Oman expands grid connectivity

10 December 2023

Oman’s power and water sector has awarded an annual average of approximately $1.5bn-worth of contracts over the past 11 years – a relatively low value compared to the total awarded every year by some of its GCC neighbours.

However, 2023 can still be considered a good year for the sultanate, as contracts worth an estimated $1.2bn have been awarded.

This is an improvement on the performance of the previous two years, which saw very limited project activity within the sector, with contract awards valued at just $104m in 2021 and $244m in 2022.

Having adopted a policy to not procure further gas-fired thermal power plants, Oman awarded the contracts to develop its second and third utility-scale solar photovoltaic (PV) plants in early 2023.

The Manah 1 and 2 solar PV independent power projects (IPPs) each have a capacity of 500MW. Wadi Noor Solar Company, comprising France’s EDF Renewables and South Korea’s Korea Western Power Company (Kowepo), will deliver and maintain the Manah 1 solar IPP project for 20 years.

Another team, comprising Singapore’s Sembcorp Industries and China-headquartered Jinko Power Technology, will develop the Manah 2 IPP scheme. The country’s first utility-scale solar project, Ibri 2, became operational in 2021. 

Oman’s Ministry of Regional Municipalities & Water Resources also awarded a $108m contract for the construction of a flood protection dam in Wadi Ajay Gorge in Muscat in early 2023. The rest of the awarded contracts comprise water and power transmission pipeline projects across the sultanate.

Demand growth

Nama Power & Water Procurement Company (PWP), formerly Oman Power & Water Procurement Company (OPWP),  expects peak electricity demand for the main interconnected system (MIS), the sultanate’s main electricity grid, to grow by an average of 3.54 per cent annually from 2022 to 2029, reaching 8,350MW at the end of the forecast period.

Most of this growth is expected to occur in the near term, as the economy recovers from the effects of the Covid-19 pandemic, according to PWP’s most recent Seven-Year Statement, which covers the years 2023-29. It is also higher compared to the 2.5 per cent average annual peak demand growth rate seen between 2015 and 2022.

PWP’s low-case forecast scenario shows an average annual peak demand growth of 1.3 per cent, with the base growing from 6,628MW to just over 7,200MW. A high-case scenario, on the other hand, indicates an annual demand growth of 5.2 per cent, which can drive the demand to reach 9,430MW.

Annual peak demand growth in the smaller Dhofar grid is expected to average 5 per cent between 2022 and 2029.

The first phase of Oman’s North-South Interconnection project, known as Rabt, became operational in November. The 400-kilovolt (kV), 670-kilometre (km) project required an investment of about $966m.

The first phase of Oman’s North-South Interconnection project, known as Rabt, became operational in November

The project enables the MIS, serving the northern half of the Oman grid, to connect with Nihada in Al-Dhahirah Governorate and Duqm Special Economic Zone (SEZ) in Al-Wusta Governorate.

Al-Wusta offers an optimal location for solar and wind projects, which the country aims to develop as part of its green energy ambitions.

Also part of Rabt's first phase, the isolated networks of Petroleum Development Oman and the Rural Areas Electricity Company (Tanweer) in Duqm SEZ, have been interconnected.

A second phase is being planned for Rabt. To be launched later this year, it will comprise a 500km, 400kV transmission line from Duqm to Dhofar.

Water requirements

Peak water demand in the MIS is expected to increase by an average of 2 per cent annually between 2022 and 2029, while peak water demand in Dhofar is expected to grow by an average of 7 per cent a year.

To meet the expected demand rise in the MIS, several independent water projects are being developed or planned. These include the Barka 5 scheme, which has a capacity of 100,000 cubic metres a day (cm/d) and is expected to come online in 2024. Ghubrah 3, which has three times as much capacity, is expected to be operational two years later.

A third project, a replacement capacity for the Barka zone of about 102,000 cm/d, is also expected to be added in 2024.

Future projects

In addition to the second phase of Rabt, Oman is in the early procurement phase of several solar and wind projects, in line with meeting demand growth and replacing expiring contracted capacity.

The power and water purchase agreement for the gas-fired Barka 2 independent water and power facility, for instance, expires in 2024, while the contract for the Barka 3 IPP expires in 2028.

KPMG Lower Gulf, a subsidiary of the Netherlands-based consultancy company, has been selected to provide financial advisory services to Nama PWP for the Ibri 3 solar IPP, which will have a capacity of 500MW. Ibri 3, along with the planned 100MW Jalaan Bani Bul Ali wind power project, will cater to the MIS.

Another key scheme being planned to connect to the MIS is Oman’s first waste-to-energy plant in Barkah. When complete, the facility is expected to treat 4,500 tonnes of municipal waste a day, produce 130MW-150MW of energy, and reduce the carbon footprint of Oman's landfills by 1.3 million tonnes annually.

For the Duqm grid, a 100MW wind IPP is being planned, in addition to a potential concentrated solar power plant. These plants are expected to become operational in 2026 and 2028, respectively. A 100MW wind project is also being planned for Dhofar, although there has been no fixed target for when it is expected to become operational.

In May, it was also announced that Oman Electricity Transmission Company is planning a second link to the GCC grid. The planned 400kV power transmission link is scheduled to start operations in the first quarter of 2026.

Hydrogen hubs

There are major plans to develop green hydrogen hubs in Duqm and Dhofar, in line with Oman's ambition to produce up to 1.25 million tonnes a year of green hydrogen by 2030.

The proposed projects will integrate renewable energy plants that will supply power to the electrolyser plants, which split water into hydrogen and oxygen, as well as the other units of the facilities.    

The government has so far awarded land concessions to international consortiums looking to develop integrated green hydrogen and ammonia facilities in the country.

The programme will have a potentially significant impact in terms of Oman’s future gross renewable energy capacity growth, with some of the earliest announced projects requiring several gigawatts of wind and solar power.

However, since most of the planned projects include captive renewable energy power plants, they will not necessarily affect the Omani utility companies' future capacity procurement plans. 

On the other hand, water demand may be affected as the electrolysis plants require pure water to be split into hydrogen and oxygen.

https://image.digitalinsightresearch.in/uploads/NewsArticle/11354723/main.jpg
Jennifer Aguinaldo
Related Articles
  • Egypt seeks consultant for major inland waterway study

    18 November 2025

    Egypt’s Transport Ministry has issued an expressions of interest (EOI) request, through the River Transport Authority, to appoint a consultancy firm for a study on a proposed inland waterway linking Lake Victoria to the Mediterranean.

    The consultant will carry out basin-wide data collection and prepare a strategic environmental and social assessment for the project.

    The assignment includes hydrological, topographic, bathymetric and geotechnical surveys across the Nile Basin.

    The consultancy is expected to run for about 15 months, starting in February or March 2026.

    Firms must submit EOIs by 6 December.

    The study forms part of the Vic-Med project, a multi-country plan to establish a continuous inland waterway from Lake Victoria to the Mediterranean Sea.

    The masterplan project aims to reduce transport costs for landlocked countries and provide a lower-carbon alternative to road freight along the Nile corridor

    The work is part of phase two, part one of the feasibility study, funded through a $2m grant from the New Partnership for Africa's Development – Infrastructure Project Preparation Facility (NEPAD–IPPF), the African Development Bank’s (AfDB) fund for early-stage project development.

    The first phase, completed in July 2019 with $650,000 in AfDB funding, developed the project’s legal and institutional framework and launched two regional inland water transport programmes.

    The second phase, valued at $11.7m, covers updated feasibility studies and expanded technical assessments supporting detailed engineering design and cost-benefit analysis in the next stage. 

    This phase also covers the establishment of a regional operating unit for the project in Cairo.


    READ THE NOVEMBER 2025 MEED BUSINESS REVIEW – click here to view PDF

    Mena players up the ante in global LNG production race; Investment takes UAE non-oil economy from strength to strength; Project finance activity draws international lenders back to market

    Distributed to senior decision-makers in the region and around the world, the November 2025 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/15108707/main.jpg
    Mark Dowdall
  • Kuwait to make decision on four oil pipeline packages

    18 November 2025

     

    Kuwait is evaluating bids on four packages for a major pipeline project after prices were submitted earlier this month, according to industry sources.

    The four separate packages cover pipeline work in the north, south, east and west regions of the country, sources said.

    Although the total of all bids submitted by Kuwait-based Alghanim International General Trading & Contracting is the lowest at KD419m ($1.4bn), the company submitted the lowest individual bid on only one package, located in northern Kuwait.

    Its bid for the north Kuwait package was KD149.8m ($488.3m).

    Mechanical Engineering & Construction Company submitted the lowest bids for pipeline work on two packages located in the south and east of the country. 

    Both of these bids were valued at KD97,868,394 ($319m).

    Al-Dar Engineering & Construction Company is the low bidder on the fourth package, for pipe work in western Kuwait, submitting a bid of KD64,825,398 ($211.3m).

    Together, all four contracts are expected to be worth about $1.4bn when awarded.

    The scope of all four packages focuses on developing new flowlines and connecting pipelines for oil-producing wells and water wells.

    In some cases, companies are also required to replace old flowlines.

    The contracts are based on work orders, so when KOC needs to connect wells it will issue a request for work execution, industry sources said. 

    Kuwait is trying to boost project activity in its upstream sector.

    The country’s national oil company, Kuwait Petroleum Corporation, is aiming to increase oil production capacity to 4 million barrels a day (b/d) by 2035.

    In August, Kuwait announced that it was producing 3.2 million b/d.

    Earlier this month, KOC said it was planning to spend KD1.2bn ($3.92bn) on its exploration drilling programme through 2030.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/15106496/main.png
    Wil Crisp
  • Indian firm wins Oman chemicals project EPC contract

    17 November 2025

    Register for MEED’s 14-day trial access 

    Indian contractor Nuberg EPC has won a contract to perform engineering, procurement and construction (EPC) works on a project to build chlor alkali and calcium chloride plants in Oman for privately-owned Al-Ghaith Chemical Industries.

    The project involves expanding Al-Ghaith’s existing chlor alkali plant in Sur Industrial City, by adding 120 tonnes a day (t/d) of capacity, taking the unit’s total output capacity to 190 t/d. The project also involves building a calcium chloride plant that will have a production capacity of 80 t/d.

    Nuberg EPC said the contract is being executed on a lump sum turnkey basis, with its scope covering design, front-end engineering and design (feed), detailed engineering, procurement, fabrication, construction, commissioning and handover.

    Project execution is already under way, with completion targeted within 19 months, Nuberg EPC said.

    The project marks the second phase of Al-Ghaith’s integrated chemicals complex in Sur and represents a first-of-its-kind large-scale chlor alkali expansion in Oman.

    Nuberg EPC also performed EPC works on the original chlor alkali plant, which has a capacity of 70 t/d.

    In addition to the Oman project, Al-Ghaith has, in the previous decade, also brought on board Nuberg EPC for its chlor alkali and calcium chloride plants in Abu Dhabi. Those contracts covered the commissioning of a 60 t/d chlor alkali plant that was later expanded to 120 t/d, and the execution of a 125 t/d calcium chloride plant and a 50 t/d carbon dioxide plant.

    Nuberg EPC has also executed the expansion of a 45 t/d chlor alkali plant and a greenfield 80 t/d calcium chloride plant for Oman Chlorine in Sohar, increasing the total chlor alkali output capacity to 75 t/d.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/15104096/main5048.jpg
    Indrajit Sen
  • Egypt starts production from strategic gas field

    17 November 2025

    Egypt has started gas production from the West Burullus field in the Mediterranean Sea, after connecting the first wells to the national gas grid, according to a statement from the country’s Petroleum & Mineral Resources Ministry.

    Productivity testing showed an output rate approaching 45 million cubic feet a day (cf/d).

    Kareem Badawi, Egypt’s Petroleum & Mineral Resources Minister, said he intends to accelerate development of the field and confirmed that work is under way to connect two additional wells, with the aim of increasing production to 75 million cf/d in the coming months.

    He added that the ministry aims to cut the county’s gas import bill by boosting domestic production.

    The operator of the concession is Cheiron, an Egyptian independent exploration and production company.

    Egypt’s oil ministry said in its statement that the West Burullus field development project represents a model for future integrated projects and investment plans.

    It said that a range of domestic and foreign companies are involved in bringing the field into production.

    In February, a banking consortium led by Banque du Caire, alongside Arab International Bank, Al-Baraka Bank Egypt and Saib Bank, arranged $75m in syndicated medium-term financing for Cheiron Egypt Delta, a subsidiary of the Cheiron Group.

    This financing will help cover part of the investment costs for the gas field development project.

    At the time, Cheiron said that the financing will provide up to 45.5% of the total $165m investment required for the project.


    READ THE NOVEMBER 2025 MEED BUSINESS REVIEW – click here to view PDF

    Mena players up the ante in global LNG production race; Investment takes UAE non-oil economy from strength to strength; Project finance activity draws international lenders back to market

    Distributed to senior decision-makers in the region and around the world, the November 2025 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/15102295/main3406.jpg
    Wil Crisp
  • Major Iraq refinery project stalls

    17 November 2025

     

    Construction has yet to start on Iraq’s Al-Faw Investment Refinery project due to a range of problems, according to industry sources.

    In May last year, a statement released by the Iraqi Prime Minister’s Office said that Iraq’s state-owned Southern Refineries Company and China National Chemical Engineering Company (CNCEC) had signed a contract to develop the project.

    Iraq’s Oil Ministry previously said the project would be worth $7bn-$8bn.

    One source said: “This project is failing to make progress despite the efforts of senior political figures in the country.”

    A meeting was chaired by Iraqi Prime Minister Mohammed Shia Al-Sudani in August this year to discuss and try to resolve the problems that are stopping the commencement of construction, according to industry sources.

    It is believed that financing remains a key obstacle for the project.

    The Al-Faw project is part of the Iraqi government’s plan to increase Iraq’s refining capacities, attract foreign investment and increase the production of petroleum products domestically.

    The refinery will have a capacity of 300,000 barrels a day and will produce oil derivatives for both domestic and international markets.

    The project will be carried out in two stages.

    The first phase will involve refining operations, while the second will involve constructing a petrochemicals complex with a capacity of 3 million tonnes a year.

    The project also includes the construction of a 2,000MW power plant and the establishment of the Al-Faw Academy for Refinery Technology, to train 5,000 Iraqi workers that will eventually work at the facility.

    Hualu, a subsidiary of CNCEC, signed a preliminary principles agreement for the project in December 2021.

    At the time, Iraq’s Oil Ministry said that the project would have a value of $7bn-$8bn.

    Due to material price inflation since December 2021, some insiders believe that the project value may now be significantly higher.


    READ THE NOVEMBER 2025 MEED BUSINESS REVIEW – click here to view PDF

    Mena players up the ante in global LNG production race; Investment takes UAE non-oil economy from strength to strength; Project finance activity draws international lenders back to market

    Distributed to senior decision-makers in the region and around the world, the November 2025 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/15102287/main.jpg
    Wil Crisp