A case study in procurement

18 March 2025

 

Register for MEED’s 14-day trial access 

While it may not be in the headlines as much as some of its more eye-catching official gigaproject counterparts, Roshn has already delivered thousands of residential units in Saudi Arabia as it seeks to fill the upscale and community living housing map.

Launched in 2020, the Roshn gigaproject is a component of the Vision 2030 plan to achieve 70% home ownership among Saudi nationals by 2030. Alongside the National Housing Company, it is the delivery vehicle for government-backed housing construction as Riyadh seeks to meet the shortfall in available stock.

Its first project was its Sedra community in the north of the capital. Currently on its fourth of eight delivery phases, the multibillion-dollar masterplanned development will comprise 30,000 homes over 20 million square metres (sq m) when completed.

Roshn’s second Riyadh community under construction is Warefa in the northeast of the capital. More compact than Sedra, it will have 2,300 units over an area of 1.4 square kilometres, with 150,000 sq m of green open space.

Three years after the launch of its first projects, Roshn announced Marafy, its first scheme in Jeddah and its largest mixed-use development to date. Designed to accommodate more than 130,000 residents, Marafy will be built around an 11-kilometre, 100-metre-wide canal, linking with Obhur Creek in the northern outskirts of the kingdom’s second city.

Already breaking ground, Marafy’s first core component is the Alarous residential community, which will offer 18,000 units over a 4 million sq m land area.

Elsewhere in the kingdom, Roshn’s other planned community projects include Almanar in Mecca, Alfulwa in Hofuf and Aldanah in Dhahran. Between them, these schemes total more than 50,000 units. It is expected that thousands of additional homes in other parts of the kingdom will be announced by the developer in the next two years.

Delivering such projects at many different locations is a complex exercise, requiring procurement strategies that not only encompass on-time and on-budget completion, but also ensure that local content is maximised while at the same time maintaining stringent quality standards.

Tasked with handling Roshn’s overall procurement strategy is Iain McBride, the gigaproject developer’s head of commercial.

It is expected that thousands of additional homes in other parts of the kingdom will be announced by the developer in the next two years

Like other gigaprojects in the kingdom, McBride and his procurement team have had to deal with the twin challenges of soaring cost inflation and maximising local content in materials and equipment.

The five official gigaprojects – Diriyah, Neom, the Red Sea Project, Qiddiya and Roshn – are free to employ their own procurement rules and processes, and each has taken a different approach to address its specific requirements. For example, Red Sea Global uses a construction management approach wherein it contracts directly with companies and suppliers that would normally work as subcontractors under the main contractors.

Similarly, Diriyah Company employs a strategy of bundling several smaller contract packages into a single large contract, as a means of consolidating work to ensure lower costs and maintain contractor interest.


Hear directly from the gigaproject owners at the biggest construction event – The Saudi Gigaprojects 2025 Summit, happening in Riyadh from 12-14 May 2025. Click here to know more


Demand signalling

The nature of Roshn’s mainly residential projects means that from the outset it knew it would need thousands of items with similar specifications, such as doors; glass panes; sanitaryware; and heating, ventilation and air-conditioning systems.

To secure this supply chain, early on the company identified local manufacturers of these products and reached long-term agreements with them for the delivery of required materials.

“Our first step was signing a lot of long-term partnership agreements through master purchase agreements where we could leverage preferential rates,” says McBride, speaking to MEED in late January.

“Ultimately, it's all about balance and risk – derisking the opportunities for the supply chain by telling them how many doors, for example, we're going to need each quarter for the next five to 10 years. It gives confidence to the manufacturers that they can start committing to.”

Roshn was the first of the gigaprojects to publicly signal its demand requirements. In 2021, it announced that it would require at least 5 million doors, 3.5 million air-conditioning units, 4.3 million windows, 80 million sq m of tiles and 6.5 million pieces of sanitaryware. These numbers have since changed, but they are indicative of the scale of the supply chain challenge.

Armed with the knowledge that Roshn is both supported by its parent, sovereign wealth vehicle the Public Investment Fund (PIF), and that it is a central element of Saudi Vision 2030, local manufacturers had the confidence to commit to investing in production capacity to meet its needs.

Significantly, most of these deals have been with manufacturers within the kingdom, thereby maximising the local content aspects. Just as importantly, Roshn has not had to make any fixed orders – so-called ‘take-or-pay agreements’ – with  suppliers, such is the latter’s faith in the developer.

“For the time being, we’ve not had to make any firm commitments,” says McBride. “We did look at it at one point, but our approach has always been to keep it as simple as possible by listening to the supply chain and seeing what they need. When we were speaking to them, it wasn’t their number one driver; they weren’t screaming at us saying, ‘We need you to give us a firm order’.

“Now, many people think a take-or-pay agreement is essential – where you commit to ordering [a certain quantity] of materials over a period of months or years and, if you don’t, you have to pay a penalty, thereby adding risk and complexity for the developer.

“What we were able to agree instead was that we'll be open and transparent with [the suppliers about] what we need. We said to ourselves, ‘Let's get a good price that works, whether we buy directly from the supplier or whether we include that supplier within our tenders with major contractors’. And we’ve seen great success with that approach, with multiple companies.”

The localisation push is supported by the design process. Wherever possible, the designs for Roshn’s projects incorporate and specify equipment and materials that are known to be manufactured locally.

There have been instances where specific, specialised materials and products are not produced in the kingdom, or not in the quantities required, such as marble and certain architectural facades.

Where this is the case, Roshn is keen to explore how it can help to build in-kingdom capacity. The developer has initiatives through which it looks to co-invest in production facilities that come with high capital requirements.

As McBride explains, Roshn is only one part of the huge and rapidly accelerating Saudi projects market ecosystem, and in helping to increase capacity, it is also putting itself in a position to help other developers with their supply chain needs.

A case in point is Roshn’s contract with China Harbour Engineering Company, which was awarded the $2bn deal in 2023 to build villas at Sedra and Warefa.  

Part of the contract requires the Chinese contractor to set up a precast manufacturing facility on site at Sedra. In this way, Roshn could not only ringfence the plant for its own needs, but when it no longer requires the output, other projects could benefit from its production capacity.

“The factory has a 15-year lifespan, so any additional capacity will be there for another 10 years after our requirements are met,” says McBride. “In Riyadh, we have Expo 2030, the new airport, the stadiums and many other projects that could draw on its output.”

There are some situations where even this is not enough, particularly when it comes to contracting expertise. One such case is Roshn’s mandate to develop a 45,000-seat stadium in the southwest of Riyadh as part of the kingdom’s Fifa World Cup 2034 plans. On such a complex, highly engineered project, Roshn has insisted that an international contractor teams up with a local company as a condition of tender participation.

This insistence is based on Roshn’s experience overseeing the construction of a football stadium in Dammam alongside co-developer, Saudi Aramco. The project, which is being built by a joint venture of Belgium’s Besix and the local Albawani, is proceeding at a rapid pace and progress has been relatively trouble-free.

McBride says: “If we have to go abroad, let’s go abroad. But make sure it’s done in a smart way and that we’re not just throwing money out of the kingdom.”

Early contractor involvement

On the issue of contracting, it is well known that the massive amount of work in Saudi Arabia is stretching contractors to the limit, pushing up prices and straining labour, engineering and equipment resources.

Roshn’s approach to this challenge has been to engage with contractors at the earliest possible stage of project planning, specifically at the design phase, through an early contractor involvement (ECI) procurement framework. In this way, the company is able to obtain contractor feedback during concept and design and subsequently lower construction risk by improving a project’s constructability.

“It's about signposting the demand by getting the contractor in early, where you can really influence the design, the buildability and the value-engineering opportunities,” says McBride. “Ideally, we bring them in as quickly as possible during the concept stages, when there's very little cost to changing things.

“The worst thing for a contractor is receiving a [request for proposal] cold. They have to … come back in four weeks and then be squeezed for a best price, whereas with ECI they can add value. They really appreciate that.”

When asked to quantify the cost benefits of such an approach, McBride is forthright: “It’s not even a case of doing the maths,” he says. “We have a great example of where it’s worked on our Aldanah project in Dammam. We selected the contract very early on and locked in the floor plans and facades that we wanted. We were then able to deliver a street of 10 show homes [that took] not much more than four months to design and construct.

“The saving, in terms of time, was massive; we probably halved the duration. I probably wouldn’t be exaggerating if I said it saved about a year.

“There are two ways you can follow your engineer,” he continues. “One: you can follow them early and make sure that the way you're looking to save costs is in areas that are not impacting the customer.

“Or two: the worst thing you can do is get to the end and you have a full structural design that could be over-engineered and you’re spending money in the wrong places.

“We don’t want to get to a point where we're trying to value-engineer by cutting things out that are important to customers,” McBride explains. “And that's what you avoid by having this early contractor involvement.”

The company is able to obtain contractor feedback during concept and design and subsequently lower construction risk by improving a project’s constructability

Unlike the other gigaprojects, Roshn has been in the favourable position of being able to raise some revenue by marketing and selling its properties off plan. While this has been beneficial from a development perspective, it has also meant that the developer must get its pricing and housing specifications right if it is to develop homes within an already-defined budget.

Having a contracting partner on board during the design and specification stage facilitates the conversation between the property sales team, which is informing on market requirements, and the builder, who can deliver within the designed cost and quality parameters.

This is in contrast to many real estate developments for which sales are completed before the construction estimates come in, potentially undermining the business case.

The step beyond ECI is for contractors and suppliers to partner with Roshn to inject equity into the projects by acting as co-developers. McBride points to several planned mid-rise towers at Marafy that could be a starting point for this.

Contractors financing projects or bringing in replacement equity has long been an ambition in the region, but builders have been reluctant to adopt this approach. Nonetheless, McBride is confident that it could happen, indicating that there has already been strong interest from the contracting community.

Cost inflation

Another major talking point in Saudi construction is the escalating costs caused by high inflation, logistical challenges and a tightening of contracting and skilled labour capacity.

In many cases, this has required the rescoping of projects, revisions to timelines and even the scrapping of elements. Neom is arguably the best example of this, as it has reprioritised The Line and is facing an estimated cost of $50bn for building each of its first three modules – far in excess of original estimates.

Roshn’s approach to the challenge is to be as open and transparent as possible with the contractor and supplier community. This has involved outlining a long-term pipeline of work that gives the supply chain confidence about its requirements, enabling them to fix in long-term pricing structures. In return, the developer expects prices to come in competitively.

“It’s no secret within the supply chain market that Roshn has quite aggressive price points,” says McBride, a former chartered surveyor who, prior to joining Roshn, worked as a quantity surveyor and cost-management director at consultants Faithful+Gould (now AtkinsRealis) and Rider Levett Bucknall.

“What we're trying to do is engage early, build trust with the contractors, let them see we’re a good client that's going to pay and have honest and fair contracting terms, and work together to try and solve issues post-contract.

“We don't mind if there's inflationary pressures because of commodity prices increasing. But what we're trying to avoid is inflationary prices through just the demand increasing.

“An innovative way that we've implemented this even on our lump-sum contracts – our traditional Redbook or older contracts – is that we have preferred supplier agreement clauses in them,” he adds.

“So, rather than a traditional bill of quantities (BoQ) that has a rate, a quantity, a total, within our rate section we have the material supply rate, the installation rate and then everything else, such as overhead profit. We protect the installation rate, so it's not a percentage of the material; it's a fixed SR100 a square metre to install, for example.

“One of the big frustrations for contractors is [that the supplier has] a material we think they're going to deliver. It's maybe not available, so they submit alternative materials. The client keeps rejecting it – it's not what they want – and it becomes a delay; it's painful.”

McBride gives the example of a pre-approved bathroom sink. Thanks to Roshn’s relationships with key long-term suppliers, the company is able to negotiate better rates for sanitaryware than would be available to a contractor on an ad hoc basis. If the developer’s rates for sinks are better than the BoQ, it splits the savings 50:50 with the contractor.

“The contractors are winning out of that exercise, we're winning out of it and, ultimately, the customers are winning out of it as well, because we’re passing on those savings,” says McBride.

Flexibility

The benefits to contractors and suppliers extend to payment terms. In today’s sellers’ market, vendors are effectively able to pick and choose the clients they want to work for. As a result, clients – including the gigaprojects – have had to introduce more flexible payment terms and develop market reputations for paying on time.

Roshn may lead the pack on this, with an average payment time from invoice to payment of just 13 days in 2024. A decade ago, this would have been unheard of, but it is now increasingly becoming the norm among the gigaprojects.

In addition, like its PIF peers, Roshn has done away with tender fees and tender bonds, viewing them as outdated means of enforcing vendor participation, especially given the tight liquidity and cashflow situation in the projects market in Saudi Arabia.

Will such flexibility ever extend to performance bonds? McBride is sceptical, pointing to the fact that Roshn’s strong relationship with local banks allows to it facilitate credit agreements between contractors and their lenders. Being a gigaproject developer supported by the PIF – and by tacit extension the state – also helps provide the underlining ease of mind for financers.

Nonetheless, Roshn also takes a proactive approach with advanced payments, enabling up to 20% of the total contract value at the initial stage of the project.

“We've been quite clever in how we do this,” says McBride. “We don't go and release 20% straight away. We’ll do 10% and then, when we’ve evidence that you’ve expended that 10% on mobilisation and site establishment, we’ll release the second 10% tranche.”

Subcontractors

One of the chief sticking points in the kingdom’s projects ecosystem in the past decade has been the capacity and capability of its subcontractors.

The payments crisis in 2017-20 forced many main and general contractors to reduce their permanent labour forces, plant and general resources. Wary of a repeat, most have retained their leaner structure and so have turned increasingly to subcontractors for their manpower and delivery requirements.

In theory, this makes sense, but in practice subcontractors in Saudi Arabia are themselves often overstretched in terms of both delivery capacity and labour availability. In turn, they frequently use their own subcontractors, which then also outsource, to the point that specific elements of a project may be completed by companies very far down the supply chain – with the quality issues that this implies.

Roshn’s solution is to ensure any subcontractor on site goes through a vetting process encompassing quality and financial checks, thereby ensuring it has full visibility on every company on site.

Increasingly, Roshn is dealing with suppliers directly, under supply-install contracts. This can create interfacing issues with the main contractors, however, which are ultimately responsible for the project’s delivery.

“We have to be quite careful on that,” McBride says. “We have to go through all the checks and balances during the prequalification process because if we are going to give a subcontractor to a contractor that we're saying is pre-vetted by Roshn, we could be opening the door to lots of claims from the main contractor against us. So, vetting for us is absolutely crucial.”

Roshn is also working with smaller suppliers and subcontractors to help them evolve and grow, so that they can start taking on smaller main contractor roles themselves.

“Not every construction package we award is in the billions of riyals,” says McBride. “Our thinking is to let the big tier-one contractors focus on the multibillion-riyal deals while we encourage the smaller ones to grow as part of our supplier development programme.”

To achieve this, the developer holds events and bootcamps with its vendors to discuss best practices on subjects including health and safety, variation procedures and how to submit good tender returns.

Roshn is also working with smaller suppliers and subcontractors to help them evolve and grow

Building information modelling

Vendor education also extends to the use of building information modelling (BIM) and other construction technologies.

BIM is mandatory on Roshn’s projects, as it is on the other gigaprojects. While use of the technology is standard across almost all main contractors in the region, its take-up among smaller companies in the supply chain has been slower, with firms pointing to the cost of its adoption and integration as a barrier, as well as the fact that some clients, particularly government ones, view it as providing limited benefit.

Roshn’s task in this area is made difficult because its projects are less complex from an engineering and construction perspective.

“We’re building villas; it’s completely different to building stadiums or airports,” McBride says. “Can these contractors build from [two-dimensional] drawings? Yes, of course they can. You're not going to convince a smaller contractor that all of these benefits will make it easier to build because they know how to build. They've been doing it for decades.

“But the savings are in making it easier to procure, savings in the repeatability, and in the change control. If you upskill yourself on a Roshn project, you are building your capability, which you can then [demonstrate] to other clients as proof you can go after bigger and more complex projects. It's something that the whole industry has to get behind.”

Indeed, there is much to learn from Roshn’s approach to delivering its infrastructure and building plans. While the comparatively straightforward nature of its projects means that its procurement strategies may not be suited to those gigaprojects with more iconic designs, for many other developers it is a case study in efficient processes that have proven effective in delivering work on time and to budget.

This is just as well given that Roshn is set to embark on the next stage of its journey, with its focus on the more complex Marafy city development in Jeddah and Roshn Stadium in Riyadh. However, the evidence suggests that from a procurement strategy perspective, it is well-positioned to also make this a success.



https://image.digitalinsightresearch.in/uploads/NewsArticle/13503828/main.gif
Edward James
Related Articles
  • EtihadWE to auction Al-Zawra power generation assets

    8 June 2026

     

    Register for MEED’s 14-day trial access 

    Etihad Water & Electricity (EtihadWE) is preparing to auction used power generation assets from its Al-Zawra facility in Ajman.

    The 200MW Al-Zawra gas-fired power plant was developed by the former Federal Electricity & Water Authority (Fewa), which was succeeded by EtihadWE.

    The sale includes gas turbines, generators and associated balance-of-plant equipment from the existing generation facility.

    The main equipment being offered comprises two GE Vernova / General Electric heavy-duty gas turbines. The units are PG 9171E / 9E machines designed for dual-fuel operation using natural gas and distillate. The package also includes two generators.

    EtihadWE said the assets will be sold on an “as is, where is” basis, with interested parties able to arrange site visits and inspections, subject to the relevant approvals.

    According to industry sources, the utility’s two power plants in Ajman and Ras Al-Khaimah have been out of service since 2021, and the Ajman plant was decommissioned in 2023. 

    Companies interested in taking part in the auction should contact:
    Mohamed.Shabeer@etihadwe.com
    khaled.reda@etihadwe.ae
    Horizon.PMO@etihadwe.ae
    https://image.digitalinsightresearch.in/uploads/NewsArticle/17143852/main.jpg
    Mark Dowdall
  • Kuwait plans to award $988m upstream contract within 30 days

    8 June 2026

     

    State-owned upstream operator Kuwait Oil Company (KOC) is planning to officially award a $988m project contract to India’s Larsen & Toubro within 30 days, according to industry sources.

    The contract is focused on developing Jurassic Light Oil (JLO) export facilities and upgrading the existing export network.

    Kuwait’s Central Agency for Public Tenders (Capt) has approved the award of the contract for the construction of export crude storage facilities and upgrades to the country’s oil export infrastructure.

    Now, talks are expected to take place between KOC and Larsen & Toubro to finalise the contract details.

    Just two companies submitted bids for the contract in October last year.

    The bidders were:

    • Larsen & Toubro (India): KD303.5m ($988m)
    • Petrofac (UK): KD310.6m ($1.01bn)

    Following bid submission, state-owned Kuwait Petroleum Corporation (KPC) discussed the potential cancellation of the contract tender due to the bids coming in significantly over budget and Petrofac becoming ineligible to win contracts in Kuwait.

    The financially troubled engineering company was temporarily banned from participation in tenders in Kuwait’s oil and gas sector in December last year.

    It was given the ban after the company announced that it had applied to appoint administrators, a move that potentially put thousands of jobs at risk and increased uncertainty for projects worth billions of dollars in the Middle East and North Africa (Mena) region.

    Despite holding talks about the potential cancellation of the tender, KPC ultimately decided to proceed with the contract award process because it considered the project a high priority.

    One source said: “Around the same time, projects worth around $8bn were cancelled because of bids coming in over budget, but this one has gone ahead because KPC sees it as an essential project.”

    The project was originally tendered in November 2024, with a bid deadline of 1 December the same year.

    The bid deadline was extended several times before bids were ultimately submitted.

    Kuwait’s oil and gas sector is in turmoil as a result of the ongoing regional conflict that started on 28 February when the US and Israel attacked Iran.

    Amid the ongoing conflict, Kuwait’s Ministry of Finance has stopped publishing its monthly report with details about revenues from oil exports.

    While there are no official figures available, many experts believe that the country failed to export crude oil during April and May.

    This is likely to have a severe impact on the country’s economy, which relies on oil exports for approximately 90% of government revenues.


    READ THE JUNE 2026 MEED BUSINESS REVIEW – click here to view PDF

    GCC looks beyond the Strait; Iraq’s reform window narrows as fiscal assumptions shatter; MEED Top 100 companies.

    Distributed to senior decision-makers in the region and around the world, the June 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/17143767/main.png
    Wil Crisp
  • Amea Power signs 1.5GWh battery storage EPC contracts

    8 June 2026

    UAE-based Amea Power has signed engineering, procurement and construction (EPC) contracts with China Energy Engineering Corporation (China Energy) for two standalone battery energy storage system (bess) projects in Egypt with a combined capacity of 1,500 megawatt-hours (MWh).

    The contracts cover the 500MWh Horus battery storage project in Zafarana and the 1,000MWh Nefertiti battery storage project in Benban.

    The agreements were signed on 4 June in the presence of Mahmoud Esmat, Egypt’s minister of electricity and renewable energy, Sheikh Hussein Al-Nowais, chairman of Al-Nowais Investments and Amea Power, and Ni Jin, chairman of China Energy.

    The projects are part of Egypt’s wider programme to expand energy storage capacity and support the integration of renewable energy into the national grid.

    According to the Ministry of Electricity & Renewable Energy, Egypt plans to increase battery storage capacity to 14,320MWh by 2028.

    The ministry said the expansion of battery storage is required to support the growing share of solar and wind power generation, improve grid stability and reduce reliance on fossil fuels.

    The signing ceremony also included an agreement between Amea Power, China Energy and Chinese battery manufacturer Gotion to establish a battery storage manufacturing facility in Egypt.

    The planned factory will have an annual production capacity of 3,000MWh.

    Amea Power previously signed capacity purchase agreements with the Egyptian government to develop the country’s first standalone bess projects in 2025.

    In March, the government announced it had signed power-purchase agreements for several renewable energy and battery storage projects with a combined capacity of 5.6GW.

    These include a 900MW wind power project in the Red Sea Governorate, along with a 2,000MW solar power plant and a 2,000MWh battery storage facility in the Qena Governorate. 


    > Be recognised among the best in the industry at the MEED Projects Awards 2026 …

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17143364/main.jpg
    Mark Dowdall
  • Opec+ approves fourth consecutive oil output quota hike

    8 June 2026

    The Opec+ alliance of oil producers has agreed a fourth increase in its oil output targets in as many months, even though the conflict involving Iran, the US and Israel is still preventing several members from pumping more crude.

    The war has disrupted oil flows via the Strait of Hormuz, creating a severe supply crisis. Key Opec+ members, including Saudi Arabia, have been unable to supply customers in full since the end of February. The crisis for Opec+ deepened when the UAE left Opec after almost 60 years of membership.

    Seven core members of Opec+ – which comprises Opec countries and a group of non-Opec states led by Russia – raised their output quotas from April to June by almost 600,000 barrels a day (b/d).

    In practice, however, the group’s production has fallen sharply due to export cuts by Gulf members, averaging 33.19 million b/d in April compared with 42.77 million b/d in February, according to Opec figures.

    At the latest meeting of Opec+ oil ministers on 7 June, the seven members agreed to increase targets by 188,000 b/d from July, Opec said in a statement. This matches the June hike, which was adjusted down from monthly increases of 206,000 b/d in April and May to take account of the UAE’s exit.

    Iraq’s oil output quota will rise by 26,000 b/d from July under the agreement, an oil ministry spokesperson told Iraq’s state news agency.

     

    On 5 June, oil prices fell to about $93 a barrel as traders gained confidence that renewed conflict between the US and Iran was becoming less likely. Prices were close to $72 before the war began on 28 February.

    Brent crude rose sharply at the start of this week after Iran launched ballistic missiles at Israel on the night of 7 June, heightening fears that US-Iran peace talks might once again collapse. Israel has since retaliated with strikes in western and central Iran, despite calls from US President Donald Trump not to respond to the Iranian missiles.

    Brent crude jumped by around 4.5% early on 8 June and was trading at $97.52 a barrel as of 11am GST.

    The seven key Opec+ members are increasing production as part of the gradual unwinding of a 1.65 million b/d production cut agreed in 2023 by the coalition, which at the time included the UAE.

    From July, the seven have about 567,000 b/d of the original cut left to return to the market – taking into account the UAE’s exit from 1 May – according to Reuters calculations.

    That would imply the remainder of the cut will be unwound by the end of September if Opec+ maintains monthly hikes of about 188,000 b/d in August and September.

    The seven of the 21 Opec+ members who met on 7 June were Saudi Arabia, Iraq, Kuwait, Algeria, Kazakhstan, Russia and Oman. In recent years, only these seven – plus the UAE when it was a member– have been involved in the group’s output-policy decisions.

    In a separate meeting on Sunday attended by all Opec+ members, ministers made no change to the group-wide output policy in place until the end of 2026, Opec+ said in another statement.

    Opec+ is also reviewing members’ oil production capacity to use as a reference for 2027 production baselines, from which quotas are set. On Sunday, the group reaffirmed the importance of completing the assessment, the statement said.

    ALSO READ: UAE to continue working with Opec, energy minister says

     


    READ THE JUNE 2026 MEED BUSINESS REVIEW – click here to view PDF

    GCC looks beyond the Strait; Iraq’s reform window narrows as fiscal assumptions shatter; MEED Top 100 companies.

    Distributed to senior decision-makers in the region and around the world, the June 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/17143267/main.jpg
    Indrajit Sen
  • Deme wins dredging work for Tunisian ports

    8 June 2026

    The Office de la Marine Marchande et des Ports (OMMP) has awarded Belgium’s Deme a contract to carry out dredging and marine works at three ports in Tunisia.

    The project covers works at Sousse, Menzel Bourguiba/Bizerte and Rades/La Goulette. Deme will first construct containment dykes at the ports of Menzel Bourguiba and Sousse. The two ports are located more than 200 kilometres apart, which the contractor says will require careful planning, coordination and optimised logistics.

    The second phase involves extensive dredging works at all three locations, for which Deme will deploy a trailing suction hopper dredger.

    The project will use three distinct approaches to sustainably and efficiently manage dredged material, tailored to the characteristics of each location.

    In Sousse and Menzel Bourguiba, the material will be reused for land reclamation. In Bizerte, a combined approach will be adopted, with part of the material used for reclamation at Menzel Bourguiba and the remainder disposed of offshore. In Rades and La Goulette, all dredged material will be pumped ashore to a designated area.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17143268/main.jpg
    Colin Foreman