Adnoc awards $17bn EPC contracts for Hail and Ghasha
5 October 2023
Register for MEED's guest programme
Abu Dhabi National Oil Company (Adnoc) has awarded $16.94bn-worth of engineering, procurement and construction (EPC) contracts for its Hail and Ghasha offshore sour gas field development project.
A consortium of Abu Dhabi’s National Petroleum Construction Company (NPCC) and Italian contractor Saipem has been awarded the offshore EPC package.
The value of the offshore contract is $8.2bn. The scope of work broadly involves EPC of offshore facilities, including facilities on artificial islands and subsea pipelines.
Italy-headquartered Tecnimont has been awarded the onshore EPC contract. The $8.74bn contract relates to the EPC of onshore facilities, including carbon dioxide (CO2) and sulphur recovery and handling.
Adnoc announced the award of EPC contracts, and reaching the final investment decision (FID), for the Hail and Ghasha project on the concluding day of the Abu Dhabi International Petroleum Exhibition and Conference (Adipec).
About 55 per cent of the investment value will flow back into the UAE’s economy under Adnoc’s In-Country Value (ICV) programme, it added.
MEED first reported in August that the consortium of NPCC and Saipem had emerged as frontrunners for the offshore package and Tecnimont for the onshore package. It was also recently reported that Adnoc was set to award EPC contracts and announce the FID during Adipec.
Net-zero gas production
The Hail and Ghasha fields are part of Abu Dhabi’s Ghasha concession, which is expected to produce more than 1.5 billion cubic feet a day (cf/d) of gas before the end of this decade.
Gas from the Ghasha concession is expected to “contribute to UAE gas self-sufficiency and Adnoc’s gas growth and export expansion plans,” Adnoc said in its statement on 5 October.
“The Hail and Ghasha megaproject aims to operate with net-zero carbon CO2 emissions, reinforcing Adnoc’s legacy of responsible energy production and supporting its net zero by 2045 ambition and accelerated decarbonisation plan,” it added.
The Hail and Ghasha development design combines decarbonisation technologies into one integrated solution. The project aims to capture 1.5 million tonnes a year (t/y) of CO2, in line with Adnoc’s committed investment for carbon capture capacity of almost 4 million t/y.
The CO2 will be captured, transported onshore and stored underground, while low-carbon hydrogen is produced that can replace fuel gas and further reduce emissions. The project will also leverage clean power from nuclear and renewable sources from the grid, Adnoc added.
“The carbon captured at Hail and Ghasha will support Adnoc’s wider carbon management strategy, which aims to create a platform that connects all the sources of emissions and sequestration sites to accelerate the delivery of Adnoc and the UAE’s decarbonisation goals,” Adnoc stated.
Execution of EPC works
The Abu Dhabi energy giant started a fresh EPC tendering round for the Hail and Ghasha project in late April, just days after cancelling the pre-construction services agreements (PCSAs) it signed with contractors in January.
Contractors expressed interest in participating in the latest Hail and Ghasha EPC tendering round by 19 May, MEED previously reported. Adnoc has since been in negotiations with contractors for the offshore and onshore EPC packages of the Hail and Ghasha scheme.
The new expression of interest document issued by Adnoc on 29 April detailed its latest EPC execution strategy for the Hail and Ghasha development. Under these plans, the offshore and onshore scope of work has been divided into three packages:
- Package one: Subsea pipelines, umbilicals, cables, risers and other offshore structures
- Package two: Offshore drilling centre facilities, the Ghasha offshore processing plant and central living quarters
- Package three: The Manayif onshore processing plant, including offsite export pipelines and tie-ins, utilities, the main control building and process buildings. Work on a Ruwais sulphur-handling terminal and other non-process buildings is an optional scope for this package.
Adnoc then integrated the EPC scope of work on the project into an offshore and onshore package.
ALSO FROM ADIPEC:
> Adnoc doubles 2030 carbon capture target
> Adnoc Gas awards $615m carbon capture contract
> Adnoc and Oxy to study direct air capture project
> Firms bid for Abu Dhabi airport tank farms project
> Sharjah and Ras al-Khaimah sign gas storage deal
PCSAs cancelled
The PCSAs signed in January with two consortiums, comprising three contractors each, marked the start of detailed engineering work and procurement of critical long-lead items for the offshore and onshore scope of work on the Hail and Ghasha development.
A consortium of France-headquartered Technip Energies, South Korean contractor Samsung Engineering and Tecnimont was awarded the PCSA for the onshore package. The contractors revealed the value of the contract to be approximately $80m.
Saipem, NPCC and state-owned China Petroleum Engineering & Construction Company (CPECC) won the PCSA for the offshore package, worth $60m.
Previously, the onshore work on the Hail and Ghasha scheme involved the construction of a gas process plant, pipeline network and new gas gathering units.
The offshore PCSA covered installing offshore platforms, gas compression facilities and more than 400 kilometres of subsea pipelines.
The reason for these PCSAs being annulled is unclear, but sources said the cost estimates submitted for the project were higher than Adnoc’s overall budget.
Protracted project timeline
The cancelled PCSAs were part of an early engagement process with contractors that Adnoc started following the termination of at least two earlier bidding rounds.
US engineering firm Bechtel completed the project’s original front-end engineering and design (feed) in 2019, with tenders for four EPC packages issued soon after.
Following the submission of commercial bids in early 2021, Adnoc made revisions to the feed as part of an optimisation process started by Technip Energies in November 2021. The revised feed aimed to reduce the scheme’s overall capital expenditure, which was previously estimated to be as high as $15bn.
The four original EPC packages were consolidated into two integrated offshore and onshore packages, thought to be worth as much as $5bn and $5.5bn, respectively, based on the previous version of the project.
MEED reported in September last year that early engagement contractors had submitted proposals for the detailed engineering work on the Hail and Ghasha development. The January PCSAs are understood to have been issued based on these proposals.
Hail and Ghasha fields
The Hail and Ghasha fields, along with the Hair Dalma, Satah, Bu Haseer, Nasr, Sarb, Shuwaihat and Mubarraz fields, are located in Abu Dhabi’s offshore Ghasha concession.
Adnoc holds the majority 55 per cent stake in the Ghasha concession. The other stakeholders are Italian energy major Eni with 25 per cent, Germany’s Wintershall Dea with 10 per cent and Austria’s OMV and Russia’s Lukoil, each with 5 per cent.
In November 2021, Adnoc and its partners in the Ghasha concession awarded two EPC contracts for the Dalma offshore sour gas development project. Abu Dhabi’s NPCC and Spain-headquartered Tecnicas Reunidas won contracts worth $1.46bn to execute offshore and onshore EPC works on the Dalma project, respectively.
Four artificial islands have already been completed in the Ghasha concession, and development drilling is under way.
In addition, Adnoc awarded two contracts totalling $2bn to its subsidiary Adnoc Drilling in July last year for the Hail and Ghasha offshore sour gas field development project.
The awards comprise a $1.3bn contract for integrated drilling services and fluids, and a $711m contract to provide four island drilling units. Their duration is 10 years.
Adnoc also awarded a third contract, valued at $681m, to another subsidiary, Adnoc Logistics & Services, to provide offshore logistics and marine support services for the planned Hail and Ghasha development.
Exclusive from Meed
-
Abu Dhabi and US firms form $25bn power joint venture
20 March 2025
-
-
Teams form for Al-Sila wind IPP
20 March 2025
-
Barakah 2 talks may start in two years
19 March 2025
-
Chinese firm wins Damac Riverside villas construction
19 March 2025
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends

Related Articles
-
Abu Dhabi and US firms form $25bn power joint venture
20 March 2025
Abu Dhabi-based critical infrastructure-focused sovereign investor, ADQ and US-headquartered Energy Capital Partners (ECP) have agreed to establish a 50:50 partnership in new build power generation and energy infrastructure.
ECP is the largest private owner of power generation and renewable facilities in the US.
The firms plan to make total capital investments of more than $25bn across 25GW worth of projects, with the US as the primary focus.
The combined initial capital contribution from the partners is expected to amount to $5bn.
“The partnership will focus on serving the needs of data centers and industrial centers in the US and selected other international markets over the long-term,” ADQ said in a statement on 19 March, a day after UAE National Security Adviser and Abu Dhabi Deputy Ruler, Sheikh Tahnoon bin Zayed Al- Nahyan met with US President Donald Trump at the White House.
ADQ said the partnership aims to service the growing power needs of data centres, hyperscale cloud companies and other energy-intensive industries.
“As the continuity and quality of power supply is crucial for these high-growth industries, the need for captive power plants that are in proximity is often a pre-requisite,” ADQ said.
The partnership is focused on meeting these needs over the long term with its mandate including greenfield development, new build and expansion opportunity projects.
A portion of the capital may also be allocated towards opportunities in selected other international markets.
The statement cited a recent report by the International Energy Agency (IEA) stating the world’s electricity consumption is forecast to rise at its fastest pace in recent years.
The growing need of data centers and industrial electrification partly account for the surging consumption.
In the US, for instance, a substantial increase in electricity demand is expected to add the equivalent of California's current power consumption to the national total over the next three years.
Recent research also forecasts that global power demand from data centres will increase by 50% by 2027 and by as much as 165% by the end of the decade, driven by the expansion of AI and high-density data centres.
The US Department of Energy estimates that data centre load growth has tripled over the past decade and is projected to double or triple by 2028.
https://image.digitalinsightresearch.in/uploads/NewsArticle/13525493/main.jpg -
QatarEnergy LNG receives bids for decarbonisation project
20 March 2025
Register for MEED’s 14-day trial access
QatarEnergy LNG has received bids from contractors for a carbon dioxide (CO2) sequestration complex project covering its liquefied natural gas (LNG) production operations in Qatar’s Ras Laffan Industrial City (RLIC).
Once commissioned, the planned sequestration facility will be capable of capturing 4.3 million tonnes a year (t/y) of CO2 from QatarEnergy LNG’s production operations in RLIC.
Contractors submitted bids for the project, estimated to be valued at $2bn-$2.5bn, by the deadline of 13 March, sources told MEED.
The following contractors are among those that are understood to have submitted bids for engineering, procurement and construction (EPC) works on the QatarEnergy LNG CO2 sequestration project:
- Chiyoda (Japan) / Consolidated Contractors Company (Greece/Lebanon)
- Larsen and Toubro Energy Hydrocarbon (India)
- Samsung C&T (South Korea)
The planned sequestration facility will capture CO2 from seven LNG trains at the QG North complex and three LNG trains at the QG South complex. The CO2 captured from the trains is to be compressed and injected into new injection wells, for which new compression trains and pipelines need to be installed.
The EPC scope of work on the project covers the following:
- QG North complex:
- Installation of four new electric-driven compressors
- New power substation for power import from Kahramaa 65MW
- New ITR for DCS/ESD/F&G
- Tie-ins with utility units
- Dehydration package
- Pig launcher
- QG South complex:
- Installation of two new electric-driven compressors
- Integration with South injection system unit 85
- Solvent reformulation for South trains 1/23
- New power substation for power import from Kahramaa 35MW
- New SIH for DCS/ESD/F&G
- Tie-ins with utility units
- Dehydration package
- Chillers package
- Pig launcher
- RLIC corridors
- Common 22-inch export pipeline stretching 18 kilometres
- Power tie-in RLF3 with Kahramaa
- Electric cables
- Fiber optic cable
- Lot W15
- Six injection wells by QatarEnergy LNG subsurface
- Six injection flowlines and metring skid
- Six wellhead control panels
- Power tie-in from Barzan
- Substation
- Pig receiver
- Access road and fencing
QatarEnergy LNG awarded Australia-headquartered consultancy Worley a contract in September 2023 for the execution of the front-end engineering and design (feed) work on the project, as well as to prepare the EPC scope of work.
North Field LNG expansion
Meanwhile, QatarEnergy LNG, a subsidiary of state enterprise QatarEnergy, continues to press forward with its North Field LNG expansion programme.
The estimated $40bn North Field LNG expansion programme aims to raise Qatar’s total LNG production capacity from 77.5 million t/y to 142 million t/y in three phases.
QatarEnergy is understood to have spent almost $30bn on the two phases of the North Field LNG expansion programme, North Field East and North Field South, which will increase its LNG production capacity from 77.5 million t/y to 126 million t/y by 2028.
EPC works on the two projects are making progress.
QatarEnergy awarded the main EPC contracts in 2021 for the North Field East project, which is projected to increase LNG output to 110 million t/y by this year. The main $13bn EPC package, which covers the engineering, procurement, construction and installation of four LNG trains with capacities of 8 million t/y each, was awarded to a consortium of Japan’s Chiyoda Corporation and France’s Technip Energies in February 2021.
QatarEnergy awarded the main EPC contract for the North Field South LNG project, worth $10bn, in May 2023. The contract covers two large LNG processing trains, each with a capacity of 7.8 million t/y, and was awarded to a consortium of Technip Energies and Lebanon-based Consolidated Contractors Company.
When fully commissioned, the first two phases of the North Field LNG expansion programme will contribute a total supply capacity of 48 million t/y to the global LNG market.
In February 2024, QatarEnergy announced the third phase of its North Field LNG expansion programme. To be called North Field West, the project will further increase QatarEnergy’s LNG production capacity to 142 million t/y when it is commissioned by 2030.
The North Field West project will have an LNG production capacity of 16 million t/y, which is expected to be achieved through two 8 million t/y LNG processing trains, based on the two earlier phases of QatarEnergy’s LNG expansion programme. The new project will draw feedstock for LNG production from the western zone of Qatar’s North Field offshore gas reserve.
February's special report on Qatar includes:
> COMMENT: Doha works to reclaim spotlight
> ECONOMY: Qatar economy rebounds alongside diplomatic activity
> BANKING: Qatar banks look to calmer waters in 2025
> UPSTREAM: QatarEnergy strives to raise gas and oil production capacity
> DOWNSTREAM: Qatar chemical projects take a step forward
> POWER & WATER: Facility E award jumpstarts Qatar’s utility projects
> CONSTRUCTION: Qatar construction shows signs of recovery
> DATABANK: Qatar maintains stable growth headinghttps://image.digitalinsightresearch.in/uploads/NewsArticle/13525489/main2030.jpg -
Teams form for Al-Sila wind IPP
20 March 2025
Register for MEED’s 14-day trial access
Prequalified developers have started to form consortiums to bid for a contract to develop a wind farm in Abu Dhabi.
In February, Abu Dhabi state offtaker Emirates Water & Electricity Company (Ewec) invited prequalified developers to submit their proposals for the contract.
According to an industry source, Ewec expects to receive bids for the Al-SIla wind independent power project (IPP) by 31 July.
The 140MW Al-Sila wind IPP will have a generation capacity of up to 140MW. When fully operational, it will more than double the existing wind generation capacity in the UAE.
Ewec has prequalified 10 firms as managing partners, which "are free to bid either individually or as part of a consortium with other prequalified bidders". These are:
- Acciona (Spain)
- Alfanar (Saudi Arabia)
- AlJomaih Energy & Water (Saudi Arabia)
- EDF Renewables (France)
- Envision (China)
- International Power (Engie, France)
- Jera (Japan)
- Marubeni (Japan)
- SPIC Huanghe Hydropower Development Company (HHDC, China)
- Sumitomo (Japan)
Ewec prequalified six firms as consortium members, which can bid as part of a consortium with a managing partner listed above.
These are:
- Alghanim International (Kuwait)
- China Energy Overseas Investment Company (China)
- Etihad Water & Electricity (local)
- Ming Yang Smart Energy Group (China)
- Orascom Construction (Egypt)
- PowerChina International Group (China)
The Al-Sila wind project will involve the development, financing, construction, operation, maintenance and ownership of the wind farm and associated infrastructure.
The project will follow Abu Dhabi’s IPP model, where developers enter into a long-term power-purchase agreement with Ewec as the sole procurer of electricity.
Ewec expects the project to generate enough clean electricity to power 36,000 homes, displacing 190,000 tonnes of carbon dioxide annually.
It will also directly contribute to Abu Dhabi’s Clean Energy Strategic Target 2035, which calls for 60% of electricity production to be generated from renewable and clean sources.
Together with the existing UAE wind assets, the new project will increase the UAE’s wind generation capacity to approximately 240MW, laying the foundation for further wind energy expansion, according to Ewec’s latest Statement of Future Capacity Requirements report.
In October last year, Ewec and Abu Dhabi Future Energy Company (Masdar) signed a power-purchase agreement for several wind power plants in Abu Dhabi and the emirate of Fujairah, with a combined capacity of over 100MW.
Their locations and capacities are:
- Sir Baniyas Island (Abu Dhabi): 45MW
- Delma Island (Abu Dhabi): 27MW
- Al-Sila Abu Dhabi: 27MW
- Al-Halah (Fujairah): 4.5MW
Masdar developed the 103.5MW wind power projects, which use “the latest technology and innovation to capture low wind speeds at utility scale, adopting advances in material science and aerodynamics to make wind power possible in the country”.
The Al-Sila wind farm takes the total number of IPPs that are at various procurement stages in Abu Dhabi to seven. The other schemes are:
- Al-Nouf combined-cycle gas turbine (CCGT) plant: 3,300MW
- Taweelah C CCGT plant: 2,500MW
- Madinat Zayed open-cycle gas turbine plant: 1,500MW
- Al-Khazna solar IPP: 1,500MW
- Al-Zarraf solar IPP: 1,500MW
- Battery energy storage system 1: 400MW
These IPPs have a total combined capacity of over 10.7GW.
https://image.digitalinsightresearch.in/uploads/NewsArticle/13525006/main4931.jpg -
Barakah 2 talks may start in two years
19 March 2025
Discussions for the next phase of the UAE's nuclear power plant in Barakah may be delayed by around two years, a source familiar with the plans tells MEED.
The 5.6GW Barakah nuclear power plant's four reactors entered full operations in September last year, which has intensified speculation about when the procurement process for the plant's next phase could start.
"I think they might be considering comparing the tariffs between the next nuclear power plant and the round-the-clock renewable energy project," the source said, referring to the 5.2GW solar photovoltaic plus 19 gigawatt-hour battery energy storage system project in Abu Dhabi, which Abu Dhabi Future Energy Company (Masdar) is developing.
The round-the-clock project is expected to deliver 1GW of 'baseload' renewable power.
In addition, the state utility, Emirates Water & Electricity Company (Ewec) does not foresee an additional 2.8GW of nuclear energy installed capacity until 2039, which implies that – given the average 10-year construction period for nuclear power plants – procurement talks "will only likely start sometime between 2027 and 2028".
Prior to the Barakah nuclear power plant's completion, Hamad Alkaabi, the UAE's permanent representative to the Austria-based International Atomic Energy Agency, was quoted as saying that the tendering process for the UAE's next nuclear power plant could start before the end of 2024.
The government has yet to budget for a second power plant or decide on the size or location of such a project, but Alkaabi said it is possible that a tender could be issued this year, the Reuters report, published in July 2024, said.
However, indications started to emerge in December that the planned second phase of the nuclear power plant could be delayed.
MEED has requested a comment from Emirates Nuclear Energy Company.
Expansion plans
The next phase of the Barakah power plant, comprising reactors five to eight, has been in the planning stage since 2019, according to regional projects tracker MEED Projects.
The UAE became the first Arab state to operate a nuclear power plant when the plant's first reactor became operational in 2021.
Each of the four reactors at the Barakah nuclear power plant can produce 1,400MW of electricity.
The entire plant reached full commercial operations approximately 16 years after Abu Dhabi first announced the project in 2008, and 12 years after construction works commenced on Unit 1.
READ THE MARCH MEED BUSINESS REVIEW – click here to view PDF
Chinese contractors win record market share; Cairo grapples with political and fiscal challenges; Stronger upstream project spending beckons in 2025
Distributed to senior decision-makers in the region and around the world, the March 2025 edition of MEED Business Review includes:
> AGENDA 1: Chinese firms dominate region’s projects market> AGENDA 2: China construction at pivotal juncture> UPSTREAM 1: Offshore oil and gas sees steady capex> UPSTREAM 2: Saudi Arabia to retain upstream dominance> DIRIYAH: Diriyah CEO sets the record straight> SAUDI POWER: Saudi power projects hit record high> AUTOMOTIVE: Saudi Arabia gears up to lead Gulf’s automotive sector> EGYPT: Egypt battles structural issues> GULF PROJECTS INDEX: Gulf hits six-month growth streak> CONTRACT AWARDS: High-value deals signed in power and industrial sectors> ECONOMIC DATA: Data drives regional projectsTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/13513708/main5944.jpg -
Chinese firm wins Damac Riverside villas construction
19 March 2025
Register for MEED’s 14-day trial access
Dubai-based real estate developer Damac Properties has appointed Chinese contractor China Nuclear Industry No. 22 Construction Company (CNNCC) as the main contractor to build its Damac Riverside villas project.
The 594-unit residential project is located in the Dubai Investment Park area.
The project award follows Damac's appointment of CNNCC as the main contractor for its Damac Casa tower.
Damac Casa is a 43-storey residential building being built in the Al-Sufouh 2 area of Dubai.
Dubai’s heightened real estate activity is in line with GlobalData’s forecast that the construction industry will register annual growth of 3.9% in 2025-27, supported by investments in infrastructure, renewable energy, oil and gas, housing, industrial and tourism projects.
The residential construction sector is expected to record an annual average growth rate of 2.7% in 2025-28, supported by private investments in the residential housing sector, along with government initiatives to meet rising housing demand.
https://image.digitalinsightresearch.in/uploads/NewsArticle/13510084/main.jpg