Abu Dhabi and Riyadh compete for capacity
24 March 2025
Electricity generation installed capacity from renewable and nuclear energy sources is expected to overtake conventional installed capacity in Abu Dhabi by 2029.
Based on known projects that are under various stages of procurement and in line with a plan to procure 1.5GW of renewable capacity annually until the mid-2030s, as well as an assumption that the contracts for thermal capacities expiring between 2025 and 2029 will not be renewed, the UAE capital could see its total electricity generation installed capacity rise to approximately 38.5GW by 2029, up from around 22GW as of the end of 2024.
This figure includes the 5.2GW capacity from the solar photovoltaic (PV) project being built by Abu Dhabi Future Energy Company (Masdar), which is expected to come on stream in 2027. The project will supply up to 1GW of baseload capacity in tandem with a 19 gigawatt-hour battery energy storage system plant.
By 2029, the share of renewable energy is expected to reach 37% and nuclear energy 14% of total installed capacity. Capacity from gas-fired fleets is forecast to be 49%, down from 69% this year.
This scenario assumes that all projects under procurement and construction achieve commercial operations according to their timeline, that all four gas-fired fleets with a combined expiring capacity of 7.2GW are not extended, and that another 1.5GW solar PV project will be launched next year, following the Al-Zarraf solar IPP.
This further implies that at least 1.5GW of renewable energy capacity will start operating annually from 2026, and planned gas-fired power plants will be completed successively between 2027 and 2029. It precludes the launch of new thermal power projects apart from those already known or announced.
This massive capacity buildout, equivalent to between 16GW or 70% and 21GW or 94%, if the round-the-clock solar capacity is included, of its current installed capacity, requires Abu Dhabi to rapidly upgrade its grid infrastructure and deploy substantial battery energy storage capacity to ensure grid resilience and flexibility.
Competing for capacity
It also tests the capacity of developers and engineering, procurement and construction (EPC) contractors, which are equally beholden to pursue new contracts in Saudi Arabia.
The kingdom faces a pending deadline to decommission ageing liquid fuel-fired plants as part of an overall energy transition plan for its electricity sector. It aspires to procure 20GW of renewable energy capacity annually until 2030 "subject to demand growth", and have renewable sources account for half its electricity generation capacity at the end of the forecast period.
According to MEED Projects and MEED data, Saudi Arabia entered what could be the busiest period for power generation capacity buildout in its history this year, with over 50GW of power generation projects under construction, or about to start construction.
This is equivalent to over a quarter of its current installed capacity, which will also require a 60% expansion of its electricity grid coverage.
Related reads:
The scale and volume of contracts in both jurisdictions are a positive development for many developers and contractors, following a major slowdown in the years before and after the Covid-19 pandemic.
Even those extremely cautious about solar PV projects' ability to deliver desired profits, or those obliged to say no to thermal projects that do not offer a clear carbon capture path, can pivot to the rapidly expanding battery energy storage projects or, indeed, the potential hydropower projects in Neom in Saudi Arabia.
Retreating bidders
It must be noted, however, that several international utility developers are shifting their geographical focus away from the region and have expressed a desire not to compete in the upcoming tenders for power generation projects.
As a result, the latest tenders in Riyadh and Abu Dhabi generally received fewer-than-expected bids. This trend may continue due to distinct factors affecting each fuel type.
“The volume of utility-scale gas projects is outstripping the availability of credible developers,” notes a senior executive with an advisory firm in the UAE. “Either they are already overloaded, withdrawing from the gas market, or uninterested in a particular country.”
Another key issue for developers and EPC contractors, regardless of the location of these projects, is the gas turbine original equipment manufacturer (OEM) gridlock, which affects delivery time and prices.
In general, top OEM manufacturers are caught between two choices: expand their capacity to accommodate rising demand and secure substantial cash flow going forward, or ignore the short to medium-term demand and eliminate the risk of building capacity that may be stranded beyond 2030, when clients may stop procuring new gas utility plants.
On the other hand, interest in renewables may remain intact, subject to improving returns prospects, another expert tells MEED.
Nonetheless, these developments translate to significant opportunities, particularly for local developers, EPC contractors and other OEM manufacturers – such as Italy's Ansaldo Energia – which have remained on the fringes of the region's utility power projects markets for many years.
Chinese firms that previously only focused on EPC, for instance, are gradually stepping up to the role of utility developers, which can help ensure that the region's offtakers continue to secure world-record-low tariffs for future projects.
This, however, may also seal the decisions by more established developers to exit the region for good.
Exclusive from Meed
-
Necessity is the mother of invention for Kuwaiti lenders6 August 2026
-
-
-
UAE leads Mena project pipeline recovery6 August 2026
-
Mubadala backs Moove in $250m funding round6 August 2026
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Necessity is the mother of invention for Kuwaiti lenders6 August 2026

If 2025 was marked by the advent of reform in the shape of public debt and mortgage laws, 2026 has been a year of resilience in the face of sharp shifts in the operating environment.
Like their peers across the GCC, Kuwait’s banks have stood out this year for their crisis preparedness. With Kuwait facing sustained attacks from Iran – testing a hydrocarbons-based economy that is uniquely vulnerable to such shocks – banks are focusing on maintaining durability under especially challenging conditions.
The sector entered 2026 in a relatively strong position. As of March 2026 – one month into the US-Israeli campaign against Iran – the non-performing loan (NPL) ratio stood at a creditable 1.7%. A capital adequacy ratio of 17.5% in Q1 is another sign of resilience, underscoring banks’ capacity to absorb unexpected losses.
Kuwaiti banks’ reserve coverage stands at 223% of problem loans, one of the highest levels of loan-loss allowance coverage for Stage 3 exposures in the region. This is in large part due to the Central Bank of Kuwait’s (CBK’s) strict regulatory requirements.
Overall, banks have strong capitalisation, solid liquidity, high loan loss-absorption buffers and sound asset quality. That mix provides confidence that the banking sector can continue to support the economy in difficult circumstances.
Kuwait has retained significant sovereign financial strength. There are large fiscal buffers, there is the existential hydrocarbon wealth, and there is a long track record of supporting the banking sector when required
Abdulla Al-Hammadi, Moody’sBank dominance
Banks also remain central to Kuwait’s economy. As the Washington-based IMF has noted, financial intermediation is overwhelmingly bank-based, with domestic currency bond and equity markets underdeveloped by emerging-market standards.
“Kuwait has retained significant sovereign financial strength. There are large fiscal buffers, there is the existential hydrocarbon wealth, and there is a long track record of supporting the banking sector when required,” says Abdulla Al-Hammadi, an analyst at Moody’s.
Bank assets reached 250% of GDP in 2024 – among the highest in the GCC, according to the IMF. This is supported by strong balance sheets, high liquidity and a large Islamic finance segment. Kuwait Finance House, Boubyan Bank, Kuwait International Bank and Warba Bank – the four main Islamic lenders – together account for KD53bn ($172bn), or 51% of total banking sector assets.
Early 2026 performance metrics show a solid rise in assets at listed Kuwaiti banks, growing by 12.5% year-on-year to KD130.82bn ($366.4bn) in Q1. Net profits increased by a smaller margin, 1.1%, to KD382.96m ($1.07bn) in the same quarter, according to KPMG.
National Bank of Kuwait (NBK), the largest bank by assets, reported net profit of KD324.8m ($1.06bn) for the first half of 2026, a 3% year-on-year increase. Despite the impact of the conflict, the second quarter saw profits rise 4.5% to KD181.2m ($588.4m).
Ratings support
Ratings agencies have retained their confidence in Kuwaiti banks. In a rating action announced on 18 June, Moody’s affirmed the long-term deposit ratings of eight Kuwaiti banks, reflecting their resilient credit profiles supported by strong capital, provisioning reserves and liquidity buffers.
Under Moody’s central scenario – which assumes a prolonged disruption to the Strait of Hormuz through autumn and persistently high and volatile energy prices – the expected deterioration in operating conditions remains within the absorption capacity of these banks’ baseline credit assessments.
Kuwait’s strong sovereign ratings and high level of system support provide additional comfort. Government financial assets are estimated at more than 475% of GDP, while the debt burden was around 19% of GDP as of March 2026 – factors that underpin the government’s capacity to support the banking system in the event of stress.
Nor is Kuwait at particular risk of external funding outflows. According to S&P Global, Kuwait has a comfortable net external asset position that mitigates such risks.
“Depositor confidence has remained stable. The banks continue to access international interbank markets,” says Al-Hammadi. “Their liquidity buffers will support their ability to continue lending and absorb any potential shock.”
Regulatory response
Regulatory supervision is another core strength. The CBK has a reputation for hands-on oversight of the banking sector. In March, it rolled out a stimulus package to encourage banks to lend as the Iran conflict buffeted the region. The measures included a temporary easing of macroprudential requirements, with the minimum liquidity coverage ratio and net stable funding ratio reduced from 100% to 80%. The minimum regulatory ratio was cut from 18% to 15%.
These measures appear to have had the intended effect. According to NBK’s research arm, domestic credit growth picked up in May, rising by half a percentage point over the previous month to 6.7% in year-on-year terms. Signs of stronger business lending, with gains across services, trade and real estate, will have been particularly welcome.
“Many Kuwaiti banks have concentrated their lending activity around the Kuwait economy,” says Al-Hammadi. “Overall GDP is under pressure given recent developments in the hydrocarbon sector. It’s still an oil-driven economy, but if you look at non-oil activity, it has continued to benefit from government investment.”
Credit growth will be supported by improving economic sentiment, so long as deposit growth keeps pace. However, lending is unlikely to match previous years’ levels.
“Our expectation is that lending growth will drop, given what is happening in the macroeconomic environment. Growth could be a bit slower compared to previous years,” says Al-Hammadi.
The CBK has urged local banks to be flexible towards customers, although anecdotal evidence suggests greater caution, including tighter personal loan limits.
Reforms, including the mortgage and housing law, provide an additional opportunity for Kuwaiti banks to support broader growth. The Real Estate Financing Law permits banks to offer supported loans under which the state covers interest payments via the Kuwait Credit Bank, while borrowers repay only the principal.
Although hydrocarbon-sector growth will be negatively impacted by events in the Gulf this year, banks should be able to secure growth by focusing on the non-hydrocarbon economy.
“We see growth driven by the non-oil economy and some of the project finance opportunities, which will benefit from the banking sector’s capital and liquidity position. It places the banks in the right place to grab this opportunity,” says Al-Hammadi.
MEED’s September 2026 report on Kuwait also includes:
> OIL & GAS: Regional war to have lasting impact on Kuwaiti oil sector
> CONSTRUCTION: Kuwait construction holds up despite regional strifehttps://image.digitalinsightresearch.in/uploads/NewsArticle/18160720/main.gif -
PDO floats tender for major flare gas monetisation scheme6 August 2026

Petroleum Development Oman (PDO) has launched a major scheme to monetise gas flared across two of its largest hydrocarbon-producing zones in the sultanate. The initiative aligns with PDO’s commitment to achieve zero routine flaring and net-zero methane emissions by 2030, on the way to attaining full carbon neutrality by 2050.
The scheme involves the monetisation of flare gas and gas associated with oil production in the Qarn Alam cluster and the Fahud field, both of which fall under PDO’s northern portfolio within its main hydrocarbon concession area, Block 6.
The scope of the flare gas and associated gas monetisation scheme has been divided into two parts. Bundle A involves the offtake of associated gas from the Wadi Umayri oil field development, located in the Qarn Alam cluster. Bundle B relates to the monetisation of flare gas and natural gas liquids (NGLs) from the Fahud North Oman Crude Stabilisation (FNOCS) facility, located at the Fahud field.
PDO issued the request for proposal document for the flare gas monetisation scheme on 21 July, inviting local and international developers to submit technical and commercial proposals by 25 August.
Developers have the option of submitting proposals for the complete design, financing, construction, operation and maintenance of offtake or monetisation facilities for one or both bundles. PDO will evaluate proposals for each bundle separately and award contracts independently.
PDO is the operator of Block 6, Oman’s largest and most prolific hydrocarbon concession. Situated onshore and covering an area of 75,119 square kilometres, Block 6 contains 202 oil fields and 43 gas fields, with PDO producing approximately 680,000 barrels a day (b/d) of oil and condensate from those fields.
The Omani government holds a 60% stake in PDO through Energy Development Oman (EDO). The other shareholders are UK-based Shell (34%), France’s TotalEnergies (4%) and Thailand’s state-owned PTTEP (2%).
Scope of Bundle A
The Wadi Umayri field development, located within the Qarn Alam cluster, produces crude oil from the Lekhwair, Shuaiba and Sudair reservoirs. A permanent processing facility is planned to come onstream by the first quarter of 2030.
As a by-product of oil production, the development will generate associated gas at an initial rate of approximately 60,000 to 68,000 standard cubic metres a day (cm/d), declining over field life.
PDO will install a sweetening unit as part of its own scope to meet Oman’s regulatory requirement of all gas with sulphur dioxide (SO₂) concentrations above 0.035 g/m³ to be treated prior to any disposal.
At the delivery point (battery limit flange), the gas made available to the future developer will consist of a blended stream from two sources: approximately 80% sweetened separator gas and 20% flashed gas recovered from atmospheric storage tanks. This blended gas composition forms the basis for downstream utilisation, processing, or disposal considerations under the development concept.
The duration of the contract to be awarded by PDO to the developer is 10 years.
The scope of work on Bundle A is split between PDO and the developer, and covers the following:
PDO tie-in scope:
- Tie-in works from the production separator and oil tank to the defined delivery point (flange at battery limit), including piping, metering and ESD/control valves.
- Sweetening unit upstream of the delivery point to treat the main gas stream and meet regulatory SO₂ limits for any non-routine flaring events.
- Allocate a designated plot plan adjacent to the permanent facility, at no cost to the developer.
- The gas delivery point is defined as the flange at PDO’s battery limit of the Wadi Umayri permanent facility. Gas will be supplied as-is at approximately 1.00 bar, with PDO bearing no obligation to provide gas at higher pressure or low hydrogen sulphide (H₂S) concentration.
Developer scope:
- Design, build, maintain and operate the gas monetisation system outside PDO’s battery limit.
- Provide all equipment, infrastructure, compression, conditioning and downstream handling from the delivery point onward.
- Bear full capital expenditure (capex), operational expenditure (opex), leases, health, safety and environment (HSE), and regulatory responsibilities for all developer scope.
- Self-generation of all required utilities, such as power, water and chemicals.
- Handling, treatment and disposal of all product and by-product streams.
Scope of Bundle B
FNOCS is a centralised processing facility at the Fahud field. The facility processes associated hydrocarbons from producing fields in PDO’s northern portfolio, generating two primary streams: produced NGL stream at FNOCS is blended into the Main Oil Line (MOL), while the produced fuel gas is supplied to the Fahud power plant.
The continued flaring of NGLs at FNOCS is an interim risk-mitigation measure and not a sustainable operating solution. To identify a viable long-term outlet for these volumes, and to meet PDO’s broader strategy to eliminate flaring and comply with its zero routine flaring commitment by 2030, the company is seeking third-party developers to monetise hydrocarbon streams currently being flared at FNOCS.
PDO’s target is to secure an attractive commercial structure to stop flaring by offering two independently proposed operating options:
Option 1 – Monetise the flare gas stream, upstream of main gas compressor: Take the currently flared gas, at an output rate of 90,000 standard cm/d, as-is in the current interim operating mode. Developer to design, build and operate a gas monetisation system outside PDO’s battery limit. This option has the highest zero routine flaring compliance impact and eliminates the need for re-operating the main gas compressor and its associated equipment.
Option 2 – Monetise NGL + fuel gas: Restart the main gas compressor and stabiliser to separate NGL and fuel gas streams for sale. Vendor takes NGL (downstream of stabiliser), at a current rate of 106,000 standard cm/d and fuel gas (upstream of Fahud power plant), at a current rate of 44,000 standard cm/d, through a combined commercial structure.
The duration of the contract to be awarded by PDO to the developer for Bundle B is five years, with the proposed facility to come onstream by the first quarter of 2029.
The scope of work on Bundle B is also split between PDO and the developer, and covers the following:
PDO tie-in scope:
Approximately 200 metres of piping to FNOCS fence, including control/ESD/relief valves and a flowmeter.
Allocate a designated plot plan approximately 4km from the existing FNOCS facility for the developer’s monetisation system.
- The delivery point for option 1 is defined as the flange at FNOCS’s fence, upstream of the main gas compressor. The delivery points for option 2 are: (i) the NGL outlet downstream of the stabiliser, and (ii) the fuel gas outlet upstream of the Fahud power plant. Streams from both options will be supplied as-is at approximately 1.00 bar, with PDO bearing no obligation to provide gas at higher pressure or low H₂S concentration.
Developer scope:
- Design, build, maintain and operate the gas monetisation system outside PDO’s battery limit.
- Provide all equipment, infrastructure, compression, conditioning and downstream handling from the delivery point onward.
- Bear full capital expenditure (capex), operational expenditure (opex), leases, health, safety and environment (HSE), and regulatory responsibilities for all developer scope.
- Self-generation of all required utilities, such as power, water,and chemicals.
- Handling, treatment and disposal of all product and by-product streams.
PDO has been striving to curb, and eventually end, flaring across its operations for several years, as part of its own targets, as well as in alignment with the environmental sustainability framework under Oman Vision 2040.
In May last year, PDO initiated a flare gas recovery project at the Zulaiyah station in Hazar South in partnership with Hungary-based Enerhash, which aims to convert flare gas into a sustainable energy source through modular digital mining infrastructure.
Enerhash’s technology powers containerised data centres directly with flare gas, offering a decentralised solution suitable for remote oil fields.
The project is designed to avoid around 25,000 tonnes a year of carbon-dioxide-equivalent emissions, and builds on PDO’s earlier South AP flare recovery project, which sought vendors to recover gas from atmospheric dehydration tanks across sites such as Bahja, Rima, Amal, Marmul and Nimr.
https://image.digitalinsightresearch.in/uploads/NewsArticle/18157702/main4946.jpg -
Sabic completes $450m divestment of thermoplastics business6 August 2026
Saudi Basic Industries Corporation (Sabic) has completed a transaction to divest its engineering thermoplastics business in the Americas and Europe to German venture capital and private equity firm Mutares, for an enterprise value of $450m.
Sabic’s Americas and Europe engineering thermoplastics business produces polycarbonate, polybutylene terephthalate and acrylonitrile butadiene styrene resins and compounds, and operates manufacturing sites in Mt Vernon, Bay St Louis and Burkville in the US; Ottawa, Canada; Tampico, Mexico; Campinas, Brazil; Cartagena, Spain; and Bergen op Zoom, the Netherlands.
The divestment process was initiated by Sabic in January this year and marks a significant milestone in the company’s broader portfolio optimisation programme.
“The transaction supports Sabic’s continued focus on exiting structurally underperforming assets, reducing cash losses, improving return on capital employed and maximising long-term shareholder value,” the Saudi chemicals giant said.
The divested business reported an operating loss of approximately $498m for full-year 2025, and approximately $173m for the first half of this year.
On a pro forma basis, the carve-out of the engineering thermoplastics business improved Sabic’s earnings before interest, taxes, depreciation and amortisation (Ebitda) margin by approximately 130-140 basis points, “reflecting the positive impact of the transaction on the company’s overall profitability and portfolio quality”.
In addition to agreeing the sale of its engineering thermoplastics business in January, Sabic also began a process to divest its European petrochemicals business to Aequita for an estimated enterprise value of $500m.
Aequita is a Munich-based venture capital and private equity firm.
Sabic’s European petrochemicals business produces and markets ethylene, propylene, low- and high-density polyethylene, polypropylene and value-added polymer compounds, and operates manufacturing sites in Teesside, the UK; Geleen, the Netherlands; Gelsenkirchen, Germany; and Genk, Belgium.
Q2 2026 financial results
Sabic reported a net loss of $100m for the second quarter of 2026, which it attributed to the impact of the Iran-US regional conflict on its business.
The company had only returned to profit in the first quarter, registering a net income of $3.52m, after posting a full-year 2025 loss of $6.87bn.
The Saudi petrochemicals giant also said Q2 2026 revenue fell 5% year-on-year to $6.62bn.
Sabic posted adjusted Ebitda of $900m for the three months to 30 June, a drop of 18% compared to the previous quarter.
Adjusted earnings before interest and taxes in Q2 also fell by 72% quarter-on-quarter to $110m, while adjusted earnings per share stood at $0.03.
Saudi Exchange-listed Sabic said its net debt position remained largely unchanged at $730m at the end of June, compared with $740m at the end of March.
https://image.digitalinsightresearch.in/uploads/NewsArticle/18153251/main4445.jpg -
UAE leads Mena project pipeline recovery6 August 2026
Register for MEED’s 14-day trial access
The Middle East and North Africa’s construction project pipeline strengthened in June 2026, recovering some of the momentum lost earlier in the year as the effects of the Israel-Iran conflict continued to work through regional project markets.
GlobalData’s Construction Projects Momentum Index (CPMI) for the Mena region rose to 0.84 in June, up 5% from 0.80 in May, leaving the region third globally behind South Asia and Sub-Saharan Africa. The three-month moving average held at 0.95, unchanged from May.
The recovery was led by execution-stage activity, where the score rose to 1.18 in June from 1.06 in May. Pre-execution momentum, however, continued to soften, falling to 0.68 from 0.73. The pre-execution stage captures project planning, design development and procurement preparation, and a sustained decline there can point to a thinning of the future pipeline even when near-term execution holds up.
Infrastructure drove the sector-level gains, with momentum rising sharply to 1.03 in June from 0.25 in May, the largest increase among the region’s sectors. Industrial momentum rose to 0.78 from 0.40. Residential activity remained elevated at 1.17, easing only marginally from 1.22.
The gains were partly offset by a steep pullback in institutional activity, where momentum fell to 0.45 in June from 1.72 in May, the largest decline of any sector. Commercial and leisure momentum eased to 0.88 from 1.13, and energy and utilities to 0.59 from 0.82.
The UAE posted the region’s highest score in June at 1.52, up from 1.16 in May. Algeria rose to 1.26 from 0.68, and Kuwait recovered to 0.76 from 0.26. Egypt reached 1.36, Oman held at 0.87, Qatar rose to 0.86 and Iran eased to 0.81.
Saudi Arabia was the main exception among the larger markets, with its score falling to 0.31 in June from 1.16 in May. GlobalData linked the decline to procurement disruption on renewable energy projects under the Public Investment Fund’s giga developments and to the Najran-Asir-Jizan direct road, which faced consecutive bidding delays and consortium withdrawals.
Israel recovered to 0.65 in June from -1.66 in May, having recorded the region’s weakest scores through the earlier phase of the conflict.
Whether the June recovery is sustained will depend on the direction of pre-execution activity, which continued to weaken even as execution-stage momentum firmed.
READ THE AUGUST 2026 MEED BUSINESS REVIEW – click here to view PDFSaudi Arabia builds for the global stage; Rising uncertainty creates fresh set of challenges in the Maghreb; Gulf banks remain robust in the face of geopolitical tensions.
Distributed to senior decision-makers in the region and around the world, the August 2026 edition of MEED Business Review includes:
> WORLD CUP: What the 2026 World Cup means for Saudi Arabia 2034> MARKET FOCUS: Maghreb fortunes diverge> INDUSTRY REPORT: GCC banks prove resilient amid turmoil> LEADERSHIP: Private capital and the GCC infrastructure inflection> INTERVIEW: Developers look beyond standalone solarTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/18153255/main.jpg -
Mubadala backs Moove in $250m funding round6 August 2026
UAE-headquartered mobility company Moove has raised $250m in a Series C funding round led by Abu Dhabi’s Mubadala Investment Company, giving the company a valuation of $2.1bn.
The round was co-led by Woven Capital, the growth fund of Japan’s Toyota, and by Ion Pacific. It also brought in BlueCrest Capital Management and Sona Capital, alongside existing backers including BlackRock, Japan’s MUFG, Franklin Templeton, Uber and the Ontario Power Generation Pension Plan.
Moove said the funding will support the expansion of its autonomous vehicle business, including fleet ownership and what it terms robotics-first depot infrastructure, or “Nests”, where autonomous fleets are charged, serviced, maintained and orchestrated. The company said the funds will also support new market launches.
The company expects to grow its autonomous vehicle workforce by more than 220% by the end of the year, increasing from about 150 employees to about 500.
Founded in 2020 and headquartered in the UAE, Moove finances, owns and operates mobility assets for ride-hailing platforms. It employs 3,300 people and operates about 42,000 vehicles across 29 cities in 13 countries, and has grown to $420m in annual recurring revenue. It has expanded through organic growth and acquisitions, including Kovi in Brazil and Tokyo Taxi in Japan.
Moove is the largest global fleet partner of ride-hailing company Uber. Through a partnership with Waymo, the autonomous driving unit of US technology group Alphabet, it operates autonomous vehicle fleets in Phoenix and Miami in the US, with operations also planned in London.
Mubadala first invested in Moove three years ago. The Series C round marks its continued backing of the company as it moves into autonomous fleet operations.
READ THE AUGUST 2026 MEED BUSINESS REVIEW – click here to view PDFSaudi Arabia builds for the global stage; Rising uncertainty creates fresh set of challenges in the Maghreb; Gulf banks remain robust in the face of geopolitical tensions.
Distributed to senior decision-makers in the region and around the world, the August 2026 edition of MEED Business Review includes:
> WORLD CUP: What the 2026 World Cup means for Saudi Arabia 2034> MARKET FOCUS: Maghreb fortunes diverge> INDUSTRY REPORT: GCC banks prove resilient amid turmoil> LEADERSHIP: Private capital and the GCC infrastructure inflection> INTERVIEW: Developers look beyond standalone solarTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/18151593/main.jpg