Adnoc Gas selects contractors for fifth Ruwais NGL train project

16 January 2025

Register for MEED's 14-day trial access 

Adnoc Gas, the natural gas processing business of Abu Dhabi National Oil Company (Adnoc Group), has selected contractors to participate in an engineering design update competition for a project to install a fifth natural gas liquids (NGL) fractionation train at its Ruwais gas processing facility in Abu Dhabi.

The fifth NGL fractionation train will have an output capacity of 22,000 tonnes a day (t/d) or about 8 million tonnes a year.

Adnoc Gas has adopted the design update competition model to deliver the Ruwais NGL Train 5 project, MEED previously reported.

The design update competition model involves the project operator selecting contractors to execute the front-end engineering and design (feed) work on the project. The operator selects the contractor with the most competitive feed proposal to execute engineering, procurement and construction (EPC) works on the project, while also compensating the other contestants for their work.

According to sources, Adnoc Gas has selected the following contractors to perform feed work on the Ruwais NGL Train 5 project as part of the design update competition:

  • JGC Corporation (Japan)
  • Technip Energies (France)
  • Tecnimont (Italy)

Adnoc Gas has held kick-off meetings with each of the selected contractors to brief them about the project’s scope of work, as per sources.

Contractors submitted technical bids for the project by 15 November, while commercial bids were submitted by 29 November, MEED earlier reported.

In addition to the three contractors selected by Adnoc Gas to participate in the design update contest, the other bidders for the project were a consortium of UK-based Petrofac and South Korea’s GS Engineering & Construction, and Spanish contractor Tecnicas Reunidas.

The scope of work on the Ruwais NGL Train 5 project covers the EPC of the following units:

  • NGL fractionation plant with a capacity of 22,000 t/d, including NGL fractionation facilities, downstream treatment units, sulphur recovery units, products storage, loading facilities and associated utilities, flares and interconnection pipelines with existing facilities
  • Two propane liquefied petroleum gas storage tanks and one paraffinic naphtha storage tank
  • Buildings – a central control building, outstations, substations and plant amenities
  • Electrical power connections. Power is to be sourced from the nearby Transco substation via a direct underground cable to the plot location

Adnoc Gas requires the feed on the project to be updated based on the design of the Ruwais NGL Train 4, which has an output capacity of 27,000 t/d and was commissioned in 2014.

MEED previously reported that Adnoc Gas issued the expression of interest (EoI) document for the feed-to-EPC competition on 28 February, with contractors submitting their responses to the EoI document by the deadline of 11 March.

Adnoc Gas business

Adnoc Group announced the creation of Adnoc Gas through the merger of its subsidiaries Adnoc Gas Processing and Adnoc LNG in November 2022. Adnoc Gas began operating as a commercial entity from 1 January 2023.

The consolidation of Adnoc’s gas processing and liquefied natural gas (LNG) operations into Adnoc Gas has created one of the world’s largest gas-processing entities, with a processing capacity of about 10 billion standard cubic feet of gas a day across eight onshore and offshore sites, which include its Asab, Bab, Bu Hasa, Habshan and Ruwais plants.

The company also owns a 3,250-kilometre gas pipeline network to supply feedstock to its customers across the UAE. This sales gas pipeline network is being expanded to over 3,500km through the estimated $3bn Estidama megaproject.

In December 2021, MEED reported that the erstwhile Adnoc Gas Processing had awarded Indian contractor Larsen & Toubro Hydrocarbon Engineering the main contract for a project to enhance the capacity of its NGL trains 1-4 at the Ruwais complex.

Financial performance

Adnoc Gas announced a net profit of $1.24bn for the third quarter of 2024, a year-on-year increase of 11%.

The company’s third-quarter revenue was recorded at $6.28bn, up 8% year-on-year, as higher product prices offset a drop in domestic sales volumes.

Free cashflow in the third quarter fell 9% year-on-year from $1.31bn to $1.18bn, as capital expenditure increased 45% to $503m.

For the first nine months of 2024, Adnoc Gas registered a net income of $3.62bn, up 18% year-on-year, excluding a non-recurring gain of $298m from recognising a deferred tax asset.

Adnoc Gas is working to increase its natural gas processing capacity by 20% within the next five years, for which it has been allocated a $15bn capital expenditure portfolio until 2029.

The company expects its capex in 2024 to be in the range of $1.9bn-$2.2bn.

Separately, Adnoc Gas earlier stated it will acquire its parent Adnoc Group’s 60% stake in the upcoming Ruwais LNG facility, at cost, in the second half of 2028 when first production from the complex is due.

ALSO READ: New CEOs take charge at Adnoc gas business units

https://image.digitalinsightresearch.in/uploads/NewsArticle/13272653/main4808.jpg
Indrajit Sen
Related Articles
  • Kuwait awards $381m oil project

    23 September 2026

    Register for MEED’s 14-day trial access 

    State-owned upstream operator Kuwait Oil Company (KOC) has awarded an oil project contract worth KD117m ($381m) to India’s Megha Engineering & Infrastructure (Meil).

    The Supreme Purchasing Committee for Kuwait Petroleum Corporation (KPC) approved the contract last month, paving the way for the official award.

    The project focuses on a water separation unit at the Al-Rawdatain facility in Kuwait.

    The water separation facility will be developed at Gathering Centre 25 (GC-25), along with a pumping facility at GC-30.

    The project will deliver a wide-ranging upgrade of processing and utility infrastructure, including new low-pressure separation and gas-handling equipment such as a three-phase wet separator package, a gas knock-out drum and associated low-pressure gas pipelines, as well as a high-integrity pressure protection system and a high-pressure flare.

    Meil will develop the new three-phase low-pressure wet separation facility at GC-25.

    The main process equipment will include two wet separator packages, each with a capacity of 150,000 barrels of liquid a day, and a low-pressure gas knock-out drum with a capacity of 53 million standard cubic feet a day, together with associated gas-handling facilities.

    The facility will also incorporate an effluent water treatment and transfer system, including an effluent water balance tank equipped with microbubble flotation and induced gas flotation systems, as well as transfer pumps.

    Additional GC-25 facilities will include fuel gas treatment, chemical injection, oil recovery and flare connections, along with firewater and deluge systems.

    The scope also covers control and safety systems, substations, and associated civil, structural, mechanical, electrical and instrumentation works.

    At GC-30, the project will focus on treated-water filtration and high-pressure injection infrastructure.

    The scope includes nutshell filters and associated feed pumps with a combined capacity of approximately 500,000 barrels of water a day.

    Booster and injection pumps will transfer treated effluent water to designated injection wells.

    Additional facilities at GC-30 will include fuel gas treatment, sludge collection and disposal systems, oil recovery systems, control and safety systems, substations, laboratory and workshop facilities, and associated civil, structural, piping, mechanical, electrical and instrumentation works.

    The project also includes transfer pipelines connecting GC-25, GC-15 and GC-30.

    Meil will carry out modifications to existing tanks at GC-30, as well as process and utility tie-ins, electrical and instrumentation modifications and other infrastructure required to integrate the new facilities with KOC’s existing assets.

    Meil’s responsibilities cover the project lifecycle from design and engineering through procurement, construction, testing, pre-commissioning, commissioning, start-up and performance testing.

    The contract also includes operation, maintenance, repair and insurance responsibilities for the designated facilities during the applicable operations and maintenance period.

    Seven companies submitted bids for the project last November.

    The full list of bids was:

    • Meil (India) – KD117m ($381m)
    • Mechanical Engineering & Contracting Company (Kuwait) – KD130m
    • Spetco (Kuwait) – KD158m
    • Al-Kharafi (Kuwait) – KD164m
    • China Oil HBP Science & Technology (China) – KD169m
    • Alghanim International (Kuwait) – KD169m
    • Jereh Oil & Gas Engineering (China) – KD191m

    In October last year, KOC awarded Meil a separate contract for a project to develop a gas sweetening and recovery facility in west Kuwait.

    Meil submitted the lowest bid for that tender, at KD69.2m ($225.5m), in February 2025.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19911322/main.jpg
    Wil Crisp
  • Kuwait refinery project on track for year-end completion

    23 September 2026

     

    A $65m project to replace a substation at the Mina Al-Ahmadi (MAA) refinery is on schedule to be mechanically complete before the end of the year, according to industry sources.

    The project is being executed by India’s Larsen & Toubro (L&T), which was awarded the contract in October 2024.

    One source said: “This project is approaching completion and is currently on schedule to be completed before the end of the year, although it could still see delays related to the ongoing regional conflict.”

    The client is state-owned downstream operator Kuwait National Petroleum Company (KNPC).

    Kuwait’s Ministry of Electricity, Water & Renewable Energy (MEW) is also involved in the project and will provide final approvals and sign-off.

    The scope of the project includes:

    • Construction of a substation
    • Installation of transformers
    • Installation of medium-voltage switchgear
    • Installation of low-voltage auxiliary systems
    • Installation of network protection systems
    • Installation of disconnecting switches
    • Installation of surge arrestors
    • Installation of feeder breakers and cubicles
    • Installation of low-voltage A/C and D/C equipment
    • Installation of battery banks and battery chargers
    • Installation of related relay and control panel boards
    • Installation of fire alarm and fire protection equipment
    • Installation of a SCADA system
    • Installation of cables
    • Civil works
    • Associated facilities

    The current project to replace a substation at the MAA refinery closely resembles another project tendered by KNPC more than a decade ago, which L&T also won.

    On 18 May 2015, KNPC signed a contract with L&T to build a new 240MW substation at the MAA refinery, valued at KD21.866m.

    The new substation, known as M20, was designed to replace an existing substation that was considered old and obsolete.

    Mohammed Al-Mutairi, who was KNPC’s chief executive at the time, said the substation building would be explosion-proof and use state-of-the-art control systems.

    He said the station’s capacity would increase from 180MW to 240MW, supplying most of the refinery’s electricity needs.

    Given the similarities between the two projects, L&T has been able to reuse some designs, creating efficiencies, according to industry sources.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19911319/main.jpg
    Wil Crisp
  • Contractor wins $208m Almoosa hospital MEP contract

    23 September 2026

    Register for MEED’s 14-day trial access 

    Riyadh-based construction firm BEC Arabia has won a SR781m ($208m) contract for the mechanical, electrical and plumbing (MEP) works at Almoosa Hospital in Al-Khobar.

    Saudi Arabia’s Almoosa Health Company awarded the contract.

    The hospital complex consists of two towers: a 24-storey in-patient tower with 380 beds, and an 11-storey tower with 224 clinics and 113 additional treatment spaces.

    It will be built on a 45,000-square-metre site.

    A podium spanning the ninth and 10th floors will connect the two towers.

    The hospital will also include parking for 1,700 cars.

    BEC Arabia won the SR656m ($175m) main construction contract for the hospital in November last year.

    In August 2025, MEED reported that Almoosa Health Company had announced it had secured a sharia-compliant credit facility worth SR650m ($173m) from Banque Saudi Fransi.

    In a statement published on the Saudi stock exchange (Tadawul), the company said the seven-year facility would be used to support its expansion and growth strategy.

    Lebanon’s Dar, US-based Perkins&Will and French design firm Pierre-Yves Rochon designed the project.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19910889/main.jpg
    Yasir Iqbal
  • UAE to develop integrated waste-to-resource pilot

    23 September 2026

    Emirates Biotech and United Arab Emirates University (UAEU) have launched a pilot project in Al-Ain that could provide a model for larger waste-to-resource facilities.

    The project involves developing the UAE’s first integrated organic-waste valorisation pilot plant, which will test whether food waste and compostable packaging can be processed together to recover resources and reduce waste sent to landfill.

    Located near the UAEU campus, the 40kg-a-day facility will process organic waste to produce renewable biogas and nutrient-rich compost. The project is intended to generate technical and operating data that could support the development of larger-scale facilities.

    Emirates Biotech and UAEU will design, build and operate the pilot plant as part of a two-year research project running from August 2026 to August 2028. Installation and commissioning are expected to be completed by August 2027.

    The plant will combine anaerobic digestion and composting. Anaerobic digestion will convert the organic waste into renewable biogas, while the resulting digestate will be composted to produce nutrient-rich compost.

    A laboratory-scale assessment will also examine the potential to convert the biogas into renewable hydrogen.

    Food waste accounts for nearly 40% of daily municipal solid waste in the UAE, according to Emirates Biotech, and much of it is currently disposed of in landfills.

    The pilot will therefore assess the technical and operational feasibility of recovering value from two waste streams through a single integrated process.

    If successfully scaled, Emirates Biotech says an integrated organic-waste valorisation plant could reduce CO₂ emissions by 89% compared with landfilling.

    The project is expected to provide a scalable and modular model for converting food waste and compostable packaging into renewable biogas and compost, with the findings intended to inform the development of larger waste-to-resource facilities.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19908972/main.jpg
    Mark Dowdall
  • Contractors prepare Oxagon Highway 55 bids

    23 September 2026

     

    Contractors are preparing to submit bids on 28 September for a design-and-build contract for permanent upgrade works on Highway 55 in the kingdom’s Oxagon region.

    The first phase of the project includes constructing 14 kilometres of road, with two lanes in each direction. It also includes one bridge and three interchanges.

    The project duration is 22 months.

    Highway 55 connects the Red Sea coast with the mainland in northwestern Saudi Arabia. It is currently the only road providing north-south connectivity between Duba and the Neom region.

    MEED reported exclusively in August 2025 that contractors had submitted responses to an expression of interest notice that Neom had issued earlier that month.

    The project is expected to support cargo movement from Duba Port to other parts of the kingdom and the wider region.

    Last year, Neom tested a pilot initiative by handling a shipment that travelled from Cairo via the Port of Safaga, across the Red Sea to the Port of Neom, and then inland to Erbil, Iraq.

    In a statement, Neom said: “The shipment travelled through an intermodal corridor spanning over 900 kilometres, marking a significant milestone in the kingdom’s transformation into a regional and global logistics hub.”

    The Port of Neom is located on the Red Sea near the Arar border, a key entry point into Iraq.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19907876/main.jpg
    Yasir Iqbal