Adnoc Gas awards EPC contract for Ewec sales pipeline
1 October 2026

Adnoc Gas has awarded the main contract for a project to build a new pipeline that will supply gas from the Habshan scraper launcher station at its Habshan gas compression complex to the Al-Nouf customer receiving station (CRS), for delivery to Emirates Water & Electricity Company (Ewec).
The proposed 56-inch pipeline, stretching 127 kilometres, will help the UAE’s state utility, Ewec, meet additional gas demand to power the second phase of an artificial intelligence (AI) data centre in Abu Dhabi, as well as support the relocation of some of its key assets in the Mirfa area of the emirate.
Adnoc Gas has awarded the engineering, procurement and construction (EPC) contract for the project to India-based Kalpataru Projects International, according to sources.
Kalpataru confirmed the contract award in a disclosure to the Bombay Stock Exchange (BSE) on 28 September. The Mumbai-headquartered contractor did not identify the project in its BSE filing, only describing the contract as “major” – a term it uses to denote values over INR40bn ($415.5m).
Adnoc Gas, the natural gas processing business of Abu Dhabi National Oil Company (Adnoc Group), issued the tender in mid-April for the project, officially titled ‘Ewec Mirfa relocation + AI data centre phase 2: Habshan to Al-Nouf pipeline’.
Contractors submitted technical bids for the project in late May, while commercial bids were submitted on 3 August, MEED previously reported.
According to sources, the following contractors, among others, are understood to have submitted bids:
- Arkad Engineering & Construction (Saudi Arabia; part of Italy’s Arkad)
- China Petroleum Pipeline Engineering (China)
- Galfar Emirates (UAE branch of Oman’s Galfar Engineering & Construction)
- Kalpataru Projects International (India)
China Petroleum Pipeline Engineering has performed front-end engineering and design (feed) work on the project.
The planned pipeline will provide two sales-gas streams to Ewec: 600-660 million cubic feet a day (cf/d) for AI data centre phase 2, and 650-715 million cf/d for the Mirfa relocation project.
The core elements of the project involve the EPC of the main Habshan-to-Al-Nouf pipeline and the following associated units:
- 56-inch scraper (pig) launcher (607-V-604) and associated hot tap
- Four block valve stations (BVSs -637-BVS-01/02/03/04)
- 56-inch scraper (pig) receiver (848-V-101)
- CRS at Al-Nouf including sales gas filters, pressure regulating stations (PRS), custody transfer metering systems (CTMS)
- 30-inch tapping to Ewec plants (cold tie-ins)
- 52-inch tie-ins between Adnoc Gas’ Maximise Ethane Recovery & Monetisation (Meram) project and package 3 of its broader project to upgrade its sales gas pipeline network across the UAE, also known as Estidama.
The detailed scope of work on the Ewec Mirfa relocation + AI data centre phase 2: Habshan to Al-Nouf pipeline project covers the following:
- 56-inch sales gas pipeline from Habshan to Ewec Al-Nouf plant:
- The new 56-inch sales gas pipeline from Habshan to Al-Nouf CRS, covering 127km, will supply sales gas to Ewec plant. Majority of the pipeline route is through the Sabkha area (approximately 100km) and will be routing parallel to existing pipeline facilities. FOCs shall be laid on both sides of the pipeline. Approximately 30 NDRCs (mostly micro tunneling) are envisaged for this pipeline.
- The 56-inch pipeline is envisaged with four block valve stations 647-BVS-01-04 based on the pipeline location class study.
- The pipeline shall be provided with scrapper launcher at Habshan (located in Estidama package 3 scrapper launcher plot) along with 48-inch hot tap tie-in at the gas source point (on existing 56-inch supply line manifold) and scraper receiver at Al-Nouf CRS for pipeline cleaning and inspection.
- Habshan outlet battery limit, available battery limit pressure is 39 – 41.5 barg.
- At Al-Nouf CRS the tie-in pressure requirement is minimum 25 barg downstream of the CRS facilities at the tie-in point to Al-Nouf plant.
- Maximum pressure during line pack condition is 41.5 barg.
- Facilities at Al-Nouf CRS:
- 56” Scraper Receiver with Scrapper Handling Trolley and Jib crane. Both CRSs shall be identical in design and size.
- The battery limit pressure at tie-in connection to Al-Nouf is 25 barg.
- Electrical and Instrumentation (E&I) building and fire point shelter.
- Permanent power supply to CRS from Ewec or Taqa and associated facilities.
- AI data centre phase 2 project – CRS 1:
- Sales gas filters (duty + standby configuration)
- Custody transfer metering skid (duty + standby configuration)
- Pressure regulating skid (duty + standby configuration)
- Gas chromatograph, hydrocarbon dew point analyser inside AC shelter
- Flow limiting control valves with bypass control valves
- 30-inch cold tie-in to AI data centre phase 2.
- Mirfa relocation – CRS 2:
- Sales gas filters (duty + standby configuration)
- Custody transfer metering skid (duty + standby configuration)
- Pressure regulating skid (duty + standby configuration)
- Gas chromatograph, hydrocarbon dew point analyser inside AC shelter
- Flow limiting control valves with bypass control valves
- 30-inch cold tie-in to Mirfa relocation power plant.
- 52-inch jump over between Meram and Estidama package 3:
- A 52-inch interconnection including ROV and associated facilities shall be provided between Meram 56” sales gas pipeline tie-in and Estidama package-3 56-inch pipeline tie-in. 52-inch piping to be installed on the existing / new pipe rack to cross the existing pipeline corridor. Cold tap Tie-ins on both existing pipeline is envisaged to install this jump-over connection.
- The existing Meram plot or Estidama package 3 plot at 8.2km shall be extended to install the new ROV and associated facilities.
- The new 52-inch ROV and associated facilities shall be connected to the Meram area existing systems and suitable modification and integration with SMC/telecommunication systems shall be performed by the EPC contractor.
- Necessary adequacy checks shall be performed on the piping structures, supports, plots, systems, as applicable.
- Electrical and instrumentation buildings:
- E&I building type 1 at Al-Nouf CRS.
- Block valve station (BVS) shall be provided with hybrid cooling shelter for equipment installation in case solar power system is to be adopted. If power source available nearby, electrical and instrumentation building (type 2) is to be provided.
The duration of EPC works on the project is 31 months from the award of contract.
ALSO READ: Adnoc Gas to move prudently on Bab gas cap project
Exclusive from Meed
-
Rabigh 2 IPP expansion secures $2.58bn financing5 October 2026
-
Dubai announces $490m e-commerce hub expansion plan5 October 2026
-
Iraq and Turkiye discuss oil and gas deal5 October 2026
-
Contractors submit bids for Libya refinery5 October 2026
-
Dubai tenders sewage and stormwater projects5 October 2026
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Rabigh 2 IPP expansion secures $2.58bn financing5 October 2026
Saudi Arabia’s Rabigh 2 combined-cycle gas-turbine (CCGT) independent power project (IPP) expansion has reached financial close.
In a disclosure to the Saudi Exchange, Acwa said it had secured SR9.69bn ($2.58bn) in long-term financing for the project, which has a generation capacity of 2,313.5MW.
In April, MEED reported that Acwa and Saudi Energy (formerly Saudi Electricity Company) had signed a 31-year power purchase agreement (PPA) with Saudi Arabia’s principal buyer, Saudi Power Procurement Company (SPPC), for the project.
The project involves developing a CCGT plant in the Mecca region. It is being developed by Al-Morjan Two Electricity Company, with Acwa and Saudi Energy each owning a 40% stake in the project.
The contract is valued at SR11.5bn ($3.07bn), the companies said in separate stock exchange filings at the time. The carbon-capture-ready power plant will be implemented under a build, own and operate contract.
The financing has a tenor of about 34 years and was provided by a consortium of local, regional and international lenders.
The lenders are:
- Abu Dhabi Commercial Bank
- Alinma Bank
- Boubyan Bank
- China Minsheng Banking Corporation, Hong Kong Branch
- Commercial Bank of Dubai
- HSBC Bank Middle East
- Industrial and Commercial Bank of China
- Industrial Bank, Beijing Branch
- National Bank of Greece, Cyprus
- Riyad Bank
- Saudi Awwal Bank
- Saudi National Bank
- Standard Chartered Bank, Taiwan
- Sumitomo Mitsui Trust Bank, London Branch
The project scope also includes financing and expanding a 380kV electrical substation.
According to regional project tracker MEED Projects, construction works have commenced on the project, and a joint venture of Egypt’s Elsewedy Electric and China’s Sinohydro has been working as the main contractor.
Rabigh 1 extension
In January, Saudi Energy announced a separate energy conversion agreement with SPPC for the purchase of electricity from the Rabigh 1 power plant expansion.
The contract is valued at SR5.33bn ($1.42bn).
It covers the development, financing, construction, ownership and operation of the gas-fired power plant, which will have a generation capacity of 1,179MW.
A joint venture of Elsewedy Electric and Germany’s Siemens Energy is undertaking the engineering, procurement and construction work for the project, which is expected to be completed by the end of 2026.
US/India-based Synergy Consulting is the financial advisory consultant to Saudi Energy on this project.
Acwa also recently started initial commercial operations at the Taiba 1 and Qassim 1 CCGT power plants, as reported by MEED.
The plants have a combined generation capacity of about 3.8GW and are two of four projects procured under the first round of Saudi Arabia’s gas-fired IPP programme by SPPC.
A team of Saudi Energy and Acwa won the contract to develop and operate the projects in 2023.
MEED’s October 2026 report on Saudi Arabia includes:
> COMMENT: Saudi projects hold steady
> GOVERNMENT: Riyadh looks to reset its regional defence outlook
> ECONOMY: Conflict bolsters case for Saudi economic diversification
> BANKING: Saudi lenders readjust to lower lending and deposit climate
> UPSTREAM: Aramco upstream spending gathers pace
> DOWNSTREAM: Sabic steps up Saudi petchems investment
> POWER: Saudi Arabia’s power award activity slows
> WATER: Saudi water sector hits sharp slowdown
> CONSTRUCTION: Saudi construction defies the headwinds
> TRANSPORT: Saudi infrastructure pushes forward amid conflict
> DATABANK: Saudi data indicates project spending shiftTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/20270643/main.jpg -
Dubai announces $490m e-commerce hub expansion plan5 October 2026
Dubai CommerCity has launched a second expansion phase valued at more than AED1.8bn ($490m), adding over 91,000 square metres (sq m) of office, retail and logistics space across the free zone’s business, social and logistics clusters.
Dubai CommerCity is a joint venture of Dubai Airport Free Zone Authority (Dafza) and Dubai government-owned Wasl Asset Management Group.
The expansion is scheduled for delivery between the first quarter of 2027 and the fourth quarter of 2028.
The developer said the move builds on sustained demand at Dubai CommerCity, where occupancy has reached nearly 96% across its office, logistics and retail assets.
Phase two will comprise a series of developments across Dubai CommerCity’s three districts: the Business Cluster, Logistics Cluster and Social Cluster.
The Business Cluster comprises 13 office buildings with a total leasable area of 108,000 sq m. The Logistics Cluster consists of 84 logistics units with a leasable area of 68,000 sq m, while the Social Cluster features art galleries, restaurants and cafes. The development will also include 4,000 parking spaces.
Dafza and Wasl Asset Management Group announced plans to develop the AED2.7bn ($735m) e-commerce free zone In 2017.
READ THE OCTOBER 2026 MEED BUSINESS REVIEW – click here to view PDFIndustry and logistics drive development at Neom; Saudi Arabia’s investment priorities realign amid conflict; MEED’s 2026 power developer ranking.
Distributed to senior decision-makers in the region and around the world, the October 2026 edition of MEED Business Review includes:
> AGENDA: Oxagon takes centre stage at Neom> MARKET FOCUS: Saudi projects hold steady> INDUSTRY REPORT: MEED’s 2026 GCC power developer ranking> LEADERSHIP: The future city does not need to hang above the groundTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/20270228/main.jpg -
Iraq and Turkiye discuss oil and gas deal5 October 2026
Iraq and Turkiye have opened talks in Ankara on a framework agreement for oil, gas and energy cooperation, according to a statement from the Iraqi Oil Ministry.
Iraq’s Oil Minister Bassem Mohammed Khudair Al-Abadi led the Iraqi side, while the Turkish Energy and Natural Resources Minister Alparslan Bayraktar led the Turkish side.
Officials discussed a proposed roadmap to deepen work on oil and gas infrastructure, petrochemicals, and trade in oil, gas and power.
Discussions about a future long-term deal to govern the Iraq-Turkiye Pipeline (ITP) were central to the talks.
The ITP exports oil from northern Iraq to the port of Ceyhan in Turkiye.
In July, Turkiye and Iraq signed a temporary agreement to allow crude flows through the ITP for a period of 12 months.
Before the temporary agreement was signed, the previous deal governing oil exports through the pipeline was due to expire on 27 July.
Speaking last month, Ali Al-Shatri, director general of Iraq’s state organisation for marketing oil (Somo), said the temporary deal was “a prelude” to a much bigger agreement.
As well as governing pipeline exports, the new agreement is expected to cover electricity, chemicals and gas deals as well as the construction of a new oil refinery in Ceyhan.
Under current plans, the new refinery will process Iraqi crude in order to produce refined products that can be exported to Europe.
Bayraktar said: “Following the crude oil transportation agreement signed between our national company … we are clarifying our roadmap for a new, longer-term and more comprehensive agreement.
“In this regard, we plan to activate our joint working groups to rapidly finalise oil and natural gas infrastructure, exploration and production, oil trading, refining-petrochemical and electricity projects.
“In close cooperation with the new Iraqi Government, we will strongly continue to implement these concrete projects for the stability and prosperity of our shared geography.”
Bayraktar said it was important to consider extending the Kirkuk-Ceyhan pipeline to reach Basra in southern Iraq.
He also said it was important to consider expanding the capacity of the ITP to create a strong alternative to the Strait of Hormuz.
The Strait of Hormuz is a key oil export route that has been disrupted by a regional war since the US and Israel attacked Iran on 28 February.
Bayraktar also said that he wanted state-owned Turkish Petroleum Corporation (TPAO) to expand its footprint in Iraq.
He said: “We aim for our national company TPAO to play an active role not only in the Kirkuk fields but also in different fields in Iraq, to reach the target of supplying one million barrels of crude oil as stated by Iraqi Prime Minister Ali ez-Zeydi; and to transform Ceyhan into a global energy hub by increasing trade volume.”
Bayraktar said that Turkiye wanted energy to be a key part of the plan for a north-south trade corridor from the Grand Faw Port to the Turkish border.
Under current plans, the corridor will combine a new railway and highway system.
Bayraktar said that Turkiye also wants the route to include oil and gas pipelines as well as electricity transmission lines.
READ THE OCTOBER 2026 MEED BUSINESS REVIEW – click here to view PDFIndustry and logistics drive development at Neom; Saudi Arabia’s investment priorities realign amid conflict; MEED’s 2026 power developer ranking.
Distributed to senior decision-makers in the region and around the world, the October 2026 edition of MEED Business Review includes:
> AGENDA: Oxagon takes centre stage at Neom> MARKET FOCUS: Saudi projects hold steady> INDUSTRY REPORT: MEED’s 2026 GCC power developer ranking> LEADERSHIP: The future city does not need to hang above the groundTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/20268590/main.jpg -
Contractors submit bids for Libya refinery5 October 2026

Bids have been submitted for the main contract for Libya’s planned South Refinery project and are currently under technical evaluation, according to industry sources.
The project, located in Ubari in southern Libya, has gained momentum over the past year, and the main contract is anticipated to be worth more than $600m.
The main contract is expected to use the engineering, procurement and construction (EPC) model.
The EPC work is expected to take 50 months, and the facility will be designed to process 30,000 barrels a day (b/d) of crude oil.
In March, US-based engineering company KBR was awarded a contract by Zallaf Exploration, Production & Refining of Oil & Gas Company to provide project management and technical services for the project.
Under the terms of the contract, KBR will provide contract management, project management and supporting technical services throughout the project’s EPC phases.
The refinery is expected to produce:
- Propane and butane for domestic and industrial uses
- Gasoline
- Kerosene
- Diesel
- Fuel oil
In March, KBR said that the project was aligned with its “long-standing commitment to advancing vital oil and gas infrastructure in Libya”.
Libya currently operates five main refineries with a combined nameplate capacity of 380,000 b/d, but actual throughput is closer to 180,000 b/d due to poor maintenance and damage from military clashes.
In addition to the South Refinery project, Libya also plans to upgrade the Zawiya refinery and carry out projects at the Serir, Brega, Tobruk and Ras Lanuf refineries.
READ THE OCTOBER 2026 MEED BUSINESS REVIEW – click here to view PDFIndustry and logistics drive development at Neom; Saudi Arabia’s investment priorities realign amid conflict; MEED’s 2026 power developer ranking.
Distributed to senior decision-makers in the region and around the world, the October 2026 edition of MEED Business Review includes:
> AGENDA: Oxagon takes centre stage at Neom> MARKET FOCUS: Saudi projects hold steady> INDUSTRY REPORT: MEED’s 2026 GCC power developer ranking> LEADERSHIP: The future city does not need to hang above the groundTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/20267178/main.jpg -
Dubai tenders sewage and stormwater projects5 October 2026
Register for MEED’s 14-day trial access
Dubai Municipality has issued tenders for a 3,000-cubic-metre-a-day sewage treatment plant (STP) and a strategic stormwater drainage system.
The first tender is for the design and construction of the Al-Lissaily STP.
The project, identified as DS311/1, covers the design, supply, installation, construction and commissioning of the plant in the Al-Lissaily area.
Dubai Municipality’s Sewerage and Recycled Water Projects Department is issuing the tender. The bid submission deadline is 29 October.
The facility is located near residential communities and farming areas. The project will therefore include measures for odour control, treated effluent quality, noise mitigation and environmental performance.
The municipality said the plant will incorporate landscaping and architectural features designed to reflect Dubai’s heritage character and the surrounding farming environment.
The second tender is for project TF-07-C1, a strategic stormwater drainage system covering more than 100 million square metres.
The project area extends from Sheikh Mohammed Bin Zayed Road (E311) to the north to Emirates Road (E611) to the south, and from Expo Road in the west to Dubailand in the east.
The project will provide stormwater infrastructure and service connections for more than 20 private developers, as well as the Al-Yalayis 5 community.
It will also support major roads in the Jebel Ali area, including Sheikh Mohammed Bin Zayed Road, Emirates Road, Sheikh Zayed Road, Sheikh Zayed Bin Hamdan Al-Nahyan Road, Hessa Street, Al-Yalayis Road and Al-Fay Road.
The scope includes a major stormwater gravity drainage system, with pipeline diameters of up to 3,000mm.
Dubai Municipality said the project is intended to increase drainage capacity, improve relief for existing and new stormwater systems, and strengthen protection against extreme rainfall events.
The bid submission deadline is 22 October.
The municipality also recently invited contractors to bid for a contract to upgrade and rehabilitate the stormwater system in Abu Hail.
The project comprises a stormwater pumping station with a total discharge capacity of 26 cubic metres a second. It is estimated to cost up to $163m.
Bid submissions are due by 15 October.
READ THE OCTOBER 2026 MEED BUSINESS REVIEW – click here to view PDFIndustry and logistics drive development at Neom; Saudi Arabia’s investment priorities realign amid conflict; MEED’s 2026 power developer ranking.
Distributed to senior decision-makers in the region and around the world, the October 2026 edition of MEED Business Review includes:
> AGENDA: Oxagon takes centre stage at Neom> MARKET FOCUS: Saudi projects hold steady> INDUSTRY REPORT: MEED’s 2026 GCC power developer ranking> LEADERSHIP: The future city does not need to hang above the groundTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/20266881/main.jpg