Adnoc Gas awards $2.1bn gas infrastructure contracts

10 January 2025

 

Register for MEED’s 14-day trial access 

Adnoc Gas, the natural gas processing business of Abu Dhabi National Oil Company (Adnoc Group), has awarded three contracts worth $2.1bn to build infrastructure that will facilitate gas feedstock for the upcoming liquefied natural gas (LNG) terminal in Abu Dhabi’s Ruwais.

A consortium of Egyptian contractors Engineering for the Petroleum & Process Industries (Enppi) and Petrojet won a $1.24bn contract for the engineering, procurement and construction (EPC) of an LNG pre-conditioning plant within Adnoc Gas’ Habshan-5 gas processing complex.

The LNG pre-conditioning plant is intended to have the capacity to supply 1.5 billion cubic feet a day (cf/d) of gas feedstock for the Ruwais LNG complex.

UK-headquartered Petrofac secured a $335m contract to develop new compression facilities at the Habshan gas processing complex. This contract constitutes package 5 of Adnoc Gas’ larger project to upgrade its sales gas pipeline network across the UAE, also known as Estidama.

China Petroleum Pipeline Engineering Company won a $514m contract for EPC works to build a transmission pipeline network to provide gas to the Ruwais LNG complex and to other Adnoc Gas customers in the Northern Emirates.

This contract constitutes package 8 of the Estidama megaproject. In November, MEED reported that China Petroleum Pipeline Engineering was the favourite to win Estidama package 8.

The selection of contractors for packages 5 and 8 concludes the contract award exercise for the estimated $3bn Estidama megaproject. Through the Estidama scheme, Adnoc Gas aims to extend the existing 3,200 kilometre (km) pipeline network to over 3,500km, enabling the transportation of higher volumes of natural gas to customers across the UAE.

Detailed scope of work

The new LNG pre-conditioning plant will treat gas processed at facilities being built as part of Adnoc Gas’ Maximise Ethane Recovery & Monetisation (Meram) project.

Adnoc Gas awarded a $3.6bn contract for Project Meram to a consortium of Abu Dhabi’s NMDC Energy and Spanish contractor Tecnicas Reunidas in August 2023.

The Meram project has dual objectives. The first goal is to increase ethane extraction by 35%-40% from Adnoc Gas’ existing onshore facilities in the Habshan gas processing complex by constructing new gas processing facilities. The second goal is to unlock further value from existing feedstock and deliver it to Ruwais via a 120km natural gas liquids (NGL) pipeline.

The new LNG pre-conditioning plant will be an intermediate gas treatment facility for gas originating at Meram facilities, with the contractors required to perform EPC of the following units:

  • High-pressure absorber and regenerator columns and internals
  • Internals for high-pressure absorber and regenerator
  • Molecular sieve adsorber
  • Air-cooled exchangers
  • Centrifugal compressor
  • Centrifugal horizontal pumps
  • Cooling water refrigeration
  • Instrument air compressor
  • Gas turbine generator
  • Steam turbine generator
  • Waste heat recovery boilers
  • Power transformers 132/33kV
  • Integrated control and safety system
  • Tie-ins with Meram units and existing Habshan-5 facilities
  • Associated civil works, including grading works, road works and fencing

Estidama package 5, won by Petrofac, broadly covers the upgrade of the Habshan gas processing complex, and includes the EPC of the following units:

  • Booster station
  • Variable frequency drive motor-driven compressors
  • New compressor trains
  • High-pressure gas discharge units
  • Fibre optic cables and other communication equipment
  • Control systems
  • Safe and security systems

Petrofac is currently involved with several key projects involving the Habshan gas processing complex. The London-listed contractor won the main EPC contract for Estidama package 2 in July 2023. The scope of work on the $720m contract involves building a new facility at the KP-30 location of the Habshan gas compressor plant and installing three variable-frequency drive motor-driven compressors.

Separately, Adnoc Gas awarded Petrofac a $615m EPC contract in October 2023 for the carbon dioxide (CO2) recovery project at the Habshan complex. The planned Habshan carbon capture, utilisation and storage (CCUS) facility will have the capacity to capture and permanently store 1.5 million tonnes a year (t/y) of CO2 within geological formations deep underground.

The scope of work on Estidama package 8, won by China Petroleum Pipeline Engineering, involves building a gas transport pipeline in two sections.

The first segment of the pipeline will be a 56-inch suction line that runs 26km from the LNG pre-conditioning plant at the Habshan-5 facility to the Habshan gas processing complex. The second section is a larger portion of the pipeline. The 52-inch, high-pressure discharge line will run 155km from the KP-30 station at the Habshan gas processing complex to the upcoming Ruwais LNG facility.

Ruwais LNG terminal project

The upcoming LNG export terminal in Ruwais will have the capacity to produce about 9.6 million t/y of LNG from two processing trains, each with a capacity of 4.8 million t/y. When the project is commissioned, Adnoc’s LNG production capacity will more than double to about 15 million t/y.

Adnoc awarded the full EPC contract to the consortium of Technip Energies, JGC Corporation and NMDC Energy and achieved the final investment decision for the Ruwais LNG terminal complex in June last year.

The complex will also feature process units, storage tanks and an export jetty for loading cargoes and LNG bunkering, as well as utilities, flare handling systems and associated buildings.

Separately, Adnoc has also signed agreements with international energy companies to divest a total stake of 40% in the Ruwais LNG project.

UK energy producer BP, Mitsui & Co, Shell and French energy producer TotalEnergies will each hold 10% stakes in the Ruwais LNG terminal project, with Adnoc retaining the majority 60% stake in the facility.

Adnoc Gas will acquire its parent’s 60% stake in the Ruwais LNG facility, at cost, in the second half of 2028, when first production from the complex is due.

Along with awarding EPC contracts for the LNG pre-conditioning plant, the new compression facilities at the Habshan complex and the gas feedstock transmission pipeline, Adnoc Gas announced that capital expenditure on the three packages does not form part of the costs previously outlined by the company for its intended acquisition of Adnoc Group’s majority stake in the Ruwais LNG project.

The capex on the three projects forms part of Adnoc Gas’ $15bn capex portfolio until 2029.

ALSO READ: New CEOs take charge at Adnoc gas business units

https://image.digitalinsightresearch.in/uploads/NewsArticle/13247811/main10281124.jpg
Indrajit Sen
Related Articles
  • Managing risk in the GCC construction market

    19 December 2025

     

    The scale and complexity of construction projects under way in the GCC region has attracted global attention. And while large-scale project announcements continue to dominate the headlines, the underlying risks – insufficient financing, harsh contract clauses and a tendency to delay dispute resolution – are often overlooked.

    Around the region, many contractors are experiencing difficulties once projects have started because they mistakenly believe they have the necessary in-house skillsets to navigate these complex issues.

    MEED has convened a panel of construction consultants and specialists to develop a checklist to help contractors and subcontractors operating in the region to navigate the market’s challenges as the sector moves into 2026.

    The proactive steps are aimed at positioning a company so that it can maximise recovery and mitigate threats posed by unresolved claims and poor commercial or contractual administration.

    Systemic risk

    The regional market is characterised by several systemic issues that amplify risks for contractors. 

    The fundamental problem is finance. Projects frequently suffer because they are not fully financed from the start, which places financial strain on contractors. This problem is then compounded by the region’s traditional contractual environment, which means disputes are typically not finalised until well after jobs have been completed, creating cash flow problems for contractors, particularly near the end of such projects.

    Further financial strain is created by unconditional performance guarantees and retention. The combined requirement for advance payment bonds, a 10% performance bond and sometimes 5%-10% retention represents a significant draw on contractors’ cash flow. The growing tendency of employers to pull bonds further exacerbates the situation.

    Many contractors sign up to one-sided contracts so as to secure more work, rather than challenging their employers. Key contractual issues include:

    > Unrealistic timelines: Contractors set themselves up to fail by accepting unrealistic timescales on projects, despite the knowledge that the work often takes twice as long.

    > Deficient design: A major risk, particularly on high-profile projects, is a lack of specification and design progress. Many contracts, such as the heavily modified Silver Book – a standard contract published by the International Federation of Consulting Engineers (Fidic) for turnkey engineering, procurement and construction projects – presuppose that the contractor has sufficient information to design, build and deliver, even when there is substantive information missing, which renders lump-sum pricing obsolete and inevitably leads to dispute.

    > Lowest-bid mentality: Contractors often fail to factor necessary commercial support from legal and claims specialists into their tender figures, making their bid appear more competitive but leaving them without a budget to seek help until it is too late. As a result, projects are managed with budgets that are barely sufficient, rather than being run properly to a successful conclusion.


    Supply-chain erosion

    The quality and capacity of the subcontractor market, particularly in the mechanical, electrical and plumbing (MEP) field, has eroded significantly. 

    Some major MEP players have closed or left the market due to underpricing, prompting contractors to call in their performance bonds. This means the region is receiving progressively lower quality for increasingly higher costs, further straining the delivery phase for main contractors.

    The risk of subcontractor insolvency is increasing and must now be considered a primary project risk. Contractors should monitor financial health, diversify subcontractor dependencies, challenge allocated resources and secure step-in rights wherever possible.

    Many Silver Book contracts in the GCC now include heavily amended, employer-friendly clauses that push design and ground-risk even further onto the contractor – often beyond what Fidic intended. These amendments require careful review and firm pushback.

    The GCC remains a market of opportunity, but success in 2026 will belong to contractors that combine disciplined tendering, transparent commercial governance and early issue resolution. Optimism is not a strategy; preparation is. 

    A 10-point checklist for contractors in 2026

    1. Mandate contractual due diligence: Invest time and money into a thorough contract review before signing. Be prepared to challenge harsh clauses, particularly those unfairly allocating risk, such as unknown conditions and full design responsibility. Assume that bespoke rather than standard amendments govern your entitlement. Treat the special conditions as the real contract.

    2. Factor commercial support into the budget: Do not omit the cost of essential commercial support from the tender, such as quantity surveyor teams, quantum and delay specialists, legal review and claims preparation. Even if not visible in the front-line figures, this cost – which could be as low as 0.01% of the project value – must be factored in to ensure a budget for early and continuous engagement.

    3. Prepare a realistic baseline programme: Stop committing to programmes just to fit the tender. Develop a realistic programme from the start, identifying risks and including necessary code books to track delays early. Consider commissioning an independent programme review at the tender stage – this is common internationally and reduces later arguments about logic, durations and sequencing.

    4. Confirm project funding: Ensure that the project financing is fully in position before starting work. Many problems stem from projects that are only partially financed, leading to cash running out near completion. Gone are the days of not asking employers for greater transparency when it comes to funding projects.

    5. Establish a strong commercial and claims function: This is where commercial management starts. Set up systems to ensure contractual compliance, including seven-day claim notifications. Variations are inevitable, and proper substantiation is required to secure entitlement – if it is not recorded, it cannot be recovered. Diaries, cost records and notice logs remain the foundation of entitlement.

    6. Seek early specialist engagement: Prevention is better than a cure. Bring in specialists early to examine time and cost issues before problems arise. Consultants can provide advice, help set up the correct commercial systems and prevent the escalation of unresolved issues.

    7. Adopt an old-school approach to claims management: Technology is useful, but nothing beats resolving issues face to face. Engage directly with the employer’s team regularly to negotiate and agree claims early. This manages the client’s expectations when it comes to budgeting and allows the contractor to secure cash flow sooner. A simple early-warning culture – even when not contractually required – prevents surprises and builds trust with the client.

    8. Avoid wasting resources: Focus claims efforts only on events that are actually recoverable and demonstrably critical. Contractors often waste time chasing things that will not be recoverable. Prioritise issues that are both time-critical and clearly fall under the employer’s risk – everything else should be logged but not pursued aggressively.

    9. Upskill internal teams: Use specialist involvement as an opportunity to upskill your in-house commercial team. Have them sit alongside specialist consultants to learn proper commercial and contractual administration processes, creating a lasting work-culture benefit.

    10. Push for faster dispute resolution: When a dispute arises, advocate for a swift resolution mechanism like adjudication, mediation or expert determination to temporarily resolve cash flow issues. Dispute adjudication boards are intended to give quick, interim decisions. However, if not set up from the start of the project, the process becomes protracted – sometimes taking many months – so fails to provide the cash-flow relief contractors urgently need.  Where clients resist adjudication, propose interim binding mediation or expert determinations, or failing this, milestone-based dispute workshops – anything that accelerates getting cash back on site.

    MEED would like to thank Refki El-Mujtahed of REM Consultant Services (refki@rem-consultant.com; www.rem-consultant.com) for facilitating this article, as well as the following co-contributors:

    Aevum Consult | Lawrence Baker | lawrence.baker@aevumconsult.com | www.aevumconsult.com

    Decerno Consultancy | Lee Sporle | leesporle@decernoconsultancy.com | www.decernoconsultancy.com

    Desimone Consulting | Mark Winrow | Mark.Winrow@de-simone.com | www.de-simone.com

    Forttas | Derek O’Reilly & Martin Hall | derek.oreilly@forttas.com & martin.hall@forttas.com | www.forttas.com

    IDH Consult | Ian Hedderick | ian.hedderick@idhconsult.com | www.idhconsult.com

    White Consulting | Nigel White | nigelwhite@whiteconsulting-me.com | www.whiteconsulting-me.com

    https://image.digitalinsightresearch.in/uploads/NewsArticle/15289183/main.gif
    Colin Foreman
  • Diriyah signs land lease deal with King Saud University

    19 December 2025

    Saudi Arabia gigaproject developer, Diriyah Company, has signed a long-term land lease agreement with Riyadh Valley Company, an investment arm of King Saud University.

    Diriyah Company will lease 552,000 square metres (sq m) of land from King Saud University for a period of 70 years. 

    The deal will enable the company to add the land bank to its second phase of the Diriyah Project, which is also known as DG2.

    The agreement was signed by Diriyah Company's Group CEO, Jerry Inzerillo, and the acting president of King Saud University and Riyadh Valley Company chairman, Ali Masmali.

    Diriyah Company is already developing the area adjacent to King Saud University. In April, it awarded an estimated SR4bn ($1.1bn) contract for a utilities relocation package for the King Saud University project located in the second phase of the Diriyah Gate development (DG2).

    The contract was awarded to the joint venture of Beijing-headquartered China Railway Construction Corporation and China Railway Construction Group Central Plain Construction Company.

    The scope of the contract covers the design, construction and relocation of KSU's utilities and administration offices, as well as the construction of a district cooling plant, water storage facilities, a sewage treatment plant, a natural gas plant, a diesel transfer pumping station, a utility tunnel, irrigation water storage tanks, office buildings, warehouses and maintenance workshops.

    In addition to KSU, DG2 will feature residential developments, hotels, an opera house, the Saudi Museum of Contemporary Art, six academies, an arena and a mosque.

    The Diriyah masterplan envisages the city as a cultural and lifestyle tourism destination. Located northwest of Riyadh’s city centre, it will cover 14 square kilometres and combine 300 years of history, culture and heritage with hospitality facilities.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/15287776/main.jpg
    Yasir Iqbal
  • Kuwait to sign Mubarak port agreement next week

    19 December 2025

    Kuwait and China are expected to sign the agreement to develop the subsequent phases of Kuwait’s Grand Mubarak Port next week.

    According to media reports, the announcement was made by Kuwait’s Public Works Minister ​Noura Al-Mashaan on Thursday.

    The contract value is estimated to be about KD1.2bn ($4bn).

    In May, Beijing-headquartered China Harbour Engineering Company, a subsidiary of China Communications Construction Company (CCCC), signed an early contractor involvement (ECI) agreement with Kuwait to develop the next phases of the project.

    The initial works include surveying, investigation, hydrological observation, geophysical exploration, testing, model testing, process simulation, design review, owner inspection, preliminary design of sand-retaining embankments, and on-site services and management.

    The project launch ceremony was held in mid-April. It was attended by several high-profile representatives from Kuwait and China, including Fu Xuyin, China’s vice-minister of the Ministry of Transport, Zhang Jianwei, the Chinese ambassador to Kuwait, and Nora Mohammad Al-Mashaan, Kuwait’s minister of public works.

    In January, MEED reported that Kuwait’s cabinet had approved a bid from China Communications Construction Company to implement all stages of its Mubarak Al-Kabeer Port project.

    The country ramped up its efforts on the project after meetings between Kuwaiti and Chinese officials in June last year.

    In 2023, the two countries signed a memorandum of understanding to develop port infrastructure.

    Phase one of the project cost $1.2bn and was completed in 2014.

    The project’s first phase included site levelling and the development of a marina, quay walls, berths, a navigational terminal and port buildings.

    The port is not operational because the phase one works did not include vital equipment such as cranes.

    It is understood that the completion of phase two will allow the port to start operations.

    The full scope for phase two of the project is expected to include:

    • Construction of loading and unloading facilities
    • Construction of quay walls and reclamation
    • Construction of the container yard and the back of the port
    • Infrastructure works
    • Construction of buildings
    • Construction of a container terminal
    • Construction of associated facilities
    • Installation of safety and security systems

    A third phase is also planned to further expand the port.

    The latest developments follow a series of agreements signed in September 2023 to deliver some of Kuwait’s immediate development goals for 2024-28. These agreements will position Chinese companies to play a leading role in the Fourth Kuwait Master Plan 2040.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/15287252/main.jpg
    Yasir Iqbal
  • Metito consortium wins Mecca sewage scheme

    19 December 2025

    A team comprising Metito (UAE), Etihad Water & Electricity Company (UAE) and SkyBridge Company (UK) has been awarded a contract to develop the Hadda independent sewage treatment plant (ISTP) project in Mecca Province, Saudi Arabia.

    The contract was awarded by Saudi Water Partnership Company (SWPC), the kingdom’s principal off-taker for water and wastewater public-private partnership (PPP) projects.

    The project will be developed on a build-own-operate-transfer basis and is expected to begin operations in 2028, followed by a 25-year operating term.

    The plant will provide an initial treatment capacity of 100,000 cubic metres a day and will feature a treated sewage effluent (TSE) reuse system with a storage tank and a 38-kilometre pipeline designed to handle 350,000 cubic metres a day.

    Earlier in December, MEED reported that the team had been named preferred bidder at a levelised tariff of SR2.354 ($0.63) a cubic metre.

    SWPC selected the Miahona-led consortium as the reserve bidder for this project with the second-lowest submitted bid of SR2.599($0.69) a cubic metre.

    According to SWPC, the TSE reuse system accounted for 31% of the preferred tariff for the Arana ISTP and 27% for the Hadda ISTP.

    In March last year, SWPC signed a 25-year water-purchase agreement with a team comprising the local Miahona Company and Belgium-based Besix for the contract to develop and operate the Al-Haer ISTP in Riyadh, as part of the third batch of the kingdom’s ISTP programme.

    Four months later, the Saudi-listed Power & Water Utility Company for Jubail & Yanbu (Marafiq) joined the developer consortium.

    The Miahona/Besix team offered to develop the project for SR1.9407 ($0.5173) a cubic metre, while the second-lowest bid, from a team comprising Spain’s Acciona and the local Tawzea, was SR2.2041($0.588) a cubic metre.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/15287185/main.jpg
    Yasir Iqbal
  • Morocco awards $1bn Casablanca airport terminal deal

    19 December 2025

    Morocco’s National Airports Office (ONDA) has awarded a MD12bn ($1.2bn) contract to build the new terminal at Casablanca’s Mohammed V International airport.

    The contract was awarded to the joint venture of local firms Societe Generale des Travaux du Maroc (SGTM) and Travaux Generaux de Construction de Casablanca (TGCC).

    Construction work on the Mohammed V International airport expansion is expected to begin immediately.

    The project is slated for completion in 2029.

    The expansion will cover more than 600,000 square metres (sq m) and increase the airport’s capacity to 30 million passengers a year.

    The project is designed by a consortium comprising the local branch of French engineering firm Egis Batiment International, Morocco’s Ala Concept and UK-based RSHP Architects.

    The scope of work covers preparatory works, structural works, waterproofing, steel structural works, building facades, electrical, mechanical and plumbing (MEP) works, data centre works, HVAC systems and other associated works.

    The tender also covers the construction of a 300-key airside hotel.

    The new terminal is expected to be ready in time for the 2030 Fifa World Cup, which Morocco is co-hosting alongside Portugal and Spain.

    ONDA tendered the project contract on 4 November, with a bid submission deadline of 16 December, as MEED reported.

    In July, ONDA began early works on the new terminal building, awarding an estimated MD294m ($29m) deal for enabling works to local firm Societe de Travaux Agricoles Marocaine.

    In January, Morocco’s Transport & Logistics Minister, Abdessamad Kayouh, said that the study to expand the airport’s capacity was nearing completion.

    The project is part of Morocco’s MD42bn ($4.3bn) plan to expand key airports in anticipation of increased passenger flow for the 2030 football World Cup.

    Morocco plans to upgrade several airports, including those in Tangier, Marrakech and Agadir, increasing their respective annual passenger capacities to 7 million, 16 million and 7 million.

    There are also plans to add a new terminal at Rabat-Sale airport, raising its capacity to 4 million passengers annually, and to increase Fez airport’s capacity to 5 million passengers annually. 

    The new terminal at Mohammed V International airport will be connected to a high-speed train network linking Kenitra to Marrakech.


    READ THE DECEMBER 2025 MEED BUSINESS REVIEW – click here to view PDF

    Prospects widen as Middle East rail projects are delivered; India’s L&T storms up MEED’s EPC contractor ranking; Manama balances growth with fiscal challenges

    Distributed to senior decision-makers in the region and around the world, the December 2025 edition of MEED Business Review includes:

    > BAHRAIN MARKET FOCUS: Manama pursues reform amid strain
    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/15287093/main.jpg
    Yasir Iqbal