Adnoc awards Abu Dhabi airport tank farm project

10 July 2024

Register for MEED's 14-day trial access 

Abu Dhabi National Oil Company (Adnoc) has awarded the main engineering, procurement and construction (EPC) contract for a major project to build aviation fuel tank farms for Abu Dhabi International airport.

A consortium of Abu Dhabi-headquartered Trojan Construction Group and Dubai-based Cylingas has been selected for the project’s main EPC contract, which is estimated to be worth up to $400m.

MEED reported in June that Adnoc had notified the Trojan/Cylingas consortium about their selection, with an official contract award due to take place in future.

The project involves building underground tank farms at two sites near Abu Dhabi airport that can store 192 million litres of jet A1 fuel.

Each tank farm will have a gross storage capacity of 96 million tonnes, with a pumping-out capacity of 5 million litres an hour.

Project tendering phase

UK-headquartered consultancy Penspen has performed the project’s front-end engineering and design works.

Adnoc issued the main EPC tender for the project in mid-August last year. Contractors were given an initial deadline of 31 August for submitting technical bids, which was later extended to 28 September.

After submitting technical proposals, contractors submitted the first round of commercial bids for the project in November.

Adnoc is understood to have eventually sought revised commercial bids from bidders after revising the project’s scope. Contractors submitted revised commercial bids by 1 March this year, MEED previously reported.

Project scope of work

The two sites selected for the Abu Dhabi airport tank farm project are located in East Midfield, which is close to the existing North Depot and about 1.5 kilometres from the first site.

The contractors will be required to execute EPC of the following units and services at each site:

  • 16 underground storage tanks measuring 30 metres in diameter and 8.8 metres in height, surrounded by a secondary concrete dyke offset by 3 metres from the tank shell
  • 22 delivery pumps, each with a capacity of 240,000 litres an hour
  • Two delivery pumps, each with a capacity of 150,000 litres an hour
  • Two metering skids at discharge header before connecting to the existing hydrant header at two different locations
  • Closed drain system consisting of closed drain vessels, closed drain transfer pumps, product recovery tanks, product recovery tank transfer pumps and filter water separators and sampling pumps
  • Open drain system consisting of open drain vessels, open drain transfer pumps and oily water separator packages
  • Dedicated plant air/instrument air system and potable/utility water systems
  • Dedicated vent pipe that will terminate above the ground at a location to be specified later
  • Forced venting system for tank annulus and pipe corridor
  • Power for each site to be sourced from the existing substation of the Abu Dhabi Distribution Company
  • Emergency diesel generators to cater to emergency power supply
  • Substation building including switchgear and transformers
  • Uninterrupted power supply system for critical services
  • Installation of fire and gas detection and alarm system, as well as public address general alarm system
  • Process control system, safety instrumented system, emergency shutdown system and fire and gas systems
  • Fire protection system, including foam storage system and spray system
  • Drone protection systems
  • Other supporting systems, such as lighting, earthing, cathodic protection, telecommunications, closed-circuit television and access control systems
  • All process and non-process facilities and services are to be provided within the buildings. All above-ground services and support buildings are to be provided with heating, ventilation and air conditioning, fire fighting, power, potable water, sewerage and stormwater systems, as applicable

The storage tanks will receive jet A1 fuel from the Mussafah industrial area in Abu Dhabi.

https://image.digitalinsightresearch.in/uploads/NewsArticle/12073025/main2707.jpg
Indrajit Sen
Related Articles
  • Consortiums prepare bids for Al-Khairan phase one IWPP

    14 May 2026

     

    Two developer consortiums are finalising bids for the first phase of Kuwait’s Al-Khairan independent water and power producer (IWPP) project, the deadline for which has been extended to 1 June.

    The facility will have a capacity of 1,800MW and 150,000 cubic metres a day of desalinated water. It will be located in Al-Khairan, adjacent to the Al-Zour South thermal plant. 

    The project is expected to run on Low Sulphur Fuel Oil (LSFO) as the primary fuel and to accommodate crude oil, gas oil, and natural gas as backup fuels. Later phases will further expand capacity.

    The main contract was tendered last September. Three consortiums and two individual companies were previously prequalified to participate, with the following groups currently preparing offers:

    • Abu Dhabi National Energy Company (Taqa) / A H Al-Sagar & Brothers (Saudi Arabia) 
    • Acwa (Saudi Arabia) / Gulf Investment Corporation (Kuwait)

    The two individual companies, Sumitomo Corporation (Japan) and Nebras Power (Qatar), are now “unlikely” to submit a bid, according to a source close to the project.

    It is also understood that the third consortium of China Power, Malakoff International (Malaysia) and Abdul Aziz Al-Ajlan Sons (Saudi Arabia) is no longer bidding for the contract.

    The project is being procured by the Kuwait Authority for Partnership Projects (Kapp) and the Ministry of Electricity, Water & Renewable Energy (MEWRE).

    The Al-Khairan IWPP project is part of Kuwait’s long-term plan to expand power and water production capacity through public-private partnerships (PPPs).

    The winning bidder will sign a set of PPP agreements covering financing, design, construction, operation and transfer of the project.

    The energy conversion and water purchase agreement is expected to cover a 25-year supply period.

    Upcoming awards

    Kuwait is also preparing to offer a contract to develop zone one of the third phase of the Al-Dibdibah power and Al-Shagaya renewable energy project.

    In January, three consortiums submitted bids for a contract to develop Kuwait’s first utility-scale solar photovoltaic (PV) plant.

    The Al-Dibdibah power and Al-Shagaya renewable energy phase three, zone one independent power project (IPP) will have a total power-generating capacity of 1,100MW.

    MEED understands that the preferred bidder announcement will happen after the bid closes for zone two of the third phase of the Al-Dibdibah power and Al-Shagaya renewable energy project.

    The PPP authority is procuring the 500MW solar photovoltaic IPP in partnership with the ministry.

    The bid deadline for this project was recently extended to 31 May.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16835649/main.jpg
    Mark Dowdall
  • Bidders compete for new Dubai Metro line project

    14 May 2026

     

    Register for MEED’s 14-day trial access 

    Dubai’s Roads & Transport Authority (RTA) has held a pre-bid meeting for the Dubai Metro Airport Express Line with consultants understood to be competing for work on the project.

    It is understood that the RTA has requested firms to form joint ventures for the project. The firms that attended the meeting include:

    • Aecom (US)
    • Arup (UK)
    • ARX (Switzerland)
    • AtkinsRealis (Canada)
    • DB (Germany)
    • Egis (France)
    • Jacobs (US)
    • Mott Macdonald (UK)
    • Parsons (US)
    • Sener (Spain)
    • Surbana Jurong (Singapore)
    • Systra (France)
    • WSP (Canada)

    The consultancy contract covers the study and design of the Airport Express Line, which will extend from the Al-Garhoud area of the city to Al-Maktoum International airport (DWC) in the Jebel Ali area. The proposed line will stretch about 55 kilometres (km) and include five stations, providing passengers with facilities such as remote airline check-in, baggage drop-off and security screening.

    Consultants have been allowed until June to submit their proposals.

    The new line will run from the Red Line metro station at Dubai International airport through Al-Jaddaf, along Al-Khail Road to a new station at Jumeirah Village Circle (JVC) before continuing on to DWC.

    There will be two spur lines. The first will run from the new JVC station to the Al-Fardan Exchange metro station at Emirates Golf Club, while the second will branch out towards Business Bay, where another station will be built.

    The new line appears to follow a similar route to the Etihad Rail high-speed railway project, which is now under construction and due to be completed by 2030.

    Route 2020 extension

    The Airport Express Line scheme is the latest metro project to be tendered by the RTA this year. Tendering activity is already ongoing for the Route 2020 extension, which will start from the Expo 2020 metro station and connect to DWC’s West Terminal.

    In April, MEED exclusively reported that consultants had submitted bids for the project.

    The extension to the line will run for about 3km and will feature two stations.

    The existing Route 2020 metro link is a 15km-long line that branches off the Red Line at Jebel Ali metro station. The line comprises 11.8km of elevated tracks and 3.2km of tunnels, and has five elevated stations and two underground stations.

    The RTA awarded the AED10.6bn ($2.9bn) design-and-build contract for the project to a consortium of Spain’s Acciona, Turkiye’s Gulermak and France’s Alstom in 2016.

    Gold Line

    Dubai’s plans for its metro network do not stop with connecting the extension of the Route 2020 metro line to DWC. There are long-term plans for further extensions.

    In October last year, MEED exclusively reported that the RTA had selected US-based engineering firm Aecom to provide consultancy services for the upcoming Dubai Metro Gold Line project, also known as Metro Line 4.

    The Gold Line will start at Al-Ghubaiba in Bur Dubai. It will run parallel to – and alleviate pressure on – the existing Red Line, before heading inland to Business Bay, Meydan, Global Village and residential developments in Dubailand.

    The existing network includes the Red and Green lines of the Dubai Metro and the Dubai Tram, which connects Al-Sufouh and Dubai Marina to the metro network. The last rail project to start operations in Dubai was the Red Line extension that opened for Expo 2020.

    There are also existing and planned rail lines connecting Dubai to other emirates that are being developed and operated by Abu Dhabi-based Etihad Rail. These include passenger and freight services, as well as a high-speed rail connection.

    Blue Line

    In December 2024, the RTA awarded a AED20.5bn main contract for the Dubai Metro Blue Line project to a consortium of Turkish firms Limak Holding and Mapa Group and the Hong Kong office of China Railway Rolling Stock Corporation.

    The Blue Line consists of 14 stations, including three interchange stations at Jaddaf, Rashidiya and International City 1, as well as a station in Dubai Creek Harbour.

    By 2040, the number of daily passengers on the Blue Line is projected to reach 320,000. It will be the first Dubai Metro line to cross Dubai Creek, doing so on a 1,300-metre viaduct.

    > Be recognised among the best in the industry at the MEED Projects Awards 2026 …

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16833450/main.jpg
    Colin Foreman
  • Local firm wins $100m Kuwait substation contract

    14 May 2026

     

    The local Al-Ahleia Switchgear Company has won an engineering, procurement and construction contract for a $100m substation project in Wafra in Kuwait’s Al-Ahmadi Governorate.

    According to a source, the firm has been appointed as the contractor for the Wafra 2Z substation 400/132/33kV project, with construction scheduled for completion in January 2029.

    The contract was awarded by US-headquartered Chevron, which is undertaking its first major power project in Kuwait, according to data from MEED Projects.

    It is understood that contractor bids for the project were first submitted in 2023 by National Contracting Company (Kuwait), Al-Ahleia Switchgear (Kuwait), Imco Engineering & Construction Company (Kuwait) and Larsen & Toubro (India).

    The tender was cancelled in 2024, and a new tender was issued last year.

    In April, Al-Ahleia Switchgear won a contract to build a 400/132/11kV substation at the South Surra township for Kuwait’s Public Authority for Housing Welfare.

    The firm also recently won a separate contract in Oman for the supply, installation, execution and maintenance of a main power substation.

    The contract was awarded by Oman’s Public Authority for Social Insurance as part of its affordable housing project, known locally as Al-Masaken Al-Muyassara.

    According to MEED Projects, Chevron owns about $11.2bn-worth of operational oil and gas projects across the Middle East and Africa. It also owns four major power generation projects in Saudi Arabia, valued at $810m.

    > Be recognised among the best in the industry at the MEED Projects Awards 2026 …

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16832909/main.jpg
    Mark Dowdall
  • Al-Ain breaks ground on Four Seasons Saadiyat

    14 May 2026

    Al-Ain Asset Management has held a groundbreaking ceremony for its Four Seasons Private Residences Abu Dhabi project at Saadiyat Beach.

    Due for completion in 2029, the gated beachfront scheme will comprise 116 ultra-luxury homes with direct beach access. The unit mix includes villas, beachfront mansions, suites and penthouses, alongside a range of bespoke amenities and Four Seasons-branded services, Wam reported.

    Al-Ain Asset Management said the majority of the residences have been sold, and that AED250m ($68m) of new villa sales were recorded within one week, underlining demand for ultra-prime homes in Abu Dhabi.

    The developer added that the development set new pricing benchmarks for the emirate’s luxury coastal real estate, achieving prices above AED14,000 a square foot. Total sales have exceeded AED4bn since the project launched less than a year ago.

    The groundbreaking ceremony was attended by senior leadership and key partners, including Four Seasons, Killa Design and Mirage Leisure & Development. LW Design Group is also involved in the development.

    Al-Ain Asset Management is also developing another residential scheme on Saadiyat Island. The Vida Residences development will comprise apartment units geared towards long-stay living, supported by hotel-style facilities and operational spaces. Mimar Architecture & Engineering is working as the consultant.

    > Be recognised among the best in the industry at the MEED Projects Awards 2026 …

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16833035/main.jpeg
    Colin Foreman
  • Aldar acquires Dubai Studio City development

    14 May 2026

    Abu Dhabi-based developer Aldar has acquired a residential and community retail development in Dubai Studio City from Dubai-based developer SRG for AED1.1bn ($300m).

    The deal is part of Aldar’s long-term strategy to build a high-quality, recurring-income portfolio and to scale its presence in the city.

    Scheduled for delivery in 2028, the project comprises six mid-rise buildings with 312 homes, including one-, two- and three-bedroom apartments and duplexes. It also includes a community mall with retail, leisure and food-and-beverage offerings, as well as a 16,000-square-metre park.

    “Dubai is a priority growth market for Aldar, and this acquisition reflects our belief in the city’s residential market and the central role that institutionally owned, professionally managed rental housing plays in meeting the needs of a growing population,” said Jassem Saleh Busaibe, CEO of Aldar Investment. 

    “Dubai Studio City’s established infrastructure, vibrant community and strong connectivity make it an excellent location for a high-quality, professionally managed living environment. This transaction is the latest step in a deliberate and broadening strategy to build a diversified portfolio of income-generating assets in Dubai, one that we expect to continue growing as the city attracts increasing global interest and talent,” he added. 

    The transaction expands Aldar’s activities in Dubai across a range of property types. Aldar Investment’s recurring-income portfolio in the emirate now includes residential, commercial, logistics and mixed-use assets. Key holdings include a mixed-use joint venture with Expo City Dubai, a signature office tower in Dubai International Financial Centre, a Grade A office building on Sheikh Zayed Road, and logistics facilities in National Industries Park and Dubai South.

    On the development front, Aldar’s partnership with Dubai Holding continues to gain traction, with three master-planned residential communities already launched and a pipeline exceeding 2.3 million sq m of new gross floor area. 

    > Be recognised among the best in the industry at the MEED Projects Awards 2026 …

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16832033/main.jpg
    Colin Foreman