Adnoc Gas to increase capacity by 20% in five years
12 August 2024
Register for MEED's 14-day trial access
Adnoc Gas has announced it is making progress on core growth projects that are expected to increase the company’s natural gas processing capacity by 20% within the next five years.
The subsidiary of Abu Dhabi National Oil Company (Adnoc Group) has made significant investments in those growth projects, the largest of which is the liquefied natural gas (LNG) export terminal facility in Ruwais, Abu Dhabi.
Peter van Driel, chief financial officer at Adnoc Gas, provided updates on some of these projects during a press conference held to discuss the company’s financial results for the second quarter of 2024.
Adnoc Gas announced an adjusted net income of $1.19bn in the first quarter of 2024, a year-on-year growth of 21%. Revenues for the second quarter were registered at $6.076bn, a year-on-year increase of 13%, the company said on 12 August.
Ruwais LNG facility
Adnoc Gas expects to commission the upcoming Ruwais LNG export terminal in 2028. The company awarded the full engineering, procurement and construction (EPC) contract and achieved the final investment decision (FID) for the project in June.
A consortium of France’s Technip Energies, Japan-based JGC Corporation and Abu Dhabi-owned NMDC Energy was awarded the EPC contract, worth $5.5bn, Adnoc announced on 12 June.
The LNG export terminal in Ruwais will have the capacity to produce about 9.6 million tonnes a year (t/y) of LNG from two processing trains, each with a capacity of 4.8 million t/y. When the project is commissioned, Adnoc’s LNG production capacity will more than double to about 15 million t/y.
Estidama advances
Adnoc Gas said it expects EPC works on its project to expand its sales gas pipeline network across the UAE, also known as Estidama, to complete in the third quarter of 2025.
Through the Estidama scheme, Adnoc Gas aims to extend the existing 3,200-kilometre pipeline network to over 3,500km, enabling the transportation of higher volumes of natural gas to customers across the UAE. EPC works on the estimated $2bn-plus Estidama project have been divided into seven packages.
Adnoc Gas, in July, awarded contracts worth a total of $550m for two EPC packages of the Estidama project.
The combined packages 4+7 of the Estidama project were awarded to the UAE unit of Oman's Galfar Engineering & Contracting, valued at $295m. Abu Dhabi’s NMDC Energy won package 6, which is worth $255m.
Habshan CO2 recovery project
Adnoc Gas awarded UK-headquartered Petrofac the main EPC contract, valued at $615m, for the Habshan carbon dioxide (CO2) recovery project in October last year. The planned Habshan carbon capture, utilisation and storage (CCUS) facility will have the capacity to capture and permanently store 1.5 million t/y of CO2 within geological formations deep underground.
In its presentation to journalists on 12 August, Adnoc Gas said it expects the Habshan CO2 recovery project to be commissioned in the first quarter of 2026.
Project Meram
Adnoc Gas anticipates EPC work on its Maximise Ethane Recovery & Monetisation (Meram) project to finish in the last quarter of 2025.
The company awarded a $3.6bn contract for Project Meram to a consortium of Abu Dhabi’s NMDC Energy and Spanish contractor Tecnicas Reunidas in August 2023. The consortium began execution of EPC work on the project in the same month, as MEED previously reported.
The strategic Meram project aims to achieve dual objectives, Adnoc stated. The first goal is to increase ethane extraction by 35%-40% from Adnoc Gas’ existing onshore facilities in the Habshan gas processing complex by constructing new gas processing facilities. The second goal is to unlock further value from existing feedstock and deliver it to Ruwais via a 120km natural gas liquids (NGL) pipeline.
Other growth projects
Regarding its other core growth projects, Adnoc Gas said it intends to complete its P5 projects in 2027. Adnoc Gas’ P5 projects are aligned with supporting its parent company's target of achieving an oil production potential of 5 million barrels a day (b/d) by 2027.
“P5 is a set of activities to accommodate the 5 million b/d [Adnoc Group target],” Van Driel told journalists.
Separately, Adnoc Gas said it now expects EPC work on the second phase of its integrated gas development expansion project (IGD-E2) to complete in the first quarter of 2025.
A consortium of Tecnicas Reunidas and Abu Dhabi’s Target Engineering Construction Company is executing EPC works on the IGD-E2 project, which is estimated to be worth about $1.4bn. The project will allow Adnoc Gas’ Habshan plant to process an additional 200 to 400 million cubic feet a day (cf/d) of offshore gas. Its output currently stands at 1.4 billion cf/d.
The Bab Gas Cap development project, which has seen delays since being initiated a few years ago, is expected to complete in 2028, Adnoc Gas said.
Lastly, Adnoc Gas also expects its LNG2.0 project, through which it plans to increase ethane output and reduce greenhouse gas emissions from its LNG production complex on Das Island, to complete in 2028.
Italian contractor Saipem and France-based Technip Energies are participating in a feed-to-EPC contest for the project, MEED previously reported. Adnoc Gas will select the contractor that submits the most competitive front-end engineering and design (feed) proposal for executing EPC works. This constitutes the basic method of a feed-to-EPC competition.
Exclusive from Meed
-
EtihadWE tenders $150m Ajman substation project21 July 2026
-
-
-
-
Dubai Municipality awards Tasreef drainage contract21 July 2026
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
EtihadWE tenders $150m Ajman substation project21 July 2026
The UAE’s Etihad Water & Electricity (EtihadWE) has tendered a contract to build three new substations in Ajman.
Estimated to cost $150m, the project involves the construction of three new 132/11kV substations in the Bahya, Rumaila and Liwara districts. It also includes associated 132kV underground cabling works to connect the substations to the existing transmission network.
The bid submission deadline is 10 August.
According to tender documents, the project will add distribution capacity to support load growth and improve the security of electricity supply in the emirate.
The scope of work includes site preparation, construction of three substation buildings and foundations, installation of 132kV GIS/AIS switchgear, 132/11kV power transformers and 11kV switchgear, as well as protection, control, Scada and telecommunications systems.
Etihad WE is responsible for electricity and water services in Ajman, Umm Al-Quwain, Ras Al-Khaimah, Fujairah and parts of Sharjah. The utility has been investing in new substations and transmission infrastructure as electricity demand continues to increase across the Northern Emirates.
This includes a 132/33/11kV substation project on Al-Marjan Island in Ras Al-Khaimah. Construction work is ongoing on the project, with Maetal Dubai serving as the main contractor.
EtihadWE is also finalising a new masterplan that will cover network capacity requirements and expansion priorities for the next 10 to 15 years.
In June, Abdulla Al-Khemeiri, chief operations officer, told MEED: “We are currently reviewing it, and we need to obtain shareholder approval first. Once it is approved, it will be released, hopefully by the end of the year.”
https://image.digitalinsightresearch.in/uploads/NewsArticle/17710661/main.jpg -
Seven seeks contractors for Dammam water park and hotel21 July 2026

Saudi Entertainment Ventures (Seven), a wholly owned subsidiary of the Public Investment Fund, is preparing to shortlist general contractors for the main construction package of its Dammam Water Park & Hotel project in the Al-Hamra district.
The waterfront development sits on a 324,300-square-metre (sq m) plot.
A notice was issued to contractors in July, and the client is expected to finalise the shortlist by the end of this month.
Seven is seeking firms capable of delivering a lump-sum, turnkey solution for both the water park and a 321-key lifestyle hotel. Construction is expected to take 24 months from contract award.
The water park is designed around five themed zones and will feature what is billed as the world’s first double-tornado/triple-wave waterslide.
The park will include 21 major rides and attractions, 21 food and beverage outlets, 66 cabanas, parking for 1,100 vehicles and a daily peak capacity of 4,500 guests.
Slide procurement has already been completed directly by Seven. The selected contractor will be responsible for locally sourcing slide towers, integrating them with rockwork and secondary steel, and installing the units.
Detailed design and issued-for-construction packages are complete.
Marine works, piling, dewatering and site utilities are being progressed separately by the existing early works contractor.
The hotel component covers roughly 31,700 sq m of gross floor area and will offer 321 guest rooms, four F&B outlets, spa and wellness facilities, a family pool, and meeting, incentive, conference and exhibition space.
The new contractor’s scope includes superstructure concrete works, façade and roof works, mechanical, electrical and plumbing, interior fit-out and landscaping.
Seven will consider only contractors with demonstrated experience delivering water parks with complex aquatics, theming and rockwork – either directly or through clearly defined subcontractor partnerships – along with a track record in high-end turnkey hotel fit-outs.
Construction of Seven’s Dammam entertainment complex is currently under way. In October 2023, Saudi Binladin Group won contracts worth around SR5bn ($1.3bn) from Seven to build two entertainment destinations in the Dammam and Al-Khobar areas of the Kingdom’s Eastern Province.
The Al-Khobar entertainment complex is being built on reclaimed waterfront land. The complex spans around 300,000 sq m and is also known as ‘The Waves’.
The Dammam entertainment complex spans 360,000 sq m and is being built on reclaimed land on the Dammam waterfront.
https://image.digitalinsightresearch.in/uploads/NewsArticle/17710096/main.jpg -
Al-Ula appoints equestrian village early works contractor21 July 2026

Saudi Arabia’s Royal Commission for Al-Ula (RCU) has awarded a contract for early construction works at the Al-Muatadil Equestrian Village.
The contract was awarded to Al-Khobar-based Al-Shalawi International Company.
Canadian engineering firm AtkinsRealis is the project management consultant. UK-headquartered Baker Wilkins & Smith and local firm Al-Hoty Company are the cost consultants.
Dubai-based SSH is the supervision consultant, and UK-based Hopkins Architects is the lead design consultant.
RCU announced the project plans in March 2023, including the development of an equestrian hub with two arenas that can accommodate 5,000 and 1,400 spectators, respectively.
The venue will also include grass polo, sand polo and endurance facilities, with capacities of 600, 400 and 600 seats, respectively.
These facilities will be complemented by visitor amenities, two stable compounds with capacity for 740 horses, and accommodation and retail outlets for event participants and workers.
https://image.digitalinsightresearch.in/uploads/NewsArticle/17710170/main.jpeg -
Contractors await decision on Riyadh airport sewage plant21 July 2026

Seven contractors are awaiting a decision on a contract to build a sewage treatment plant at the King Salman International airport (KSIA) development in Riyadh, according to sources.
It is understood that bids were submitted to King Salman International Airport Development Company (KSIADC) in March, following the tender’s release earlier this year.
The plant will treat wastewater generated by the airport and surrounding developments, including passenger terminals, runways, residential districts, commercial facilities and logistics areas.
The facility will have a treatment capacity of 92,000 cubic metres a day. The contract is estimated to be worth SR700m ($187m).
The bidders (all local) are:
- Al-Rawaf Trading & Contracting
- Almajal Alarabi
- Nesma Water & Energy
- Safari Company
- Saudi Services for Electro-Mechanic Works
- Washnah Contracting
- Water & Environment Technologies (Wetico)
The project scope includes the construction of the treatment plant, the installation of preliminary, secondary and tertiary treatment systems, sewage collection and conveyance pipelines, pumping stations, and electrical and control systems.
US-headquartered Jacobs is acting as the main project consultant. Commercial operations for the plant are scheduled for 2029.
The sewage treatment plant is one of several water infrastructure packages planned for the airport. KSIADC is also evaluating bids for a separate $30m engineering, procurement and construction contract covering potable water and fire water tanks and an associated pumping station. The same seven companies have submitted bids for that package.
Earlier in July, MEED exclusively reported that a joint venture of Beijing-headquartered China Civil Engineering Construction Corporation and Dammam-based Mofarreh AlHarbi & Partners had won a deal to undertake the enabling and substructure works for Terminal 6 at KSIA.
The latest development followed KSIADC’s receipt of prequalification statements from contractors on 1 July for two new packages at KSIA.
These include the construction of a permanent East-West corridor and landside access roads serving the North and South terminals.
https://image.digitalinsightresearch.in/uploads/NewsArticle/17709281/main.jpg -
Dubai Municipality awards Tasreef drainage contract21 July 2026

Dubai Municipality has awarded local firm Detech Contracting the engineering, procurement and construction (EPC) contract for the TF-15-C1 package of its Tasreef Rainwater Drainage Network programme.
It is understood the municipality issued the letter of award for the contract earlier this month, covering the construction of a stormwater drainage system along Al-Wasl Road and communities west of the Dubai Canal.
The project includes the construction of a gravity-based stormwater pipeline network with diameters of up to 3.5 metres. It is estimated to cost $100m.
It was tendered in February through the government’s Sewerage and Recycled Water Projects Department, with bids submitted in April.
The package forms part of the wider Tasreef initiative, which is intended to improve Dubai’s flood resilience.
The TF-15-C2 package was recently awarded to China State Construction Engineering Corporation for a stormwater drainage network project located along Umm Suqeim Road in the Al-Barsha and Al-Quoz areas of Dubai.
The project is estimated to cost $162m and includes the construction of about 20 kilometres of new stormwater pipelines. Similar to the C1 package, it is located west of the Dubai Canal and will connect the Al-Quoz 3 and Al-Quoz 4 industrial areas with Al-Quoz 1.
Separately, Al-Kharafi has won a drainage EPC contract (Ds207) to upgrade an existing pumping station for the municipality, a source said. The package focuses mainly on mechanical works and is valued at about $39m.
In May, MEED reported that local firm Nael Construction & Contracting had signed a contract with Dubai Municipality to build a sewage and stormwater drainage system in Dubailand.
The project (DS-204-C1) involves the construction of a drainage system with sewage gravity pipelines of up to 2,200mm in diameter.
https://image.digitalinsightresearch.in/uploads/NewsArticle/17707980/main.jpg