Abu Dhabi and Riyadh compete for capacity
24 March 2025
Electricity generation installed capacity from renewable and nuclear energy sources is expected to overtake conventional installed capacity in Abu Dhabi by 2029.
Based on known projects that are under various stages of procurement and in line with a plan to procure 1.5GW of renewable capacity annually until the mid-2030s, as well as an assumption that the contracts for thermal capacities expiring between 2025 and 2029 will not be renewed, the UAE capital could see its total electricity generation installed capacity rise to approximately 38.5GW by 2029, up from around 22GW as of the end of 2024.
This figure includes the 5.2GW capacity from the solar photovoltaic (PV) project being built by Abu Dhabi Future Energy Company (Masdar), which is expected to come on stream in 2027. The project will supply up to 1GW of baseload capacity in tandem with a 19 gigawatt-hour battery energy storage system plant.
By 2029, the share of renewable energy is expected to reach 37% and nuclear energy 14% of total installed capacity. Capacity from gas-fired fleets is forecast to be 49%, down from 69% this year.
This scenario assumes that all projects under procurement and construction achieve commercial operations according to their timeline, that all four gas-fired fleets with a combined expiring capacity of 7.2GW are not extended, and that another 1.5GW solar PV project will be launched next year, following the Al-Zarraf solar IPP.
This further implies that at least 1.5GW of renewable energy capacity will start operating annually from 2026, and planned gas-fired power plants will be completed successively between 2027 and 2029. It precludes the launch of new thermal power projects apart from those already known or announced.
This massive capacity buildout, equivalent to between 16GW or 70% and 21GW or 94%, if the round-the-clock solar capacity is included, of its current installed capacity, requires Abu Dhabi to rapidly upgrade its grid infrastructure and deploy substantial battery energy storage capacity to ensure grid resilience and flexibility.
Competing for capacity
It also tests the capacity of developers and engineering, procurement and construction (EPC) contractors, which are equally beholden to pursue new contracts in Saudi Arabia.
The kingdom faces a pending deadline to decommission ageing liquid fuel-fired plants as part of an overall energy transition plan for its electricity sector. It aspires to procure 20GW of renewable energy capacity annually until 2030 "subject to demand growth", and have renewable sources account for half its electricity generation capacity at the end of the forecast period.
According to MEED Projects and MEED data, Saudi Arabia entered what could be the busiest period for power generation capacity buildout in its history this year, with over 50GW of power generation projects under construction, or about to start construction.
This is equivalent to over a quarter of its current installed capacity, which will also require a 60% expansion of its electricity grid coverage.
Related reads:
The scale and volume of contracts in both jurisdictions are a positive development for many developers and contractors, following a major slowdown in the years before and after the Covid-19 pandemic.
Even those extremely cautious about solar PV projects' ability to deliver desired profits, or those obliged to say no to thermal projects that do not offer a clear carbon capture path, can pivot to the rapidly expanding battery energy storage projects or, indeed, the potential hydropower projects in Neom in Saudi Arabia.
Retreating bidders
It must be noted, however, that several international utility developers are shifting their geographical focus away from the region and have expressed a desire not to compete in the upcoming tenders for power generation projects.
As a result, the latest tenders in Riyadh and Abu Dhabi generally received fewer-than-expected bids. This trend may continue due to distinct factors affecting each fuel type.
“The volume of utility-scale gas projects is outstripping the availability of credible developers,” notes a senior executive with an advisory firm in the UAE. “Either they are already overloaded, withdrawing from the gas market, or uninterested in a particular country.”
Another key issue for developers and EPC contractors, regardless of the location of these projects, is the gas turbine original equipment manufacturer (OEM) gridlock, which affects delivery time and prices.
In general, top OEM manufacturers are caught between two choices: expand their capacity to accommodate rising demand and secure substantial cash flow going forward, or ignore the short to medium-term demand and eliminate the risk of building capacity that may be stranded beyond 2030, when clients may stop procuring new gas utility plants.
On the other hand, interest in renewables may remain intact, subject to improving returns prospects, another expert tells MEED.
Nonetheless, these developments translate to significant opportunities, particularly for local developers, EPC contractors and other OEM manufacturers – such as Italy's Ansaldo Energia – which have remained on the fringes of the region's utility power projects markets for many years.
Chinese firms that previously only focused on EPC, for instance, are gradually stepping up to the role of utility developers, which can help ensure that the region's offtakers continue to secure world-record-low tariffs for future projects.
This, however, may also seal the decisions by more established developers to exit the region for good.
Exclusive from Meed
-
-
Contractor wins Oman housing substation contract7 April 2026
-
UAE reviews $1.63bn fourth federal road project7 April 2026
-
Kingdom Holding Company signs Riyadh project deal7 April 2026
-
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Adnoc builds long-term oil and gas production potential7 April 2026

Between 2023 and 2024, Abu Dhabi National Oil Company (Adnoc Group) spent an estimated $37bn on projects critical to achieving its upstream targets: increasing oil production capacity to 5 million barrels a day (b/d) by 2027 and attaining gas self-sufficiency by the end of the decade.
The state energy company spent more than $22.5bn in 2023 alone, marking the highest annual oil and gas project spending on record in the UAE. The Hail and Ghasha sour gas development – accounting for approximately $17bn – remains the single-largest contract award in the country’s hydrocarbons sector.
A slowdown in capital expenditure (capex) following two years of elevated spending is therefore in line with expectations. While engineering, procurement and construction (EPC) contract awards for upstream projects declined in 2025 and into this year, Adnoc has still committed close to $10bn over the past 15 months.
The largest award during this period came from Adnoc Offshore, which let contracts worth $7.5bn for three EPC packages under the Lower Zakum Long-Term Development Plan (LTDP-1). Spain’s Tecnicas Reunidas and Abu Dhabi-based NMDC Energy and Target Engineering Construction Company were selected last February to execute the works.
The Lower Zakum field, located 65 kilometres northwest of Abu Dhabi, is majority-owned by Adnoc Offshore (60%). Other stakeholders include an Indian consortium led by ONGC Videsh (10%), Japan’s Inpex (10%), China National Petroleum Corporation (10%), Italy’s Eni (5%) and France’s TotalEnergies (5%).
Adnoc Offshore aims to increase production capacity at Lower Zakum to 520,000 b/d by 2027 and sustain that level through 2034.
Offshore contracts in 2026
So far this year, Adnoc Offshore has awarded contracts for two key projects: the Satah Al-Razboot (Sarb) deep gas development and the expansion of the Nasr oil field.
Adnoc achieved final investment decision (FID) on the Sarb project in January and awarded the main EPC contract to US-based McDermott International. The contract is estimated to be worth around $500m, sources told MEED.
The project is expected to deliver 200 million cubic feet a day (cf/d) of gas by the end of the decade – enough to power more than 300,000 homes.
The scope includes the EPC of an offshore wellhead tower with four gas production wells, which will be connected to Das Island for processing through Adnoc Gas facilities. Works also include the installation of pipelines and intra-field connections linking the Sarb field to Das Island.
Also in January, Adnoc Offshore awarded McDermott a $942m contract for the Nasr-115 project, which will increase production capacity at the Nasr offshore field to 115,000 b/d. The field is located about 130km northwest of Abu Dhabi.
McDermott’s scope covers full EPCI services for two topside structures, a new manifold tower, a jacket, a bridge, associated pipelines, subsea cables and brownfield modifications.
Strategic projects in queue
Over the next 12-18 months, Adnoc’s upstream spending is expected to shift from meeting near-term production targets –now largely within reach – to building longer-term capacity beyond 2030.
Following $1.3bn in EPC awards in 2024 for the Upper Zakum expansion to 1.2 million b/d, Adnoc Offshore is advancing the next phase, which will increase capacity to 1.5 million b/d.
Located 84km offshore, Upper Zakum is the world’s second-largest offshore oil field. Adnoc Offshore has divided the EPC scope into three packages, with contractors submitting commercial bids for the UZ1.5MMBD project in February.
Adnoc Offshore is also progressing the Umm Shaif gas cap and surface pressure boosting project, aimed at increasing gas production by 550 million cubic feet a day (cf/d) and condensate output by 50,000 b/d. About 520 million cf/d of additional gas is expected to be fed into Adnoc’s sales gas network.
The first phase of the project has been split into three EPC packages:
- Offshore package 1: fabrication of a 30,000-tonne gas compression system
- Offshore package 2: fabrication of a 30,000-tonne gas compression system
- Onshore package: EPC of gas inlet and processing systems at Das Island
Adnoc Offshore is currently evaluating commercial bids submitted in February for these packages.
https://image.digitalinsightresearch.in/uploads/NewsArticle/16285814/main.gif -
Contractor wins Oman housing substation contract7 April 2026
Oman’s Public Authority for Social Insurance has awarded a contract for the supply, installation, execution and maintenance of a main power substation for its affordable housing project.
The contract was awarded to Kuwait-based Al-Ahleia Switchgear Company.
The project comprises a 400/132/11kV main substation for the Affordable Housing Project, known locally as Al-Masaken Al-Muyassara.
The tender was announced last November, with the bid envelopes opened on 16 December 2025.
Al-Ahleia Switchgear submitted another bid in March for a contract to build three 132/11kV main transformer stations for Kuwait’s Public Authority for Housing Welfare (PAHW).
As reported by MEED, the company’s price of KD10.5m ($34.1m) was the lowest of two offers for the engineering, procurement and construction (EPC) contract.
Separately, in December, Al-Ahleia Switchgear submitted the lowest bid of KD33.9m ($110.3m) for a contract to build a 400/132/11 kV substation at the South Surra township for Kuwait’s PAHW.
The bid was marginally lower than the two other offers submitted by Saudi Arabia’s National Contracting Company (NCC) and India’s Larsen & Toubro.
READ THE APRIL 2026 MEED BUSINESS REVIEW – click here to view PDFEconomic shock threatens long-term outlook; Riyadh adjusts to fiscal and geopolitical risk; GCC contractor ranking reflects gigaprojects slowdown.
Distributed to senior decision-makers in the region and around the world, the April 2026 edition of MEED Business Review includes:
> AGENDA: Gulf economies under fire> GCC CONTRACTOR RANKING: Construction guard undergoes a shift> MARKET FOCUS: Risk accelerates Saudi spending shift> QATAR LNG: Qatar’s new $8bn investment heats up global LNG race> LEADERSHIP: Shaping the future of passenger rail in the Middle EastTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/16285335/main5555.jpg -
UAE reviews $1.63bn fourth federal road project7 April 2026
UAE authorities on 6 April unveiled details of the AED6bn ($1.63bn) fourth federal corridor scheme, a major highway programme aimed at boosting inter-emirate connectivity, increasing road capacity and easing congestion.
The project comprises a 68-kilometre corridor with 10 major interchanges, four flyovers and six to eight lanes in each direction.
Officials provided technical updates on the corridor, including revised connection points and coordination with local authorities to finalise route alignments in line with broader development plans.
Suhail Mohamed Al-Mazrouei, minister of energy and infrastructure, said the programme underscores the central role of infrastructure in the UAE’s development agenda and competitiveness. He was speaking while chairing the first meeting of the UAE Infrastructure and Housing Council this year.
The council also reviewed progress on federal infrastructure initiatives aimed at improving transport efficiency and strengthening coordination between federal and local authorities.
Al-Mazrouei said the next phase will focus on accelerating the delivery of high-impact projects to enhance transport system performance and support the shift towards smart and sustainable mobility in line with population growth and urban expansion.
The council also assessed progress on linking Ajman to the third and fourth federal corridors, which is expected to provide alternative routes, improve traffic flow and further enhance mobility between the emirates.
On public transport, the council reviewed a study on transport links between Dubai, Sharjah and Ajman to address rising commuting demand.
The proposed plan includes 10 priority routes incorporating bus rapid transit and dedicated lanes, with connections to key hubs such as the Dubai Metro and city centres.
READ THE APRIL 2026 MEED BUSINESS REVIEW – click here to view PDFEconomic shock threatens long-term outlook; Riyadh adjusts to fiscal and geopolitical risk; GCC contractor ranking reflects gigaprojects slowdown.
Distributed to senior decision-makers in the region and around the world, the April 2026 edition of MEED Business Review includes:
> AGENDA: Gulf economies under fire> GCC CONTRACTOR RANKING: Construction guard undergoes a shift> MARKET FOCUS: Risk accelerates Saudi spending shift> QATAR LNG: Qatar’s new $8bn investment heats up global LNG race> LEADERSHIP: Shaping the future of passenger rail in the Middle EastTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/16285296/main.jpg -
Kingdom Holding Company signs Riyadh project deal7 April 2026
Saudi Arabia’s Kingdom Holding Company has signed an agreement with Sumou Real Estate Company under which Sumou will manage the development, marketing and sale of a 3-million-square-metre land plot in Riyadh.
The scheme is expected to generate about SR4bn ($1bn) in total sales.
In a Tadawul disclosure, Kingdom Holding Company said its subsidiaries, Kingdom Real Estate Development Company and Trade Centre Company, have appointed Sumou as the exclusive development manager for the site.
The project is scheduled to be implemented over 36 months, starting once the masterplans are approved by the relevant authorities.
In a separate stock exchange statement, Sumou said it will be paid 6.5% of total infrastructure development costs and 2.5% of project sales, in addition to the brokerage commission paid by buyers.
Kingdom Holding Company said the agreement aligns with its long-term strategy for its Riyadh landbank, which originally totalled around 20 million sq m and is being developed in phases.
READ THE APRIL 2026 MEED BUSINESS REVIEW – click here to view PDFEconomic shock threatens long-term outlook; Riyadh adjusts to fiscal and geopolitical risk; GCC contractor ranking reflects gigaprojects slowdown.
Distributed to senior decision-makers in the region and around the world, the April 2026 edition of MEED Business Review includes:
> AGENDA: Gulf economies under fire> GCC CONTRACTOR RANKING: Construction guard undergoes a shift> MARKET FOCUS: Risk accelerates Saudi spending shift> QATAR LNG: Qatar’s new $8bn investment heats up global LNG race> LEADERSHIP: Shaping the future of passenger rail in the Middle EastTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/16284668/main.jpg -
Saudi Arabia’s Jubail industrial city hit by missile debris7 April 2026
Explosions were reported in Saudi Arabia’s Jubail industrial city on 7 April. Saudi authorities said the country’s air defence systems intercepted seven ballistic missiles targeting the Eastern Province, with debris landing near energy facilities, primarily in Jubail.
Jubail is one of the world’s largest petrochemical production hubs, with an annual output of about 60 million tonnes, accounting for an estimated 6% to 8% of global supply.
The incident places renewed focus on the kingdom’s flagship petrochemical cluster, where majority state-owned Saudi Basic Industries Corporation (Sabic) is a key investor.
Jubail also hosts major downstream oil, gas and petrochemical assets operated by Saudi Aramco, US-based Dow and France’s TotalEnergies, underscoring the industrial zone’s international significance.
Saudi officials said damage assessments are ongoing.
The developments follow an Israeli strike on 6 April targeting a major petrochemical complex in Iran’s southern Asaluyeh region, described as the country’s largest industrial hub.
Separately, authorities closed the King Fahd Causeway – the main bridge linking Saudi Arabia and Bahrain – early on 7 April as a precaution amid heightened security concerns.
The King Fahd Causeway Authority said in a post on X that vehicle movement had been “suspended as a precautionary measure” due to Iranian attacks targeting Saudi Arabia’s Eastern Province.
The 25-kilometre bridge is Bahrain’s only road link to the Arabian Peninsula.
US President Donald Trump has issued an ultimatum for Iran to reopen the Strait of Hormuz and threatened to bomb Iranian power plants and bridges if Tehran does not comply by 8pm EDT on 7 April.
READ THE APRIL 2026 MEED BUSINESS REVIEW – click here to view PDFEconomic shock threatens long-term outlook; Riyadh adjusts to fiscal and geopolitical risk; GCC contractor ranking reflects gigaprojects slowdown.
Distributed to senior decision-makers in the region and around the world, the April 2026 edition of MEED Business Review includes:
> AGENDA: Gulf economies under fire> GCC CONTRACTOR RANKING: Construction guard undergoes a shift> MARKET FOCUS: Risk accelerates Saudi spending shift> QATAR LNG: Qatar’s new $8bn investment heats up global LNG race> LEADERSHIP: Shaping the future of passenger rail in the Middle EastTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/16283711/main2424.jpg
