Oman expands grid connectivity

10 December 2023

Oman’s power and water sector has awarded an annual average of approximately $1.5bn-worth of contracts over the past 11 years – a relatively low value compared to the total awarded every year by some of its GCC neighbours.

However, 2023 can still be considered a good year for the sultanate, as contracts worth an estimated $1.2bn have been awarded.

This is an improvement on the performance of the previous two years, which saw very limited project activity within the sector, with contract awards valued at just $104m in 2021 and $244m in 2022.

Having adopted a policy to not procure further gas-fired thermal power plants, Oman awarded the contracts to develop its second and third utility-scale solar photovoltaic (PV) plants in early 2023.

The Manah 1 and 2 solar PV independent power projects (IPPs) each have a capacity of 500MW. Wadi Noor Solar Company, comprising France’s EDF Renewables and South Korea’s Korea Western Power Company (Kowepo), will deliver and maintain the Manah 1 solar IPP project for 20 years.

Another team, comprising Singapore’s Sembcorp Industries and China-headquartered Jinko Power Technology, will develop the Manah 2 IPP scheme. The country’s first utility-scale solar project, Ibri 2, became operational in 2021. 

Oman’s Ministry of Regional Municipalities & Water Resources also awarded a $108m contract for the construction of a flood protection dam in Wadi Ajay Gorge in Muscat in early 2023. The rest of the awarded contracts comprise water and power transmission pipeline projects across the sultanate.

Demand growth

Nama Power & Water Procurement Company (PWP), formerly Oman Power & Water Procurement Company (OPWP),  expects peak electricity demand for the main interconnected system (MIS), the sultanate’s main electricity grid, to grow by an average of 3.54 per cent annually from 2022 to 2029, reaching 8,350MW at the end of the forecast period.

Most of this growth is expected to occur in the near term, as the economy recovers from the effects of the Covid-19 pandemic, according to PWP’s most recent Seven-Year Statement, which covers the years 2023-29. It is also higher compared to the 2.5 per cent average annual peak demand growth rate seen between 2015 and 2022.

PWP’s low-case forecast scenario shows an average annual peak demand growth of 1.3 per cent, with the base growing from 6,628MW to just over 7,200MW. A high-case scenario, on the other hand, indicates an annual demand growth of 5.2 per cent, which can drive the demand to reach 9,430MW.

Annual peak demand growth in the smaller Dhofar grid is expected to average 5 per cent between 2022 and 2029.

The first phase of Oman’s North-South Interconnection project, known as Rabt, became operational in November. The 400-kilovolt (kV), 670-kilometre (km) project required an investment of about $966m.

The first phase of Oman’s North-South Interconnection project, known as Rabt, became operational in November

The project enables the MIS, serving the northern half of the Oman grid, to connect with Nihada in Al-Dhahirah Governorate and Duqm Special Economic Zone (SEZ) in Al-Wusta Governorate.

Al-Wusta offers an optimal location for solar and wind projects, which the country aims to develop as part of its green energy ambitions.

Also part of Rabt's first phase, the isolated networks of Petroleum Development Oman and the Rural Areas Electricity Company (Tanweer) in Duqm SEZ, have been interconnected.

A second phase is being planned for Rabt. To be launched later this year, it will comprise a 500km, 400kV transmission line from Duqm to Dhofar.

Water requirements

Peak water demand in the MIS is expected to increase by an average of 2 per cent annually between 2022 and 2029, while peak water demand in Dhofar is expected to grow by an average of 7 per cent a year.

To meet the expected demand rise in the MIS, several independent water projects are being developed or planned. These include the Barka 5 scheme, which has a capacity of 100,000 cubic metres a day (cm/d) and is expected to come online in 2024. Ghubrah 3, which has three times as much capacity, is expected to be operational two years later.

A third project, a replacement capacity for the Barka zone of about 102,000 cm/d, is also expected to be added in 2024.

Future projects

In addition to the second phase of Rabt, Oman is in the early procurement phase of several solar and wind projects, in line with meeting demand growth and replacing expiring contracted capacity.

The power and water purchase agreement for the gas-fired Barka 2 independent water and power facility, for instance, expires in 2024, while the contract for the Barka 3 IPP expires in 2028.

KPMG Lower Gulf, a subsidiary of the Netherlands-based consultancy company, has been selected to provide financial advisory services to Nama PWP for the Ibri 3 solar IPP, which will have a capacity of 500MW. Ibri 3, along with the planned 100MW Jalaan Bani Bul Ali wind power project, will cater to the MIS.

Another key scheme being planned to connect to the MIS is Oman’s first waste-to-energy plant in Barkah. When complete, the facility is expected to treat 4,500 tonnes of municipal waste a day, produce 130MW-150MW of energy, and reduce the carbon footprint of Oman's landfills by 1.3 million tonnes annually.

For the Duqm grid, a 100MW wind IPP is being planned, in addition to a potential concentrated solar power plant. These plants are expected to become operational in 2026 and 2028, respectively. A 100MW wind project is also being planned for Dhofar, although there has been no fixed target for when it is expected to become operational.

In May, it was also announced that Oman Electricity Transmission Company is planning a second link to the GCC grid. The planned 400kV power transmission link is scheduled to start operations in the first quarter of 2026.

Hydrogen hubs

There are major plans to develop green hydrogen hubs in Duqm and Dhofar, in line with Oman's ambition to produce up to 1.25 million tonnes a year of green hydrogen by 2030.

The proposed projects will integrate renewable energy plants that will supply power to the electrolyser plants, which split water into hydrogen and oxygen, as well as the other units of the facilities.    

The government has so far awarded land concessions to international consortiums looking to develop integrated green hydrogen and ammonia facilities in the country.

The programme will have a potentially significant impact in terms of Oman’s future gross renewable energy capacity growth, with some of the earliest announced projects requiring several gigawatts of wind and solar power.

However, since most of the planned projects include captive renewable energy power plants, they will not necessarily affect the Omani utility companies' future capacity procurement plans. 

On the other hand, water demand may be affected as the electrolysis plants require pure water to be split into hydrogen and oxygen.

https://image.digitalinsightresearch.in/uploads/NewsArticle/11354723/main.jpg
Jennifer Aguinaldo
Related Articles
  • Kuwait shows tentative signs of economic development

    7 August 2026

     

    Kuwait was one of the chief targets of Iranian drone and missile strikes during July, but against the backdrop of regional instability, the Kuwaiti authorities also managed to conclude a series of significant deals during the month. That suggests that, if the US and Iran can come to some sort of agreement to end their conflict, there is the potential for the Kuwaiti economy to diversify and expand in a way that it has, until now, struggled to do.

    The sense of nascent progress was bolstered in early August, when a survey of local businesses found that the non-oil sector had returned to growth at the start of the third quarter, having been in a slump since the start of the war. However, the risk of renewed fighting means most observers remain deeply cautious about whether the latest purchasing managers index (PMI) is just a blip, or the start of a longer trend.

    Debt deals

    The first big deal came on 22 July, when the government sold $6bn-worth of bonds. It was the second debt issuance by the authorities since a long-awaited public debt law was passed by decree last year. The latest package included debt with tenors of three, five and 10 years. In a sign of the turbulent geopolitical environment, the bonds were priced at 70-85 basis points over US Treasuries. Notably higher than the 40-50 basis point spread the government achieved in its bond sale late last year.

    The second significant development came just a few days later, with Kuwait Oil Company (KOC) unveiling a $16bn deal with international investors Blackstone, Brookfield and KKR for its crude oil pipeline network. In a similar structure to deals struck in the past by Abu Dhabi National Oil Company (Adnoc) and Saudi Aramco, KOC will lease the country’s domestic and export pipelines to a new joint venture it has set up with the trio of international partners. The Kuwaiti energy company will then lease back the pipelines on an exclusive basis, in return for a volume-based tariff.

    KOC will have a 51% stake in the joint venture and – in line with Kuwaiti law – will retain full ownership and operational control of the 320-kilometre network.

    It was the largest energy infrastructure deal ever agreed in Kuwait and, according to KOC, the largest foreign direct investment made in the country. The $7.85bn that the three international partners will invest upfront will be used to support KOC parent company Kuwait Petroleum Corporation’s wider capital expenditure plans.

    The fact that the country was able to secure the deal at a time when its only existing export route – through the Strait of Hormuz – has been effectively closed off is an important vote of confidence by investors in the country’s longer-term prospects. According to energy consultancy Wood Mackenzie, Kuwait’s crude export volumes had fallen from 1.2 million barrels a day before the year to zero in April.

    It was the largest energy infrastructure deal ever agreed in Kuwait and, according to KOC, the largest foreign direct investment made in the country

    UK-based Oxford Economics noted that the bond issue and the pipeline deal came at a time when Kuwait “faces elevated fiscal funding needs and remains one of the GCC’s most exposed oil exporters to any disruption in the Strait of Hormuz given its limited alternative export infrastructure”.

    Blackstone said it also plans to open an office in Kuwait this year. There was a further show of investor interest in early August, when the Kuwait Investment Authority (KIA) reportedly agreed a $4.25bn, three-year loan from a group of 14 banks. The facility will be used for general corporate purposes, according to Bloomberg.

    In a further notable development, Kuwait’s Ministry of Public Works also handed a contract in late July to China State Construction Engineering Corporation (CSCEC) to build the country’s largest wastewater treatment plant. The North Kabd plant will have a capacity of up to 1 million cubic metres a day (cm/d). Kuwaiti water desalination plants have been hit on several occasions by Iranian drones during this year’s war, causing fires and other damage.

    Policy reforms

    On a smaller level, some notable reforms have been rolled out to try to shape the direction of the non-oil economy too. In late July, the Ministry of Commerce & Industry stopped issuing any more sole-trader or freelance business licences, while a review is carried out into the sector and official oversight is tightened.

    The authorities went a step further on 2 August, when a decree was issued to stop businesses offering goods and services without the right sort of licence. Anyone found to be working without the required permit could now face a prison term of up to three years and a fine of up to KD100,000 ($323,000) – or a sum equivalent to the profits generated by the unlicensed activity, whichever is greater.

    Some steps have been taken to ease restrictions in other areas. In early August, a change to the visa system was announced that will allow some foreign nationals to convert a visit visa into a regular residency permit in return for a fee of KD150. The measure proved immediately popular, but many applicants had failed to read the small print and, according to local media reports, several hundred were rejected. The scheme is primarily aimed at those seeking to bring their wives or children to Kuwait, as well as humanitarian cases and others with exceptional circumstances.

    Economic recovery

    The wider economy is showing tentative signs of improvement. The latest PMI survey delivered an unexpectedly strong result, showing that the non-oil private sector returned to growth in July for the first time since the war began.

    S&P Global Market Intelligence, which compiles the index, said the resumption of flights at Kuwait International airport had helped to support a rise in output and new orders – the first for five months. That in turn supported greater purchasing and hiring activity by local businesses and took the index up to 50.8 points – just above the 50-point threshold that separates growth from contraction.

    Even so, S&P warned that market conditions remain “challenging” while local bank NBK Capital warned in early August that “it remains to be seen how much of this improvement [in the PMI] will be sustained … following the reescalation in US-Iran tensions in the past weeks”.

    If the Kuwaiti economy is to make the most of its potential, the country needs the war between Iran and the US to come to a definitive end.


    MEED’s September 2026 report on Kuwait also includes:

    > BANKING: Necessity is the mother of invention for Kuwaiti lenders
    > OIL & GAS: Regional war to have lasting impact on Kuwaiti oil sector
    > CONSTRUCTION: Kuwait construction holds up despite regional strife

    https://image.digitalinsightresearch.in/uploads/NewsArticle/18199239/main.gif
    Dominic Dudley
  • Contractors submit bids for Adnoc Onshore field facilities project

    7 August 2026

     

    Contractors have submitted technical bids to Abu Dhabi National Oil Company’s onshore business (Adnoc Onshore) for a key project to build on-plot and off-plot facilities at the Rumaitha and Shanayel fields, part of the Northeast Bab cluster of oil fields in Abu Dhabi.

    The project aims to enhance and sustain oil production at the Rumaitha and Shanayel fields at a rate of 45,000 barrels a day (b/d). It forms part of Adnoc Onshore’s contribution to parent company Adnoc Group’s broader objective of increasing oil production capacity to 5 million b/d by 2027 through its Accelerated Integrated Programme 5 (AiP5). Adnoc Group currently has a production capacity of 4.85 million b/d.

    Contractors submitted technical bids for the project by the final deadline of 5 August set by Adnoc Onshore, according to sources.

    Adnoc Onshore issued the main tender for the engineering, procurement and construction (EPC) works package for the Rumaitha and Shanayel on-plot and off-plot facilities project on 19 June, MEED previously reported.

    Prior to that, Adnoc Onshore issued an expression of interest for the Rumaitha and Shanayel on-plot and off-plot facilities project in early December, with contractors submitting their responses later that month, MEED previously reported.

    The prequalification and ongoing tendering process is understood to result from Adnoc Onshore revising its strategy for executing EPC works on an earlier, larger project covering the Northeast Bab cluster, which comprises the Al-Nouf, Rumaitha and Shanayel fields.

    MEED reported in December that Adnoc Onshore cancelled an engineering, procurement and construction management (EPCm) phase it launched in 2024 for the Northeast Bab on-plot and off-plot facilities project, in favour of executing the scheme under a conventional EPC model.

    The operator awarded a contract to state-owned China Petroleum Engineering & Construction Corporation (CPECC) to carry out EPCm services for the Northeast Bab off-plot facilities package in October 2024. However, the contract was subsequently cancelled.

    Separately, Adnoc Onshore received bids during the second quarter of 2025 for the EPCm tender covering the Northeast Bab on-plot facilities package, but that procurement process was also later cancelled.

    Project scope of work

    The detailed scope of work on the Rumaitha and Shanayel on-plot and off-plot facilities project is as follows:

    On-plot facilities:

    • Oil train: One new oil train with slug catcher, two-stage separation, desalting, exchangers for crude heating and stabilisation, and all associated interconnections, utilities and civil/structural works, etc.
    • Produced water treatment (PWT): New produced water treatment package to enable 100% produced water reinjection (PWRI), including chemical dosing, tanks, pumps, all associated controls and blending with aquifer water, etc.
    • Water injection system: New water injection system, including surface water injection pumps, necessary connections and controls from produced water systems, headers, chemical dosing, power and controls, etc.
    • Gas handling and export:
      • Low-pressure gas compression system
      • Medium-pressure gas compression system
      • Gas dehydration and regeneration system
      • Export gas compression system
    • Utilities and offsites: Plant air and instrument air systems, nitrogen generation system, potable water system, vapour recovery system (liquid ejector package), fuel gas import and distribution, closed and open drain systems, hot oil heater, snuffing nitrogen package, enclosed ground flare systems (high-pressure and tank flares), etc.
    • Modifications in existing systems, including, but not limited to, installation of a slug catcher at phase-I, connectivity of gas systems, water systems, existing high-pressure compressors modifications, etc
    • Electrical, instrumentation and control, and safety: Electrical systems, instrumentation and control system (ICSS, F&G system, field instrumentation, HIPPS, etc.), substation and ITR room building, fire water system, etc.
    • Overhead line (220 kV): Installation and extension of overhead lines and 220 KV GIS compound or equivalent power distribution solutions to the central processing plant and other designated areas, as necessary.

    Off-plot facilities:

    • New gas-lifted oil producers and water injectors installation with necessary piping, controls, etc. and their connections to the new or existing clusters and pipeline networks
    • New clusters with facilities such as control panels, ITR, production and test manifolds, headers, chemical injection skids, multiphase flow meters, closed drain systems, HIPPS valves, WHCPs, pig traps, ICSS/telecom extensions, etc.
    • Modifications in existing clusters, including the addition or extension of manifolds, headers, additional pipelines with pig traps, ICSS/telecom extensions, chemical injection kids, etc.
    • Gathering and injection networks: Construction of new and modified oil gathering and water injection trunklines/laterals, pigging facilities (launchers/receivers), valve stations, block valves, corrosion protection and monitoring, and all associated equipment, etc.
    • Export gas pipelines and Adnoc Gas interface: Provision for export gas pipeline and facilities from Rumaitha central processing plant to new manifold station and from NMS to Adnoc Gas, including isolation/blowdown, etc.
    • Overhead line: Installation and extension of 33kV overhead lines to clusters, etc., as required.

    The tendering exercise for the Rumaitha and Shanayel on-plot and off-plot facilities project is taking place as Adnoc Onshore continues to make progress with EPC works on another, similar project to build off-plot facilities at the Southeast cluster of oil fields in Abu Dhabi, which is also integral to Adnoc Group’s AiP5 campaign.

    The Southeast cluster comprises the Asab, Mender, Qusahwira, Sahil and Shah fields and accounts for approximately a third of Adnoc Onshore’s oil production capacity.

    MEED previously reported that Adnoc Onshore had awarded EPC works on the Southeast off-plot facilities project to state-owned China Petroleum Engineering & Construction Corporation (CPECC), with the value of the contract estimated to be around $1.2bn.

    The overall scope of work on the Southeast off-plot facilities project includes tying in more than 150 wells across the area’s fields, upgrading remote and central degassing stations, laying more than 270 kilometres of flowlines, digitising wells for remote monitoring, and implementing artificial intelligence-driven telemetry technologies.

    MEED also recently reported that CPECC awarded subcontracts on the Southeast off-plot facilities project, in its capacity as the main EPC contractor.

    The off-plot facilities project is a component of the overall $2bn-$3bn Southeast AIP5 development, with the on-plot facilities project forming the other part of the programme.

    CPECC is also performing EPC works on the Southeast on-plot facilities project in a consortium with Greece-headquartered Archirodon. Adnoc Onshore awarded an estimated $1.5bn contract for that project to the consortium in December 2024, with EPC works scheduled for completion in 2027.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/18194842/main2845.jpeg
    Indrajit Sen
  • Consultant progresses work on Petro Rabigh project

    7 August 2026

     

    Saudi Arabia's Rabigh Refining & Petrochemical Company (Petro Rabigh) is overseeing progress on a project to build additional units at its integrated refining and petrochemical complex in Rabigh, on the kingdom’s Red Sea coast.

    Petro Rabigh, which is majority-owned by Saudi Aramco, appointed Australia-headquartered Worley to provide engineering and project management consultancy (PMC) services for the project in the first quarter of this year, sources told MEED.

    The overall scope of work on the project covers the construction of the following units:

    • Light naphtha isomerisation unit
    • De-asphalting and dewaxing unit
    • Ebullated bed configuration
    • Sulphur block (SRU/ARU/SWS/SFU)
    • Sales gas allocation and pipeline construction
    • Utilities unit outside battery limit
    • Auxiliary piping modifications
    • Utility and hydrocarbon tie-ins.

    Under the contract, the consultant will perform engineering studies and PMC functions, and assist the client in developing cost estimates and project-specific execution and technical procedures, based on Aramco guidelines for both the design basis scoping paper (DBSP) stage and, subsequently, the front-end engineering and design (feed) stage.

    Petro Rabigh will draw on the consultant’s advice on design, procurement and the development of new processing technologies, including for light naphtha isomerisation; vacuum residue processing technologies such as de-asphalting and dewaxing; an ebullated-bed configuration integrated with the diesel hydrotreating section; and unconverted oil hydrotreatment.

    According to sources, Petro Rabigh issued the tender for engineering and PMC services for the additional units project on 30 May last year.

    It set an initial bid submission deadline of 29 June last year, which it then extended to 17 July and again to 24 July, with engineering firms submitting their proposals by that date, sources said.

    Following months of evaluation, discussions and negotiations with bidders, Petro Rabigh selected Worley for the contract.

    Red Sea downstream complex

    Petro Rabigh was originally established in 1989 as a basic topping refinery with crude oil processing facilities in Rabigh, along Saudi Arabia’s Red Sea coastline, about 165 kilometres to the north of Jeddah in Mecca Province.

    Saudi Aramco and Japan’s Sumitomo Chemical Company formed an equal joint venture in 2005 to transform the Petro Rabigh crude oil refining complex into an integrated refinery and petrochemicals complex, with the strategic objective of expanding Saudi Arabia’s annual production capacity of refined products and petrochemicals.

    Three years after the creation of the Petro Rabigh joint venture, the partners floated 25% of its shares in an initial public offering on the Saudi Stock Exchange (Tadawul) in 2008, following which Aramco and Sumitomo Chemical each held 37.5% shares in Petro Rabigh, with the remaining shares listing on the Tadawul.

    In October last year, however, Aramco completed the acquisition of an additional 22.5% stake in Petro Rabigh from Sumitomo Chemical. Following the completion of the transaction, valued at $702m or SR7 a share, Aramco became the majority shareholder in Petro Rabigh, with an equity stake of 60%, while Sumitomo retains an interest of 15%. The remaining 25% shares of Petro Rabigh continue to trade on the Tadawul.

    ALSO READ: Petro Rabigh and Indian firm to study joint project investment

    Following the formation of the Petro Rabigh joint venture in 2005, Aramco and Sumitomo Chemical launched the expansion of the refining facility into an integrated refining and petrochemicals complex in 2006, investing $9.8bn in the project, 60% of which was secured through external financing. Engineering, procurement and construction works on phase one were completed in 2009, with the integrated downstream complex entering operations in November of that year.

    The Petro Rabigh downstream complex consists of a topping refinery that has a 340,000 barrel-a-day (b/d) crude distillation unit, a 47,000 b/d hydrotreater, a 12 million cubic-feet-a-day hydrogen plant, a 75,000 b/d naphtha merox unit and a 60,000 b/d kerosene merox unit, along with supporting utilities, product tankage and a marine terminal.

    Aramco and Sumitomo Chemical initiated Petro Rabigh’s phase two expansion project, valued at $8bn, in 2014. The second expansion phase was commissioned in 2018 and added 15 chemicals plants to the Petro Rabigh complex, raising the facility’s total production capacity to 18.4 million tonnes a year (t/y) of petroleum-based products.  

    The expansion also increased Petro Rabigh’s capacity to process an additional 30 million cubic feet a year of ethane into 2.4 million t/y of ethylene and propylene-based derivatives, and achieved a naphtha output of 3 million t/y.

    Expansion of the main existing chemicals plant and the establishment of a clean fuels complex comprising polyether polyols, naphtha treating and sulphur recovery units were also part of the phase two project.

    In addition to awarding Worley the engineering and PMC services contract this year, Petro Rabigh awarded US-based KBR a 10-year contract in February this year to provide maintenance services covering the company’s polymer plants in Rabigh, on the kingdom’s Red Sea coast.

    Work on the operations and maintenance contract will be executed by KBR’s  business line, which operates under the Houston-headquartered firm’s Technology Solutions portfolio, sources told MEED.

    Prior to this contract, in March 2024, Petro Rabigh awarded KBR a similar five-year asset condition monitoring programme contract. As part of that job, KBR is to provide predictive maintenance services at Petro Rabigh’s main plant.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/18197902/main3022.jpg
    Indrajit Sen
  • Bahrain opens Northern Link Road prices

    7 August 2026

    Three international consultancy firms have opened price bids for a contract to provide transaction advisory services on the Bahrain Northern Link Road (BNLR), a highway the government intends to deliver on a public-private partnership (PPP) basis.

    The Bahrain Tender Board opened the financial proposals on 6 August. Local units of KPMG, PriceWaterhouseCoopers (PwC) and Ernst & Young (EY) submitted bids, all of which were accepted.

    PwC Bahrain submitted the lowest price at BD1.92m ($5.1m), followed by EY Consulting at BD2.26m ($6m) and KPMG Advisory at BD3.89m ($10.3m).

    The selected adviser will provide financial, technical and legal advisory services, including feasibility studies, project structuring and bid documentation, along with support through tendering, evaluation and negotiation, and assistance up to financial close.

    The 29.5-kilometre highway will run from North Manama Causeway Bridge to Suhaila Island and onwards to King Hamad Causeway. The project is intended to serve as a parallel east-west corridor to Sheikh Isa Bin Salman Highway and to support traffic flow between Khalifa Bin Salman Port and Saudi Arabia.

    Causeway connection

    The BNLR will connect to the planned King Hamad Causeway. Earlier project plans, drawn up in 2016, included an arterial road with six or eight lanes that could run alongside a light rail or rapid bus transit system.

    In October 2019, King Fahd Causeway Authority appointed a consortium to provide transaction advisory services for King Hamad Causeway. The $8.9m consultancy agreement was signed with a consortium of Netherlands-headquartered KPMG, US-based Aecom and UK-based CMS. The plan was for the project to be funded by tolls, as with the existing King Fahd Causeway.

    The King Fahd Causeway opened in 1986 and extends for 25km. The bridge cost an estimated $1.2bn to construct and serves about 45,000 vehicles a day on average, rising to about 60,000 at weekends. It has been undergoing an expansion to ease severe congestion during peak periods.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/18198641/main.jpg
    Colin Foreman
  • Seven opens entertainment complex in Abha

    7 August 2026

    Saudi Entertainment Ventures (Seven) has opened its integrated recreational complex in Abha, the first of 14 entertainment destinations the company plans to develop across the kingdom.

    Local contractor Modern Building Leaders (MBL) built the complex under an estimated SR950m ($253m) contract awarded in December 2022. The scheme has a built-up area of more than 70,000 square metres and features go-karting, edutainment, bowling and indoor golf facilities.

    Seven is a wholly owned subsidiary of Qiddiya Investment Company. The Abha complex is the first Seven project to be completed, and supports the Public Investment Fund’s strategy to develop the entertainment and sports sector in line with Saudi Vision 2030.

    The destination is located within the Abha International airport cluster and connects the airport with the region’s cultural, tourism and entertainment sites. Entertainment experiences at the complex include Formula E Karting alongside Seven-developed concepts such as Kawaken, GolFi, Cyber Bowling and Scene Cinema.

    Consultants on the project include Dar Engineering and Lebanon’s Khatib & Alami, with the UK’s Mace International as project management consultant, according to regional projects tracker MEED Projects.

    Seven plans to invest SR50bn ($13.3bn) in developing 21 integrated entertainment destinations across 14 cities in the kingdom as Riyadh pursues its strategy to diversify away from hydrocarbons, create jobs and improve quality of life.


    READ THE AUGUST 2026 MEED BUSINESS REVIEW – click here to view PDF

    Saudi Arabia builds for the global stage; Rising uncertainty creates fresh set of challenges in the Maghreb; Gulf banks remain robust in the face of geopolitical tensions.

    Distributed to senior decision-makers in the region and around the world, the August 2026 edition of MEED Business Review includes:

    > MARKET FOCUS: Maghreb fortunes diverge
    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/18196472/main.jpg
    Colin Foreman