Warming erodes Kuwait’s power and water reserves

14 August 2023

More on Kuwait’s power and water sector: 

> IWPP: Firms respond to Kuwait independent utilities request
> POWERLocal firm wins 250MW Subiya package
> PRIVATISATIONKuwait thermal plant privatisation to go ahead


 

The temperature in Kuwait soared to 51 degrees Celsius on 1 August, sending its electricity load index up to 16,940MW. This breached its maximum expected load this year of 16,830MW by 0.7 per cent.

This year’s projected maximum load is already 4 per cent higher than the previous year's recorded maximum load. It leaves only roughly 8 per cent of reserve capacity against an available capacity understood to stand at 18,250MW.

Similarly, water consumption across the Gulf state on 2 August, when the temperature decreased to 50 degrees, exceeded production by 29 million gallons, prompting the state utility to access its strategic water reserve capacity to plug the shortfall.

The electricity consumption spike reportedly caused two feeders at the country’s main substation south of Surra in the capital to trip, which led to power outages in some parts of Zahra, a district in Kuwait’s Hawalli governorate.

Kuwait’s Electricity & Renewable Energy Ministry (MEWRE) assured the public that the maximum capacity available in the country’s electricity network during the current summer is 18,250MW, as earlier cited, and that it could safely provide up to 17,660MW.

Persistent delays

The following week MEWRE – through the Kuwait Authority for Partnership Projects (Kapp) – received prequalification applications for the contracts to develop Kuwait’s next two independent water and power producer (IWPP) projects.

The two schemes – Al-Zour North 2 & 3 and Al-Khiran 1 – will have a total combined power generation capacity of 4,500MW and a water desalination capacity of over 150 million imperial gallons a day (MIGD), which will go a long way to address Kuwait’s precarious electricity and water supply situation.

Ironically, these two schemes have been in the planning and early procurement stages since 2017 and have suffered significant delays in the intervening period.

It is the second time developers have submitted statements of qualification (SOQs) for the contracts over the preceding 11 months.

The delays have caused major frustration for some developers and contractors. One utility developer that submitted an SOQ in September last year told MEED they did not participate in the latest attempt to start the prequalification process for the IWPP schemes, without elaborating.

Others expect the country’s stakeholders to eventually approve and expedite the procurement process for the integrated power and desalination facilities.

“I’m not very optimistic, but we submitted an SOQ anyway,” another source tells MEED.

EPC projects motoring ahead

The ministry’s conventional power plant projects have been moving at a relatively faster pace. In June this year, the local company Heavy Engineering Industries & Shipbuilding (Heisco) won a contract for the phase 2 upgrade of the Subiya power plant complex in Kuwait.

Heisco saw off competition from two local companies, Alghanim International and Al-Zain United General Trading & Contracting, for the KD114.28m ($372m) contract.

The project aims to convert an existing 250MW simple-cycle plant into a combined-cycle gas-turbine plant.

In April, a consortium comprising Heisco and Japan’s Mitsubishi Power was also awarded a contract to retrofit the main thermal power generation plant at the power complex.

The contract is understood to be valued at KD90.9m. It entails the upgrade of eight steam turbines and electric generators at the Subiya power plant, which is expected to reach a capacity of 2,400MW once the project is complete.

The existing plant at the Subiya power complex was commissioned between 1998 and 2002. This implies that the steam turbines and generators in commercial operation for nearly 20 years require upgrades to continue operating and improve their performance.

Two steps forward

While the country has pledged to become carbon neutral by 2060, the state utility has yet to make any remarkable progress in procuring new renewable energy capacity.

The recent political deadlock has hampered the procurement of the next phases of the Shagaya Renewable Energy Programme (SREP), despite the award 12 months previously of the project’s transaction advisory contract to a team led by London-headquartered consultancy firm EY.

At the time, the advisory contract was understood to cover the Al-Dibdibah solar project, which will comprise SREP’s second phase, and a third phase expected to include a 720MW solar photovoltaic (PV) plant, a 1,150MW concentrated solar power (CSP) facility and a wind power farm.

Notably, two state-backed downstream operators – Kuwait National Petroleum Company and Kuwait Integrated Petroleum Industries Company (Kipic) – have launched a tender for a contract to undertake a pre-feasibility study identifying opportunities to use renewable energy in their operations.

Kuwait is also expected to make some progress on its first utility privatisation scheme, which forms part of the initiative to strengthen private sector participation in the sector.

In December last year, it was revealed that UK-headquartered Deloitte had submitted a low bid of KD1.2m ($3.9m) for the transaction advisory contract in line with the planned privatisation of the $1.26bn North Shuaiba power and water plant in Kuwait.

GCC grid

While working to boost its electricity reserves and make its electricity systems greener, Kuwait stands to benefit from the ongoing upgrade of the GCC electricity grid, through which other GCC states, such as the UAE, may decide to transmit excess clean energy.

The Al-Fadhili high-voltage direct current (HVDC) converter station upgrade in Saudi Arabia is expected to enable the exchange of 1,800MW of electricity between the six states once complete.

In October last year, the GCC Interconnection Authority (GCCIA) awarded India-based KEC International a contract for an overhead transmission line project linking the substations in Wafra in Kuwait and Fadhili in Saudi Arabia.

The estimated $120m project extends an existing double-circuit 400kV line from Al-Zour in Kuwait to Ghunan in Saudi Arabia. The line has an intermediate interconnection at Fadhili, with associated substations completed in 2009 as part of the first phase of the GCCIA network. The new project is expected to complete in 2025.


This month’s special report on Kuwait also includes: 

> ECONOMYStakeholders hope Kuwait can execute spending plans
> ENERGYKuwait’s $300bn energy target is a big test
> BANKINGKuwaiti banks enter bounce-back mode
> INTERVIEWKuwait’s Gulf Centre United sets course for expansion

https://image.digitalinsightresearch.in/uploads/NewsArticle/11069881/main.gif
Jennifer Aguinaldo
Related Articles
  • Public Investment Fund backs Neom

    16 April 2026

    Commentary
    Colin Foreman
    Editor

    Register for MEED’s 14-day trial access 

    Saudi Arabia’s Public Investment Fund (PIF) has backed Neom by including it as one of six strategic ecosystems in its newly approved 2026-30 strategy.

    The future of the $500bn gigaproject had been thrown into doubt following the postponement of the 2029 Asian Winter Games at the Trojena mountain resort, the cancellation of construction contracts – such as the $5bn deal with Italian contractor Webuild for dam works at Trojena – and the slowdown of development at The Line, where tunnelling contracts were cancelled and staff left the project.

    The backing comes as Neom’s operational focus appears to be evolving in response to shifting regional dynamics and global economic conditions. For example, on 15 April Neom posted on its official X account about a new Europe-Egypt-Neom-GCC corridor, describing it as a faster route for time-sensitive goods. It said the corridor combines trucking and ferry services to move goods quickly into the Gulf, adding that importers from several European markets are already using it to reach the UAE, Kuwait, Iraq, Oman and beyond.

    Powered by Pan Marine, DFDS and regional RoPax services, the initiative is positioned as a way to add flexibility and resilience to regional supply chains. This emphasis on logistics and immediate trade utility suggests a shift away from the more speculative architectural announcements that characterised Neom’s early years, towards activity more directly tied to current market realities.

    PIF’s broader 2026-30 strategy places heavy emphasis on “delivering competitive domestic ecosystems to connect sectors, unlock the full potential of strategic assets, maximise long-term returns and continue to drive the economic transformation of Saudi Arabia”.

    The inclusion of Neom as a standalone ecosystem within the Vision Portfolio suggests that while the project remains part of the kingdom’s Vision 2030 goals, it will be subject to the fund's focus on working with the private sector.

    That means the long-term success of Neom will increasingly depend on its ability to attract external investment and function as a viable economic hub rather than just a state-funded construction site.


    MEED’s April 2026 report on Saudi Arabia includes:

    > COMMENT: Risk accelerates Saudi spending shift
    > GVT &: ECONOMY: Riyadh navigates a changed landscape
    > BANKING: Testing times for Saudi banks
    > UPSTREAM: Offshore oil and gas projects to dominate Aramco capex in 2026
    > DOWNSTREAM: Saudi downstream projects market enters lean period
    > POWER: Wind power gathers pace in Saudi Arabia

    > WATER: Sharakat plan signals next phase of Saudi water expansion
    > CONSTRUCTION: Saudi construction enters a period of strategic readjustment
    > TRANSPORT: Rail expansion powers Saudi Arabia’s infrastructure push

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/16417262/main.jpeg
    Colin Foreman
  • Kuwait gas project worth $3.3bn put on hold

    16 April 2026

     

    State-owned Kuwait Gulf Oil Company’s (KGOC’s) planned tender for the development of an onshore gas plant next to the Al-Zour refinery has been put on hold due to uncertainty created by the US and Israel’s war with Iran, according to industry sources.

    The project budget is estimated to be $3.3bn, and the last meeting with contractors to discuss the project took place in Kuwait on 10 February.

    Previously, it was expected to be tendered in late March, but the tendering process was delayed due to the regional conflict and disruption to shipping through the Strait of Hormuz.

    One source said: “This tender is now effectively on hold while KGOC waits for increased stability in the region before it invites companies to bid for the contract.”

    Under current plans, the plant will have the capacity to process up to 632 million cubic feet a day of gas and 88.9 million barrels a day of condensates from the Dorra offshore field, located in Gulf waters in the Saudi-Kuwait Neutral Zone.

    Ownership of the field is disputed by Iran, which refers to the field as Arash.

    Iran claims the field partially extends into Iranian territory and asserts that Tehran should be a stakeholder in its development.

    It is believed that the Dorra field’s close proximity to Iran will make development difficult due to the current security environment.

    The offshore elements of the project are expected to be especially difficult to protect from attacks from Iran.

    In July last year, MEED reported that KGOC had initiated the project by launching an early engagement process with contractors for the main engineering, procurement and construction tender.

    France-based Technip Energies completed the contract for the front-end engineering and design.


    READ THE APRIL 2026 MEED BUSINESS REVIEW – click here to view PDF

    Economic shock threatens long-term outlook; Riyadh adjusts to fiscal and geopolitical risk; GCC contractor ranking reflects gigaprojects slowdown.

    Distributed to senior decision-makers in the region and around the world, the April 2026 edition of MEED Business Review includes:

    > GCC CONTRACTOR RANKING: Construction guard undergoes a shift
    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/16413221/main.png
    Wil Crisp
  • Iraq pushes to revive oil pipeline through Saudi Arabia

    16 April 2026

    Iraq is pushing to revive an oil pipeline that passes through Saudi Arabia, allowing it to diversify export routes.

    Saheb Bazoun, a spokesman for Iraq’s Oil Ministry, said the pipeline would help to insulate Iraq from any future blockades of the Strait of Hormuz, which has been largely closed since 28 February.

    The original pipeline through Saudi Arabia has not been used for more than 30 years and would need work to be done in order to bring it online.

    It is 1,568km long, extending from the city of Zubair in Iraq to the Saudi port of Yanbu on the Red Sea.

    The pipeline was built in two phases during the 1980s. The first phase stretches between Zubair and Khurais, while the second extends to Yanbu. The pipeline’s operating capacity reached over 1.6 million barrels a day (b/d).

    Following the Gulf War, the pipeline was shut down in August 1990. It has remained out of operation for decades, despite Iraq’s several attempts to restart it.

    The original pipeline project cost over $2.6bn, including storage tanks and loading terminals.

    In the wake of the US and Israel attacking Iran on 28 February, global markets have lost 11 million barrels a day (b/d) of oil supply due to the effective closure of the Strait of Hormuz.


    READ THE APRIL 2026 MEED BUSINESS REVIEW – click here to view PDF

    Economic shock threatens long-term outlook; Riyadh adjusts to fiscal and geopolitical risk; GCC contractor ranking reflects gigaprojects slowdown.

    Distributed to senior decision-makers in the region and around the world, the April 2026 edition of MEED Business Review includes:

    > GCC CONTRACTOR RANKING: Construction guard undergoes a shift
    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/16413290/main.jpg
    Wil Crisp
  • Algeria opens bidding for water treatment plant

    15 April 2026

     

    State-owned Cosider Pipelines, part of Algeria’s public infrastructure group Cosider, has issued a tender for the construction of a demineralisation plant in In Salah in Algeria.

    The contract covers the design, supply, installation, testing and commissioning of a plant with a treatment capacity of 62,000 cubic metres a day (cm/d).

    The tender is open to local and international companies specialising in the design and construction of demineralisation and reverse osmosis desalination plants.

    The bid submission deadline is 26 April.

    The project will be located at In Salah, a key industrial area in southern Algeria, where treated water supply is important for both municipal and industrial use.

    Cosider said that individual bidders must demonstrate that they have completed at least one reverse osmosis demineralisation or desalination plant with a capacity of 20,000 cubic metres a day or more.

    They must also show an average annual turnover of at least AD1bn ($7.7m) for their five best years over the past decade.

    For consortium bids, all partners must share full responsibility for the contract, while the lead company must meet the technical and financial requirements.

    Recent projects

    In 2023, MEED reported that Riyadh-based water utility developer Wetico had won two contracts to develop water desalination plants in Algeria.

    Societe Algerienne de Realisation de Projects Industriels (Sarpi) awarded the contract for the El-Tarf desalination plant, while Entreprise Nationale de Canalisations (Enac) is the client for the Bejaja facility.

    Both plants were commissioned in 2025, each with a production capacity of 300,000 cm/d.

    Separately, Wetico was the main contractor on a third plant commissioned last year. The Cap Dijinet 2 seawater desalination plant in Boumerdes province covers 18 hectares and also has a capacity of 300,000 cm/d.

    Like many countries, Algeria is facing pressure on resources due to longer and more frequent droughts. Seawater desalination is seen as a key driver of the government’s strategy to guarantee drinking water supply.

    According to previous reports, the government is planning to build up to six additional plants by 2030.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16404325/main.jpg
    Mark Dowdall
  • WEBINAR: UAE Projects Market 2026

    15 April 2026

    Webinar: UAE Projects Market 2026
    Tuesday, 28 April 2026 | 11:00 GST  |  Register now


    Agenda:

    • Overview of the UAE projects market landscape
    • 2025 projects market performance
    • Value of work awarded 2026 YTD
    • Impact of the Iran conflict on the projects market and real estate, assessing supply chain disruptions, material cost inflation and war risk premiums
    • Key drivers, challenges and opportunities
    • Size of future pipeline by sector and status
    • Ranking of the top contractors and clients
    • Summary of key current and future projects
    • Short and long-term market outlook
    • Audience Q&A

    Hosted by: Colin Foreman, editor of MEED 

    Colin Foreman is editor and a specialist construction journalist for news and analysis on MEED.com and the MEED Business Review magazine. He has been reporting on the region since 2003, specialising in the construction sector and its impact on the broader economy. He has reported exclusively on a wide range of projects across the region including Dubai Metro, the Burj Khalifa, Jeddah Airport, Doha Metro, Hamad International airport and Yas Island. Before joining MEED, Colin reported on the construction sector in Hong Kong.

    Click here to register

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16401868/main.gif
    Colin Foreman