Oman expands grid connectivity

10 December 2023

Oman’s power and water sector has awarded an annual average of approximately $1.5bn-worth of contracts over the past 11 years – a relatively low value compared to the total awarded every year by some of its GCC neighbours.

However, 2023 can still be considered a good year for the sultanate, as contracts worth an estimated $1.2bn have been awarded.

This is an improvement on the performance of the previous two years, which saw very limited project activity within the sector, with contract awards valued at just $104m in 2021 and $244m in 2022.

Having adopted a policy to not procure further gas-fired thermal power plants, Oman awarded the contracts to develop its second and third utility-scale solar photovoltaic (PV) plants in early 2023.

The Manah 1 and 2 solar PV independent power projects (IPPs) each have a capacity of 500MW. Wadi Noor Solar Company, comprising France’s EDF Renewables and South Korea’s Korea Western Power Company (Kowepo), will deliver and maintain the Manah 1 solar IPP project for 20 years.

Another team, comprising Singapore’s Sembcorp Industries and China-headquartered Jinko Power Technology, will develop the Manah 2 IPP scheme. The country’s first utility-scale solar project, Ibri 2, became operational in 2021. 

Oman’s Ministry of Regional Municipalities & Water Resources also awarded a $108m contract for the construction of a flood protection dam in Wadi Ajay Gorge in Muscat in early 2023. The rest of the awarded contracts comprise water and power transmission pipeline projects across the sultanate.

Demand growth

Nama Power & Water Procurement Company (PWP), formerly Oman Power & Water Procurement Company (OPWP),  expects peak electricity demand for the main interconnected system (MIS), the sultanate’s main electricity grid, to grow by an average of 3.54 per cent annually from 2022 to 2029, reaching 8,350MW at the end of the forecast period.

Most of this growth is expected to occur in the near term, as the economy recovers from the effects of the Covid-19 pandemic, according to PWP’s most recent Seven-Year Statement, which covers the years 2023-29. It is also higher compared to the 2.5 per cent average annual peak demand growth rate seen between 2015 and 2022.

PWP’s low-case forecast scenario shows an average annual peak demand growth of 1.3 per cent, with the base growing from 6,628MW to just over 7,200MW. A high-case scenario, on the other hand, indicates an annual demand growth of 5.2 per cent, which can drive the demand to reach 9,430MW.

Annual peak demand growth in the smaller Dhofar grid is expected to average 5 per cent between 2022 and 2029.

The first phase of Oman’s North-South Interconnection project, known as Rabt, became operational in November. The 400-kilovolt (kV), 670-kilometre (km) project required an investment of about $966m.

The first phase of Oman’s North-South Interconnection project, known as Rabt, became operational in November

The project enables the MIS, serving the northern half of the Oman grid, to connect with Nihada in Al-Dhahirah Governorate and Duqm Special Economic Zone (SEZ) in Al-Wusta Governorate.

Al-Wusta offers an optimal location for solar and wind projects, which the country aims to develop as part of its green energy ambitions.

Also part of Rabt's first phase, the isolated networks of Petroleum Development Oman and the Rural Areas Electricity Company (Tanweer) in Duqm SEZ, have been interconnected.

A second phase is being planned for Rabt. To be launched later this year, it will comprise a 500km, 400kV transmission line from Duqm to Dhofar.

Water requirements

Peak water demand in the MIS is expected to increase by an average of 2 per cent annually between 2022 and 2029, while peak water demand in Dhofar is expected to grow by an average of 7 per cent a year.

To meet the expected demand rise in the MIS, several independent water projects are being developed or planned. These include the Barka 5 scheme, which has a capacity of 100,000 cubic metres a day (cm/d) and is expected to come online in 2024. Ghubrah 3, which has three times as much capacity, is expected to be operational two years later.

A third project, a replacement capacity for the Barka zone of about 102,000 cm/d, is also expected to be added in 2024.

Future projects

In addition to the second phase of Rabt, Oman is in the early procurement phase of several solar and wind projects, in line with meeting demand growth and replacing expiring contracted capacity.

The power and water purchase agreement for the gas-fired Barka 2 independent water and power facility, for instance, expires in 2024, while the contract for the Barka 3 IPP expires in 2028.

KPMG Lower Gulf, a subsidiary of the Netherlands-based consultancy company, has been selected to provide financial advisory services to Nama PWP for the Ibri 3 solar IPP, which will have a capacity of 500MW. Ibri 3, along with the planned 100MW Jalaan Bani Bul Ali wind power project, will cater to the MIS.

Another key scheme being planned to connect to the MIS is Oman’s first waste-to-energy plant in Barkah. When complete, the facility is expected to treat 4,500 tonnes of municipal waste a day, produce 130MW-150MW of energy, and reduce the carbon footprint of Oman's landfills by 1.3 million tonnes annually.

For the Duqm grid, a 100MW wind IPP is being planned, in addition to a potential concentrated solar power plant. These plants are expected to become operational in 2026 and 2028, respectively. A 100MW wind project is also being planned for Dhofar, although there has been no fixed target for when it is expected to become operational.

In May, it was also announced that Oman Electricity Transmission Company is planning a second link to the GCC grid. The planned 400kV power transmission link is scheduled to start operations in the first quarter of 2026.

Hydrogen hubs

There are major plans to develop green hydrogen hubs in Duqm and Dhofar, in line with Oman's ambition to produce up to 1.25 million tonnes a year of green hydrogen by 2030.

The proposed projects will integrate renewable energy plants that will supply power to the electrolyser plants, which split water into hydrogen and oxygen, as well as the other units of the facilities.    

The government has so far awarded land concessions to international consortiums looking to develop integrated green hydrogen and ammonia facilities in the country.

The programme will have a potentially significant impact in terms of Oman’s future gross renewable energy capacity growth, with some of the earliest announced projects requiring several gigawatts of wind and solar power.

However, since most of the planned projects include captive renewable energy power plants, they will not necessarily affect the Omani utility companies' future capacity procurement plans. 

On the other hand, water demand may be affected as the electrolysis plants require pure water to be split into hydrogen and oxygen.

https://image.digitalinsightresearch.in/uploads/NewsArticle/11354723/main.jpg
Jennifer Aguinaldo
Related Articles
  • Houthi truce collapse widens Gulf risk map

    15 July 2026

    Register for MEED’s 14-day trial access 

    The Houthis’ declaration ending the de facto truce with Saudi Arabia has significantly increased the likelihood of renewed attacks on Red Sea shipping and regional infrastructure, broadening the threat environment beyond the Strait of Hormuz.

    S&P Global Market Intelligence says the 13 July exchange is best understood as a potential widening of the renewed US-Iran escalation cycle into the Yemen and Red Sea theatres.

    Houthi claims that Saudi Arabia was responsible for a strike on Sanaa International airport have not been independently confirmed. Saudi Arabia had not formally commented at the time the analysis was written.

    The Yemeni militant group is likely to use the incident as a trigger that allows it to justify renewed military action while aligning with Iran’s wider effort to impose costs on US and Gulf interests, according to the research firm.

    The decision to declare an end to de-escalation with Riyadh materially increases the likelihood of further missile and unmanned aerial vehicle (UAV) activity against infrastructure near the Yemen-Saudi border, as well as renewed pressure on maritime routes in the Red Sea and Bab Al-Mandab.

    Aviation exposure

    The resumption of direct hostilities broadens the range of vessels and ports likely to be subject to Houthi targeting, and presents severe risk to airports and stationary aircraft, S&P Global Market Intelligence says.

    While the Houthis would probably not intentionally down civilian aircraft, there is a significant risk to aircraft in flight, particularly at lower altitudes close to airports, due to incoming UAVs and missiles and interceptor activity.

    The broader risk is to regional logistics rather than any single target set, the analysis says.

    If escalation around the Strait of Hormuz coincides with renewed Houthi activity in the southern Red Sea, Bab Al-Mandab and the Gulf of Aden, commercial operators face a more complex dual-chokepoint environment, with the added likelihood that the Houthis will seek to target Hormuz bypass infrastructure across the Gulf.

    That would raise the likelihood of shipping delays, higher insurance costs, more conservative routing decisions and greater interest in alternative corridors or bypass routes.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17680608/main.jpg
    Colin Foreman
  • Saudi Downtown awards Al-Khobar infrastructure deal

    15 July 2026

    Register for MEED’s 14-day trial access 

    Saudi Downtown Company, a wholly owned subsidiary of the Public Investment Fund (PIF), has awarded a contract for infrastructure works in downtown Al-Khobar.

    The contract was awarded to local contractor Ansab General Contracting Company.

    The scope of work includes the design and development of overall infrastructure, road networks and street lighting for the downtown Al-Khobar project.

    Saudi Downtown Company was officially launched in 2022 by Saudi Crown Prince Mohammed Bin Salman Bin Abdulaziz Al-Saud, who is also chairman of PIF.

    At the time, the company announced plans to develop downtown areas in 12 cities across the kingdom: Medina, Al-Khobar, Al-Ahsa, Buraidah, Najran, Jizan, Hail, Al-Baha, Arar, Taif, Dumat Al-Jandal and Tabuk.

    SDC’s mandate is to develop more than 10 million square metres of land across its projects

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17677176/main.jpg
    Yasir Iqbal
  • Saudi Arabia opens third round of gas-fired IPPs

    15 July 2026

    Register for MEED’s 14-day trial access 

    Principal buyer Saudi Power Procurement Company (SPPC) has opened the qualification process for the third round of conventional independent power projects (IPPs) using combined-cycle gas turbine (CCGT) technology.

    The round is being tendered under the supervision of the Ministry of Energy. Each plant will be built with provision for carbon capture unit readiness, allowing the technology to be deployed at a later stage.

    Each project will be developed on a build-own-operate (BOO) basis, with the winning consortium taking 100% equity in a special purpose vehicle (SPV) set up to develop and operate the plant.

    Each SPV will sign a power purchase agreement with SPPC, which is licensed by the Saudi Electricity Regulatory Authority (SERA) to prepare preliminary studies, tender and award IPPs, and purchase electricity from energy projects in the kingdom.

    The programme forms part of Saudi Arabia’s Circular Carbon Economy approach, which underpins the energy sector element of the Vision 2030 strategy. Riyadh is displacing liquid fuels with natural gas in power generation to cut emissions intensity, while designing new plants so that carbon capture equipment can be retrofitted in support of national emissions targets.

    In April, Acwa and Saudi Energy (formerly Saudi Electricity Company) signed a 31-year power purchase agreement (PPA) with SPPC for the Rabigh 2 IPP expansion.

    The project involves the development of a CCGT plant in the Mecca region. It will have a total capacity of 2,313.5MW.

    The contract is valued at SR11.5bn ($3.07bn), the companies said in separate stock exchange filings.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17676286/main.jpg
    Colin Foreman
  • Dubai selects contractor for Al-Maktoum airport people mover

    15 July 2026

     

    Register for MEED’s 14-day trial access 

    Dubai Aviation Engineering Projects (DAEP) has selected a contractor to deliver the automated people-mover system as part of the first phase of the $35bn expansion of Al-Maktoum International airport.

    A team of Japan’s Mitsubishi Corporation and Indian contractor Larsen & Toubro is the selected contractor.

    The automated people-mover system will serve as a critical facility for operations at Al-Maktoum International airport. The system will run under the apron of the entire airfield and the airport’s terminals. It will consist of multiple tracks, taking passengers from the terminals to the concourses.

    Four underground stations will be built as part of the first phase. The overall plan includes 14 stations across the airport.

    The firms submitted the bids for the project in July last year, as MEED exclusively reported.

    The contract is the latest in a series of awards signed by DAEP recently. DAEP has awarded contracts valued at about AED13bn, with construction works currently under way on several airport packages.

    These include enabling works, the second runway, and the initial structural foundations for passenger terminals and gates.

    Upcoming awards

    In June, DAEP said that it will award contracts worth over AED55bn ($15bn) by the end of this year for construction works at Al-Maktoum International airport.

    The projects slated for contract awards include the substructure works for the Western Passenger Terminal, the fourth aircraft concourse building and the baggage handling system, in addition to the superstructure works for the Western Passenger Terminal and the first, second and third aircraft concourses.

    The packages also encompass long-span structural frameworks for buildings covering about 1.5 million square metres (sq m), infrastructure works for the southern airfield area, and power generation and district cooling plants supporting the construction programme.

    The award of the facade and roofing packages is also planned for this year.

    Construction progress

    In May last year, MEED exclusively reported that DAEP had awarded a AED1bn ($272m) deal to UAE firm Binladin Contracting Group to construct the second runway at the airport.

    The enabling works on the terminal were awarded to Abu Dhabi-based Tristar E&C.

    Construction on the project’s first phase is expected to be completed by 2032.

    Construction on substructure works began in November last year, when DAEP formally selected a contractor to deliver the package.

    The government approved the updated designs and timelines for its largest construction project in April 2024.

    In a statement, the authorities said the plan is for all operations from Dubai International airport to be transferred to Al-Maktoum International within 10 years.

    According to an official description on DAEP’s website, the expanded airport’s West Terminal will be a seven-level, 800,000 sq m facility with an annual capacity of 45 million passengers.

    It will be the second of three terminals at Al-Maktoum International airport.

    In September 2024, MEED exclusively reported that a team comprising Austria’s Coop Himmelb(l)au and Lebanon’s Dar Al-Handasah had been confirmed as the lead masterplanning and design consultants on the expansion of Al-Maktoum airport.

    The airport’s construction is planned to be undertaken in three phases. The airport will cover an area of 70 square kilometres south of Dubai and will have five parallel runways and 430 aircraft gates.

    It will be five times the size of the existing Dubai International airport and will have the world’s largest passenger-handling capacity of 260 million passengers a year. For cargo, it will have the capacity to handle 12 million tonnes a year.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17674721/main.png
    Yasir Iqbal
  • Chinese contractor wins Kuwait investment authority HQ

    15 July 2026

    Register for MEED’s 14-day trial access 

    Beijing-headquartered China State Construction Engineering Corporation (CSCEC) has won a contract to build the permanent headquarters of the Kuwait Direct Investment Promotion Authority (KDIPA).

    The contract covers the construction of a 275-metre, 55-storey office tower located in Kuwait City’s Sharq district. The project is expected to be completed by 2028.

    According to results published on the Kuwait Central Agency for Public Tenders (Capt) website, the firm initially submitted a bid of $233m, as MEED reported in January. The tender was issued on 19 October 2025 and bids were submitted on 18 November, MEED reported.

    The contract is the latest in a series of high-profile projects signed by CSCEC in the GCC region this year. Last month, it won a contract to deliver the Janadriyah cultural district at Qiddiya entertainment city on the outskirts of Riyadh. The contract was awarded by gigaproject developer Qiddiya Investment Company (QIC).

    The scope covers the construction of six structures, including a heritage building, a gateway hotel, a wadi hotel, a creative hub, a community centre and an open-air market.

    In June, MEED exclusively reported that QIC had awarded CSCEC a contract to build a new transport hub at Qiddiya entertainment city.

    The project is located within the resort core zone of the development.

    Kuwait market overview

    UK analytics firm GlobalData expects Kuwait’s construction industry to average annual growth of 4.9% in 2026-29, supported by government investment in renewable energy and transport infrastructure.

    In September 2025, Kuwait’s government allocated KD1.3bn ($4.2bn) for 141 projects, as part of its capital spending during the fiscal year 2025-26. This allocation was intended for 162 current projects and 17 new projects.

    According to government data, as of September 2025, the country had around 300 active projects, valued at about KD35.3bn ($115bn), with large infrastructure projects making up nearly half of that total.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17674440/main.jpg
    Yasir Iqbal