Abu Dhabi and Riyadh compete for capacity

24 March 2025

Electricity generation installed capacity from renewable and nuclear energy sources is expected to overtake conventional installed capacity in Abu Dhabi by 2029.

Based on known projects that are under various stages of procurement and in line with a plan to procure 1.5GW of renewable capacity annually until the mid-2030s, as well as an assumption that the contracts for thermal capacities expiring between 2025 and 2029 will not be renewed, the UAE capital could see its total electricity generation installed capacity rise to approximately 38.5GW by 2029, up from around 22GW as of the end of 2024.

This figure includes the 5.2GW capacity from the solar photovoltaic (PV) project being built by Abu Dhabi Future Energy Company (Masdar), which is expected to come on stream in 2027. The project will supply up to 1GW of baseload capacity in tandem with a 19 gigawatt-hour battery energy storage system plant.

By 2029, the share of renewable energy is expected to reach 37% and nuclear energy 14% of total installed capacity. Capacity from gas-fired fleets is forecast to be 49%, down from 69% this year.

This scenario assumes that all projects under procurement and construction achieve commercial operations according to their timeline, that all four gas-fired fleets with a combined expiring capacity of 7.2GW are not extended, and that another 1.5GW solar PV project will be launched next year, following the Al-Zarraf solar IPP.

This further implies that at least 1.5GW of renewable energy capacity will start operating annually from 2026, and planned gas-fired power plants will be completed successively between 2027 and 2029. It precludes the launch of new thermal power projects apart from those already known or announced.

This massive capacity buildout, equivalent to between 16GW or 70% and 21GW or 94%, if the round-the-clock solar capacity is included, of its current installed capacity, requires Abu Dhabi to rapidly upgrade its grid infrastructure and deploy substantial battery energy storage capacity to ensure grid resilience and flexibility.

Competing for capacity

It also tests the capacity of developers and engineering, procurement and construction (EPC) contractors, which are equally beholden to pursue new contracts in Saudi Arabia.

The kingdom faces a pending deadline to decommission ageing liquid fuel-fired plants as part of an overall energy transition plan for its electricity sector. It aspires to procure 20GW of renewable energy capacity annually until 2030 "subject to demand growth", and have renewable sources account for half its electricity generation capacity at the end of the forecast period.

According to MEED Projects and MEED data, Saudi Arabia entered what could be the busiest period for power generation capacity buildout in its history this year, with over 50GW of power generation projects under construction, or about to start construction.

This is equivalent to over a quarter of its current installed capacity, which will also require a 60% expansion of its electricity grid coverage. 

Related reads

The scale and volume of contracts in both jurisdictions are a positive development for many developers and contractors, following a major slowdown in the years before and after the Covid-19 pandemic.

Even those extremely cautious about solar PV projects' ability to deliver desired profits, or those obliged to say no to thermal projects that do not offer a clear carbon capture path, can pivot to the rapidly expanding battery energy storage projects or, indeed, the potential hydropower projects in Neom in Saudi Arabia.

Retreating bidders 

It must be noted, however, that several international utility developers are shifting their geographical focus away from the region and have expressed a desire not to compete in the upcoming tenders for power generation projects.

As a result, the latest tenders in Riyadh and Abu Dhabi generally received fewer-than-expected bids. This trend may continue due to distinct factors affecting each fuel type.

“The volume of utility-scale gas projects is outstripping the availability of credible developers,” notes a senior executive with an advisory firm in the UAE. “Either they are already overloaded, withdrawing from the gas market, or uninterested in a particular country.”

Another key issue for developers and EPC contractors, regardless of the location of these projects, is the gas turbine original equipment manufacturer (OEM) gridlock, which affects delivery time and prices.

In general, top OEM manufacturers are caught between two choices: expand their capacity to accommodate rising demand and secure substantial cash flow going forward, or ignore the short to medium-term demand and eliminate the risk of building capacity that may be stranded beyond 2030, when clients may stop procuring new gas utility plants.

On the other hand, interest in renewables may remain intact, subject to improving returns prospects, another expert tells MEED.

Nonetheless, these developments translate to significant opportunities, particularly for local developers, EPC contractors and other OEM manufacturers – such as Italy's Ansaldo Energia  which have remained on the fringes of the region's utility power projects markets for many years.

Chinese firms that previously only focused on EPC, for instance, are gradually stepping up to the role of utility developers, which can help ensure that the region's offtakers continue to secure world-record-low tariffs for future projects.

This, however, may also seal the decisions by more established developers to exit the region for good.

https://image.digitalinsightresearch.in/uploads/NewsArticle/13526524/main.jpg
Jennifer Aguinaldo
Related Articles
  • Read the May 2026 MEED Business Review

    30 April 2026

    Download / Subscribe / 14-day trial access

    The regional war – and resulting disruption to oil and gas shipping – has triggered a major global energy security shock that is likely to recalibrate long-term decisions on how energy is produced and consumed.

    The effective closure of the Strait of Hormuz is exposing the vulnerability of Middle East supply chains and pushing import-dependent countries to strengthen energy security by expanding domestic fossil fuels, speeding up nuclear projects, and investing in renewables and storage.

    At the same time, higher prices are encouraging producers unencumbered by reliance on the Strait to boost output.

    Like the oil shocks of the 1970s, the conflict is likely to have lasting effects, reshaping energy policies and partnerships and accelerating diversification away from existing arrangements. Read more here

    The conflict is also undermining the business case for Middle East liquefied natural gas (LNG) projects, as prices rise, demand drops and confidence in the reliability of the region’s suppliers is eroded. 

    May’s market focus is on the UAE, where disruption from the Iran war has challenged every assumption behind the country’s non-oil model.

    This edition also includes our industry report on Gulf capital markets, as well as analysis on the region’s initial public offering market.

    In the latest issue, we explore why regional banks are feeling the strain despite strong buffers; consider why force majeure offers no shield against construction breaches; examine the Public Investment Fund’s 2026-30 strategy and talk to Estelle Brachlianoff, CEO of water infrastructure operator Veolia.   

    We hope our valued subscribers enjoy the May 2026 issue of MEED Business Review

     

    Must-read sections in the May 2026 issue of MEED Business Review include:

    AGENDA: War in the Middle East recalibrates global energy markets

    REGIONAL LNG: War undermines business case for Middle East LNG

    INDUSTRY REPORT:
    Gulf capital markets
    Damage avoidance frames debt issuance
    Regional IPO market dries up amid war

    > INTERVIEW: Desalination holds steady amid tensions, says Veolia CEO

    > LEGAL: Force majeure will not cure pre-existing construction industry breaches  

    > BANKS: GCC banks to feel the strain despite strong buffers

    > PIF STRATEGY: Public Investment Fund approves 2026-30 strategy

    > UAE MARKET FOCUS
    > COMMENT: Conflict tests UAE diversification
    > GVT &: ECONOMY: UAE economy absorbs multi-sector shock

    > BANKING: UAE banks ready to weather the storm
    > ATTACKS: UAE counts energy infrastructure costs

    > UPSTREAM: Adnoc builds long-term oil and gas production potential
    > DOWNSTREAM: Adnoc Gas to rally UAE downstream project spending
    > POWER: Large-scale IPPs drive UAE power market
    > WATER: UAE water investment broadens beyond desalination
    > CONSTRUCTION: War casts shadow over UAE construction boom
    > TRANSPORT: UAE rail momentum grows as trade routes face strain
    > DATABANK: UAE GDP projection corrects on conflict

    MEED COMMENTS: 
    War takes a rising toll on Kuwait’s oil sector

    Libya budget approval could lead to surge in oil and gas projects
    Masdar’s move abroad will not be the last
    Saudi Landbridge finds its moment in Gulf turmoil

    > GULF PROJECTS INDEX: Gulf index plateaus despite ceasefire

    > MARCH 2026 CONTRACTS: Middle East contract awards

    > ECONOMIC DATA: Data drives regional projects

    > OPINIONThe road to hell is paved with gold

    BUSINESS OUTLOOK: Finance, oil and gas, construction, power and water contracts

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/16623768/main.gif
    MEED Editorial
  • Algeria extends bid deadline for stalled power plant

    30 April 2026

    Algeria’s state-owned electricity and gas utility Sonelgaz has extended a deadline for contractors to submit expressions of interest for the construction of the 1.2GW Djelfa combined-cycle power plant.

    The project is being procured through Sonelgaz’s power generation subsidiary, Societe Algerienne de l’Electricite et du Gaz – Production de l’Electricite (SPE).

    In March, MEED reported that the utility was seeking contractors to complete works at the existing Djelfa plant, including the remaining construction, the supply of missing equipment and the assessment of installed equipment.

    The original bid submission deadline for prequalification was 7 April. The new deadline is 5 May.

    The tender is open to both local and international companies, and will be conducted in three phases: prequalification, preliminary technical assessment, and final technical and financial submission.

    The retender follows earlier plans to complete the project through a Chinese consortium comprising China Energy Engineering Group Company, Northwest Electric Power Design Institute and Anhui Electric Power Construction Company.

    This proposal was made after Spanish contractor Duro Felguera halted work on the project in June 2024. 

    According to MEED Projects, construction works had progressed to 72% at the time of the suspension.

    It is understood that an agreement in principle was then reached to transfer the remaining works to the Chinese group after the Spanish firm entered a pre-bankruptcy phase in December 2024.

    A company statement at the time said: “The Chinese group is committed to completing the plant construction, with commissioning scheduled to start in the ninth month following the final agreement.”

    However, in October 2025, it was revealed that the attempt to transfer the project to a consortium of Chinese companies had failed, leaving the Spanish firm with an official demand to pay €413m in compensation to Sonelgaz.

    This was revealed via a lengthy report containing a restructuring plan sent by Duro Felguera to creditors in Spain and the Madrid Financial Markets Authority.

    Gas-fired power plants

    Located in Djelfa province, the project remains a key part of Algeria’s power generation expansion plans.

    Sonelgaz has been seeking contractors to build a separate 1.2GW combined-cycle gas-fired power plant in Aldrar since last April.

    The most recent deadline extension was 29 April.

    According to recent reports, Algeria has also begun construction of a power generation plant in El-Aouinet, with a total installed capacity of 1,406MW.

    The combined-cycle gas turbine plant is being developed in partnership with China National Electric Engineering Company.

    Gas-fired combined-cycle plants continue to account for the majority of Algeria’s electricity generation capacity. Data from MEED Projects indicates that more than 5,000MW of oil- and gas-fired power capacity is currently in the execution phase.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16623787/main.jpg
    Mark Dowdall
  • Dewa announces new record for power reliability

    30 April 2026

    Dubai Electricity & Water Authority (Dewa) has announced that it set a new world record for the lowest electricity customer minutes lost (CML), at 0.82 minutes a year in 2025.

    The figure is equivalent to about 49 seconds of annual outage per customer. It improves on the utility’s previous record of 0.94 minutes in 2024, a reduction of around 13%.

    Dewa said it has reduced CML in Dubai from 6.88 minutes a year in 2012 to 0.82 minutes in 2025, significantly lower than the average of about 15 minutes recorded by leading electricity utilities in the European Union.

    The smart grid is a central component of Dewa’s strategy to improve reliability and efficiency. The programme is being implemented with total investments of AED7bn up to 2035.

    One of the key initiatives of the programme is the Automatic Smart Grid Restoration System, which enables remote, round-the-clock control and monitoring.

    Dewa currently has tenders out for several power and water infrastructure projects in the emirate. These include at least four Glass Reinforced Epoxy (GRE) water transmission pipeline projects.

    According to regional projects tracker MEED Projects, Dewa awarded $1.1bn-worth of new power and water contracts in 2025. Contract awards had previously reached $2.6bn in 2024, and $4bn in 2024.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16623721/main.jpg
    Mark Dowdall
  • Riyadh tenders PMC deal for major sports arena

    30 April 2026

     

    Saudi Arabia’s Sports Boulevard Foundation has tendered a contract inviting firms to bid for project management consultancy (PMC) services for the Global Sports Tower in the Athletics District of the Sports Boulevard development in Riyadh.

    The tender was issued on 8 April, with a bid submission deadline of 10 May.

    The 130-metre-tall Global Sports Tower will cover an area of 84,000 square metres and will include more than 30 sports facilities. The tower will feature the world’s tallest indoor climbing wall at 98 metres and a 250-metre running track.

    Earlier this week, MEED reported that the Sports Boulevard Foundation is preparing to award the main construction contract for the Global Sports Tower. MEED understands that bid evaluation has reached an advanced stage and the contract is likely to be awarded by the end of May.

    MEED reported in May last year that design work on the tower had been completed. Saudi Arabia’s Crown Prince Mohammed Bin Salman Bin Abdulaziz Al-Saud approved the designs in 2024.

    The Sports Boulevard development runs across Riyadh from east to west and, once complete, is set to be the world’s longest park spanning more than 135 kilometres.

    The development will be spread across several districts, including Wadi Hanifah, Arts, Urban Wadi, Entertainment, Athletics and Eco, as well as Sands Sports Park.

    The large-scale project aims to transform central Riyadh – currently dominated by major highways – into a recreational corridor.

    Sports Boulevard, which will feature 4.4 million sq m of public realm and landmark buildings, will also be home to the Centre for Cinematic Arts and a 2,000-seat amphitheatre.

    The development will provide more than 2.3 million sq m of mixed-use commercial, residential, and retail assets, along with sports facilities around the park, known as Linear Park.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16622287/main.jpeg
    Yasir Iqbal
  • Contractors submit Saudi Arabia phosphate rail track bids

    30 April 2026

     

    Saudi Arabian Railways (SAR) received bids from contractors on 27 April for a multibillion-riyal tender to double the tracks on the existing phosphate transport railway network connecting the Waad Al-Shamal mines to Ras Al-Khair in the kingdom’s Eastern Province.

    The tender – covering the second section of the track-doubling works and spanning more than 150 kilometres (km) – was issued on 9 February.

    This follows SAR receiving bids on 1 February for the project’s first phase, which spans about 100km from the AZ1/Nariyah Yard to Ras Al-Khair.

    The scope includes track doubling, alignment modifications, new utility bridges, culvert widening and hydrological structures, as well as the conversion of the AZ1 siding into a mainline track. It also includes support for signalling and telecommunications systems.

    The tender notice was issued in late November.

    Switzerland-based engineering firm ARX is the project consultant.

    MEED understands that these two packages are the first of four that SAR is expected to tender for the phosphate railway line. Other packages anticipated to be tendered shortly include the depot and systems packages.

    In 2023, MEED reported that SAR was planning two projects to increase its freight capacity, including an estimated SR4.2bn ($1.1bn) project to install a second track along the North Train Freight Line and construct three new freight yards.

    Formerly known as the North-South Railway, the North Train is a 1,550km-long freight line running from the phosphate and bauxite mines in the far north of the kingdom to the Al-Baithah junction. There, it diverges into a line southward to Riyadh and a second line running east to downstream fertiliser production and alumina refining facilities at Ras Al-Khair on the Gulf coast.

    Adding a second track and the freight yards will significantly increase the network’s cargo-carrying capacity and facilitate increased industrial production. Project implementation is expected to take four years.

    State-owned SAR is also considering increasing the localisation of railway materials and equipment, including the construction of a cement sleeper manufacturing facility.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16622526/main.jpg
    Yasir Iqbal