Adnoc awards Abu Dhabi airport tank farm project
10 July 2024

Register for MEED's 14-day trial access
Abu Dhabi National Oil Company (Adnoc) has awarded the main engineering, procurement and construction (EPC) contract for a major project to build aviation fuel tank farms for Abu Dhabi International airport.
A consortium of Abu Dhabi-headquartered Trojan Construction Group and Dubai-based Cylingas has been selected for the project’s main EPC contract, which is estimated to be worth up to $400m.
MEED reported in June that Adnoc had notified the Trojan/Cylingas consortium about their selection, with an official contract award due to take place in future.
The project involves building underground tank farms at two sites near Abu Dhabi airport that can store 192 million litres of jet A1 fuel.
Each tank farm will have a gross storage capacity of 96 million tonnes, with a pumping-out capacity of 5 million litres an hour.
Project tendering phase
UK-headquartered consultancy Penspen has performed the project’s front-end engineering and design works.
Adnoc issued the main EPC tender for the project in mid-August last year. Contractors were given an initial deadline of 31 August for submitting technical bids, which was later extended to 28 September.
After submitting technical proposals, contractors submitted the first round of commercial bids for the project in November.
Adnoc is understood to have eventually sought revised commercial bids from bidders after revising the project’s scope. Contractors submitted revised commercial bids by 1 March this year, MEED previously reported.
Project scope of work
The two sites selected for the Abu Dhabi airport tank farm project are located in East Midfield, which is close to the existing North Depot and about 1.5 kilometres from the first site.
The contractors will be required to execute EPC of the following units and services at each site:
- 16 underground storage tanks measuring 30 metres in diameter and 8.8 metres in height, surrounded by a secondary concrete dyke offset by 3 metres from the tank shell
- 22 delivery pumps, each with a capacity of 240,000 litres an hour
- Two delivery pumps, each with a capacity of 150,000 litres an hour
- Two metering skids at discharge header before connecting to the existing hydrant header at two different locations
- Closed drain system consisting of closed drain vessels, closed drain transfer pumps, product recovery tanks, product recovery tank transfer pumps and filter water separators and sampling pumps
- Open drain system consisting of open drain vessels, open drain transfer pumps and oily water separator packages
- Dedicated plant air/instrument air system and potable/utility water systems
- Dedicated vent pipe that will terminate above the ground at a location to be specified later
- Forced venting system for tank annulus and pipe corridor
- Power for each site to be sourced from the existing substation of the Abu Dhabi Distribution Company
- Emergency diesel generators to cater to emergency power supply
- Substation building including switchgear and transformers
- Uninterrupted power supply system for critical services
- Installation of fire and gas detection and alarm system, as well as public address general alarm system
- Process control system, safety instrumented system, emergency shutdown system and fire and gas systems
- Fire protection system, including foam storage system and spray system
- Drone protection systems
- Other supporting systems, such as lighting, earthing, cathodic protection, telecommunications, closed-circuit television and access control systems
- All process and non-process facilities and services are to be provided within the buildings. All above-ground services and support buildings are to be provided with heating, ventilation and air conditioning, fire fighting, power, potable water, sewerage and stormwater systems, as applicable
The storage tanks will receive jet A1 fuel from the Mussafah industrial area in Abu Dhabi.
Exclusive from Meed
-
-
Chinese firm wins Dubai drainage contract20 July 2026
-
-
Abu Dhabi launches E20 highway expansion project20 July 2026
-
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Consultants submit bids for Saudi Arabia’s GCC rail link20 July 2026

Consultants submitted proposals on 14 July for a contract to provide design consultancy services for the Saudi Arabian section of the GCC railway network, which is intended to link all six member states.
Saudi Arabia Railways (SAR) issued the tender on 7 May, MEED previously reported.
The tender covers the concept, preliminary and issued for construction design stages. SAR requires the selected consultant to review, update and complete the existing preliminary design.
The consultants who submitted bids include:
- Atkins with Khatib & Alami
- DeutscheBahn with ARX
- Egis with Sener
- Idom with Dal al-Handasah
- Systra
Saudi Arabia’s section of the railway will start at Al-Khafji in the Eastern Province, near the border with Kuwait, and end at Al-Batha, on Saudi Arabia’s border with the UAE. The route length in Saudi Arabia will be about 672 kilometres (km).
The railway will interface with the Kuwait National Rail Road (KNRR) project on the Kuwaiti side. Last year, MEED exclusively reported that the KNRR design contract was awarded to Turkiye’s Proyapi Muhendislik ve Musavirlik Anonim Sirketi.
The KNRR forms part of the wider GCC rail network. GCC railway projects have gained renewed momentum since the six member states signed the Al-Ula Declaration in January 2021.
In October last year, Qatar’s cabinet approved a draft agreement paving the way for a railway link between Qatar and Saudi Arabia as part of the GCC railway network.
GCC railway line
Under the overall plan, the railway will run from Kuwait, pass through Dammam in Saudi Arabia, reach Bahrain via a planned causeway, and continue from Dammam to Qatar, the UAE and, ultimately, Muscat via Sohar in Oman. The railway is reported to span about 2,186km in total.
The route length within each member state is as follows: 684km in the UAE, 672km in Saudi Arabia, 306km in Oman, 283km in Qatar, 145km in Kuwait and 36km in Bahrain.
The railway is designed for passenger trains travelling at 220km/h and freight trains operating at 80-120km/h.
With high levels of project activity, governments in spending mode and renewed cooperation under the Al-Ula Declaration, the latest efforts to restart the GCC railway project may make more progress than previous attempts. If completed, the railway could prove transformational for a region that is globally connected but still divided by national borders.
https://image.digitalinsightresearch.in/uploads/NewsArticle/17705320/main.gif -
Chinese firm wins Dubai drainage contract20 July 2026
China State Construction Engineering Corporation (CSCEC) has announced it has won a contract to deliver a stormwater drainage pipeline package under Dubai Municipality’s Tasreef programme.
The contract is for the TF-15-C2 stormwater drainage network project located along Umm Suqeim Road in the Al-Barsha and Al-Quoz areas of Dubai.
MEED exclusively revealed in May that the contractor had been selected for the engineering, procurement and construction (EPC) contract. The project is estimated to cost $162m.
The scope of work includes the construction of about 20 kilometres of new stormwater pipelines, together with associated inspection and intake manholes. The project is located west of the Dubai Canal and will connect the Al-Quoz 3 and Al-Quoz 4 industrial areas with Al-Quoz 1.
It is being delivered as part of Dubai’s Tasreef strategic plan, which supports the Dubai 2040 Urban Master Plan. Once completed, the new drainage infrastructure is expected to improve the emirate’s stormwater network, increase flood protection and enhance the resilience of Dubai’s infrastructure.
In February, the municipality confirmed it had awarded contracts for five new projects under phase two of the programme to expand and strengthen Dubai’s stormwater drainage network.
These include a separate contract awarded to CSCEC for the TF-11-C1 stormwater drainage project in the Dubailand area.
Also in February, Dubai Municipality invited consultants to qualify for a contract to supervise construction on the TF-15-C2 stormwater drainage projects along with two other projects (TF-13-C1 and TF-16-C1) under the Tasreef programme.
According to a source, a consultant has yet to be appointed.
TF-16-C1 involves upgrading and rehabilitating the stormwater system east of the Dubai Canal, while TF-13-C1 involves building a water pipeline stormwater drainage system at Al-Marmoum, Al-Qudra and Al-Yalayis 2 & 3.
Bids are currently under evaluation for the EPC contracts for both projects.
https://image.digitalinsightresearch.in/uploads/NewsArticle/17705058/main.jpg -
Dubai receives eight bids for Hassyan SWRO pipeline contract20 July 2026
Register for MEED’s 14-day trial access
Eight contractors have made offers for a contract to supply, install, test and commission glass-reinforced epoxy (GRE) water transmission pipelines and associated works for the Hassyan seawater reverse osmosis (SWRO) phase two network in Dubai.
The contract relates to project one of the Hassyan pipeline network expansion being undertaken by state utility Dubai Electricity & Water Authority (Dewa).
Local firm Binladin Contracting Group submitted the lowest offer of AED335.92m ($91.5m), according to results published by the utility.
The other bids were:
- Green Oasis General Contracting (UAE) – AED345.00m ($93.9m)
- Al-Nasr Contracting (UAE) – AED391.54m ($106.6m)
- Wade Adams Contracting (UAE) – AED393.80m ($107.2m)
- RMB Contracting (UAE) – AED437.96m ($119.3m)
- Tristar Engineering & Construction (UAE) – AED441.55m ($120.2m)
- Shapoorji Pallonji Mideast (UAE/India) – AED451.47m ($122.9m)
- Gulf Petrochemical Services Trading (UAE) – AED495.20m ($134.8m)
RMB also submitted a conditional discounted offer of AED427.02m ($116.3m). Three companies submitted regret notices, while one offer was rejected after no valid commercial offer was received.
In January, Dewa announced that construction of the 180-million-imperial-gallon-a-day phase one of the Hassyan SWRO independent water project was 90% complete.
Dewa has two other contracts out for tender for GRE water transmission pipeline work related to the Hassyan SWRO phase two network.
Project two was tendered on 22 January and has a bid submission deadline of 21 July. Project three was tendered on 26 January and has a bid submission deadline of 29 July.
https://image.digitalinsightresearch.in/uploads/NewsArticle/17704940/main.jpg -
Abu Dhabi launches E20 highway expansion project20 July 2026
Abu Dhabi’s Department of Municipalities and Transport (DMT) has announced the E20 highway expansion project.
The scheme covers widening the main carriageway from three to five lanes, constructing more than 10 kilometres (km) of new ramps and loops, and building four bridges.
Works also include 1.5km of internal roads and the addition of eight signalised junctions across Khalifa City and the Zayed International airport precinct.
The project includes utility works, comprising 62km of stormwater drainage, 37km of irrigation networks and the installation of 485 streetlights.
The E20 expansion is one of the major infrastructure schemes being overseen by DMT in Abu Dhabi.
Separately, DMT is evaluating bids for a design-and-build contract to construct two bridges serving Hudayriyat Island in Abu Dhabi.
The scope includes a two-lane bridge connecting 32nd Street to Shakhbout Bin Sultan Street, and a single-lane bridge on 8th Street. It also includes upgrades to signalised intersections.
Shakhbout Bin Sultan Street is a two-way road with three lanes in each direction, providing access to and from Hudayriyat Island.
https://image.digitalinsightresearch.in/uploads/NewsArticle/17704696/main.jpg -
Firms given more time for Mid Island Parkway prequalifications20 July 2026

Abu Dhabi’s Modon Infrastructure has extended the deadline to 31 July for firms to submit expressions of interest and prequalification statements for the next phase of Abu Dhabi’s Mid Island Parkway Project (MIPP), which will be developed as a public-private partnership (PPP).
The previous deadline was 15 July. MEED understands the prequalification notice was issued in June, following Modon Infrastructure’s invitation in May for firms to register their interest.
Modon Infrastructure will act as the lead developer and will hold a majority equity stake in the project company. It will award contracts for engineering, procurement and construction; operations and maintenance; and project advisory services.
Phase two of the MIPP involves the construction of about 11 kilometres (km) of highways, comprising a mix of three-, four- and five-lane sections. The highways will connect the Um-Yifeenah, Al-Jubail, Al-Sammaliyyah and Sas Al-Nakhl islands to Khalifa City and the E10 road.
The scope also includes the construction of three interchanges – E20, E10 and Dumbbell – on Al-Sammaliyyah Island.
The project includes several major structures, including the E20 interchange, which will feature cast-in-place box-girder and void-slab bridges, and the E10 interchange, which will feature cast-in-place box-girder bridges. It also includes I-girder bridges between Raha Beach West and Sas Al-Nakhl Island, as well as a causeway at Sas Al-Nakhl Island.
Further elements include a cast-in-place balanced cantilever bridge between Sas Al-Nakhl Island and Al-Sammaliyyah Island; a tunnel between Al-Sammaliyyah Island and Bilrimaid Island; and a cut-and-cover (open) tunnel on Bilrimaid Island. Another tunnel will connect Bilrimaid Island to Um-Yifeenah Island.
Abu Dhabi awarded three packages for phase one of the MIPP in 2024. The contract for Package 1A was awarded to a joint venture of Turkish contractor Dogus Construction and UAE firm Gulf Contractors. Package 1B was awarded to a joint venture of Yas Projects (Alpha Dhabi Holding) and China Railway International Group. Beijing-headquartered China Harbour Engineering Company and the UAE’s Agility Engineering & Contracting Company won the contract for Package 1C.
Phase one starts at the existing Saadiyat Interchange, connecting the E12 to the MIPP, and ends at the recently constructed Um-Yifeenah Highway.
It comprises a dual main road with a total length of 8km, including four traffic lanes in each direction, two interchanges, a tunnel and associated infrastructure works.
https://image.digitalinsightresearch.in/uploads/NewsArticle/17704765/main.jpg