A case study in procurement

18 March 2025

 

Register for MEED’s 14-day trial access 

While it may not be in the headlines as much as some of its more eye-catching official gigaproject counterparts, Roshn has already delivered thousands of residential units in Saudi Arabia as it seeks to fill the upscale and community living housing map.

Launched in 2020, the Roshn gigaproject is a component of the Vision 2030 plan to achieve 70% home ownership among Saudi nationals by 2030. Alongside the National Housing Company, it is the delivery vehicle for government-backed housing construction as Riyadh seeks to meet the shortfall in available stock.

Its first project was its Sedra community in the north of the capital. Currently on its fourth of eight delivery phases, the multibillion-dollar masterplanned development will comprise 30,000 homes over 20 million square metres (sq m) when completed.

Roshn’s second Riyadh community under construction is Warefa in the northeast of the capital. More compact than Sedra, it will have 2,300 units over an area of 1.4 square kilometres, with 150,000 sq m of green open space.

Three years after the launch of its first projects, Roshn announced Marafy, its first scheme in Jeddah and its largest mixed-use development to date. Designed to accommodate more than 130,000 residents, Marafy will be built around an 11-kilometre, 100-metre-wide canal, linking with Obhur Creek in the northern outskirts of the kingdom’s second city.

Already breaking ground, Marafy’s first core component is the Alarous residential community, which will offer 18,000 units over a 4 million sq m land area.

Elsewhere in the kingdom, Roshn’s other planned community projects include Almanar in Mecca, Alfulwa in Hofuf and Aldanah in Dhahran. Between them, these schemes total more than 50,000 units. It is expected that thousands of additional homes in other parts of the kingdom will be announced by the developer in the next two years.

Delivering such projects at many different locations is a complex exercise, requiring procurement strategies that not only encompass on-time and on-budget completion, but also ensure that local content is maximised while at the same time maintaining stringent quality standards.

Tasked with handling Roshn’s overall procurement strategy is Iain McBride, the gigaproject developer’s head of commercial.

It is expected that thousands of additional homes in other parts of the kingdom will be announced by the developer in the next two years

Like other gigaprojects in the kingdom, McBride and his procurement team have had to deal with the twin challenges of soaring cost inflation and maximising local content in materials and equipment.

The five official gigaprojects – Diriyah, Neom, the Red Sea Project, Qiddiya and Roshn – are free to employ their own procurement rules and processes, and each has taken a different approach to address its specific requirements. For example, Red Sea Global uses a construction management approach wherein it contracts directly with companies and suppliers that would normally work as subcontractors under the main contractors.

Similarly, Diriyah Company employs a strategy of bundling several smaller contract packages into a single large contract, as a means of consolidating work to ensure lower costs and maintain contractor interest.


Hear directly from the gigaproject owners at the biggest construction event – The Saudi Gigaprojects 2025 Summit, happening in Riyadh from 12-14 May 2025. Click here to know more


Demand signalling

The nature of Roshn’s mainly residential projects means that from the outset it knew it would need thousands of items with similar specifications, such as doors; glass panes; sanitaryware; and heating, ventilation and air-conditioning systems.

To secure this supply chain, early on the company identified local manufacturers of these products and reached long-term agreements with them for the delivery of required materials.

“Our first step was signing a lot of long-term partnership agreements through master purchase agreements where we could leverage preferential rates,” says McBride, speaking to MEED in late January.

“Ultimately, it's all about balance and risk – derisking the opportunities for the supply chain by telling them how many doors, for example, we're going to need each quarter for the next five to 10 years. It gives confidence to the manufacturers that they can start committing to.”

Roshn was the first of the gigaprojects to publicly signal its demand requirements. In 2021, it announced that it would require at least 5 million doors, 3.5 million air-conditioning units, 4.3 million windows, 80 million sq m of tiles and 6.5 million pieces of sanitaryware. These numbers have since changed, but they are indicative of the scale of the supply chain challenge.

Armed with the knowledge that Roshn is both supported by its parent, sovereign wealth vehicle the Public Investment Fund (PIF), and that it is a central element of Saudi Vision 2030, local manufacturers had the confidence to commit to investing in production capacity to meet its needs.

Significantly, most of these deals have been with manufacturers within the kingdom, thereby maximising the local content aspects. Just as importantly, Roshn has not had to make any fixed orders – so-called ‘take-or-pay agreements’ – with  suppliers, such is the latter’s faith in the developer.

“For the time being, we’ve not had to make any firm commitments,” says McBride. “We did look at it at one point, but our approach has always been to keep it as simple as possible by listening to the supply chain and seeing what they need. When we were speaking to them, it wasn’t their number one driver; they weren’t screaming at us saying, ‘We need you to give us a firm order’.

“Now, many people think a take-or-pay agreement is essential – where you commit to ordering [a certain quantity] of materials over a period of months or years and, if you don’t, you have to pay a penalty, thereby adding risk and complexity for the developer.

“What we were able to agree instead was that we'll be open and transparent with [the suppliers about] what we need. We said to ourselves, ‘Let's get a good price that works, whether we buy directly from the supplier or whether we include that supplier within our tenders with major contractors’. And we’ve seen great success with that approach, with multiple companies.”

The localisation push is supported by the design process. Wherever possible, the designs for Roshn’s projects incorporate and specify equipment and materials that are known to be manufactured locally.

There have been instances where specific, specialised materials and products are not produced in the kingdom, or not in the quantities required, such as marble and certain architectural facades.

Where this is the case, Roshn is keen to explore how it can help to build in-kingdom capacity. The developer has initiatives through which it looks to co-invest in production facilities that come with high capital requirements.

As McBride explains, Roshn is only one part of the huge and rapidly accelerating Saudi projects market ecosystem, and in helping to increase capacity, it is also putting itself in a position to help other developers with their supply chain needs.

A case in point is Roshn’s contract with China Harbour Engineering Company, which was awarded the $2bn deal in 2023 to build villas at Sedra and Warefa.  

Part of the contract requires the Chinese contractor to set up a precast manufacturing facility on site at Sedra. In this way, Roshn could not only ringfence the plant for its own needs, but when it no longer requires the output, other projects could benefit from its production capacity.

“The factory has a 15-year lifespan, so any additional capacity will be there for another 10 years after our requirements are met,” says McBride. “In Riyadh, we have Expo 2030, the new airport, the stadiums and many other projects that could draw on its output.”

There are some situations where even this is not enough, particularly when it comes to contracting expertise. One such case is Roshn’s mandate to develop a 45,000-seat stadium in the southwest of Riyadh as part of the kingdom’s Fifa World Cup 2034 plans. On such a complex, highly engineered project, Roshn has insisted that an international contractor teams up with a local company as a condition of tender participation.

This insistence is based on Roshn’s experience overseeing the construction of a football stadium in Dammam alongside co-developer, Saudi Aramco. The project, which is being built by a joint venture of Belgium’s Besix and the local Albawani, is proceeding at a rapid pace and progress has been relatively trouble-free.

McBride says: “If we have to go abroad, let’s go abroad. But make sure it’s done in a smart way and that we’re not just throwing money out of the kingdom.”

Early contractor involvement

On the issue of contracting, it is well known that the massive amount of work in Saudi Arabia is stretching contractors to the limit, pushing up prices and straining labour, engineering and equipment resources.

Roshn’s approach to this challenge has been to engage with contractors at the earliest possible stage of project planning, specifically at the design phase, through an early contractor involvement (ECI) procurement framework. In this way, the company is able to obtain contractor feedback during concept and design and subsequently lower construction risk by improving a project’s constructability.

“It's about signposting the demand by getting the contractor in early, where you can really influence the design, the buildability and the value-engineering opportunities,” says McBride. “Ideally, we bring them in as quickly as possible during the concept stages, when there's very little cost to changing things.

“The worst thing for a contractor is receiving a [request for proposal] cold. They have to … come back in four weeks and then be squeezed for a best price, whereas with ECI they can add value. They really appreciate that.”

When asked to quantify the cost benefits of such an approach, McBride is forthright: “It’s not even a case of doing the maths,” he says. “We have a great example of where it’s worked on our Aldanah project in Dammam. We selected the contract very early on and locked in the floor plans and facades that we wanted. We were then able to deliver a street of 10 show homes [that took] not much more than four months to design and construct.

“The saving, in terms of time, was massive; we probably halved the duration. I probably wouldn’t be exaggerating if I said it saved about a year.

“There are two ways you can follow your engineer,” he continues. “One: you can follow them early and make sure that the way you're looking to save costs is in areas that are not impacting the customer.

“Or two: the worst thing you can do is get to the end and you have a full structural design that could be over-engineered and you’re spending money in the wrong places.

“We don’t want to get to a point where we're trying to value-engineer by cutting things out that are important to customers,” McBride explains. “And that's what you avoid by having this early contractor involvement.”

The company is able to obtain contractor feedback during concept and design and subsequently lower construction risk by improving a project’s constructability

Unlike the other gigaprojects, Roshn has been in the favourable position of being able to raise some revenue by marketing and selling its properties off plan. While this has been beneficial from a development perspective, it has also meant that the developer must get its pricing and housing specifications right if it is to develop homes within an already-defined budget.

Having a contracting partner on board during the design and specification stage facilitates the conversation between the property sales team, which is informing on market requirements, and the builder, who can deliver within the designed cost and quality parameters.

This is in contrast to many real estate developments for which sales are completed before the construction estimates come in, potentially undermining the business case.

The step beyond ECI is for contractors and suppliers to partner with Roshn to inject equity into the projects by acting as co-developers. McBride points to several planned mid-rise towers at Marafy that could be a starting point for this.

Contractors financing projects or bringing in replacement equity has long been an ambition in the region, but builders have been reluctant to adopt this approach. Nonetheless, McBride is confident that it could happen, indicating that there has already been strong interest from the contracting community.

Cost inflation

Another major talking point in Saudi construction is the escalating costs caused by high inflation, logistical challenges and a tightening of contracting and skilled labour capacity.

In many cases, this has required the rescoping of projects, revisions to timelines and even the scrapping of elements. Neom is arguably the best example of this, as it has reprioritised The Line and is facing an estimated cost of $50bn for building each of its first three modules – far in excess of original estimates.

Roshn’s approach to the challenge is to be as open and transparent as possible with the contractor and supplier community. This has involved outlining a long-term pipeline of work that gives the supply chain confidence about its requirements, enabling them to fix in long-term pricing structures. In return, the developer expects prices to come in competitively.

“It’s no secret within the supply chain market that Roshn has quite aggressive price points,” says McBride, a former chartered surveyor who, prior to joining Roshn, worked as a quantity surveyor and cost-management director at consultants Faithful+Gould (now AtkinsRealis) and Rider Levett Bucknall.

“What we're trying to do is engage early, build trust with the contractors, let them see we’re a good client that's going to pay and have honest and fair contracting terms, and work together to try and solve issues post-contract.

“We don't mind if there's inflationary pressures because of commodity prices increasing. But what we're trying to avoid is inflationary prices through just the demand increasing.

“An innovative way that we've implemented this even on our lump-sum contracts – our traditional Redbook or older contracts – is that we have preferred supplier agreement clauses in them,” he adds.

“So, rather than a traditional bill of quantities (BoQ) that has a rate, a quantity, a total, within our rate section we have the material supply rate, the installation rate and then everything else, such as overhead profit. We protect the installation rate, so it's not a percentage of the material; it's a fixed SR100 a square metre to install, for example.

“One of the big frustrations for contractors is [that the supplier has] a material we think they're going to deliver. It's maybe not available, so they submit alternative materials. The client keeps rejecting it – it's not what they want – and it becomes a delay; it's painful.”

McBride gives the example of a pre-approved bathroom sink. Thanks to Roshn’s relationships with key long-term suppliers, the company is able to negotiate better rates for sanitaryware than would be available to a contractor on an ad hoc basis. If the developer’s rates for sinks are better than the BoQ, it splits the savings 50:50 with the contractor.

“The contractors are winning out of that exercise, we're winning out of it and, ultimately, the customers are winning out of it as well, because we’re passing on those savings,” says McBride.

Flexibility

The benefits to contractors and suppliers extend to payment terms. In today’s sellers’ market, vendors are effectively able to pick and choose the clients they want to work for. As a result, clients – including the gigaprojects – have had to introduce more flexible payment terms and develop market reputations for paying on time.

Roshn may lead the pack on this, with an average payment time from invoice to payment of just 13 days in 2024. A decade ago, this would have been unheard of, but it is now increasingly becoming the norm among the gigaprojects.

In addition, like its PIF peers, Roshn has done away with tender fees and tender bonds, viewing them as outdated means of enforcing vendor participation, especially given the tight liquidity and cashflow situation in the projects market in Saudi Arabia.

Will such flexibility ever extend to performance bonds? McBride is sceptical, pointing to the fact that Roshn’s strong relationship with local banks allows to it facilitate credit agreements between contractors and their lenders. Being a gigaproject developer supported by the PIF – and by tacit extension the state – also helps provide the underlining ease of mind for financers.

Nonetheless, Roshn also takes a proactive approach with advanced payments, enabling up to 20% of the total contract value at the initial stage of the project.

“We've been quite clever in how we do this,” says McBride. “We don't go and release 20% straight away. We’ll do 10% and then, when we’ve evidence that you’ve expended that 10% on mobilisation and site establishment, we’ll release the second 10% tranche.”

Subcontractors

One of the chief sticking points in the kingdom’s projects ecosystem in the past decade has been the capacity and capability of its subcontractors.

The payments crisis in 2017-20 forced many main and general contractors to reduce their permanent labour forces, plant and general resources. Wary of a repeat, most have retained their leaner structure and so have turned increasingly to subcontractors for their manpower and delivery requirements.

In theory, this makes sense, but in practice subcontractors in Saudi Arabia are themselves often overstretched in terms of both delivery capacity and labour availability. In turn, they frequently use their own subcontractors, which then also outsource, to the point that specific elements of a project may be completed by companies very far down the supply chain – with the quality issues that this implies.

Roshn’s solution is to ensure any subcontractor on site goes through a vetting process encompassing quality and financial checks, thereby ensuring it has full visibility on every company on site.

Increasingly, Roshn is dealing with suppliers directly, under supply-install contracts. This can create interfacing issues with the main contractors, however, which are ultimately responsible for the project’s delivery.

“We have to be quite careful on that,” McBride says. “We have to go through all the checks and balances during the prequalification process because if we are going to give a subcontractor to a contractor that we're saying is pre-vetted by Roshn, we could be opening the door to lots of claims from the main contractor against us. So, vetting for us is absolutely crucial.”

Roshn is also working with smaller suppliers and subcontractors to help them evolve and grow, so that they can start taking on smaller main contractor roles themselves.

“Not every construction package we award is in the billions of riyals,” says McBride. “Our thinking is to let the big tier-one contractors focus on the multibillion-riyal deals while we encourage the smaller ones to grow as part of our supplier development programme.”

To achieve this, the developer holds events and bootcamps with its vendors to discuss best practices on subjects including health and safety, variation procedures and how to submit good tender returns.

Roshn is also working with smaller suppliers and subcontractors to help them evolve and grow

Building information modelling

Vendor education also extends to the use of building information modelling (BIM) and other construction technologies.

BIM is mandatory on Roshn’s projects, as it is on the other gigaprojects. While use of the technology is standard across almost all main contractors in the region, its take-up among smaller companies in the supply chain has been slower, with firms pointing to the cost of its adoption and integration as a barrier, as well as the fact that some clients, particularly government ones, view it as providing limited benefit.

Roshn’s task in this area is made difficult because its projects are less complex from an engineering and construction perspective.

“We’re building villas; it’s completely different to building stadiums or airports,” McBride says. “Can these contractors build from [two-dimensional] drawings? Yes, of course they can. You're not going to convince a smaller contractor that all of these benefits will make it easier to build because they know how to build. They've been doing it for decades.

“But the savings are in making it easier to procure, savings in the repeatability, and in the change control. If you upskill yourself on a Roshn project, you are building your capability, which you can then [demonstrate] to other clients as proof you can go after bigger and more complex projects. It's something that the whole industry has to get behind.”

Indeed, there is much to learn from Roshn’s approach to delivering its infrastructure and building plans. While the comparatively straightforward nature of its projects means that its procurement strategies may not be suited to those gigaprojects with more iconic designs, for many other developers it is a case study in efficient processes that have proven effective in delivering work on time and to budget.

This is just as well given that Roshn is set to embark on the next stage of its journey, with its focus on the more complex Marafy city development in Jeddah and Roshn Stadium in Riyadh. However, the evidence suggests that from a procurement strategy perspective, it is well-positioned to also make this a success.



https://image.digitalinsightresearch.in/uploads/NewsArticle/13503828/main.gif
Edward James
Related Articles
  • Bahrain extends deadline for Hawar Island water station

    25 November 2025

    Bahrain’s Electricity & Water Authority (Ewa) has extended the bid submission deadline for the main contract to build a new water distribution station on Hawar Island.

    The deadline, initially set for 23 November, has been moved to 7 December. 

    The $15m project covers the construction of two steel ground storage tanks with a capacity of one million gallons each, pumping stations, motors, pipelines and associated facilities.

    The scheme forms a key part of Bahrain’s wider plans to develop Hawar Island, which currently has limited utility infrastructure and relies on water transported from the mainland.

    The government is advancing tourism-led investment on the island, including eco-resorts and hospitality developments that require reliable potable water supplies.

    The tender is linked to Ewa’s ongoing procurement for a new seawater reverse osmosis (SWRO) desalination plant on Hawar.

    The engineering, procurement and construction contract for the SWRO facility, designed to produce one million imperial gallons a day, is currently out to tender, with bids due on 30 November.

    According to Ewa, the desalination plant will connect with two related contracts.

    One of these covers the construction of the new water distribution station, while the second covers offshore seawater intake and outfall systems.

    The main desalination contractor will be required to ensure its design and construction align with these works so that all three components function together as one integrated system.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/15149229/main.jpg
    Mark Dowdall
  • November 2025: Data drives regional projects

    25 November 2025

    Click here to download the PDF

    Includes: Top 10 global contractors | Brent Spot Price | Construction output

     MEED's 2025 EPC contractor ranking


    MEED’s December 2025 report on Bahrain includes:

    > COMMENT: Manama pursues reform amid strain
    > GVT & ECONOMY: Bahrain’s cautious economic evolution

    > BANKING: Mergers loom over Bahrain’s banking system
    > OIL & GAS: Bahrain remains in pursuit of hydrocarbon resources
    > POWER & WATER: Bahrain advances utility reform
    > CONSTRUCTION: Bahrain construction faces major slowdown
    > TRANSPORT: Air Asia aviation deal boosts connectivity

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/15149339/main.gif
    MEED Editorial
  • Bahrain pursues reform amid strain

    25 November 2025

    Commentary
    John Bambridge
    Analysis editor

    Cautious optimism defines Bahrain’s current economic moment as the country presses ahead with a broad agenda of diversification, reform and targeted investment. Yet the more assertively Manama moves to reshape its future, the more the tension between its ambition and its fiscal constraints becomes evident as the defining feature of its policymaking.

    Bahrain’s projects sector, which has now been shrinking for the past seven years, is emblematic of the country’s constricted spending. This year, contract awards have fallen to their lowest value in a decade. This signals a decisive shift to a more disciplined investment strategy aligned with fiscal realities and a more selective approach to forward-looking capital spending. 

    The diminished projects market is in turn a challenge for the financial sector, which now faces a receding pool of project financing and other contracting loans. This is giving further impetus to the potential consolidation of local lenders in the overbanked market, which is also beset by thinning margins, rising compliance costs and pressure to scale amid financial system modernisation. While it could create short-term pain, consolidation should boost the financial health of legacy lenders and provide stability in a sector increasingly being defined by new digital banking models and innovation.

    Yet even as some sectors change, Bahrain’s government remains deeply reliant on hydrocarbons, which continues to drive exploration, including in the technically complex Khaleej Al-Bahrain basin. These activities reflect the practical need to maintain oil revenues in the medium term and, should additional recoverable reserves be discovered, a potent source of optimism.

    Manana is meanwhile looking to overhaul the utilities sector by creating a dedicated regulator and new national operator. The reforms should make space for greater private participation, drawing more capital into power and water projects while improving efficiency and reducing state expenditure in an aspirationally positive step towards greater long-term sustainability.

    Even as fiscal concerns narrow Manama’s policy options, it continues to secure strategic wins. A new aviation agreement with Air Asia establishes Bahrain as a regional hub for one of Asia’s largest low-cost carriers. This move opens new connectivity corridors and, alongside the renewal of direct Gulf Air routes to the US, reinforces Bahrain’s position as a gateway between regions, promising benefits for tourism, logistics and services.

    Overall, Bahrain’s economic trajectory remains delicately balanced – marked by reform-driven progress yet tempered by fiscal constraint. But in threading this needle, Manama shows that cautious optimism can still be a powerful catalyst for change.

     


    MEED’s December 2025 report on Bahrain includes:

    > GVT & ECONOMY: Bahrain’s cautious economic evolution
    > BANKING: Mergers loom over Bahrain’s banking system
    > OIL & GAS: Bahrain remains in pursuit of hydrocarbon resources
    > POWER & WATER: Bahrain advances utility reform
    > CONSTRUCTION: Bahrain construction faces major slowdown
    > AVIATION: Bahrain signs game-changer aviation deal with Air Asia

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/15109785/main.gif
    John Bambridge
  • Chinese firms expand oil and gas presence

    25 November 2025

     

    > This package also includes: Larsen & Toubro climbs EPC contractor ranking


    Chinese contractors have been present in the oil and gas projects market in the Middle East and North Africa (Mena) region since the turn of this century, but largely remained on the fringes. In a hydrocarbons market that has traditionally been dominated by European and American contractors, and those from Japan and South Korea, Chinese firms have become a rising force, especially since the start of the decade.

    Economic competitiveness in bid battles, significant improvement in engineering and technological capabilities and commitment to execution schedules have been primary factors behind the success of Chinese contractors in the regional oil and gas projects market since 2020.

    Competitive edge

    Traditionally, Chinese engineering, procurement and construction (EPC) contractors have enjoyed a lower cost base than their international competitors. This comes from lower manpower costs, access to cheaper materials and equipment, and financial support from state banks. 

    In addition, Chinese firms have typically had a different attitude to risk than many other contractors. Instead of seeking to turn a profit on specific projects, Chinese firms have entered markets cautiously and, as their knowledge of the local market grew, built a commanding long-term position.

    More recently, the edge that Chinese contractors enjoy has come from the technical experience they have gained from delivering large-scale, complex projects in their domestic market. While in the past Chinese contractors were only considered capable of delivering basic construction work, they now have some of the best project references in the world.

    Regional leaders

    Chinese EPC contractors have strengthened their performance in the Mena oil and gas projects market, particularly since the end of the Covid-19 pandemic. Since 2023, the combined value of projects won by Chinese firms has consistently remained well over $13bn, with them winning key contracts on major projects.

    The largest EPC scheme under execution by a Chinese contractor in the region is on a project to maintain and increase the oil production potential of the Bul Hanine offshore oil field development in Qatar. China Offshore Oil Engineering Company won contracts worth $4bn for the two main EPC packages of the project in the third quarter of 2025.

    Also this year, Abu Dhabi’s Taziz awarded the main EPC contract to build a complex of specialty chemicals plants in the Taziz Industrial Chemicals Zone at Ruwais Industrial City to China National Chemical Engineering & Construction Corporation Seven (CC7). 

    The EPC contract is valued at $1.99bn, with work expected to be completed by Q4 2028. The chemicals cluster, known as Project Salt, will produce 1.9 million tonnes a year of marketable polyvinyl chloride (PVC), ethylene dichloride (EDC), vinyl chloride monomer (VCM) and caustic soda.

    Chinese contractors have also enjoyed success in Saudi Arabia, with Aramco having awarded several key EPC contracts to Chinese firms since 2023. China Petroleum Engineering & Construction Company, Sepco and Sinopec Petroleum Services are executing EPC works on four out of the 17 packages of the third expansion phase of Aramco’s Master Gas System project.

    Sinopec Group has played a significant role in Aramco’s Jafurah unconventional gas development in Saudi Arabia. In a consortium with Spanish contractor Tecnicas Reunidas, in 2024 Sinopec won packages one and two of the Riyas natural gas liquids scheme, part of the second Jafurah unconventional gas expansion phase. The combined value of the two EPC contracts was $3.2bn.

    Just weeks after securing these EPC contracts, the consortium also won the contract to deliver the entire scope of work on the scheme’s third expansion phase, valued at $2.24bn.

    In Iraq, China Petroleum Engineering (CPE) won a major contract in August to carry out EPC works on a package covering a major seawater transmission pipeline to be built in Basra as part of the larger Common Seawater Supply Project, which is one of four main components of the estimated $10bn Gas Growth Integrated Project masterplan.

    Work on the $2.52bn contract will be carried out by CPE’s engineering arm, China Petroleum Pipeline Engineering.

    China has built up extensive resources, from skilled personnel to technical know-how. As the domestic market shows signs of slowing, these resources are being deployed internationally, supporting the growing presence of Chinese contractors in the Mena region.

    MEED's 2025 EPC contractor ranking

    https://image.digitalinsightresearch.in/uploads/NewsArticle/15149182/main.gif
    Indrajit Sen
  • Ineco appointed for Spain-Morocco tunnel study

    25 November 2025

    Spanish engineering firm Ineco has been commissioned to conduct an exploratory tunnel study to validate the feasibility of the railway connection linking Spain and Morocco.

    According to reports in Spanish media, the $1m contract will establish a detailed technical roadmap for the project.

    Ineco’s scope of work includes the preliminary design of the exploratory tunnel, revisions to previous studies, and a comprehensive update of the route, geology, geotechnical conditions, security systems, terminals and associated installations.

    Ineco will validate the critical geological conditions of the Strait, particularly in the areas where the project’s greatest risks are located.

    The study is expected to be completed by August next year.

    The latest development comes after German company Herrenknecht completed its study in October. Herrenknecht said it found the project feasible to undertake due to the availability of the technology needed to execute it.

    The media reports added that clients will further study the project and make a final decision in 2027 regarding tendering.

    Recent developments

    MEED reported in August that Ineco had secured an estimated €350,000 ($409,000) contract to carry out a financial feasibility study for the proposed infrastructure.

    UK-based Vodafone also won a contract to provide advanced telecommunications support to teams working on the project.

    These developments followed the appointment of Herrenknecht in January for a €296,400 ($307,483) contract to conduct a drilling feasibility study.

    The Spanish government revived the Morocco-Spain undersea rail link in June last year, after allocating about $2.5m for a renewed design study.

    Project background

    The project, originally launched in 2003, was put on hold following the 2008 financial crisis. It has undergone several rounds of feasibility studies, but remains in the planning phase after nearly two decades of funding-related delays.

    The proposed design includes a double-track railway and a service tunnel extending 38.5 kilometres (km) between Tarifa in Spain and Tangier in Morocco. Of this, 28km will run beneath the Mediterranean Sea at a maximum depth of 475 metres.

    Each single-track tunnel will have an inner diameter of 7.9 metres, while the service gallery will be 6 metres in diameter.

    The project is being jointly developed by Morocco’s National Society for Strait of Gibraltar Studies and Spain’s Sociedad Espanola de Estudios para la Comunicacion Fija a Traves del Estrecho de Gibraltar.

    In 2006, Swiss engineering firm Lombardi Engineering was selected to design the tunnel. Preliminary studies were completed two years later.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/15148660/main.jpg
    Yasir Iqbal