Adnoc awards artificial island contract

15 January 2024

Register for MEED's guest programme 

Abu Dhabi National Oil Company (Adnoc) has awarded National Marine Dredging Company (NMDC) a contract for construction of Al-Nouf artificial island.

The value of the contract awarded by Adnoc is $136.78m, NMDC said in a filing with Abu Dhabi Securities Exchange (ADX), where it is listed.

NMDC did not provide other details about its contract.

The contract could be linked to the Al-Nouf seawater treatment plant and water collection and distribution network project, for which Adnoc and Abu Dhabi National Energy Company (Taqa) are expected to start the tendering process for in the second half of 2024.

Al-Nouf project is the second public-private partnership (PPP) phase of Project Wave, which will replace the current aquifer water injection systems used to maintain reservoir pressure in all onshore oil fields in Abu Dhabi.

Like the first-phase Mirfa seawater treatment plant, the Al-Nouf facility will be developed and maintained as a build-own-operate-transfer (BOOT) project. 

https://image.digitalinsightresearch.in/uploads/NewsArticle/11436116/main1346.jpg
Indrajit Sen
Related Articles
  • Hyundai E&C signs $725m Saudi high voltage deal

    13 November 2024

    Register for MEED's 14-day trial access 

    South Korea’s Hyundai Engineering & Construction (E&C) has won a KRW1tn ($725m) contract to build a high-voltage direct current (HVDC) network project in Saudi Arabia.

    The contract forms part of a 1,089-kilometre (km), 500-kilovolt (kV) HVDC transmission line connecting Riyadh Power Plant 14 (PP14) to the Kudmi substation in southwest Saudi Arabia.

    Related read: Interconnection vital to GCC energy future

    The company signed the contract to build the transmission line's first package, which extends over 369km, with National Grid, the power transmission unit of state utility Saudi Electricity Company (SEC).

    The lump sum turnkey project is expected to be completed by January 2027.

    Hyundai E&C said the project will utilise a double bipole HVDC system with a power transmission capacity of 4,000MW.

    Regarded as a next-generation electricity transmission technology, an HVDC transmission system is ideal for renewable energy such as solar or wind power. It uses direct current for electricity transmission, with voltages between 100kV and 800kV.

    An HVDC system is often referred to as a 'power superhighway', transporting significantly more power over greater distances than the common high-voltage alternating current line, and incurs lower power losses.

    The South Korean contractor said it has completed 35 transmission line projects in Saudi Arabia in the past 50 years.

    Related read: Hitachi Energy rides HVDC boom

    https://image.digitalinsightresearch.in/uploads/NewsArticle/12909551/main.jpg
    Jennifer Aguinaldo
  • Chinese-led consortium wins $262m Algeria rail deal

    13 November 2024

    Register for MEED's 14-day trial access 

    Algeria’s Anesrif has awarded a $262m construction contract to a consortium led by the China Road & Bridge Corporation (CRBC).

    The CRBC-led consortium includes China Civil Engineering Construction Corporation and Algeria’s EPE SNTP.

    The contract covers construction work for the Bouchegouf-Souk Ahras-Drea railway section, with a total length of 121 kilometres (km). It is scheduled to be completed in 32 months.

    This contract is the latest example of Chinese companies undertaking major projects in Algeria.

    MEED reported in January this year that Algeria had selected a team of Beijing-headquartered China Railway Construction Corporation and local contractor Cosider Travaux Publics for a contract to build a 575km railway line.

    The line will connect the Gara Djebilet iron ore mine in Western Algeria’s Tindouf Province with the national rail network at Bechar.

    The project will facilitate transporting materials from the Gara Djebilet iron ore mine to industrial centres and ports along Algeria’s national rail network.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/12908841/main5239.gif
    Colin Foreman
  • Contractors prepare prices for major Lower Zakum oil project

    13 November 2024

    Register for MEED's 14-day trial access 

    Contractors are preparing commercial bids for the engineering, procurement and construction (EPC) works on a major Adnoc Offshore project to boost oil production at the Lower Zakum offshore hydrocarbons concession in Abu Dhabi.

    The Lower Zakum hydrocarbons zone is located 65 kilometres northwest of Abu Dhabi in the Gulf’s waters. The offshore arm of Abu Dhabi National Oil Company (Adnoc Offshore) holds the majority 60% stake in the Lower Zakum asset. Foreign partners include an Indian consortium of companies led by ONGC Videsh (10%), Japan’s Inpex Corporation (10%), China National Petroleum Corporation (10%), Italy’s Eni (5%) and France’s TotalEnergies (5%).

    Adnoc Offshore’s larger, longer-term objective is to raise the asset’s output capacity to 520,000 barrels a day (b/d) by 2027 and maintain that level until 2034. This strategic goal will be accomplished through the Lower Zakum Long-Term Development Plan (LTDP-1) project.

    Contractors have been set a deadline of 15 November for the submission of commercial bids for the multibillion-dollar Lower Zakum LTDP-1 project, according to sources. Bidders were earlier required to submit prices in September.

    MEED previously reported that contractors submitted technical bids for the project by 14 August.

    Adnoc Offshore issued the main EPC tender for the Lower Zakum LTDP-1 project in March, MEED reported.

    Adnoc Offshore intends to award EPC contracts for the Lower Zakum LTDP-1 project by the end of the year, sources told MEED.

    Lower Zakum LTDP-1 project

    Adnoc Offshore has divided the scope of work on the Lower Zakum LTDP-1 project into three EPC packages:

    Topside facilities on G Island – Civil works on process facilities and associated buildings on the artificial greenfield G Island.

    Process facilities include well pads, inlet and export reception, production separation, export pumps, gas compression, dehydration and lift, produced water treatment and disposal, vapour recovery units, water injection units, riser tower, flare towers, accommodation, drilling of high-pressure flare knock out drum, power distribution facility, substations and local equipment rooms.

    Offshore WHTs and pipelines – Seven WHTs will be installed: six in the east area, and one in the AGI area. Five of the WHTs are to be 16-slot, while the other two are to be nine-slot.

    Das Island Terminal, ZCSC and ZWSC – The five existing oil processing trains at the Lower Zakum offshore development are to be decommissioned in 2028, with the new configuration of the main processing plant at Das Island to be:

    • Two existing trains with a processing/stabilisation capacity of 110,000 b/d each
    • Three new trains with a processing/stabilisation capacity of 150,000 b/d

    The scope of work also covers the installation of other structures such as:

    • Three high-pressure separator trains
    • High-pressure scrubber
    • Three low-pressure separator trains
    • Low-pressure scrubber
    • Three atmospheric separator trains
    • Four crude charge pumps
    • Three crude charge heaters
    • Three cold strippers integrated with a degassing vessel
    • Six stripped crude product pumps
    • Common ejector with a spare for three cold strippers
    • Closed drain drum with transfer pump
    • Blow case vessel

    Adnoc Offshore expects the Lower Zakum LTDP-1 project to be commissioned by the end of 2027.

    Technip Energies has performed the front-end engineering and design (feed) work on the Lower Zakum LTDP-1 project. Adnoc Offshore awarded the French firm the contract in November 2022, and set a feed completion deadline of January 2024.

    Adnoc Offshore began the main contract prequalification process for the EPC works on the Lower Zakum LTDP-1 project in March 2023. Contractors were initially asked to submit expression of interest documents by 10 April that year, with the deadline extended to 27 April.

    Adnoc Offshore started an early engagement process for the main EPC tendering process on the Lower Zakum LTDP-1 project in the fourth quarter of last year.

    ALSO READ: Adnoc awards Lower Zakum offshore project

    https://image.digitalinsightresearch.in/uploads/NewsArticle/12908046/main0244.jpeg
    Indrajit Sen
  • Hatta hydropower plant heads for trial operation

    13 November 2024

    Construction work on Dubai’s Hatta pumped-storage hydroelectric power plant is 94.15% complete, and generator installations are under way in preparation for a trial operation in the first quarter of 2025.

    According to the state utility, Dubai Electricity & Water Authority (Dewa), the plant’s upper dam, which includes a 72-metre-high main wall and a 37-metre-high side dam, has also been filled.

    The plant will have a production capacity of 250MW, a storage capacity of 1,500 megawatt-hours and a lifespan of up to 80 years.

    The state utility awarded the contract to build the plant to a consortium of Austrian firms Strabag and Andritz and Turkey’s Ozkar in August 2019.

    Dewa said on 12 November that the AED1.421bn ($387m) project is expected to be fully completed by the end of the second quarter of 2025.

    The hydroelectric power plant is designed as an energy storage facility with a turnaround efficiency of 78.9%.

    It uses the potential energy of water stored in the upper dam, converting it into kinetic energy as the water flows through a 1.2-kilometre subterranean tunnel.

    This kinetic energy rotates the turbines, converting mechanical energy into electrical energy, which can be delivered to Dewa’s grid within 90 seconds to meet demand.

    To store energy, clean power generated at the Mohammed Bin Rashid Al-Maktoum Solar Park will be used to pump water back to the upper dam, converting electrical power into kinetic energy during the process.

    Dewa said the project is part of a comprehensive vision to develop Hatta and enhance its sustainable development, including the creation of job opportunities for Emiratis.

    It added that the project “also supports the Dubai Clean Energy Strategy and the Dubai Net Zero Carbon Emissions Strategy 2050”.

    Through the project, Dewa aims to diversify energy production from renewable and clean sources in Dubai. These include different available technologies, such as solar photovoltaic panels and concentrated solar power, as well as the use of renewable energy to produce green hydrogen.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/12908014/main.jpg
    Jennifer Aguinaldo
  • Bahrain invites independent water prequalifications

    13 November 2024

    Register for MEED's 14-day trial access 

    Bahrain’s Electricity & Water Authority (EWA) has invited interested firms to prequalify for a tender to develop the state’s first independent water project (IWP).

    The Al-Hidd seawater reverse osmosis (SWRO) plant is expected to have a production capacity of about 60 million imperial gallons a day (MIGD) of potable water.

    The client expects firms to submit their statements of qualifications (SOQs) by 18 December.

    The facility will be developed on a brownfield site and is expected to be fully operational by the second quarter of 2028. It will help expand Bahrain’s water infrastructure to meet projected demand based on its 2030 master plan.

    The Al-Hidd IWP will be developed using a build, own and operate (BOO) model for 20 to 25 years.

    EWA has also issued the prequalification request for another BOO project, MEED reported on 11 November.

    The Sitra independent water and power project (IWPP) is a combined-cycle gas turbine (CCGT) plant expected to have a production capacity of about 1,200MW of electricity. The project’s SWRO desalination facility will have a production capacity of 30MIGD of potable water.

    The plant is Bahrain’s fourth IWPP, replacing the previously planned Al-Dur 3. The Sitra IWPP is expected to be fully operational by the second quarter of 2029.

    Sixty representatives from utility developers and contracting firms attended a market-sounding event for the two separate utility BOO projects in Manama on 21 October.

    The firms that sent representatives to the event included France’s Engie, Japan’s Mitsui, Saudi Arabia’s Acwa Power, AlJomaih Electricity & Water Company and Ajlan & Bros, and Kuwait’s Gulf Investment Corporation, among others, said sources.

    EWA’s transaction advisory team for the two BOO projects comprises KPMG Fakhro as the financial consultant, WSP Parsons Brinckerhoff as the technical consultant and Trowers & Hamlins as the legal consultant.

    MEED understands that EWA’s Sitra IWPP will likely be Bahrain’s last CCGT plant project. Solar power is expected to account for all future electricity generation capacity.

    Bahrain aims to reach net-zero carbon emissions by 2060.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/12907891/main.gif
    Jennifer Aguinaldo