Riyadh rides power projects surge
7 September 2023
This package on Saudi Arabia's power sector also includes:
> Israeli talks decisive for Saudi nuclear programme
> Jinko outprices other bidders for Tubarjal solar contract
> Synergy wins 7.2GW Saudi advisory role
> Team submits lowest Hinakiyah solar bid
> Saudi offtaker holds Taiba and Qassim bidder meetings
> Saudi Arabia confirms Shuaibah financial close

Recent months have been busier than usual for the Saudi power generation sector. Riyadh’s plan to build its first large-scale nuclear power plant has gathered momentum, with the tendering process under way for the project’s main contract.
In May, the Public Investment Fund (PIF) awarded three solar photovoltaic (PV) power plant contracts with a total combined capacity of 4,550MW.
In August, utility developer Acwa Power reached financial close for the Shuaibah 1 and Shuaibah 2 solar PV independent power producer (IPP) projects, which have a total combined capacity of over 2,600MW.
French energy heavyweight TotalEnergies has also reached financial close for the 120MW Wadi al-Dawasir solar scheme, tendered under round three of the kingdom’s National Renewable Energy Programme (NREP).
During the past few months, the state-backed power offtaker, Saudi Power Procurement Company (SPPC), has received proposals and shortlisted two bidders each for the two solar PV contracts under NREP’s round four.
Riyadh has also accelerated the procurement of gas-fired capacity over the past year.
SPPC is simultaneously evaluating bids for four combined-cycle gas turbine (CCGT) plants, the Taiba 1 and 2 and Al-Qassim 1 and 2 IPPs, which have a total combined capacity of 7,200MW.
In addition to the potential award of these four contracts over the next few months, the state offtaker is expected to tender two more gas-fired projects – the PP15 IPP in Riyadh and another power generation plant in Al-Khafji – next year. Each will have a design capacity of 3,600MW.
Overall, close to $30bn-worth of power generation projects are in execution or about to start construction in Saudi Arabia, according to the latest data from MEED Projects.
At least $44bn are in the pre-execution phase, excluding the kingdom’s $35bn nuclear power plant programme.
Liquid fuel displacement
Given the kingdom’s ambitious plan to boost its renewable energy installed capacity to 58,700MW by 2030, up from about 1,100MW today, the pace of renewable energy contract awards is no surprise.
CCGT projects support the kingdom’s plan to cut down on burning liquid fuels. The Energy Ministry’s liquid fuel displacement programme, launched as part of Saudi Vision 2030, aims to displace 1 million barrels a day of liquid fuels across the utilities, industry and agriculture sectors by 2030.
The latest data from the King Abdullah Petroleum Studies & Research Centre (Kapsarc) shows that liquid fuels, comprising crude oil, heavy fuel oil and diesel, accounted for up to 43 per cent of Saudi Arabia’s fuel mix for power generation and water desalination processes as of 2018.
This translates to about 1,670 trillion BTUs, roughly equivalent to 760,000 barrels a day, of liquid fuels.
Meanwhile, natural gas consumption across the kingdom’s power generation and water desalination sectors is estimated at 2,226 trillion BTUs, or 6 billion cubic feet a day.
Kapsarc research fellow Rami Shabaneh noted in a 2020 report: “Overall fuel consumption saw a significant decline of almost 8 per cent year-on-year in 2018. This was due to increased energy-efficiency regulations and energy price reforms.”
This trend – along with other energy-efficiency measures in the power generation, water desalination, and transmission and distribution network – suggests there has been a decrease in fuel consumption in the intervening years too.
However, much still needs to be done to reach the kingdom’s 2030 liquid fuel displacement target, as well as its energy diversification objectives.
While the massive expansion of gas-fired capacity seems inconsistent with cutting emissions, the significant number of fleets that still burn liquid fuel appears to justify the dual approach to expanding both renewable and gas-fired capacity to meet rising demand and security of supply.
“Plants running on highly efficient CCTG technologies is the way to go,” says an expert who works for an international utility developer.
This approach also dovetails with the kingdom’s goal for 50 per cent natural gas and 50 per cent clean or renewable energy in its energy mix by 2030.
Saudi’s ambition to achieve carbon neutrality by 2060 – 10 years later than typical targets – could also be advantageous in terms of procuring more efficient CCGT plants in the interim.
With the kingdom’s power-purchase agreements (PPAs) generally lasting 25 years, gas-fired IPPs procured this year and next will reach commercial operations by 2027 or 2028. This takes the validity of upcoming PPAs into the early 2050s, still well within the country’s energy transition period.
Different tunes
As things stand, not everyone is convinced of the need for the scale of the new natural gas fleet planned in the kingdom.
“I think they should focus more on renewables,” says a Dubai-based industry expert, who notes the large gap between Saudi Arabia’s current renewable energy installed capacity and 2030 target.
Given that renewable energy accounts for, roughly, just 1 per cent of known power generation installed capacity, 70-fold growth is needed to hit the end-of-the-decade target.
Some international utility developers, with internal carbon-neutrality deadlines of 2050 or before, may not be able to participate in the ongoing CCGT tenders, unless they integrate decarbonisation measures. This could affect the competitiveness of bid prices.
However, Paddy Padmanathan, former CEO of Saudi utility Acwa Power, says the kingdom has room for both technologies.
“I see no reason why a fast or even faster pace of renewable energy procurement cannot run in parallel with CCGT procurement,” he tells MEED.
“[The] Saudi procurement process, PPA risk allocation and certainty of projects moving forward to the timetable set out in the requests for proposals are well recognised and appreciated,” the executive, who is a member of Acwa Power’s board following his retirement as CEO earlier this year, explains.
Padmanathan says there is no shortage of equity and debt funding for these projects. He also cites the kingdom’s “very high” credit rating.
These factors, along with abating supply chain challenges for solar PV modules and the keenness of CCGT original equipment manufacturers for new contracts, mean the kingdom will continue to be an exciting market for power projects well into the next decade, Padmanathan asserts.
Exclusive from Meed
-
Dubai seeks consultants for drainage projects6 February 2026
-
Modon tenders Ras El-Hekma construction contracts6 February 2026
-
Egypt contractor secures €58m loan for Hungary power plant6 February 2026
-
AD Ports signs Jordan Aqaba port PPP deal6 February 2026
-
Chinese firm wins Ceer automotive supplier park deal6 February 2026
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Dubai seeks consultants for drainage projects6 February 2026
Dubai Municipality has invited consultants to qualify for a contract to supervise three stormwater drainage projects under the $8bn Tasreef programme.
The contract, titled TF-15-S1 Supervision of Stormwater Drainage System projects – Package 2, will be awarded as a single package with dedicated teams assigned to each project.
The request for qualifications (RFQs) was issued by the municipality’s Sewerage and Recycled Water Projects Department (SRPD).
The bid submission deadline is 26 February.
The first scheme under the package is TF-16-C1, which involves upgrading and rehabilitating the stormwater system east of the Dubai Canal.
The second, TF-15-C2, will deliver stormwater links along Umm Suqeim Road to serve the Al-Barsha and Al-Quoz communities.
The third project, TF-13-C1, focuses on developing a drainage system for the Al-Marmum area.
Several engineering, procurement and construction (EPC) contracts have been awarded under the Tasreef initiative, which aims to expand Dubai’s rainwater drainage capacity by 700% by 2033
In January, local firm DeTech Contracting won the main contract to construct a stormwater drainage system in Jebel Ali.
The project, listed under TF-05-C1, covers approximately 27 kilometres of stormwater network and will serve major transport routes, including Sheikh Zayed Road and Al-Jamayel Road.
Separately, Dubai Municipality has opened bidding for EPC contracts to expand and rehabilitate the emirate’s sewerage networks.
The four projects cover more than 95km of recycled water and sewerage pipelines.
READ THE FEBRUARY 2026 MEED BUSINESS REVIEW – click here to view PDFSpending on oil and gas production surges; Doha’s efforts support extraordinary growth in 2026; Water sector regains momentum in 2025.
Distributed to senior decision-makers in the region and around the world, the February 2026 edition of MEED Business Review includes:
> AGENDA: Mena upstream spending set to soar> INDUSTRY REPORT: MEED's GCC water developer ranking> INDUSTRY REPORT: Pipeline boom lifts Mena water awards> MARKET FOCUS: Qatar’s strategy falls into place> CURRENT AFFAIRS: Iran protests elevate regional uncertainty> CONTRACT AWARDS: Contract awards decline in 2025> LEADERSHIP: Tomorrow’s communities must heal us, not just house us> INTERVIEW: AtkinsRealis on building faster> LEADERSHIP: Energy security starts with rethinking wasteTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/15593832/main.jpg -
Modon tenders Ras El-Hekma construction contracts6 February 2026

Abu Dhabi-based developer Modon Holding has tendered several contracts as part of the first phase of development at Ras El-Hekma, a planned new city on Egypt’s Mediterranean coast.
MEED understands that the tenders were issued in January.
These include:
DP3 assets: covering 146 residential villas, 590 three-bedroom townhouses, 356 four-bedroom townhouses, a mall and other associated works.
Bids due on 23 February.
DP4 assets: DP4 includes 54 villas, a clubhouse and other associated infrastructure.
Bids due on 2 March.
DP5 assets: The scope covers the construction of two hotels, branded residences, a retail facility and other associated works.
Bids due on 10 March.
DP6 assets: This package covers a 200-key Montage hotel, 96-unit Montage-branded residences and related infrastructure.
Bids due on 17 March.
DP7 assets: 120 five-bedroom villas, 230 seven-bedroom villas, 284 branded residential units and other infrastructural works.
Bids due on 3 March.
MEED understands that the contract duration for all these packages is 21 months from the start of construction.
Modon has accelerated development works at Ras El-Hekma this year. In January, MEED reported that Modon Holding had awarded a E£15bn ($316m) contract for the construction of a project at Ras El-Hekma.
The contract was awarded to the local firm Orascom Construction.
The scope of the contract covers the construction of residential units, commercial facilities and a 70-key hotel.
In September, MEED reported that Modon Holding had tendered contracts for the infrastructure works for the first phase of the Ras El-Hekma project.
As part of the first phase, Modon plans to develop more than 50 million square metres (sq m), including hotels and a marina.
Ras El-Hekma is on a spur of land on Egypt’s northern Mediterranean coastline, about 240 kilometres west of Alexandria.
Last year, Abu Dhabi-based holding company ADQ appointed Modon Holding as the master developer for the Ras El-Hekma project.
According to an official statement, Modon will act as the master developer for the entire development, which will cover more than 170 million sq m.
Modon Holding will develop the first phase of the project, which will cover 50 million sq m.
The remaining 120 million sq m will be developed in partnership with private developers under the supervision of the recently established ADQ subsidiary Ras El-Hekma Urban Development Project Company and Modon Holding.
In September 2024, Modon signed several memorandums of understanding (MoUs) with local and international firms to join the development. It signed a framework agreement with Orascom Construction to serve as the primary contractor for the project’s first phase.
Ras El-Hekma is planned as a combined business and leisure destination, with hotels, leisure facilities, a free zone, a financial district and residential components.
The master development has been billed as capable of attracting over $150bn in investment.
READ THE FEBRUARY 2026 MEED BUSINESS REVIEW – click here to view PDFSpending on oil and gas production surges; Doha’s efforts support extraordinary growth in 2026; Water sector regains momentum in 2025.
Distributed to senior decision-makers in the region and around the world, the February 2026 edition of MEED Business Review includes:
> AGENDA: Mena upstream spending set to soar> INDUSTRY REPORT: MEED's GCC water developer ranking> INDUSTRY REPORT: Pipeline boom lifts Mena water awards> MARKET FOCUS: Qatar’s strategy falls into place> CURRENT AFFAIRS: Iran protests elevate regional uncertainty> CONTRACT AWARDS: Contract awards decline in 2025> LEADERSHIP: Tomorrow’s communities must heal us, not just house us> INTERVIEW: AtkinsRealis on building faster> LEADERSHIP: Energy security starts with rethinking wasteTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/15593388/main.jpg -
Egypt contractor secures €58m loan for Hungary power plant6 February 2026
Commercial International Bank Egypt (CIB) has provided €58m in credit facilities to local firm Elsewedy Electric for the construction of a combined-cycle gas turbine (CCGT) power plant in Hungary.
Located in Visonta, the plant will be the largest combined-cycle facility built in Hungary in decades and the country’s first power plant capable of using hydrogen.
Once complete, hydrogen will be able to supply up to 30% of the plant’s fuel needs.
The project is being developed through a consortium comprising Energy Projects, a subsidiary of Elsewedy Electric, and local firms Status KPRIA and West Hungaria Bau (WHB).
It was awarded by MVM Matra Energia, a subsidiary of Hungary’s state-owned power holding company Magya Villamos Muvek (MVM).
As MEED understands, the plant is expected to have a power generation capacity of between 500MW and 650MW.
Total investment in the scheme is estimated at about €700m, with CIB acting as the sole financier for Elsewedy Electric’s portion of the project.
Construction officially began last September, with commercial operations scheduled for 2028.
The scheme also represents Elsewedy Electric’s first major investment in Europe, adding to other foreign investment interests.
Last May, it was reported that Elsewedy Electric intends to build a $100m electrical cable manufacturing plant in Iraq. This project has yet to advance beyond the initial stages.
In 2024, the contractor connected three additional hydro turbine generators to Tanzania’s national power grid in partnership with The Arab Contractors.
This brought the total power supply from the Julius Nyerere hydroelectric power project to 705MW.
READ THE FEBRUARY 2026 MEED BUSINESS REVIEW – click here to view PDFSpending on oil and gas production surges; Doha’s efforts support extraordinary growth in 2026; Water sector regains momentum in 2025.
Distributed to senior decision-makers in the region and around the world, the February 2026 edition of MEED Business Review includes:
> AGENDA: Mena upstream spending set to soar> INDUSTRY REPORT: MEED's GCC water developer ranking> INDUSTRY REPORT: Pipeline boom lifts Mena water awards> MARKET FOCUS: Qatar’s strategy falls into place> CURRENT AFFAIRS: Iran protests elevate regional uncertainty> CONTRACT AWARDS: Contract awards decline in 2025> LEADERSHIP: Tomorrow’s communities must heal us, not just house us> INTERVIEW: AtkinsRealis on building faster> LEADERSHIP: Energy security starts with rethinking wasteTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/15593289/main.jpg -
AD Ports signs Jordan Aqaba port PPP deal6 February 2026
Abu Dhabi’s AD Ports Group has signed an agreement with Jordan’s Aqaba Development Corporation (ADC) to manage and operate the Aqaba multipurpose port.
AD Ports will manage and operate the port under a 30-year concession agreement.
Under the agreement, AD Ports and ADC will establish a joint venture to oversee port operations.
AD Ports will hold a 70% stake in the joint venture, with the remaining 30% held by ADC.
AD Ports Group will also invest AED141m ($38.4m) in the joint venture.
The signing ceremony was held at the Aqaba Special Economic Zone Authority headquarters in Aqaba on 5 February.
The agreement was signed by Hussein Safadi, CEO of ADC, and Ahmed Al-Mutawa, regional CEO of AD Ports Group.
Aqaba port handles about 80% of Jordan’s exports and 65% of its imports.
It serves as a key transit point for Jordan’s neighbouring countries, including Saudi Arabia and Iraq. The port has an annual handling capacity of 11 million tonnes, supported by nine berths, a quay length of 2 kilometres and a draft of 13.5 metres.
In 2025, the terminal handled over 5.3 million tonnes of cargo and nearly 85,000 car equivalent units of Ro-Ro imports.
Abu Dhabi has been deeply involved in making investments in Jordan’s infrastructure sector. In February last year, AD Ports Group signed an agreement to manage and operate the Al-Madouneh customs centre in Amman, as MEED reported.
The Al-Madouneh customs centre covers about 1.3 million square metres (sq m) and was inaugurated in June last year.
The announcement followed AD Ports Group’s signing of a shareholders’ agreement in January 2024 between its digital arm, Maqta Gateway, and Jordan’s Aqaba Development Corporation regarding their existing joint-venture company, Maqta Ayla.
The joint venture company will upgrade operations at the Aqaba port complex in Jordan by implementing a port community system “that leverages Maqta Gateway’s expertise, also marking the first-ever export of Abu Dhabi’s key port digitalisation solution”, AD Ports said in a statement.
AD Ports Group operates the Aqaba cruise terminal, and selected Dubai-based real estate developer Mag Group to lead the first phase of the Marsa Zayed mixed-use project.
READ THE FEBRUARY 2026 MEED BUSINESS REVIEW – click here to view PDFSpending on oil and gas production surges; Doha’s efforts support extraordinary growth in 2026; Water sector regains momentum in 2025.
Distributed to senior decision-makers in the region and around the world, the February 2026 edition of MEED Business Review includes:
> AGENDA: Mena upstream spending set to soar> INDUSTRY REPORT: MEED's GCC water developer ranking> INDUSTRY REPORT: Pipeline boom lifts Mena water awards> MARKET FOCUS: Qatar’s strategy falls into place> CURRENT AFFAIRS: Iran protests elevate regional uncertainty> CONTRACT AWARDS: Contract awards decline in 2025> LEADERSHIP: Tomorrow’s communities must heal us, not just house us> INTERVIEW: AtkinsRealis on building faster> LEADERSHIP: Energy security starts with rethinking wasteTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/15592973/main.jpg -
Chinese firm wins Ceer automotive supplier park deal6 February 2026

Beijing-headquartered Metallurgical Construction Corporation (MCC) has won a contract to undertake the steel structure works on the Ceer automotive supplier park in King Abdullah Economic City (KAEC).
The supplier park is located next to Ceer’s electric vehicle (EV) production facility in KAEC.
The automotive supplier park will include production and ancillary facilities for various suppliers and provide the material supply infrastructure for Ceer’s EV plant.
The facilities include:
- Cold stamping, body-in-white assembly and stamping facility – Shin Young (South Korea)
- Hot stamping, sub-frames and axles subsystem supply facility – Benteler Group (Austria)
- Façade and exterior-trim supply facility – JVIS (US)
- Instrument panel, trims and console supply facility – Forvia (France)
- Seat supplier – Lear Corporation (US)
Earlier this week, MEED exclusively reported that Ceer had awarded a contract to build the automotive supplier park to Jeddah-based construction firm Modern Building Leaders (MBL).
Netherlands-based engineering firm Arcadis is the project consultant, and Pac Project Advisors is the project management consultant.
Ceer retendered the project in September last year.
The latest contract award is another significant contract win for MCC in Saudi Arabia. In January, MEED reported that MCC had won a contract to undertake the steel structure works on Mohammed Bin Salman Stadium at the Qiddiya City project on the outskirts of Riyadh.
The 45,000-seat stadium will feature a fully combined retractable pitch, roof and LED wall.
The stadium’s main construction works are being undertaken by a joint venture of Spanish firm FCC Construction and local firm Nesma & Partners.
In January, MCC won another contract to undertake steel structure works for the expansion of Medina airport in Saudi Arabia.
The scope covers work on boarding bridges, Terminal Two and the renovation of Terminal One.
READ THE FEBRUARY 2026 MEED BUSINESS REVIEW – click here to view PDFSpending on oil and gas production surges; Doha’s efforts support extraordinary growth in 2026; Water sector regains momentum in 2025.
Distributed to senior decision-makers in the region and around the world, the February 2026 edition of MEED Business Review includes:
> AGENDA: Mena upstream spending set to soar> INDUSTRY REPORT: MEED's GCC water developer ranking> INDUSTRY REPORT: Pipeline boom lifts Mena water awards> MARKET FOCUS: Qatar’s strategy falls into place> CURRENT AFFAIRS: Iran protests elevate regional uncertainty> CONTRACT AWARDS: Contract awards decline in 2025> LEADERSHIP: Tomorrow’s communities must heal us, not just house us> INTERVIEW: AtkinsRealis on building faster> LEADERSHIP: Energy security starts with rethinking wasteTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/15592955/main.gif