Abu Dhabi and Riyadh compete for capacity
24 March 2025
Electricity generation installed capacity from renewable and nuclear energy sources is expected to overtake conventional installed capacity in Abu Dhabi by 2029.
Based on known projects that are under various stages of procurement and in line with a plan to procure 1.5GW of renewable capacity annually until the mid-2030s, as well as an assumption that the contracts for thermal capacities expiring between 2025 and 2029 will not be renewed, the UAE capital could see its total electricity generation installed capacity rise to approximately 38.5GW by 2029, up from around 22GW as of the end of 2024.
This figure includes the 5.2GW capacity from the solar photovoltaic (PV) project being built by Abu Dhabi Future Energy Company (Masdar), which is expected to come on stream in 2027. The project will supply up to 1GW of baseload capacity in tandem with a 19 gigawatt-hour battery energy storage system plant.
By 2029, the share of renewable energy is expected to reach 37% and nuclear energy 14% of total installed capacity. Capacity from gas-fired fleets is forecast to be 49%, down from 69% this year.
This scenario assumes that all projects under procurement and construction achieve commercial operations according to their timeline, that all four gas-fired fleets with a combined expiring capacity of 7.2GW are not extended, and that another 1.5GW solar PV project will be launched next year, following the Al-Zarraf solar IPP.
This further implies that at least 1.5GW of renewable energy capacity will start operating annually from 2026, and planned gas-fired power plants will be completed successively between 2027 and 2029. It precludes the launch of new thermal power projects apart from those already known or announced.
This massive capacity buildout, equivalent to between 16GW or 70% and 21GW or 94%, if the round-the-clock solar capacity is included, of its current installed capacity, requires Abu Dhabi to rapidly upgrade its grid infrastructure and deploy substantial battery energy storage capacity to ensure grid resilience and flexibility.
Competing for capacity
It also tests the capacity of developers and engineering, procurement and construction (EPC) contractors, which are equally beholden to pursue new contracts in Saudi Arabia.
The kingdom faces a pending deadline to decommission ageing liquid fuel-fired plants as part of an overall energy transition plan for its electricity sector. It aspires to procure 20GW of renewable energy capacity annually until 2030 "subject to demand growth", and have renewable sources account for half its electricity generation capacity at the end of the forecast period.
According to MEED Projects and MEED data, Saudi Arabia entered what could be the busiest period for power generation capacity buildout in its history this year, with over 50GW of power generation projects under construction, or about to start construction.
This is equivalent to over a quarter of its current installed capacity, which will also require a 60% expansion of its electricity grid coverage.
Related reads:
The scale and volume of contracts in both jurisdictions are a positive development for many developers and contractors, following a major slowdown in the years before and after the Covid-19 pandemic.
Even those extremely cautious about solar PV projects' ability to deliver desired profits, or those obliged to say no to thermal projects that do not offer a clear carbon capture path, can pivot to the rapidly expanding battery energy storage projects or, indeed, the potential hydropower projects in Neom in Saudi Arabia.
Retreating bidders
It must be noted, however, that several international utility developers are shifting their geographical focus away from the region and have expressed a desire not to compete in the upcoming tenders for power generation projects.
As a result, the latest tenders in Riyadh and Abu Dhabi generally received fewer-than-expected bids. This trend may continue due to distinct factors affecting each fuel type.
“The volume of utility-scale gas projects is outstripping the availability of credible developers,” notes a senior executive with an advisory firm in the UAE. “Either they are already overloaded, withdrawing from the gas market, or uninterested in a particular country.”
Another key issue for developers and EPC contractors, regardless of the location of these projects, is the gas turbine original equipment manufacturer (OEM) gridlock, which affects delivery time and prices.
In general, top OEM manufacturers are caught between two choices: expand their capacity to accommodate rising demand and secure substantial cash flow going forward, or ignore the short to medium-term demand and eliminate the risk of building capacity that may be stranded beyond 2030, when clients may stop procuring new gas utility plants.
On the other hand, interest in renewables may remain intact, subject to improving returns prospects, another expert tells MEED.
Nonetheless, these developments translate to significant opportunities, particularly for local developers, EPC contractors and other OEM manufacturers – such as Italy's Ansaldo Energia – which have remained on the fringes of the region's utility power projects markets for many years.
Chinese firms that previously only focused on EPC, for instance, are gradually stepping up to the role of utility developers, which can help ensure that the region's offtakers continue to secure world-record-low tariffs for future projects.
This, however, may also seal the decisions by more established developers to exit the region for good.
Exclusive from Meed
-
Contractor wins $197m Doha infrastructure works6 November 2026
-
Stakeholders aim to sign Iraq pipeline deal by year end6 November 2026
-
Taqa shortlists 17 contractors for Mirfa-Liwa scheme6 November 2026
-
Gulf conflict cuts Emirates Group profit by 66%6 November 2026
-
King Salman airport tenders roads and utilities package6 November 2026
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Contractor wins $197m Doha infrastructure works6 November 2026

Register for MEED’s 14-day trial access
Qatar’s Public Works Authority (Ashghal) has awarded an estimated QR722m ($197m) contract to develop roads and infrastructure north of Al-Rifaa Street in Doha.
The contract was awarded to local firm Tadmur Contracting Company.
Six other contractors submitted bids:
- Qatar Trading & Contracting Group ($244m)
- Iris Construction Tourism Industry & Trade ($259m)
- Lotus Trading & Contracting ($260m)
- Generic Engineering Technologies & Contracting ($261m)
- Alghanim International / National Industrial Contracting ($268m)
- Hamad Bin Khalid Contracting Company ($281m)
The scope of work covers the construction of more than 34 kilometres of roads, dedicated plot developments, site clearance, backfill and earthworks.
The package also requires the installation of surface and groundwater drainage systems, a foul-water drainage network and treated sewage effluent lines.
In addition, the contractor will deliver a dedicated pumping station, an emergency flood area pond, 3,735 car parking spaces, road cross-sectional elements and verge parking bays.
Secondary infrastructure works include electrical distribution, water mains, utility lines, manholes, gully pots and house connections, along with kerbing, road pavement works, landscaping, street lighting, road markings and directional signage.
https://image.digitalinsightresearch.in/uploads/NewsArticle/21204827/main.jpg -
Stakeholders aim to sign Iraq pipeline deal by year end6 November 2026

Stakeholders expect a key contract to be signed before the end of the year for the development of a major oil export pipeline network in Iraq, according to industry sources.
Iraq and Syria’s governments, state-owned oil companies and a consortium led by Qatar’s UCC are currently discussing the terms.
If all parties agree to the proposed deal, the UCC-led coalition will become the selected developer responsible for tendering engineering, procurement and construction (EPC) contracts for the project.
The consortium includes US-based Chevron, the investment company TI Capital and France’s TotalEnergies.
The proposed plan will use a fast-track framework to bring the pipelines online as quickly as possible.
One source said: “The plan that is being discussed is highly unusual, because it is such a large-scale pipeline project and it would be brought online in a relatively short timeframe.”
A team from UCC is currently in Iraq for meetings with government officials to discuss the project, one source said.
The project will be focused on four pipeline packages:
- Basra to Najaf
- Najaf to Haditha
- Haditha to Fish Khapour
- Haditha to Banias Port in Syria
In July, Iraq’s cabinet approved state-owned Basra Oil Company signing a ​heads of agreement and a non-disclosure agreement with the UCC-led consortium to explore possible future oil pipeline projects.
Under the terms of the agreement, the consortium is preparing technical and financial feasibility studies for strategic export pipeline projects.
Also in July, US-based KBR was awarded a consultancy contract for the section of pipeline due to extend from Basra to Haditha.
In April, Iraq announced the allocation of $1.5bn for the Basra-Haditha route, while the larger scheme is estimated at around $5bn.
https://image.digitalinsightresearch.in/uploads/NewsArticle/21181262/main.jpg -
Taqa shortlists 17 contractors for Mirfa-Liwa scheme6 November 2026

Up to 17 contractors have been invited to submit bids for a major water transmission and distribution scheme serving Mirfa, Madinat Zayed and Liwa in Abu Dhabi, a source close to the project has confirmed to MEED.
The project, originally estimated to cost $775m, comprises a water transmission system from Mirfa, alongside distribution networks serving farms and settlements in Abu Dhabi’s western region.
In October, MEED exclusively reported that a request for proposals had been issued, with bids due on 5 January 2027, following an extension from the initial deadline of 11 November 2026.
The Mirfa-Liwa scheme has been in procurement for several years and was previously tendered in December 2024 as an engineering, procurement and construction scheme, divided between transmission and distribution works.
As MEED understands, it was recently re-tendered under a design, build and operate model, extending the contractor’s responsibilities to operating the infrastructure after construction.
According to sources, the full list of contractors invited to bid for the tender includes:
- Afcons Infrastructure (India)
- Alkhorayef Water & Power Technologies (Saudi Arabia)
- China Machinery Engineering Corporation (China)
- China National Chemical Engineering (China)
- China Tiesiju Civil Engineering Group (China)
- Danway Electrical & Mechanical Engineering (UAE)
- Emarat Aloula Contracting (UAE)
- FCC Aqualia (Spain)
- Gulf Contractors Company (UAE)
- Hydropower Energy & General Construction (UAE)
- Jereh Oil & Gas Engineering Corporation (China)
- Mapa (Turkiye)
- Nesma & Partners Contracting Company (Saudi Arabia)
- Orascom Construction (Egypt)
- Power Construction Corporation of China (China)
- Tecton Engineering & Construction (UAE)
- Tristar Engineering & Construction (UAE)
According to details seen by MEED, the scope includes a pumping station at Mirfa with a capacity of 128 million imperial gallons a day, approximately 125 kilometres of transmission pipelines to Muzairah, with branches to Madinat Zayed and Liwa Summit, and storage tanks at the three locations.
The distribution network is divided into four geographic clusters covering Liwa East, Liwa West, Madinat Zayed and Seih Al-Kheir. The works include associated pipelines, pumping stations and storage facilities.
https://image.digitalinsightresearch.in/uploads/NewsArticle/21181223/main.jpg -
Gulf conflict cuts Emirates Group profit by 66%6 November 2026
Register for MEED’s 14-day trial access
Dubai’s Emirates Group made a profit before tax of AED4.1bn ($1.1bn) in the first half of its 2026-27 financial year, 66% less than the AED12.2bn it made in the same period last year.
The six months to 30 September were the group’s first full half-year since military activity disrupted commercial air traffic across the Gulf on 28 February. Group revenue fell 12% to AED66.2bn ($18bn), from AED75.4bn a year earlier. Profit after tax fell 66% to AED3.6bn ($1bn).
Earnings before interest, tax, depreciation and amortisation (Ebitda) fell 41% to AED12.5bn ($3.4bn).
The results follow a record 2025-26 financial year. The group made a profit before tax of AED24.4bn in that year, on revenue of AED150.5bn.
“It has been a demanding six months, and once again our business model and our people stood up to the test,” said Sheikh Ahmed Bin Saeed Al-Maktoum, chairman and chief executive of Emirates Airline and Group. “Customer demand held firm and our cargo operations made a strong contribution, keeping revenue and cash levels healthy even as global jet fuel prices doubled against the same period last year.”
Airline performance
Emirates airline’s profit before tax fell 68% to AED3.7bn ($1bn), compared with AED11.4bn a year earlier. Its revenue fell 13% to AED56.9bn ($15.5bn). The airline carried 21.8 million passengers, 22% fewer than a year earlier. Capacity measured in available seat kilometres fell 17%, and the passenger seat factor dropped to 72% from 79.5%.
Cargo partly offset the drop in passenger numbers. Emirates SkyCargo carried 1.2 million tonnes, 1% less than a year earlier, but its revenue rose 52%. The conflict reduced the airfreight capacity available on the market, and disruption to shipping pushed shippers towards air transport.
Before hedging gains, fuel costs rose 60%, even though the airline uplifted 12% less fuel. Gains of AED7.1bn ($1.9bn) from fuel hedging cut the net increase in fuel costs to 13%. Fuel accounted for 34% of operating costs.
On 30 September, Emirates was operating 91% of its pre-disruption network, serving 150 airports in 78 countries and territories. On 31 March, it had been flying 58% of its passenger capacity to 122 destinations in 65 countries.
Fleet investment
The airline received nine Airbus A350s and five Boeing 777 freighters during the period. Its fleet grew to 289 aircraft, from 277 on 31 March. Emirates is continuing its cabin retrofit programme, a planned investment of more than $7bn. It refurbished 12 aircraft in the first half. In May, it broke ground on a $5.1bn engineering and maintenance, repair and overhaul (MRO) facility at Al-Maktoum International airport, which is expected to be completed in the mid-2030s.
The group’s cash position was AED54.1bn ($14.7bn) on 30 September, down from a record AED59.6bn on 31 March. The group said it had used its reserves to make pre-delivery payments for aircraft and to service existing debt. It also paid the remaining AED2bn of the AED3.5bn dividend declared for 2025-26 to its owner, the Investment Corporation of Dubai.
Ground services and travel company dnata made a profit before tax of AED410m ($112m), down 51%. Its revenue fell 7% to AED11bn ($3bn), and the group said dnata’s international businesses helped offset weaker traffic in the UAE.
The group’s workforce fell 2% to 128,237 people.
“We enter the second half of our 2026-27 financial year with measured optimism,” said Sheikh Ahmed.
https://image.digitalinsightresearch.in/uploads/NewsArticle/21198114/main.jpg -
King Salman airport tenders roads and utilities package6 November 2026

Register for MEED’s 14-day trial access
Saudi Arabia’s King Salman International Airport Development Company (KSIADC) has tendered the Zone C1+C2 roads, bridges and utility networks package for King Salman International airport (KSIA) in Riyadh.
The tender was issued on 26 October, and bids are due by 6 December.
The request for proposals covers the procurement, construction, testing and commissioning of civil infrastructure supporting Terminal 6, alongside the existing Terminals 1-5.
The scope includes upgrades to Airport Road 539, which runs west of Terminals 1-5, and to part of Mohamed Bin Faraj Road 5333, west of Junction 6.
It also includes new roads, ramps, service roads, and signalised at-grade junctions. An additional access road will connect the Terminal 6 site offices to Road 5333.
Structures will include the Junction 6 and Terminal 6 bridges, retaining walls and reinforced-soil structures.
The contractor will also construct the central ground services equipment (GSE) bridge. Before construction begins, the contractor must validate the design, complete any outstanding elements – including mechanically stabilised earth walls, approach slabs, drainage and lighting – and secure the required authority approvals.
Dry utilities will comprise high- and extra-high-voltage containment, a 13.8kV medium-voltage network with package substations, low-voltage distribution and street lighting, and security-surveillance systems.
Wet utilities will include potable water, fire water, irrigation water, treated sewage effluent, district cooling and wastewater networks. Wastewater pipes will range from 200mm u-PVC gravity lines to 1,700mm glass-reinforced plastic mains.
The stormwater network will include channels, culverts, ponds and pipes ranging from 400mm to 1,400mm in diameter. Crossings will be constructed using open-cut excavation, horizontal directional drilling or microtunneling.
Utilities serving the operational terminals will be diverted on a design-and-build basis. Enabling works will include earthworks and the relocation of the security fence and trees. The contractor will also demolish a temporary car park, existing bridges and a sewage pumping station.
Optional works comprise two design-and-build elements that will proceed only at the client’s instruction.
The first is the south GSE bridge. The second is an approximately 1,400-metre, multi-lane access road to the Terminal 6 Transportation Hub, including bridges, underpasses, ramps and tunnels, as well as provisions for future Wadi Loop utilities and structures.
https://image.digitalinsightresearch.in/uploads/NewsArticle/21176175/main.png