” he says. “It is changing the way they are delivered, operated and adapted over time.”

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19502016/main.gif
    Yasir Iqbal
  • Jordan tenders advisory for wastewater treatment plant

    9 September 2026

    The Water Authority Jordan (WAJ) has issued an invitation to prequalify for advisory services for the rehabilitation and expansion of the Shallala wastewater treatment plant in Irbid, northern Jordan.

    The Shallala plant was commissioned in 2013 with a design capacity of about 14,000 cubic metres a day (cm/d).

    The rehabilitation and expansion project will increase its treatment capacity to about 30,500 cm/d to meet projected wastewater flows through 2050.

    The PIU Support and Construction Supervision Consultancy Services tender was released on 19 August.

    The submission deadline is 21 September.

    The consultancy will support the project implementation unit and provide construction supervision services for the project. The project has an estimated value of $69m and is being financed by the European Bank for Reconstruction and Development.

    The planned works include rehabilitating the existing activated sludge and treatment units and constructing a new treatment train.

    The scope also includes installing biogas combined heat and power units, improving sludge handling and dewatering systems, and installing odour control and chemical containment systems.

    WAJ is also undertaking the upgrade and expansion of the Ain Ghazal wastewater treatment plant in Amman.

    The existing facility had a capacity of 330,000 cm/d and is being upgraded to 726,712 cm/d to accept and treat expected incoming flows until 2045.

    The local Arab Towers Contracting Company was appointed as the main contractor for the project last year.


    READ THE SEPTEMBER 2026 MEED BUSINESS REVIEW – click here to view PDF

    Nuclear power ambitions gather pace; Kuwait keeps dealmaking alive despite war; Region invests in raising gas processing capacity.

    Distributed to senior decision-makers in the region and around the world, the September 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/19498520/main.jpg
    Mark Dowdall
  • Medina’s KEC signs real estate project development deal

    9 September 2026

    Medina’s Knowledge Economic City (KEC) has signed an agreement with Riyadh-based Kaden Investment Company to develop a mixed-use project in Medina.

    The project will have an estimated gross floor area of about 230,000 square metres (sq m).

    According to a statement filed by KEC with the Saudi Exchange (Tadawul), the project – called Multaqa Al-Madinah 2 – will be built on a 92,000 sq m plot located directly north of the first phase of the Multaqa Al-Madinah development.

    It is expected to include about 1,527 residential units across three residential zones, along with commercial and office space totalling about 31,108 sq m of net leasable area.

    It will also feature parking, recreational and service facilities, landscaping and other supporting infrastructure.

    KEC and Kaden intend to deliver the project through a closed-ended real estate investment fund regulated by Saudi Arabia’s Capital Market Authority.

    Under the proposed structure, KEC will contribute the land as an in-kind contribution and hold 75% of the fund units, while Kaden will contribute cash and hold the remaining 25%.

    Kaden will also serve as the development manager.

    KEC said the land has been initially valued at about SR692.3m ($184.6m), while the total equity required for the project is estimated at around SR833m.

    Once final agreements are signed, KEC expects to receive SR67.7m in cash and fund units valued at approximately SR624.6m.


    READ THE SEPTEMBER 2026 MEED BUSINESS REVIEW – click here to view PDF

    Nuclear power ambitions gather pace; Kuwait keeps dealmaking alive despite war; Region invests in raising gas processing capacity.

    Distributed to senior decision-makers in the region and around the world, the September 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/19492407/main.png
    Yasir Iqbal
  • Morocco signs agreement for synthetic fuel complex

    9 September 2026

    Switzerland-based Synhelion has signed an agreement with the Government of Morocco with the aim of developing a large-scale commercial synthetic fuel plant in the country’s southern Tan-Tan province.

    The memorandum of understanding (MoU) relates to a facility with the capacity to produce 100,000 tonnes a year of fuel, according to a statement released by the company.

    Synhelion has secured land for the project site and established a subsidiary in Morocco to develop the fuel complex.

    Gianluca Ambrosetti, one of Synhelion’s co-chief executives, said: “Morocco’s exceptional renewable energy resources and its clear industrial strategy make it an ideal location for scaling our synthetic fuel technology.

    “With the MoU signed, the land reservation secured and our branch in place, we are moving from evaluation to execution and toward our first commercial-scale plant in the region.”

    Synhelion specialises in producing hydrocarbon fuels using renewable energy. Its products include synthetic jet fuel, gasoline and diesel.


    READ THE SEPTEMBER 2026 MEED BUSINESS REVIEW – click here to view PDF

    Nuclear power ambitions gather pace; Kuwait keeps dealmaking alive despite war; Region invests in raising gas processing capacity.

    Distributed to senior decision-makers in the region and around the world, the September 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/19489903/main.jpg
    Wil Crisp
  • Iraq solar package on track to come online in December

    9 September 2026

     

    The 1,000MW solar photovoltaic project in Artawi – also called Ratawi – in southern Iraq is on track for its second phase to come online on 8 December, according to industry sources.

    This phase has a capacity of 250MW and will bring the project’s total online capacity to 500MW.

    The first phase of the project, also with a capacity of 250MW, came online in March this year.

    The third and fourth phases, each with a capacity of 250MW, are expected to be brought online next year.

    The solar project is part of the broader Gas Growth Integrated Project (GGIP), which has an estimated total value of $27bn and a first phase worth an estimated $10bn.

    The solar project’s ownership differs from the headline GGIP ownership structure, with its ownership equally divided between France’s TotalEnergies and QatarEnergy.

    The wider GGIP consortium includes TotalEnergies, Iraq’s Basra Oil Company and QatarEnergy, which hold stakes of 45%, 30% and 25%, respectively.

    China Energy Engineering Corporation is part of a consortium that is executing the main engineering, procurement and construction contract for the project.

    It announced that the first 250MW of capacity had been connected to the grid on 4 March this year.

    The consortium also includes China Energy Engineering Group Tianjin Electric Power Construction Company and Chengdu-headquartered Southwest Electric Power Design Institute Company.

    The project scope includes:

    • Construction of a substation
    • Installation of a 132kV booster station
    • Installation of solar panels
    • Installation of transformers
    • Laying of transmission lines
    • Construction of related infrastructure

    In February 2025, Basra Investment Commission director Alaa Abdul Hussein said the solar plant had an estimated total value of $820m.

    The GGIP programme is focused on developing four major projects in Iraq:

    • The Common Seawater Supply Project (CSSP)
    • The Ratawi gas processing complex
    • The 1GW solar power project for Iraq’s electricity ministry
    • A field development project at Ratawi, known as the Associated Gas Upstream Project (AGUP)

    All four of these projects are currently under execution, though there have been some delays related to the regional war that started when the US and Israel attacked Iran on 28 February.

    The conflict has caused significant disruption to shipping through the Strait of Hormuz, which Iraq uses to export crude oil and import equipment and materials for projects.


    READ THE SEPTEMBER 2026 MEED BUSINESS REVIEW – click here to view PDF

    Nuclear power ambitions gather pace; Kuwait keeps dealmaking alive despite war; Region invests in raising gas processing capacity.

    Distributed to senior decision-makers in the region and around the world, the September 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/19489818/main.jpg
    Wil Crisp