A case study in procurement
18 March 2025

Register for MEED’s 14-day trial access
While it may not be in the headlines as much as some of its more eye-catching official gigaproject counterparts, Roshn has already delivered thousands of residential units in Saudi Arabia as it seeks to fill the upscale and community living housing map.
Launched in 2020, the Roshn gigaproject is a component of the Vision 2030 plan to achieve 70% home ownership among Saudi nationals by 2030. Alongside the National Housing Company, it is the delivery vehicle for government-backed housing construction as Riyadh seeks to meet the shortfall in available stock.
Its first project was its Sedra community in the north of the capital. Currently on its fourth of eight delivery phases, the multibillion-dollar masterplanned development will comprise 30,000 homes over 20 million square metres (sq m) when completed.
Roshn’s second Riyadh community under construction is Warefa in the northeast of the capital. More compact than Sedra, it will have 2,300 units over an area of 1.4 square kilometres, with 150,000 sq m of green open space.
Three years after the launch of its first projects, Roshn announced Marafy, its first scheme in Jeddah and its largest mixed-use development to date. Designed to accommodate more than 130,000 residents, Marafy will be built around an 11-kilometre, 100-metre-wide canal, linking with Obhur Creek in the northern outskirts of the kingdom’s second city.
Already breaking ground, Marafy’s first core component is the Alarous residential community, which will offer 18,000 units over a 4 million sq m land area.
Elsewhere in the kingdom, Roshn’s other planned community projects include Almanar in Mecca, Alfulwa in Hofuf and Aldanah in Dhahran. Between them, these schemes total more than 50,000 units. It is expected that thousands of additional homes in other parts of the kingdom will be announced by the developer in the next two years.
Delivering such projects at many different locations is a complex exercise, requiring procurement strategies that not only encompass on-time and on-budget completion, but also ensure that local content is maximised while at the same time maintaining stringent quality standards.
Tasked with handling Roshn’s overall procurement strategy is Iain McBride, the gigaproject developer’s head of commercial.
It is expected that thousands of additional homes in other parts of the kingdom will be announced by the developer in the next two years
Like other gigaprojects in the kingdom, McBride and his procurement team have had to deal with the twin challenges of soaring cost inflation and maximising local content in materials and equipment.
The five official gigaprojects – Diriyah, Neom, the Red Sea Project, Qiddiya and Roshn – are free to employ their own procurement rules and processes, and each has taken a different approach to address its specific requirements. For example, Red Sea Global uses a construction management approach wherein it contracts directly with companies and suppliers that would normally work as subcontractors under the main contractors.
Similarly, Diriyah Company employs a strategy of bundling several smaller contract packages into a single large contract, as a means of consolidating work to ensure lower costs and maintain contractor interest.
Hear directly from the gigaproject owners at the biggest construction event – The Saudi Gigaprojects 2025 Summit, happening in Riyadh from 12-14 May 2025. Click here to know more
Demand signalling
The nature of Roshn’s mainly residential projects means that from the outset it knew it would need thousands of items with similar specifications, such as doors; glass panes; sanitaryware; and heating, ventilation and air-conditioning systems.
To secure this supply chain, early on the company identified local manufacturers of these products and reached long-term agreements with them for the delivery of required materials.
“Our first step was signing a lot of long-term partnership agreements through master purchase agreements where we could leverage preferential rates,” says McBride, speaking to MEED in late January.
“Ultimately, it's all about balance and risk – derisking the opportunities for the supply chain by telling them how many doors, for example, we're going to need each quarter for the next five to 10 years. It gives confidence to the manufacturers that they can start committing to.”
Roshn was the first of the gigaprojects to publicly signal its demand requirements. In 2021, it announced that it would require at least 5 million doors, 3.5 million air-conditioning units, 4.3 million windows, 80 million sq m of tiles and 6.5 million pieces of sanitaryware. These numbers have since changed, but they are indicative of the scale of the supply chain challenge.
Armed with the knowledge that Roshn is both supported by its parent, sovereign wealth vehicle the Public Investment Fund (PIF), and that it is a central element of Saudi Vision 2030, local manufacturers had the confidence to commit to investing in production capacity to meet its needs.
Significantly, most of these deals have been with manufacturers within the kingdom, thereby maximising the local content aspects. Just as importantly, Roshn has not had to make any fixed orders – so-called ‘take-or-pay agreements’ – with suppliers, such is the latter’s faith in the developer.
“For the time being, we’ve not had to make any firm commitments,” says McBride. “We did look at it at one point, but our approach has always been to keep it as simple as possible by listening to the supply chain and seeing what they need. When we were speaking to them, it wasn’t their number one driver; they weren’t screaming at us saying, ‘We need you to give us a firm order’.
“Now, many people think a take-or-pay agreement is essential – where you commit to ordering [a certain quantity] of materials over a period of months or years and, if you don’t, you have to pay a penalty, thereby adding risk and complexity for the developer.
“What we were able to agree instead was that we'll be open and transparent with [the suppliers about] what we need. We said to ourselves, ‘Let's get a good price that works, whether we buy directly from the supplier or whether we include that supplier within our tenders with major contractors’. And we’ve seen great success with that approach, with multiple companies.”
The localisation push is supported by the design process. Wherever possible, the designs for Roshn’s projects incorporate and specify equipment and materials that are known to be manufactured locally.
There have been instances where specific, specialised materials and products are not produced in the kingdom, or not in the quantities required, such as marble and certain architectural facades.
Where this is the case, Roshn is keen to explore how it can help to build in-kingdom capacity. The developer has initiatives through which it looks to co-invest in production facilities that come with high capital requirements.
As McBride explains, Roshn is only one part of the huge and rapidly accelerating Saudi projects market ecosystem, and in helping to increase capacity, it is also putting itself in a position to help other developers with their supply chain needs.
A case in point is Roshn’s contract with China Harbour Engineering Company, which was awarded the $2bn deal in 2023 to build villas at Sedra and Warefa.
Part of the contract requires the Chinese contractor to set up a precast manufacturing facility on site at Sedra. In this way, Roshn could not only ringfence the plant for its own needs, but when it no longer requires the output, other projects could benefit from its production capacity.
“The factory has a 15-year lifespan, so any additional capacity will be there for another 10 years after our requirements are met,” says McBride. “In Riyadh, we have Expo 2030, the new airport, the stadiums and many other projects that could draw on its output.”
There are some situations where even this is not enough, particularly when it comes to contracting expertise. One such case is Roshn’s mandate to develop a 45,000-seat stadium in the southwest of Riyadh as part of the kingdom’s Fifa World Cup 2034 plans. On such a complex, highly engineered project, Roshn has insisted that an international contractor teams up with a local company as a condition of tender participation.
This insistence is based on Roshn’s experience overseeing the construction of a football stadium in Dammam alongside co-developer, Saudi Aramco. The project, which is being built by a joint venture of Belgium’s Besix and the local Albawani, is proceeding at a rapid pace and progress has been relatively trouble-free.
McBride says: “If we have to go abroad, let’s go abroad. But make sure it’s done in a smart way and that we’re not just throwing money out of the kingdom.”
Early contractor involvement
On the issue of contracting, it is well known that the massive amount of work in Saudi Arabia is stretching contractors to the limit, pushing up prices and straining labour, engineering and equipment resources.
Roshn’s approach to this challenge has been to engage with contractors at the earliest possible stage of project planning, specifically at the design phase, through an early contractor involvement (ECI) procurement framework. In this way, the company is able to obtain contractor feedback during concept and design and subsequently lower construction risk by improving a project’s constructability.
“It's about signposting the demand by getting the contractor in early, where you can really influence the design, the buildability and the value-engineering opportunities,” says McBride. “Ideally, we bring them in as quickly as possible during the concept stages, when there's very little cost to changing things.
“The worst thing for a contractor is receiving a [request for proposal] cold. They have to … come back in four weeks and then be squeezed for a best price, whereas with ECI they can add value. They really appreciate that.”
When asked to quantify the cost benefits of such an approach, McBride is forthright: “It’s not even a case of doing the maths,” he says. “We have a great example of where it’s worked on our Aldanah project in Dammam. We selected the contract very early on and locked in the floor plans and facades that we wanted. We were then able to deliver a street of 10 show homes [that took] not much more than four months to design and construct.
“The saving, in terms of time, was massive; we probably halved the duration. I probably wouldn’t be exaggerating if I said it saved about a year.
“There are two ways you can follow your engineer,” he continues. “One: you can follow them early and make sure that the way you're looking to save costs is in areas that are not impacting the customer.
“Or two: the worst thing you can do is get to the end and you have a full structural design that could be over-engineered and you’re spending money in the wrong places.
“We don’t want to get to a point where we're trying to value-engineer by cutting things out that are important to customers,” McBride explains. “And that's what you avoid by having this early contractor involvement.”
The company is able to obtain contractor feedback during concept and design and subsequently lower construction risk by improving a project’s constructability
Unlike the other gigaprojects, Roshn has been in the favourable position of being able to raise some revenue by marketing and selling its properties off plan. While this has been beneficial from a development perspective, it has also meant that the developer must get its pricing and housing specifications right if it is to develop homes within an already-defined budget.
Having a contracting partner on board during the design and specification stage facilitates the conversation between the property sales team, which is informing on market requirements, and the builder, who can deliver within the designed cost and quality parameters.
This is in contrast to many real estate developments for which sales are completed before the construction estimates come in, potentially undermining the business case.
The step beyond ECI is for contractors and suppliers to partner with Roshn to inject equity into the projects by acting as co-developers. McBride points to several planned mid-rise towers at Marafy that could be a starting point for this.
Contractors financing projects or bringing in replacement equity has long been an ambition in the region, but builders have been reluctant to adopt this approach. Nonetheless, McBride is confident that it could happen, indicating that there has already been strong interest from the contracting community.
Cost inflation
Another major talking point in Saudi construction is the escalating costs caused by high inflation, logistical challenges and a tightening of contracting and skilled labour capacity.
In many cases, this has required the rescoping of projects, revisions to timelines and even the scrapping of elements. Neom is arguably the best example of this, as it has reprioritised The Line and is facing an estimated cost of $50bn for building each of its first three modules – far in excess of original estimates.
Roshn’s approach to the challenge is to be as open and transparent as possible with the contractor and supplier community. This has involved outlining a long-term pipeline of work that gives the supply chain confidence about its requirements, enabling them to fix in long-term pricing structures. In return, the developer expects prices to come in competitively.
“It’s no secret within the supply chain market that Roshn has quite aggressive price points,” says McBride, a former chartered surveyor who, prior to joining Roshn, worked as a quantity surveyor and cost-management director at consultants Faithful+Gould (now AtkinsRealis) and Rider Levett Bucknall.
“What we're trying to do is engage early, build trust with the contractors, let them see we’re a good client that's going to pay and have honest and fair contracting terms, and work together to try and solve issues post-contract.
“We don't mind if there's inflationary pressures because of commodity prices increasing. But what we're trying to avoid is inflationary prices through just the demand increasing.
“An innovative way that we've implemented this even on our lump-sum contracts – our traditional Redbook or older contracts – is that we have preferred supplier agreement clauses in them,” he adds.
“So, rather than a traditional bill of quantities (BoQ) that has a rate, a quantity, a total, within our rate section we have the material supply rate, the installation rate and then everything else, such as overhead profit. We protect the installation rate, so it's not a percentage of the material; it's a fixed SR100 a square metre to install, for example.
“One of the big frustrations for contractors is [that the supplier has] a material we think they're going to deliver. It's maybe not available, so they submit alternative materials. The client keeps rejecting it – it's not what they want – and it becomes a delay; it's painful.”
McBride gives the example of a pre-approved bathroom sink. Thanks to Roshn’s relationships with key long-term suppliers, the company is able to negotiate better rates for sanitaryware than would be available to a contractor on an ad hoc basis. If the developer’s rates for sinks are better than the BoQ, it splits the savings 50:50 with the contractor.
“The contractors are winning out of that exercise, we're winning out of it and, ultimately, the customers are winning out of it as well, because we’re passing on those savings,” says McBride.
Flexibility
The benefits to contractors and suppliers extend to payment terms. In today’s sellers’ market, vendors are effectively able to pick and choose the clients they want to work for. As a result, clients – including the gigaprojects – have had to introduce more flexible payment terms and develop market reputations for paying on time.
Roshn may lead the pack on this, with an average payment time from invoice to payment of just 13 days in 2024. A decade ago, this would have been unheard of, but it is now increasingly becoming the norm among the gigaprojects.
In addition, like its PIF peers, Roshn has done away with tender fees and tender bonds, viewing them as outdated means of enforcing vendor participation, especially given the tight liquidity and cashflow situation in the projects market in Saudi Arabia.
Will such flexibility ever extend to performance bonds? McBride is sceptical, pointing to the fact that Roshn’s strong relationship with local banks allows to it facilitate credit agreements between contractors and their lenders. Being a gigaproject developer supported by the PIF – and by tacit extension the state – also helps provide the underlining ease of mind for financers.
Nonetheless, Roshn also takes a proactive approach with advanced payments, enabling up to 20% of the total contract value at the initial stage of the project.
“We've been quite clever in how we do this,” says McBride. “We don't go and release 20% straight away. We’ll do 10% and then, when we’ve evidence that you’ve expended that 10% on mobilisation and site establishment, we’ll release the second 10% tranche.”
Subcontractors
One of the chief sticking points in the kingdom’s projects ecosystem in the past decade has been the capacity and capability of its subcontractors.
The payments crisis in 2017-20 forced many main and general contractors to reduce their permanent labour forces, plant and general resources. Wary of a repeat, most have retained their leaner structure and so have turned increasingly to subcontractors for their manpower and delivery requirements.
In theory, this makes sense, but in practice subcontractors in Saudi Arabia are themselves often overstretched in terms of both delivery capacity and labour availability. In turn, they frequently use their own subcontractors, which then also outsource, to the point that specific elements of a project may be completed by companies very far down the supply chain – with the quality issues that this implies.
Roshn’s solution is to ensure any subcontractor on site goes through a vetting process encompassing quality and financial checks, thereby ensuring it has full visibility on every company on site.
Increasingly, Roshn is dealing with suppliers directly, under supply-install contracts. This can create interfacing issues with the main contractors, however, which are ultimately responsible for the project’s delivery.
“We have to be quite careful on that,” McBride says. “We have to go through all the checks and balances during the prequalification process because if we are going to give a subcontractor to a contractor that we're saying is pre-vetted by Roshn, we could be opening the door to lots of claims from the main contractor against us. So, vetting for us is absolutely crucial.”
Roshn is also working with smaller suppliers and subcontractors to help them evolve and grow, so that they can start taking on smaller main contractor roles themselves.
“Not every construction package we award is in the billions of riyals,” says McBride. “Our thinking is to let the big tier-one contractors focus on the multibillion-riyal deals while we encourage the smaller ones to grow as part of our supplier development programme.”
To achieve this, the developer holds events and bootcamps with its vendors to discuss best practices on subjects including health and safety, variation procedures and how to submit good tender returns.
Roshn is also working with smaller suppliers and subcontractors to help them evolve and grow
Building information modelling
Vendor education also extends to the use of building information modelling (BIM) and other construction technologies.
BIM is mandatory on Roshn’s projects, as it is on the other gigaprojects. While use of the technology is standard across almost all main contractors in the region, its take-up among smaller companies in the supply chain has been slower, with firms pointing to the cost of its adoption and integration as a barrier, as well as the fact that some clients, particularly government ones, view it as providing limited benefit.
Roshn’s task in this area is made difficult because its projects are less complex from an engineering and construction perspective.
“We’re building villas; it’s completely different to building stadiums or airports,” McBride says. “Can these contractors build from [two-dimensional] drawings? Yes, of course they can. You're not going to convince a smaller contractor that all of these benefits will make it easier to build because they know how to build. They've been doing it for decades.
“But the savings are in making it easier to procure, savings in the repeatability, and in the change control. If you upskill yourself on a Roshn project, you are building your capability, which you can then [demonstrate] to other clients as proof you can go after bigger and more complex projects. It's something that the whole industry has to get behind.”
Indeed, there is much to learn from Roshn’s approach to delivering its infrastructure and building plans. While the comparatively straightforward nature of its projects means that its procurement strategies may not be suited to those gigaprojects with more iconic designs, for many other developers it is a case study in efficient processes that have proven effective in delivering work on time and to budget.
This is just as well given that Roshn is set to embark on the next stage of its journey, with its focus on the more complex Marafy city development in Jeddah and Roshn Stadium in Riyadh. However, the evidence suggests that from a procurement strategy perspective, it is well-positioned to also make this a success.
Exclusive from Meed
-
Egypt places fuel order for El-Dabaa nuclear plant21 November 2025
-
Iraq unveils 20-year plan to add 57GW of power capacity21 November 2025
-
Kuwait upstream project to be completed in 202721 November 2025
-
Regional rail construction surges ahead21 November 2025
-
Middle East becomes a hub as rail networks mature21 November 2025
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Egypt places fuel order for El-Dabaa nuclear plant21 November 2025
Egypt’s government has signed a nuclear fuel purchase order for the first unit of the El-Dabaa nuclear power plant, which is expected to be operational in 2026.
The fuel order was signed with Russia’s State Atomic Energy Corporation (Rosatom).
The signing ceremony was attended by Egypt’s Prime Minister Mostafa Madbouli. It included senior officials from Egypt’s Ministry of Electricity & Renewable Energy and the Nuclear Power Plants Authority (NPPA).
The agreement coincided with the installation of the VVER-1200 Generation III+ reactor pressure vessel for the project’s first unit.
The El-Dabaa nuclear power plant will have four units, each capable of generating 1,200MW of electricity. The VVER-1200 Generation III+ reactor model has been selected for all four units.
Egypt and Russia signed the initial inter-governmental agreement for the North African state’s first nuclear facility in November 2015.
Rosatom, the project’s main contractor, announced that it started the production of electrical components in Saint Petersburg for a reactor vessel for the plant in June 2022.
The two countries also agreed on broader cooperation covering nuclear technology, medical radioisotopes, technical applications such as 3D printing, and communications.
El-Dabaa project status
In September 2023, the Egyptian Nuclear & Radiological Regulation Authority (ENRRA) granted a construction permit for the plant’s fourth reactor. ENRRA granted the construction permit for unit three in March that year and units one and two in June 2022 and October 2022, respectively.
In November 2022, South Korea’s Doosan Enerbility signed a contract valued at $1.2bn with state-owned South Korea Hydro & Nuclear Power (KHNP), a subsidiary of Korea Electric Power Corporation (Kepco), for the project.
Rosatom subsidiary ASE earlier appointed KHNP as the single supplier for constructing the turbine islands.
The simultaneous installation of the reactor pressure vessel and fuel order indicates that Unit 1 has transitioned from civil construction into the core mechanical and systems-installation phase.
The latest advancements align with Egypt’s annual Nuclear Energy Day, observed on 19 November to mark the 2015 agreement that initiated the El-Dabaa project.
https://image.digitalinsightresearch.in/uploads/NewsArticle/15132504/main37223922.jpg -
Iraq unveils 20-year plan to add 57GW of power capacity21 November 2025
Register for MEED’s 14-day trial access
Iraq has unveiled a 20-year plan to add 57GW of new power capacity in partnership with Germany’s Siemens Energy and US-based GE Vernova.
The programme aims to expand the electricity sector through new gas-fired plants, renewable energy schemes and long-term maintenance plans for existing plants.
Prime Minister Mohammed Shia Al-Sudani announced the plan on 19 November as he launched a project to build the 1,400MW Al-Youssifiyah thermal power plant under a build-own-operate (BOO) model.
Located about 30 kilometres from Baghdad, there have been previous attempts to restore the Al-Youssifiyah plant, which has been stalled since it was destroyed during the Gulf War.
In 2015, the project was cancelled amid civil unrest in the region.
No official timeline was given for the latest “implementation phase” of the project.
In a statement, however, the prime minister said the country will move towards an alternative financial model for electricity investments.
“We have adopted an investment financial model that addresses the injustices of previous phase contracts to provide an attractive environment for investment,” he said.
“We have worked to reduce the tariff rate and provide up to a 43% [reduction] from previous contracts while preserving public funds,” he added.
MEED understands that these savings refer to reduced generation costs under a model supported by long-term power purchase agreements (PPAs).
Al-Sudani has also directed the ministry to calculate the actual cost of producing electricity and recover it through improved billing and collection.
Iraq’s government has also set a target of adding more than 7GW of solar capacity by 2030 to reduce reliance on oil- and gas-fired generation. The country continues to face chronic electricity shortages, especially during the summer months, as it aims to meet 24-hour demand.
In August, the government approved five major power generation projects, with a combined capacity exceeding 10,000MW.
The projects include three major independent power producer (IPP) combined-cycle plants at Al-Faw, Abu Ghraib and Kirkuk, totalling 7,500MW.
The Iraqi cabinet also approved the development of two thermal power plants, one in Najaf and the other in Youssifiyah, with output capacities of 1,500MW and 1,800MW, respectively.
Furthermore, in September, Iraq started power generation at its first utility-scale solar plant.
The first phase of the 300MW Karbala solar power plant has started generating 22MW, with plans to increase to the full capacity of 300MW by the end of the year.
https://image.digitalinsightresearch.in/uploads/NewsArticle/15131975/main2817.jpg -
Kuwait upstream project to be completed in 202721 November 2025

State-owned upstream operator Kuwait Oil Company (KOC) is expecting its project to install depletion compression systems and sulphur recovery units (SRUs) to be completed in the middle of 2027, according to industry sources.
KOC signed a contract with Kuwait-based engineering contractor Spetco earlier this year, and construction work is currently ongoing.
In November last year, Spetco submitted a bid of KD126.5m ($412m), beating bids from companies based in China, Saudi Arabia and India.
The project involves installing new units at the facilities known as Early Production Facility 50 (EPF-50) and Jurassic Production Facility 3 (JPF-3).
Tender documents were originally made available on 17 September 2023, with a bid deadline of 17 December that year.
Due to scope changes, the deadline was extended several times before bids were ultimately submitted ahead of a 15 October 2024 deadline.
Scope changes
In August last year, MEED reported that the estimated budget for the project had been increased from about $380m to approximately $460m due to scope changes.
The project uses the build-own-operate-transfer contract model.
EPF-50 and JPF-3 are sour hydrocarbons processing and handling facilities located in North Kuwait, designed to handle high-pressure (HP) sour hydrocarbons from several Jurassic wells in North Kuwait fields.
The project was launched to sustain production from the facilities by installing compression systems and SRUs.
Boosting compression
The contract’s original scope of work was divided into two parts, according to the tender documents that were released in September 2023.
The first part focused on installing a new medium-pressure (MP) compression system and SRU at EPF-50.
The second part focused on installing a new MP compression system and SRU at JPF-3.
The EPF-50 and JPF-3 facilities receive sour wet hydrocarbons reservoir fluids through flowline gathering networks and trunk lines.
Crude, gas and water are separated in a separation section that is currently receiving well fluid at 1,100 pounds a square inch gauge (psig), and the crude is stabilised for export after desalting.
The separation section consists of HP, MP and low-pressure (LP) separators in series. MP and LP gases are compressed to HP and combined with gas from HP separators.
The gas is then treated in gas sweetening and dehydration units before being exported via pipeline.
As the well fluid pressure depletes to MP, the combined feed from the inlet production headers and test header will be routed through a crude pre-heater to the new MP separator, which operates at about 425-450 psig.
The new compressors will compress the gas from MP to HP.
The EPF-50 facility can currently process 200 million standard cubic feet a day (scf/d) of gas, 50,000 barrels a day (b/d) of oil and 130 tonnes a day (t/d) of sulphur.
Originally, the upgrade project was expected to increase the volume of sulphur it can process to 270-310 t/d, but after the proposed changes to the scope, the capacity is now likely to be larger.
The JPF-3 facility can currently process 150 million scf/d of gas, 50,000 b/d of oil and 200 t/d of sulphur.
Originally, the planned upgrade was expected to increase the volume of gas that the facility can process to 240 million scf/d and the volume of sulphur to 440 t/d.
Due to the scope changes, the capacity of JPF-3 will now be increased by more than the volumes outlined in the original tender documents.
It is currently unclear by how much the capacities of EPF-50 and JPF-3 will increase under the new project scope.
https://image.digitalinsightresearch.in/uploads/NewsArticle/15129453/main.png -
Regional rail construction surges ahead21 November 2025

> This package also includes: Middle East becomes a hub as rail networks mature
The GCC is at the centre of global rail construction activity after a decade of stop-start activity. Progress is being made on several large-scale rail schemes, providing renewed opportunities for international contractors to re-enter the market.
From the Qiddiya high-speed rail in Saudi Arabia to the planned expansion of Dubai’s metro network and the long-awaited revival of the GCC railway, a new wave of projects is shaping the region’s economic future.
Well-timed resurgenceAccording to data from regional projects tracker MEED Projects, the region boasts a pipeline of over $140bn-worth of railway schemes. Several factors are driving the renewed focus on major infrastructure.
Firstly, the region’s post-pandemic recovery has been underpinned by robust fiscal performance. Higher oil prices since 2022 have strengthened government balance sheets, enabling public investment in capital projects. Unlike in previous cycles, however, the current wave of spending is guided by a clearer vision rooted in diversification and long-term national development strategies.
Saudi Arabia’s Vision 2030, the UAE’s Centennial Plan 2071 and Oman’s Vision 2040 all emphasise connectivity, mobility and urban liveability as essential components of sustainable growth. Governments are therefore prioritising infrastructure that forms the backbone for tourism, logistics and housing development.
Secondly, project delivery capabilities have matured across the GCC. Local developers, contractors and authorities have gained experience delivering large and complex schemes such as the Dubai and Riyadh metros and Doha’s Fifa World Cup infrastructure. This has built confidence and the capacity to handle more ambitious undertakings.
Thirdly, global construction markets are shifting. With slowing growth in some developed economies, the GCC offers a stable, well-capitalised and politically supportive environment for investment.
In addition, international contractors, consultants and suppliers are facing shrinking margins elsewhere and are therefore refocusing on the Gulf region’s more promising project pipelines.
Strong prospects
Saudi Arabia has a pipeline of about $60bn-worth of rail projects. The long-discussed Saudi Land Bridge, connecting the Red Sea to the Gulf through Riyadh, is being prepared for procurement. Once complete, it will be a 1,300-kilometre (km) corridor from Jeddah to Dammam, transforming freight logistics and positioning Saudi Arabia as a regional trade hub.
The kingdom’s planned Qiddiya high-speed rail, meanwhile, will link King Salman International airport with Qiddiya entertainment city. It is part of Riyadh’s broader mobility masterplan and reflects the government’s intention to integrate developments with efficient public transport.
Riyadh also continues to expand its metro system, with Line 7 currently under tendering. This addition will extend the network’s reach to growing urban districts, further embedding mass transit into the daily life of the city.

Dubai is moving forward with the proposed Metro Gold Line
In the UAE, the momentum is just as strong. The ongoing Etihad Rail project is entering a new phase with the anticipated rollout of passenger services, connecting Abu Dhabi, Dubai and eventually the northern emirates. Freight operations are already under way, providing a backbone for industrial connectivity and cross-border trade. Plans for an Abu Dhabi–Dubai high-speed link are also progressing as bid evaluation continues for the main construction works.
Dubai is also going ahead with the proposed Metro Gold Line, which is designed to serve new growth corridors and improve connectivity to emerging districts.
Meanwhile, regional integration is back on the agenda with the GCC Railway, a long-delayed project that is finally gaining traction. Once realised, the network will connect Kuwait to Oman via Saudi Arabia, Bahrain, Qatar and the UAE, and governments are now actively coordinating to align standards, timelines and funding mechanisms.
The GCC offers a stable, well-capitalised and politically supportive environment for investment
Evolving delivery models
While public funding remains central to these initiatives, the GCC’s infrastructure landscape is also seeing a gradual shift towards new delivery and financing models.
Public-private partnerships (PPPs) are gaining traction, especially in Saudi Arabia. The proposed Qiddiya high-speed rail project is planned as a PPP, while several components of Hafeet Rail are being delivered through joint ventures providing financing arrangements.
This evolution comes with challenges, however. These frameworks must balance investor confidence with
public value, creating a need for clear risk allocation and transparent governance.The scale and ambition of the ongoing projects have not gone unnoticed internationally. Leading construction, engineering, and technology firms are either expanding or returning to the region after years of reduced activity.
Global rail specialists are competing for lucrative contracts in the region, while international consultancies are increasingly embedded in master planning and programme management roles.
The resurgence in project activity within the regional rail sector means firms will have many prospects to explore.
“The regional market has not been this exciting in a long, long time,” a senior executive from a major international rail firm told MEED.
“The market is shaping up for a golden era in rail and we will make sure that we give it our full attention.”
Another executive added: “This is primarily because of the resources available to governments now compared to in previous years, but more importantly [it is due to] the intent and will to make the projects happen.”
The GCC’s clear project pipeline and decisive execution are also a draw. Several rail projects in the region, such as Dubai Metro and Etihad Rail, have progressed from concept to implementation in relatively short timeframes.
Moreover, sustainability and innovation are becoming central to the GCC’s value proposition. Digital engineering, modular construction and low-carbon materials are being adopted more widely.
Developers are under pressure to meet environmental standards and align with global best practices. Commitment to these concerns, particularly through the UAE and Saudi Arabia’s net-zero goals, further enhances the region’s attractiveness to global investors.
Bringing together transport, tourism, logistics and sustainability is creating a practical approach to modern urban development
Challenges ahead
Despite the optimism, challenges remain. Cost pressures, supply chain disruptions and competition for skilled labour could slow progress or inflate project budgets.
The rapid pace of project launches also risks overstretching local capacity. Maintaining quality, timelines and financial discipline will require strong governance and careful coordination between various government agencies.
Long-term success depends on integrating infrastructure investment with broader social and economic goals. Transport systems must connect to affordable housing, job clusters and educational hubs, otherwise benefits remain limited.
That said, the GCC has shown remarkable adaptability. The lessons learned from previous cycles, especially the importance of phasing, master planning and stakeholder alignment, are helping to shape current strategies. Authorities are more selective, prioritising projects that yield clear economic multipliers and align with national visions.
The current wave of infrastructure expansion looks set to position the GCC region as a global rail construction hotspot. The projects will also define the physical and economic landscape of the region for decades to come.
By connecting cities, ports, and industries, these projects are reshaping the region’s economy. Bringing together transport, tourism, logistics and sustainability is creating a practical approach to modern urban development.
If the previous era of regional construction was defined by skyscrapers and luxury resorts, the coming decade will be defined by connectivity and integration. The GCC’s major projects today are not about scale alone, but also about building more connected economies that can sustain growth.
The renewed momentum also presents an opportunity for regional governments to amplify their national ambitions by building more diversified economies, reducing carbon emissions and enhancing liveability.
Main image: Haramain high-speed train in Jeddah, Saudi Arabia
Middle East becomes a hub as rail networks mature: MEED interviews Martin Vaujour, Alstom’s Africa, Middle East and Central Asia region presidenthttps://image.digitalinsightresearch.in/uploads/NewsArticle/15132273/main.gif -
Middle East becomes a hub as rail networks mature21 November 2025

The resurgence in investment in metro and intercity lines means the region is no longer an emerging market for the global rail industry. It is now an established hub with an expanding network of projects and, increasingly, the need for ongoing servicing, upgrades and new technologies.
“We are reaching a point where it is not just about building new lines. Customers are now understanding that it is not enough to just buy new trains – they also need long-term partnerships to service and maintain them efficiently,” says Martin Vaujour, Alstom’s Africa, Middle East and Central Asia region president.Alstom, which has supplied rolling stock and systems for major schemes in the region such as the Riyadh Metro, is now seeing growing demand for both new-build contracts and service agreements. “There are still lots of new investments,” he says, “but also growing activity in signalling projects, service projects and spare parts – areas that used to be small but are now taking off. That is a [source] of satisfaction for me, because those businesses are less risky, have better margins and create long-term relationships with customers.”
The change is an important development as the region becomes a mature market with diverse opportunities for the rail industry. “There was a time when countries would just buy materials with export credit,” says Vaujour. “Now, they are supporting local capacity to service and maintain trains. The mindset is evolving, and that is a very positive sign.”
Saudi expansion
Buoyed by the opening of Riyadh Metro at the end of 2024, Saudi Arabia remains an important market. “They are happy with the success [of Riyadh Metro],” says Vaujour. “There is extension work on the existing lines, new rolling stock being discussed and a potential Line 7 project. The network is expanding, and that is a great success story.”
The next wave of growth in Saudi Arabia includes the planned Qiddiya Express high-speed line, which has recently attracted expressions of interest.
“That project has been on our radar for some time,” says Vaujour. “It is under the umbrella of the Royal Commission for Riyadh City, which is very well organised and structured. That gives the project strength and credibility.”
The scheme is being developed as a public-private partnership, a model that Vaujour says fits Saudi Arabia’s stable economic environment. “Public-private partnerships (PPPs) take longer to put together because they are more complex to structure, but in countries like Saudi Arabia – stable and with the capacity to raise debt – why not?” he says.
“We are fine with PPPs. We have experience from France, the UK and Spain.”
While Alstom does not invest directly, it plays a key role in structuring deals. “We are facilitators and advisers,” says Vaujour.
“Our job is to accompany the customer, to adjust and iterate with them, and to help find the best solution. PPP is one of the tools in the box – not the simplest one, but one that works.”
The challenge in the market today is not a lack of opportunity, but deciding where to focus.
“Our main problem is not the market; it is how to be selective,” he says. “We have more than enough opportunities to ensure a nice trajectory of growth. The difficulty is to pick our battles and fight for the right ones.”
The challenge in the market today is not a lack of opportunity, but deciding where to focus
Shifting focus
In Africa and Central Asia, Alstom has long-term locomotive and commuter train partnerships that offer years of visibility. In the Gulf, by contrast, the model remains dominated by engineering, procurement and construction-style projects.
“It is more big projects, where civil contractors team up with us to deliver metros or airport people movers,” says Vaujour.
As regional urban transport networks become established, attention is turning to intercity and high-speed rail. “In the Gulf, the Abu Dhabi-Dubai high-speed project is probably the most advanced, while Qiddiya Express and upgrades to the Haramain line in Saudi Arabia could also accelerate momentum.”
Interest in high-speed connections between Riyadh, Doha and Kuwait is also growing, although such schemes will depend on electrification. “High-speed rail comes with electrification,” Vaujour notes. “And that means significant investment.”
In addition to new infrastructure, the rail sector is being reshaped by technology. Alstom is investing in clean traction systems, such as hydrogen and battery-powered trains, as well as in autonomous operations.
“Hydrogen and battery traction are progressing, but they are still in an early stage,” says Vaujour. “Diesel will continue to dominate freight for some time, because there is no clean technology yet that can deliver that level of power. But for passenger services, we are starting to see progress.”
Driverless trains are another major growth area. “Customers everywhere are interested, partly because it is increasingly hard to find drivers, and also because software drives more efficiently than humans. It is more energy-efficient and reduces wear and tear,” says Vaujour.
As the Middle East’s networks expand, upgrading existing infrastructure is becoming as important as building new lines. Signalling systems are central to this evolution. “You cannot just create new lines every year – it is too expensive,” says Vaujour. “Signalling allows you to double train frequency. It is what makes networks more efficient.”
The evolution reflects a wider transformation of the region’s rail sector. “The Middle East has become an established rail hub,” says Vaujour. “It is no longer just about building – it is about operating, maintaining and evolving.”
https://image.digitalinsightresearch.in/uploads/NewsArticle/15131845/main.gif


