Oman expands grid connectivity

10 December 2023

Oman’s power and water sector has awarded an annual average of approximately $1.5bn-worth of contracts over the past 11 years – a relatively low value compared to the total awarded every year by some of its GCC neighbours.

However, 2023 can still be considered a good year for the sultanate, as contracts worth an estimated $1.2bn have been awarded.

This is an improvement on the performance of the previous two years, which saw very limited project activity within the sector, with contract awards valued at just $104m in 2021 and $244m in 2022.

Having adopted a policy to not procure further gas-fired thermal power plants, Oman awarded the contracts to develop its second and third utility-scale solar photovoltaic (PV) plants in early 2023.

The Manah 1 and 2 solar PV independent power projects (IPPs) each have a capacity of 500MW. Wadi Noor Solar Company, comprising France’s EDF Renewables and South Korea’s Korea Western Power Company (Kowepo), will deliver and maintain the Manah 1 solar IPP project for 20 years.

Another team, comprising Singapore’s Sembcorp Industries and China-headquartered Jinko Power Technology, will develop the Manah 2 IPP scheme. The country’s first utility-scale solar project, Ibri 2, became operational in 2021. 

Oman’s Ministry of Regional Municipalities & Water Resources also awarded a $108m contract for the construction of a flood protection dam in Wadi Ajay Gorge in Muscat in early 2023. The rest of the awarded contracts comprise water and power transmission pipeline projects across the sultanate.

Demand growth

Nama Power & Water Procurement Company (PWP), formerly Oman Power & Water Procurement Company (OPWP),  expects peak electricity demand for the main interconnected system (MIS), the sultanate’s main electricity grid, to grow by an average of 3.54 per cent annually from 2022 to 2029, reaching 8,350MW at the end of the forecast period.

Most of this growth is expected to occur in the near term, as the economy recovers from the effects of the Covid-19 pandemic, according to PWP’s most recent Seven-Year Statement, which covers the years 2023-29. It is also higher compared to the 2.5 per cent average annual peak demand growth rate seen between 2015 and 2022.

PWP’s low-case forecast scenario shows an average annual peak demand growth of 1.3 per cent, with the base growing from 6,628MW to just over 7,200MW. A high-case scenario, on the other hand, indicates an annual demand growth of 5.2 per cent, which can drive the demand to reach 9,430MW.

Annual peak demand growth in the smaller Dhofar grid is expected to average 5 per cent between 2022 and 2029.

The first phase of Oman’s North-South Interconnection project, known as Rabt, became operational in November. The 400-kilovolt (kV), 670-kilometre (km) project required an investment of about $966m.

The first phase of Oman’s North-South Interconnection project, known as Rabt, became operational in November

The project enables the MIS, serving the northern half of the Oman grid, to connect with Nihada in Al-Dhahirah Governorate and Duqm Special Economic Zone (SEZ) in Al-Wusta Governorate.

Al-Wusta offers an optimal location for solar and wind projects, which the country aims to develop as part of its green energy ambitions.

Also part of Rabt's first phase, the isolated networks of Petroleum Development Oman and the Rural Areas Electricity Company (Tanweer) in Duqm SEZ, have been interconnected.

A second phase is being planned for Rabt. To be launched later this year, it will comprise a 500km, 400kV transmission line from Duqm to Dhofar.

Water requirements

Peak water demand in the MIS is expected to increase by an average of 2 per cent annually between 2022 and 2029, while peak water demand in Dhofar is expected to grow by an average of 7 per cent a year.

To meet the expected demand rise in the MIS, several independent water projects are being developed or planned. These include the Barka 5 scheme, which has a capacity of 100,000 cubic metres a day (cm/d) and is expected to come online in 2024. Ghubrah 3, which has three times as much capacity, is expected to be operational two years later.

A third project, a replacement capacity for the Barka zone of about 102,000 cm/d, is also expected to be added in 2024.

Future projects

In addition to the second phase of Rabt, Oman is in the early procurement phase of several solar and wind projects, in line with meeting demand growth and replacing expiring contracted capacity.

The power and water purchase agreement for the gas-fired Barka 2 independent water and power facility, for instance, expires in 2024, while the contract for the Barka 3 IPP expires in 2028.

KPMG Lower Gulf, a subsidiary of the Netherlands-based consultancy company, has been selected to provide financial advisory services to Nama PWP for the Ibri 3 solar IPP, which will have a capacity of 500MW. Ibri 3, along with the planned 100MW Jalaan Bani Bul Ali wind power project, will cater to the MIS.

Another key scheme being planned to connect to the MIS is Oman’s first waste-to-energy plant in Barkah. When complete, the facility is expected to treat 4,500 tonnes of municipal waste a day, produce 130MW-150MW of energy, and reduce the carbon footprint of Oman's landfills by 1.3 million tonnes annually.

For the Duqm grid, a 100MW wind IPP is being planned, in addition to a potential concentrated solar power plant. These plants are expected to become operational in 2026 and 2028, respectively. A 100MW wind project is also being planned for Dhofar, although there has been no fixed target for when it is expected to become operational.

In May, it was also announced that Oman Electricity Transmission Company is planning a second link to the GCC grid. The planned 400kV power transmission link is scheduled to start operations in the first quarter of 2026.

Hydrogen hubs

There are major plans to develop green hydrogen hubs in Duqm and Dhofar, in line with Oman's ambition to produce up to 1.25 million tonnes a year of green hydrogen by 2030.

The proposed projects will integrate renewable energy plants that will supply power to the electrolyser plants, which split water into hydrogen and oxygen, as well as the other units of the facilities.    

The government has so far awarded land concessions to international consortiums looking to develop integrated green hydrogen and ammonia facilities in the country.

The programme will have a potentially significant impact in terms of Oman’s future gross renewable energy capacity growth, with some of the earliest announced projects requiring several gigawatts of wind and solar power.

However, since most of the planned projects include captive renewable energy power plants, they will not necessarily affect the Omani utility companies' future capacity procurement plans. 

On the other hand, water demand may be affected as the electrolysis plants require pure water to be split into hydrogen and oxygen.

https://image.digitalinsightresearch.in/uploads/NewsArticle/11354723/main.jpg
Jennifer Aguinaldo
Related Articles
  • Iranian drones hit Kuwait International airport’s Terminal 1

    3 June 2026

    Kuwait International airport was struck by a fresh wave of hostile drone attacks on 3 June. The drones caused significant structural damage to Terminal 1 and wounded several individuals.

    Brigadier General Saud Abdulaziz Al-Otaibi, official spokesman for the Ministry of Defence, blamed the strikes on “criminal Iranian aggression”. He confirmed that the injured had been evacuated for medical care and stated that the armed forces remain in a state of complete readiness to secure the state.

    The incident is the third major drone strike on the hub in recent months. On 1 April, a drone strike hit fuel tanks managed by Kuwait Aviation Fuelling Company, sparking massive fires. On March 28, another multi-drone raid severely damaged the airport’s primary radar systems.

    The airport is being expanded with the construction of a new terminal, and works on the project are expected to be completed by 2027. It consists of three packages.

    These are:

    • Package 1: Main works – $4,329m
    • Package 2: Multistorey car park building, connection roads, bridges and landscaping works – $550m
    • Package 3: Aircraft parking, runways and service buildings – $950m

    Turkiye’s Limak Holding is executing the main works.

    The terminal building was designed by Foster+Partners and Gulf Consult.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17089683/main.gif
    Colin Foreman
  • Consortium signs PPA for Taweelah C power plant

    3 June 2026

    Emirates Water & Electricity Company (Ewec) has confirmed it has signed a power-purchase agreement (PPA) with a developer consortium for the Taweelah C independent power producer (IPP) project.

    The agreement, which will run through to 2050, was signed with Abu Dhabi National Energy Company (Taqa), Al-Jomaih Energy & Water Company (Saudi Arabia) and Sembcorp Industries (Singapore), the utility said in a statement.

    Taqa will own a 60% stake in the project, with the international consortium holding 40%. The ADX-listed company will also own 40% of the project’s operations and maintenance company, while the international consortium will own 60%.

    Last month, MEED exclusively revealed that the winning consortium had been selected for the project, with the PPA initially expected to be signed in mid-May.

    It is understood that China Energy Engineering Corporation (CEEC) will be the engineering, procurement and construction contractor.

    The combined-cycle gas turbine plant will have a capacity of about 2.5GW. It will be located at the Al-Taweelah power and desalination complex, about 50 kilometres northeast of Abu Dhabi city.

    Taweelah C is part of Ewec’s wider programme to support the UAE’s Net Zero by 2050 Strategic Initiative and the Abu Dhabi Department of Energy’s Clean Energy Strategic Target 2035.

    Ewec plans to raise solar power capacity to 18GW and wind capacity to 2.6GW by 2035, while reducing the carbon intensity of its power generation by more than half compared with 2019.

    The Taweelah C IPP is now expected to start commercial operations in 2029. The facility had previously been scheduled to begin commercial operations in the fourth quarter of 2028.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17089163/main.jpg
    Mark Dowdall
  • Local contractor wins Oman water transmission contract

    3 June 2026

     

    Local contractor Al-Jesr United has won the main engineering, procurement and construction contract to reinforce Oman’s Sur water transmission system.

    The contract, awarded by state-owned utility Nama Water Services (NWS), forms part of a project to improve the reliability of potable water supply to Sur, a coastal city about 200 kilometres southeast of Muscat.

    The scheme, estimated to cost $80m, is designed to strengthen the network’s resilience during peak-demand periods and emergencies.

    The scope of work includes upgrading the pumps at the Sur DP Pump Station with variable frequency drive units and replacing ductile iron pipes and fittings within the facility. It also covers about 17km of new transmission pipelines.

    According to regional projects tracker MEED Projects, at least five local firms submitted commercial bids for the contract, which was tendered in August 2025.

    These include:

    • Al-Jesr United
    • Al-Rafaa Trading & Contracting
    • Gulf Petrochemical Services & Trading
    • Professionals Trading
    • Sarooj Construction Company

    In June 2024, NWS awarded a $1.3m contract for the project’s design and construction supervision to Muscat-headquartered Ibn Khaldun Almadaen Engineering Consultants.

    Sur is home to one of the sultanate’s key desalination plants, which supplies potable water to communities across eastern Oman. 

    The water transmission project will support network expansion in areas such as Al-Aigah and Ahiae, as the existing ductile iron pipeline serving Wilayat Sur is no longer sufficient to meet current and future demand.

    Construction is expected to start in the third quarter of 2026 and take about two years to complete.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17088454/main.jpg
    Mark Dowdall
  • Syria to tender gas plant contract

    3 June 2026

     

    Syria is preparing to tender a project to rehabilitate the Conoco gas plant in Deir ez-Zor province in the east of the country within the next 10 weeks, according to a document published by the US-Syria Business Council.

    The gas plant was reclaimed by Syria’s military during an offensive in January this year.

    It is Syria’s largest gas plant, but is severely damaged and cannot be operated in its current condition.

    Before the country’s civil war, it processed 13 million cubic metres of gas a day.

    The US-based companies ConocoPhillips and Novaterra signed a memorandum of understanding with the state-owned Syria Petroleum Company (SPC) to restore the facility in November last year.

    Syria is currently in the midst of a push to ramp up oil and gas production and establish itself as a regional energy hub.

    Earlier this year, Yousef Qiblawy, chief executive of SPC, said that his organisation was aiming to double national oil production before 2027 and boost output to 800,000 barrels a day by the end of 2029, not including offshore production.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17088320/main.jpg
    Wil Crisp
  • AD Ports enters South America with $835m Brazil deal

    3 June 2026

    Abu Dhabi-listed AD Ports Group has entered the South American market by agreeing to acquire a majority stake in Corredor Logística e Infraestrutura (CLI), Brazil’s leading independent agri-bulk port terminal operator, for an enterprise value of $835m.

    The transaction represents AD Ports’ largest acquisition to date, surpassing its $720m purchase of Spain’s Noatum in 2023, and its $510m purchase of a 51% stake in Dubai-based Global Feeder Shipping in early 2024.

    Under the terms of the agreement, AD Ports will acquire CLI from joint owners Macquarie Asset Management and IG4 Capital. CLI operates two major agri-bulk export terminals under long-term concessions: CLI Norte at the Port of Itaqui, which is 100% owned by CLI, and CLI Sul at the Port of Santos, which is 80% owned. In 2025, CLI handled 17 million tonnes of cargo, generating $178m in revenue and profits of $98m.

    The deal, expected to close in the second half of 2026, subject to regulatory approvals, aligns with AD Ports’ strategy to expand its agrifood vertical. The group has recently secured similar international assets, including a 30-year concession at Jordan’s Aqaba multipurpose port, a $30m investment in Kazakhstan’s Sarzha Grain Terminal, and a clean bulk facility development at Pakistan’s Karachi Port.

    The acquisition also reflects broader economic ties between the UAE and Brazil, where UAE investments total about $5bn. The UAE is currently negotiating a Comprehensive Economic Partnership Agreement (CEPA) with the Mercosur trading bloc, which includes Brazil.

    The major capital deployment follows a period of significant financial growth and international expansion for the Abu Dhabi operator, which is 75.42% owned by sovereign wealth fund ADQ. AD Ports reported record results for 2025, with revenue rising 20% year-on-year to AED20.77bn ($5.66bn) and net profit increasing 16% to AED2.07bn.

    According to its 2025 annual report, the group plans to invest AED2.45bn in port infrastructure development during 2026 alone, alongside AED1.3bn for liquefied petroleum gas and liquefied natural gas storage terminals between 2026 and 2028. To fund higher-return projects and optimise its balance sheet, AD Ports launched an asset monetisation programme in late 2025 targeting the recycling of AED4.6bn of capital.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17087945/main.jpg
    Colin Foreman