Abu Dhabi installs final solar panel for 1.5GW project
12 April 2023
Dhafrah PV2 Energy Company has installed the last crystalline bifacial solar panel for the 1,500MW Al-Dhafra solar photovoltaic (PV) independent power producer (IPP) project in Abu Dhabi.
This paves the way for the project company to start commissioning the project, which is expected to reach commercial operation this year.
The project is understood to involve deploying over 3 million bifacial solar PV modules mounted on 30,000 single-axis sun trackers.
The key shareholders in the firm implementing the project, Dhafrah PV2 Energy Company, are Abu Dhabi National Energy Company (Taqa), which maintains a 40 per cent stake, and Abu Dhabi clean energy firm Masdar, EDF and Jinko Power, which each own 20 per cent.
In March, it was reported that 1,200MW of the Al-Dhafra power plant had been connected to the Abu Dhabi Transmission & Company (Transco) power transmission grid.
Energoprojekt Entel, which advised Transco on the project, also said in March that a 400kilovolt (kV) substation and associated equipment had been tested, completed and connected to the 400kV overhead transmission line in the area.
The execution of the project, which is the world's largest single-site solar power plant under construction, coincided with global lockdowns and supply-chain constraints associated with the Covid-19 pandemic.
The Al-Dhafra solar PV power plant is key to the state utility's objective to increase its solar power generation capacity to 7,300MW by 2030.
RELATED READS:
State utility Emirates Water & Electricity Company (Ewec) signed the power-purchase agreement (PPA) and shareholders agreement with the developer consortium implementing the Al-Dhafra solar IPP project in July 2020.
A team comprising France's EDF and China's Jinko Power won the contract to implement the project.
The project reached financial close in December of the same year, with seven international banks providing project financing.

Photo: EPE (2023)
![]()
Photo: CMEC (2021)
China Machinery Engineering Corporation (CMEC), the project's engineering, procurement and construction (EPC) contractor, broke ground on the site in July 2021, after winning the $1bn EPC contract in January of that year.
Project milestones
Ewec received five initial bids for the contract to develop the scheme in November 2019.
The EDF/Jinko Power team submitted a levelised cost of electricity of AED4.97 fils a kilowatt-hour (kWh) (1.35 $cents/kWh).
The consultancy team advising the client on the project includes the UK's Alderbrook Finance, the US' White & Case and Austria's ILF Consulting.
The project involves the solar plant's financing, construction, operation and maintenance under a 30-year PPA.
The solar plant covers an area of 20 square kilometres. Upon completion, the project is expected to reduce Abu Dhabi's carbon emissions by more than 2.4 million metric tonnes a year, equivalent to removing about 470,000 cars from the roads.
Main photo: Noor Abu Dhabi, Ewec
Exclusive from Meed
-
Arada completes Sokoon buildings construction26 March 2026
-
Local contractor wins Medina substation contract26 March 2026
-
Neom terminates $5bn Trojena dams contract with WeBuild26 March 2026
-
Iraq gas field project disrupted by regional conflict26 March 2026
-
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Arada completes Sokoon buildings construction26 March 2026
Sharjah-based private real estate developer Arada has announced the completion of five additional buildings in the Naseej District of its Aljada development.
Kuwaiti firm Mohammad Abdulmohsen Al-Kharafi & Sons secured the construction contract for the Sokoon buildings in 2023, replacing Airolink Building Contracting as the project’s main contractor.
The first four Sokoon buildings were completed in December 2023.
In April last year, Arada also announced the completion of all eight Tiraz buildings in the Naseej District. The Tiraz buildings comprise 920 homes, including studios, one-bedroom and two-bedroom apartments.
With the completion of the five Sokoon buildings, Aljada’s total number of completed residential units has risen to more than 8,200.
Spanning 2.2 square kilometres, Aljada features residential districts, retail spaces, educational institutions, healthcare services and other facilities.
https://image.digitalinsightresearch.in/uploads/NewsArticle/16141382/main.png -
Local contractor wins Medina substation contract26 March 2026
Danway Saudi Arabia has won a contract with National Grid SA to construct a new 110/13.8kV substation in Medina.
The contract is valued at more than SR100m ($26.7m) and covers the construction of the King Abdulaziz Road substation, including design, engineering, supply, installation, testing and commissioning.
The project is expected to take approximately 23 months to complete.
Key components include 110kV gas-insulated switchgear (GIS), 50/67MVA 110/13.8kV power transformers and 13.8kV switchgear.
National Grid SA is a wholly owned subsidiary of Saudi Energy, formerly Saudi Electricity Company. It owns and operates the kingdom’s high-voltage transmission network and is responsible for grid planning, interconnection and system reliability.
The operator recently appointed another local firm, Nesma Infrastructure & Technology, as the contractor for the construction of two 380kV double-circuit overhead transmission lines in Riyadh, connecting an existing substation to a wind power substation, referred to as Samha Wind BSP.
As MEED understands, National Grid SA is also due to begin construction on the replacement of 132kV oil-filled underground cable circuits between several substations in the Central Operation Area in Murabba in Riyadh.
Riyadh-based Keir International is the engineering, procurement and construction contractor for the project.
https://image.digitalinsightresearch.in/uploads/NewsArticle/16139578/main.jpg -
Neom terminates $5bn Trojena dams contract with WeBuild26 March 2026
Register for MEED’s 14-day trial access
Neom has terminated its contract with Italian contractor Webuild for the construction of three dams feeding a freshwater lake, as well as ‘The Bow’ architectural structure at Trojena in northwest Saudi Arabia.
In a statement posted on its website, Webuild said: “The termination will become effective on 29 March. As of that date, the works are approximately 30% complete, with a remaining project backlog for Webuild of approximately €2.8bn ($3.2bn).”
Neom awarded Webuild a SR20bn ($5bn) contract to build the dams in late 2023, which MEED exclusively reported at the time.
The termination is the latest in a series of high-profile contract cancellations by Neom in recent weeks. Earlier this week, Neom terminated its contract with Malaysian contractor Eversendai Corporation for the steel structural works on the Ski Village project in Trojena.
In a statement published on its website, Eversendai said it had received an official notice that the termination would take effect from 26 March.
In January this year, Saudi Arabia confirmed the postponement of the 2029 Asian Winter Games, which were scheduled to be held at Trojena. Trojena was chosen to host the event in October 2022.
Neom has also cancelled contracts for the construction of the tunnel sections of The Line in northwest Saudi Arabia.
In a stock exchange filing dated 13 March, South Korean contractor Hyundai E&C said Neom cancelled its contract on 29 December last year.
Hyundai E&C was executing the drill-and-blast section of The Line’s tunnels in a joint venture with Greece’s Archirodon and South Korean counterpart Samsung C&T.
These developments follow a wider strategic review of Neom last year, as Saudi Arabia reassesses priorities under its Vision 2030 programme.
With tighter liquidity at the sovereign wealth fund level, resources are being redirected towards projects linked to the Fifa World Cup 2034, Expo 2030, and essential housing, healthcare and education initiatives.
https://image.digitalinsightresearch.in/uploads/NewsArticle/16140200/main.jpg -
Iraq gas field project disrupted by regional conflict26 March 2026

Register for MEED’s 14-day trial access
Progress on Iraq’s project to develop the strategically important Akkas gas field has been disrupted by security issues related to the US and Israel’s ongoing war with Iran, according to industry sources.
Work activity at the project site has been significantly reduced due to security concerns, and the project is now expected to take longer to complete.
Iraq held a ceremony in January this year to mark the restart of drilling operations at the site as part of the field development project.
In July last year, Iraq’s Oil Ministry announced signing a contract with the US-based oil field services provider SLB to develop production at Iraq’s Akkas gas field.
Under the terms of the deal, SLB will drill wells at the Akkas field, aiming to initially raise production to 100 million cubic feet a day (cf/d).
Many of SLB’s non-Iraqi employees have now been evacuated from the country.
Over the long term, Iraq is targeting gas production of 400 million cf/d from the field.
The contract with SLB replaces a previous deal with Ukraine-based Ukrzemresurs, which has been terminated.
It also covers the construction of surface infrastructure and pipelines to connect Akkas to central processing units.
The gas produced at Akkas will be used to fuel the Anbar combined-cycle power plant, which is under construction by the Electricity Ministry.
Akkas gas field development
The Akkas gas field, located in Anbar province in western Iraq, has 5.6 trillion cubic feet of proven reserves. The field was discovered in 1992 and began production in 1993.
Since then, Iraq’s plans to develop the Akkas gas field to its full potential have experienced several setbacks.
In April last year, the Iraqi Oil Ministry signed an agreement with Ukrzemresurs to develop the field.
At the time, the Oil Ministry said that the partners were aiming to produce 100 million cf/d in the first two years, as per the agreement, with output targeted to increase to 400 million cf/d within four years.
Prior to Ukrzemresurs, South Korean company Kogas was responsible for developing the field.
Rights to the field were originally awarded to a consortium of Kogas and Kazakhstan’s state-owned oil company KazMunaiGas (KMG) in the third licensing round, which was launched in October 2011.
KMG pulled out, leaving Kogas as the sole investor and operator on new contract terms.
When the deal with Ukrzemresurs was originally announced last year, it was negatively received by some Iraqi politicians, with the Oil and Gas Committee in Iraq’s parliament rejecting the contract signing.
At the time, Ali Al-Mashkour, a member of the Oil and Gas Committee, told Iraq’s Shafaq News Agency: “This contract involves a great waste of Iraq’s wealth, and there will be a waste of Iraq’s oil, and this confirms that Iraq is once again failing to choose reputable companies to work with in the most important economic field in the country.”
He added: “We will work to uncover and expose the suspicions in this contract during the next stage, especially since this contract was made by some representatives for specific interests, which we will reveal soon with evidence.”
Plans to sign the contract to develop the Akkas gas field with a Ukrainian company were first announced by the Oil Ministry in September 2023, but Ukrzemresurs was not named at the time.
Iraq’s government is trying to transform the country into a gas-exporting nation. Currently, Iraq is reliant on Iran for gas imports.
Both Saudi Arabia and the US, which are looking to contain Iranian influence in the region, have been supporting Iraq in developing its non-associated gas fields as this will reduce Iraq’s economic reliance on Iran.
https://image.digitalinsightresearch.in/uploads/NewsArticle/16138892/main.png -
Dubai seeks contractors for Nadd Hessa stormwater project26 March 2026
Dubai Municipality has invited contractors to prequalify for a contract to build a sewerage and stormwater system in the Nadd Hessa area.
The project is being procured through the Sewerage and Recycled Water Projects Department.
The submission deadline is 2 April.
Nadd Hessa is an emerging development area, located between Dubai Silicon Oasis and Academic City along the E311 corridor.
It has been earmarked for future residential expansion, with enabling infrastructure now being tendered to support planned housing and community developments in the area.
The scheme, known as DS 328/1–C1, covers the construction of sewerage and stormwater infrastructure, including approximately 12.4 kilometres of sewerage lines with diameters of up to 400 millimetres.
The scope also includes about 14km of stormwater lines with diameters of up to 1,000 millimetres.
In addition, the project involves around 500 metres of microtunnelling works for both sewerage and stormwater networks.
The municipality is currently prequalifying contractors for several upcoming water projects, including the expansion of the Jebel Ali sewage treatment plant (STP) phases one and two.
The upgraded facility will be capable of treating an additional sewage flow of 100,000 cubic metres a day (cm/d).
Bid submissions for this project are also due by 2 April.
In addition, the authority is planning a broader review of Dubai’s water and wastewater infrastructure to support future population growth, including identifying locations for future infrastructure.
Two separate consultancy tenders were issued in March.
One involves a study to develop a sustainable urban drainage systems strategy across the emirate. The other covers a review of the emirate’s sewage treatment and recycled water distribution strategy.
https://image.digitalinsightresearch.in/uploads/NewsArticle/16138660/main.jpg
