Abu Dhabi and Riyadh compete for capacity
24 March 2025
Electricity generation installed capacity from renewable and nuclear energy sources is expected to overtake conventional installed capacity in Abu Dhabi by 2029.
Based on known projects that are under various stages of procurement and in line with a plan to procure 1.5GW of renewable capacity annually until the mid-2030s, as well as an assumption that the contracts for thermal capacities expiring between 2025 and 2029 will not be renewed, the UAE capital could see its total electricity generation installed capacity rise to approximately 38.5GW by 2029, up from around 22GW as of the end of 2024.
This figure includes the 5.2GW capacity from the solar photovoltaic (PV) project being built by Abu Dhabi Future Energy Company (Masdar), which is expected to come on stream in 2027. The project will supply up to 1GW of baseload capacity in tandem with a 19 gigawatt-hour battery energy storage system plant.
By 2029, the share of renewable energy is expected to reach 37% and nuclear energy 14% of total installed capacity. Capacity from gas-fired fleets is forecast to be 49%, down from 69% this year.
This scenario assumes that all projects under procurement and construction achieve commercial operations according to their timeline, that all four gas-fired fleets with a combined expiring capacity of 7.2GW are not extended, and that another 1.5GW solar PV project will be launched next year, following the Al-Zarraf solar IPP.
This further implies that at least 1.5GW of renewable energy capacity will start operating annually from 2026, and planned gas-fired power plants will be completed successively between 2027 and 2029. It precludes the launch of new thermal power projects apart from those already known or announced.
This massive capacity buildout, equivalent to between 16GW or 70% and 21GW or 94%, if the round-the-clock solar capacity is included, of its current installed capacity, requires Abu Dhabi to rapidly upgrade its grid infrastructure and deploy substantial battery energy storage capacity to ensure grid resilience and flexibility.
Competing for capacity
It also tests the capacity of developers and engineering, procurement and construction (EPC) contractors, which are equally beholden to pursue new contracts in Saudi Arabia.
The kingdom faces a pending deadline to decommission ageing liquid fuel-fired plants as part of an overall energy transition plan for its electricity sector. It aspires to procure 20GW of renewable energy capacity annually until 2030 "subject to demand growth", and have renewable sources account for half its electricity generation capacity at the end of the forecast period.
According to MEED Projects and MEED data, Saudi Arabia entered what could be the busiest period for power generation capacity buildout in its history this year, with over 50GW of power generation projects under construction, or about to start construction.
This is equivalent to over a quarter of its current installed capacity, which will also require a 60% expansion of its electricity grid coverage.
Related reads:
The scale and volume of contracts in both jurisdictions are a positive development for many developers and contractors, following a major slowdown in the years before and after the Covid-19 pandemic.
Even those extremely cautious about solar PV projects' ability to deliver desired profits, or those obliged to say no to thermal projects that do not offer a clear carbon capture path, can pivot to the rapidly expanding battery energy storage projects or, indeed, the potential hydropower projects in Neom in Saudi Arabia.
Retreating bidders
It must be noted, however, that several international utility developers are shifting their geographical focus away from the region and have expressed a desire not to compete in the upcoming tenders for power generation projects.
As a result, the latest tenders in Riyadh and Abu Dhabi generally received fewer-than-expected bids. This trend may continue due to distinct factors affecting each fuel type.
“The volume of utility-scale gas projects is outstripping the availability of credible developers,” notes a senior executive with an advisory firm in the UAE. “Either they are already overloaded, withdrawing from the gas market, or uninterested in a particular country.”
Another key issue for developers and EPC contractors, regardless of the location of these projects, is the gas turbine original equipment manufacturer (OEM) gridlock, which affects delivery time and prices.
In general, top OEM manufacturers are caught between two choices: expand their capacity to accommodate rising demand and secure substantial cash flow going forward, or ignore the short to medium-term demand and eliminate the risk of building capacity that may be stranded beyond 2030, when clients may stop procuring new gas utility plants.
On the other hand, interest in renewables may remain intact, subject to improving returns prospects, another expert tells MEED.
Nonetheless, these developments translate to significant opportunities, particularly for local developers, EPC contractors and other OEM manufacturers – such as Italy's Ansaldo Energia – which have remained on the fringes of the region's utility power projects markets for many years.
Chinese firms that previously only focused on EPC, for instance, are gradually stepping up to the role of utility developers, which can help ensure that the region's offtakers continue to secure world-record-low tariffs for future projects.
This, however, may also seal the decisions by more established developers to exit the region for good.
Exclusive from Meed
-
Saudi Arabia approves new procurement law17 August 2026
-
GCC reviews first phase of water interconnection study17 August 2026
-
Neom’s next phase is crucial to green hydrogen pipeline17 August 2026
-
Five bid for King Salman Bay construction work17 August 2026
-
PDO allows more time for Al-Ghubar field project prices17 August 2026
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Saudi Arabia approves new procurement law17 August 2026
Saudi Arabia’s Council of Ministers has approved a new Government Tenders and Procurement Law (GTPL), introducing changes to public procurement procedures and government contracting.
The Ministry of Finance announced the approval on 5 August.
The new law aims to strengthen governance and transparency, improve procurement planning and implementation, and promote fairness and equal opportunities in government contracting.
The changes give government entities greater flexibility in procurement while introducing new provisions that could affect contractors and suppliers, including contract variations, outstanding payments and procurement procedures.
Contract flexibility
According to a Ministry of Finance summary of the key amendments, one of the main changes allows government entities to increase existing contract items by up to 20% of the contract value. Contractor approval is required for increases exceeding 10%, while the total increase from adding new items or increasing existing items cannot exceed 20% of the contract value.
The amendments also introduce measures addressing outstanding payments to contractors. A government entity cannot make a new award when it has outstanding amounts owed to contractors for works or procurement and the required procedures have not been taken, after notification from the Ministry of Finance.
Exceptions apply where non-payment relates to ministry procedures or where the government entity has taken the required action on a claim but does not have sufficient budget allocations.
Single committee
Under the new law, the committees responsible for opening and examining bids will be merged into a single committee.
The maximum value for direct procurement will rise from SR100,000 ($26,700) to SR1m ($267,000) while government entities will be required to explain and document their use of direct procurement.
Direct procurement will also be permitted in cases involving research, development and innovation and certain contracts with professional practitioners.
The amendments reduce the minimum standstill period following a procurement award from five working days to three working days. Government entities will also be able to negotiate where the best bid exceeds the estimated cost plus the permitted contingency.
Localisation
The new framework includes provisions covering industrial localisation and knowledge transfer. The Ministry of Finance said it will issue rules for contracting for these purposes in cooperation with the Local Content and Government Procurement Authority.
A new regulation will also cover research, development and innovation, including tendering and contracting provisions for these activities.
Other changes involve contractors’ exposure to penalties. The maximum delay penalty on contracts, excluding supply contracts, will fall from 20% to 15% of contract value. The maximum penalty for non-performance in continuous-performance contracts will also fall from 20% to 15%.
The value of purchases exempt from providing a final guarantee will rise from SR100,000 ($26,700) to SR300,000 ($80,000). Additional exemptions will apply to contracts with professional practitioners and emergency or urgent cases.
https://image.digitalinsightresearch.in/uploads/NewsArticle/18805103/main.jpg -
GCC reviews first phase of water interconnection study17 August 2026
The GCC General Secretariat has completed the first phase of a study examining the feasibility of developing water interconnection projects between GCC member states.
A two-day workshop reviewing the study’s findings concluded on 12 August at the headquarters of the GCC Interconnection Authority (GCCIA) in Dammam, Saudi Arabia.
The GCC General Secretariat organised the workshop in cooperation with GCCIA, with representatives from relevant authorities and experts in water, infrastructure and water security taking part.
Participants reviewed the first phase findings, including an assessment of existing water supply infrastructure and the actual water needs of GCC member states. They also discussed the technical requirements and data needed to complete the study.
The study is intended to identify practical options and feasible solutions for developing a regional water interconnection network. This includes establishing an implementation roadmap.
The initiative aims to improve the GCC states’ ability to respond to emergencies and crises and support continuity of water supplies.
First meeting
The workshop followed a virtual meeting on 22 July between the GCC General Secretariat and Saudi Arabia’s water authorities as part of the study.
That meeting, which also involved consultancy Artelia, reviewed the study’s methodology and implementation stages. These include assessing existing water systems across GCC states, their resilience and emergency readiness, and developing technical options for bilateral water interconnection projects.
In Saudi Arabia, the study is focused primarily on the Eastern Province and Riyadh. It is assessing water production and desalination facilities, transmission pipelines, strategic reservoirs, pumping stations and existing and planned projects.
The study is also examining potential bilateral connections between Saudi Arabia and Bahrain, Kuwait and Qatar, as well as the possibility of a connection with the UAE.
The 22 July meeting also discussed potential connection points and routes, water flow directions and the possibility of designing interconnection pipelines to operate in both directions.
https://image.digitalinsightresearch.in/uploads/NewsArticle/18802726/main.jpg -
Neom’s next phase is crucial to green hydrogen pipeline17 August 2026
Commentary
Mark Dowdall
Power & water editorThe completion of construction at Neom Green Hydrogen comes at an important point for Saudi Arabia’s wider hydrogen ambitions.
The project has already shown that a large green hydrogen scheme can secure financing by reaching financial close in 2023 with long-term offtake from Air Products.
With the facility now moving into commissioning ahead of a targeted commercial operations date next year, Neom could soon give lenders and developers real evidence on the performance, costs and risks of a large-scale green hydrogen project.
That could be important for projects still moving through development. Acwa’s Yanbu Green Hydrogen Hub, for example, is targeting commercial operations in 2030.
The project has brought in Germany’s EnBW as a co-developer and minority investor and Japan’s Itochu as a co-developer, investor and offtaker. Acwa is targeting production of 2.5 million tonnes a year of green ammonia from the hub.
Saudi Arabia is also putting more of the framework around the industry in place. In July, the government granted Acwa exclusive rights to export green hydrogen produced in the kingdom along with its derivatives, including green ammonia, methanol and fuels.
However, partnerships and policy support alone will not remove the commercial questions facing projects. Yanbu still needs to progress through development and secure the financing needed to move into construction.
Neom’s financing structure and 30-year offtake may be specific to the project, but its operating performance should give future developers and lenders a clearer reference point for assessing production, reliability and costs.
While Neom will not make the next projects bankable on its own, if it stays on track and performs as expected, it could give lenders a stronger basis for assessing projects that follow. In the long-run, this could be one of its most important contributions.
https://image.digitalinsightresearch.in/uploads/NewsArticle/18800285/main.jpg -
Five bid for King Salman Bay construction work17 August 2026

Five teams have submitted bids for the contract covering the marine infrastructure works at King Salman Bay on the Red Sea coast, north of Jeddah.
MEED understands that the bids were submitted on 31 July.
The bidders include:
- Deme / Archirodon (Belgium/Netherlands)
- Van Oord (Netherlands)
- Abdulmohsen Altamimi / NMDC Group (local/UAE)
- Urbacon / Negida Contracting (Qatar/Egypt )
- Modern Building Leaders / China Harbour (local/China)
The scope includes dredging and earthworks, as well as quay wall and edge protection works spanning about 11 kilometres.
King Salman Bay is expected to be a waterfront development that aims to reshape the city’s northern Red Sea frontage into a mixed-use destination, anchored by public-realm improvements and leisure-led development.
Saudi gigaproject developer Red Sea Global (RSG) is developing the project.
The latest development follows RSG’s award of an estimated SR100m ($27m) contract to construct a solid waste management centre at its Red Sea Project. The scope includes four buildings: a materials recycling facility, a transfer station, an administration building and a vehicle maintenance building.
In October last year, MEED reported that RSG had secured a SR6.5bn ($1.7bn) credit facility to further develop Amaala, its luxury tourism destination on Saudi Arabia’s northwestern Red Sea coast.
READ THE AUGUST 2026 MEED BUSINESS REVIEW – click here to view PDFSaudi Arabia builds for the global stage; Rising uncertainty creates fresh set of challenges in the Maghreb; Gulf banks remain robust in the face of geopolitical tensions.
Distributed to senior decision-makers in the region and around the world, the August 2026 edition of MEED Business Review includes:
> WORLD CUP: What the 2026 World Cup means for Saudi Arabia 2034> MARKET FOCUS: Maghreb fortunes diverge> INDUSTRY REPORT: GCC banks prove resilient amid turmoil> LEADERSHIP: Private capital and the GCC infrastructure inflection> INTERVIEW: Developers look beyond standalone solarTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/18800910/main.jpg -
PDO allows more time for Al-Ghubar field project prices17 August 2026

Petroleum Development Oman (PDO) has allowed contractors additional time to prepare commercial bids for a project to build a new facility to handle additional oil production from the Al-Ghubar field in the sultanate.
The Al-Ghubar field is located in the Ghaba Salt Basin at Qarn Alam, within majority state-owned PDO’s Block 6 concession area.
The Al-Ghubar gas-oil gravity drainage (GOGD) facility will be designed as a sour (hydrogen sulphide) facility and is expected to handle maximum oil production of 1,800 standard cubic metres a day (cm/d), a maximum total water flow rate of 10,421 standard cm/d, and maximum gas lift of 256,934 standard cm/d. Production from the planned Al-Ghubar GOGD facility will be exported to PDO’s main oil line.
Following receipt of the technical bids for the project in July, PDO granted contractors additional time – until 16 August – to submit commercial bids for the project, MEED recently reported.
The project operator has now extended the deadline for submitting commercial bids to 1 September, sources told MEED.
PDO floated the tender for the Al-Ghubar GOGD facility project in March, setting an initial bid submission deadline of 4 May, MEED previously reported.
PDO later extended the deadlines for submission of technical and commercial bids to 26 July and 7 August, respectively. Contractors submitted technical proposals by the revised deadline, according to sources.
The following contractors, among others, are understood to be bidding for the project:
- Archirodon (Greece)
- Engineering for the Petroleum & Process Industries (Egypt) / Petrojet (Egypt)
- Jereh (China)
- Kent (UAE)
- Larsen & Toubro Energy Hydrocarbon (India)
The scope of work on the Al-Ghubar GOGD facility project covers the engineering, procurement and construction (EPC) of the following:
- On-plot scope consists of:
- Production separator
- Test separator
- Concentric wash tank
- Wet oil pump
- Water bath heater
- Surge tank
- Gas injection/gas lift compressor (centrifugal)
- Utilities (Instrument Air compressors, chemical injection skids, drain system, vent system)
- Suction scrubber
- Air coolers
- Discharge scrubbers
- Condensate flash drum
- Atmospheric pressure knock-out drum
- Flare system
- Gas heater
- Water disposal pump
- Oil shipping pump
- New 132kV substation and plant substation (housing 6.6kV & 415-Volt switchboard)
- New control room
- Off-plot scope consists of:
- Off-plot pipeline network (bulk header, test header, gathering infrastructure/ gathering line header, instrument air header, water disposal header)
- Two remote manifold stations
- Tie-in connection to main oil line
- Tie-in to gas network pipeline
PDO previously intended to tender the Al-Ghubar GOGD project under its framework structure with selected EPC contractors, but eventually tendered it separately.
PDO is the operator of the Block 6 hydrocarbons concession in Oman, which is the sultanate’s largest and most prolific concession. Situated onshore and covering an area of 75,119 square kilometres, Block 6 contains 202 oil fields and 43 gas fields, with PDO producing a total of approximately 680,000 barrels a day (b/d) of oil and condensates from those fields.
The Omani government holds a 60% stake in PDO through Energy Development Oman (EDO). The other shareholders are UK-based Shell (34%), France’s TotalEnergies (4%) and Thailand’s state-owned PTTEP (2%).
ALSO READ: PDO floats tender for major flare gas monetisation scheme
https://image.digitalinsightresearch.in/uploads/NewsArticle/18799485/main.jpg