A case study in procurement
18 March 2025

Register for MEED’s 14-day trial access
While it may not be in the headlines as much as some of its more eye-catching official gigaproject counterparts, Roshn has already delivered thousands of residential units in Saudi Arabia as it seeks to fill the upscale and community living housing map.
Launched in 2020, the Roshn gigaproject is a component of the Vision 2030 plan to achieve 70% home ownership among Saudi nationals by 2030. Alongside the National Housing Company, it is the delivery vehicle for government-backed housing construction as Riyadh seeks to meet the shortfall in available stock.
Its first project was its Sedra community in the north of the capital. Currently on its fourth of eight delivery phases, the multibillion-dollar masterplanned development will comprise 30,000 homes over 20 million square metres (sq m) when completed.
Roshn’s second Riyadh community under construction is Warefa in the northeast of the capital. More compact than Sedra, it will have 2,300 units over an area of 1.4 square kilometres, with 150,000 sq m of green open space.
Three years after the launch of its first projects, Roshn announced Marafy, its first scheme in Jeddah and its largest mixed-use development to date. Designed to accommodate more than 130,000 residents, Marafy will be built around an 11-kilometre, 100-metre-wide canal, linking with Obhur Creek in the northern outskirts of the kingdom’s second city.
Already breaking ground, Marafy’s first core component is the Alarous residential community, which will offer 18,000 units over a 4 million sq m land area.
Elsewhere in the kingdom, Roshn’s other planned community projects include Almanar in Mecca, Alfulwa in Hofuf and Aldanah in Dhahran. Between them, these schemes total more than 50,000 units. It is expected that thousands of additional homes in other parts of the kingdom will be announced by the developer in the next two years.
Delivering such projects at many different locations is a complex exercise, requiring procurement strategies that not only encompass on-time and on-budget completion, but also ensure that local content is maximised while at the same time maintaining stringent quality standards.
Tasked with handling Roshn’s overall procurement strategy is Iain McBride, the gigaproject developer’s head of commercial.
It is expected that thousands of additional homes in other parts of the kingdom will be announced by the developer in the next two years
Like other gigaprojects in the kingdom, McBride and his procurement team have had to deal with the twin challenges of soaring cost inflation and maximising local content in materials and equipment.
The five official gigaprojects – Diriyah, Neom, the Red Sea Project, Qiddiya and Roshn – are free to employ their own procurement rules and processes, and each has taken a different approach to address its specific requirements. For example, Red Sea Global uses a construction management approach wherein it contracts directly with companies and suppliers that would normally work as subcontractors under the main contractors.
Similarly, Diriyah Company employs a strategy of bundling several smaller contract packages into a single large contract, as a means of consolidating work to ensure lower costs and maintain contractor interest.
Hear directly from the gigaproject owners at the biggest construction event – The Saudi Gigaprojects 2025 Summit, happening in Riyadh from 12-14 May 2025. Click here to know more
Demand signalling
The nature of Roshn’s mainly residential projects means that from the outset it knew it would need thousands of items with similar specifications, such as doors; glass panes; sanitaryware; and heating, ventilation and air-conditioning systems.
To secure this supply chain, early on the company identified local manufacturers of these products and reached long-term agreements with them for the delivery of required materials.
“Our first step was signing a lot of long-term partnership agreements through master purchase agreements where we could leverage preferential rates,” says McBride, speaking to MEED in late January.
“Ultimately, it's all about balance and risk – derisking the opportunities for the supply chain by telling them how many doors, for example, we're going to need each quarter for the next five to 10 years. It gives confidence to the manufacturers that they can start committing to.”
Roshn was the first of the gigaprojects to publicly signal its demand requirements. In 2021, it announced that it would require at least 5 million doors, 3.5 million air-conditioning units, 4.3 million windows, 80 million sq m of tiles and 6.5 million pieces of sanitaryware. These numbers have since changed, but they are indicative of the scale of the supply chain challenge.
Armed with the knowledge that Roshn is both supported by its parent, sovereign wealth vehicle the Public Investment Fund (PIF), and that it is a central element of Saudi Vision 2030, local manufacturers had the confidence to commit to investing in production capacity to meet its needs.
Significantly, most of these deals have been with manufacturers within the kingdom, thereby maximising the local content aspects. Just as importantly, Roshn has not had to make any fixed orders – so-called ‘take-or-pay agreements’ – with suppliers, such is the latter’s faith in the developer.
“For the time being, we’ve not had to make any firm commitments,” says McBride. “We did look at it at one point, but our approach has always been to keep it as simple as possible by listening to the supply chain and seeing what they need. When we were speaking to them, it wasn’t their number one driver; they weren’t screaming at us saying, ‘We need you to give us a firm order’.
“Now, many people think a take-or-pay agreement is essential – where you commit to ordering [a certain quantity] of materials over a period of months or years and, if you don’t, you have to pay a penalty, thereby adding risk and complexity for the developer.
“What we were able to agree instead was that we'll be open and transparent with [the suppliers about] what we need. We said to ourselves, ‘Let's get a good price that works, whether we buy directly from the supplier or whether we include that supplier within our tenders with major contractors’. And we’ve seen great success with that approach, with multiple companies.”
The localisation push is supported by the design process. Wherever possible, the designs for Roshn’s projects incorporate and specify equipment and materials that are known to be manufactured locally.
There have been instances where specific, specialised materials and products are not produced in the kingdom, or not in the quantities required, such as marble and certain architectural facades.
Where this is the case, Roshn is keen to explore how it can help to build in-kingdom capacity. The developer has initiatives through which it looks to co-invest in production facilities that come with high capital requirements.
As McBride explains, Roshn is only one part of the huge and rapidly accelerating Saudi projects market ecosystem, and in helping to increase capacity, it is also putting itself in a position to help other developers with their supply chain needs.
A case in point is Roshn’s contract with China Harbour Engineering Company, which was awarded the $2bn deal in 2023 to build villas at Sedra and Warefa.
Part of the contract requires the Chinese contractor to set up a precast manufacturing facility on site at Sedra. In this way, Roshn could not only ringfence the plant for its own needs, but when it no longer requires the output, other projects could benefit from its production capacity.
“The factory has a 15-year lifespan, so any additional capacity will be there for another 10 years after our requirements are met,” says McBride. “In Riyadh, we have Expo 2030, the new airport, the stadiums and many other projects that could draw on its output.”
There are some situations where even this is not enough, particularly when it comes to contracting expertise. One such case is Roshn’s mandate to develop a 45,000-seat stadium in the southwest of Riyadh as part of the kingdom’s Fifa World Cup 2034 plans. On such a complex, highly engineered project, Roshn has insisted that an international contractor teams up with a local company as a condition of tender participation.
This insistence is based on Roshn’s experience overseeing the construction of a football stadium in Dammam alongside co-developer, Saudi Aramco. The project, which is being built by a joint venture of Belgium’s Besix and the local Albawani, is proceeding at a rapid pace and progress has been relatively trouble-free.
McBride says: “If we have to go abroad, let’s go abroad. But make sure it’s done in a smart way and that we’re not just throwing money out of the kingdom.”
Early contractor involvement
On the issue of contracting, it is well known that the massive amount of work in Saudi Arabia is stretching contractors to the limit, pushing up prices and straining labour, engineering and equipment resources.
Roshn’s approach to this challenge has been to engage with contractors at the earliest possible stage of project planning, specifically at the design phase, through an early contractor involvement (ECI) procurement framework. In this way, the company is able to obtain contractor feedback during concept and design and subsequently lower construction risk by improving a project’s constructability.
“It's about signposting the demand by getting the contractor in early, where you can really influence the design, the buildability and the value-engineering opportunities,” says McBride. “Ideally, we bring them in as quickly as possible during the concept stages, when there's very little cost to changing things.
“The worst thing for a contractor is receiving a [request for proposal] cold. They have to … come back in four weeks and then be squeezed for a best price, whereas with ECI they can add value. They really appreciate that.”
When asked to quantify the cost benefits of such an approach, McBride is forthright: “It’s not even a case of doing the maths,” he says. “We have a great example of where it’s worked on our Aldanah project in Dammam. We selected the contract very early on and locked in the floor plans and facades that we wanted. We were then able to deliver a street of 10 show homes [that took] not much more than four months to design and construct.
“The saving, in terms of time, was massive; we probably halved the duration. I probably wouldn’t be exaggerating if I said it saved about a year.
“There are two ways you can follow your engineer,” he continues. “One: you can follow them early and make sure that the way you're looking to save costs is in areas that are not impacting the customer.
“Or two: the worst thing you can do is get to the end and you have a full structural design that could be over-engineered and you’re spending money in the wrong places.
“We don’t want to get to a point where we're trying to value-engineer by cutting things out that are important to customers,” McBride explains. “And that's what you avoid by having this early contractor involvement.”
The company is able to obtain contractor feedback during concept and design and subsequently lower construction risk by improving a project’s constructability
Unlike the other gigaprojects, Roshn has been in the favourable position of being able to raise some revenue by marketing and selling its properties off plan. While this has been beneficial from a development perspective, it has also meant that the developer must get its pricing and housing specifications right if it is to develop homes within an already-defined budget.
Having a contracting partner on board during the design and specification stage facilitates the conversation between the property sales team, which is informing on market requirements, and the builder, who can deliver within the designed cost and quality parameters.
This is in contrast to many real estate developments for which sales are completed before the construction estimates come in, potentially undermining the business case.
The step beyond ECI is for contractors and suppliers to partner with Roshn to inject equity into the projects by acting as co-developers. McBride points to several planned mid-rise towers at Marafy that could be a starting point for this.
Contractors financing projects or bringing in replacement equity has long been an ambition in the region, but builders have been reluctant to adopt this approach. Nonetheless, McBride is confident that it could happen, indicating that there has already been strong interest from the contracting community.
Cost inflation
Another major talking point in Saudi construction is the escalating costs caused by high inflation, logistical challenges and a tightening of contracting and skilled labour capacity.
In many cases, this has required the rescoping of projects, revisions to timelines and even the scrapping of elements. Neom is arguably the best example of this, as it has reprioritised The Line and is facing an estimated cost of $50bn for building each of its first three modules – far in excess of original estimates.
Roshn’s approach to the challenge is to be as open and transparent as possible with the contractor and supplier community. This has involved outlining a long-term pipeline of work that gives the supply chain confidence about its requirements, enabling them to fix in long-term pricing structures. In return, the developer expects prices to come in competitively.
“It’s no secret within the supply chain market that Roshn has quite aggressive price points,” says McBride, a former chartered surveyor who, prior to joining Roshn, worked as a quantity surveyor and cost-management director at consultants Faithful+Gould (now AtkinsRealis) and Rider Levett Bucknall.
“What we're trying to do is engage early, build trust with the contractors, let them see we’re a good client that's going to pay and have honest and fair contracting terms, and work together to try and solve issues post-contract.
“We don't mind if there's inflationary pressures because of commodity prices increasing. But what we're trying to avoid is inflationary prices through just the demand increasing.
“An innovative way that we've implemented this even on our lump-sum contracts – our traditional Redbook or older contracts – is that we have preferred supplier agreement clauses in them,” he adds.
“So, rather than a traditional bill of quantities (BoQ) that has a rate, a quantity, a total, within our rate section we have the material supply rate, the installation rate and then everything else, such as overhead profit. We protect the installation rate, so it's not a percentage of the material; it's a fixed SR100 a square metre to install, for example.
“One of the big frustrations for contractors is [that the supplier has] a material we think they're going to deliver. It's maybe not available, so they submit alternative materials. The client keeps rejecting it – it's not what they want – and it becomes a delay; it's painful.”
McBride gives the example of a pre-approved bathroom sink. Thanks to Roshn’s relationships with key long-term suppliers, the company is able to negotiate better rates for sanitaryware than would be available to a contractor on an ad hoc basis. If the developer’s rates for sinks are better than the BoQ, it splits the savings 50:50 with the contractor.
“The contractors are winning out of that exercise, we're winning out of it and, ultimately, the customers are winning out of it as well, because we’re passing on those savings,” says McBride.
Flexibility
The benefits to contractors and suppliers extend to payment terms. In today’s sellers’ market, vendors are effectively able to pick and choose the clients they want to work for. As a result, clients – including the gigaprojects – have had to introduce more flexible payment terms and develop market reputations for paying on time.
Roshn may lead the pack on this, with an average payment time from invoice to payment of just 13 days in 2024. A decade ago, this would have been unheard of, but it is now increasingly becoming the norm among the gigaprojects.
In addition, like its PIF peers, Roshn has done away with tender fees and tender bonds, viewing them as outdated means of enforcing vendor participation, especially given the tight liquidity and cashflow situation in the projects market in Saudi Arabia.
Will such flexibility ever extend to performance bonds? McBride is sceptical, pointing to the fact that Roshn’s strong relationship with local banks allows to it facilitate credit agreements between contractors and their lenders. Being a gigaproject developer supported by the PIF – and by tacit extension the state – also helps provide the underlining ease of mind for financers.
Nonetheless, Roshn also takes a proactive approach with advanced payments, enabling up to 20% of the total contract value at the initial stage of the project.
“We've been quite clever in how we do this,” says McBride. “We don't go and release 20% straight away. We’ll do 10% and then, when we’ve evidence that you’ve expended that 10% on mobilisation and site establishment, we’ll release the second 10% tranche.”
Subcontractors
One of the chief sticking points in the kingdom’s projects ecosystem in the past decade has been the capacity and capability of its subcontractors.
The payments crisis in 2017-20 forced many main and general contractors to reduce their permanent labour forces, plant and general resources. Wary of a repeat, most have retained their leaner structure and so have turned increasingly to subcontractors for their manpower and delivery requirements.
In theory, this makes sense, but in practice subcontractors in Saudi Arabia are themselves often overstretched in terms of both delivery capacity and labour availability. In turn, they frequently use their own subcontractors, which then also outsource, to the point that specific elements of a project may be completed by companies very far down the supply chain – with the quality issues that this implies.
Roshn’s solution is to ensure any subcontractor on site goes through a vetting process encompassing quality and financial checks, thereby ensuring it has full visibility on every company on site.
Increasingly, Roshn is dealing with suppliers directly, under supply-install contracts. This can create interfacing issues with the main contractors, however, which are ultimately responsible for the project’s delivery.
“We have to be quite careful on that,” McBride says. “We have to go through all the checks and balances during the prequalification process because if we are going to give a subcontractor to a contractor that we're saying is pre-vetted by Roshn, we could be opening the door to lots of claims from the main contractor against us. So, vetting for us is absolutely crucial.”
Roshn is also working with smaller suppliers and subcontractors to help them evolve and grow, so that they can start taking on smaller main contractor roles themselves.
“Not every construction package we award is in the billions of riyals,” says McBride. “Our thinking is to let the big tier-one contractors focus on the multibillion-riyal deals while we encourage the smaller ones to grow as part of our supplier development programme.”
To achieve this, the developer holds events and bootcamps with its vendors to discuss best practices on subjects including health and safety, variation procedures and how to submit good tender returns.
Roshn is also working with smaller suppliers and subcontractors to help them evolve and grow
Building information modelling
Vendor education also extends to the use of building information modelling (BIM) and other construction technologies.
BIM is mandatory on Roshn’s projects, as it is on the other gigaprojects. While use of the technology is standard across almost all main contractors in the region, its take-up among smaller companies in the supply chain has been slower, with firms pointing to the cost of its adoption and integration as a barrier, as well as the fact that some clients, particularly government ones, view it as providing limited benefit.
Roshn’s task in this area is made difficult because its projects are less complex from an engineering and construction perspective.
“We’re building villas; it’s completely different to building stadiums or airports,” McBride says. “Can these contractors build from [two-dimensional] drawings? Yes, of course they can. You're not going to convince a smaller contractor that all of these benefits will make it easier to build because they know how to build. They've been doing it for decades.
“But the savings are in making it easier to procure, savings in the repeatability, and in the change control. If you upskill yourself on a Roshn project, you are building your capability, which you can then [demonstrate] to other clients as proof you can go after bigger and more complex projects. It's something that the whole industry has to get behind.”
Indeed, there is much to learn from Roshn’s approach to delivering its infrastructure and building plans. While the comparatively straightforward nature of its projects means that its procurement strategies may not be suited to those gigaprojects with more iconic designs, for many other developers it is a case study in efficient processes that have proven effective in delivering work on time and to budget.
This is just as well given that Roshn is set to embark on the next stage of its journey, with its focus on the more complex Marafy city development in Jeddah and Roshn Stadium in Riyadh. However, the evidence suggests that from a procurement strategy perspective, it is well-positioned to also make this a success.
Exclusive from Meed
-
SAR tenders design review consultancy for GCC rail link18 September 2026
-
Tender issued for Libyan gas project17 September 2026
-
Nakheel awards $218m Dubai Islands buildings deal17 September 2026
-
Aldar and Mubadala acquire Masdar City Square17 September 2026
-
Neom tenders Oxagon highway contract17 September 2026
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
SAR tenders design review consultancy for GCC rail link18 September 2026

Register for MEED’s 14-day trial access
Saudi Arabia Railways (SAR) has issued a request for proposals (RFP) for a design management and review consultant to oversee engineering works on the GCC railway network, the latest step in advancing the long-delayed regional rail link.
The RFP was issued on 9 September, with a submission deadline of 18 October.
The tender seeks a consultant to manage, audit and verify deliverables produced by SAR's separately appointed design services consultant, rather than carry out the design itself. The tendering for the design services consultancy is currently in progress.
Construction will be tendered separately through competitive bidding once designs are approved.
The GCC railway will run for about 672 kilometres (km) inside Saudi Arabia, linking the kingdom's existing network to Kuwait, Qatar, the UAE and Bahrain, with four sections of about 141km, 200km, 151km and 21km, respectively.
The line is planned as a single-track, non-electrified corridor for mixed freight and passenger traffic, with a maximum axle load of 32.4 tonnes and passing loops for bidirectional working.
The appointed consultant will develop a design management and review plan covering governance, interdisciplinary coordination and stage-gate approvals, and will issue formal review and audit reports against SAR's requirements and international standards.
The scope also covers stakeholder engagement, interface management and oversight of land acquisition activity tied to the design consultant's land acquisition plan.
Key design stages are expected to take about 16 months: four months for concept design, six for preliminary design and six for issued-for-construction design, each with four weeks of contingency.
SAR has asked bidders to mobilise a core team from day one. These must include a project director, engineering and design manager, stakeholder manager and lead document controller, all based at SAR's offices, with minimum experience thresholds ranging from three years for junior operators up to 25 years, including 15 in rail, for the project director role.
GCC railway line
Under the overall plan, the railway will run from Kuwait, pass through Dammam in Saudi Arabia, reach Bahrain via a planned causeway, and continue from Dammam to Qatar, the UAE and, ultimately, Muscat via Sohar in Oman. The railway is reported to cover about 2,186km in total.
The route length within each member state is as follows:
- UAE – 684km
- Saudi Arabia – 672km
- Oman – 306km
- Qatar – 283km
- Kuwait – 145km
- Bahrain – 36km
The railway is designed for passenger trains travelling at 220 kilometres an hour (km/h) and freight trains operating at 80km/h–120km/h.
With high levels of project activity, governments in spending mode and renewed cooperation under the Al-Ula Declaration, the latest efforts to restart the GCC railway project may make more progress than previous attempts. If completed, the railway could prove transformational for a region that is globally connected but still divided by national borders.
READ THE SEPTEMBER 2026 MEED BUSINESS REVIEW – click here to view PDFNuclear power ambitions gather pace; Kuwait keeps dealmaking alive despite war; Region invests in raising gas processing capacity.
Distributed to senior decision-makers in the region and around the world, the September 2026 edition of MEED Business Review includes:
> AGENDA: Gulf nuclear revival takes shape> MARKET FOCUS: Kuwait keeps dealmaking alive under fire> INDUSTRY REPORT: Gas processing takes centre stage in Mena regionTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/19783331/main.gif -
Tender issued for Libyan gas project17 September 2026
An invitation to bid has been issued for a contract to conduct environmental assessments for the project to expand the Mellitah oil and gas complex in Libya.
The bid submission deadline is 2pm today (17 September) Libyan time.
The scope of the project includes provision of:
- An environmental baseline study (EBS)
- An environmental impact assessment (EIA)
- An environmental management plan (EMP)
The client is Mellitah Oil & Gas (MOG), which is a joint venture of Italy’s Eni and Libya’s National Oil Corporation (NOC).
MOG is based in Tripoli and operates both onshore and offshore oil and gas facilities.
The joint venture owns and operates six major oil and gas fields across the North African country.
According to the tender documents, the company that is awarded the contract will need to prepare environmental management measures in compliance with:
- Libyan environmental legislation
- Ministry of Environment requirements
- NOC environmental guidelines
- Applicable international environmental standards and best practices
The expansion of the Mellitah oil and gas complex is part of a project estimated to be worth $8bn.
The wider project is known as the Mellitah Complex Expansion & CO2 Management Integrated Development Project.
It has six main packages:
- Onshore package
- Offshore Structure A
- Offshore Structure E
- Subsea pipeline package
- Site preparation work
- Carbon capture and storage facility
Security issues and political instability have been a major problem for Libya’s oil and gas sector since the country’s civil war started in 2011.
Earlier this month, the Mellitah oil and gas complex was forced to shut down temporarily due to a protest over deteriorating public services.
The existing onshore complex includes housing, processing units, storage facilities and export facilities.
It also serves as the launch point for the Greenstream pipeline, which delivers Libyan gas directly to Italy.
The planned expansion of the complex will involve:
- Construction of a new fourth gas processing train
- Construction of a third condensate train
- Construction of a third natural gas liquids fractionation train
- Construction of a fourth sulphur recovery unit train
- Installation of a hydrogen sulphide enrichment unit
- Installation of a sulphur recovery unit
- Construction of other associated facilities
The Mellitah complex is located about 100 kilometres west of Tripoli and is a key energy facility in the west of the country.
https://image.digitalinsightresearch.in/uploads/NewsArticle/19748920/main.png -
Nakheel awards $218m Dubai Islands buildings deal17 September 2026
Register for MEED’s 14-day trial access
Dubai-based developer Nakheel, now part of Dubai Holding, has awarded a main construction contract worth more than AED800m ($218m) for phases one and three of Bay Grove Residences at Dubai Islands.
The contract was awarded to the local firm Metac General Contracting Company.
It covers the construction of 537 apartments, comprising one- to four-bedroom units, across seven residential buildings.
Phase one includes 296 units in four buildings, while phase three comprises 241 units across three buildings.
The works are scheduled for completion in late 2028.
Bay Grove Residences will ultimately comprise 1,154 homes across 15 buildings. Planning is under way for the remaining 617 homes in phases two and four, with further contract awards expected.
In August last year, Nakheel awarded a AED2.6bn ($708m) contract to Abu Dhabi-based Fibrex Contracting to build the Bay Villas project at Dubai Islands. The contract includes constructing 636 villas.
In April this year, another AED527m ($143m) contract was awarded to local firm Al-Nasr Contracting Company to construct the primary infrastructure and utilities works on Island B at the development.
The Dubai Islands development consists of five islands spanning 18.6 square kilometres. It features more than 59 kilometres (km) of waterfront and 20km of beaches, as well as parks, golf courses, promenades and cycling paths.
The offshore island project gained renewed momentum in 2022, when Nakheel unveiled a new masterplan and rebranded it as Dubai Islands.
The reclaimed islands were originally part of the Palm Deira project, which was partially completed before being put on hold in 2008.
READ THE SEPTEMBER 2026 MEED BUSINESS REVIEW – click here to view PDFNuclear power ambitions gather pace; Kuwait keeps dealmaking alive despite war; Region invests in raising gas processing capacity.
Distributed to senior decision-makers in the region and around the world, the September 2026 edition of MEED Business Review includes:
> AGENDA: Gulf nuclear revival takes shape> MARKET FOCUS: Kuwait keeps dealmaking alive under fire> INDUSTRY REPORT: Gas processing takes centre stage in Mena regionTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/19748850/main.jpg -
Aldar and Mubadala acquire Masdar City Square17 September 2026
Abu Dhabi-based sovereign wealth fund Mubadala Investment Company and local developer Aldar have completed the acquisition of Masdar City Square at Masdar City, in a transaction valued at AED918m ($250m).
The deal was executed through their joint venture established in 2024.
Masdar City Square comprises more than 47,000 square metres (sq m) of net leasable area across seven office buildings.
Completed in Q1 2026, the development is 99% occupied. Tenants include Taqa, the Department of Energy, Emirates College and the Mohamed Bin Zayed University of Artificial Intelligence.
The transaction expands the joint venture’s real estate portfolio in Masdar City, which is now valued at AED4.7bn ($1.3bn).
Masdar City is one of the region’s leading hubs for clean energy, artificial intelligence, advanced research and sustainable urban development.
The joint venture acquired The Link project at Masdar City for AED654m ($178m) in April.
Comprising about 32,000 sq m of net leasable area across five buildings, The Link is fully leased to a portfolio of major tenants, including Abu Dhabi Future Energy Company (Masdar) and the Mohamed Bin Zayed University of Artificial Intelligence.
The asset includes Grade A, Leed Platinum office space, a net-zero-energy headquarters building, a multi-use hall and residential accommodation, supporting its position as a high-performing, integrated component of Masdar City.
https://image.digitalinsightresearch.in/uploads/NewsArticle/19748241/main5814.png -
Neom tenders Oxagon highway contract17 September 2026

Saudi Arabia’s Neom has tendered a design-and-build contract covering permanent upgrade works on Highway 55 in the kingdom’s Oxagon region.
The first phase of the project includes constructing 14 kilometres of road, with two lanes in each direction. It also covers one bridge and three interchanges.
The project duration is 22 months.
Contractors have been given until 21 September to submit their proposals.
Highway 55 connects the Red Sea coast with the mainland in northwestern Saudi Arabia. It is currently the only road providing north-south connectivity between Duba and the Neom region.
MEED exclusively reported in August 2025 that contractors had submitted responses to the expressions of interest notice that Neom had issued earlier that month.
The project is expected to support the movement of cargo vehicles from Duba Port to other parts of the country and the wider region.
Neom tested a pilot initiative last year by handling a shipment that travelled from Cairo via the Port of Safaga, across the Red Sea to the Port of Neom, and then inland to Erbil, Iraq.
In a statement, Neom said: “The shipment travelled through an intermodal corridor spanning over 900 kilometres, marking a significant milestone in the kingdom’s transformation into a regional and global logistics hub.”
The Port of Neom is located on the Red Sea near the Arar border, a key entry point into Iraq.
READ THE SEPTEMBER 2026 MEED BUSINESS REVIEW – click here to view PDFNuclear power ambitions gather pace; Kuwait keeps dealmaking alive despite war; Region invests in raising gas processing capacity.
Distributed to senior decision-makers in the region and around the world, the September 2026 edition of MEED Business Review includes:
> AGENDA: Gulf nuclear revival takes shape> MARKET FOCUS: Kuwait keeps dealmaking alive under fire> INDUSTRY REPORT: Gas processing takes centre stage in Mena regionTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/19746896/main.gif
