A case study in procurement

18 March 2025

 

Register for MEED’s 14-day trial access 

While it may not be in the headlines as much as some of its more eye-catching official gigaproject counterparts, Roshn has already delivered thousands of residential units in Saudi Arabia as it seeks to fill the upscale and community living housing map.

Launched in 2020, the Roshn gigaproject is a component of the Vision 2030 plan to achieve 70% home ownership among Saudi nationals by 2030. Alongside the National Housing Company, it is the delivery vehicle for government-backed housing construction as Riyadh seeks to meet the shortfall in available stock.

Its first project was its Sedra community in the north of the capital. Currently on its fourth of eight delivery phases, the multibillion-dollar masterplanned development will comprise 30,000 homes over 20 million square metres (sq m) when completed.

Roshn’s second Riyadh community under construction is Warefa in the northeast of the capital. More compact than Sedra, it will have 2,300 units over an area of 1.4 square kilometres, with 150,000 sq m of green open space.

Three years after the launch of its first projects, Roshn announced Marafy, its first scheme in Jeddah and its largest mixed-use development to date. Designed to accommodate more than 130,000 residents, Marafy will be built around an 11-kilometre, 100-metre-wide canal, linking with Obhur Creek in the northern outskirts of the kingdom’s second city.

Already breaking ground, Marafy’s first core component is the Alarous residential community, which will offer 18,000 units over a 4 million sq m land area.

Elsewhere in the kingdom, Roshn’s other planned community projects include Almanar in Mecca, Alfulwa in Hofuf and Aldanah in Dhahran. Between them, these schemes total more than 50,000 units. It is expected that thousands of additional homes in other parts of the kingdom will be announced by the developer in the next two years.

Delivering such projects at many different locations is a complex exercise, requiring procurement strategies that not only encompass on-time and on-budget completion, but also ensure that local content is maximised while at the same time maintaining stringent quality standards.

Tasked with handling Roshn’s overall procurement strategy is Iain McBride, the gigaproject developer’s head of commercial.

It is expected that thousands of additional homes in other parts of the kingdom will be announced by the developer in the next two years

Like other gigaprojects in the kingdom, McBride and his procurement team have had to deal with the twin challenges of soaring cost inflation and maximising local content in materials and equipment.

The five official gigaprojects – Diriyah, Neom, the Red Sea Project, Qiddiya and Roshn – are free to employ their own procurement rules and processes, and each has taken a different approach to address its specific requirements. For example, Red Sea Global uses a construction management approach wherein it contracts directly with companies and suppliers that would normally work as subcontractors under the main contractors.

Similarly, Diriyah Company employs a strategy of bundling several smaller contract packages into a single large contract, as a means of consolidating work to ensure lower costs and maintain contractor interest.


Hear directly from the gigaproject owners at the biggest construction event – The Saudi Gigaprojects 2025 Summit, happening in Riyadh from 12-14 May 2025. Click here to know more


Demand signalling

The nature of Roshn’s mainly residential projects means that from the outset it knew it would need thousands of items with similar specifications, such as doors; glass panes; sanitaryware; and heating, ventilation and air-conditioning systems.

To secure this supply chain, early on the company identified local manufacturers of these products and reached long-term agreements with them for the delivery of required materials.

“Our first step was signing a lot of long-term partnership agreements through master purchase agreements where we could leverage preferential rates,” says McBride, speaking to MEED in late January.

“Ultimately, it's all about balance and risk – derisking the opportunities for the supply chain by telling them how many doors, for example, we're going to need each quarter for the next five to 10 years. It gives confidence to the manufacturers that they can start committing to.”

Roshn was the first of the gigaprojects to publicly signal its demand requirements. In 2021, it announced that it would require at least 5 million doors, 3.5 million air-conditioning units, 4.3 million windows, 80 million sq m of tiles and 6.5 million pieces of sanitaryware. These numbers have since changed, but they are indicative of the scale of the supply chain challenge.

Armed with the knowledge that Roshn is both supported by its parent, sovereign wealth vehicle the Public Investment Fund (PIF), and that it is a central element of Saudi Vision 2030, local manufacturers had the confidence to commit to investing in production capacity to meet its needs.

Significantly, most of these deals have been with manufacturers within the kingdom, thereby maximising the local content aspects. Just as importantly, Roshn has not had to make any fixed orders – so-called ‘take-or-pay agreements’ – with  suppliers, such is the latter’s faith in the developer.

“For the time being, we’ve not had to make any firm commitments,” says McBride. “We did look at it at one point, but our approach has always been to keep it as simple as possible by listening to the supply chain and seeing what they need. When we were speaking to them, it wasn’t their number one driver; they weren’t screaming at us saying, ‘We need you to give us a firm order’.

“Now, many people think a take-or-pay agreement is essential – where you commit to ordering [a certain quantity] of materials over a period of months or years and, if you don’t, you have to pay a penalty, thereby adding risk and complexity for the developer.

“What we were able to agree instead was that we'll be open and transparent with [the suppliers about] what we need. We said to ourselves, ‘Let's get a good price that works, whether we buy directly from the supplier or whether we include that supplier within our tenders with major contractors’. And we’ve seen great success with that approach, with multiple companies.”

The localisation push is supported by the design process. Wherever possible, the designs for Roshn’s projects incorporate and specify equipment and materials that are known to be manufactured locally.

There have been instances where specific, specialised materials and products are not produced in the kingdom, or not in the quantities required, such as marble and certain architectural facades.

Where this is the case, Roshn is keen to explore how it can help to build in-kingdom capacity. The developer has initiatives through which it looks to co-invest in production facilities that come with high capital requirements.

As McBride explains, Roshn is only one part of the huge and rapidly accelerating Saudi projects market ecosystem, and in helping to increase capacity, it is also putting itself in a position to help other developers with their supply chain needs.

A case in point is Roshn’s contract with China Harbour Engineering Company, which was awarded the $2bn deal in 2023 to build villas at Sedra and Warefa.  

Part of the contract requires the Chinese contractor to set up a precast manufacturing facility on site at Sedra. In this way, Roshn could not only ringfence the plant for its own needs, but when it no longer requires the output, other projects could benefit from its production capacity.

“The factory has a 15-year lifespan, so any additional capacity will be there for another 10 years after our requirements are met,” says McBride. “In Riyadh, we have Expo 2030, the new airport, the stadiums and many other projects that could draw on its output.”

There are some situations where even this is not enough, particularly when it comes to contracting expertise. One such case is Roshn’s mandate to develop a 45,000-seat stadium in the southwest of Riyadh as part of the kingdom’s Fifa World Cup 2034 plans. On such a complex, highly engineered project, Roshn has insisted that an international contractor teams up with a local company as a condition of tender participation.

This insistence is based on Roshn’s experience overseeing the construction of a football stadium in Dammam alongside co-developer, Saudi Aramco. The project, which is being built by a joint venture of Belgium’s Besix and the local Albawani, is proceeding at a rapid pace and progress has been relatively trouble-free.

McBride says: “If we have to go abroad, let’s go abroad. But make sure it’s done in a smart way and that we’re not just throwing money out of the kingdom.”

Early contractor involvement

On the issue of contracting, it is well known that the massive amount of work in Saudi Arabia is stretching contractors to the limit, pushing up prices and straining labour, engineering and equipment resources.

Roshn’s approach to this challenge has been to engage with contractors at the earliest possible stage of project planning, specifically at the design phase, through an early contractor involvement (ECI) procurement framework. In this way, the company is able to obtain contractor feedback during concept and design and subsequently lower construction risk by improving a project’s constructability.

“It's about signposting the demand by getting the contractor in early, where you can really influence the design, the buildability and the value-engineering opportunities,” says McBride. “Ideally, we bring them in as quickly as possible during the concept stages, when there's very little cost to changing things.

“The worst thing for a contractor is receiving a [request for proposal] cold. They have to … come back in four weeks and then be squeezed for a best price, whereas with ECI they can add value. They really appreciate that.”

When asked to quantify the cost benefits of such an approach, McBride is forthright: “It’s not even a case of doing the maths,” he says. “We have a great example of where it’s worked on our Aldanah project in Dammam. We selected the contract very early on and locked in the floor plans and facades that we wanted. We were then able to deliver a street of 10 show homes [that took] not much more than four months to design and construct.

“The saving, in terms of time, was massive; we probably halved the duration. I probably wouldn’t be exaggerating if I said it saved about a year.

“There are two ways you can follow your engineer,” he continues. “One: you can follow them early and make sure that the way you're looking to save costs is in areas that are not impacting the customer.

“Or two: the worst thing you can do is get to the end and you have a full structural design that could be over-engineered and you’re spending money in the wrong places.

“We don’t want to get to a point where we're trying to value-engineer by cutting things out that are important to customers,” McBride explains. “And that's what you avoid by having this early contractor involvement.”

The company is able to obtain contractor feedback during concept and design and subsequently lower construction risk by improving a project’s constructability

Unlike the other gigaprojects, Roshn has been in the favourable position of being able to raise some revenue by marketing and selling its properties off plan. While this has been beneficial from a development perspective, it has also meant that the developer must get its pricing and housing specifications right if it is to develop homes within an already-defined budget.

Having a contracting partner on board during the design and specification stage facilitates the conversation between the property sales team, which is informing on market requirements, and the builder, who can deliver within the designed cost and quality parameters.

This is in contrast to many real estate developments for which sales are completed before the construction estimates come in, potentially undermining the business case.

The step beyond ECI is for contractors and suppliers to partner with Roshn to inject equity into the projects by acting as co-developers. McBride points to several planned mid-rise towers at Marafy that could be a starting point for this.

Contractors financing projects or bringing in replacement equity has long been an ambition in the region, but builders have been reluctant to adopt this approach. Nonetheless, McBride is confident that it could happen, indicating that there has already been strong interest from the contracting community.

Cost inflation

Another major talking point in Saudi construction is the escalating costs caused by high inflation, logistical challenges and a tightening of contracting and skilled labour capacity.

In many cases, this has required the rescoping of projects, revisions to timelines and even the scrapping of elements. Neom is arguably the best example of this, as it has reprioritised The Line and is facing an estimated cost of $50bn for building each of its first three modules – far in excess of original estimates.

Roshn’s approach to the challenge is to be as open and transparent as possible with the contractor and supplier community. This has involved outlining a long-term pipeline of work that gives the supply chain confidence about its requirements, enabling them to fix in long-term pricing structures. In return, the developer expects prices to come in competitively.

“It’s no secret within the supply chain market that Roshn has quite aggressive price points,” says McBride, a former chartered surveyor who, prior to joining Roshn, worked as a quantity surveyor and cost-management director at consultants Faithful+Gould (now AtkinsRealis) and Rider Levett Bucknall.

“What we're trying to do is engage early, build trust with the contractors, let them see we’re a good client that's going to pay and have honest and fair contracting terms, and work together to try and solve issues post-contract.

“We don't mind if there's inflationary pressures because of commodity prices increasing. But what we're trying to avoid is inflationary prices through just the demand increasing.

“An innovative way that we've implemented this even on our lump-sum contracts – our traditional Redbook or older contracts – is that we have preferred supplier agreement clauses in them,” he adds.

“So, rather than a traditional bill of quantities (BoQ) that has a rate, a quantity, a total, within our rate section we have the material supply rate, the installation rate and then everything else, such as overhead profit. We protect the installation rate, so it's not a percentage of the material; it's a fixed SR100 a square metre to install, for example.

“One of the big frustrations for contractors is [that the supplier has] a material we think they're going to deliver. It's maybe not available, so they submit alternative materials. The client keeps rejecting it – it's not what they want – and it becomes a delay; it's painful.”

McBride gives the example of a pre-approved bathroom sink. Thanks to Roshn’s relationships with key long-term suppliers, the company is able to negotiate better rates for sanitaryware than would be available to a contractor on an ad hoc basis. If the developer’s rates for sinks are better than the BoQ, it splits the savings 50:50 with the contractor.

“The contractors are winning out of that exercise, we're winning out of it and, ultimately, the customers are winning out of it as well, because we’re passing on those savings,” says McBride.

Flexibility

The benefits to contractors and suppliers extend to payment terms. In today’s sellers’ market, vendors are effectively able to pick and choose the clients they want to work for. As a result, clients – including the gigaprojects – have had to introduce more flexible payment terms and develop market reputations for paying on time.

Roshn may lead the pack on this, with an average payment time from invoice to payment of just 13 days in 2024. A decade ago, this would have been unheard of, but it is now increasingly becoming the norm among the gigaprojects.

In addition, like its PIF peers, Roshn has done away with tender fees and tender bonds, viewing them as outdated means of enforcing vendor participation, especially given the tight liquidity and cashflow situation in the projects market in Saudi Arabia.

Will such flexibility ever extend to performance bonds? McBride is sceptical, pointing to the fact that Roshn’s strong relationship with local banks allows to it facilitate credit agreements between contractors and their lenders. Being a gigaproject developer supported by the PIF – and by tacit extension the state – also helps provide the underlining ease of mind for financers.

Nonetheless, Roshn also takes a proactive approach with advanced payments, enabling up to 20% of the total contract value at the initial stage of the project.

“We've been quite clever in how we do this,” says McBride. “We don't go and release 20% straight away. We’ll do 10% and then, when we’ve evidence that you’ve expended that 10% on mobilisation and site establishment, we’ll release the second 10% tranche.”

Subcontractors

One of the chief sticking points in the kingdom’s projects ecosystem in the past decade has been the capacity and capability of its subcontractors.

The payments crisis in 2017-20 forced many main and general contractors to reduce their permanent labour forces, plant and general resources. Wary of a repeat, most have retained their leaner structure and so have turned increasingly to subcontractors for their manpower and delivery requirements.

In theory, this makes sense, but in practice subcontractors in Saudi Arabia are themselves often overstretched in terms of both delivery capacity and labour availability. In turn, they frequently use their own subcontractors, which then also outsource, to the point that specific elements of a project may be completed by companies very far down the supply chain – with the quality issues that this implies.

Roshn’s solution is to ensure any subcontractor on site goes through a vetting process encompassing quality and financial checks, thereby ensuring it has full visibility on every company on site.

Increasingly, Roshn is dealing with suppliers directly, under supply-install contracts. This can create interfacing issues with the main contractors, however, which are ultimately responsible for the project’s delivery.

“We have to be quite careful on that,” McBride says. “We have to go through all the checks and balances during the prequalification process because if we are going to give a subcontractor to a contractor that we're saying is pre-vetted by Roshn, we could be opening the door to lots of claims from the main contractor against us. So, vetting for us is absolutely crucial.”

Roshn is also working with smaller suppliers and subcontractors to help them evolve and grow, so that they can start taking on smaller main contractor roles themselves.

“Not every construction package we award is in the billions of riyals,” says McBride. “Our thinking is to let the big tier-one contractors focus on the multibillion-riyal deals while we encourage the smaller ones to grow as part of our supplier development programme.”

To achieve this, the developer holds events and bootcamps with its vendors to discuss best practices on subjects including health and safety, variation procedures and how to submit good tender returns.

Roshn is also working with smaller suppliers and subcontractors to help them evolve and grow

Building information modelling

Vendor education also extends to the use of building information modelling (BIM) and other construction technologies.

BIM is mandatory on Roshn’s projects, as it is on the other gigaprojects. While use of the technology is standard across almost all main contractors in the region, its take-up among smaller companies in the supply chain has been slower, with firms pointing to the cost of its adoption and integration as a barrier, as well as the fact that some clients, particularly government ones, view it as providing limited benefit.

Roshn’s task in this area is made difficult because its projects are less complex from an engineering and construction perspective.

“We’re building villas; it’s completely different to building stadiums or airports,” McBride says. “Can these contractors build from [two-dimensional] drawings? Yes, of course they can. You're not going to convince a smaller contractor that all of these benefits will make it easier to build because they know how to build. They've been doing it for decades.

“But the savings are in making it easier to procure, savings in the repeatability, and in the change control. If you upskill yourself on a Roshn project, you are building your capability, which you can then [demonstrate] to other clients as proof you can go after bigger and more complex projects. It's something that the whole industry has to get behind.”

Indeed, there is much to learn from Roshn’s approach to delivering its infrastructure and building plans. While the comparatively straightforward nature of its projects means that its procurement strategies may not be suited to those gigaprojects with more iconic designs, for many other developers it is a case study in efficient processes that have proven effective in delivering work on time and to budget.

This is just as well given that Roshn is set to embark on the next stage of its journey, with its focus on the more complex Marafy city development in Jeddah and Roshn Stadium in Riyadh. However, the evidence suggests that from a procurement strategy perspective, it is well-positioned to also make this a success.



https://image.digitalinsightresearch.in/uploads/NewsArticle/13503828/main.gif
Edward James
Related Articles
  • Bahrain retenders Hawar desalination works

    25 September 2026

     

    Bahrain’s Electricity & Water Authority (EWA) has retendered a contract to develop a seawater intake and outfall system for a planned seawater reverse osmosis (SWRO) desalination plant on Hawar Island.

    The scope includes constructing a seawater intake facility with a capacity of 1,515 cubic metres an hour and a seawater outfall structure with a diffuser system.

    The bid deadline is 21 October.

    The original tender received just two bids from Noble Development (UAE) and Al-Hassanain Company (Bahrain). These were opened in December 2025.

    The reissued tender is expected to attract bids from Al-Hassanain Company, Noble Development, UK-based engineering consultancy HR Wallingford, Bahrain Mechanical & Diving Services and Ocean Diving & Marine Services (Bahrain).

    As previously reported, the marine works project is linked to two other contracts: one covering the main Hawar desalination plant and another involving the construction of two ground storage tanks and the installation of water transmission pumps.

    Malaysia-based Sparco Engineering recently won the engineering, procurement and construction contract for the desalination plant project after submitting the lowest bid last year.

    The plant is designed to produce 1 million imperial gallons a day (MIGD) of potable water.

    The Hawar Islands form an archipelago of 16 desert islands and islets located approximately 26 kilometres southeast of Ras Al-Bar in Bahrain. The desalination plant is intended to support water supply requirements on the islands.

    The third package linked with the SWRO project was tendered last November, with Greece-headquartered Ergotem submitting the lowest bid of $1.92m.

    This contract covers the construction of two steel ground storage tanks with a capacity of 1 million gallons each, pumping stations, motors, pipelines and associated facilities.

    As of August, the contract had not yet been awarded.

    It is understood that Sparco Engineering will be required to ensure that the plant’s design and construction align technically and operationally with these two projects so that all three components function together as one integrated system.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19993971/main.jpg
    Mark Dowdall
  • Dubai property bubble risk rises as price growth stalls

    25 September 2026

    Register for MEED’s 14-day trial access 

    Dubai’s residential property market remains in elevated bubble-risk territory after a sharp slowdown in price growth, according to UBS.

    The emirate’s housing boom came to an abrupt halt at the onset of the regional conflict, the Swiss bank said in its Global Real Estate Bubble Index 2026 report. Inflation-adjusted house prices have fallen back to mid-2025 levels, after real growth of more than 10% in 2025.

    Dubai scored 1.16 on the index, up on last year, placing it fourth among the 23 cities covered. Only Zurich and Tokyo, at 1.69 and 1.54 respectively, are classed as high risk. Miami, Seoul, Geneva and Lisbon join Dubai in the elevated category, which covers scores between 1.0 and 1.5.

    Real prices in Dubai rose by 0.4% in the year to Q2 2026, while real rents fell by 4%. UBS said bubble risk remained elevated despite some easing since March.

    Ownership costs

    UBS said existing tenants were likely to take advantage of the pause in price growth and, in some cases, price concessions to buy homes. Despite elevated mortgage rates, Dubai remains one of the few markets where ownership is relatively attractive given the high cost of renting, according to the bank.

    A skilled service worker in Dubai needs about five years of average income to buy a 60-square-metre apartment near the city centre, compared with about 15 years in Hong Kong and 11 years in London. It takes 16 years of rent to pay for an equivalent apartment, one of the lowest ratios in the study. UBS attributed the low price-to-rent ratios in Dubai, Sao Paulo and the US cities surveyed to less regulated rental markets and higher interest rates, as well as elevated risk premiums in Dubai and Sao Paulo.

    The bank said uncertainty over whether the inflow of high-income earners would recover was weighing on the premium segment. It added that Dubai’s structural advantages, including its strategic location and its appeal as an international business hub, remained intact, and that an improvement in the geopolitical environment was likely to support a rapid recovery in market sentiment and price expectations.

    Supply is a further source of uncertainty. Some developments have stalled, and others may be delivered later than planned, although UBS said the market remained exposed to heightened volatility because of persistent concerns about structural oversupply.

    Global slowdown

    Across the cities analysed, real residential prices rose by an average of 0.5% in the year, down from 1.4% in mid-2025. Seoul recorded the strongest real growth, at 11%, while Toronto and Vancouver fell by about 10%.

    The report also points to Gulf capital supporting other markets. UBS said interest from Middle Eastern buyers could further lift prices in Geneva, and that investors from the Middle East, the US and Asia had supported London’s prime segment.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19987757/main.jpg
    Colin Foreman
  • UAE vehicle manufacturing push moves into production

    25 September 2026

     

    Register for MEED’s 14-day trial access 

    Chinese-linked carmaker Rox has begun vehicle production at Khalifa Economic Zones Abu Dhabi (Kezad). The start-up represents the most significant output so far from the UAE’s efforts to build an automotive manufacturing industry.

    The first three Rox Adamas vehicles, carrying the Made in the Emirates mark, came off the production line at the company’s new Abu Dhabi facility in early September. The 10,000-square-metre plant is expected to reach an initial capacity of 20,000 vehicles a year by 2027, rising to 300,000 vehicles a year by 2030.

    The facility can sub-assemble more than 80 types of vehicle components and also carries out complete vehicle assembly, calibration, rain and road testing, and final inspection. Rox moved its global headquarters to the UAE last year and plans to supply local and export markets.

    The project forms part of Rox’s partnership with the Abu Dhabi Investment Office (Adio) and is supported by the UAE Ministry of Industry & Advanced Technology. Kezad Group signed the lease agreement for the facility in May.

    Programme targets

    The Rox plant is the first major output of a state-led strategy that has gathered pace over the past 18 months. Adio launched its automotive programme at the Make it in the Emirates forum in May 2025, with the aim of creating a hub for vehicle manufacturing and assembly, research and development, restoration, auctions and luxury cars.

    The programme is projected to contribute AED100bn ($27.2bn) to Abu Dhabi’s GDP by 2045, attract more than AED8bn ($2.2bn) in foreign direct investment and create 7,000 skilled jobs. Adio has also introduced an automotive artificial intelligence curriculum with universities to develop Emirati talent in the sector.

    In October last year, Adio and AD Ports Group agreed to work with Netherlands-based Stellantis to develop the emirate’s automotive ecosystem. The memorandum of understanding covers expansion into Middle East and Africa markets, an ecosystem for autonomous taxi services, and research into next-generation mobility technologies.

    Under the agreement, Stellantis will explore investment opportunities in Abu Dhabi, while Adio and AD Ports Group will provide market intelligence and logistics support. The announcements did not include a commitment to build a production facility.

    Kezad already hosts smaller electric vehicle (EV) operations. In 2024, UAE-headquartered NWTN signed a lease for a Kezad facility with capacity to assemble 5,000-10,000 semi-knocked-down EVs a year, with plans to expand to 50,000 units in a second phase.

    Trading hub

    Dubai has focused on vehicle trade rather than manufacturing. In November last year, Dubai Municipality signed a partnership agreement with DP World’s Economic Zones division to establish and manage the Dubai Auto Market, a 22 million-square-foot complex with more than 1,500 showrooms that is designed to handle over 800,000 new and used vehicles a year.

    Enabling works are under way, carried out by local contractor Rad International Road Construction, with US-based Aecom serving as project consultant. Sheikh Maktoum Bin Mohammed Bin Rashid Al-Maktoum, first deputy ruler of Dubai, said at the launch that the project would foster a cluster of light industries for vehicle assembly and trade.

    The market builds on an established base. Jebel Ali Free Zone hosts more than 940 automotive and spare-parts companies, including Ford, General Motors, Honda, Hyundai, Nissan and Volkswagen. In 2022, M Glory Group laid the foundation stone for a AED1.5bn ($408m) EV plant at Dubai Industrial City, with a planned capacity of 55,000 cars a year.

    Regional competition

    The UAE is not alone in pursuing automotive manufacturing. In Saudi Arabia, the Public Investment Fund (PIF) owns 70% of Hyundai Motor Manufacturing Middle East, which will roll out its first vehicle by Q4 2026 and targets annual production of 50,000 vehicles. Ceer, the kingdom’s first EV manufacturer, intends to roll its first vehicle off the production line in late 2026.

    Saudi Arabia’s National Industrial Strategy aims to attract three to four manufacturers capable of producing more than 300,000 vehicles a year within a single automotive cluster. In Qatar, JTA International Investment Holding said last month that it was working with the UK’s Watt Electric Vehicle Company to set up a factory.

    The two leading Gulf economies are taking different approaches. Saudi Arabia has relied on direct PIF shareholdings in manufacturers. In the UAE, investment offices, port groups and economic zone operators have led the effort, using land, logistics and incentives to attract privately owned carmakers.

    Scaling up is the next test. Rox’s plan to increase output fifteen-fold between 2027 and 2030 will show whether Abu Dhabi’s model can support volume manufacturing. Achieving it would give the UAE production capacity comparable to the level Saudi Arabia is targeting across its entire automotive cluster.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19986887/main.jpeg
    Colin Foreman
  • SAR prepares phosphate rail second section contract award

    25 September 2026

     

    Saudi Arabian Railways (SAR) is preparing to formally award another multibillion-riyal contract to double the tracks on the existing phosphate transport railway network connecting the Waad Al-Shamal mines to Ras Al-Khair in the kingdom’s Eastern Province.

    The contract covers construction works on the second section of the railway line, spanning more than 150 kilometres (km).

    The scope of work includes civil works, alignment modifications, track and loop construction, and associated infrastructure such as bridges and culverts, as well as enhancements to signalling and telecommunications systems.

    SAR floated the tender in February, and bids were submitted in April.

    SAR is making significant progress on its Phosphate 3 rail programme. Last month, MEED exclusively reported that SAR had awarded an estimated SR4bn-plus ($1.1bn) contract to add another track to the first section of the existing phosphate transport railway network.

    The contract was awarded to local firm Alomaier Trading & Contracting Company.

    The scope includes track doubling, alignment modifications, utility bridges, culvert widening and hydrological structures, as well as the conversion of the AZ1 siding into a mainline track. It also covers support works for signalling and telecommunications systems.

    The existing railway runs from the Waad Al-Shamal mines to Ras Al-Khair. The first-section works will cover about 100km, connecting the AZ1/Nariyah Yard to Ras Al-Khair.

    Switzerland-based engineering firm ARX is the project consultant.

    Formerly known as the North-South Railway, the North Train is a 1,550km freight line running from the phosphate and bauxite mines in the far north of the kingdom to the Al-Baithah junction. From there, it diverges into a line south to Riyadh and another line east to downstream fertiliser production and alumina refining facilities at Ras Al-Khair on the Gulf coast.

    Adding a second track and freight yards will significantly increase the network’s cargo-carrying capacity and support growth in industrial production. Project implementation is expected to take four years.

    State-owned SAR is also considering increasing the localisation of railway materials and equipment, including developing a cement sleeper manufacturing facility.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19983928/main.jpg
    Yasir Iqbal
  • Meraas awards $272m Nad Al-Sheba Gardens villas deal

    25 September 2026

    Dubai-based real estate developer Meraas Holding, part of Dubai Holding, has awarded a AED1bn ($272m) contract for the construction of the seventh phase of the Nad Al-Sheba Gardens community.

    The contract, which covers the delivery of 272 villas and townhouses, was awarded to local firm GCC Contracting.

    The scope of work includes 130 villas, 142 three-bedroom townhouses, and associated utilities and infrastructure.

    Construction has started, and the project is slated for completion in 2028.

    Last year, Meraas awarded a AED690m ($188m) contract for the construction of the fourth phase of the Nad Al-Sheba Gardens community in Dubai.

    Meraas awarded the contract to local firm Bhatia General Contracting.

    The scope of that contract covers the construction of 92 townhouses, 96 villas and two pool houses.

    In December last year, Meraas announced the eleventh and final phase of its Nad Al-Sheba Gardens residential community. This phase includes the development of 210 new villas and townhouses, as well as a school, located in the northwest corner of the development.

    According to UK analytics firm GlobalData, the UAE’s construction industry will register annual growth of 3.9% between 2025 and 2027, supported by investments in infrastructure, renewable energy, oil and gas, housing, industrial and tourism projects.

    The residential construction sector is expected to record an average annual growth rate of 2.7% between 2025 and 2028, supported by private investment in residential housing, along with government initiatives to meet rising demand.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19983032/main.png
    Yasir Iqbal