Adnoc awards $1.34bn Estidama project contracts
3 July 2023

Register for MEED's guest programme
Adnoc Gas, the natural gas processing business of Abu Dhabi National Oil Company (Adnoc Group), has awarded contracts for two key packages of its project to upgrade its sales gas pipeline network across the UAE.
The total value of the two engineering, procurement and construction (EPC) contracts for the project, also known as Estidama, is estimated to be $1.34bn, Adnoc Group said in a statement on 3 July.
UK-headquartered Petrofac has been awarded the EPC contract for package 2 of the Estidama project. Package 2 is understood to be worth $720m, sources told MEED.
A consortium of Abu Dhabi’s National Petroleum Construction Company (NPCC) and Lebanon-headquartered CAT Group has won Estidama package 3, which is valued at approximately $630m, according to sources.
The new pipeline will extend Adnoc Gas’ existing 3,200-kilometre pipeline network to over 3,500km, enabling the transportation of higher volumes of natural gas to customers in the Northern Emirates of the UAE.
“This strategic pipeline extension will drive further growth for Adnoc Gas as it continues to supply sustainable gas supplies in the UAE in support of the company’s strategy to increase its market share and enhance its customer base,” Adnoc said in its statement.
Over 70 per cent of the contracts’ value is expected to flow back into the UAE economy under Adnoc Group’s In-Country Value (ICV) localisation scheme, Adnoc added.
Key Estidama packages
Adnoc Gas Processing, now part of Adnoc Gas, initially intended to issue separate EPC tenders for packages 2 and 5. However, it tendered these as a combined job in June last year. Contractors submitted technical bids for these packages in August 2022.
Eventually, Adnoc Gas divided the scope of work on combined packages 2 and 5, MEED reported in February this year.
Following the revision of the scope of work, Estidama package 2 broadly involves building a new facility at the KP-30 location of the Habshan gas compressor plant (HGCP) and installing three variable frequency drive motor-driven compressors.
Adnoc Gas received technical proposals for Estidama package 2 on 24 February. Contractors submitted commercial bids by 27 March.
Along with Petrofac, the following contractors, among others, are understood to have submitted commercial bids for Estidama package 2:
- Archirodon (Greece)
- Engineering for Petroleum & Process Industries (Enppi, Egypt)
- Larsen & Toubro Energy Hydrocarbon (India)
- NPCC (UAE)/Target Engineering Construction Company (UAE)/Tecnicas Reunidas (Spain)
Package 5 is expected to be tendered separately to contractors as part of a planned second phase of the sales gas pipeline upgrade project.
ALSO READ: Gas takes centre stage in Adnoc downstream expansion
Adnoc Gas issued the main tender for Estidama package 3 in late June last year.
Contractors submitted technical bids for the package in August 2022, while commercial bids were submitted by 21 November.
MEED previously reported that Italy-headquartered Arkad was the lowest bidder for package 3, with a quotation of about $590m. A source close to the project said that following months of “intense negotiations, due diligence processes and evaluation of project delivery capabilities”, Adnoc Gas picked the consortium of NPCC and CAT for the package.
The scope of work on package 3 covers the installation of new gas pipelines from the Habshan complex to the HGCP, and from the HGCP to the Sweihan customer receipt, along with associated facilities.
Sales gas pipeline project packages
Erstwhile Adnoc Gas Processing, now consolidated into Adnoc Gas, initially divided the EPC work on its estimated $2bn sales gas pipeline network enhancement project into seven main packages.
China Petroleum Pipeline Engineering performed the Estidama project’s front-end engineering and design works as part of a contract worth about $6m that Adnoc Gas Processing awarded the Chinese state-owned firm in October 2020.
MEED reported in December 2021 that Abu Dhabi-based contractor Integrated Specialised General Contracting Company (Iscco) had won package 1, which is understood to have a contract value of $18m.
Iscco subcontracted the detailed engineering works on package 1 to the Abu Dhabi branch of Sweden-headquartered consultancy Rejlers.
Adnoc Gas issued the main tender for package 6 and packages 3 and 2+5 in late June last year.
Contractors also submitted technical bids for package 6 in August 2022 and commercial bids by 21 November.
Work on package 6 entails the installation of a 52-inch, 74km pipeline from Sweihan to Al-Shuwaib in Abu Dhabi and building two block valve stations.
Adnoc Gas combined the scope of work on packages 4 and 7, and issued the main tender in November last year.
Contractors submitted technical bids for combined package 4+7 by 27 March. The project operator is yet to call for commercial bids for this package.
The main scope of work on the Estidama combined package 4+7 involves laying a new pipeline from the Al-Shuwaib pig launcher and pig receiver station to the Sajaa gas facility in Sharjah.
The scope also covers building a new gas pipeline between BVS-2/KP28.7 in Abu Dhabi to Dubai’s Margham gas facility to meet increased gas demand from Adnoc Gas Processing’s customer Dubai Supply Authority (Dusup).
“Up to a dozen contractors are likely to have submitted technical bids for [combined package] 4+7,” one source said.
Exclusive from Meed
-
Houthi truce collapse widens Gulf risk map15 July 2026
-
Saudi Downtown awards Al-Khobar infrastructure deal15 July 2026
-
Saudi Arabia opens third round of gas-fired IPPs15 July 2026
-
-
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Houthi truce collapse widens Gulf risk map15 July 2026
Register for MEED’s 14-day trial access
The Houthis’ declaration ending the de facto truce with Saudi Arabia has significantly increased the likelihood of renewed attacks on Red Sea shipping and regional infrastructure, broadening the threat environment beyond the Strait of Hormuz.
S&P Global Market Intelligence says the 13 July exchange is best understood as a potential widening of the renewed US-Iran escalation cycle into the Yemen and Red Sea theatres.
Houthi claims that Saudi Arabia was responsible for a strike on Sanaa International airport have not been independently confirmed. Saudi Arabia had not formally commented at the time the analysis was written.
The Yemeni militant group is likely to use the incident as a trigger that allows it to justify renewed military action while aligning with Iran’s wider effort to impose costs on US and Gulf interests, according to the research firm.
The decision to declare an end to de-escalation with Riyadh materially increases the likelihood of further missile and unmanned aerial vehicle (UAV) activity against infrastructure near the Yemen-Saudi border, as well as renewed pressure on maritime routes in the Red Sea and Bab Al-Mandab.
Aviation exposure
The resumption of direct hostilities broadens the range of vessels and ports likely to be subject to Houthi targeting, and presents severe risk to airports and stationary aircraft, S&P Global Market Intelligence says.
While the Houthis would probably not intentionally down civilian aircraft, there is a significant risk to aircraft in flight, particularly at lower altitudes close to airports, due to incoming UAVs and missiles and interceptor activity.
The broader risk is to regional logistics rather than any single target set, the analysis says.
If escalation around the Strait of Hormuz coincides with renewed Houthi activity in the southern Red Sea, Bab Al-Mandab and the Gulf of Aden, commercial operators face a more complex dual-chokepoint environment, with the added likelihood that the Houthis will seek to target Hormuz bypass infrastructure across the Gulf.
That would raise the likelihood of shipping delays, higher insurance costs, more conservative routing decisions and greater interest in alternative corridors or bypass routes.
https://image.digitalinsightresearch.in/uploads/NewsArticle/17680608/main.jpg -
Saudi Downtown awards Al-Khobar infrastructure deal15 July 2026
Register for MEED’s 14-day trial access
Saudi Downtown Company, a wholly owned subsidiary of the Public Investment Fund (PIF), has awarded a contract for infrastructure works in downtown Al-Khobar.
The contract was awarded to local contractor Ansab General Contracting Company.
The scope of work includes the design and development of overall infrastructure, road networks and street lighting for the downtown Al-Khobar project.
Saudi Downtown Company was officially launched in 2022 by Saudi Crown Prince Mohammed Bin Salman Bin Abdulaziz Al-Saud, who is also chairman of PIF.
At the time, the company announced plans to develop downtown areas in 12 cities across the kingdom: Medina, Al-Khobar, Al-Ahsa, Buraidah, Najran, Jizan, Hail, Al-Baha, Arar, Taif, Dumat Al-Jandal and Tabuk.
SDC’s mandate is to develop more than 10 million square metres of land across its projects
https://image.digitalinsightresearch.in/uploads/NewsArticle/17677176/main.jpg -
Saudi Arabia opens third round of gas-fired IPPs15 July 2026
Register for MEED’s 14-day trial access
Principal buyer Saudi Power Procurement Company (SPPC) has opened the qualification process for the third round of conventional independent power projects (IPPs) using combined-cycle gas turbine (CCGT) technology.
The round is being tendered under the supervision of the Ministry of Energy. Each plant will be built with provision for carbon capture unit readiness, allowing the technology to be deployed at a later stage.
Each project will be developed on a build-own-operate (BOO) basis, with the winning consortium taking 100% equity in a special purpose vehicle (SPV) set up to develop and operate the plant.
Each SPV will sign a power purchase agreement with SPPC, which is licensed by the Saudi Electricity Regulatory Authority (SERA) to prepare preliminary studies, tender and award IPPs, and purchase electricity from energy projects in the kingdom.
The programme forms part of Saudi Arabia’s Circular Carbon Economy approach, which underpins the energy sector element of the Vision 2030 strategy. Riyadh is displacing liquid fuels with natural gas in power generation to cut emissions intensity, while designing new plants so that carbon capture equipment can be retrofitted in support of national emissions targets.
In April, Acwa and Saudi Energy (formerly Saudi Electricity Company) signed a 31-year power purchase agreement (PPA) with SPPC for the Rabigh 2 IPP expansion.
The project involves the development of a CCGT plant in the Mecca region. It will have a total capacity of 2,313.5MW.
The contract is valued at SR11.5bn ($3.07bn), the companies said in separate stock exchange filings.
https://image.digitalinsightresearch.in/uploads/NewsArticle/17676286/main.jpg -
Dubai selects contractor for Al-Maktoum airport people mover15 July 2026

Register for MEED’s 14-day trial access
Dubai Aviation Engineering Projects (DAEP) has selected a contractor to deliver the automated people-mover system as part of the first phase of the $35bn expansion of Al-Maktoum International airport.
A team of Japan’s Mitsubishi Corporation and Indian contractor Larsen & Toubro is the selected contractor.
The automated people-mover system will serve as a critical facility for operations at Al-Maktoum International airport. The system will run under the apron of the entire airfield and the airport’s terminals. It will consist of multiple tracks, taking passengers from the terminals to the concourses.
Four underground stations will be built as part of the first phase. The overall plan includes 14 stations across the airport.
The firms submitted the bids for the project in July last year, as MEED exclusively reported.
The contract is the latest in a series of awards signed by DAEP recently. DAEP has awarded contracts valued at about AED13bn, with construction works currently under way on several airport packages.
These include enabling works, the second runway, and the initial structural foundations for passenger terminals and gates.
Upcoming awards
In June, DAEP said that it will award contracts worth over AED55bn ($15bn) by the end of this year for construction works at Al-Maktoum International airport.
The projects slated for contract awards include the substructure works for the Western Passenger Terminal, the fourth aircraft concourse building and the baggage handling system, in addition to the superstructure works for the Western Passenger Terminal and the first, second and third aircraft concourses.
The packages also encompass long-span structural frameworks for buildings covering about 1.5 million square metres (sq m), infrastructure works for the southern airfield area, and power generation and district cooling plants supporting the construction programme.
The award of the facade and roofing packages is also planned for this year.
Construction progress
In May last year, MEED exclusively reported that DAEP had awarded a AED1bn ($272m) deal to UAE firm Binladin Contracting Group to construct the second runway at the airport.
The enabling works on the terminal were awarded to Abu Dhabi-based Tristar E&C.
Construction on the project’s first phase is expected to be completed by 2032.
Construction on substructure works began in November last year, when DAEP formally selected a contractor to deliver the package.
The government approved the updated designs and timelines for its largest construction project in April 2024.
In a statement, the authorities said the plan is for all operations from Dubai International airport to be transferred to Al-Maktoum International within 10 years.
According to an official description on DAEP’s website, the expanded airport’s West Terminal will be a seven-level, 800,000 sq m facility with an annual capacity of 45 million passengers.
It will be the second of three terminals at Al-Maktoum International airport.
In September 2024, MEED exclusively reported that a team comprising Austria’s Coop Himmelb(l)au and Lebanon’s Dar Al-Handasah had been confirmed as the lead masterplanning and design consultants on the expansion of Al-Maktoum airport.
The airport’s construction is planned to be undertaken in three phases. The airport will cover an area of 70 square kilometres south of Dubai and will have five parallel runways and 430 aircraft gates.
It will be five times the size of the existing Dubai International airport and will have the world’s largest passenger-handling capacity of 260 million passengers a year. For cargo, it will have the capacity to handle 12 million tonnes a year.
https://image.digitalinsightresearch.in/uploads/NewsArticle/17674721/main.png -
Chinese contractor wins Kuwait investment authority HQ15 July 2026
Register for MEED’s 14-day trial access
Beijing-headquartered China State Construction Engineering Corporation (CSCEC) has won a contract to build the permanent headquarters of the Kuwait Direct Investment Promotion Authority (KDIPA).
The contract covers the construction of a 275-metre, 55-storey office tower located in Kuwait City’s Sharq district. The project is expected to be completed by 2028.
According to results published on the Kuwait Central Agency for Public Tenders (Capt) website, the firm initially submitted a bid of $233m, as MEED reported in January. The tender was issued on 19 October 2025 and bids were submitted on 18 November, MEED reported.
The contract is the latest in a series of high-profile projects signed by CSCEC in the GCC region this year. Last month, it won a contract to deliver the Janadriyah cultural district at Qiddiya entertainment city on the outskirts of Riyadh. The contract was awarded by gigaproject developer Qiddiya Investment Company (QIC).
The scope covers the construction of six structures, including a heritage building, a gateway hotel, a wadi hotel, a creative hub, a community centre and an open-air market.
In June, MEED exclusively reported that QIC had awarded CSCEC a contract to build a new transport hub at Qiddiya entertainment city.
The project is located within the resort core zone of the development.
Kuwait market overview
UK analytics firm GlobalData expects Kuwait’s construction industry to average annual growth of 4.9% in 2026-29, supported by government investment in renewable energy and transport infrastructure.
In September 2025, Kuwait’s government allocated KD1.3bn ($4.2bn) for 141 projects, as part of its capital spending during the fiscal year 2025-26. This allocation was intended for 162 current projects and 17 new projects.
According to government data, as of September 2025, the country had around 300 active projects, valued at about KD35.3bn ($115bn), with large infrastructure projects making up nearly half of that total.
https://image.digitalinsightresearch.in/uploads/NewsArticle/17674440/main.jpg