Oman expands grid connectivity

10 December 2023

Oman’s power and water sector has awarded an annual average of approximately $1.5bn-worth of contracts over the past 11 years – a relatively low value compared to the total awarded every year by some of its GCC neighbours.

However, 2023 can still be considered a good year for the sultanate, as contracts worth an estimated $1.2bn have been awarded.

This is an improvement on the performance of the previous two years, which saw very limited project activity within the sector, with contract awards valued at just $104m in 2021 and $244m in 2022.

Having adopted a policy to not procure further gas-fired thermal power plants, Oman awarded the contracts to develop its second and third utility-scale solar photovoltaic (PV) plants in early 2023.

The Manah 1 and 2 solar PV independent power projects (IPPs) each have a capacity of 500MW. Wadi Noor Solar Company, comprising France’s EDF Renewables and South Korea’s Korea Western Power Company (Kowepo), will deliver and maintain the Manah 1 solar IPP project for 20 years.

Another team, comprising Singapore’s Sembcorp Industries and China-headquartered Jinko Power Technology, will develop the Manah 2 IPP scheme. The country’s first utility-scale solar project, Ibri 2, became operational in 2021. 

Oman’s Ministry of Regional Municipalities & Water Resources also awarded a $108m contract for the construction of a flood protection dam in Wadi Ajay Gorge in Muscat in early 2023. The rest of the awarded contracts comprise water and power transmission pipeline projects across the sultanate.

Demand growth

Nama Power & Water Procurement Company (PWP), formerly Oman Power & Water Procurement Company (OPWP),  expects peak electricity demand for the main interconnected system (MIS), the sultanate’s main electricity grid, to grow by an average of 3.54 per cent annually from 2022 to 2029, reaching 8,350MW at the end of the forecast period.

Most of this growth is expected to occur in the near term, as the economy recovers from the effects of the Covid-19 pandemic, according to PWP’s most recent Seven-Year Statement, which covers the years 2023-29. It is also higher compared to the 2.5 per cent average annual peak demand growth rate seen between 2015 and 2022.

PWP’s low-case forecast scenario shows an average annual peak demand growth of 1.3 per cent, with the base growing from 6,628MW to just over 7,200MW. A high-case scenario, on the other hand, indicates an annual demand growth of 5.2 per cent, which can drive the demand to reach 9,430MW.

Annual peak demand growth in the smaller Dhofar grid is expected to average 5 per cent between 2022 and 2029.

The first phase of Oman’s North-South Interconnection project, known as Rabt, became operational in November. The 400-kilovolt (kV), 670-kilometre (km) project required an investment of about $966m.

The first phase of Oman’s North-South Interconnection project, known as Rabt, became operational in November

The project enables the MIS, serving the northern half of the Oman grid, to connect with Nihada in Al-Dhahirah Governorate and Duqm Special Economic Zone (SEZ) in Al-Wusta Governorate.

Al-Wusta offers an optimal location for solar and wind projects, which the country aims to develop as part of its green energy ambitions.

Also part of Rabt's first phase, the isolated networks of Petroleum Development Oman and the Rural Areas Electricity Company (Tanweer) in Duqm SEZ, have been interconnected.

A second phase is being planned for Rabt. To be launched later this year, it will comprise a 500km, 400kV transmission line from Duqm to Dhofar.

Water requirements

Peak water demand in the MIS is expected to increase by an average of 2 per cent annually between 2022 and 2029, while peak water demand in Dhofar is expected to grow by an average of 7 per cent a year.

To meet the expected demand rise in the MIS, several independent water projects are being developed or planned. These include the Barka 5 scheme, which has a capacity of 100,000 cubic metres a day (cm/d) and is expected to come online in 2024. Ghubrah 3, which has three times as much capacity, is expected to be operational two years later.

A third project, a replacement capacity for the Barka zone of about 102,000 cm/d, is also expected to be added in 2024.

Future projects

In addition to the second phase of Rabt, Oman is in the early procurement phase of several solar and wind projects, in line with meeting demand growth and replacing expiring contracted capacity.

The power and water purchase agreement for the gas-fired Barka 2 independent water and power facility, for instance, expires in 2024, while the contract for the Barka 3 IPP expires in 2028.

KPMG Lower Gulf, a subsidiary of the Netherlands-based consultancy company, has been selected to provide financial advisory services to Nama PWP for the Ibri 3 solar IPP, which will have a capacity of 500MW. Ibri 3, along with the planned 100MW Jalaan Bani Bul Ali wind power project, will cater to the MIS.

Another key scheme being planned to connect to the MIS is Oman’s first waste-to-energy plant in Barkah. When complete, the facility is expected to treat 4,500 tonnes of municipal waste a day, produce 130MW-150MW of energy, and reduce the carbon footprint of Oman's landfills by 1.3 million tonnes annually.

For the Duqm grid, a 100MW wind IPP is being planned, in addition to a potential concentrated solar power plant. These plants are expected to become operational in 2026 and 2028, respectively. A 100MW wind project is also being planned for Dhofar, although there has been no fixed target for when it is expected to become operational.

In May, it was also announced that Oman Electricity Transmission Company is planning a second link to the GCC grid. The planned 400kV power transmission link is scheduled to start operations in the first quarter of 2026.

Hydrogen hubs

There are major plans to develop green hydrogen hubs in Duqm and Dhofar, in line with Oman's ambition to produce up to 1.25 million tonnes a year of green hydrogen by 2030.

The proposed projects will integrate renewable energy plants that will supply power to the electrolyser plants, which split water into hydrogen and oxygen, as well as the other units of the facilities.    

The government has so far awarded land concessions to international consortiums looking to develop integrated green hydrogen and ammonia facilities in the country.

The programme will have a potentially significant impact in terms of Oman’s future gross renewable energy capacity growth, with some of the earliest announced projects requiring several gigawatts of wind and solar power.

However, since most of the planned projects include captive renewable energy power plants, they will not necessarily affect the Omani utility companies' future capacity procurement plans. 

On the other hand, water demand may be affected as the electrolysis plants require pure water to be split into hydrogen and oxygen.

https://image.digitalinsightresearch.in/uploads/NewsArticle/11354723/main.jpg
Jennifer Aguinaldo
Related Articles
  • Abu Dhabi seeks firms for Mid Island Parkway PPP

    15 May 2026

     

    Register for MEED’s 14-day trial access 

    Modon Infrastructure, formerly known as Gridora, has invited firms to submit their registrations for the next phase of Abu Dhabi’s Mid Island Parkway Project (MIPP), which will be developed on a public-private partnership (PPP) basis.

    The request for qualifications (RFQ) is expected to be issued to interested parties soon.

    Modon Infrastructure will act as the lead developer with the majority of the equity in the project company. It will award the engineering, procurement, and construction contractor, the operations and maintenance providers, and the advisers.

    The second phase of the MIPP involves the construction of about 11 kilometres (km) of highways, including a mix of three-, four- and five-lane highways. The highways will connect the Um-Yifeenah, Al-Jubail, Al-Sammaliyyah and Sas Al-Nakhl islands to Khalifa City and the E10 road.

    The scope also covers the construction of three interchanges: the E20, E10 and Dumbbell interchanges on Al-Sammaliyyah Island.

    The project includes several major structures, such as the E20 interchange featuring cast-in-place box girder and void slab bridges, and the E10 interchange with cast-in-place box girder bridges. It also includes I-girder bridges between Raha Beach West and Sas Al-Nakhl Island, as well as a causeway at Sas Al-Nakhl Island.

    Further key elements include a cast-in-place balanced cantilever bridge between Sas Al-Nakhl Island and Al-Sammaliyyah Island, a tunnel between Al-Sammaliyyah Island and Bilrimaid Island, and a cut-and-cover (open) tunnel on Bilrimaid Island. The project is completed with another tunnel connecting Bilrimaid Island to Um-Yifeenah Island.

    Abu Dhabi awarded three packages for phase one of the MIPP in 2024. The contract for package 1A was awarded to a joint venture of Turkish contractor Dogus Construction and UAE firm Gulf Contractors. Package 1B was awarded to a joint venture of Yas Projects (Alpha Dhabi Holding) and China Railway International Group. Beijing-headquartered China Harbour Engineering Company and the UAE’s Agility Engineering & Contracting Company won the contract for package 1C.

    Phase one starts at the existing Saadiyat interchange, connecting the E12 to the MIPP, and ends at the recently constructed Um-Yifeenah highway. 

    It comprises a dual main road with a total length of 8km, including four traffic lanes in each direction, two interchanges, a tunnel and associated infrastructure works.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16858325/main.jpg
    Colin Foreman
  • Oman seeks adviser for gas-fired IPPs

    15 May 2026

    Oman’s Nama Power & Water Procurement Company (PWP) has issued a request for proposals for technical consultancy services for the development of new gas-fired independent power projects (IPPs) in the sultanate.

    The state offtaker said the projects will have a total capacity of up to 2,800MW.

    The bid submission deadline is 17 June.

    While Oman is accelerating investment in renewable energy and battery storage, gas-fired thermal generation is expected to remain a core part of the country’s power mix over the coming decade.

    The Misfah and Duqm combined-cycle gas turbine power plants are advancing towards construction following the appointment of China-headquartered Shandong Electric Power Construction No. 3 Company (Sepco 3) and South Korea’s Doosan Enerbility as contractors.

    According to Nama PWP’s 2025 annual report, the Duqm IPP will have a total capacity of 877MW, including 555MW of early power capacity, which is scheduled to commence in Q2 2028.

    The Misfah IPP will have a total capacity of 1,700MW, including 1,203MW of early power capacity, which is scheduled to commence in the same quarter.

    Nama PWP has also recently awarded new power-purchase agreements (PPAs) to three IPPs to extend the operating life of existing gas-fired power plants beyond the expiry of their current contracts.

    The new agreements for the 750MW Sohar 2 IPP and 750MW Barka 3 IPP will take effect on 1 April 2028 and run until 31 March 2043. The agreement for the 200MW Sur IPP will commence on 1 April 2029 and run until 31 March 2044.

    The awards form part of Nama PWP’s 2028-29 procurement programme. The programme aims to secure firm generation capacity from existing assets whose current PPAs are due to expire during that period.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16857037/main4750.jpg
    Mark Dowdall
  • Alghanim submits lowest offer for Kuwait oil refinery project

    15 May 2026

    Kuwait’s Alghanim International General Trading & Contracting has submitted the lowest bid for a contract to upgrade the country’s Mina Al-Ahmadi (MAA) refinery.

    The client is state-owned downstream operator Kuwait National Petroleum Company (KNPC). The project scope covers upgrades to water transmission and storage infrastructure at the refinery.

    The contract will be delivered under an engineering, procurement and construction (EPC) model. The tender was issued in October 2025 with an initial bid deadline of 4 January 2026, which was later extended several times. The most recent rescheduling moved the deadline from 19 April to 10 May.

    Alghanim submitted a bid of KD37.0m ($120m), significantly lower than the other two bidders, both Kuwait-based: Heavy Engineering Industries & Shipbuilding Company (Heisco) at KD60.6m ($197m) and Gulf Spic General Trading & Contracting at KD63.9m ($207m).

    The project is expected to take two years to complete and will expand water storage capacity at the facility by extending existing tanks or constructing new ones. The contractor will also develop associated infrastructure and upgrade systems that transport desalinated water to the refinery, including pipelines and related equipment.

    In its 2024-25 annual report, KNPC said the project will help meet water demand for the facility’s refining and gas production units.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16852744/main.jpg
    Wil Crisp
  • Civil and piping work starts on Iraq field development

    15 May 2026

     

    Civil works and piping work have started for the project to develop a second central processing facility (CPF) at Iraq’s Ratawi oil and gas field, according to industry sources.

    The project is part of the $27bn Gas Growth Integrated Project (GGIP), which is being developed by TotalEnergies along with its partners Basra Oil Company (BOC) and Qatar Energy.

    Phase one of the GGIP is expected to be worth about $10bn.

    Work is progressing on the project despite logistical problems related to the regional conflict that broke out after the US and Israel attacked Iran on 28 February.

    While early works are ongoing, equipment needed for later stages of the project is being delayed as it was due to be transported to the project site using ships that would have travelled through the Strait of Hormuz.

    Shipping through the Strait is still severely disrupted due to the regional conflict.

    In September, Turkiye’s Enka signed a contract to develop the second CPF at Iraq’s Ratawi field as part of the second phase of the field’s development.

    Enka did not give a value for the contract, but it is believed to be worth more than $1bn.

    In November, US-based KBR was selected by Enka to provide detailed design services for the project.

    Enka’s contract covers the engineering, procurement, supply, construction and commissioning of the CPF for the project known as the Associated Gas Upstream Project Phase 2 (AGUP2).

    The aim of the AGUP2 project is to process oil and associated gas from the Ratawi oil field to increase production capacity to 210,000 barrels a day of oil and 154 million standard cubic feet a day of gas.

    GGIP masterplan

    The GGIP programme is being led by TotalEnergies, the operator, which holds a 45% stake.

    Basra Oil Company and QatarEnergy hold 30% and 25% stakes, respectively. The consortium formalised the investment agreement with the Iraqi government in September 2021.

    The four projects that comprise the GGIP are:

    • The Common Seawater Supply Project (CSSP)
    • The Ratawi gas processing complex
    • A 1GW solar power project for Iraq’s electricity ministry
    • A field development project at Ratawi, known as the Associated Gas Upstream Project (AGUP)

    The CSSP is designed to support oil production in Iraq’s southern oil and gas fields – mainly Zubair, Rumaila, Majnoon, West Qurna and Ratawi – by delivering treated seawater for injection, a method used to boost crude recovery rates and improve long-term reservoir performance.

    China Petroleum Engineering & Construction Corporation (CPECC) won a $1.61bn contract in May to execute EPC work for the gas processing complex at the Ratawi field development.

    CPECC’s project team based in its Dubai office is performing detailed engineering work on the project.

    In August last year, TotalEnergies awarded China Energy Engineering International Group the engineering, procurement and construction (EPC) contract for the 1GW solar project at the Ratawi field. A month later, QatarEnergy signed an agreement with TotalEnergies to acquire a 50% interest in the project.

    The 1GW Ratawi solar scheme will be developed in phases, with each phase coming online between 2025 and 2027. It will have the capacity to provide electricity to about 350,000 homes in Iraq’s Basra region.

    The project, consisting of 2 million bifacial solar panels mounted on single-axis trackers, will include the design, procurement, construction and commissioning of the photovoltaic power station site and 132kV booster station.

    Separately, in June, TotalEnergies awarded China Petroleum Pipeline Engineering an EPC contract worth $294m to build a pipeline as part of a package known as the Ratawi Gas Midstream Pipeline.

    Also, TotalEnergies awarded UK-based consultant Wood Group a pair of engineering framework agreements in April, worth a combined $11m, under the GGIP scheme.

    The agreements have a three-year term under which Wood will support TotalEnergies in advancing the AGUP.

    One of the aims of the AGUP is to debottleneck and upgrade existing facilities to increase production capacity to 120,000 b/d of oil on completion of the first phase, according to a statement by Wood.


    READ THE MAY 2026 MEED BUSINESS REVIEW – click here to view PDF

    Global energy sector forced to recalibrate; Conflict hits debt issuance and listings activity; UAE’s non-oil sector faces unclear recovery period amid disruption.

    Distributed to senior decision-makers in the region and around the world, the May 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/16852654/main.png
    Wil Crisp
  • Abu Dhabi selects Yas Island site for $1.7bn Sphere venue

    14 May 2026

    Abu Dhabi’s Department of Culture & Tourism (DCT Abu Dhabi) and US-based Sphere Entertainment have selected Yas Island as the location for the $1.7bn Sphere Abu Dhabi project.

    The venue will be built on a plot between Yas Mall and SeaWorld Abu Dhabi, close to Yas Island’s theme parks and attractions. Construction is expected to be completed by the end of 2029. Dubai-listed Alec is understood to be the selected contractor and has been working on the project’s pre-construction phase.

    The project will be the first Sphere venue outside the US. It is expected to echo the scale of Sphere Las Vegas, with a capacity of up to 20,000 depending on configuration.

    DCT Abu Dhabi said it will coordinate enabling and infrastructure works with Abu Dhabi entities, including the Department of Municipalities & Transport and its Integrated Transport Centre, the Department of Energy, Taqa, Etihad Rail and Aldar. The scope includes road enhancements, site access and site-wide infrastructure integrated with surrounding Yas Island assets.

    Sphere Abu Dhabi is the latest addition to Abu Dhabi’s integrated tourism and destination-development pipeline on Yas Island, alongside major attractions and the Disney theme park resort that was announced in 2025.

    DCT and Sphere Entertainment finalised an agreement last year related to the construction, development and operation of the Sphere entertainment venue in Abu Dhabi. According to the agreement, Sphere Entertainment granted DCT the exclusive rights to build and operate the Sphere Abu Dhabi entertainment venue.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16837302/main.gif
    Colin Foreman