A case study in procurement
18 March 2025

Register for MEED’s 14-day trial access
While it may not be in the headlines as much as some of its more eye-catching official gigaproject counterparts, Roshn has already delivered thousands of residential units in Saudi Arabia as it seeks to fill the upscale and community living housing map.
Launched in 2020, the Roshn gigaproject is a component of the Vision 2030 plan to achieve 70% home ownership among Saudi nationals by 2030. Alongside the National Housing Company, it is the delivery vehicle for government-backed housing construction as Riyadh seeks to meet the shortfall in available stock.
Its first project was its Sedra community in the north of the capital. Currently on its fourth of eight delivery phases, the multibillion-dollar masterplanned development will comprise 30,000 homes over 20 million square metres (sq m) when completed.
Roshn’s second Riyadh community under construction is Warefa in the northeast of the capital. More compact than Sedra, it will have 2,300 units over an area of 1.4 square kilometres, with 150,000 sq m of green open space.
Three years after the launch of its first projects, Roshn announced Marafy, its first scheme in Jeddah and its largest mixed-use development to date. Designed to accommodate more than 130,000 residents, Marafy will be built around an 11-kilometre, 100-metre-wide canal, linking with Obhur Creek in the northern outskirts of the kingdom’s second city.
Already breaking ground, Marafy’s first core component is the Alarous residential community, which will offer 18,000 units over a 4 million sq m land area.
Elsewhere in the kingdom, Roshn’s other planned community projects include Almanar in Mecca, Alfulwa in Hofuf and Aldanah in Dhahran. Between them, these schemes total more than 50,000 units. It is expected that thousands of additional homes in other parts of the kingdom will be announced by the developer in the next two years.
Delivering such projects at many different locations is a complex exercise, requiring procurement strategies that not only encompass on-time and on-budget completion, but also ensure that local content is maximised while at the same time maintaining stringent quality standards.
Tasked with handling Roshn’s overall procurement strategy is Iain McBride, the gigaproject developer’s head of commercial.
It is expected that thousands of additional homes in other parts of the kingdom will be announced by the developer in the next two years
Like other gigaprojects in the kingdom, McBride and his procurement team have had to deal with the twin challenges of soaring cost inflation and maximising local content in materials and equipment.
The five official gigaprojects – Diriyah, Neom, the Red Sea Project, Qiddiya and Roshn – are free to employ their own procurement rules and processes, and each has taken a different approach to address its specific requirements. For example, Red Sea Global uses a construction management approach wherein it contracts directly with companies and suppliers that would normally work as subcontractors under the main contractors.
Similarly, Diriyah Company employs a strategy of bundling several smaller contract packages into a single large contract, as a means of consolidating work to ensure lower costs and maintain contractor interest.
Hear directly from the gigaproject owners at the biggest construction event – The Saudi Gigaprojects 2025 Summit, happening in Riyadh from 12-14 May 2025. Click here to know more
Demand signalling
The nature of Roshn’s mainly residential projects means that from the outset it knew it would need thousands of items with similar specifications, such as doors; glass panes; sanitaryware; and heating, ventilation and air-conditioning systems.
To secure this supply chain, early on the company identified local manufacturers of these products and reached long-term agreements with them for the delivery of required materials.
“Our first step was signing a lot of long-term partnership agreements through master purchase agreements where we could leverage preferential rates,” says McBride, speaking to MEED in late January.
“Ultimately, it's all about balance and risk – derisking the opportunities for the supply chain by telling them how many doors, for example, we're going to need each quarter for the next five to 10 years. It gives confidence to the manufacturers that they can start committing to.”
Roshn was the first of the gigaprojects to publicly signal its demand requirements. In 2021, it announced that it would require at least 5 million doors, 3.5 million air-conditioning units, 4.3 million windows, 80 million sq m of tiles and 6.5 million pieces of sanitaryware. These numbers have since changed, but they are indicative of the scale of the supply chain challenge.
Armed with the knowledge that Roshn is both supported by its parent, sovereign wealth vehicle the Public Investment Fund (PIF), and that it is a central element of Saudi Vision 2030, local manufacturers had the confidence to commit to investing in production capacity to meet its needs.
Significantly, most of these deals have been with manufacturers within the kingdom, thereby maximising the local content aspects. Just as importantly, Roshn has not had to make any fixed orders – so-called ‘take-or-pay agreements’ – with suppliers, such is the latter’s faith in the developer.
“For the time being, we’ve not had to make any firm commitments,” says McBride. “We did look at it at one point, but our approach has always been to keep it as simple as possible by listening to the supply chain and seeing what they need. When we were speaking to them, it wasn’t their number one driver; they weren’t screaming at us saying, ‘We need you to give us a firm order’.
“Now, many people think a take-or-pay agreement is essential – where you commit to ordering [a certain quantity] of materials over a period of months or years and, if you don’t, you have to pay a penalty, thereby adding risk and complexity for the developer.
“What we were able to agree instead was that we'll be open and transparent with [the suppliers about] what we need. We said to ourselves, ‘Let's get a good price that works, whether we buy directly from the supplier or whether we include that supplier within our tenders with major contractors’. And we’ve seen great success with that approach, with multiple companies.”
The localisation push is supported by the design process. Wherever possible, the designs for Roshn’s projects incorporate and specify equipment and materials that are known to be manufactured locally.
There have been instances where specific, specialised materials and products are not produced in the kingdom, or not in the quantities required, such as marble and certain architectural facades.
Where this is the case, Roshn is keen to explore how it can help to build in-kingdom capacity. The developer has initiatives through which it looks to co-invest in production facilities that come with high capital requirements.
As McBride explains, Roshn is only one part of the huge and rapidly accelerating Saudi projects market ecosystem, and in helping to increase capacity, it is also putting itself in a position to help other developers with their supply chain needs.
A case in point is Roshn’s contract with China Harbour Engineering Company, which was awarded the $2bn deal in 2023 to build villas at Sedra and Warefa.
Part of the contract requires the Chinese contractor to set up a precast manufacturing facility on site at Sedra. In this way, Roshn could not only ringfence the plant for its own needs, but when it no longer requires the output, other projects could benefit from its production capacity.
“The factory has a 15-year lifespan, so any additional capacity will be there for another 10 years after our requirements are met,” says McBride. “In Riyadh, we have Expo 2030, the new airport, the stadiums and many other projects that could draw on its output.”
There are some situations where even this is not enough, particularly when it comes to contracting expertise. One such case is Roshn’s mandate to develop a 45,000-seat stadium in the southwest of Riyadh as part of the kingdom’s Fifa World Cup 2034 plans. On such a complex, highly engineered project, Roshn has insisted that an international contractor teams up with a local company as a condition of tender participation.
This insistence is based on Roshn’s experience overseeing the construction of a football stadium in Dammam alongside co-developer, Saudi Aramco. The project, which is being built by a joint venture of Belgium’s Besix and the local Albawani, is proceeding at a rapid pace and progress has been relatively trouble-free.
McBride says: “If we have to go abroad, let’s go abroad. But make sure it’s done in a smart way and that we’re not just throwing money out of the kingdom.”
Early contractor involvement
On the issue of contracting, it is well known that the massive amount of work in Saudi Arabia is stretching contractors to the limit, pushing up prices and straining labour, engineering and equipment resources.
Roshn’s approach to this challenge has been to engage with contractors at the earliest possible stage of project planning, specifically at the design phase, through an early contractor involvement (ECI) procurement framework. In this way, the company is able to obtain contractor feedback during concept and design and subsequently lower construction risk by improving a project’s constructability.
“It's about signposting the demand by getting the contractor in early, where you can really influence the design, the buildability and the value-engineering opportunities,” says McBride. “Ideally, we bring them in as quickly as possible during the concept stages, when there's very little cost to changing things.
“The worst thing for a contractor is receiving a [request for proposal] cold. They have to … come back in four weeks and then be squeezed for a best price, whereas with ECI they can add value. They really appreciate that.”
When asked to quantify the cost benefits of such an approach, McBride is forthright: “It’s not even a case of doing the maths,” he says. “We have a great example of where it’s worked on our Aldanah project in Dammam. We selected the contract very early on and locked in the floor plans and facades that we wanted. We were then able to deliver a street of 10 show homes [that took] not much more than four months to design and construct.
“The saving, in terms of time, was massive; we probably halved the duration. I probably wouldn’t be exaggerating if I said it saved about a year.
“There are two ways you can follow your engineer,” he continues. “One: you can follow them early and make sure that the way you're looking to save costs is in areas that are not impacting the customer.
“Or two: the worst thing you can do is get to the end and you have a full structural design that could be over-engineered and you’re spending money in the wrong places.
“We don’t want to get to a point where we're trying to value-engineer by cutting things out that are important to customers,” McBride explains. “And that's what you avoid by having this early contractor involvement.”
The company is able to obtain contractor feedback during concept and design and subsequently lower construction risk by improving a project’s constructability
Unlike the other gigaprojects, Roshn has been in the favourable position of being able to raise some revenue by marketing and selling its properties off plan. While this has been beneficial from a development perspective, it has also meant that the developer must get its pricing and housing specifications right if it is to develop homes within an already-defined budget.
Having a contracting partner on board during the design and specification stage facilitates the conversation between the property sales team, which is informing on market requirements, and the builder, who can deliver within the designed cost and quality parameters.
This is in contrast to many real estate developments for which sales are completed before the construction estimates come in, potentially undermining the business case.
The step beyond ECI is for contractors and suppliers to partner with Roshn to inject equity into the projects by acting as co-developers. McBride points to several planned mid-rise towers at Marafy that could be a starting point for this.
Contractors financing projects or bringing in replacement equity has long been an ambition in the region, but builders have been reluctant to adopt this approach. Nonetheless, McBride is confident that it could happen, indicating that there has already been strong interest from the contracting community.
Cost inflation
Another major talking point in Saudi construction is the escalating costs caused by high inflation, logistical challenges and a tightening of contracting and skilled labour capacity.
In many cases, this has required the rescoping of projects, revisions to timelines and even the scrapping of elements. Neom is arguably the best example of this, as it has reprioritised The Line and is facing an estimated cost of $50bn for building each of its first three modules – far in excess of original estimates.
Roshn’s approach to the challenge is to be as open and transparent as possible with the contractor and supplier community. This has involved outlining a long-term pipeline of work that gives the supply chain confidence about its requirements, enabling them to fix in long-term pricing structures. In return, the developer expects prices to come in competitively.
“It’s no secret within the supply chain market that Roshn has quite aggressive price points,” says McBride, a former chartered surveyor who, prior to joining Roshn, worked as a quantity surveyor and cost-management director at consultants Faithful+Gould (now AtkinsRealis) and Rider Levett Bucknall.
“What we're trying to do is engage early, build trust with the contractors, let them see we’re a good client that's going to pay and have honest and fair contracting terms, and work together to try and solve issues post-contract.
“We don't mind if there's inflationary pressures because of commodity prices increasing. But what we're trying to avoid is inflationary prices through just the demand increasing.
“An innovative way that we've implemented this even on our lump-sum contracts – our traditional Redbook or older contracts – is that we have preferred supplier agreement clauses in them,” he adds.
“So, rather than a traditional bill of quantities (BoQ) that has a rate, a quantity, a total, within our rate section we have the material supply rate, the installation rate and then everything else, such as overhead profit. We protect the installation rate, so it's not a percentage of the material; it's a fixed SR100 a square metre to install, for example.
“One of the big frustrations for contractors is [that the supplier has] a material we think they're going to deliver. It's maybe not available, so they submit alternative materials. The client keeps rejecting it – it's not what they want – and it becomes a delay; it's painful.”
McBride gives the example of a pre-approved bathroom sink. Thanks to Roshn’s relationships with key long-term suppliers, the company is able to negotiate better rates for sanitaryware than would be available to a contractor on an ad hoc basis. If the developer’s rates for sinks are better than the BoQ, it splits the savings 50:50 with the contractor.
“The contractors are winning out of that exercise, we're winning out of it and, ultimately, the customers are winning out of it as well, because we’re passing on those savings,” says McBride.
Flexibility
The benefits to contractors and suppliers extend to payment terms. In today’s sellers’ market, vendors are effectively able to pick and choose the clients they want to work for. As a result, clients – including the gigaprojects – have had to introduce more flexible payment terms and develop market reputations for paying on time.
Roshn may lead the pack on this, with an average payment time from invoice to payment of just 13 days in 2024. A decade ago, this would have been unheard of, but it is now increasingly becoming the norm among the gigaprojects.
In addition, like its PIF peers, Roshn has done away with tender fees and tender bonds, viewing them as outdated means of enforcing vendor participation, especially given the tight liquidity and cashflow situation in the projects market in Saudi Arabia.
Will such flexibility ever extend to performance bonds? McBride is sceptical, pointing to the fact that Roshn’s strong relationship with local banks allows to it facilitate credit agreements between contractors and their lenders. Being a gigaproject developer supported by the PIF – and by tacit extension the state – also helps provide the underlining ease of mind for financers.
Nonetheless, Roshn also takes a proactive approach with advanced payments, enabling up to 20% of the total contract value at the initial stage of the project.
“We've been quite clever in how we do this,” says McBride. “We don't go and release 20% straight away. We’ll do 10% and then, when we’ve evidence that you’ve expended that 10% on mobilisation and site establishment, we’ll release the second 10% tranche.”
Subcontractors
One of the chief sticking points in the kingdom’s projects ecosystem in the past decade has been the capacity and capability of its subcontractors.
The payments crisis in 2017-20 forced many main and general contractors to reduce their permanent labour forces, plant and general resources. Wary of a repeat, most have retained their leaner structure and so have turned increasingly to subcontractors for their manpower and delivery requirements.
In theory, this makes sense, but in practice subcontractors in Saudi Arabia are themselves often overstretched in terms of both delivery capacity and labour availability. In turn, they frequently use their own subcontractors, which then also outsource, to the point that specific elements of a project may be completed by companies very far down the supply chain – with the quality issues that this implies.
Roshn’s solution is to ensure any subcontractor on site goes through a vetting process encompassing quality and financial checks, thereby ensuring it has full visibility on every company on site.
Increasingly, Roshn is dealing with suppliers directly, under supply-install contracts. This can create interfacing issues with the main contractors, however, which are ultimately responsible for the project’s delivery.
“We have to be quite careful on that,” McBride says. “We have to go through all the checks and balances during the prequalification process because if we are going to give a subcontractor to a contractor that we're saying is pre-vetted by Roshn, we could be opening the door to lots of claims from the main contractor against us. So, vetting for us is absolutely crucial.”
Roshn is also working with smaller suppliers and subcontractors to help them evolve and grow, so that they can start taking on smaller main contractor roles themselves.
“Not every construction package we award is in the billions of riyals,” says McBride. “Our thinking is to let the big tier-one contractors focus on the multibillion-riyal deals while we encourage the smaller ones to grow as part of our supplier development programme.”
To achieve this, the developer holds events and bootcamps with its vendors to discuss best practices on subjects including health and safety, variation procedures and how to submit good tender returns.
Roshn is also working with smaller suppliers and subcontractors to help them evolve and grow
Building information modelling
Vendor education also extends to the use of building information modelling (BIM) and other construction technologies.
BIM is mandatory on Roshn’s projects, as it is on the other gigaprojects. While use of the technology is standard across almost all main contractors in the region, its take-up among smaller companies in the supply chain has been slower, with firms pointing to the cost of its adoption and integration as a barrier, as well as the fact that some clients, particularly government ones, view it as providing limited benefit.
Roshn’s task in this area is made difficult because its projects are less complex from an engineering and construction perspective.
“We’re building villas; it’s completely different to building stadiums or airports,” McBride says. “Can these contractors build from [two-dimensional] drawings? Yes, of course they can. You're not going to convince a smaller contractor that all of these benefits will make it easier to build because they know how to build. They've been doing it for decades.
“But the savings are in making it easier to procure, savings in the repeatability, and in the change control. If you upskill yourself on a Roshn project, you are building your capability, which you can then [demonstrate] to other clients as proof you can go after bigger and more complex projects. It's something that the whole industry has to get behind.”
Indeed, there is much to learn from Roshn’s approach to delivering its infrastructure and building plans. While the comparatively straightforward nature of its projects means that its procurement strategies may not be suited to those gigaprojects with more iconic designs, for many other developers it is a case study in efficient processes that have proven effective in delivering work on time and to budget.
This is just as well given that Roshn is set to embark on the next stage of its journey, with its focus on the more complex Marafy city development in Jeddah and Roshn Stadium in Riyadh. However, the evidence suggests that from a procurement strategy perspective, it is well-positioned to also make this a success.
Exclusive from Meed
-
Saudi housing entity awards infrastructure contract24 November 2025
-
Saudi utility firm awards water transmission contract24 November 2025
-
Larsen & Toubro climbs EPC contractor ranking24 November 2025
-
Chinese firm signs deal for Algerian steel project24 November 2025
-
Contractors submit Riyadh Expo infrastructure bids24 November 2025
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Saudi housing entity awards infrastructure contract24 November 2025

Saudi Arabia’s National Housing Company (NHC) has awarded Riyadh-based Alomaier Trading & Contracting Company a contract to carry out infrastructure works at its Khuzam residential development in Riyadh.
The scope of work covers all infrastructure works across an area of 4,000,000 square metres (sq m) in stage three, phase three of the Khuzam residential project.
Construction works have started, and the project is expected to be completed in 2028.
NHC’s Khuzam project is located to the north of Riyadh, near King Khalid International airport and the Expo 2030 site.
The development will offer more than 50,000 residential units and will include parks, commercial areas and other associated amenities.
It will also feature a grand park spanning an area of more than 4.5 million sq m.
MEED reported in 2020 that Riyadh planned to oversee the development of more than 1 million homes by 2025 to meet growing demand in the kingdom.
By 2030, the Saudi capital aims to more than double its population, from 7-8 million to 15-20 million, and become one of the 10 wealthiest cities in the world.
Alomaier Trading & Contracting is undertaking some major infrastructural development projects across the kingdom.
In 2023, MEED reported that Saudi Arabia’s National Water Company had awarded a contract worth SR371m ($99m) to Alomaier Trading & Contracting. It covers the construction of a sewage network in Dammam’s King Fahd suburb and adjacent areas.
The contract also involves the construction of regression lines with diameters of up to 700 millimetres (mm) and a total length of 300 kilometres (km), as well as five ejection lines with diameters of up to 500mm and a total length of 15km, according to data obtained from the regional projects tracker MEED Projects.
The firm specialises in the construction of roads, railways and other infrastructural development works.
https://image.digitalinsightresearch.in/uploads/NewsArticle/15141143/main.jpeg -
Saudi utility firm awards water transmission contract24 November 2025
Saudi Arabia’s state-owned utility National Water Company (NWC) has awarded a contract for the operation and maintenance of water distribution networks to local firm International Water Distribution Company (Tawzea).
The project comprises the operation and maintenance of water transmission pipelines in Medina province, Sisco Holding announced.
Sisco Holding, also known as Saudi Industrial Services Company, holds a 50% stake in Tawzea. The other 50% stake is owned by Amiantit Water, a subsidiary of Saudi Arabian Amiantit Company.
The contract is valued at SR133.4m ($35.6m) and has a duration of 36 months.
It covers main and secondary pipelines, reservoirs, pumping stations, valves and all related components of the water distribution system.
NWC has also been advancing major sewer network expansion plans in Hafar Al-Batin and Al-Qaisomah.
The utility recently awarded local firm Alkhorayef Water & Power Technologies (AWPT) a contract to deliver the next phase of this project.
The phase four (part two) package involves constructing about 184 kilometres of sanitary sewer pipeline.
As of September, NWC had awarded $337m-worth of contracts. This includes a separate contract awarded to AWPT in August for a sewage network scheme in Al-Kharj governorate.
https://image.digitalinsightresearch.in/uploads/NewsArticle/15140733/main.jpg -
Larsen & Toubro climbs EPC contractor ranking24 November 2025

The oil, gas and petrochemical engineering, procurement and construction (EPC) sector in the Middle East and North Africa (Mena) has enjoyed another strong year in historical terms.This remains true even though the total value of awards in 2025 – $62.5bn as of the first week of November – looks set to fall short of the record highs of $86bn in 2023 and $95bn in 2024. The level of market activity nevertheless remains well above the long-term average of $46bn and the 10-year average of $50bn.
Looking beyond the top line, the most notable trend of the year is the outsized success of India’s Larsen & Toubro (L&T) in securing many of the largest recent schemes in Saudi Arabia and Qatar.
Chinese contractors have also made steady progress in increasing their market share. Some industry stalwarts, by contrast, have seen considerably less success.
While some of this can be attributed to the cyclical nature of tendering and more selective bidding by established players with already large order books, MEED’s ranking of total execution values bears out the broader trends.

L&T’s dramatic surge
The most dramatic shift in the EPC landscape over the past 12 months (Q4 2024-Q3 2025) has been a $12.7bn surge in awards secured by L&T. This rapid expansion of its value of work under execution to $25.4bn has brought the company to within one place of the top of MEED’s EPC contractor rankings – falling just shy of the $26.9bn currently being executed by Italy’s Saipem.
L&T’s recent successes include the March win of the $4bn combined package 4A and 4B (Comp4) of QatarEnergy LNG’s North Field Production Sustainability programme – the largest project awarded during the period. L&T also won the $2.5bn fifth natural gas liquids train (NGL-5) project from QatarEnergy, and four separate contracts worth more than $1bn each with Saudi Aramco.
These wins built on an already burgeoning order book – one that also includes the $3.6bn phase 2: package 1 of the Jafurah gas treatment facility, awarded by Aramco in September 2023.
L&T’s rise has also been helped by relative inactivity among other top firms. Both Saipem and Italy’s Maire Tecnimont achieved prominent ranking positions a year earlier after securing, respectively, the $8.2bn offshore and $8.7bn onshore packages of Adnoc’s Hail and Ghasha programme in October 2023. Those awards, together with other contracts, saw the two Italian firms secure roughly $12bn in awards each in a single 12‑month stretch, catapulting them up the ranking.
However, neither company has added significantly to their pools of work over the past 12 months, in sharp contrast with L&T, which has seized momentum in the regional contracting landscape. So far, L&T has displaced Maire Tecnimont to reach second place regionally; another year of even marginally comparable momentum should put it at the top.
Also notable is the gap between L&T’s total awards over the past 12 months and those of its nearest competitors. L&T’s $12.7bn in wins rivals the combined value of the next three largest EPC contractors. As a share of an estimated $70bn in total awards across the sector over the same period, L&T secured about 18% of the work.The previous year, Saipem and Maire Tecnimont each secured closer to 12% of awards. This underlines L&T’s considerable momentum both in terms of its order book and market share growth.
Chinese push
Two other significant winners over the past 12 months are China Petroleum Engineering & Construction Corporation (CPECC) and China Offshore Oil Engineering Company (COOEC), which secured $5bn and $4.3bn-worth of awards, respectively.
These contracts wins have moved the two Chinese firms up into the top 20 EPC contractors. CPECC’s success is largely attributable to the niche it has developed in Iraq and Algeria, where about $4.4bn of its awards were won – led by a $1.6bn contract to deliver the central gas complex for Basra Oil Company’s Artawi development.
COOEC’s recent wins have been concentrated in the GCC, specifically on phases one and two of QatarEnergy’s Bul Hanine offshore oil field expansion, which are worth a combined $4bn.
The US’ McDermott and Spain’s Tecnicas Reunidas – two long-term regional players – recorded the next strongest order-book additions, securing about $3.8bn and $3.4bn, respectively. McDermott’s new work includes the $2bn phase two of Adnoc Offshore’s Umm Shaif long‑term development plan and a $1.8bn contract to lay offshore pipelines and subsea power cables for QatarEnergy LNG’s North Field South programme.
The next five biggest bookers over the period were South Korea’s Samsung C&T and Samsung E&A, the UAE’s Lamprell and Target Engineering, and Qatar’s Doha Petroleum Construction Company (DOPET) – each securing more than $2bn.
Samsung C&T’s top award was for QatarEnergy’s $2.5bn carbon sequestration complex; Samsung E&A’s was for Taziz Chemicals’ $1.7bn methanol plant in phase one of its industrial chemicals zone.
Lamprell secured five separate contracts from Saudi Aramco, the largest a $1.5bn award for offshore infrastructure on the Zuluf development.
Target secured three UAE contracts, led by a $1.5bn award from Adnoc Offshore for phase five of its Das Island terminal facilities (part of the Lower Zakum long‑term development).
DOPET secured two contracts from QatarEnergy, led by a $2bn award for phase three of the Bul Hanine offshore oil field expansion.
Across the activity, it remains conspicuous how rapidly values fall away from the top winners and how concentrated the recent awards are with L&T. While the contraction in total award value may partly explain this dynamic, the broader trend is clear: the concentration of work with L&T makes it the company to watch in regional bidding rounds in the year ahead.
https://image.digitalinsightresearch.in/uploads/NewsArticle/15140734/main.gif -
Chinese firm signs deal for Algerian steel project24 November 2025
China’s Sinomach Heavy Equipment has signed a contract to develop a steel rolling facility in Algeria.
The project will be executed by its subsidiary, China National Heavy Machinery Corporation (CNHMC).
The turnkey contract includes planning, design, equipment supply, construction, installation and commissioning.
The scope of the project includes:
- A rolling mill production line
- Auxiliary facilities
- Steel structure workshops
In a statement, CNHMC said: “The signing of this contract marks a new stage in the company's market expansion in the African metallurgical sector.
“CNHMC will fully leverage its technological and management advantages in the metallurgical field, strictly control the project's quality and schedule, and strive to complete and deliver the project on schedule with high quality and high standards, making it a benchmark project in the Algerian market.”
The company said it will use its regional headquarters in Turkiye to ramp up its activities in the Algerian market and other neighbouring countries.
https://image.digitalinsightresearch.in/uploads/NewsArticle/15139865/main3657.jpg -
Contractors submit Riyadh Expo infrastructure bids24 November 2025

Register for MEED’s 14-day trial access
Saudi Arabia’s Expo 2030 Riyadh Company (ERC), which is tasked with delivering the Expo 2030 Riyadh venue, received commercial bids from contractors on 23 November for the tender to undertake the initial infrastructure works at the site.
The tender for the project’s initial infrastructure works was issued in September, MEED previously reported.
In October, MEED revealed that 16 firms had been invited to bid for the contract to undertake the initial infrastructure works at the Expo 2030 Riyadh site.
The firms invited to bid include:
- Shibh Al-Jazira Contracting (local)
- Hassan Allam Construction (Egypt)
- El-Seif Engineering Contracting (local)
- Al-Ayuni Investment & Contracting (local)
- Kolin Construction (Turkiye)
- Al-Yamama Trading & Contracting Company (local)
- Saudi Pan Kingdom (local)
- Unimac (local)
- Mapa Insaat (Turkiye)
- Yuksel Insaat (Turkiye)
- IC Ictas / Al-Rashid Trading & Contracting (Turkiye/local)
- Mota-Engil / Albawani (Portugal/local)
- Almabani / FCC Construction (local/Spain)
The overall infrastructure works – covering the construction of the main utilities and civil works at Expo 2030 Riyadh – will be split into three packages:
- Lot 1 covers the main utilities corridor
- Lot 2 includes the northern cluster of the nature corridor
- Lot 3 comprises the southern cluster of the nature corridor
In July, US-based engineering firm Bechtel Corporation announced it had won the project management consultancy deal for the delivery of the Expo 2030 Riyadh masterplan construction works.
The masterplan encompasses an area of 6 square kilometres, making it one of the largest sites designated for a World Expo event. Situated to the north of the Saudi capital, the site will be located near the future King Salman International airport, providing direct access to various landmarks within Riyadh.
Countries participating in Expo 2030 Riyadh will have the option to construct permanent pavilions. This initiative is expected to create opportunities for business and investment growth in the region.
The expo is forecast to attract more than 40 million visitors.
The Public Investment Fund (PIF), Saudi Arabia’s sovereign wealth vehicle, launched ERC in June as a wholly owned subsidiary to build and operate facilities for Expo 2030.
In a statement, the PIF said: “During its construction phases, Expo 2030 Riyadh and its legacy are projected to contribute around $64bn to Saudi GDP and generate approximately 171,000 direct and indirect jobs. Once operational, it is expected to contribute approximately $5.6bn to GDP.”
https://image.digitalinsightresearch.in/uploads/NewsArticle/15140538/main.jpg

