Kuwait enjoys sustained non-oil growth

25 August 2023

This month’s special report on Kuwait also includes: 

> POLITICSStakeholders hope Kuwait can execute spending plans
> ENERGYKuwait’s $300bn energy target is a big test
> POWER & WATERWarming erodes Kuwait’s power and water reserves
> BANKINGKuwaiti banks enter bounce-back mode
> INTERVIEWKuwait’s Gulf Centre United sets course for expansion


 

After witnessing a substantial upswing in its economy in 2022, with real GDP growth surging to 8.2 per cent, according to the IMF, Kuwait’s growth has nominally slowed to 0.1 per cent in 2023. However, this plummet on paper is more a function of the country’s pullback in oil production than any dramatic swing in its economic fate.

Amid the surprise production cuts by the Opec+ producers in April 2023, Kuwait announced a cut of 128,000 barrels a day (b/d), equivalent to about 10 per cent of the group’s 1.15 million b/d in total cuts and around 5 per cent of Kuwait’s output. 

In May and June, Kuwait pumped 2.55 million b/d of crude oil, down from 2.65 million b/d in April. For 2024, the country’s quota is 2.676 million b/d.

This curbing of the country’s primary export has naturally had a significant impact on headline growth, but looking ahead to 2024, the growth rate is projected to recover to 2.7 per cent.

Non-oil sustenance

Behind the fluctuations in Kuwait’s headline real GDP growth due to oil production and prices, the country continues to enjoy strong domestic demand and robust non-oil growth, with 4 per cent non-oil GDP growth in 2022 and a projection of 3.8 per cent growth in 2023, according to the IMF.

The World Bank, meanwhile, expects Kuwait’s non-oil economy to grow by 4.4 per cent in 2023.

Kuwait’s fiscal surplus stood at an estimated 7 per cent of GDP in the 2022/23 fiscal year, although that surplus is expected to disappear in 2023/24 after the Kuwait government approved an expansionary budget with a spending allocation of KD26.3bn ($85.5bn) for the current fiscal period – more than 12 per cent larger than the KD23.5bn spending budget for 2022/23. 

If ultimately spent, the significantly higher allocated expenditure should further stimulate the non-oil economy.

The budget, approved on 2 August before the parliamentary summer recess, anticipates a fiscal deficit of KD6.8bn. This follows Kuwait achieving its first budget surplus in nine years in 2022/23. The current budget is based on an assumed average oil price of $70 a barrel, with an estimated government revenue of KD19.5bn, including KD17.2bn from oil revenue.

Kuwaiti business leaders are cautiously optimistic that this 2023 government could be the one to break the political gridlock

Oil price uncertainty

Looking ahead, oil price volatility remains the key threat to the oil-dependent Kuwaiti economy. Despite this, 2023/24 is conservatively budgeted in terms of its oil price assumptions, broadly aligning with the IMF assumptions for a $73.1 average in 2023, and $68.9 in 2024, and comparing with a July 2023 spot price around the $80-mark.

The hope will be that the price will remain at a higher mark and that the budgeted oil price turns out to be overly precautionary.

However, China’s economy showed signs of slipping again in July, with both imports and exports falling – a worrying sign for global trade and commodity prices. In mid-August, the International Energy Agency lowered its 2024 oil demand growth forecast to 1 million b/d in 2024, down 150,000 b/d from its prior forecast, pointing to a combination of high interest rates, tight credit, and sluggish manufacturing and trade.

The uncertainty of such scenarios should lend haste to the fiscal and structural reforms waiting in the wings. The hope is that Kuwait’s newly minted parliament and cabinet could mean that a resolution to the political gridlock is in sight, offering a path to the fiscal and structural reforms the country requires.

Kuwaiti business leaders are cautiously optimistic that this 2023 government could be the one to break the political gridlock between the government and parliament and reset the loop of successive resignations, reappointments and elections that have recently prevented any reform progress.

Reform requirements

Fiscal measures identified by the IMF as priorities include the need to rationalise Kuwait’s public sector wage bill and phase out energy subsidies, alongside introducing the long-delayed value-added tax and expanding the country’s corporate income tax base. 

Advocated structural reforms include labour market reforms, competition strengthening, and climate change adaptation and mitigation.

Enacting at least some of these reforms will be crucial to Kuwait’s fiscal and economic viability in the medium to long term, with each delay only making tackling items such as the public sector wage bill harder.

In the short term, Kuwait can, of course, keep pumping. In June, Kuwait Oil Company CEO Ahmed Jaber al-Aydan told the Kuwait Times that the country’s oil production capacity would reach 3 million b/d by 2025. He also said the oil company would spend KD13bn ($42.5bn) on oil projects over the next five years. 

The Kuwait government, meanwhile, announced in July that it planned to boost its crude oil production capacity to 3.15 million b/d within four years.

Yet at some point, Kuwait will still need to take a long, hard look at its future finances. All hopes are presently set on the 2023 government being the one to start moving in the right direction.

https://image.digitalinsightresearch.in/uploads/NewsArticle/11071825/main.gif
John Bambridge
Related Articles
  • WEBINAR: Saudi gigaprojects 2026 and beyond

    7 November 2025

    Webinar: Saudi Gigaprojects 2026 & Beyond
    Tuesday 25 November 2025 | 11:00 GST  |  Register now


    Agenda:

    • Latest update to November 2025 on the gigaprojects programme and the Saudi projects market in general, with full data analysis for 2025 year-to-date
    • Latest assessment on the reprioritisation of the programme and views on which of the gigaprojects are being prioritised
    • Summary of key recent project developments and announcements 
    • Analysis of key contracts awarded this year to date
    • Highlights of key contracts to be tendered and awarded over the next six months
    • Key drivers and challenges going forward plus MEED’s outlook for the future short and long-term prospects of the gigaprojects programme
    • In-depth look at the recently announced King Salman Gate gigaproject and other planned, but unannounced PIF developments
    • Life beyond the gigaprojects – what other key project programmes are being implemented in the kingdom 
    • Q&A session

    Hosted by: Edward James, head of content and analysis at MEED

    A well-known and respected thought leader in Mena affairs, Edward James has been with MEED for more than 19 years, working as a researcher, consultant and content director. Today he heads up all content and research produced by the MEED group. His specific areas of expertise are construction, hydrocarbons, power and water, and the petrochemicals market. He is considered one of the world’s foremost experts on the Mena projects market. He is a regular guest commentator on Middle East issues for news channels such as the BBC, CNN and ABC News and is a regular speaker at events in the region. 

    Click here to register

    https://image.digitalinsightresearch.in/uploads/NewsArticle/15045990/main.gif
    Edward James
  • Bahrain advances utility reform

    7 November 2025

     

    In September, Bahrain’s government referred a draft law to parliament to restructure the kingdom’s electricity and water sector.

    This proposes dissolving the Electricity & Water Authority (Ewa) and transferring its assets and functions to a newly established National Electricity & Water Company, which will operate under the oversight of the Electricity & Water Regulatory Authority. 

    The reform marks the first full structural overhaul of Bahrain’s utilities sector in nearly two decades and signals a shift towards a more commercially driven model. 

    Regulatory and operational roles would be separated for the first time, allowing private sector participation under transparent licensing and tariff systems, aligning Bahrain with utility reforms seen in Saudi Arabia, Oman and the UAE.

    It comes amid a relatively subdued year for new contracts that broadly falls in line with 2024’s performance. Most significantly, Bahrain continues to move towards its two upcoming utility public-private partnership (PPP) schemes, the Sitra independent water and power project (IWPP) and the Al-Hidd independent water project (IWP).

    In August, a developer tender was issued for the main works package for the Sitra IWPP. This followed the prequalification of seven companies and consortiums, reflecting a wide range of international interest.

    The planned Sitra IWPP replaces the previously planned Al-Dur 3 and will be the first IWPP project to be awarded since the 1,500MW Al-Dur 2 IWPP was completed in 2021.

    The combined-cycle gas turbine (CCGT) plant is expected to have a production capacity of about 1,200MW of electricity, while the project’s seawater reverse osmosis (SWRO) desalination unit will have a production capacity of 30 million imperial gallons a day (MIGD) of potable water. The main contract is expected to be awarded by the end of the year, with commercial operations set for 2029. 

    A developer tender was also recently launched for Bahrain’s first independent, standalone SWRO plant following a prequalification process that shortlisted nine companies and consortiums.

    The Al-Hidd IWP is expected to have a production capacity of about 60MIGD of potable water and be completed in 2028. It is likely to be the last IWPP for Bahrain, which aims to reach net-zero carbon emissions by 2060.

    The imminent launch of the two projects boosts Bahrain’s projects pipeline, which has experienced muted growth in the aftermath of the Covid-19 pandemic, carried by relatively small-scale projects.

    Solar PV projects

    The creation of the National Electricity & Water Company as Bahrain’s new operational entity could also support the rollout of future renewable energy schemes. 

    As a corporatised offtaker, the company will be able to enter long-term power purchase agreements (PPAs) with private developers under a more bankable framework. Currently, these are negotiated by Ewa on a case-by-case basis.

    The government recently signed a 123MWp solar PPA with the UAE’s Yellow Door Energy, highlighting growing private sector interest in the market. The project includes the world’s largest single-site rooftop solar installation and will be developed at Foulath Holding’s industrial complex in Salman Industrial City.

    Bahrain has already set a target to source 20% of its energy from renewables by 2035 and reach net-zero emissions by 2060.

    In October, Ewa also issued a tender for the development of the Bilaj Al-Jazayer solar independent power project (IPP). The planned 100MW project will be developed on a build-own-operate basis with a 25-year contract term.

    In parallel, Bahrain is broadening its long-term energy strategy beyond solar. In July, the kingdom signed a cooperation agreement with the US on the peaceful use of nuclear energy, aimed at advancing research and potential deployment of small modular reactor (SMR) technology.

    For countries like Bahrain, which has limited land availability and high energy demand growth, SMRs could offer a way to produce low-carbon, reliable baseload power without requiring vast areas of land for solar or wind farms. 

    Officials have indicated that SMRs, along with floating solar solutions, are being studied as part of a broader push to diversify energy sources and expand renewable generation capacity.

    Water and waste

    Bids for four Ewa-owned projects are currently being evaluated. This includes the construction of a new SWRO desalination plant on Hawar Island and rehabilitation works for the Ras Abu Jarjur water treatment plant in Askar. Contracts for both projects are expected to be awarded this year.

    Bahrain’s Ministry of Works (MoW) is the other client for the island-state’s power and water infrastructure-related projects. It has awarded three smaller sewage-related contracts this year.

    It is also preparing to tender the construction of a $130m sewage treatment plant in Khalifa City, which will be developed in two phases. Meanwhile, the construction of MoW’s sewerage scheme phase 2 network in Bahrain remains in the early design stage with no further updates.

    As Bahrain moves ahead with these projects, the new electricity and water law could define how future investments are structured, regulated and financed. This could reshape the kingdom’s utilities landscape for decades to come.


    MEED's December special report on Bahrain also includes:

    > ECONOMY: Bahrain’s cautious economic evolution
    > BANKING: Mergers loom over Bahrain’s banking system
    > OIL & GAS: Bahrain remains in pursuit of hydrocarbon resources
    > CONSTRUCTION: Bahrain construction faces major slowdown
    > TRANSPORT: Bahrain signs game-changer aviation deal with Air Asia

    https://image.digitalinsightresearch.in/uploads/NewsArticle/15044915/main.gif
    Mark Dowdall
  • Masdar and OMV sign 140MW green hydrogen plant deal

    7 November 2025

    Register for MEED’s 14-day trial access 

    Abu Dhabi Future Energy Company (Masdar) has signed a binding agreement with Austrian energy company OMV to develop and operate a major green hydrogen production plant in Austria.

    The 140MW green hydrogen electrolyser plant will be Europe's fifth-largest hydrogen plant, according to Masdar chairman, Sultan Ahmed Al-Jaber.

    It will be built in Bruck an der Leitha, about 40 kilometres southeast of Vienna.

    The facility will be developed under a newly established joint venture, in which Masdar owns 49% and OMV holds the majority 51% stake.

    The agreement was signed at the Abu Dhabi International Petroleum Exhibition and Conference (Adipec), in the presence of Al-Jaber; Austria’s Federal Minister of Economy, Energy and Tourism, Wolfgang Hattmannsdorfer; OMV CEO Alfred Stern; and Masdar CEO Mohamed Jameel Al-Ramahi.

    It is expected that the project will reach financial close in early 2026, subject to final documentation, shareholder consent and regulatory approvals.

    Construction began in September, with operations scheduled to start in 2027.

    OMV, which already operates a 10MW electrolyser in Schwechat, will procure renewable electricity for hydrogen production and retain ownership of the output.

    Several large-scale hydrogen facilities across Europe are currently under construction.

    In 2024, Germany's Siemens Energy signed a deal with German utility EWE to build a 280MW green hydrogen electrolysis plant. This is expected to begin operations in 2027.

    Masdar and OMV previously signed a letter of intent to cooperate on green hydrogen, synthetic sustainable aviation fuels (e-SAF) and synthetic chemicals in both the UAE and central and northern Europe.


    READ THE NOVEMBER 2025 MEED BUSINESS REVIEW – click here to view PDF

    Mena players up the ante in global LNG production race; Investment takes UAE non-oil economy from strength to strength; Project finance activity draws international lenders back to market

    Distributed to senior decision-makers in the region and around the world, the November 2025 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/15040802/main0933.jpg
    Mark Dowdall
  • Syria signs deal for 5GW power projects

    7 November 2025

    Register for MEED’s 14-day trial access 

    The Syrian Ministry of Energy has signed final concession agreements with an international consortium led by Qatar’s Urbacon (UCC) Holding to build and operate eight power plants with a total capacity of 5GW.

    The consortium includes Urbacon Concessions Investment (a subsidiary of UCC Holding), Kalyon GIS Energy (Turkiye), Cengiz Energy (Turkiye) and Power International (US).

    UCC Holding and Power International USA are both subsidiaries of Qatar’s Power International Holding. The US-based subsidiary was likely created to ease transactions and imports to Syria under the new General Licence 25 (GL 25) US sanctions exemptions for Syria.

    The final contracts cover the construction and operation of the following four natural gas-fired combined-cycle plants:

    • North Aleppo (1,200MW)
    • Deir Ezzor (1,000MW)
    • Zayzoun (1,000MW)
    • Mehardeh (800MW)

    It also includes four solar projects totalling 1,000MW across Widian Al-Rabee, Deir Ezzor, Aleppo and Homs.

    The agreements were signed in Damascus by Energy Minister Mohammad Al-Bashir and UCC Holding president Ramez Al-Khayyat, in the presence of consortium representatives and senior Syrian energy officials.

    The deal represents Syria’s first integrated public-private partnership model in the energy sector and marks the start of the implementation phase of Syria’s national energy rehabilitation programme. 

    The projects also form part of a wider Qatari investment package in Syria.

    In May, the ministry signed a $7bn memorandum of understanding that set the framework for strategic energy cooperation.

    Preparatory engineering and technical works, including site surveys and feasibility studies, have since been completed.

    Completion is expected within three years for the gas plants and two years for the solar plants, with the projects doubling the country’s output.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/15040717/main.jpg
    Mark Dowdall
  • Firms submit Saudi customs warehouses PPP bids

    7 November 2025

     

    Three Saudi-based firms submitted bids on 29 September for a contract to build new customs warehouses in Saudi Arabia.

    The project is being tendered as a public-private partnership (PPP) on a design, build, finance, operate, maintain and transfer basis, with a contract duration of 15 years, including the construction period.

    The bidders include:

    • Al-Drees Petroleum & Transport Services Company
    • Lamar Holding
    • Mada International Holding

    The contract scope covers the development of 13 warehouses – including the design and construction of 12 new facilities and the renovation of one – across 13 different points of entry in the kingdom, along with the maintenance of all sites.

    The contract also includes the supply of equipment, as well as logistical support and cleaning services, for all new and existing warehouses at 38 points of entry across the kingdom.

    In January, the Zakat, Tax and Customs Authority (Zatca), through the National Centre for Privatisation and PPP (NCP), prequalified five companies to bid, MEED reported.

    The client issued the expressions of interest (EOI) and request for qualifications (RFQ) notices for the project in October last year.

    PPP plans

    In April 2023, Saudi Arabia announced a privatisation and public-private partnership (P&PPP) pipeline comprising 200 projects across 16 sectors.

    The P&PPP pipeline aims to attract both local and international investors and ensure their readiness to participate in the schemes tendered to the market.

    The initiative supports the kingdom’s efforts to enhance the attractiveness of its economy and increase the private sector’s contribution to GDP.


    READ THE NOVEMBER 2025 MEED BUSINESS REVIEW – click here to view PDF

    Mena players up the ante in global LNG production race; Investment takes UAE non-oil economy from strength to strength; Project finance activity draws international lenders back to market

    Distributed to senior decision-makers in the region and around the world, the November 2025 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/15040496/main.gif
    Yasir Iqbal