Middle East project disputes increasing
8 November 2023

The number of project disputes recorded every year in the Middle East and North Africa (Mena) is trending upwards as project activity increases and the pressure grows to execute projects on a fast-track basis.
Greater use of fast-track project models, where project execution starts before all the details of the preparatory design work are complete, can lead to a “triple whammy” of design issues that trigger disputes, according to Jad Chouman, a partner and the head of Middle East for the consultancy HKA, which specialises in risk mitigation and dispute resolution.
The three key causes of disputes related to fast-track projects are changes to the scope, design information being issued late, and incomplete designs supplied to contractors.
“In many fast-track projects, they start work before the design is 100 per cent complete,” says Chouman. “The fast-track nature of these projects is a major reason why we are seeing what we refer to as the ‘triple design whammy’.
“Owners want the projects quickly and they push the contractors to start early, and changes to the designs can cause serious problems to the projects.”
Growing pains
Due to the expanding Mena projects market, increasing project complexity and growing tendency to use fast-track project schedules, Chouman says he would not be surprised to see an upturn in the volume of project disputes every year until 2030.
“The rise in disputes related to fast-track projects is something that we’ve noticed over the past two or three years,” he says.
“The very compressed time frames for projects means that if there is disruption due to a change or a delay to an approval, the overall impact of that delay is often magnified.”
HKA also says some contractors are not fully considering the impact of the shortage of skilled labour in the region when estimating how quickly projects can be executed.
While these are all significant challenges, HKA also has reason to believe that many of the disputes could be resolved amicably.
Saudi resolution
In Saudi Arabia, Chouman says a share of future disputes could be resolved amicably because the kingdom is so focused on rapid project execution and will want to avoid projects stalling due to drawn-out legal disputes.
“In order for projects to be successful and to be completed within a reasonable time period, it is in the interest of everyone that they are resolved amicably.”
Another factor that could reduce the number of legal disputes is the increased use of more collaborative contract models.
In these contracts, the parties share the risk. The main contractor usually gets involved in the project at an earlier stage so they have a say in how the design is created.
One model increasingly used in Saudi Arabia is the early contractor involvement (ECI) model.
Under the ECI model, a single contractor is selected at an earlier stage of the design process. This may be either at the concept or detailed design stages, depending on the employer client’s preference and the level of involvement required.
A key objective of using an ECI contract and selecting a contractor early is to allow the contractor to use its knowledge and experience to influence design decisions to increase buildability or value during the process.
The contractor is appointed by the client during the first stage to perform services similar to a professional consultant.
“One of the main positive impacts that this sort of contract is likely to have is avoiding the worst kind of disputes between clients and contractors,” says Chouman.
“At the end of the day, the leadership in Saudi Arabia wants to be successful and get things done, and because of this, they are going to want to try and resolve any delays or cost overruns in a fair and amicable way.
“There is significant project momentum in Saudi Arabia and they want to maintain this positive environment.”
Arbitration centres
Dispute resolution processes have progressed significantly in several key markets in the Mena region over the past 20 years, which is having a positive impact on the projects market, according to Chouman.
He says Dubai and Abu Dhabi have developed mature arbitration processes that are competitive with international dispute resolution centres across the world.
The systems are maturing in Saudi Arabia and will soon reach a similar level.
“The development of these advanced dispute resolution centres has helped to make the UAE an attractive business hub,” says Chouman.
But while dispute resolution processes in some Mena markets parallel other world-leading hubs, the Middle East, on the whole, performs poorly in terms of project delays.
According to data collected by HKA, the average delay for projects in the Middle East is 82 per cent of the original time schedule.
This is high compared to the US, Europe, Asia and Oceania, where the average delay times are 59 per cent, 60 per cent, 63 per cent and 49 per cent.
Africa is the only continent that performs worse than the Middle East, with average project delays of 83 per cent of the original project schedule.
A key reason for the significant delays in the Middle East is the size of the projects market and complexity of the projects, says Chouman.
“It is a market with a lot of ambitious projects both in terms of size and complexity,” he says. “Additionally, the clients and contractors are also being even more optimistic with their predictions for project completion times, which is a factor.”
With the Mena region’s projects market continuing to expand rapidly, there are plenty of opportunities for contractors. However, there is also a growing scope for delays and disputes over project execution.
As the region’s biggest markets push ahead with ambitious project plans, it remains to be seen whether they have put enough thought into dispute resolution frameworks and methods to keep construction issues out of the courts.
Exclusive from Meed
-
Dubai seeks consultants for drainage projects6 February 2026
-
Modon tenders Ras El-Hekma construction contracts6 February 2026
-
Egypt contractor secures €58m loan for Hungary power plant6 February 2026
-
AD Ports signs Jordan Aqaba port PPP deal6 February 2026
-
Chinese firm wins Ceer automotive supplier park deal6 February 2026
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Dubai seeks consultants for drainage projects6 February 2026
Dubai Municipality has invited consultants to qualify for a contract to supervise three stormwater drainage projects under the $8bn Tasreef programme.
The contract, titled TF-15-S1 Supervision of Stormwater Drainage System projects – Package 2, will be awarded as a single package with dedicated teams assigned to each project.
The request for qualifications (RFQs) was issued by the municipality’s Sewerage and Recycled Water Projects Department (SRPD).
The bid submission deadline is 26 February.
The first scheme under the package is TF-16-C1, which involves upgrading and rehabilitating the stormwater system east of the Dubai Canal.
The second, TF-15-C2, will deliver stormwater links along Umm Suqeim Road to serve the Al-Barsha and Al-Quoz communities.
The third project, TF-13-C1, focuses on developing a drainage system for the Al-Marmum area.
Several engineering, procurement and construction (EPC) contracts have been awarded under the Tasreef initiative, which aims to expand Dubai’s rainwater drainage capacity by 700% by 2033
In January, local firm DeTech Contracting won the main contract to construct a stormwater drainage system in Jebel Ali.
The project, listed under TF-05-C1, covers approximately 27 kilometres of stormwater network and will serve major transport routes, including Sheikh Zayed Road and Al-Jamayel Road.
Separately, Dubai Municipality has opened bidding for EPC contracts to expand and rehabilitate the emirate’s sewerage networks.
The four projects cover more than 95km of recycled water and sewerage pipelines.
READ THE FEBRUARY 2026 MEED BUSINESS REVIEW – click here to view PDFSpending on oil and gas production surges; Doha’s efforts support extraordinary growth in 2026; Water sector regains momentum in 2025.
Distributed to senior decision-makers in the region and around the world, the February 2026 edition of MEED Business Review includes:
> AGENDA: Mena upstream spending set to soar> INDUSTRY REPORT: MEED's GCC water developer ranking> INDUSTRY REPORT: Pipeline boom lifts Mena water awards> MARKET FOCUS: Qatar’s strategy falls into place> CURRENT AFFAIRS: Iran protests elevate regional uncertainty> CONTRACT AWARDS: Contract awards decline in 2025> LEADERSHIP: Tomorrow’s communities must heal us, not just house us> INTERVIEW: AtkinsRealis on building faster> LEADERSHIP: Energy security starts with rethinking wasteTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/15593832/main.jpg -
Modon tenders Ras El-Hekma construction contracts6 February 2026

Abu Dhabi-based developer Modon Holding has tendered several contracts as part of the first phase of development at Ras El-Hekma, a planned new city on Egypt’s Mediterranean coast.
MEED understands that the tenders were issued in January.
These include:
DP3 assets: covering 146 residential villas, 590 three-bedroom townhouses, 356 four-bedroom townhouses, a mall and other associated works.
Bids due on 23 February.
DP4 assets: DP4 includes 54 villas, a clubhouse and other associated infrastructure.
Bids due on 2 March.
DP5 assets: The scope covers the construction of two hotels, branded residences, a retail facility and other associated works.
Bids due on 10 March.
DP6 assets: This package covers a 200-key Montage hotel, 96-unit Montage-branded residences and related infrastructure.
Bids due on 17 March.
DP7 assets: 120 five-bedroom villas, 230 seven-bedroom villas, 284 branded residential units and other infrastructural works.
Bids due on 3 March.
MEED understands that the contract duration for all these packages is 21 months from the start of construction.
Modon has accelerated development works at Ras El-Hekma this year. In January, MEED reported that Modon Holding had awarded a E£15bn ($316m) contract for the construction of a project at Ras El-Hekma.
The contract was awarded to the local firm Orascom Construction.
The scope of the contract covers the construction of residential units, commercial facilities and a 70-key hotel.
In September, MEED reported that Modon Holding had tendered contracts for the infrastructure works for the first phase of the Ras El-Hekma project.
As part of the first phase, Modon plans to develop more than 50 million square metres (sq m), including hotels and a marina.
Ras El-Hekma is on a spur of land on Egypt’s northern Mediterranean coastline, about 240 kilometres west of Alexandria.
Last year, Abu Dhabi-based holding company ADQ appointed Modon Holding as the master developer for the Ras El-Hekma project.
According to an official statement, Modon will act as the master developer for the entire development, which will cover more than 170 million sq m.
Modon Holding will develop the first phase of the project, which will cover 50 million sq m.
The remaining 120 million sq m will be developed in partnership with private developers under the supervision of the recently established ADQ subsidiary Ras El-Hekma Urban Development Project Company and Modon Holding.
In September 2024, Modon signed several memorandums of understanding (MoUs) with local and international firms to join the development. It signed a framework agreement with Orascom Construction to serve as the primary contractor for the project’s first phase.
Ras El-Hekma is planned as a combined business and leisure destination, with hotels, leisure facilities, a free zone, a financial district and residential components.
The master development has been billed as capable of attracting over $150bn in investment.
READ THE FEBRUARY 2026 MEED BUSINESS REVIEW – click here to view PDFSpending on oil and gas production surges; Doha’s efforts support extraordinary growth in 2026; Water sector regains momentum in 2025.
Distributed to senior decision-makers in the region and around the world, the February 2026 edition of MEED Business Review includes:
> AGENDA: Mena upstream spending set to soar> INDUSTRY REPORT: MEED's GCC water developer ranking> INDUSTRY REPORT: Pipeline boom lifts Mena water awards> MARKET FOCUS: Qatar’s strategy falls into place> CURRENT AFFAIRS: Iran protests elevate regional uncertainty> CONTRACT AWARDS: Contract awards decline in 2025> LEADERSHIP: Tomorrow’s communities must heal us, not just house us> INTERVIEW: AtkinsRealis on building faster> LEADERSHIP: Energy security starts with rethinking wasteTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/15593388/main.jpg -
Egypt contractor secures €58m loan for Hungary power plant6 February 2026
Commercial International Bank Egypt (CIB) has provided €58m in credit facilities to local firm Elsewedy Electric for the construction of a combined-cycle gas turbine (CCGT) power plant in Hungary.
Located in Visonta, the plant will be the largest combined-cycle facility built in Hungary in decades and the country’s first power plant capable of using hydrogen.
Once complete, hydrogen will be able to supply up to 30% of the plant’s fuel needs.
The project is being developed through a consortium comprising Energy Projects, a subsidiary of Elsewedy Electric, and local firms Status KPRIA and West Hungaria Bau (WHB).
It was awarded by MVM Matra Energia, a subsidiary of Hungary’s state-owned power holding company Magya Villamos Muvek (MVM).
As MEED understands, the plant is expected to have a power generation capacity of between 500MW and 650MW.
Total investment in the scheme is estimated at about €700m, with CIB acting as the sole financier for Elsewedy Electric’s portion of the project.
Construction officially began last September, with commercial operations scheduled for 2028.
The scheme also represents Elsewedy Electric’s first major investment in Europe, adding to other foreign investment interests.
Last May, it was reported that Elsewedy Electric intends to build a $100m electrical cable manufacturing plant in Iraq. This project has yet to advance beyond the initial stages.
In 2024, the contractor connected three additional hydro turbine generators to Tanzania’s national power grid in partnership with The Arab Contractors.
This brought the total power supply from the Julius Nyerere hydroelectric power project to 705MW.
READ THE FEBRUARY 2026 MEED BUSINESS REVIEW – click here to view PDFSpending on oil and gas production surges; Doha’s efforts support extraordinary growth in 2026; Water sector regains momentum in 2025.
Distributed to senior decision-makers in the region and around the world, the February 2026 edition of MEED Business Review includes:
> AGENDA: Mena upstream spending set to soar> INDUSTRY REPORT: MEED's GCC water developer ranking> INDUSTRY REPORT: Pipeline boom lifts Mena water awards> MARKET FOCUS: Qatar’s strategy falls into place> CURRENT AFFAIRS: Iran protests elevate regional uncertainty> CONTRACT AWARDS: Contract awards decline in 2025> LEADERSHIP: Tomorrow’s communities must heal us, not just house us> INTERVIEW: AtkinsRealis on building faster> LEADERSHIP: Energy security starts with rethinking wasteTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/15593289/main.jpg -
AD Ports signs Jordan Aqaba port PPP deal6 February 2026
Abu Dhabi’s AD Ports Group has signed an agreement with Jordan’s Aqaba Development Corporation (ADC) to manage and operate the Aqaba multipurpose port.
AD Ports will manage and operate the port under a 30-year concession agreement.
Under the agreement, AD Ports and ADC will establish a joint venture to oversee port operations.
AD Ports will hold a 70% stake in the joint venture, with the remaining 30% held by ADC.
AD Ports Group will also invest AED141m ($38.4m) in the joint venture.
The signing ceremony was held at the Aqaba Special Economic Zone Authority headquarters in Aqaba on 5 February.
The agreement was signed by Hussein Safadi, CEO of ADC, and Ahmed Al-Mutawa, regional CEO of AD Ports Group.
Aqaba port handles about 80% of Jordan’s exports and 65% of its imports.
It serves as a key transit point for Jordan’s neighbouring countries, including Saudi Arabia and Iraq. The port has an annual handling capacity of 11 million tonnes, supported by nine berths, a quay length of 2 kilometres and a draft of 13.5 metres.
In 2025, the terminal handled over 5.3 million tonnes of cargo and nearly 85,000 car equivalent units of Ro-Ro imports.
Abu Dhabi has been deeply involved in making investments in Jordan’s infrastructure sector. In February last year, AD Ports Group signed an agreement to manage and operate the Al-Madouneh customs centre in Amman, as MEED reported.
The Al-Madouneh customs centre covers about 1.3 million square metres (sq m) and was inaugurated in June last year.
The announcement followed AD Ports Group’s signing of a shareholders’ agreement in January 2024 between its digital arm, Maqta Gateway, and Jordan’s Aqaba Development Corporation regarding their existing joint-venture company, Maqta Ayla.
The joint venture company will upgrade operations at the Aqaba port complex in Jordan by implementing a port community system “that leverages Maqta Gateway’s expertise, also marking the first-ever export of Abu Dhabi’s key port digitalisation solution”, AD Ports said in a statement.
AD Ports Group operates the Aqaba cruise terminal, and selected Dubai-based real estate developer Mag Group to lead the first phase of the Marsa Zayed mixed-use project.
READ THE FEBRUARY 2026 MEED BUSINESS REVIEW – click here to view PDFSpending on oil and gas production surges; Doha’s efforts support extraordinary growth in 2026; Water sector regains momentum in 2025.
Distributed to senior decision-makers in the region and around the world, the February 2026 edition of MEED Business Review includes:
> AGENDA: Mena upstream spending set to soar> INDUSTRY REPORT: MEED's GCC water developer ranking> INDUSTRY REPORT: Pipeline boom lifts Mena water awards> MARKET FOCUS: Qatar’s strategy falls into place> CURRENT AFFAIRS: Iran protests elevate regional uncertainty> CONTRACT AWARDS: Contract awards decline in 2025> LEADERSHIP: Tomorrow’s communities must heal us, not just house us> INTERVIEW: AtkinsRealis on building faster> LEADERSHIP: Energy security starts with rethinking wasteTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/15592973/main.jpg -
Chinese firm wins Ceer automotive supplier park deal6 February 2026

Beijing-headquartered Metallurgical Construction Corporation (MCC) has won a contract to undertake the steel structure works on the Ceer automotive supplier park in King Abdullah Economic City (KAEC).
The supplier park is located next to Ceer’s electric vehicle (EV) production facility in KAEC.
The automotive supplier park will include production and ancillary facilities for various suppliers and provide the material supply infrastructure for Ceer’s EV plant.
The facilities include:
- Cold stamping, body-in-white assembly and stamping facility – Shin Young (South Korea)
- Hot stamping, sub-frames and axles subsystem supply facility – Benteler Group (Austria)
- Façade and exterior-trim supply facility – JVIS (US)
- Instrument panel, trims and console supply facility – Forvia (France)
- Seat supplier – Lear Corporation (US)
Earlier this week, MEED exclusively reported that Ceer had awarded a contract to build the automotive supplier park to Jeddah-based construction firm Modern Building Leaders (MBL).
Netherlands-based engineering firm Arcadis is the project consultant, and Pac Project Advisors is the project management consultant.
Ceer retendered the project in September last year.
The latest contract award is another significant contract win for MCC in Saudi Arabia. In January, MEED reported that MCC had won a contract to undertake the steel structure works on Mohammed Bin Salman Stadium at the Qiddiya City project on the outskirts of Riyadh.
The 45,000-seat stadium will feature a fully combined retractable pitch, roof and LED wall.
The stadium’s main construction works are being undertaken by a joint venture of Spanish firm FCC Construction and local firm Nesma & Partners.
In January, MCC won another contract to undertake steel structure works for the expansion of Medina airport in Saudi Arabia.
The scope covers work on boarding bridges, Terminal Two and the renovation of Terminal One.
READ THE FEBRUARY 2026 MEED BUSINESS REVIEW – click here to view PDFSpending on oil and gas production surges; Doha’s efforts support extraordinary growth in 2026; Water sector regains momentum in 2025.
Distributed to senior decision-makers in the region and around the world, the February 2026 edition of MEED Business Review includes:
> AGENDA: Mena upstream spending set to soar> INDUSTRY REPORT: MEED's GCC water developer ranking> INDUSTRY REPORT: Pipeline boom lifts Mena water awards> MARKET FOCUS: Qatar’s strategy falls into place> CURRENT AFFAIRS: Iran protests elevate regional uncertainty> CONTRACT AWARDS: Contract awards decline in 2025> LEADERSHIP: Tomorrow’s communities must heal us, not just house us> INTERVIEW: AtkinsRealis on building faster> LEADERSHIP: Energy security starts with rethinking wasteTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/15592955/main.gif