Adnoc awards $1.34bn Estidama project contracts

3 July 2023

 

Register for MEED's guest programme 

Adnoc Gas, the natural gas processing business of Abu Dhabi National Oil Company (Adnoc Group), has awarded contracts for two key packages of its project to upgrade its sales gas pipeline network across the UAE.

The total value of the two engineering, procurement and construction (EPC) contracts for the project, also known as Estidama, is estimated to be $1.34bn, Adnoc Group said in a statement on 3 July.

UK-headquartered Petrofac has been awarded the EPC contract for package 2 of the Estidama project. Package 2 is understood to be worth $720m, sources told MEED.

A consortium of Abu Dhabi’s National Petroleum Construction Company (NPCC) and Lebanon-headquartered CAT Group has won Estidama package 3, which is valued at approximately $630m, according to sources.

The new pipeline will extend Adnoc Gas’ existing 3,200-kilometre pipeline network to over 3,500km, enabling the transportation of higher volumes of natural gas to customers in the Northern Emirates of the UAE.

“This strategic pipeline extension will drive further growth for Adnoc Gas as it continues to supply sustainable gas supplies in the UAE in support of the company’s strategy to increase its market share and enhance its customer base,” Adnoc said in its statement.

Over 70 per cent of the contracts’ value is expected to flow back into the UAE economy under Adnoc Group’s In-Country Value (ICV) localisation scheme, Adnoc added.

Key Estidama packages

Adnoc Gas Processing, now part of Adnoc Gas, initially intended to issue separate EPC tenders for packages 2 and 5. However, it tendered these as a combined job in June last year. Contractors submitted technical bids for these packages in August 2022.

Eventually, Adnoc Gas divided the scope of work on combined packages 2 and 5, MEED reported in February this year.

Following the revision of the scope of work, Estidama package 2 broadly involves building a new facility at the KP-30 location of the Habshan gas compressor plant (HGCP) and installing three variable frequency drive motor-driven compressors.

Adnoc Gas received technical proposals for Estidama package 2 on 24 February. Contractors submitted commercial bids by 27 March.

Along with Petrofac, the following contractors, among others, are understood to have submitted commercial bids for Estidama package 2:

Package 5 is expected to be tendered separately to contractors as part of a planned second phase of the sales gas pipeline upgrade project.

ALSO READ: Gas takes centre stage in Adnoc downstream expansion

Adnoc Gas issued the main tender for Estidama package 3 in late June last year.

Contractors submitted technical bids for the package in August 2022, while commercial bids were submitted by 21 November.

MEED previously reported that Italy-headquartered Arkad was the lowest bidder for package 3, with a quotation of about $590m. A source close to the project said that following months of “intense negotiations, due diligence processes and evaluation of project delivery capabilities”, Adnoc Gas picked the consortium of NPCC and CAT for the package.

The scope of work on package 3 covers the installation of new gas pipelines from the Habshan complex to the HGCP, and from the HGCP to the Sweihan customer receipt, along with associated facilities.

Sales gas pipeline project packages

Erstwhile Adnoc Gas Processing, now consolidated into Adnoc Gas, initially divided the EPC work on its estimated $2bn sales gas pipeline network enhancement project into seven main packages.

China Petroleum Pipeline Engineering performed the Estidama project’s front-end engineering and design works as part of a contract worth about $6m that Adnoc Gas Processing awarded the Chinese state-owned firm in October 2020.

MEED reported in December 2021 that Abu Dhabi-based contractor Integrated Specialised General Contracting Company (Iscco) had won package 1, which is understood to have a contract value of $18m.

Iscco subcontracted the detailed engineering works on package 1 to the Abu Dhabi branch of Sweden-headquartered consultancy Rejlers.

Adnoc Gas issued the main tender for package 6 and packages 3 and 2+5 in late June last year.

Contractors also submitted technical bids for package 6 in August 2022 and commercial bids by 21 November.

Work on package 6 entails the installation of a 52-inch, 74km pipeline from Sweihan to Al-Shuwaib in Abu Dhabi and building two block valve stations.

Adnoc Gas combined the scope of work on packages 4 and 7, and issued the main tender in November last year.

Contractors submitted technical bids for combined package 4+7 by 27 March. The project operator is yet to call for commercial bids for this package.

The main scope of work on the Estidama combined package 4+7 involves laying a new pipeline from the Al-Shuwaib pig launcher and pig receiver station to the Sajaa gas facility in Sharjah.

The scope also covers building a new gas pipeline between BVS-2/KP28.7 in Abu Dhabi to Dubai’s Margham gas facility to meet increased gas demand from Adnoc Gas Processing’s customer Dubai Supply Authority (Dusup).

“Up to a dozen contractors are likely to have submitted technical bids for [combined package] 4+7,” one source said.

https://image.digitalinsightresearch.in/uploads/NewsArticle/10980546/main.jpg
Indrajit Sen
Related Articles
  • Eni completes $1bn Libya gas project

    20 October 2026

    Register for MEED’s 14-day trial access 

    Libya’s Mellitah Oil & Gas Company, a joint venture of Libya’s National Oil Corporation (NOC) and Italian oil and gas company Eni, has achieved mechanical completion on its Bouri gas utilisation project (GUP).

    In a statement, Eni said that start-up procedures are currently under way, enabling the recovery of associated gas produced from the Bouri field, which is located in Libya’s western offshore area.

    The main contract for the project, worth $1bn, was awarded to Italy’s Saipem in August 2023.

    The project involved the construction and installation of the new Bouri gas recovery module and related tie-in infrastructure that enables the recovery and treatment of gas that was previously flared.

    In its statement, Eni said that the project “represents one of the most significant emissions reduction initiatives in Libya’s energy sector”.

    It also said that it would contribute to improving the environmental performance of the country’s production system by reducing greenhouse gas emissions by approximately 1.5 million tonnes of carbon dioxide a year.

    The recovered gas will be supplied to the domestic market, adding about 700 million cubic metres a year and helping meet demand from the power generation sector.

    The project will also support additional gas volumes available for export to Europe through the GreenStream pipeline.

    Eni said: “The start-up of the Bouri GUP confirms the joint commitment of Eni and NOC to the development of Libya’s energy sector through initiatives that combine production growth, operational efficiency and environmental stewardship.

    “The project is part of a broader strategy aimed at enhancing the value of the country’s gas resources while reducing the emissions intensity of upstream activities.”

    Other key projects currently under way in Libya include the A&E Structures Project, which is focused on bringing new offshore gas resources onstream for both the domestic market and exports, as well as initiatives aimed at upgrading and optimising gas production and transportation infrastructures.

    Eni has been present in Libya since 1959, and the company’s equity production in the country in 2025 amounted to approximately 162,000 barrels of oil equivalent a day.

    The Bouri offshore field is part of Libya’s Block NC-41, located 120 kilometres north of the Libyan coast in the Mediterranean Sea.

    It was first discovered in 1976 at a depth of 8,700 feet. It is estimated to contain 4.5 billion barrels in proven recoverable crude oil reserves and 3.5 trillion cubic feet of associated natural gas, with an annual production potential of 6 billion cubic metres.

    The first development phase, costing nearly $2bn, was completed in 1990.

    This was immediately followed by a second development phase, which entailed drilling 55 new wells and constructing three additional platforms. Production began from the oil platforms DP4 and DP3 in August 1998.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/20770288/main3529.jpg
    Wil Crisp
  • Diriyah Company tenders East Wadi bridge

    20 October 2026

     

    Saudi Arabia’s Diriyah Company has invited contractors to bid on the construction of the DG II East Wadi Bridge, a key crossing within Riyadh’s Diriyah master development.  

    The bridge will provide an arterial road connection linking the Diriyah Gate Phase 2 (DG II) Infrastructure Package 1 and Package 2 zones.  

    The project scope involves the construction of a 100-metre clear-span, 44-metre-wide, single-span post-tensioned concrete bridge structure with integrated abutments and four architectural towers.  

    The contract also encompasses approach slabs, access roads, pavements, associated earthworks, architectural finishes and cladding, mechanical, electrical and plumbing installations, utility interfaces, bridge parapets, vehicle restraint systems, waterproofing, testing and commissioning, and associated temporary works.  

    The client will supply the detailed engineering design, and the selected contractor will develop the construction methodology.

    Diriyah Company issued the prequalification tender on 14 September, with submissions due by 10 December.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/20769223/main.png
    Yasir Iqbal
  • Kuwait selects firms for power works at housing projects

    20 October 2026

     

    Kuwait’s Public Authority for Housing Welfare (PAHW) has appointed contractors for works covering the supply and installation of 132kV underground cables at South Sabah Al-Ahmad Residential City.

    The contracts relate to engineering, procurement and construction (EPC) packages for works for 28 main 132/11kV substations across four phases.

    According to sources, Egypt’s Elsewedy Cables has won contracts for phases 1 and 3, while China’s TBEA Shandong Luneng Taishan Cable Company has won contracts for phases 2 and 4 of the development.

    In April, MEED reported that PAHW had received at least five bids for each of the first two packages, with Elsewedy and TBEA offering $44m and $40.5m, respectively.

    The first contract (phase 1) covers seven substations in zones N9, N7 and N5. The second contract (phase 2) covers seven substations in zones N10 and N5.

    PAHW issued two further 132kV underground cable tenders for the South Sabah Al-Ahmad residential development at the end of May, as reported by MEED.

    This included a contract (phase 3) covering the supply, extension and maintenance of 132kV underground cables linked to seven substations serving the N5, N6, N8 and N10 districts. Egytech Cables, a subsidiary of Elsewedy, submitted an offer of $39.95m, the lowest of four bids.

    The other contract (phase 4) covers the supply, extension and maintenance of 132kV underground cables feeding eight main transformer substations serving the N1, N6 and N11 districts. 

    MEED reported in July that TBEA had submitted an offer of $44.06m for the contract.

    South Saad Al-Abdullah 

    Separately, PAHW has appointed contractors for power transmission works at the South Saad Al-Abdullah residential development.

    The local firm Sayed Hamid Behbehani & Sons has won a contract to supply, install and maintain 10 main 132/11kV transformer substations for the development’s third phase. 

    Another local firm, Al-Ahleia Switchgear, has won a contract to supply, install and maintain 10 main 132/11kV transformer substations for the project’s fourth phase. 

    As reported in August, the contractors submitted bids of $104.2m and $103.3m, respectively.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/20761431/main.jpg
    Mark Dowdall
  • Taqa moves forward with Mirfa-Liwa scheme

    20 October 2026

     

    Taqa Transmission and Taqa Distribution are advancing a major water transmission and distribution scheme serving Mirfa, Madinat Zayed and Liwa in Abu Dhabi, sources told MEED.

    The project, originally estimated to cost $775m, has been in procurement for several years. According to sources, a request for proposals has been issued, with bids due on 5 January 2027.

    The initial submission deadline was 11 November, before it was extended.

    The project was previously tendered in December 2024, with contractors submitting bids for transmission and distribution packages in January 2025.  As of August, the bids were still under evaluation. It is unclear whether the latest tender represents a revised procurement process for the same scheme.

    The project comprises a water transmission system from Mirfa, alongside distribution networks serving farms and settlements in the western region.

    According to details seen by MEED, the latest scope includes a pumping station at Mirfa with a capacity of 128 million imperial gallons a day, about 125 kilometres of transmission pipelines to Muzairah, with branches to Madinat Zayed and Liwa Summit, and storage tanks at the three locations.

    The distribution network is divided into four geographic clusters covering Liwa East, Liwa West, Madinat Zayed and Seih Al-Kheir. The works include associated pipelines, pumping stations and storage facilities.

    The earlier procurement was structured as an engineering, procurement and construction scheme, divided between transmission and distribution works.

    As MEED understands, the latest tender is being pursued under a design, build and operate model, which extends the contractor’s responsibilities to operating the infrastructure after construction.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/20758109/main2934.jpg
    Mark Dowdall
  • Contractors prepare prices for Adnoc Onshore field facilities project

    20 October 2026

     

    Contractors are preparing commercial bids for Adnoc Onshore’s project to build on-plot and off-plot facilities at the Rumaitha and Shanayel fields in Abu Dhabi’s North East Bab oil field cluster.

    The project will enhance and sustain crude output at Rumaitha and Shanayel at 45,000 barrels a day (b/d), supporting Adnoc’s Accelerated Integrated Programme 5 (AiP5) drive to lift capacity to 5 million b/d by 2027.

    Adnoc Onshore issued the main tender for engineering, procurement and construction (EPC) works on 19 June. Contractors submitted technical bids by 5 August, sources told MEED.

    The on-plot works include adding a crude processing train, produced water treatment and reinjection systems, surface water pumps, and multi-stage gas compression and dehydration units. Works also include utilities, safety and control systems, modifications to existing Phase 1 units and 220kV power infrastructure.

    The off-plot scope includes installing and tying in new gas-lifted producer and water-injection wells, as well as building and expanding wellhead clusters. Contractors will also lay crude-gathering, water-injection and gas-export pipelines connecting to the Adnoc Gas network and extend 33kV overhead power lines across the fields.

    The tender follows Adnoc Onshore’s shift in strategy for the wider North East Bab development – comprising the Al-Nouf, Rumaitha and Shanayel fields – after scrapping an earlier engineering, procurement and construction management (EPCm) approach. MEED reported in December that the operator had cancelled an off-plot EPCm contract awarded to China Petroleum Engineering & Construction Corporation (CPECC) in October 2024. Adnoc later cancelled a separate on-plot EPCm tender that it received bids for in the second quarter of 2025.

    In addition to the North East cluster, Adnoc Onshore continues to make progress on EPC works for another similar project to build off-plot facilities at the South East cluster of oil fields in Abu Dhabi, which is also integral to Adnoc Group’s AiP5 campaign.

    The South East cluster comprises the Asab, Mender, Qusahwira, Sahil and Shah fields and accounts for approximately a third of Adnoc Onshore’s oil production capacity.

    MEED previously reported that Adnoc Onshore awarded CPECC the EPC works for the South East off-plot facilities project, with the contract value estimated at around $1.2bn.

    CPECC is also performing EPC works on the South East on-plot facilities project in a consortium with Greece-headquartered Archirodon. Adnoc Onshore awarded an estimated $1.5bn contract for that project to the consortium in December 2024, with EPC works scheduled for completion in 2027.

    ALSO READ: Adnoc Onshore seeks bids for Bu Hasa field EOR project

    https://image.digitalinsightresearch.in/uploads/NewsArticle/20757699/main.jpeg
    Indrajit Sen