Abu Dhabi to tender Project Wave phase two in 2024
30 October 2023
Abu Dhabi National Oil Company (Adnoc) and Abu Dhabi National Energy Company (Taqa) are expected to start the tendering process for the Al-Nouf seawater treatment plant and water collection and distribution network project in the second half of 2024.
It is the second public-private partnership (PPP) phase of Project Wave, which will replace the current aquifer water injection systems used to maintain reservoir pressure in all onshore oil fields in Abu Dhabi.
According to a source close to the project, the tender could be issued to qualified developers between the middle and end of 2024.
Like the first-phase Mirfa seawater treatment plant, the Al-Nouf facility will be developed and maintained as a build-own-operate-transfer (BOOT) project.
The $2.2bn Mirfa water treatment plant reached financial close in September.
Adnoc and Taqa awarded the 30-year BOOT contract for the Mirfa scheme to a team of Egypt's Orascom Construction and Metito in May this year.
Adnoc and Taqa will hold a joint majority stake of 51 per cent in the project company, while the developer consortium will hold the remaining 49 per cent.
The Orascom-Metito team will develop and operate the facilities to treat and supply seawater for Adnoc's operations at the Bab and Bu Hasa fields in Abu Dhabi.
The Mirfa plant package involves the development of a nanofiltration plant with a capacity of 115 million imperial gallons a day (MIGD) in Mirfa.
The package also includes the plant's seawater intake and outfall facilities, two pumping stations, a 75-kilometre water transmission pipeline and 230 kilometres of distribution pipelines to the Bab and Bu Hasa oil fields.
The project is expected to reduce the water injection-related energy consumption of the oil fields by up to 30 per cent.
Orascom, Metito and Egypt's Petrojet will undertake the engineering, procurement and construction (EPC) works for the project.
Aquifer injection system
Project Wave aims to utilise seawater as an additional source for enhanced oil recovery-based injection into Abu Dhabi's onshore fields.
The Mirfa and Al-Nouf facilities were initially expected to have a total combined treatment capacity of about 210MIGD. This is understood to have been expanded.
Adnoc will be the sole offtaker of the treated seawater at the battery limit of the Adnoc Onshore fields.
A team of UK-based Alderbrook Finance and Saudi Arabia-based SMBC are the financial advisers to the client for the BOOT projects. Austria-headquartered ILF Consulting Engineers is the technical adviser.
In-field distribution
Engineering, procurement, construction and management (EPCM) work for a third component of Project Wave is under way.
Adnoc Onshore awarded Greece's Archirodon the EPCM contract for an in-field distribution network to disseminate treated seawater to water injection wells in Adnoc's onshore oil fields.
The EPCM contract will cover the replacement of an existing water injection infrastructure with a new treated seawater injection network, as well as the installation of sub-adits.
The contract awarded to Archirodon is for three years, with the client expected to tender the EPC work at some point during the duration of the contract.
MEED’s November 2023 special report on the UAE includes:
> COMMENT: UAE eyes global leadership role
> POLITICS: Abu Dhabi networks on the global stage
> ECONOMY: UAE economy maintains robust growth
> BANKING: UAE banks enjoy the good times
> UPSTREAM: Hail and Ghasha galvanises UAE upstream market
> DOWNSTREAM: Adnoc spurs downstream gas expansions
> POWER: UAE closes ranks ahead of Cop28
> WATER: UAE ramps up decarbonisation of water sector
> PROJECTS: Top 10 UAE clean energy projects
> CONSTRUCTION: UAE construction sector returns to form
> TRANSPORT: UAE aviation returns to growth
Exclusive from Meed
-
Adnoc-Covestro deal decision due in May
2 April 2025
-
Edgnex acquires Nordic data centre developer
2 April 2025
-
Developers prepare Saudi round six solar IPP bids
2 April 2025
-
Iraq approves two major energy project contracts
2 April 2025
-
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends

Related Articles
-
Adnoc-Covestro deal decision due in May
2 April 2025
EU antitrust regulators are expected to decide by 12 May whether to clear or extend the review of Abu Dhabi National Oil Company's (Adnoc) €15.9bn ($17.1bn) takeover of German chemicals producer Covestro.
The 27-country EU competition enforcer can either clear the deal with or without conditions, or open a four-month investigation after its preliminary review, a Reuters report said, citing a filing on the European Commission's website.
It was reported in October last year that Adnoc International, the overseas business arm of Adnoc Group, had signed an investment agreement Covestro in which it made a takeover offer of €14.7bn.
Adnoc International said at the time that it will launch a voluntary public takeover of €62 ($69) a share, which implies an equity value for Covestro of about €11.7bn and represents a premium of about 54% to Covestro’s closing price on 19 June, the day before the first media coverage regarding a potential transaction.
Leverkusen-headquartered Covestro’s supervisory and management boards supported the takeover offer.
In addition, Adnoc International will subscribe to a 10% non-preemptive capital increase of €1.17bn in Covestro at the closing of the transaction.
The offer will be subject to a minimum acceptance level of 50% plus one share and customary closing conditions, including merger control, foreign investment control and EU foreign subsidies clearances, the companies said.
The agreement between Adnoc International and Covestro, which runs until the end of 2028, contains several obligations on the part of the Abu Dhabi energy producer, including maintaining Covestro’s existing business activities, corporate governance and organisational business structure.
Adnoc approached Covestro about a potential takeover in September 2023, but initial advances were rejected, leading the Abu Dhabi state enterprise to raise the value of its offer.
Adnoc’s initial approaches included a takeover price of €55 and then €57 a share, Bloomberg News reported at the time.
Covestro’s expertise lies in chemicals recycling, which is key for the future of the energy industry and a target area for Adnoc.
Russia's invasion of Ukraine in 2022 slashed deliveries of natural gas to Germany, resulting in a crisis that gripped the German chemicals industry, which accounts for about 5% of the country’s GDP.
Precedent
In September, the European Commission approved the takeover of the telecommunications assets of Czech investment group PPF by UAE telecoms group e&.
Sovereign wealth fund Emirates Investment Authority holds a 60% stake in e&. The commission's review concluded that the “subsidies received by e& did not lead to actual or potential negative effects on competition in the acquisition process”.
https://image.digitalinsightresearch.in/uploads/NewsArticle/13602719/main.jpg -
Edgnex acquires Nordic data centre developer
2 April 2025
Register for MEED’s 14-day trial access
Edgnex, a subsidiary of Dubai-based property developer Damac, has acquired Helsinki-headquartered data centre-focused real estate developer Hyperco as part of its European expansion strategy.
Damac announced the acquisition on 31 March.
Hyperco operates data centres in Finland and Sweden, "leveraging the region’s renewable energy sources, mature digital ecosystem and high connectivity", local media reports said.
Hyperco's three co-founders and existing team will continue to lead operations through the next phase of growth, according to a statement by the company.
Hussain Sajwani, founder of Damac Group, said his firm plans to "build a significant future capacity in the Nordics and establish a strong foothold in the market".
Edgnex’s recent European activities include a €150m ($161.9m) joint venture in Greece with Public Power Corporation to develop a 12.5MW facility, expandable to 25MW, and a €400m commitment to build a 40MW data centre in Madrid, Spain.
In January, Sajwani pledged $20bn to develop data centres in the US.
Sajwani and then US President-Elect Donald Trump announced the plan on 7 January in Florida, a day after the US Congress certified Trump as the winner of the 2024 presidential election.
The project’s initial phase covers establishing data centres in Texas, Arizona, Oklahoma, Louisiana, Ohio, Illinois, Michigan and Indiana.
It was previously reported that the Dubai-based property developer plans to develop $1bn-worth of data centres in countries in Europe, Asia, Africa, the Middle East and the Commonwealth of Independent States.
Edgnex is constructing two data centre facilities in Dammam and Riyadh in Saudi Arabia that will deliver 55MW in 2025. There are also plans for a data centre in Amman, Jordan, and another in Turkiye in partnership with Vodafone.
In May, Damac announced its entry into the Indonesian market with plans to build a 15MW data centre in Jakarta. The first construction phase for the facility is scheduled to be completed in the fourth quarter of 2025.
https://image.digitalinsightresearch.in/uploads/NewsArticle/13602668/main1456.jpg -
Developers prepare Saudi round six solar IPP bids
2 April 2025
Register for MEED’s 14-day trial access
Prequalified developers are forming teams to bid for the contracts to develop solar farms under the sixth round of Saudi Arabia's National Renewable Energy Programme (NREP).
MEED understands that bids are due for the four solar photovoltaic (PV) independent power projects (IPPs) by 1 June.
The four solar IPPs have a combined capacity of 3,000MW.
A 1,400MW solar PV IPP will be located in Najran, while the smallest – the 400MW Al-Sufun solar IPP – will be in Hail.
The 600MW Samtah and 600MW Al-Darb solar IPPs will be located in Jizan, a region that has been placed under security-related travel alerts by some countries and international firms.
Most of the prequalified bidders participated in site visits, which Saudi Arabia’s principal buyer, Saudi Power Procurement Company (SPPC), conducted in late January.
SPPC prequalified 16 companies that can bid as managing and technical members for the solar PV contracts. These are:
- Abu Dhabi Future Energy Company (Masdar, UAE)
- Alfanar Company (local)
- EDF Renewables (France)
- Kahrabel (Engie, France)
- FAS Energy (local)
- Jinko Power (Hong Kong)
- Korea Electric Power Corporation (Kepco, South Korea)
- Marubeni Corporation (Japan)
- Nesma Renewable Energy (local)
- SPIC Hunaghe Hydropower Development (China)
- Sumitomo Corporation (Japan)
- TotalEnergies Renewables (France)
- AlJomaih Energy & Water (local)
- Sembcorp Utilities (Singapore)
- AlGihaz Holding Company (local)
- Korea Western Power Company (Kowepo, South Korea)
The following five companies have been prequalified to bid as managing partners:
- Jera Nex (Japan)
- Power Construction Corporation of China (PowerChina)
- China Power Engineering Consulting Group International Engineering (China)
- Posco International (South Korea)
- Saudi Electricity Company (SEC, local)
Round six of the NREP will have a total combined capacity of 4,500MW, including the 1,500MW Dawadmi wind farm, for which a separate set of bidders has been prequalified.
SPPC issued the prequalification request for round six of the NREP in September last year and received statements of qualifications from interested developers and developer consortiums the following month.
SPPC is responsible for the pre-development, tendering and subsequent offtaking of the energy from the projects.
US/India-based Synergy Consulting is the client's financial adviser for the NREP sixth-round tender. Germany’s Fichtner Consulting and US-headquartered CMS are the technical and legal consultants, respectively.
https://image.digitalinsightresearch.in/uploads/NewsArticle/13602412/main0154.jpg -
Mitsubishi Power confirms Rumah 1 and Nairiyah 1 deal
2 April 2025
Register for MEED’s 14-day trial access
Mitsubishi Power, part of Japan’s Mitsubishi Heavy Industries, has confirmed it has received two orders to supply six M501JAC gas turbines for the Rumah 1 and Al-Nairiyah 1 power generation projects in Saudi Arabia.
Rumah 1 is located in the Central Region in Riyadh and is part of the previously planned Riyadh Power Plant 15. Nairiyah 1 is located in the Eastern Region.
The scope includes the supply of generators and auxiliary equipment, Mitsubishi Power said in a statement.
MEED exclusively reported that the Japanese original equipment manufacturer had been selected to supply its gas turbines for the independent power project (IPP) in November last year.
A consortium comprising the local Saudi Electricity Company (SEC) and Acwa Power and South Korea’s Korea Electric Power Corporation (Kepco) won the contract to develop the Rumah 1 and Al-Nairiyah 1 IPP the same month.
The power plants will deliver a combined 3.6GW, accounting for nearly 2.5% of the national grid’s capacity.
The M501JAC turbines will be assembled at Mitsubishi Power Saudi Arabia’s Dammam factory.
The 17,730 square-metre facility also provides services for gas turbine components.
According to Mitsubishi Power, the plant features "a majority of Saudi employees, in line with the firm’s Saudi National programme".
China’s Sepco 3 and South Korea's Doosan Enerbility will undertake the engineering, procurement and construction (EPC) contract for the projects, as MEED reported.
The SEC, Acwa Power and Kepco team offered a levelised electricity cost (LCOE) of $cents 4.5859 a kilowatt-hour ($c/kWh) for Rumah 1 and 4.6114 $c/kWh for Al-Nairiyah 1.
Acwa Power said that the two IPPs will require a combined investment of approximately SR15bn ($4bn). The IPPs are expected to reach commercial operations in Q2 2028.
Saudi Power Procurement Company (SPPC) received bids for the contracts for four thermal IPPs – the other two being the similarly configured Rumah 2 and Al-Nairiyah 2 – in August last year.
The four power generation facilities will be developed using a build, own and operate model over 25 years.
SPPC’s transaction advisory team for the Rumah 1 and 2 and Al-Nairiyah 1 and 2 IPP projects comprises US/India-based Synergy Consulting, Germany’s Fichtner and US-headquartered Baker McKenzie.
Photo credit: Mitsubishi Power (for illustrative purposes only)
https://image.digitalinsightresearch.in/uploads/NewsArticle/13599792/main4910.jpg -
Iraq approves two major energy project contracts
2 April 2025
Register for MEED’s 14-day trial access
Iraq’s Council of Ministers has approved two major energy contracts that form part of the $10bn Gas Growth Integrated Project (GGIP), according to a statement from the prime minister’s office.
French oil and gas company TotalEnergies and its partners are developing the GGIP.
TotalEnergies is the main operator of the GGIP. Basra Oil Company (30%) and QatarEnergy (25%) are the other stakeholders.
One of the two awarded contracts is focused on the development of the Ratawi gas field and the other is focused on the Common Seawater Supply Project (CSSP), which will transport seawater to oil fields for injection to increase production.
The statement said that Iraq's Council of Ministers had approved the award of tender CSSP-ITT-06 from state-owned Basra Oil Company to China Petroleum Pipeline Engineering Corporation (CPP).
The contract awarded to CPP is for the pipeline package, which involves the construction of a seawater pipeline.
MEED reported that CPP was a frontrunner to win the pipeline package in May last year.
CPP is a subsidiary of China National Petroleum Corporation and the primary builder of pipelines in its home country.
The pipeline package is one of two major packages in the CSSP. The other major package focuses on developing a water processing facility.
The pipeline contract awarded to CPP will be executed over 54 months, including 42 months for engineering, procurement and construction and 12 months for operation, maintenance and training.
The second contract that has been approved is for a planned gas processing plant at the Ratawi gas processing complex project.
The Ratawi field is also sometimes called the Artawi field.
This contract has been awarded by Iraq’s state-owned South Gas Company to China Petroleum Engineering & Construction Corporation (CPECC).
In January, MEED revealed that CPECC had emerged as the frontrunner to win the contract, which is estimated to be worth about $1.7bn.
When commissioned, the planned facility is expected to process 300 million cubic feet a day of gas. Its capacity is expected to double when a second expansion phase becomes operational in the future.
The Ratawi gas processing facility project aims to improve Iraq’s electricity supply by capturing gas that would have otherwise been flared at several oil fields, including:
- Luhais
- Majnoon
- Ratawi
- West Qurna 2
- Tuba
Large gas volumes are flared from these oil fields, causing significant environmental damage. Collecting and processing flared gas will generate increased hydrocarbons revenues and reduce ecological damage.
The gas tapped and processed from the oil fields will then be used to supply power plants, helping to reduce Iraq’s power import bill.
As well as supplying Iraq’s national gas network to generate electricity, the Ratawi gas processing complex will increase the production of gas products, including liquefied petroleum gas (LPG) and condensates.
US-based consultant KBR has performed the front-end engineering and design work on the project.