Adnoc curates vast downstream portfolio
25 October 2024

In January this year, Abu Dhabi-based Borouge announced that engineering, procurement and construction (EPC) works on the fourth expansion phase of its petrochemicals complex in Ruwais had exceeded 50%.
The upcoming Borouge 4 polyolefins complex will feature two polyethylene plants – each with a capacity of 700,000 tonnes a year (t/y) – cementing Abu Dhabi’s position as a major producer of petrochemicals. These plants will be supplied by an ethane cracker with a capacity of more than 1.5 million t/y of ethylene and associated derivatives.
Borouge is the petrochemicals-producing joint venture (JV) of Abu Dhabi National Oil Company (Adnoc) and Austrian energy company Borealis. Adnoc owns the majority 70.84% stake in Borouge, with Borealis holding a 19.16% stake. The remaining 10% of shares in Borouge trade on the Abu Dhabi Securities Exchange.
Following the signing of a final investment decision agreement worth $6.2bn by Adnoc and Borealis in November 2021, Borouge awarded the main EPC contracts for the Borouge 4 project, estimated to be worth a total of $4.8bn, in December of that year.
Adnoc has not scaled back spending on petrochemicals projects, or on midstream and downstream oil and gas projects. Subsidiaries and affiliates of the Abu Dhabi energy giant beat the 2021 capital expenditure (capex) level last year by awarding up to $7.5bn-worth of projects to increase its gas transport and processing capabilities, which will facilitate the growth of the petrochemicals and chemicals industries.
Focus on gas processing projects
The biggest EPC contract award on a downstream project in Abu Dhabi in 2023 was an estimated $3.6bn by Adnoc Gas on its project to maximise ethane recovery and monetisation (Meram). A consortium of Abu Dhabi’s NMDC Energy and Spanish contractor Tecnicas Reunidas won the main EPC contract for Project Meram.
The Meram project has dual objectives. The first goal is to increase ethane extraction from Adnoc Gas’ existing onshore facilities in the Habshan gas processing complex by 35%-40% through the construction of new facilities. The second goal is to unlock further value from existing feedstock and deliver it to Ruwais via a 120-kilometre natural gas liquids (NGL) pipeline.
Adnoc Gas is also making progress with the Estidama project, which is crucial to enhancing Adnoc’s sales gas pipeline network across the UAE. The project aims to cater to rising demand for gas from industrial consumers in the country, particularly in the Northern Emirates.
EPC works on the estimated $2bn-plus Estidama project have been divided into seven packages. In July last year, Adnoc Gas awarded contracts worth a combined $1.3bn for two packages of the Estidama project. UK-headquartered Petrofac was awarded the EPC contract for package two of the scheme, estimated to be worth $720m. A consortium of NMDC Energy and Lebanon-headquartered CAT Group won Estidama package three, which is valued at about $630m.
Meanwhile, investors in the Taziz petrochemicals derivatives-producing industrial complex in Ruwais are pushing ahead with their projects. Taziz – a 60:40 JV of Adnoc and Abu Dhabi’s industrial holding company ADQ – is overseeing the development of the industrial complex, which will mainly draw ethylene feedstock from the Borouge 4 facility to produce several in-demand chemicals.
A JV of UAE-based Fertiglobe, South Korea’s GS Energy and Japanese investment firm Mitsui awarded Italian contractor Tecnimont the main EPC contract, estimated to be worth $1.5bn, for its planned blue ammonia project in the Taziz Industrial Chemicals Zone last February. The JV has appointed KBR to provide the technology licence, basic engineering design, proprietary equipment and catalyst for the low-carbon ammonia plant, which will have a capacity of 1 million t/y.
Rise in downstream spending
Further spending by investors on projects in the Taziz master development is set to drive capex on downstream and chemicals projects in the UAE this year.
India’s Reliance Industries has forged a partnership with Taziz and Abu Dhabi-based Shaheen Chem Holdings Investment to invest $2bn in the development of three chemicals plants that will produce 940,000 t/y of chlor-alkali, 1.1 million t/y of ethylene dichloride and 360,000 t/y of polyvinyl chloride. Reliance is expected to award EPC contracts for all three plants this year.
Switzerland-based Proman has committed to building the UAE’s first methanol plant at Taziz, with a planned production capacity of 1.8 million t/y. The Proman-Taziz JV has issued the main tender for the project and contractors are currently preparing technical bids.
As projects in the first phase of the chemicals complex move forward, Taziz is also understood to be gearing up for a second phase that will more than double the categories of chemicals produced at the derivatives hub.
Separately, Adnoc has awarded the main EPC contract this year for a project to build a west-to-east pipeline to transport crude oil produced in Abu Dhabi to the UAE’s northern emirate of Fujairah. The contract is worth up to $3bn.
Egyptian contractor Engineering for Petroleum & Process Industries (Enppi) has been selected to execute the project’s engineering, procurement and construction management.
Looking ahead, close to $8bn-worth of contracts are due to be awarded in the remainder of 2024 on midstream, upstream and downstream projects in Abu Dhabi. When commissioned in the second half of this decade, these projects will go a long way towards consolidating Abu Dhabi’s status as a global downstream hub.
Exclusive from Meed
-
Dubai seeks contractors for Metro Gold Line20 May 2026
-
-
Aldar launches Al-Ghadeer Gardens project19 May 2026
-
-
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Dubai seeks contractors for Metro Gold Line20 May 2026

Register for MEED’s 14-day trial access
Dubai's Roads & Transport Authority (RTA) has invited contractors to express interest in a contract to build the new Gold Line, as part of its expansion of the Dubai Metro network.
The notice was issued in mid-May with a submission deadline of 13 June.
Dubai officially announced the launch of the new Gold Line in April.
In a post on social media site X, Sheikh Mohammed Bin Rashid Al-Maktoum, UAE Vice President and Prime Minister and Ruler of Dubai, said the project will cost about AED34bn ($9.2bn).
The Gold Line will increase the total length of the Dubai Metro network by 35%.
The project is scheduled for completion in September 2032.
The Gold Line will be a fully underground network covering more than 42 kilometres, with 18 stations.
It will pass through 15 areas in Dubai, benefiting 1.5 million residents.
The project is expected to provide connectivity to over 55 under-construction real estate development projects.
The Gold Line will start at Al-Ghubaiba in Bur Dubai and end at Jumeirah Golf Estates.
It will be connected to Dubai Metro’s existing Red and Green lines and will integrate with the Etihad Rail passenger line.
The contractor will be responsible for the design and build of all civil works, electromechanical equipment, rolling stock and rail systems.
The selected contractor will also be required to assist in the systems maintenance and operations during an initial three-year period.
In October last year, MEED exclusively reported that the RTA had selected US-based engineering firm Aecom to provide consultancy services for the Dubai Metro Gold Line project.
Stage one covers concept design, stage two covers preliminary design, stage three covers the preparation of tender documents, stage four encompasses construction supervision and stage five covers the defects and liability period.
MEED’s May 2026 report on the UAE includes:
> COMMENT: Conflict tests UAE diversification
> GVT &: ECONOMY: UAE economy absorbs multi-sector shock
> BANKING: UAE banks ready to weather the storm
> ATTACKS: UAE counts energy infrastructure costs
> UPSTREAM: Adnoc builds long-term oil and gas production potential
> DOWNSTREAM: Adnoc Gas to rally UAE downstream project spending
> POWER: Large-scale IPPs drive UAE power market
> WATER: UAE water investment broadens beyond desalination
> CONSTRUCTION: War casts shadow over UAE construction boom
> TRANSPORT: UAE rail momentum grows as trade routes face strainTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/16919605/main.png -
Construction advances on Riyadh King Salman airport19 May 2026
King Salman International Airport (KSIA) is advancing airside infrastructure works under its long-term expansion programme in Riyadh, including the delivery of a third runway and new private aviation facilities.
Construction activity on the central runway programme is progressing across several operational zones, with works covering excavation, grading, site preparation and taxiway-enabling infrastructure to support upcoming phases.
The third runway is intended to increase airfield capacity and cater to the airport’s future operational requirements.
In a separate development, KSIA has completed initial landside works for the private aviation apron, marking a milestone in the rollout of its executive aviation infrastructure.
The completed scope includes pavement markings, waterproofing systems, firefighting infrastructure chambers and final operational inspections to support readiness for the next stages.
KSIA has also secured General Authority of Civil Aviation (GACA) approval for phase one airside works, which includes the planned connection of Taxiway Alpha to the private aviation facilities, strengthening operational integration between executive aviation assets and airfield movement areas.
The packages form part of the wider KSIA masterplan, which covers about 57 square kilometres and supports Saudi Arabia’s objective of positioning Riyadh as a global aviation and logistics hub.
The airport aims to accommodate up to 100 million passengers by 2030.
Saudi Arabia plans to invest $100bn in its aviation sector. The Saudi Aviation Strategy, announced by GACA, aims to triple annual passenger traffic to 330 million travellers by 2030. It also targets air cargo growth to 4.5 million tonnes and an increase in total air connections to more than 250 destinations.
https://image.digitalinsightresearch.in/uploads/NewsArticle/16906496/main.jpeg -
Aldar launches Al-Ghadeer Gardens project19 May 2026
Abu Dhabi-based real estate developer Aldar Properties has launched the Al-Ghadeer Gardens project, located on the Abu Dhabi-Dubai border.
The new residential development will feature 437 villas and townhouses, offering two-, three- and four-bedroom homes.
Al-Ghadeer Gardens will include more than 30,000 square metres of landscaped open space, supporting a pedestrian-friendly layout and outdoor-focused living.
As part of its sustainability and wellbeing approach, the project is targeting Estidama Pearl 2 and Fitwel 2-star certifications.
Earlier this month, Aldar announced its Q1 financial results, reporting a 20% year-on-year increase in net profit after tax to AED2.3bn ($626m).
Aldar Development recorded a 14% year-on-year rise in revenue to $1.7bn, while earnings before interest, taxes, depreciation and amortisation (Ebitda) increased 23% to $599m.
UAE revenue backlog rose to $17bn at the end of March from $16.6bn at the end of December, with an average duration of 29 months.
The group attributed its performance to revenue from its development backlog and steady income from its investment properties.
https://image.digitalinsightresearch.in/uploads/NewsArticle/16906154/main.jpg -
Iraq trucks oil from the south to Kurdish pipeline19 May 2026

Iraq is trucking crude from Basra to the north of the country to be exported via the Iraq-Turkiye Pipeline (ITP), according to industry sources.
The oil is being loaded into trucks at fields in Basra before being driven to the north, where it is injected into the pipeline network at Khurmala Dome, in the northern section of the Kirkuk field.
Once it has entered the network at Khurmala Dome, it is transported to the main ITP export pipeline and eventually to the port of Ceyhan in Turkiye, where it can be loaded onto ships.
The volumes of crude being transported using trucks have surged in Iraq since the US and Israel attacked Iran on 28 February, starting a regional conflict that has disrupted shipping through the Strait of Hormuz.
One source said: “Most of the crude that is being trucked out of Iraqi oil fields at the moment is going to Syria, but some is being trucked to the north where it is being funnelled through the pipeline.”
Even with the additional volumes being trucked from the south, Iraq is struggling to boost exports using the ITP.
At the end of March, Amer Khalil, the director-general of Iraq’s state-run North Oil Company, said that Iraq was exporting 200,000 barrels a day (b/d) through the ITP.
At the time, he said that the pipeline, which runs from Kirkuk in Iraqi Kurdistan to the port of Ceyhan in Turkiye, was expected to start transporting 300,000 b/d “in the near future”.
As of early May, the pipeline was still exporting about 200,000 b/d, despite having a nameplate capacity of 1.4 million b/d.
One of the factors said to be stopping increased volumes from being shipped through the pipeline is that several key oil fields in northern Iraq evacuated staff and stopped production after the US and Israel started their war with Iran.
Another factor is that Iraq has not invested in domestic pipeline infrastructure to pipe production from Basra to Kurdistan, where it could be exported via the Kurdish ITP route.
READ THE MAY 2026 MEED BUSINESS REVIEW – click here to view PDFGlobal energy sector forced to recalibrate; Conflict hits debt issuance and listings activity; UAE’s non-oil sector faces unclear recovery period amid disruption.
Distributed to senior decision-makers in the region and around the world, the May 2026 edition of MEED Business Review includes:
> REGIONAL LNG: War undermines business case for Middle East LNG> CAPITAL MARKETS: Damage avoidance frames debt issuance> MARKET FOCUS: Conflict tests UAE diversificationTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/16902345/main1824.jpg -
Kuwaiti oil services company secures credit facility19 May 2026
The Kuwaiti drilling and oilfield services provider Action Energy Company (AEC) has secured a new credit facility and renewed and expanded an existing facility in order to support the company’s rig fleet expansion.
The new facility and the expansion were obtained from two Kuwaiti banks and had a combined value of KD40.9m ($132.8m).
In its statement, AEC said that the facilities support the financing and deployment of new rigs linked to contract awards previously announced with the state-owned upstream operator Kuwait Oil Company (KOC).
The company added: “They further reinforce AEC’s financing structure and strengthen its ability to execute its contracted fleet expansion plan through 2026 and beyond, while maintaining a disciplined approach to capital allocation.”
The new credit facility was obtained from Kuwait International Bank (KIB).
It is worth KD7.3m ($23.7m) and will finance two new 750-horsepower (HP) rigs.
The renewal and expansion of the existing facility is worth KD33.6m ($109.1m) and was obtained from Commercial Bank of Kuwait (CBK) to finance four new 1,500 HP rigs and one 1,000 HP rig, in addition to the renewal of the existing facilities.
AEC announced its financial and operational performance for the first quarter earlier this month.
The company reported a net profit of KD2.2m ($7.1m).
The company’s revenue grew by 69.2% year-on-year, primarily driven by the expansion of the operating rig fleet from 13 rigs in the first quarter of 2025 to 20 rigs in the first quarter of 2026, including the full-quarter contribution of 10 new rigs deployed during 2025.
The company is benefitting from a substantial multi-year contracted backlog with KOC.
https://image.digitalinsightresearch.in/uploads/NewsArticle/16902234/main.jpg