The immense challenge posed by global warming and the pressing need to reduce carbon emissions cannot be overcome by one single policy, nation or group. Action by every segment of society, from individuals to companies and governments, is essential. 

Historically, the main impetus in the drive toward net zero has come top down from policymaking, laws and strategies at a government or international level.

Global treaties such as the 1997 Kyoto Protocol, the 2016 Paris Agreement and the annual Conference of the Parties (COP), all held under the United Nations Framework Convention on Climate Change (UNFCCC), have provided the frameworks and targets to which each member state must bind itself.

In turn, each nation has implemented its own laws and strategies to ensure these targets are met. Regulatory examples include banning new combustion-engine-car sales, green building codes, and subsidies and incentives for renewable energy expansion.

While countries have coordinated policies through intergovernmental organisations such as UNFCCC and the International Renewable Energy Agency (IRENA), companies have often operated in silos as they seek to follow regulations or enact their own decarbonisation agenda. 

Corporates are critical to the net-zero process because they directly or indirectly contribute a large percentage of global emissions. According to IRENA, the industrial sector alone accounts for 28 per cent of total global greenhouse gases, of which four segments in particular – iron and steel, chemicals and petrochemicals, cement and lime, and aluminium – account for almost three-quarters.

Therefore, a situation where companies act in isolation and at different paces is far from ideal.

Industrial decarbonisation alliance

But this is changing. In early September, IRENA and Siemens Energy announced the formation of the Alliance for Industry Decarbonization. The new alliance, which launched with 13 other international energy and industrial members, aims to speed up net-zero ambitions and the decarbonisation of industrial value chains in pursuit of the Paris Agreement climate goals.

“Climate action needs industry leaders,” says Francesco La Camera, IRENA's Director General. “This Alliance stands for the growing commitment of global industry to act on decarbonisation and unlock opportunities that come with a green industrialisation through renewables and other transition-related technologies like green hydrogen.

“By standing together, we send a clear signal of solidarity ahead of COP27 and we invite new partners to join our common vision.”

The new industry grouping aims to achieve country-specific net-zero goals faster by encouraging action to decarbonise industrial value chains and enhance the understanding of renewables-based solutions and their adoption by industry. It will also work toward strengthening dialogue among key industrial stakeholders.

Coordinated and facilitated by IRENA, the Alliance will hold its first meeting during COP27 in Egypt in November. Siemens Energy, the principal driver behind its formation next to IRENA, will chair the Alliance together with Tata Steel.

“We need to slash greenhouse gas emissions urgently to tackle climate change,” says Karim Amin, a member of Siemens Energy's executive board. “Accounting for more than a quarter of global emissions, the industrial sector is the second-largest emitter and requires rapid decarbonisation. In this endeavour, partnerships are crucial.

“With our technologies, we at Siemens Energy constantly seek to create value with our partners toward a low-carbon future. I am convinced the Alliance for Decarbonization will accelerate decarbonisation by installing a first-class exchange forum for industry, technology and knowledge partners.”

By standing together, we send a clear signal of solidarity ahead of COP27 and we invite new partners to join our common vision

Francesco La Camera, IRENA

Collective potential

The Alliance's founding members cover a wide range of industrial players. They comprise two regional firms – Abu Dhabi-based energy and water company, TAQA, and Egyptian energy and utility provider TAQA Arabia – oil giants Eni, Equinor and Repsol, engineering, procurement and construction contractor Technip Energies, energy firms Enel Green Power, Tatanga Power and EDF Renewables, steelmakers Tata Steel and JSW, Zimbabwean fertiliser producer Sable Chemicals, and consultancy Roland Berger. 

“We all know we need innovative approaches to achieve net zero by the middle of this century. No single company or sector can get there alone,” says Jasim Husain Thabet, TAQA Group’s CEO and Managing Director, explaining why his company joined the Alliance.

“Only by harnessing the power of partnerships can we unlock our collective innovation potential … the world urgently needs us to act.” 

By bringing together renewable energy providers, manufacturers and technology companies, the hope is that industrial firms will benefit from low-carbon solutions to their energy requirements, harness industrial electrification technologies and better understand what their peers are doing to meet their own net-zero commitments. 

Over time, more companies and industry stakeholders are expected to join the alliance as it gains momentum and the benefits of its collaborative approach become clear. Since its launch, a further eight companies have joined, bringing its total number of members up to 22 

New members include Omani global integrated energy company OQ, Cairo-based energy, digital and infrastructure group, El Sewedy, the KIS Group, VALE, ATC Development, Subsea 7, FLSmidth and Petronas.

Energy-intensive heavy industry players – under pressure to transition from coal and other carbon-intensive fuels to renewables and further clean energy sources such as green hydrogen – have been playing a prominent role in the alliance.

But any private or public industrial company with the ambition to reduce its carbon output or with experience and expertise in deploying energy transition technologies is welcome to join.

The Alliance for Industry Decarbonization will not be a magic wand to reduce global warming. But it is a significant first step in encouraging industry stakeholders to work together.

Climate change represents an existential challenge to humanity. Ultimately, companies have an obligation to act now to play their part in mitigating its impact, and the Alliance’s vision is set to help achieve that.

Related reads:

Click here to visit Siemens Energy 
https://image.digitalinsightresearch.in/uploads/NewsArticle/10141926/main.gif
MEED Editorial
Related Articles
  • Dubai awards $272m Al-Maktoum airport runway deal

    9 May 2025

     

    Dubai Aviation Engineering Projects (DAEP) has awarded a AED1bn ($272m) deal to local firm Binladin Contracting Group to construct the second runway as part of the expansion of Dubai’s Al-Maktoum International airport.

    MEED understands that the contract was finalised in Q1 of this year, and the construction works have started.

    The airport, which will cover an area of 70 square kilometres south of Dubai, will have five parallel runways, five terminal buildings and 400 aircraft gates.

    It will be five times the size of the existing Dubai International airport and have the world’s largest passenger handling capacity of 260 million passengers a year. For cargo, it will have the capacity to handle 12 million tonnes a year.

    The construction works on the first phase of the project are expected to be completed by 2032.

    Dubai approved the updated designs and timelines for its largest construction project in April last year.

    The government of Dubai said that the plan is for all operations from Dubai International airport to be transferred to Al-Maktoum International airport within 10 years.

    The government statement added that the project will create housing demand for 1 million people around the airport.

    In September last year, MEED exclusively reported that a team comprising Austria’s Coop Himmelb(l)au and Lebanon’s Dar Al-Handasah had been confirmed as the lead master planning and design consultants on the expansion of Dubai’s Al-Maktoum International airport.

    Project history

    The expansion of Al-Maktoum International airport is a long-standing project. Also known as Dubai World Central (DWC), it was officially launched in 2014 with a different design from the one approved in April 2024. Back then, it involved building the biggest airport in the world by 2050, with the capacity to handle 255 million passengers a year.

    An initial phase, due to be completed in 2030, involved increasing the airport’s capacity to 130 million passengers a year. The development was to cover an area of 56 square kilometres.

    Progress on the project slipped as the region grappled with the impact of lower oil prices and Dubai focused on developing the Expo 2020 site. Tendering for work on the project then stalled with the onset of the Covid-19 pandemic in early 2020.


    MEED’s May 2025 report on the UAE includes:

    > COMMENT: UAE is poised to weather the storm
    > GOVERNMENT & ECONOMY: UAE looks to economic longevity
    > BANKING: UAE banks dig in for new era

    > UPSTREAM: Adnoc in cruise control with oil and gas targets
    > DOWNSTREAM: Abu Dhabi chemicals sector sees relentless growth
    > POWER: AI accelerates UAE power generation projects sector
    > CONSTRUCTION: Dubai construction continues to lead region
    > TRANSPORT: UAE accelerates its $60bn transport push
    > DATABANK: UAE growth prospects head north

    https://image.digitalinsightresearch.in/uploads/NewsArticle/13847301/main.jpg
    Yasir Iqbal
  • Siemens Energy signs preliminary 14GW Iraq pact

    9 May 2025

    Register for MEED’s 14-day trial access 

    Germany’s Siemens Energy and Iraq’s Electricity Ministry have signed a preliminary agreement to add 14GW of electricity generation capacity to Iraq’s grid.

    The firms also signed two long-term service contracts for the Dibis and Al-Mussaib gas-fired power plants.

    The contract for the Dibis power plant covers two generating units with a combined capacity of 340MW.

    The five-year maintenance contract for the Al-Mussaib power station includes rehabilitating units with a capacity of 750MW and an additional 150MW, along with support for safe operations and performance optimisation.

    The announcement was made following a meeting between Siemens Energy CEO Christian Bruch and Iraqi Prime Minister Mohammed Al-Sudani, local media reported. 

    The deals were signed a few weeks after US-headquartered GE Vernova signed a memorandum of understanding (MoU) with the Iraqi government to establish 24GW of combined-cycle gas turbine (CCGT) power plants in the country.

    In late April, Iraq and Siemens Energy also announced breaking ground on a project to build a new CCGT power generation plant in Nasiriyah in Iraq’s southern Dhi Qar governorate.   

    The project is part of a $1.68bn development package that Al-Sudani recently launched.

    In addition to the CCGT plant, the other projects include the Nasiriyah Integrated Medical City, a 700-bed hospital complex and infrastructure works in the Suq Al-Shuyukh district.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/13847219/main.jpg
    Jennifer Aguinaldo
  • Abu Dhabi hopes bigger is better with Disney theme park

    8 May 2025

    Commentary
    Colin Foreman
    Editor

    Ever since Aldar Properties first launched the Yas Island project with its Yas Marina Circuit for the Abu Dhabi Grand Prix in 2006, Abu Dhabi has been steadily adding theme parks to the island’s roster of attractions. First, there was the Ferrari theme park, then came a water park, a Warner Bros theme park and, most recently, SeaWorld. 

    The theory with theme park development is bigger is better. 

    A destination needs a series of parks to create a critical mass to attract visitors who can stay and enjoy multiple parks in one visit. The example always cited is Florida, which is home to many of the world’s largest theme parks, including Disney World. 

    The theory gained particular traction in the region when Dubai Parks and Resorts opened. The company, which was public until it was acquired by Meraas in 2021, reported significant losses as it struggled to attract enough visitors.

    Although it opened with Legoland, Legoland Waterpark, Motiongate and Bollywood theme parks, insiders said that the problem with the development was that it did not have enough attractions to turn it into a successful theme park destination. 

    The financial performance of theme parks on Yas Island has not been publicly disclosed. While it is accepted that they have been more successful than their counterparts in Dubai, some say that the island still does not have the critical mass required to establish itself as a global destination for theme park visitors.


    Miral has developed a series of theme parks and other entertainment-related attractions on Yas Island 


    Enter Disney

    Disney changes that. It is the largest brand in the theme park space and will be a major attraction, but with limited information released on the project so far, it is difficult to fully gauge how significant the project will be. 

    The official release said that the project will be developed and operated by Abu Dhabi developer Miral, adding that Disney’s in-house design and engineering unit, Walt Disney Imagineering, will lead creative design and operational oversight to provide a world-class experience. It did not give any details on the ownership of the project. 

    In Hong Kong, for example, a company, Hong Kong International Theme Parks, was established as a joint venture, with the Government of Hong Kong holding 57% and The Walt Disney Company holding 43%. 

    In Japan, the structure is different. The Tokyo Disney Resort is owned and operated by Oriental Land, and the company pays licences and royalties to The Walt Disney Company.

    In interviews following the launch announcement, Miral CEO Mohamed Abdalla Al-Zaabi confirmed the arrangement will be like Tokyo. 

    Waterfront location

    The official release for the Abu Dhabi launch also said that the project is on Yas Island, which only has limited areas of land to develop. The release also said that the land is waterfront, and imagery in the launch video shows the Abu Dhabi skyline in the background, suggesting the land is on the northern waterfront of Yas Island. 

    There is a substantial tract of undeveloped land on the north shore of the island, which measures about 2 square kilometres (sq km). This is larger than the site that Hong Kong Disneyland occupies, and much smaller than Disney World in Florida, which spans an area of 111 sq km – nearly five times the size of the whole of Yas Island and nearly double the size of Abu Dhabi Island.

    The hope is that Yas Island will become a leading global theme park destination and attract large numbers of visitors wanting a holiday with multiple theme park visits

    Exclusivity clause

    Another area of interest will be whether Abu Dhabi has an exclusivity agreement with Disney for the region. No exclusivity was mentioned at the launch, but in Hong Kong, the issue became contentious when Disney announced plans to build a park shortly after Disneyland Hong Kong opened. Local politicians criticised the Hong Kong government for not including an exclusivity clause in its deal with Disney. 

    Tourism gateway

    Like Hong Kong, Abu Dhabi is a smaller economy sitting next to a larger regional player. With Saudi Arabia’s ambitious Vision 2030 strategy and its existing roster of theme park developments at Qiddiya, which includes a Six Flags, a water park and a Dragon Ball Z theme park, developers in Riyadh would likely be keen to have a Disney theme park, too. 

    For now, with Disney on board in Abu Dhabi, the hope is that Yas Island will become a leading global theme park destination and attract large numbers of visitors wanting a holiday with multiple theme park visits.

    The potential is certainly there. During the project launch, Disney highlighted that the UAE is located within a four-hour flight of one-third of the world’s population, making it a significant gateway for tourism. It is also home to the largest global airline hub in the world, with 120 million passengers travelling through Abu Dhabi and Dubai each year.

    If that potential is realised, then the bigger is better theory will be proved right. If the park’s performance disappoints, then it will suggest the region is not such a great destination for theme parks after all. 

    https://image.digitalinsightresearch.in/uploads/NewsArticle/13840555/main.gif
    Colin Foreman
  • Firms bag $850m Qatar substation contracts

    8 May 2025

    Four local and international firms have won contracts for the construction of seven high-voltage substations in Qatar.

    State-backed Qatar General Electricity & Water Corporation (Kahramaa) signed the contracts, which have a total combined value of approximately QR3.1bn ($850m), with the following firms:

    • Elsewedy Cables Qatar Company (local/Egypt)
    • Voltage Engineering (local)
    • Best/Betas Consortium (Turkey)
    • Taihan Cable & Solution (South Korea)

    Kahramaa said the projects aim to “meet electrical network demand in light of the country's fast-growing …urban development”.

    The contracts include the provision and installation of underground cables and overhead lines extending around 212 kilometres to connect these substations.

    Qatari companies won the largest share, equivalent to 58.4% or QR1.8bn, of the total contract value.

    This reflects “our great confidence in the capabilities of the local private sector and its pivotal role in achieving our development vision and achieving Qatar National Vision 2030”, said Kahramaa president Abdulla Bin Ali Al-Theyab.

    Qatar Minister of State for Energy Affairs, Saad Sherida Al-Kaabi, and senior executives from Kahramaa and the contracting firms signed the deals at a ceremony held in Doha.

    Al-Kaabi said the projects will help “ensure our networks' continued and sustainable ability to accommodate the unprecedented growth of the power sector and meet the increasing electricity demand”.

    Kahramaa said the contractors will undertake the construction of electrical substations and the connection of cables and overhead lines, as well as the development of some existing substations to increase their capacity.

    Qatar has been ramping up its power generation capacity in recent years.  

    Qatar's Emir, Sheikh Tamim Bin Hamad Al-Thani, inaugurated the Ras Laffan and Mesaieed solar photovoltaic (PV) power plants on 28 April.

    The two plants have a combined capacity of 875MW and will more than double Qatar’s solar energy production to 1,675MW.

    In February, Qatar Electricity & Water Company (QEWC) and Kahramaa signed a power-purchase agreement for a 511MW peak electricity generation plant at Ras Abu Fontas, which will have a total cost of approximately QR1.6bn. The peak power plant is scheduled to become operational by January 2027.

    A consortium led by South Korea's Doosan Enerbility, and that includes Beijing-headquartered PowerChina, will undertake the Ras Abu Fontas peak power plant's engineering, procurement and construction contract, with Germany's Siemens Energy supplying the plant's gas turbines.

    Photo credit: Kahramaa

    https://image.digitalinsightresearch.in/uploads/NewsArticle/13838850/main.jpg
    Jennifer Aguinaldo
  • OQ to take interest in Oman renewable projects

    8 May 2025

    OQ Alternative Energy (OQAE), part of Oman’s state-backed energy group OQ, will be taking shares in Oman’s renewable energy independent power projects (IPP), starting with the Ibri 3 solar scheme.

    “The direction seems to be for OQ Alternative Energy to own up to 25% shares in the upcoming solar and wind IPP projects in the sultanate,” says a source familiar with the plans.

    Before this development, private developers and investors owned the total shares in such projects, similar to the existing structure in Saudi Arabia.

    With this policy change, Oman will now be more closely aligned with the existing project structure in the UAE, where either Abu Dhabi National Energy Company (Taqa), Abu Dhabi Future Energy Company (Masdar) or the state utility, Dubai Electricity & Water Authority (Dewa), owns stakes in these projects.

    However, OQAE’s planned 25% ownership share will be slightly lower than the typical 40% to 60% shares that Taqa, Masdar or Dewa owns in the UAE’s renewable energy IPP projects.

    Currently, OQAE owns a 51% share in three renewable energy projects being developed in partnership with France’s TotalEnergies for the state-backed firm, Petroleum Development Oman (PDO).

    The Riyah-1 and Riyah-2 wind power plants will be located in the Amin and West Nimr fields in southern Oman, while the North Solar project will be situated in northern Oman.

    Each plant will have a capacity of 100MW, Total Energies announced in December.

    PDO will purchase the electricity from the plants through long-term power-purchase agreements with the developer team, whose 49% shares are owned by TotalEnergies.

    OQAE is also part of Hyport Coordination Company, a consortium comprising Belgium’s Deme Concessions and BP Oman. The consortium plans to develop a green hydrogen project in Duqm that can produce more than 50 tonnes a year of green hydrogen in its first phase by 2029.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/13838800/main.jpg
    Jennifer Aguinaldo