Warming erodes Kuwait’s power and water reserves

14 August 2023

More on Kuwait’s power and water sector: 

> IWPP: Firms respond to Kuwait independent utilities request
> POWERLocal firm wins 250MW Subiya package
> PRIVATISATIONKuwait thermal plant privatisation to go ahead


 

The temperature in Kuwait soared to 51 degrees Celsius on 1 August, sending its electricity load index up to 16,940MW. This breached its maximum expected load this year of 16,830MW by 0.7 per cent.

This year’s projected maximum load is already 4 per cent higher than the previous year's recorded maximum load. It leaves only roughly 8 per cent of reserve capacity against an available capacity understood to stand at 18,250MW.

Similarly, water consumption across the Gulf state on 2 August, when the temperature decreased to 50 degrees, exceeded production by 29 million gallons, prompting the state utility to access its strategic water reserve capacity to plug the shortfall.

The electricity consumption spike reportedly caused two feeders at the country’s main substation south of Surra in the capital to trip, which led to power outages in some parts of Zahra, a district in Kuwait’s Hawalli governorate.

Kuwait’s Electricity & Renewable Energy Ministry (MEWRE) assured the public that the maximum capacity available in the country’s electricity network during the current summer is 18,250MW, as earlier cited, and that it could safely provide up to 17,660MW.

Persistent delays

The following week MEWRE – through the Kuwait Authority for Partnership Projects (Kapp) – received prequalification applications for the contracts to develop Kuwait’s next two independent water and power producer (IWPP) projects.

The two schemes – Al-Zour North 2 & 3 and Al-Khiran 1 – will have a total combined power generation capacity of 4,500MW and a water desalination capacity of over 150 million imperial gallons a day (MIGD), which will go a long way to address Kuwait’s precarious electricity and water supply situation.

Ironically, these two schemes have been in the planning and early procurement stages since 2017 and have suffered significant delays in the intervening period.

It is the second time developers have submitted statements of qualification (SOQs) for the contracts over the preceding 11 months.

The delays have caused major frustration for some developers and contractors. One utility developer that submitted an SOQ in September last year told MEED they did not participate in the latest attempt to start the prequalification process for the IWPP schemes, without elaborating.

Others expect the country’s stakeholders to eventually approve and expedite the procurement process for the integrated power and desalination facilities.

“I’m not very optimistic, but we submitted an SOQ anyway,” another source tells MEED.

EPC projects motoring ahead

The ministry’s conventional power plant projects have been moving at a relatively faster pace. In June this year, the local company Heavy Engineering Industries & Shipbuilding (Heisco) won a contract for the phase 2 upgrade of the Subiya power plant complex in Kuwait.

Heisco saw off competition from two local companies, Alghanim International and Al-Zain United General Trading & Contracting, for the KD114.28m ($372m) contract.

The project aims to convert an existing 250MW simple-cycle plant into a combined-cycle gas-turbine plant.

In April, a consortium comprising Heisco and Japan’s Mitsubishi Power was also awarded a contract to retrofit the main thermal power generation plant at the power complex.

The contract is understood to be valued at KD90.9m. It entails the upgrade of eight steam turbines and electric generators at the Subiya power plant, which is expected to reach a capacity of 2,400MW once the project is complete.

The existing plant at the Subiya power complex was commissioned between 1998 and 2002. This implies that the steam turbines and generators in commercial operation for nearly 20 years require upgrades to continue operating and improve their performance.

Two steps forward

While the country has pledged to become carbon neutral by 2060, the state utility has yet to make any remarkable progress in procuring new renewable energy capacity.

The recent political deadlock has hampered the procurement of the next phases of the Shagaya Renewable Energy Programme (SREP), despite the award 12 months previously of the project’s transaction advisory contract to a team led by London-headquartered consultancy firm EY.

At the time, the advisory contract was understood to cover the Al-Dibdibah solar project, which will comprise SREP’s second phase, and a third phase expected to include a 720MW solar photovoltaic (PV) plant, a 1,150MW concentrated solar power (CSP) facility and a wind power farm.

Notably, two state-backed downstream operators – Kuwait National Petroleum Company and Kuwait Integrated Petroleum Industries Company (Kipic) – have launched a tender for a contract to undertake a pre-feasibility study identifying opportunities to use renewable energy in their operations.

Kuwait is also expected to make some progress on its first utility privatisation scheme, which forms part of the initiative to strengthen private sector participation in the sector.

In December last year, it was revealed that UK-headquartered Deloitte had submitted a low bid of KD1.2m ($3.9m) for the transaction advisory contract in line with the planned privatisation of the $1.26bn North Shuaiba power and water plant in Kuwait.

GCC grid

While working to boost its electricity reserves and make its electricity systems greener, Kuwait stands to benefit from the ongoing upgrade of the GCC electricity grid, through which other GCC states, such as the UAE, may decide to transmit excess clean energy.

The Al-Fadhili high-voltage direct current (HVDC) converter station upgrade in Saudi Arabia is expected to enable the exchange of 1,800MW of electricity between the six states once complete.

In October last year, the GCC Interconnection Authority (GCCIA) awarded India-based KEC International a contract for an overhead transmission line project linking the substations in Wafra in Kuwait and Fadhili in Saudi Arabia.

The estimated $120m project extends an existing double-circuit 400kV line from Al-Zour in Kuwait to Ghunan in Saudi Arabia. The line has an intermediate interconnection at Fadhili, with associated substations completed in 2009 as part of the first phase of the GCCIA network. The new project is expected to complete in 2025.


This month’s special report on Kuwait also includes: 

> ECONOMYStakeholders hope Kuwait can execute spending plans
> ENERGYKuwait’s $300bn energy target is a big test
> BANKINGKuwaiti banks enter bounce-back mode
> INTERVIEWKuwait’s Gulf Centre United sets course for expansion

https://image.digitalinsightresearch.in/uploads/NewsArticle/11069881/main.gif
Jennifer Aguinaldo
Related Articles
  • Egypt approves $1.7bn capital spending in 2026-27

    31 March 2026

    Egypt’s cabinet has approved E£90bn ($1.7bn) in capital spending as part of the draft 2026-27 budget announced this week.

    Total spending under the new budget is projected to be about 13% higher than this year’s, aimed at supporting economic growth and reducing debt.

    Expenditure is estimated at E£5.1tn ($98bn), while revenue is projected at about E£4tn ($77bn), up 27.6% compared with the previous budget.

    According to remarks posted on the cabinet’s website, Finance Minister Ahmed Kouchouk said the draft budget – still subject to parliamentary approval – sets aside E£90bn for projects and other economic activities and seeks to lower the overall deficit by 2.1 percentage points to 4.9%.

    The budget will take effect on 1 July 2026 and aims to bring public debt down to around 78% by the end of the fiscal year, from nearly 78% the year before.


    MEED’s March 2026 report on Egypt includes:

    > COMMENT: Egypt’s crisis mode gives way to cautious revival
    > GOVERNMENT: Egypt adapts its foreign policy approach

    > ECONOMY & BANKING: Egypt nears return to economic stability
    > OIL & GAS: Egypt’s oil and gas sector shows bright spots
    > POWER & WATER: Egypt utility contracts hit $5bn decade peak
    > CONSTRUCTION: Coastal destinations are a boon to Egyptian construction

    To see previous issues of MEED Business Review, please click here

     

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16186238/main.jpg
    Yasir Iqbal
  • Abu Dhabi receives four bids for Al-Nouf IPP

    30 March 2026

    State utility Emirates Water & Electricity Company (Ewec) has announced it has received four bids for the development of the 3.3GW Al-Nouf independent power producer (IPP) project in Abu Dhabi.

    Located within the newly established Al-Nouf complex, the facility will be the largest single-site, carbon-capture-ready, combined-cycle gas turbine plant in the UAE. 

    Ewec issued a request for proposals for the project last August. It received statements of qualifications for the contract in April 2025.

    Earlier this month, MEED exclusively revealed that Aljomaih Energy & Water (Saudi Arabia) and Sumitomo (Japan) were among the bidders for the project.

    The groups that submitted bids include the following three consortiums and one individual company:

    • Aljomaih Energy & Water (Saudi Arabia) / Sembcorp Industries (Singapore) / EDF Power Solutions (France)
    • Engie (France) / Korea Overseas Infrastructure & Urban Development Corporation (Kind) / Korea Western Power Company (Kowepo)
    • Korea Electric Power Corporation (Kepco) / Etihad Water & Electricity (EtihadWE)
    • Sumitomo (Japan) 

    As MEED previously reported, the project will follow the model of Abu Dhabi’s IPP programme, in which developers enter into a long-term agreement with Ewec as the sole procurer. 

    This involves the development, financing, construction, operation, maintenance and ownership of the plant, with the successful developer or developer consortium owning up to 40% of the entity. The remaining equity will be held indirectly by the Abu Dhabi government.

    The project site was selected for its ability to accommodate both seawater-cooled power generation and reverse osmosis desalination technologies.

    The plant will have the capacity to support several utility-scale energy and desalination projects in the future.

    The facility is scheduled to begin commercial operations in the third quarter of 2029.

    Taweelah C IPP

    Last year, the Taweelah C IPP became the first gas-fired power plant project to be procured by Abu Dhabi since 2020, when Ewec awarded Japan’s Marubeni Corporation the contract to develop the Fujairah 3 IPP.

    Ewec is procuring the 2,500MW gas-fired IPP, which will be located in the Al-Taweelah power and desalination complex, approximately 50 kilometres to the northeast of Abu Dhabi.

    It is understood that three groups have submitted bids for the developer contract. These are:

    • Sumitomo (Japan) / Korean Midland Power / Korea Overseas Infrastructure & Urban Development Corporation 
    • Aljomaih Energy & Water (Saudi Arabia)  / Sembcorp (Singapore)
    • Etihad Water & Electricity (UAE) / Korea Western Power (Kowepo) / Kyuden (Japan)

    A team of UK-based Alderbrook Finance and US-based Sargent & Lundy is providing financial and technical advisory services to Ewec for the Taweelah C IPP.

    The power purchase agreement for the project was previously expected to be signed by the end of 2025, with the project scheduled to begin commercial operations in the fourth quarter of 2028.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16185238/main.jpg
    Mark Dowdall
  • Neom cancels major desalination project

    30 March 2026

     

    Saudi gigaproject developer Neom has cancelled plans to build a major seawater reverse osmosis (SWRO) desalination plant, according to industry sources.

    The plant, due to have a capacity of 150,000 cubic metres a day (cm/d), had been tendered in 2024.

    In October that year, MEED reported that Enowa, the Neom utility subsidiary, had received four bids from companies for a contract to build the plant.

    These included:

    • Alfanar Company (local) / Abengoa (Spain)
    • China Machinery Engineering Corporation (CMEC)
    • Orascom (Egypt) / Wetico (local)
    • VA Tech Wabag (India) 

    In 2025, the project failed to reach the contract award stage. It has since been cancelled as part of a “complete restructure for Neom”, a source told MEED. 

    Neom did not respond to a request for comment. However, it is understood that the desalination project will not be retendered under a new scope. 

    The SWRO plant, previously known as the Moonlight desalination plant, was due to be built adjacent to the 125,000 cm/d desalination plant at Duba on Saudi Arabia’s Red Sea coast. It was expected to take 12 months to complete.

    Previously, in May 2024, Enowa confirmed the cancellation of another project to develop a renewable-energy-powered advanced SWRO project with zero liquid discharge in Oxagon, Neom’s industrial cluster.

    The scope of the cancelled project’s first phase, to be developed by a team of Japan’s Itochu Corporation and France’s Veolia, included a desalination plant with a production capacity of 500,000 cm/d of desalinated water.  

    In recent months, Saudi Arabia’s construction sector has been pivoting away from prestige-driven capital expenditure towards more deliverable priorities.

    In March, MEED exclusively revealed that Neom had cancelled the contracts related to the construction of the tunnel sections of The Line in northwest Saudi Arabia.

    The tunnels formed part of the infrastructure backbone of Neom’s 170-kilometre The Line development, launched in January 2021.

    Separately, it was also announced that a contract between Neom and Malaysian contractor Eversendai Corporation had been terminated for the steel structural works on the Ski Village Trojena project.

    According to media reports, the shift away from large-scale gigaprojects includes a pivot towards repositioning what remains of Neom as an industrial and data centre hub.

    Such plans would leverage the Red Sea coastline’s access to seawater cooling for artificial intelligence (AI) infrastructure.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16141326/main.jpg
    Mark Dowdall
  • Construction guard undergoes a shift

    30 March 2026

     

    The 2026 GCC Construction Contractor Ranking reflects two key trends. One is a growing trend that has been steadily rising across the region for more than a decade, while the other is a more recent development, which is now followed by the added uncertainty of a war with Iran.

    The long-running trend is the rise of Chinese contractors. After years of Saudi-based dominance, Beijing’s China State Construction Engineering Corporation has claimed the top spot as the region’s most active contractor, with $10.399bn of work currently at the execution stage. This represents a notable rise for the firm, which was ranked second in 2025.

    China State is not the only Chinese contractor in the top three. China Harbour Engineering Company ranks third, with $8.64bn of work under execution. Both firms are among China’s largest construction companies and have a longstanding presence in the region. In recent years, their success has encouraged other Chinese contractors to enter the market and win work. This trend is reflected in the national rankings, where other Chinese players feature prominently and may follow China State and China Harbour in rising to the top of the regional rankings.

    Saudi reprioritisation

    The other more recent trend affecting the 2026 ranking is the reprioritisation of projects in Saudi Arabia. The reassessment of the kingdom’s capital expenditure commitments led to a sharp decrease in contract awards during 2025. Combined with contractors completing work on projects secured immediately after the Covid-19 pandemic in 2021 and 2022, this has resulted in an overall decline in the value of work at the execution stage.”

    This trend is reflected in China State’s figures. Although it moved up the rankings in 2026, the total value of work at the execution stage declined from $13.5bn to $10.4bn – a drop of about 30%.

    The decline was even more pronounced for Saudi Arabia-based Nesma & Partners, which, unlike China State, does not have extensive operations in other GCC markets. Nesma moved to second place with $8.844bn of work under execution.

    Despite the slowdown in activity in the kingdom, Saudi contractors continue to hold four of the top 10 positions, down from six in the 2025 ranking. El-Seif Engineering Contracting, Al-Bawani and Shibh Al-Jazira dropped out of the rankings, while Modern Building Leaders entered the top 10.

    The other newcomer to the list is London-headquartered Innovo, which has rapidly become one of the most active building contractors in the UAE, with projects in Dubai and Abu Dhabi.

    Bahrain

    The Bahraini market remains dominated by large-scale social infrastructure and residential developments. In 2026, the ranking shows that contractors that have maintained a steady amount of work at the execution stage have risen up the ranking as other contractors complete projects and drop down the listing.

    China Machinery Engineering Company maintains its position at the top of the ranking, with $689m of work under execution. Its primary focus continues to be the East Sitra housing scheme, a multi-phase project for the Ministry of Housing & Urban Planning that has involved the construction of thousands of housing units since 2019.

    Nass Contracting has climbed back to second position with $639m. The local contractor was ranked fourth in 2025. Its portfolio is bolstered by significant infrastructure wins, including the Busaiteen Link scheme and the expansion of the RCSI Bahrain campus. Al-Hamad Building Contracting follows in third place with $610m, continuing its work on major Manama-based projects such as the Villamar residential complex.

    In fourth position is the local Saleh Abdulla Kameshki & Sons, with $237m of work at the execution stage, followed by the local Kooheji Contractors in fifth place, with $230m of work at the execution stage. Kooheji was the seventh-ranked contractor in 2025.

    Another local contractor that has risen up the ranking is Cebarco, which now sits in sixth place up from eighth, with $218m of work under execution. The local Almoayyed Contracting Group now sits in seventh place, down from sixth last year.

    The other companies were not in the top 10 in 2025. They are CCT Constructor Group, Dar Al-Binaa Construction and Haji Hassan Group.

    Kuwait

    Turkiye’s Limak remains the top-ranked contractor in Kuwait, with $6.052bn of projects at the execution stage. The firm’s ranking reflects its work on the multibillion-dollar expansion of Kuwait International airport Terminal 2 and various road maintenance contracts for the Ministry of Public Works.

    Chinese contractors have significantly increased their footprint in the country. China signed a series of agreements in 2023 that covered the delivery of some of Kuwait’s immediate development goals between 2024 and 2028. These agreements positioned Chinese companies to play a leading role in the Fourth Kuwait Master Plan 2040, and this is now shown in the contractor ranking for 2026.

    China Communications Construction Company (CCCC) takes the second spot with $3.625bn, while China Gezhouba Group Construction holds third with $1.670bn.

    In December last year, CCCC signed a $4bn agreement to develop the next phases of Kuwait’s Grand Mubarak Port on Boubyan Island. In March 2025, China Gezhouba won two contracts worth over $557m from the Public Authority for Housing Welfare for the South Saad Al-Abdullah residential project in Al-Jahra Governorate.

    While Chinese contractors are playing a growing role, local players continue to manage substantial orderbooks, including Al-Ahmadiah with $1.071bn of work under execution, Khalid Ali Kharafi & Sons with $1.017bn of work, and Mohamed Abdulmohsin Al-Kharafi & Sons with $992m.

    Oman

    The Omani construction sector has changed at the top as the value of projects that contractors have at the execution stage has declined. Al-Adrak Trading & Contracting Company has moved into first place with $1.423bn of work. The top-ranked contractor in 2025 had $2.4bn of projects at the execution stage.

    Al-Adrak was the eighth-ranked contractor in 2025, with $700m of projects at the execution stage.

    The local contractor’s recent success has been anchored by securing work on Oman’s new generation of real estate projects. In May 2025, it secured a contract with Saudi developer Dar Global to build the villas and apartments at the Aida project.

    Last year’s top-ranked contractor, Galfar Engineering & Contracting, is now in second place with $1.392bn. Galfar’s portfolio is headlined by the $1.5bn Hafeet Railway project connecting Oman and the UAE.

    Sarooj Construction Company follows closely in third with $1.372bn, while India’s Larsen & Toubro maintains a strong presence in fourth with $906m. Overall, the market shows further softening in 2026, with contractors across the rest of the ranking holding less work than in 2025, when the 10th-ranked contractor, PowerChina, had $500m of projects under construction. In 2026, it has $250m.

    Qatar

    Qatar’s market is transitioning into a post-World Cup phase, focusing on social infrastructure and utility projects. Midmac Contracting Company has moved to the top spot with $2.082bn, nearly doubling the value of projects held by the second-ranked UCC Holding, which has $1.05bn.

    Midmac’s return to the top 10 and the top of the ranking is largely due to it recently securing the $2bn Amiri flight facilities project at Hamad International airport, while UCC’s work remains centred on public-private partnership school schemes and road infrastructure for Ashghal.

    The contracting joint venture of Qatari Diar and Saudi Binladin Group, QD-SBG Construction, is in third position with $843m. Its largest ongoing project is Al-Rafidain Mall for Abraaj Al-Mustaqbal RealEstate.

    As the Qatari market transitions, four other contractors have moved into the top 10 in 2026. They are Badr Contracting & Trading with $534m of projects under execution, Al-Masaken Trading & Contracting Company with $400m, Marbu Contracting Company with $395m and Al-Mohannadi Group with $369m. As these contractors join the ranking, Consolidated Contractors Company (CCC), Shelter Contracting, InfraRoad Trading & Contracting Company, Changda Construction and American International Contractors Incorporated have moved out of the top 10.

    Saudi Arabia

    Much is changing in Saudi construction, but one constant is Nesma & Partners’ position at the top of the kingdom’s contractor ranking. While its position remains the same, the value of construction work that Nesma has under execution has decreased significantly when compared to 2025. This year, the contractor tops the Saudi ranking with nearly $9bn of work; last year it led with nearly $14bn of work.

    Nesma is not the only contractor that has experienced a reduction. Second-placed Almabani has $6.5bn of projects under construction this year compared with $8.5bn in 2025. Third-placed contractor Saudi Binladin Group has maintained a total of about $6.5bn over 2025 and 2026, and this has allowed the Jeddah-based contractor to jump up from seventh position last year. The company is working on several high-profile projects in the kingdom, including the world’s tallest tower in Jeddah, which will be over 1,000 metres tall.

    All the other contractors in the top 10 have similar declines in the value of their projects under execution. The exception is the local Building Contracting Company, which joins the top 10 in 10th position with $3.2bn of work. The 10th-ranked contractor in 2025 was China Harbour Engineering Corporation with $5.9bn of work, a total that in 2025 would have meant it would be the fourth-ranked contractor in 2026.

    The reduction in work volumes reflects the ongoing reprioritisation of projects in Saudi Arabia. Government officials have said that while some projects, such as The Line at Neom, have slowed down, other projects, such as those for Expo 2030 Riyadh and the Fifa World Cup in 2034, will be accelerated.

    UAE

    Contractors in the UAE are benefitting from high levels of spending across public infrastructure and real estate. Following on from 2025, Trojan General Contracting continues to lead the UAE ranking. In 2026, it has $7.59bn of projects under execution, up slightly from the $7.2bn recorded in 2025. The Abu Dhabi-based contractor has work on public infrastructure schemes for Abu Dhabi-based government agencies, and this base is supplemented by work on real estate projects across the UAE.

    China State Construction is in second position with $5.618bn under execution. The Beijing-based contractor has risen up the rankings from seventh position last year when it had $4bn of work under execution thanks to a series of deals for the construction of real estate and roads.

    In third position is London-headquartered Innovo with $5.443bn of work at the execution stage. Innovo is working on major real estate developments in Abu Dhabi and Dubai and has quickly grown in recent years to become one of the key players in the UAE’s construction sector.

    Sobha Constructions, the construction arm of property developer Sobha, is in fourth position with just over $5bn of work under execution. It is the main contractor for Sobha’s projects, which include the $763m Sobha Reserve and the $400m Skyvue Towers at Sobha Hartland 2.

    The local Dutco, with $4.43bn of work under execution, has joined the top 10 in fifth position. The contractor has picked up a wide range of work on Dubai real estate projects over the past two years. Three other contractors in the ranking, Ginco, Unec and Arabian Construction Company, also work extensively on real estate projects in Dubai and Abu Dhabi. The local Alec is active in the real estate sector too. Additionally, it is working on a large data centre project in Abu Dhabi as well as the Wynn resort in Ras Al-Khaimah.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16184074/main.gif
    Colin Foreman
  • Contractors submit bids for Aramco-backed logistics hub

    30 March 2026

     

    Contractors submitted bids on 18 March for a contract to build a logistics complex at King Salman Energy Park (Spark).

    Asmo, the logistics joint venture of Saudi Aramco and DHL Supply Chain, tendered the estimated SR804m ($214m) contract on 7 December.

    The logistics hub will span more than 100,700 square metres at Spark.

    Al-Khobar-based engineering firm House of Consulting Office is the project consultant.

    Last month, Asmo signed an agreement with Bahrain‑headquartered Arcapita Group Holdings to deliver the project at King Salman Energy Park (Spark).

    Last month, Asmo signed an agreement with Bahrain-headquartered Arcapita Group Holdings to deliver the project.

    The project will feature a 43,000 sq m temperature-controlled Grade A warehouse; more than 3,000 sq m of offices and staff amenities; 5,300 sq m dedicated to chemical storage; and an open yard spanning about 1.2 million sq m.

    Planned for large-scale industrial use, the site is expected to incorporate advanced warehouse and building management systems, end-to-end digital connectivity, automation and robotics.

    It will also be developed in line with internationally recognised sustainability standards, featuring solar (photovoltaic) readiness, electric-vehicle charging infrastructure and a target of LEED Gold certification.

    The development is aimed at supporting the next stage of Saudi Arabia’s logistics and supply chain expansion.

    Under the deal structure, Arcapita will provide funding and retain ownership of the asset, while Asmo will develop the facility and then lease and operate it under a 22-year occupational lease.

    According to a statement, “the scheme will be executed via a forward-funding model, underscoring a long-term commitment to national infrastructure”.

    Asmo added that this will be its first purpose-built logistics centre and one of four strategic locations planned to anchor its nationwide logistics network, aligned with the National Transport and Logistics Strategy under Saudi Vision 2030.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16183461/main.gif
    Yasir Iqbal