Adnoc Gas stalls decision on Ruwais NGL project
21 January 2026

Adnoc Gas is understood to be considering next steps regarding the progress of its project to install a fifth natural gas liquids (NGL) fractionation train at its Ruwais gas processing facility in Abu Dhabi.
The fifth NGL fractionation train will have an output capacity of 22,000 tonnes a day (t/d), or about 8 million tonnes a year.
Adnoc Gas, the natural gas processing business of Abu Dhabi National Oil Company (Adnoc Group), has adopted the design-update competition model to deliver the Ruwais NGL Train 5 project, MEED previously reported.
Contractors participating in the design-update competition for the project submitted commercial bids for engineering, procurement and construction (EPC) works by the deadline of 8 December, as part of the design‑update competition.
The design-update competition model involves the project operator selecting contractors to execute front-end engineering and design (feed) work on the project. The operator selects the contractor with the most competitive feed proposal to execute EPC works on the project, while also compensating the other contestants for their work.
Since receiving commercial bids from contractors in early December, however, Adnoc Gas is understood to have gone back to the drawing board to decide on the next course of action, according to sources.
Sources attribute the delay in contractor selection to bids received by Adnoc Gas that exceeded its budget.
In January 2025, MEED reported that Adnoc Gas had selected the following contractors to participate in the design-update competition for the Ruwais NGL Train 5 project:
- JGC Corporation (Japan)
- Technip Energies (France)
- Tecnimont (Italy)
MEED previously reported that participants had submitted technical proposals for feed work on 6 October.
The Ruwais NGL Train 5 project represents the second phase of Adnoc Gas’ Rich Gas Development programme and is estimated to be valued at $3.5bn-$4bn, according to the company’s chief financial officer, Peter Van Driel.
In a call with journalists in November to discuss Adnoc Gas’ financial results for the third quarter of 2025, Van Driel said Adnoc Gas was expected to achieve a final investment decision on the Habshan 7 gas train project in the first half of 2026.
ALSO READ: Adnoc Gas capex budget to rise to $28bn by 2029
The scope of work on the Ruwais NGL Train 5 project covers the EPC of the following units:
- NGL fractionation plant with a capacity of 22,000 t/d, including NGL fractionation facilities, downstream treatment units, sulphur recovery units, product storage, loading facilities and associated utilities, flares and interconnection pipelines with existing facilities;
- Two propane liquefied petroleum gas storage tanks and one paraffinic naphtha storage tank;
- Buildings – a central control building, outstations, substations and plant amenities;
- Electrical power connections. Power is to be sourced from the nearby Transco substation via a direct underground cable to the plot location.
Adnoc Gas requires the feed on the project to be updated based on the design of Ruwais NGL Train 4, which has an output capacity of 27,000 t/d and was commissioned in 2014.
In December 2021, MEED reported that Adnoc Gas, then operating as Adnoc Gas Processing, had awarded Indian contractor Larsen & Toubro Hydrocarbon Engineering the main contract for a project to enhance the capacity of its NGL trains 1-4 at the Ruwais complex.
Adnoc Gas business
Adnoc Group announced the creation of Adnoc Gas through the merger of its subsidiaries Adnoc Gas Processing and Adnoc LNG in November 2022. Adnoc Gas began operating as a commercial entity on 1 January 2023.
The consolidation of Adnoc’s gas processing and liquefied natural gas (LNG) operations into Adnoc Gas has created one of the world’s largest gas-processing entities, with a processing capacity of about 10 billion standard cubic feet of gas a day at eight onshore and offshore sites, which include its Asab, Bab, Bu Hasa, Habshan and Ruwais plants.
The company also owns a 3,250-kilometre (km) gas pipeline network to supply feedstock to its customers in the UAE. This sales gas pipeline network is being expanded to over 3,500km through the estimated $3bn Estidama project.
The company will also acquire its parent Adnoc Group’s 60% share in the Ruwais LNG terminal project at cost in the second half of 2028. UK energy producer BP, Japan’s Mitsui & Co, UK-based Shell and French energy producer TotalEnergies are the other shareholders in the project, holding 10% stakes each.
Adnoc Gas share sale
In February 2025, Adnoc Group completed a marketed offering of approximately 3.1 billion shares in Adnoc Gas, raising $2.8bn from the exercise.
The offering consisted of 3,070,056,880 shares, representing 4% of the issued and outstanding share capital of Adnoc Gas.
Following the marketed offering of shares, Adnoc Group continues to hold the majority 86% of shares in Adnoc Gas.
The parent entity listed 5% of Adnoc Gas’ shares on the Abu Dhabi Securities Exchange in March 2023, in an initial public offering from which it raised about $2.5bn.
Abu Dhabi National Energy Company (Taqa) owns the remaining 5% shares in Adnoc Gas.
ALSO READ: Contractors submit prices for Habshan 7 project to Adnoc Gas
READ THE JANUARY 2026 MEED BUSINESS REVIEW – click here to view PDF
Saudi Arabia courts real estate investment; EVs and battery production are key regional tech themes; Muscat holds a steady growth course despite headwinds
Distributed to senior decision-makers in the region and around the world, the January 2026 edition of MEED Business Review includes:
|
> AGENDA: Saudi real estate to surge in 2026
> BATTERIES: Batteries shape the region's energy future
> INTERVIEW: Tabreed finishes the year on a high
> CONTRACTORS: Managing risk in the GCC construction market
> ECONOMIC ACTIVITY INDEX: UAE and Qatar emerge as markets to watch
> AIRSHOW: Top deals signed at Dubai Airshow 2025
> MARKET FOCUS: Oman steadies growth with strategic restraint
|
Exclusive from Meed
-
Chinese contractor wins Morocco solar plant deal10 August 2026
-
Aramco puts out fire at Jizan refinery after Houthi strike10 August 2026
-
Shamal picks Dutco for Dubai Zoo site homes10 August 2026
-
WEBINAR: Mena Oil & Gas Projects Market 2026-2710 August 2026
-
Spanish firm renews Yanbu desalination O&M contract10 August 2026
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Chinese contractor wins Morocco solar plant deal10 August 2026
China Harbour Engineering Company (CHEC), a subsidiary of China Communications Construction Company (CCCC), has won a contract to build a solar photovoltaic (PV) power plant in Fez in northern Morocco.
Known as GreenPower Morocco 4 (GPM4), the project is being developed by Moroccan company GPM Holding through its utility-scale solar subsidiary GPM Parks.
The project covers engineering design, equipment procurement and installation, construction of an operation and maintenance building, grid connection and commissioning. It also includes upgrades to the associated substation.
According to CHEC, the completed plant will supply electricity to the local grid, although it did not disclose the project’s capacity or contract value.
The project is being developed under Law 13-09, which provides Morocco’s framework for private renewable energy generation.
According to its website, GPM Holding is also developing another solar PV project called GreenPower Morocco 2 (GPM2). This follows the completion of its first solar project, the 34MW project (GPM1) commissioned in Tangier in 2024.
GPM1 was developed by Green Power Morocco, a special purpose vehicle owned by GPM Holding and UAE-based Amea Power. The $30m project covers 75 hectares and includes 91,000 PV panels. It is expected to generate about 66,149MWh a year.
The project has a 25-year power purchase agreement in place with Amendis, a subsidiary of Veolia Morocco. PowerChina was the main engineering, procurement and construction (EPC) contractor.
Chinese contractors have previously been involved in other projects in Morocco’s renewable energy sector.
Shandong Electric Power Construction Company (Sepco 3), a subsidiary of PowerChina, was part of the EPC consortium for the 200MW Noor 2 concentrated solar plants and 150MW Noor 3 concentrated solar power projects at the Noor Ouarzazate complex.
New contract awards have been limited in Morocco in 2026, although six solar PV plants are now in the execution stage under phases one and two of the 305MW Noor Atlas solar PV programme.
https://image.digitalinsightresearch.in/uploads/NewsArticle/18263680/main.jpg -
Aramco puts out fire at Jizan refinery after Houthi strike10 August 2026
Saudi Aramco said it had extinguished a fire that broke out at its Jizan refinery on Saudi Arabia’s Red Sea coast after the facility was hit in drone strikes by Yemen-based Houthi rebels on 9 August.
The kingdom’s Ministry of Energy said the fire occurred at an Aramco refinery facility in Jizan and that emergency authorities had completed the necessary procedures to deal with the incident.
The energy ministry did not say what started the fire, saying only that the incident caused no injuries.
The Houthi rebels later claimed responsibility for the attack.
The province of Jizan lies close to Saudi Arabia’s border with Yemen and has repeatedly been targeted by the Houthis in attacks on the kingdom’s energy infrastructure.
The strike on the Jizan refinery was the second attack on the facility by the Houthis in as many weeks. Aramco shut the refinery on 27 July following a similar drone strike, which, according to media reports, damaged the integrated gasification combined-cycle unit and tank farm at the complex.
On a call with investors to discuss Aramco’s second-quarter results, CEO Amin Nasser said recent attacks on the company’s facilities in the world’s top oil-exporting country had caused some disruption to production, but that he was confident operations could be restored quickly. He said the attacks had had no material operational or financial impact.
Jizan refinery complex
Saudi Aramco’s sprawling Jizan refinery complex entered operations in 2021.
Aramco undertook the estimated $16bn-plus project in late 2010. The scheme consists of a refinery with an output capacity of 400,000 barrels a day (b/d), a major marine terminal and a 4GW combined-cycle power plant in Baish, in Saudi Arabia’s southwestern Jizan region.
The Jizan refinery covers an area of 12 square kilometres. The complex processes Arabian Heavy and Arabian Medium crude grades to produce 80 million b/d of gasoline, 250 million b/d of diesel and more than 1 million tonnes a year of petrochemical products such as benzene and paraxylene.
A multiple-pier marine terminal supports the supply of crude oil from oil fields located mainly in the kingdom’s Eastern Province to the refinery, as well as the export of surplus refined products to overseas markets. The terminal has been designed to accommodate very large crude carriers.
A 4,000MW combined-cycle power plant uses approximately 90,000 b/d of vacuum residue from the refinery to generate electricity, hydrogen and water for the refinery, while conveying excess power to the national grid.
The hydrocracker unit comprises two parallel trains with a combined capacity of 54,500 b/d. The diesel hydrotreater plant comprises two trains, each with a capacity of 87,500 b/d.
https://image.digitalinsightresearch.in/uploads/NewsArticle/18262347/main.jpg -
Shamal picks Dutco for Dubai Zoo site homes10 August 2026
Dubai-based Shamal Holding has awarded local contractor Dutco Construction the main construction works contract for a low-rise residential project on the site of the former Dubai Zoo in Jumeirah 1.
The project will comprise 90 low-rise homes and is designed as a residential leasing community that will remain under Shamal’s ownership, with all homes offered for premium leasing.
The development will retain mature trees from the former zoo and is planned around shared courtyards, landscaped open spaces and a central park. Residents will have access to a clubhouse, wellness area, children’s play area, family pool, lounge and gym.
The architect is DXB Lab. The local H&H is the development manager for the project.
Dutco has previously worked with Shamal on infrastructure elements of the Dubai Harbour and Dubai Harbour Marinas developments.
Shamal’s wider real estate portfolio includes the Naia Island, Dubai Harbour and Nad Al-Sheba Gardens developments. The company also holds hospitality and leisure assets, including partnerships with Jumeirah, Hilton and Baccarat, and operates attractions such as Skydive Dubai and Deep Dive Dubai.
https://image.digitalinsightresearch.in/uploads/NewsArticle/18262386/main.png -
WEBINAR: Mena Oil & Gas Projects Market 2026-2710 August 2026
Webinar: Mena Oil & Gas Projects Market 2026-27
Thursday 27 August 2026 | 11:00 AM GST | Register now
Agenda:
- Summary of the Mena oil, gas and petrochemicals projects market
- Overview of major megaprojects, including project programmes
- Analysis of active contracts and spending to date
- Review of top contracts by work already awarded
- Long-term capital expenditure outlays and forecasts
- Key contracts expected to be tendered and awarded over the next 18 months
- Leading clients, contractors and market participants
- Spending by segment: oil, gas and petrochemicals (upstream, downstream, onshore and offshore)
- Audience Q&A
Hosted by: Indrajit Sen, MEED’s oil & gas editor
https://image.digitalinsightresearch.in/uploads/NewsArticle/18260597/main.gif -
Spanish firm renews Yanbu desalination O&M contract10 August 2026
Spain’s Aqualia has announced it has renewed a contract to operate and maintain three floating desalination plants in Yanbu on Saudi Arabia’s Red Sea coast.
The contract was awarded by the National Shipping Company of Saudi Arabia (Bahri) and will run until 14 September 2028, with an option to extend for a further two years.
The three reverse osmosis (RO) plants are mounted on barges and have a combined production capacity of 150,000 cubic metres a day (cm/d). Each plant has a capacity of 50,000 cm/d.
The three plants were originally deployed at Al-Shuqaiq and are designed to be relocated along Saudi Arabia’s coastline according to water demand. The barges are currently located at Yanbu.
The $255m floating desalination project was commissioned for the Saudi Water Authority in 2022, with Bahri as the developer and UAE-based Metitio as the main contractor.
Bahri is publicly listed on the Saudi Exchange but has significant government ownership, with the Public Investment Fund (PIF) holding 22.5% and Saudi Aramco Development Company owning 20% of the company.
Aqualia is providing operation and maintenance services in Saudi Arabia through its joint venture Haji Abdullah Alireza Integrated Services Company (Haaisco), in which it holds a 51% stake.
https://image.digitalinsightresearch.in/uploads/NewsArticle/18259350/main.jpg