Foreign interest in Syria’s oil and gas sector is growing as the government moves to revive the industry and elevated global energy prices improve the economics of new developments.

A series of agreements signed in recent months has attracted some of the world’s largest energy companies, raising expectations that investment and production could accelerate.

However, despite growing optimism, significant security, financial and regulatory challenges remain, which could constrain the pace of growth for years to come.

Military control

Optimism among foreign businesses about potential opportunities in the country was boosted in January this year when Syria’s central government regained control of most of the country’s oil and gas assets.

On 13 January 2026, the Syrian government launched an offensive against the Kurdish-led Syrian Democratic Forces (SDF) in the territories of the Democratic Autonomous Administration of North and East Syria.

The offensive was initially focused on eastern Aleppo Governorate, around the towns of Deir Hafer and Maskanah, and was expanded on 17 January to include Raqqa, Deir ez-Zor and Al-Hasakah Governorates.

The offensive eventually led to Syria’s Omar and Conoco fields being seized, as well as the Tanak, Rmeilan and Suwaydiyah fields.

The Omar field is Syria’s largest oil field and the Conoco field hosts Syria’s largest gas processing plant, which previously supplied several power stations, including the Jandar plant in Homs, one of the country’s largest.

Before the outbreak of the Syrian civil war in 2011, this field produced about 10 million cubic metres of natural gas a day.

On 18 January, an agreement was signed under which Damascus assumed administrative and security control over all major oil and gas assets previously held by the SDF in the northeast of the country.

Wider market

The push to take control of the oil and gas assets came ahead of the US and Israel attacking Iran on 28 February, which led to a regional conflict and disrupted shipping through the Strait of Hormuz.

Disruption in the waterway – which normally transports about 20 million barrels a day (b/d) of oil and refined products, as well as around 20% of the world’s liquefied natural gas – triggered a surge in global energy prices and sent oil companies scrambling to develop resources that did not rely on the strait as an export route.

Syria is increasingly being viewed as a potential option for major oil and gas development projects due to its significant unrealised reserves and its geographic position across the Mediterranean from consumer markets in Europe.

Syria’s production currently stands at around 110,000 b/d, down from a peak of 380,000 b/d in 2011, according to a report published by the US-Syria Business Council in April.

The country’s recoverable oil reserves are estimated at 2.5 billion barrels, and Syria also has significant gas reserves.

In April, Yousef Qiblawy, chief executive of the state-owned Syria Petroleum Company (SPC), said his organisation aimed to double national production before 2027 and boost output to 800,000 b/d by the end of 2029, not including offshore production.

He said: “Before the takeover of the northeast, we were producing 10,000-15,000 b/d.

“Currently, we are producing 100,000 b/d, and the plan now is to double this production number by the end of this year.”

He also expressed optimism about the outlook for projects in Syria’s portion of the Mediterranean Sea, saying: “New offshore and onshore exploration is also starting … there are 15 or 17 brand new green blocks, untouched in Syria, with huge reservoirs of oil mainly, and some gas.”

So far, no offshore wells have been drilled in Syrian waters.

In 2013, Russia’s Soyuzneftegaz signed an offshore exploration agreement with Damascus, but the project was abandoned during the civil war and never progressed to drilling.

Making deals

In recent months, a range of significant deals and meetings has raised expectations for the future of Syria’s oil and gas sector.

On 11 May, SPC announced plans for Syria’s first-ever offshore oil and gas exploration project.

The deep-water project is being carried out in partnership with US-based Chevron and Qatar’s UCC Holding.

SPC said that it had, together with Chevron and UCC Holding, defined the boundaries of the offshore block, paving the way for finalising contracts and starting technical operations this year.

The three companies previously signed a preliminary deal in February to evaluate offshore oil and gas exploration in Syrian waters.

On 12 May, France’s TotalEnergies, state-owned QatarEnergy and US-based ConocoPhillips signed a memorandum of understanding (MoU) with SPC relating to the exploration of Syria’s offshore Block 3.

Under the terms of the preliminary deal, the companies will carry out a technical review of the area.

The agreement also established a framework for technical and commercial discussions related to exploration activities on the block.

ConocoPhillips also signed another MoU in November last year, along with Houston-headquartered Novaterra Energy, focused on developing several gas fields and launching exploration programmes.

This MoU included an agreement to rehabilitate the gas plant at the Conoco field in Deir ez-Zor province.

At the time, Qiblawy said the agreement was expected to boost the country’s gas production by 4-5 million cubic metres a day within a year.

On 8 May, the Croatian oil company INA and Hungary’s MOL announced that they had held a series of meetings with SPC focused on exploring options to restart INA’s oil and gas operations in Syria.

They said a joint technical team established by INA and SPC was assessing the feasibility of INA resuming operations on its Syrian concessions by evaluating operational, technical, commercial and regulatory conditions.

In 2011, oil and gas production at INA’s Syrian concessions had reached 37,300 barrels of oil equivalent a day.

By the time the company suspended operations in Syria in 2012, it had invested approximately $1.1bn in the country and had built a gas processing plant at the Hayan gas field.

Resuming activities

In April, the managing director of London-headquartered  met with Syria’s president, Ahmed Al-Sharaa.

Gulfsands is the official operator of Syria’s Block 26, but for 15 years after the start of the Syrian civil war, it could not access the asset.

The company declared force majeure in late 2011 and, until recently, it was under the control of the Kurdish-led SDF.

In a statement released after the April meeting with Syria’s president, John Bell confirmed that his company had recently regained access to Block 26, which he described as “an important milestone for Gulfsands and for Syria”.

He added: “This development provides a strong foundation for the recommencement of operations and investment.

“We are now back on the ground in Syria, working closely with SPC to accelerate towards a full resumption of activities.”

Bell also said that, as a result of a global drive to diversify away from “traditional choke points like the Strait of Hormuz”, Syria had the potential to become “a new world energy hub”.

In April, Saudi Arabia’s ADES Holding Company signed an implementation contract with SPC to develop several gas fields in Syria.

In a statement, SPC said the scope of the deal with ADES included executing maintenance and development works on existing wells, in addition to drilling new exploratory wells within the agreed operational areas.

It added that it expected the deal to increase gas production by 25% within the first six months and by 50% by the end of this year.

Industry insiders are also watching US-based HKN Energy, which has close ties to the Trump administration, after Qiblawy said in January that the company had expressed interest in entering the Syrian oil and gas sector.

In April, a statement from the US-Syria Business Council said an MoU with HKN was “in the pipeline”.

Over recent months, expectations have been building about a potential deal involving US-based oil and gas companies Baker Hughes, Hunt Energy and Argent LNG.

In July last year, Jonathan Bass, chief executive of Argent LNG, said that the three companies were planning to develop a masterplan for Syria’s oil, gas and power sector.

It was later reported, in February this year, that the three US-based companies were planning to form a consortium for oil and gas exploration and energy production in northeast Syria.

The consortium is expected to become involved in approximately four to five exploration blocks.

Commenting on his company’s plans in Syria, Argent LNG’s chief executive said: “We're very excited to be realising the visions of US President Donald Trump and Syrian President Ahmed Al-Sharaa, bringing the country forward from darkness to light.”

In a separate statement in April, Hunter Hunt, chief executive and chairman of Hunt Oil Company, said: “President Sharaa’s vision is bold, it is comprehensive, and it is full of execution and getting things done … We like what we see on a forward-looking basis.”

Challenges remain

While SPC’s Qiblawy has outlined ambitious targets to increase oil and gas production and international interest in the sector is growing, significant obstacles remain.

A report published by the US-Syria Business Council in April highlighted several risks facing prospective projects. Among the most significant is the threat posed by Islamic State, particularly to pipeline infrastructure crossing remote desert regions.

The report warned that securing large stretches of sparsely populated territory remains difficult, increasing the risk of attacks on critical energy infrastructure.

It also highlighted the possibility of renewed conflict in northeastern Syria, where the SDF previously controlled many of the country’s most important oil and gas assets. According to the report, the current ceasefire remains fragile and any deterioration in relations could reignite territorial disputes.

Beyond security concerns, international investors continue to face substantial financial and regulatory hurdles.

Although sanctions on Syria have been eased considerably, the country remains designated by the US as a State Sponsor of Terrorism. As a result, licences are still required for many controlled exports, including oilfield equipment, software and technology.

Restrictions also remain on support from international financial institutions. The US Export-Import Bank and the US International Development Finance Corporation continue to face limitations on their ability to support projects in Syria, constraining access to capital for large-scale developments.

These factors suggest that progress towards SPC’s production targets is likely to be slower than official projections imply.

Nevertheless, if Syria can continue to improve security conditions, strengthen political stability and maintain a supportive investment environment, the country’s oil and gas sector has the potential to deliver steady production growth over the coming years.

For international energy companies seeking opportunities outside traditional export routes and geopolitical chokepoints, Syria is increasingly emerging as a market with significant long-term potential, albeit one accompanied by substantial risk.

https://image.digitalinsightresearch.in/uploads/NewsArticle/17088770/main.png
Wil Crisp
Related Articles
  • Oman tenders Thumrait Industrial City infrastructure

    22 September 2026

     

    Oman’s Public Establishment for Industrial Estates (Madayn) has tendered an estimated RO15m ($39m) contract to develop infrastructure for Thumrait Industrial City.

    The tender was issued on 14 September, with bids due by 12 November.

    The scope covers site-wide utilities and services, including an internal road network, stormwater channels and culverts. It also includes installing sewerage and water networks, along with landscaping works.

    In addition, Madayn intends to build plug-and-play industrial units and a facilities building.

    The first phase of the development will cover about 120,000 square metres (sq m).

    Thumrait Industrial City is located in Oman’s Dhofar Governorate and spans an area of more than four million sq m.

    The project location is close to concession blocks, quarry sites and the Najd agricultural areas. It is positioned to attract industrial investments in sectors such as mining and minerals processing (including gypsum and cement), food production, and a range of light and general manufacturing activities.

    In March, Madayn said it is preparing to invest more than RO245m ($637m) to upgrade and expand infrastructure across its industrial cities between 2026 and 2030, as part of efforts to attract new investment and advance economic diversification.

    According to media reports, Madayn chief executive Dawood Bin Salim Al-Hadabi said the programme is part of an expanded, phased plan aligned with Oman Vision 2040 and the authority’s long-term Madayn 2040 strategy.

    The objective is to deepen Oman’s industrial base and spread growth across the sultanate’s governorates.

    Madayn said the pipeline comprises about 90 strategic projects to improve industrial-city infrastructure, extend serviced land and increase the overall ease of doing business for investors.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19866218/main.jpg
    Yasir Iqbal
  • Kuwait halves drilling contractor pool

    22 September 2026

     

    State-owned upstream operator Kuwait Oil Company (KOC) has reduced the number of approved contractors for onshore drilling and shallow-well maintenance from 51 to 24.

    Firms that are no longer qualified include major contractors such as Italy’s Saipem, Oklahoma-based Helmerich & Payne and Houston-based Patterson-UTI Energy.

    The latest list still includes a wide range of Kuwaiti, regional and international companies, according to the latest update on its electronic system, published on 21 September 2026.

    The full list of contractors that are now qualified to participate in tenders is:

    • Burgan Company for Well Drilling, Trading & Maintenance (Kuwait)
    • Kuwait Drilling Company (Kuwait)
    • Sun Drilling Kuwait (Kuwait)
    • TDL Kuwait for Oil Rigs & Natural Gas Extraction Activities, Services and Facilities (Kuwait)
    • United Precision Drilling (Kuwait)
    • Abraj Energy Services (Oman)
    • Adnoc Drilling Company (UAE)
    • Arabian Drilling Company (Saudi Arabia)
    • Anton Oilfield Services (China)
    • China Oilfield Services (China)
    • Egyptian Drilling Company (Egypt)
    • CNPC Bohai Drilling Engineering Company (China)
    • Great Wall Drilling Company (China)
    • John Energy (India)
    • Kerui Oilfield Service (China)
    • KCA Deutag Drilling (Germany)
    • Mohammed Al-Barwani Petroleum Services (Oman)
    • Nabors Drilling International (US)
    • National Drilling & Services Company (Oman)
    • Sea & Land Drilling Contractors (Oman)
    • Sinopec International Petroleum Service Corporation (China)
    • Karamay Jianye Energy (China)
    • Modern Drilling Company (Egypt)
    • Grey Wolf Drilling International (US)

    An earlier list, which was published on 11 February, included 51 qualified companies.

    The reduction in qualified drilling contractors follows KOC’s notice on 27 April this year, informing existing qualified contractors that they would need to reapply.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19863744/main3435.jpg
    Wil Crisp
  • Abu Dhabi expects 45% emissions cut as electricity demand rises

    21 September 2026

    Register for MEED’s 14-day trial access 

    Abu Dhabi-based Emirates Water & Electricity Company (Ewec) expects carbon emissions from power and water production to fall by more than 45% by 2035 as the UAE expands renewable energy and reverse osmosis (RO) desalination.

    The state offtaker's latest long-term system planning forecasts emissions will decline from about 42 million tonnes in 2019 to approximately 23 million tonnes in 2035.

    The reduction is expected despite annual electricity demand that is forecast to rise by about 70% in 2026-33.

    Ewec said the expansion of renewable energy and the shift towards RO desalination will be the principal drivers of the reduction.

    The company plans to increase Abu Dhabi's solar capacity to 14GW by 2030 and more than 35GW by 2035. This will be supported by up to 15GW of battery storage capacity.

    According to regional project tracker MEED Projects, Ewec has over $16bn-worth of power and water projects in the execution stage as part of its long-term procurement programme to increase renewable energy and low-carbon water production capacity.

    This includes a 5.2GW Abu Dhabi solar and battery energy storage system (bess) round-the-clock renewable energy project, as well as three 1.5GW solar photovoltaic independent power projects (IPP): Al-Ajban, Al-Khazna and Al-Zarraf.

    It also comprises the 1GW Al-Dhafra open-cycle gas turbine power plant, the 2.5GW Taweelah C combined-cycle gas turbine (CCGT) plant and a separate 400MW bess IPP.

    As previously reported, it is expected that the developer's agreement for the 3.3GW Al-Nouf 1 CCGT IPP will be signed by the end of the year, while contractors are preparing to submit bids for a separate 2.6GW power plant project in Ajman.

    The expansion of solar and battery storage is expected to reduce the system's reliance on gas-fired generation. However, gas-fired generation will continue to provide flexibility to support the system and balance intermittent renewable power output, according to Ewec. 

    The offtaker also expects RO desalination to account for more than 95% of total water production by 2035, with the procurement programme supporting the Abu Dhabi Department of Energy's Clean Energy Strategic Target 2035 for electricity production and the UAE Net Zero by 2050 Strategy.


    READ THE SEPTEMBER 2026 MEED BUSINESS REVIEW – click here to view PDF

    Nuclear power ambitions gather pace; Kuwait keeps dealmaking alive despite war; Region invests in raising gas processing capacity.

    Distributed to senior decision-makers in the region and around the world, the September 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/19849749/main.jpg
    Mark Dowdall
  • Seven bid for Bahrain highway upgrade

    21 September 2026

    Register for MEED’s 14-day trial access 

    Seven contractors have submitted bids for the next phase of the Sheikh Jaber Al-Ahmed Al-Sabah Highway upgrade project.

    According to results published by the Bahrain Tender Board, the firms that have submitted bids include:

    • Nass Contracting Company
    • Haji Hassan Group
    • Almoayyed Contracting Group
    • Mohammed Abdulmohsen Al-Kharafi & Sons
    • Eastern Asphalt & Concrete Production
    • Cebarco Bahrain
    • Kingdom Asphalt

    The contract scope includes expansion works on 2 kilometres of the highway. It consists of a four-lane dual carriageway with service roads on both sides.

    The scope of works also includes excavation and backfill work, construction of stormwater drainage networks, a pumping station, installation of ducts for future utilities, upgraded street lighting, traffic signs and directional signage.

    The project aims to improve traffic capacity, reduce congestion and enhance safety along the transport corridor linking Manama with industrial zones.

    In April, MEED reported that Bahrain had approved a financing agreement framework to fund the construction of the next phase of the Sheikh Jaber Al-Ahmed Al-Sabah Highway upgrade.

    In March last year, the Kuwait Fund for Arab Economic Development and the Bahraini government signed a KD10m ($32.4m) loan agreement to fund the second phase of the project, which is expected to cost about $404m.

    This was followed in September 2025 by the appointment of US-based Parsons Corporation on a $1.5m contract to provide pre-contract engineering consultancy services for the project.

    According to data from regional project tracker MEED Projects, construction of the first phase was completed in 2020.

    A joint venture of local firm Nass Contracting and Kuwait’s KCC Engineering & Contracting undertook the main construction works.


    READ THE SEPTEMBER 2026 MEED BUSINESS REVIEW – click here to view PDF

    Nuclear power ambitions gather pace; Kuwait keeps dealmaking alive despite war; Region invests in raising gas processing capacity.

    Distributed to senior decision-makers in the region and around the world, the September 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/19847073/main.png
    Yasir Iqbal
  • Teams prepare bids for Oman PPP wastewater project

    21 September 2026

     

    At least three consortiums are preparing bids for a contract to develop and operate two major sewage treatment plants (STPs) in Oman.

    The public-private partnership (PPP) project covers expanding two Muscat-based plants: the Al-Ansab STP (phase three) and the Al-Amerat STP (phase two). It will be delivered under a build-own-operate-transfer model.

    At Al-Ansab, capacity will increase from 125,000 cubic metres a day (cm/d) to 207,000 cm/d. At Al-Amerat, capacity will rise from 18,000 cm/d to 54,000 cm/d.

    According to sources, the bidders for the project include:

    • Etihad Water & Electricity (UAE) / Metito (UAE)
    • Lamar Holding (Bahrain) / Tawzea (Saudi Arabia)
    • Civil Works Company (CWC, Saudi Arabia)  / Suez (France)

    The bid submission deadline is 5 January 2027.

    State-owned Nama Water Services (NWS) issued a request for proposals for the project in July, as exclusively reported by MEED.

    It is understood that Veolia (France), Miahona (Saudi Arabia) and Samsung E&A (South Korea) are also among the firms that prequalified for the project after the request for qualifications was issued last November.

    The project scope includes the design, financing, construction, operation and maintenance of the new facilities, alongside the long-term operation of the existing facilities.

    It has been over a decade since the Al-Ansab STP first entered full operation at a capacity of about 54,000 cm/d. In 2015, South Korea’s Doosan Ennerbility, formerly Doosan Heavy Industries, was awarded the main engineering, procurement, and construction contract for the phase two expansion, which increased the facility’s maximum flow capacity to 125,000 cm/d. This phase was completed in 2017.

    Phase one of the Al-Amerat STP was awarded to a joint venture of France’s Degremont (Suez) and local contractor Al-Ansari Trading Enterprise under a design, build and short-term operation contract valued at about €50m ($58.1m). The plant was developed for Haya Water and commissioned in 2019 as part of the Muscat wastewater scheme.

    Haya Water, the former wastewater utility, was later incorporated into NWS following a government restructuring programme.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19794912/main.jpg
    Mark Dowdall