Adnoc Gas awards $550m of Estidama contracts

15 July 2024

Register for MEED's 14-day trial access 

Adnoc Gas has awarded contracts worth a total of $550m for two engineering, procurement and construction (EPC) packages of its sales gas pipeline network upgrade project, also known as Estidama.

The combined packages four and seven of the Estidama project were awarded to the UAE unit of Oman's Galfar Engineering & Contracting. The value of the contract is understood to be about $295m.

Abu Dhabi’s NMDC Energy has won package six. The value of the contract is $255m, NMDC Energy said in a filing with the Abu Dhabi Securities Exchange.

The main scope of work on Estidama Package 4+7 involves laying a new pipeline from the Al-Shuwaib pig launcher and pig receiver station in Abu Dhabi to the Sajaa gas facility in the emirate of Sharjah.

The scope also covers building a new gas pipeline between BVS-2/KP28.7 in Abu Dhabi and Dubai’s Margham gas facility, to meet increased demand from Adnoc Gas’ customer Dubai Supply Authority (Dusup).

The EPC scope of work on Estidama Package 6 entails the installation of a 52-inch, 74-kilometre (km) pipeline from Sweihan to Al-Shuwaib in Abu Dhabi, and building two block valve stations.

Adnoc Gas received technical and commercial bids for package six and the combined packages four and seven in 2022 and 2023, respectively.

Contractors submitted technical bids for package six in August 2022 and commercial bids by 21 November of that year.

Contractors submitted technical bids for the combined packages four and seven by 27 March last year, and commercial bids by 9 August.

in late May, MEED reported that Adnoc Gas had asked contractors to extend the validity of their bids for the two packages until 30 June. This was the latest in a series of bid validity extension requests made by the project operator.

Estidama scheme

Adnoc Gas, the natural gas producing and processing subsidiary of Abu Dhabi National Oil Company (Adnoc) has made significant progress with the Estidama project, which will enhance Adnoc’s sales gas pipeline network across the UAE. The objective of the scheme is to cater to rising demand for gas from industrial consumers, particularly in the Northern Emirates.

Through the Estidama scheme, Adnoc Gas aims to extend the existing 3,200km pipeline network to over 3,500km, enabling the transportation of higher volumes of natural gas to customers across the UAE.

EPC works on the estimated $2bn-plus Estidama project have been divided into seven packages.

China Petroleum Pipeline Engineering performed the Estidama project’s front-end engineering and design works as part of a contract worth about $6m that Adnoc Gas Processing awarded to the Chinese state-owned firm in October 2020.

MEED reported in December 2021 that Abu Dhabi-based contractor Integrated Specialised General Contracting Company (Iscco) had won package one of the project, which is understood to have a contract value of $18m. Iscco later sub-contracted the detailed engineering works on package one to the Abu Dhabi branch of Sweden-headquartered consultancy Rejlers.

In July 2023, Adnoc Gas awarded the EPC contract for package two, estimated to be worth $720m, to UK-based Petrofac, and package three, valued at $630m, was won by a consortium of NMDC Energy and Lebanon’s CAT Group.

Separately, Adnoc Gas received technical bids from contractors for package five of the Estidama project on 24 June, MEED reported. Package five was previously part of package two but was later split off and tendered as a separate package by Adnoc Gas.

The scope of work on package five involves EPC works to upgrade the Habshan gas processing complex in Abu Dhabi.

MEED also recently reported that contractors were preparing technical bids for package eight of the Estidama scheme, which involves building a new pipeline that will transport gas as feedstock from the Habshan gas processing complex in Abu Dhabi to its upcoming liquefied natural gas terminal in Ruwais. The proposed pipeline will cover about 190km and will be built in two sections.

https://image.digitalinsightresearch.in/uploads/NewsArticle/12123642/main.jpg
Indrajit Sen
Related Articles
  • Completing infrastructure ahead of time

    10 December 2024

     

    In late December 2023, Bahrain opened the Al-Fateh Highway project to traffic five months ahead of schedule. The highway connects key areas in Bahrain, including Manama, Mina Salman, Sitra, Muharraq, Bahrain Bay and Juffair, and opening the scheme promptly has significantly improved traffic in one of the most congested areas of the country.

    “The secret to success was implementing the project in stages, combined with excellent traffic management,” says Minister of Works Ibrahim Bin Hassan Al-Hawaj. 

    The successful completion of the Al-Fateh Highway project comes at an important time for Bahrain, as it continues to upgrade its road network. 

    “The lessons we learned from Al-Fateh Highway are being utilised on other projects. We are working on the Muharraq Ring Road project, and that is also going to be open for traffic well ahead of time,” says Al-Hawaj.

    Like Al-Fateh Highway, the Muharraq Ring Road project connects key commercial and residential areas in Bahrain, including North Muharraq, Diyar Al-Muharraq and Dilmunia.

    Multifaceted approach

    These projects are part of Bahrain’s comprehensive approach to alleviating road traffic.

    “In 2016, we launched a study that identified projects that could help ease congestion. It proposed a multifaceted approach that covers many things, including public transport and an intelligent transport system, which introduces automation,” explains Al-Hawaj. 

    “We have not implemented everything in the study, but we are working through it gradually with the Traffic Council, headed by his excellency the minister of interior, and including the Ministry of Works, Ministry of Transportation and Ministry of Housing & Urban Planning. We have regular meetings to identify challenges and then put forward suitable projects to solve them,” says Al-Hawaj. 

    The Ministry of Works is responsible for maintaining, improving and expanding the road network. Its projects are split into four categories. 

    The first two categories are the major projects. The first is building new roads, while the second is improving the existing road network, either by widening roads or upgrading intersections. 

    Then there are the other two categories. These are maintaining the existing road network – which is a challenging task with existing traffic – and a fourth category that is known as ‘quick wins’. These small, tactical-level projects can be completed quickly to ease specific traffic black spots. 

    “We have about 60 projects under implementation, valued at BD172m ($456.2m), and among these are 14 strategic projects that amount to BD117m,” says Al-Hawaj.

    Upcoming schemes

    The pipeline of projects under execution will soon be expanded with the addition of a fourth crossing connecting Busaiteen with Bahrain Bay. The Bahrain Tender Board opened prices for the contract to build the signature bridge crossing in late November. 

    “The fourth crossing project is going to start in 2025,” says Al-Hawaj.

    Looking further ahead, more road contracts will be awarded. “There are more than BD200m of future projects approved, and they will go to tender in the coming two years,” says Al-Hawaj.

    There are more than BD200m of future projects approved, and they will go to tender in the coming two years

    One of the roads that suffers from high traffic volumes is Sheikh Jaber Ahmed Al-Sabah Highway, from Umm Al-Hassam to the Alba intersection. 

    “This is our biggest project in the future. There will be four lanes in each direction, and all the intersections will be free-flowing traffic either by underpass or flyovers. We will get rid of all the traffic lights,” says Al-Hawaj. 

    The project will move into the construction phase next year with preparation works. 

    “One of the main lessons from the Al-Fateh Highway project is to free the construction zone from any services before construction starts. It will take some time to redirect the existing utilities, and then we will immediately go into construction,” says Al-Hawaj.

    Another upcoming major scheme is the Bahrain Northern Link Road (BNLR) project that will run along the northern coast of Manama from the Bahrain Bay area in the east to Madinat Salman in the west. Initial estimates suggest that the scheme, which will have sections onshore and offshore, could cost BD500m to deliver. 

    Together with the fourth crossing project and the Northern Muharraq Ring Road, the BNLR scheme will create a new road corridor along the northern edge of Bahrain. 

    Unlike other road projects in Bahrain, the BNLR will be delivered as a public-private partnership project. Dar Al-Handasah was selected for the project’s feasibility study in 2022. 

    Away from roads, another major area of responsibility for the Ministry of Works is sanitation. At present, 86% of premises in Bahrain are connected to the sanitation network and sewage treatment plants (STPs), and there are plans to connect the remaining 14%.

    STP capacity is also increasing. The capacity of Bahrain’s largest plant at Tubli is being doubled, and there is an expansion under way for the STP at Muharraq. The Sitra STP is also being upgraded, using technology from UK company Bluewater, which allows for capacity to increase without adding to the footprint of the site. 

    A greenfield project is also planned. “We have a new plant coming soon at Khalifa City,” says Al-Hawaj. 

    “We are finalising the drawings, and a tender is expected to be issued in the first quarter of 2025. We will start with 20,000 cubic metres a day, but the ultimate capacity will be 40,000 cubic metres a day.” 

    https://image.digitalinsightresearch.in/uploads/NewsArticle/13100800/main.gif
    Colin Foreman
  • Oman’s mining ambitions take a leap forward

    10 December 2024

     

    While Oman is at a disadvantage in terms of hydrocarbon reserves compared to its Gulf neighbours, when it comes to mineral resources, the sultanate, with its considerably large geographical area, enjoys benefits that its Gulf peers – barring Saudi Arabia – do not.

    Exploration for mineral resources and mining activities for metals production are fundamental pillars of Oman Vision 2040 – a socio-economic strategy designed to diversify the sultanate’s economy away from oil and gas revenues and harness the potential of non-hydrocarbon industrial sectors.

    At the forefront of this ambition is Minerals Development Oman (MDO), which was created in 2017 to explore the country’s mineral resources base and develop the mining sector.

    Minerals exploration and production

    MDO, a subsidiary of Oman Investment Authority, continues to advance its exploration campaigns across a range of minerals, including copper, chromite, gypsum, limestone, dolomite and silica.

    The company had a major success recently when its subsidiary, Mazoon Mining, broke ground on a copper concentrate production project in Yanqul in northwestern Oman.

    The Mazoon copper project site, located in the wilayat of Yanqul in Al-Dhahirah Governorate, covers 20 square kilometres (sq km) and comprises five open-pit mines. It is estimated to hold copper ore reserves of 22.9 million tonnes.

    The project includes the construction of a processing plant spanning 56,000 square metres, with the capacity to process 2.5 million tonnes a year (t/y) of copper ore.

    The Mazoon copper project will have the capacity to produce 115,000 t/y of copper concentrate, at a 21.5% copper grade, making it the largest copper concentrate production project in the sultanate.

    Mazoon Mining was granted exclusive rights by Oman’s Energy & Minerals Ministry in 2022 to explore, develop and produce copper concentrates in concession area 12-A1, with gold as a secondary by-product.

    Following feasibility studies, Australian/Canadian firm Lycopodium was appointed as the engineering, procurement and construction management contractor for the Yanqul project.

    Construction of the processing plant is planned to begin in the first quarter of 2025, and production of copper concentrate is set to commence in the first quarter of 2027.

    In addition to the Mazoon copper project, MDO has also initiated the redevelopment of copper mines in Sohar and Liwa, aiming to produce 800,000 t/y of copper ore annually, with confirmed reserves of 2.78 million t/y of copper ore.

    In October, the Omani Ministry of Energy & Minerals awarded MDO a concession agreement to explore and develop silica resources in Block 51F in the wilayat of Mahout in Al-Wusta Governorate. The block covers 2,156 sq km and is estimated to hold silica, limestone and dolomite deposits.

    Steel production investments

    Several other metal production projects in Oman, particularly steel schemes, have also made progress in recent months.

    In late October, Brazilian mining major Vale and China’s Jinnan Iron & Steel Group entered a joint venture (JV) to establish an iron ore concentration plant in Oman’s northern city of Sohar.

    The Brazilian-Chinese JV intends to invest more than $600m in the iron ore concentration plant project, which will be the first such facility in Oman.

    Vale will invest $227m to connect the plant to its agglomerate facilities in the region, while Jinnan will invest about $400m to build, own and operate the plant.

    The planned complex, to be located within Sohar Port and Freezone, is scheduled to start operations by mid-2027.

    The plant will be able to process 18 million t/y of iron ore and produce 12.6 million t/y of high-grade concentrate.

    The proposed iron ore concentration plant project in Sohar is understood to be the second-biggest foreign investment in Oman’s steel industry. As such, it will contribute to the sultanate becoming a key player in the global supply chain for direct reduction grade iron ore (DRI).

    Vulcan Green Steel (VGS), the steel arm of Vulcan Green, which is owned by India’s Jindal Steel Group, is developing the largest green steel project in Oman. VGS broke ground on the estimated $3bn project in December 2023.

    The planned facility, which covers 2 sq km in the Special Economic Zone at Duqm (Sezad), will have two 2.5 million t/y production lines, comprising DRI units, an electric arc furnace and a hot strip mill. 

    The planned facility, set for completion by 2026, will primarily use green hydrogen to produce 5 million t/y of green steel. Once commissioned, it will be the world’s largest renewable energy-based green steel manufacturing complex.

    Sezad could also host another large-scale green steel project if Japanese steel manufacturer Kobe Steel and Tokyo-based Mitsui & Company can reach the final investment decision on a preliminary agreement they signed in April 2023 to develop a low-carbon iron metallics project.

    The two Japanese firms agreed to conduct a detailed business study in line with the goal of commencing low-carbon dioxide iron metallics production by 2027. The project is expected to produce 5 million t/y of DRI using a process called Midrex, where DRI is produced from iron ores through a natural gas or hydrogen-based shaft furnace.

    Polysilicon production

    Oman is also set to become a key regional producer of polysilicon once private player United Solar Polysilicon completes the construction of its estimated $1.35bn production facility in Sohar Port and Freezone in 2025. 

    The polysilicon plant will have the capacity to produce 100,000 t/y of high-quality metallurgical silicon. United Solar Polysilicon broke ground on the factory, which will be spread across 160,000 square metres, in March this year.

    United Solar Polysilicon made further progress with the project in July when it awarded a contract to provide water services to Sohar-based Majis Industrial Services, a subsidiary of Omani state energy conglomerate OQ Group. 

    Polysilicon is a high-purity form of silicon, which is a key raw material in producing solar photovoltaic panels. Polysilicon production involves pouring the liquid metallurgical silicon from the furnace into moulds and then cooling it through mould or continuous casting. After cooling, the metallurgical silicon is ground and packaged for global export.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/13100480/main.gif
    Indrajit Sen
  • Oman construction continues its positive trajectory

    10 December 2024

     

    Oman has had its best year for construction and transport contract awards in nearly a decade in 2024. By late November, there had been $4.1bn of awards, which already exceeds the $3.6bn recorded in 2023, according to regional projects tracker MEED Projects. 

    The total for 2024 is the first time the market has exceeded $4bn since 2015 and builds on the steady growth that the sultanate has delivered since it emerged from the Covid-19 pandemic in 2021 and the change in leadership in 2020, when Sultan Haitham Bin Tariq Al-Said replaced Sultan Qaboos Bin Said. 

    Transport contracts

    The big moment for Oman construction in 2024 came in April, when three civil works contracts were awarded for the Hafeet Rail project connecting Oman and the UAE. The estimated AED5.5bn ($1.5bn) design-and-build contract was awarded to a consortium of Abu Dhabi-based National Projects Construction, National Infrastructure Construction Company, Tristar Engineering & Construction and Oman’s Galfar Engineering & Contracting.

    Hafeet Rail may be just the start of rail projects in Oman. In February, it was reported that studies for the proposed Muscat Metro scheme would be completed by the end of 2024. The scheme is expected to stretch 55 kilometres (km) and have 42 stations. The project is expected to cost about RO1bn ($2.6bn).

    There has also been a steady flow of road contract awards in 2024. According to MEED Projects, there were close to $1.9bn of road construction contracts in Oman by the end of November. Three awards totalling $667m were awarded in November to contractors for work on the Adam to Thumrait highway. 

    Airports projects are also being planned. The Civil Aviation Authority appointed Swiss engineering firm Renardet SA & Partners to prepare designs for Musandam airport in March, and later in the year, it tendered engineering and design contracts for the Jabal Akhdar, Masirah and Sohar airports.

    These projects are part of the National Aviation Strategy 2030, which aims to attract an investment of $3.6bn in airport cities over 20 years.

    Real estate

    Real estate development is also gathering pace, with several masterplanned developments going ahead. Since coming to power, Sultan Haitham has pushed ahead with key schemes, some of which had been on hold for a number of years. One of these is the Grand Blue City project, also known as Al-Madina Al-Zarqa, located along the Al-Sawadi seafront, almost 100km northwest of Muscat. The project was first launched in 2005 and stalled during the global finance crisis. 

    In June this year, the Oman Investment Authority-backed Grand Blue City Development Company awarded local contractor Galfar Engineering & Contracting the marine works for the project, which is the clearest sign yet that construction work is gaining momentum.

    The most high-profile new masterplanned project is Sultan Haitham City, which is managed by the Ministry of Housing & Urban Planning (MHUP). In February, MHUP signed contracts worth RO1bn ($2.6bn) to develop the first phase of Sultan Haitham City. The first phase includes the development of a city centre and six of the development’s 19 planned neighbourhoods. Completion is expected in 2030.

    Another masterplanned development near the capital is Al-Khuwair Downtown, which is close to Muscat International airport and is also being developed by the MHUP. Design work is progressing on the scheme, which includes a marina, waterfront with beaches and sports facilities, canal and promenade areas, a cultural quarter and a ministry campus.

    Another MHUP project is the Omani Mountain Destination on Jabal Al-Akhdar, 150km from Muscat. The $2.4bn destination includes 2,537 housing units, 2,000 hotel rooms, and a health and wellness village, all situated at an altitude of 2,400 metres above sea level.

    Investment avenues

    Foreign investors are also playing a role. Dar Global is developing the Aida project, and this year, it launched The Trump International Resort, Golf Club & Residences. The estimated $500m development comprises a 140-key five-star hotel, villas, serviced apartments, an 18-hole championship golf course, a club and a nightclub.

    As well as traditional real estate investment, public-private partnerships are playing a role. The Asyad Group is tendering a 4,925 square-metre office complex in the Muscat airport free zone, with the selected firm developing it on a design, build, finance, operate and transfer basis over 25 years.

    All these subsectors are expected to generate opportunities for construction companies over the coming years. The market also has the potential to grow far beyond its achievements in 2024. While that growth was positive, analysis of the historical numbers shows that the Oman market can achieve much more. In 2014, when the market peaked, there were over $9bn of awards – more than double the 2024 total. 

    https://image.digitalinsightresearch.in/uploads/NewsArticle/13097819/main.gif
    Colin Foreman
  • Morocco explores offshore wind project

    9 December 2024

    Luxembourg-headquartered European Investment Bank (EIB) has tendered a contract covering the feasibility study of Morocco's first offshore wind project off the coast of Essaouira.

    EIB, which is supporting the Moroccan Agency for Sustainable Energy (Masen) in the project, expects to receive bids from technical and engineering consultants for the contract by 30 January 2025.

    The selected consultant will undertake the project's feasibility and complementary studies and environmental and social impact assessment. 

    The duration of the contract is 29 months, with the possibility of one or more extensions, consisting of a maximum of 14 additional months for a maximum period of 43 months in total, said EIB.

    The value of the contract is €2m, with the possibility of one or more budget increases for additional services, of a maximum amount of €3m, if additional eligible funds are available, the bank added.

    Recent studies indicate Morocco has a high potential to exploit offshore wind, particularly along its Atlantic coast where wind speed is high and where the shallow waters are suitable for fixed-bottom offshore wind.

    Renewable target

    Morocco has set a target for 52% of its energy to be produced from clean energy sources by 2030, one of the most ambitious targets in the Middle East and North Africa region.

    It aims to increase its renewable capacity to 10,000MW by 2030. Solar PV capacity is expected to comprise 4,500MW, with wind and hydroelectric comprising 4,200MW and 1,300MW, respectively.

    Masen tendered contracts to develop and operate the Noor Midelt 2 and Noor Midelt 3 solar photovoltaic (PV) and battery energy storage system (bess) projects this year

    The Noor Midelt 2 solar independent power project (IPP) consists of a 400MW solar PV power plant with battery storage of two hours.

    It replaces a previous scheme that was expected to include thermal concentrated solar power and PV solar components, similar to Noor Midelt 1, which was previously awarded to a consortium of EDF and Masdar.

    The Noor Midelt 3 IPP scheme is expected to have a solar PV capacity of up to 400MW and a bess capacity not exceeding 400 megawatt-hours (MWh).     

    The client has moved the last day for bid submissions from 29 November to 12 December, according to a source close to the projects.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/13095822/main.jpg
    Jennifer Aguinaldo
  • Hassan Allam wins Ramhan Island villas construction deal

    9 December 2024

     

    Register for MEED’s 14-day trial access 

    Egyptian construction firm Hassan Allam has been awarded a construction contract to build about 321 villas at the Ramhan Island development in Abu Dhabi.

    The contract was awarded by the local firm Eagle Hills, which is led by Mohamed Alabbar, the founder and chairman of Emaar Properties.

    Located off the coast of Abu Dhabi, the Ramhan Island development spans an area of over 4 million square metres.

    The overall development includes the construction of 1,800 villas, 900 residences, a hotel and retail facilities.

    Eagle Hills signed an agreement with US-based hotel operator Marriott International to build a Ritz-Carlton Reserve hotel on Ramhan Island in July.

    The property will feature 50 private one- to four-bedroom villas, including floating villas. The development is expected to open in 2029.

    Mohamed Alabbar launched the Ramhan Island development in May this year.

    GlobalData expects the construction industry in the UAE to expand by 4.6% in real terms in 2024, supported by improved investments in transport, industrial and residential construction projects. Private sector investments in the real estate sector will also support the industry’s growth this year. 

    The construction industry is expected to register an annual average growth of 3.8% in 2025-28, supported by investments in transport, housing and renewable energy projects.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/13095728/main.jpg
    Yasir Iqbal