Adnoc spurs downstream gas expansions

13 October 2023

This package on the UAEs downstream sector also includes: 

Adnoc Gas picks site for planned LNG terminal
Adnoc Gas receives prices for Estidama package
> Adnoc and Dusup sign key gas supply agreement

Adnoc receives bids for gas pipeline packages
> Adnoc receives prices for sales gas pipeline packages
Adnoc Gas awards $3.6bn Project Meram contract


 

Demand for natural gas has risen exponentially in this decade, with its share in the global energy mix set to grow further in the decades to come.

Regional energy producers are deploying major capital expenditure programmes to increase their gas production and processing capabilities to cater to growing demand.

The UAE is striving to achieve self-sufficiency in gas production by 2030. With this objective in mind, Abu Dhabi National Oil Company (Adnoc) has committed significant investment towards expanding its midstream and downstream gas capabilities.

These projects seek to increase the availability of gas for utility providers and industrial customers in the UAE and ramp up ethane output to grow the country’s petrochemical sector and its derivatives ecosystem.

Hail and Ghasha galvanises UAE upstream market

Ruwais LNG project

Adnoc Gas, the gas processing business of Adnoc, has finalised the location for its planned liquefied natural gas (LNG) export terminal. The facility will have the capacity to produce about 9.6 million tonnes a year (t/y) of LNG from two processing trains, each with a capacity of 4.8 million t/y.

The overall value of the planned project is estimated to be upwards of $4.5bn, based on capital expenditure by operators on similar schemes worldwide.

Adnoc Gas received technical bids from contractors in May for the engineering, procurement and construction (EPC) works on the project, which will be built in Ruwais Industrial City in Abu Dhabi’s Al-Dhafrah region.

Adnoc Gas had originally planned to build the LNG terminal in the UAE emirate of Fujairah, which sits outside the Strait of Hormuz on the coast of the Gulf of Oman. In early May, however, the company announced it was shifting the location of the project from Fujairah to Ruwais, Abu Dhabi.

Sales gas pipeline network

Adnoc Gas is progressing the Estidama project, which is crucial to enhancing Adnoc’s sales gas pipeline network across the UAE. The project aims to cater to rising demand for gas from industrial consumers across the UAE, particularly in the Northern Emirates.

Contractors submitted commercial bids in August for combined package numbers 4 and 7. The combined package involves laying a new pipeline from the Al-Shuwaib pig launcher and pig receiver station to the Sajaa gas facility in Sharjah.

The scope also covers building a new gas pipeline between BVS-2/KP28.7 in Abu Dhabi to Dubai’s Margham gas facility to meet increased gas demand from Adnoc Gas’ customer Dubai Supply Authority (Dusup).

EPC works on the estimated $2bn-plus Estidama project have been divided into seven packages. Abu Dhabi-based contractor Integrated Specialised General Contracting Company (Iscco) won package 1, understood to have a contract value of $18m, in December 2021.

In early July, Adnoc Gas awarded contracts worth a combined $1.34bn for two other packages of the Estidama project. UK-headquartered Petrofac was awarded the EPC contract for package 2 of the Estidama project, estimated to be worth $720m.

A consortium of Abu Dhabi’s National Petroleum Construction Company (NPCC) and Lebanon-headquartered CAT Group won Estidama package 3, which is valued at about $630m.

Contractors submitted technical bids for package 6 in August 2022 and commercial bids by 21 November. Work on package 6 entails the installation of a 52-inch, 74-kilometre pipeline from Sweihan to Al-Shuwaib in Abu Dhabi and building two block valve stations.

Package 5 is expected to be tendered separately to contractors as part of a planned second phase of the sales gas pipeline upgrade project.

As per the original project schedule, EPC works on the Estidama project are due to be completed in 2025.

Ramping up ethane output

Adnoc Gas is in charge of one of the world’s largest gas processing complexes in Abu Dhabi, with the capacity to process about 8 billion cubic feet a day from its Asab, Bab, Bu Hasa, Habshan and Ruwais plants.

Increased volumes of ethane production will allow the company to commercialise it to supply feedstock to Borouge for its under-construction Borouge 4 petrochemicals complex, as well as to derivatives plants in the upcoming Taziz complex. Adnoc Gas intends to achieve this through the Maximise Ethane Recovery & Monetisation (Meram) project.

Adnoc Gas awarded a $3.6bn contract for Project Meram to a consortium of NPCC and Spanish contractor Tecnicas Reunidas in early August, with EPC work on the project starting later that month. The scope of work on the contract includes commissioning new gas processing facilities to enable an optimised supply to the Ruwais industrial complex, Adnoc Group said.

The strategic Meram project aims to achieve dual objectives, Adnoc stated.

The first goal is to increase ethane extraction by 35 to 40 per cent from Adnoc Gas’ existing onshore facilities in the Habshan gas processing complex by constructing new gas processing facilities.

The second goal is to unlock further value from existing feedstock and deliver it to Ruwais via a 120km natural gas liquids (NGL) pipeline.


LATEST NEWS FROM THE UAE's CHEMICALS SECTOR:
Lummus seeks to expand Abu Dhabi office
Firms express interest for Abu Dhabi methanol project
> Borouge and Borealis launch recycled products range
Fertiglobe makes $84m profit in second quarter
> Borouge announces $231m profit in second quarter
Adnoc opens formal chemicals integration talks with OMV


Taziz chemicals complex

Meanwhile, investors in the Taziz petrochemicals derivatives-producing industrial complex in Ruwais are pushing ahead with their projects.

Taziz – a 60:40 joint venture (JV) of Adnoc and Abu Dhabi’s industrial holding company ADQ – is overseeing the development of the sprawling industrial complex, which will mainly draw ethylene feedstock from the Borouge 4 facility to produce several in-demand chemicals.

A JV of UAE-based Fertiglobe, South Korea’s GS Energy and Japanese investment firm Mitsui awarded Italian contractor Tecnimont the main EPC contract for its planned blue ammonia project in the Taziz Industrial Chemicals Zone in February.

The JV has appointed KBR to provide the technology licence, basic engineering design, proprietary equipment and catalyst for the low-carbon ammonia plant, which will have a capacity of 1 million t/y.

India’s Reliance Industries is also an investor in the Taziz complex, having forged a partnership with Taziz and Abu Dhabi-based Shaheen Chem Holdings Investment to invest $2bn in developing three chemical plants producing chlor-alkali (940,000 t/y), ethylene dichloride (1.1 million t/y) and polyvinyl chloride (360,000 t/y).

Switzerland-based Proman has committed to building the UAE’s first methanol plant at Taziz, with a planned production capacity of 1.8 million t/y. The Proman-Taziz JV completed the contractor prequalification process for the EPC tendering round for the methanol production project in August. The operator is expected to issue the main EPC tender later this year.

As projects in the first phase of the chemicals complex move forward, Taziz is also understood to be gearing up for a second phase to more than double the number of chemicals produced at the derivatives hub.

https://image.digitalinsightresearch.in/uploads/NewsArticle/11214144/main.jpg
Indrajit Sen
Related Articles
  • Saudi Landbridge rail scheme to be delivered by 2034

    21 January 2026

    Register for MEED’s 14-day trial access 

    Saudi Arabia Railways (SAR) has said that it will deliver the Saudi Landbridge project through a "new mechanism" by 2034, after failing to reach an agreement with a Chinese consortium for the construction of the project.

    In an interview with local media, SAR CEO Bashar Bin Khalid Al-Malik said that the consortium failed to meet local content requirements, and the project will now be delivered in several phases through a different procurement model.

    The project has been under negotiation between Saudi Arabia and China-backed investors keen to develop it on a public-private-partnership basis.

    Al-Malik said that the project cost is about SR100bn ($26.6bn).

    It comprises more than 1,500 kilometres (km) of new track. The core component is a 900km new railway between Riyadh and Jeddah, which will provide direct freight access to the capital from King Abdullah Port on the Red Sea.

    Other key sections include upgrading the existing Riyadh-Dammam line, a bypass around the capital called the Riyadh Link, and a link between King Abdullah Port and Yanbu.

    The Saudi Landbridge is one of the kingdom’s most anticipated project programmes. Plans to develop it were first announced in 2004, but put on hold in 2010 before being revived a year later. Key stumbling blocks were rights-of-way issues, route alignment and its high cost.

    In April last year, MEED exclusively reported that SAR had issued a tender for the lead design consultancy services contract on the Saudi Landbridge railway network.

    MEED understands that the scope covered the concept design and options for the preliminary and issued-for-construction design stages on the network.

    MEED reported that the launch of a design tender directly by SAR suggested that Riyadh was looking at other options to develop it alongside the Chinese proposal.

    In December 2023, MEED reported that a team of US-based Hill International, Italy’s Italferr and Spain’s Sener had been awarded the contract to provide project management services for the programme.

    If it proceeds, the Saudi Landbridge will be one of the largest railway projects ever undertaken in the Middle East and one of the biggest globally. Based on typical design timeframes, tenders for construction are likely to be ready by mid-2026, although the question of how it will be financed will need to be answered before it can proceed to the next step.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/15475837/main.gif
    Yasir Iqbal
  • Firms submit bids for Dorra gas scheme PMC

    21 January 2026

     

    Register for MEED’s 14-day trial access 

    Engineering firms have submitted bids to Al-Khafji Joint Operations (KJO) for a tender covering project management consultancy (PMC) for the multibillion-dollar Dorra gas field facilities development project.

    MEED reported last March that KJO was pushing forwards with a project to produce gas from the Dorra offshore field, located in Gulf waters in the Neutral Zone shared by Saudi Arabia and Kuwait.

    KJO has divided the engineering, procurement and construction (EPC) scope of work on the project to produce gas from the Dorra field into four EPC packages – three offshore and one onshore.

    The broad scope of services under the tender involves providing PMC for EPC works for the Dorra gas facilities development project.

    Firms submitted bids for the PMC tender by the deadline of 19 January, sources told MEED.

    KJO issued the tender for PMC services for EPC works on the Dorra gas facilities development project on 29 September. Engineering firms were initially given until 24 November to submit bids for the tender, with that deadline then extended until 15 December and then finally until 19 January, according to sources.

    Sources said that the following firms, among others, are understood to be bidding for the PMC tender:

    • Fluor (US)
    • KBR (US)
    • Kent (Saudi Arabia/UAE)
    • Tecnicas Reunidas (Spain)
    • Wood (UK)
    • Worley (Australia)

    KJO hosted a job explanation meeting with the bidders for the tender on 15 October, the sources said.

    KJO offshore and onshore facilities

    KJO, which is jointly owned by Aramco subsidiary Aramco Gulf Operations Company (AGOC) and KPC subsidiary Kuwait Gulf Oil Company (KGOC), is moving forward with its Dorra gas field facilities project. KJO has divided the project’s scope of work into four EPC packages – three offshore and one onshore.

    Indian contractor Larsen & Toubro Energy Hydrocarbon (L&TEH) has won package 1 of the Dorra facilities project, which covers the EPC of seven offshore jackets and the laying of intra-field pipelines. The contract awarded by KJO to L&TEH is estimated to be valued between $140m and $150m, MEED reported in October.

    Contractors are presently preparing to submit bids for the remaining three packages — offshore packages 2A and 2B, and onshore package 3 by 26 January, sources told MEED. KJO has extended the bid submission deadlines for these packages multiple times.

    The EPC scope of work for package 2A includes Dorra gas field wellhead topsides, flowlines and umbilicals. Package 2B involves the central gathering platform complex, export pipelines and cables. Package 3 includes the EPC of onshore gas processing facilities.

    Saudi Arabia and Kuwait are pressing ahead with their ambitious plan to jointly produce 1 billion cubic feet a day (cf/d) of gas from the Dorra gas field, located in the waters of their shared Neutral Zone. Discovered in 1965, the Dorra gas field is estimated to hold 20 trillion cubic metres of gas and 310 million barrels of oil.

    Saudi Arabia and Kuwait have been producing oil from the Neutral Zone – primarily from the onshore Wafra field and offshore Khafji field – since at least the 1950s. With a growing need to increase natural gas production, both countries have been working to exploit the Dorra offshore field, understood to be the only gas field in the Neutral Zone.

    The Dorra facilities project is one of three major multibillion-dollar projects launched by subsidiaries of Saudi Aramco and Kuwait Petroleum Corporation (KPC) to produce and process gas from the Dorra field that have been advancing over the past few months.

    AGOC onshore Khafji gas plant

    Meanwhile, AGOC has extended the bid submission deadline for seven EPC packages as part of a project to construct the Khafji gas plant, which will process gas from the Dorra field onshore Saudi Arabia, until 22 April.

    MEED previously reported that AGOC had issued main tenders for the seven EPC packages earlier in 2025. Contractors were initially set deadlines of 24 October for technical bid submissions and 9 November for submission of commercial bids, which was then extended by AGOC until 22 December.

    The seven EPC packages cover a wide range of works, including open-art and licensed process facilities, pipelines, industrial support infrastructure, site preparation, overhead transmission lines, power supply systems, and main operational and administrative buildings.

    France-based Technip Energies has carried out a concept study and front-end engineering and design (feed) work on the entire Dorra gas field development programme.

    Progress has been hampered by a geopolitical dispute over ownership of the Dorra gas field. Iran, which refers to the field as Arash, claims it partially extends into Iranian territory and asserts that Tehran should be a stakeholder in its development. Kuwait and Saudi Arabia maintain that the field lies entirely within their jointly administered Neutral Zone – also known as the Divided Zone – and that Iran has no legal basis for its claim.

    In February 2024, Kuwait and Saudi Arabia reiterated their claim to the Dorra field in a joint statement issued during an official meeting in Riyadh between Kuwaiti Emir Sheikh Mishal Al-Ahmad Al-Jaber Al-Sabah and Saudi Crown Prince and Prime Minister Mohammed Bin Salman Bin Abdulaziz Al-Saud.

    Since that show of strength and unity, projects targeting production and processing of gas from the Dorra field have gained momentum.

    KGOC onshore processing facilities

    KGOC has initiated early engagement with contractors for the main EPC tendering process for a planned Dorra onshore gas processing facility, which is to be located in Kuwait.

    KGOC is in the feed stage of the project, which is estimated to be valued at up to $3.3bn, and is now expected to issue the main EPC tender in the second quarter of this year, MEED recently reported.

    The proposed facility will receive gas via a pipeline from the Dorra offshore field, which is being separately developed by KJO. The complex will have the capacity to process up to 632 million cf/d of gas and 88.9 million barrels a day of condensates from the Dorra field.

    The facility will be located near the Al-Zour refinery, owned by another KPC subsidiary, Kuwait Integrated Petroleum Industries Company (Kipic).

    A 700,000-square-metre plot has been allocated next to the Al-Zour refinery for the gas processing facility, and discussions regarding survey work are ongoing. The site may require shoring, backfilling and dewatering.

    The onshore gas processing plant will also supply surplus gas to KPC’s upstream business, Kuwait Oil Company (KOC), for possible injection into its oil fields.

    Additionally, KGOC plans to award licensed technology contracts to US-based Honeywell UOP and Shell subsidiary Shell Catalysts & Technologies for the plant’s acid gas removal unit and sulphur recovery unit, respectively.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/15472237/main3457.jpg
    Indrajit Sen
  • Libya announces $2.7bn Misurata Port expansion

    21 January 2026

    Register for MEED’s 14-day trial access 

    Libya has announced the $2.7bn expansion of Misurata Port, led by Terminal Investment Limited.

    The consortium comprises Switzerland's Mediterranean Shipping Company and Qatari firm Maha Capital Partners.

    The project is being implemented under a public-private partnership model, and is the first of its kind in the country's non-oil sector

    The expansion aims to increase the port's container-handling capacity to 4 million containers a year.

    Misurata Free Zone (MFZ) is Libya’s largest free zone, spanning an area of 2,576 hectares.

    According to an MFZ statement, the expansion includes:

    • Expanding container-handling capacity to accommodate larger vessels and more complex logistics chains;  
    • Integrating port operations with MFZ’s industrial ecosystem to support small and medium-sized entities, manufacturing and value-added services;
    • Deploying modern terminal equipment and digital systems;  
    • Enhancing safety, performance and environmental standards in line with global benchmarks;
    • Creating long-term employment opportunities.

    The Libyan Prime Minister’s Office said the expanded port is expected to generate around $600m in annual operating revenues, create about 8,400 direct jobs and support nearly 60,000 indirect jobs.

    The investment scope includes:

    • Five ship-to-shore (STS) gantry cranes
    • 10 mobile harbour cranes 
    • Eight rubber-tired gantry (RTG) cranes  
    • 32 reach stackers
    • Eight other pieces of equipment, like trucks and forklifts

    The project's first phase will raise container-handling capacity to 1.5 million 20-foot equivalent units (TEU), increase throughput by 7% and develop and manage berths to 2,000 metres in total.

    It also includes installing six RTG cranes and three STS cranes, developing 56 acres of container yards, building a 2,096-square-metre (sq m) refrigerated container warehouse and constructing an additional 7,500 sq m facility.

    An advanced terminal operating system will also be implemented.

    The second phase will add a further 2.5 million TEUs of capacity, construct a 2,500-metre breakwater, build a new 1,200-metre berth and a new 60-acre container yard, and deepen the port to 17 metres.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/15471059/main.jpg
    Yasir Iqbal
  • Ras Al-Khaimah awards sewage PPP contract

    20 January 2026

    A consortium of Abu Dhabi National Energy Company (Taqa), France’s Saur and the local Etihad Water & Electricity (Etihad WE) has signed a contract to develop and operate a wastewater treatment plant in the UAE’s northern emirate of Ras Al-Khaimah.

    The Rakwa wastewater infrastructure project is Ras Al-Khaimah’s first public-private partnership (PPP) for a sewage treatment plant.

    It is being developed in partnership with Ras Al-Khaimah’s Public Services Department and Investment & Development Office.

    The $120m project entails developing a wastewater treatment plant with a capacity of 60,000 cubic metres a day (cm/d), expandable to 150,000 cm/d. 

    On 9 January, MEED exclusively reported that the consortium was set to be awarded the contract. The consortium is being led by Ajman-based Emirates Utilities Development Company, a subsidiary of Etihad WE.

    US/India-based Synergy Consulting is the financial advisory consultant to Taqa and EtihadWE on this project.

    MEED previously reported that two bidding consortiums had submitted bids for the contract. The other bidding consortium comprised the UAE’s Metito Utilities and Omani firm Sogex.

    The scope of the build, own, operate and transfer scheme will include extensive sewerage and distribution works in addition to the main treatment plant.

    Future PPP project

    For its part, Etihad WE is preparing to procure another utility PPP project in Ras Al-Khaimah.

    The project involves expanding the capacity of an existing seawater reverse osmosis plant in Ghalilah, which became operational in 2015. 

    The state-owned utility recently appointed Austria’s ILF Consulting Engineers to provide technical advisory services for the project, which is expected to be tendered this year.

    If successfully procured, it will be the first independent water project in Ras Al-Khaimah.


    READ THE JANUARY 2026 MEED BUSINESS REVIEW – click here to view PDF

    Saudi Arabia courts real estate investment; EVs and battery production are key regional tech themes; Muscat holds a steady growth course despite headwinds

    Distributed to senior decision-makers in the region and around the world, the January 2026 edition of MEED Business Review includes:

    > ECONOMIC ACTIVITY INDEX: UAE and Qatar emerge as markets to watch
    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/15465691/main.jpg
    Mark Dowdall
  • Dubai tenders Al-Maktoum airport metro link

    20 January 2026

     

    Register for MEED’s 14-day trial access 

    Dubai's Roads & Transport Authority (RTA) has invited consultants to bid for the design contract for the Route 2020 extension.

    The extended line will start from the Expo 2020 metro station and connect with Al-Maktoum International airport's West Terminal.

    The extension to the line will run for about 3 kilometres (km) and will feature two stations.

    MEED understands that the invitation to bid was issued earlier in January with a submission deadline of mid-March.

    The existing Route 2020 metro link is a 15km-long line branching off the existing Red Line at Jebel Ali metro station. The line comprises 11.8km of elevated tracks, 3.2km of tunnels, and has five elevated stations and two underground stations.

    In 2016, the RTA awarded the AED10.6bn ($2.9bn) design-and-build contract for the project to a consortium of Spain's Acciona, Turkiye's Gulermak and France's Alstom.

    Dubai's plans for its metro network do not stop with connecting the extension of the Route 2020 metro line to Al-Maktoum International airport. There are long-term plans for further extensions.

    Other metro projects

    In October last year, MEED exclusively reported that the RTA had selected US-based engineering firm Aecom to provide consultancy services for the upcoming Dubai Metro Gold Line project, also known as Metro Line 4.

    The Gold Line will start at Al-Ghubaiba in Bur Dubai. It will run parallel to – and alleviate pressure on – the existing Red Line, before heading inland to Business Bay, Meydan, Global Village and residential developments in Dubailand.

    The other metro lines in the pipeline are the Purple Line and the Pink Line, both of which are in the early stages of development.

    Firms are also bidding to update the emirate’s rail masterplan. Also in October 2025, MEED reported that 10 firms had submitted offers to undertake the project.

    The rail masterplan study will update and modify the RTA’s rail network, which includes the Dubai Metro and Dubai Tram. These plans will support Dubai’s 2040 urban masterplan, which aims for all residents to be within a 30-minute metro or light-rail trip to their place of work. 

    The existing network includes the Red and Green lines of the Dubai Metro and the Dubai Tram, which connects Al-Sufouh and Dubai Marina to the metro network. The last rail project to start operations in Dubai was the Red Line extension that opened for Expo 2020.

    There are also existing and planned rail lines connecting Dubai to other emirates that are being developed and operated by Abu Dhabi-based Etihad Rail. These include passenger and freight services as well as a high-speed rail connection.

    In December 2024, the RTA awarded a AED20.5bn main contract for the Dubai Metro Blue Line project to a consortium of Turkish firms Limak Holding and Mapa Group and the Hong Kong office of China Railway Rolling Stock Corporation.

    The Blue Line consists of 14 stations, including three interchange stations at Al-Jaddaf, Al-Rashidiya and International City 1, as well as a station in Dubai Creek Harbour. By 2040, daily ridership on the Blue Line is projected to reach 320,000 passengers. It will be the first Dubai Metro line to cross Dubai Creek and will do so on a 1,300-metre viaduct.


    READ THE JANUARY 2026 MEED BUSINESS REVIEW – click here to view PDF

    Saudi Arabia courts real estate investment; EVs and battery production are key regional tech themes; Muscat holds a steady growth course despite headwinds

    Distributed to senior decision-makers in the region and around the world, the January 2026 edition of MEED Business Review includes:

    > ECONOMIC ACTIVITY INDEX: UAE and Qatar emerge as markets to watch
    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/15465636/main.jpg
    Yasir Iqbal