Warming erodes Kuwait’s power and water reserves
14 August 2023
More on Kuwait’s power and water sector:
> IWPP: Firms respond to Kuwait independent utilities request
> POWER: Local firm wins 250MW Subiya package
> PRIVATISATION: Kuwait thermal plant privatisation to go ahead

The temperature in Kuwait soared to 51 degrees Celsius on 1 August, sending its electricity load index up to 16,940MW. This breached its maximum expected load this year of 16,830MW by 0.7 per cent.
This year’s projected maximum load is already 4 per cent higher than the previous year's recorded maximum load. It leaves only roughly 8 per cent of reserve capacity against an available capacity understood to stand at 18,250MW.
Similarly, water consumption across the Gulf state on 2 August, when the temperature decreased to 50 degrees, exceeded production by 29 million gallons, prompting the state utility to access its strategic water reserve capacity to plug the shortfall.
The electricity consumption spike reportedly caused two feeders at the country’s main substation south of Surra in the capital to trip, which led to power outages in some parts of Zahra, a district in Kuwait’s Hawalli governorate.
Kuwait’s Electricity & Renewable Energy Ministry (MEWRE) assured the public that the maximum capacity available in the country’s electricity network during the current summer is 18,250MW, as earlier cited, and that it could safely provide up to 17,660MW.
Persistent delays
The following week MEWRE – through the Kuwait Authority for Partnership Projects (Kapp) – received prequalification applications for the contracts to develop Kuwait’s next two independent water and power producer (IWPP) projects.
The two schemes – Al-Zour North 2 & 3 and Al-Khiran 1 – will have a total combined power generation capacity of 4,500MW and a water desalination capacity of over 150 million imperial gallons a day (MIGD), which will go a long way to address Kuwait’s precarious electricity and water supply situation.
Ironically, these two schemes have been in the planning and early procurement stages since 2017 and have suffered significant delays in the intervening period.
It is the second time developers have submitted statements of qualification (SOQs) for the contracts over the preceding 11 months.
The delays have caused major frustration for some developers and contractors. One utility developer that submitted an SOQ in September last year told MEED they did not participate in the latest attempt to start the prequalification process for the IWPP schemes, without elaborating.
Others expect the country’s stakeholders to eventually approve and expedite the procurement process for the integrated power and desalination facilities.
“I’m not very optimistic, but we submitted an SOQ anyway,” another source tells MEED.
EPC projects motoring ahead
The ministry’s conventional power plant projects have been moving at a relatively faster pace. In June this year, the local company Heavy Engineering Industries & Shipbuilding (Heisco) won a contract for the phase 2 upgrade of the Subiya power plant complex in Kuwait.
Heisco saw off competition from two local companies, Alghanim International and Al-Zain United General Trading & Contracting, for the KD114.28m ($372m) contract.
The project aims to convert an existing 250MW simple-cycle plant into a combined-cycle gas-turbine plant.
In April, a consortium comprising Heisco and Japan’s Mitsubishi Power was also awarded a contract to retrofit the main thermal power generation plant at the power complex.
The contract is understood to be valued at KD90.9m. It entails the upgrade of eight steam turbines and electric generators at the Subiya power plant, which is expected to reach a capacity of 2,400MW once the project is complete.
The existing plant at the Subiya power complex was commissioned between 1998 and 2002. This implies that the steam turbines and generators in commercial operation for nearly 20 years require upgrades to continue operating and improve their performance.
Two steps forward
While the country has pledged to become carbon neutral by 2060, the state utility has yet to make any remarkable progress in procuring new renewable energy capacity.
The recent political deadlock has hampered the procurement of the next phases of the Shagaya Renewable Energy Programme (SREP), despite the award 12 months previously of the project’s transaction advisory contract to a team led by London-headquartered consultancy firm EY.
At the time, the advisory contract was understood to cover the Al-Dibdibah solar project, which will comprise SREP’s second phase, and a third phase expected to include a 720MW solar photovoltaic (PV) plant, a 1,150MW concentrated solar power (CSP) facility and a wind power farm.
Notably, two state-backed downstream operators – Kuwait National Petroleum Company and Kuwait Integrated Petroleum Industries Company (Kipic) – have launched a tender for a contract to undertake a pre-feasibility study identifying opportunities to use renewable energy in their operations.
Kuwait is also expected to make some progress on its first utility privatisation scheme, which forms part of the initiative to strengthen private sector participation in the sector.
In December last year, it was revealed that UK-headquartered Deloitte had submitted a low bid of KD1.2m ($3.9m) for the transaction advisory contract in line with the planned privatisation of the $1.26bn North Shuaiba power and water plant in Kuwait.
GCC grid
While working to boost its electricity reserves and make its electricity systems greener, Kuwait stands to benefit from the ongoing upgrade of the GCC electricity grid, through which other GCC states, such as the UAE, may decide to transmit excess clean energy.
The Al-Fadhili high-voltage direct current (HVDC) converter station upgrade in Saudi Arabia is expected to enable the exchange of 1,800MW of electricity between the six states once complete.
In October last year, the GCC Interconnection Authority (GCCIA) awarded India-based KEC International a contract for an overhead transmission line project linking the substations in Wafra in Kuwait and Fadhili in Saudi Arabia.
The estimated $120m project extends an existing double-circuit 400kV line from Al-Zour in Kuwait to Ghunan in Saudi Arabia. The line has an intermediate interconnection at Fadhili, with associated substations completed in 2009 as part of the first phase of the GCCIA network. The new project is expected to complete in 2025.
This month’s special report on Kuwait also includes:
> ECONOMY: Stakeholders hope Kuwait can execute spending plans
> ENERGY: Kuwait’s $300bn energy target is a big test
> BANKING: Kuwaiti banks enter bounce-back mode
> INTERVIEW: Kuwait’s Gulf Centre United sets course for expansion
Exclusive from Meed
-
Read the December 2025 MEED Business Review28 November 2025
-
Petrofac’s UAE operations continue after layoffs28 November 2025
-
PDO starts Dhulaima field early phase development project28 November 2025
-
Top deals signed at Dubai Airshow 202527 November 2025
-
Prequalification begins for Riyadh King Salman Stadium27 November 2025
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Read the December 2025 MEED Business Review28 November 2025
Download / Subscribe / 14-day trial access The region boasts a pipeline of over $140bn-worth of railway schemes, according to data from regional projects tracker MEED Projects.
This puts the GCC at the centre of global rail construction activity, with progress being made on several large-scale rail schemes.From the Qiddiya high-speed rail in Saudi Arabia to the planned expansion of Dubai’s metro network and the long-awaited revival of the GCC railway, a new wave of projects is shaping the region’s economic future.
As leading construction, engineering and technology firms either expand or return to the region after years of reduced activity, MEED’s latest issue of MEED Business Review looks at the scale and ambition of ongoing rail projects.
We also consider the region’s growing role as a rail hub, with an increasing need for ongoing servicing, upgrades and new technologies.
This month’s market focus covers Bahrain, where Manama is pushing ahead with diversification amid mounting fiscal constraints and external pressures.
MEED’s latest issue also includes our 2025 EPC contractor ranking, as well as analysis on the cost advantages, technological gains and strong execution giving Chinese contractors a regional edge.
This edition is bursting with features and interviews. The team looks at Libya's ramp up of oil activity; visits the under-construction Aramco Stadium in Khobar as it races towards completion; provides an update on Abu Dhabi's $6bn solar and storage project; and interviews Turki AlShehri, regional vice president for Saudi Arabia and the GCC at French power and water developer Engie.
We hope our valued subscribers enjoy the December 2025 issue of MEED Business Review.

Must-read sections in the December 2025 issue of MEED Business Review include:
> AGENDA:
> Regional rail construction surges ahead
> Middle East becomes a hub as rail networks matureINDUSTRY REPORT:
EPC contractor ranking
> Larsen & Toubro climbs EPC contractor ranking
> Chinese firms expand oil and gas presence> CURRENT AFFAIRS: Oil companies ramp up activity in Libya
> CONSTRUCTION: Aramco Stadium races towards completion
> RENEWABLES: UAE moves ahead with $6bn solar and storage project
> INTERVIEW: Engie pivots towards renewables projects
> BAHRAIN MARKET REPORT:
> COMMENT: Manama pursues reform amid strain
> GVT & ECONOMY: Bahrain’s cautious economic evolution
> BANKING: Mergers loom over Bahrain’s banking system
> OIL & GAS: Bahrain remains in pursuit of hydrocarbon resources
> POWER & WATER: Bahrain advances utility reform
> CONSTRUCTION: Bahrain construction faces major slowdown
> TRANSPORT: Air Asia aviation deal boosts connectivity
> DATABANK: Bahrain’s economy walks precarious path> MEED COMMENTS:
> Bahrain’s willingness to disrupt takes flight with Air Asia
> Projects shift from spending plans to investment opportunities
> Lukoil deal collapse puts $1.8bn of Iraq projects at risk
> Clear rules drive Saudi Arabia's tariff edge> GULF PROJECTS INDEX: UAE fuels Gulf projects expansion
> OCTOBER 2025 CONTRACTS: Saudi Arabia and UAE lead deal signings
> ECONOMIC DATA: November 2025: Data drives regional projects
> OPINION: Riyadh’s American bond
> BUSINESS OUTLOOK: Finance, oil and gas, construction, power and water contracts
To see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/15168493/main.gif -
Petrofac’s UAE operations continue after layoffs28 November 2025
The UK-headquartered company Petrofac is continuing to work on projects in the UAE after issuing termination notices to around 180 of its staff in the country.
Operations across Petrofac’s portfolio in the UAE are progressing as normal, according to statements sent to several media organisations.
The employees were given notice of their early release from the company on 19 November as part of restructuring measures.
On 27 October, Petrofac announced that it had applied to appoint administrators, a move that potentially put thousands of jobs at risk and increased uncertainty for projects worth billions of dollars in the Middle East and North Africa (Mena) region.
The total value of projects awarded to Petrofac and under construction in the region is $5.83bn, according to information recorded by the regional project-tracking service MEED Projects.
Petrofac also has bids under evaluation for 15 projects in the region worth a total of $19.28bn, according to MEED Projects data.
Ongoing restructuring
On 25 November, Petrofac released a statement saying that it was seeking to appoint administrators to its subsidiary Petrofac International Limited (PIL).
This subsidiary was previously focused on the group’s engineering and construction activities in the Mena region.
In its statement, Petrofac said that its subsidiary would “shortly make an application to the Royal Court of Jersey seeking a letter of request under section 426 of the Insolvency Act 1986”.
It added: “The purpose of this application is to ask the Royal Court of Jersey to issue a letter of request to the High Court of England and Wales and seek its assistance in appointing administrators to PIL.”
Petrofac said that PIL had no ongoing contracts in the Mena region and it intends to redeploy PIL’s 120 staff to other subsidiaries “wherever possible”.
It added: “The administration of PIL is expected to facilitate the purpose of Petrofac Limited’s administration, to help preserve the value of the wider Group and to facilitate the planned M&A solutions.”
Petrofac has said that it is continuing to push ahead with options for alternative restructuring and M&A solutions with key creditors.
https://image.digitalinsightresearch.in/uploads/NewsArticle/15173959/main.jpg -
PDO starts Dhulaima field early phase development project28 November 2025

Petroleum Development Oman (PDO) has started the prequalification process for engineering, procurement and construction (EPC) works on a project to develop key on-plot facilities as part of an early phase development of the Dhulaima onshore field.
The Dhulaima Upper Shuaiba field is located in the Lekhwair cluster in PDO’s Block 6 concession area. The Dhulaima early phase development project is to be executed on an operation lease contract for a duration of five years, PDO said in the prequalification document.
Majority state-owned PDO floated the prequalification questionnaire on 18 November, and has set a deadline of 7 December for contractors to submit responses.
The broad scope of work on the Dhulaima early phase development project covers EPC, as well as all associated civil, mechanical, piping, electrical, fabrication, instrumentation, control, testing, and pre-commissioning commissioning, and de-commissioning activities of the following on-plot facilities:
- Gas injection compressor package: Complete gas injection compressor package with all auxiliary systems, associated piping, associated instrumentation for safeguarding and control, etc, as complete skid. All the necessary power, utilities as required for the compressor package and its driver shall be included as part of the scope, along with all associated systems, foundations, piping, electrical, instrumentation. Type of compressor and driver to be proposed by the bidders.
- Gas injection manifold package: Complete gas injection manifold including all tie-ins to existing facilities, pipe supports, control valves, and instrumentation.
PDO is the operator of the Block 6 hydrocarbons concession in Oman, which is the sultanate’s largest and most prolific concession. Situated onshore and covering an area of 75,119 square kilometres, Block 6 contains 202 oil fields and 43 gas fields.
The Omani government holds a 60% stake in PDO, with the other shareholders being UK-based Shell (34%), France’s TotalEnergies (4%) and Thai state-owned PTTEP (2%).
https://image.digitalinsightresearch.in/uploads/NewsArticle/15169037/main.jpg -
Top deals signed at Dubai Airshow 202527 November 2025
The Dubai Airshow 2025 drew to a close on 21 November, with deals exceeding $202bn, double the $101bn secured at the 18th edition in 2023.
This new milestone reinforces Dubai’s position as a global aviation hub and central force shaping the future of the aviation and space industries, according to a statement from the Government of Dubai Media Office.
The 19th edition of the event, held at Dubai World Central under the theme ‘The Future is Here’, also drew record attendance, welcoming 248,788 visitors, including industry leaders, government officials and aviation specialists from across the globe.
More than 1,500 exhibitors took part, with 440 participating for the first time, along with 490 military and civil delegations from 115 countries. The show also included 21 national pavilions, 98 chalets, an extra 8,000 square metres of display space, and a startup ecosystem with 120 startups and 50 investors.
One of the most globally diverse editions to date, this year’s airshow featured the usual mega-orders, but also a surprise fleet pivot and an emerging picture of the region’s biggest players taking control of their futures by influencing the development of tomorrow’s jets and securing their supply chains.
Anchor customer
UAE national carriers placed orders for 502 aircraft during the five-day event, with Emirates leading the charge. On the first day of the airshow, Emirates announced a $38bn order for 65 new Boeing 777-9 aircraft. The airline also ordered 130 GE9X engines from GE Aerospace, which power the new twin-engined planes.
The deal gives Boeing a boost after the 777-9’s debut was delayed to 2027 – but equally significantly, it provides strong backing for Boeing’s feasibility study to develop the 777-10, a larger variant of its 777X family, as Emirates pushes to replace its Airbus A380 fleet.
“Emirates has been open about the fact that we are keen for manufacturers to build larger capacity aircraft, which are more efficient to operate, especially with projected air traffic growth and increasing constraints at airports,” said Sheikh Ahmed Bin Saeed Al-Maktoum, chairman and chief executive of Emirates Airline and Group.
“We fully support Boeing’s feasibility study to develop the 777-10 and have options to convert our latest 777-9 order to the 777-10 or the 777-8.”
Several days later, Emirates also ordered eight more A350-900 aircraft, worth $3.4bn and powered by Rolls-Royce Trent XWB84 engines, while also urging Airbus to explore a larger version of its A350-1000 wide-body.
Emirates’ commitment to new aircraft at the Dubai Airshow 2025 is worth $41.4bn at list prices, and brings the airline’s total wide-body aircraft orders to 375, with deliveries scheduled through 2038.
It was also announced that Emirates would deploy Starlink Wi-Fi across its entire in-service fleet, beginning with Boeing 777 aircraft in November 2025 and completing the rollout by mid-2027.
Airbus pivot
Flydubai also signed a memorandum of understanding (MoU) with Boeing to purchase 75 Boeing 737 MAX aircraft valued at $13bn. In one of the show’s biggest strategic shifts, a further MoU was signed with Airbus for 150 A321neo aircraft, making the airline a new Airbus customer.
Sheikh Ahmed, also chairman and CEO of flydubai, said this addition would diversify the airline’s narrow-body fleet and “enable flydubai to play a key role in the success of Dubai World Central’s expansion plans, an airport we aim to become the largest airport in the world”.
“We look forward to establishing a strong and enduring partnership between flydubai and Airbus,” he said.
Etihad Airways confirmed an order for 32 new Airbus aircraft, including freighters, marking a significant expansion of its wide-body fleet, while Gulf Air, Bahrain’s national carrier, finalised a firm order for 15 787 Dreamliners with options for three more as the carrier looks to further develop its international network. The order adds three Boeing 787s to the airline’s commitment this July and brings Gulf Air’s order book to 17 of the versatile widebody jets.
Saudi Arabia's emerging airline, Riyadh Air, confirmed a purchase of 120 CFM LEAP-1A engines for its incoming A321neo fleet.
Taking control
In a clear sign that Gulf airlines are taking charge of their supply chains, Emirates and France's Safran Seats signed an MoU to bring a manufacturing and plane seat assembly factory to Dubai. The joint industrial cooperation, the first of its kind, will initially focus on Emirates’ business and economy class seats for cabin retrofit projects, with plans to expand into new aircraft in the future.
“This agreement with Safran marks a pivotal and strategic cooperation that establishes Dubai as an aerospace manufacturing hub,” commented Sheikh Ahmed. “We're bringing world-class seat production capabilities and supply chain to our doorstep, creating highly skilled jobs, and developing capabilities to support Emirates and produce seats for export to other carriers.”
Emirates is also securing its own engine maintenance capabilities, signing an MoU with Rolls Royce to conduct engine maintenance, repair and overhaul on its own A380 fleet at a new plant in Dubai from 2027.
Green airline fuel
Sustainability was a core priority at the airshow, with initiatives including the supply of sustainable aviation fuel (SAF) for participating aircraft, the use of electric and propane-powered ground support equipment in partnership with Jetex, and exhibition halls run entirely on renewable energy.
On the sidelines of the event, Emirates and Enoc Group signed a memorandum of understanding to explore and develop joint initiatives for the supply of SAF to Emirates at its Dubai hub.
Defence deals
Capping the exhibition were the 36 deals signed on behalf of the Ministry of Defence and Abu Dhabi Police by the UAE’s Tawazun council – the national authority mandated to enable, regulate and sustain the UAE’s defence and security industrial ecosystem. Valued at AED25.455bn, the deals included contracts for drones, rescue gear, aircraft parts and support.
https://image.digitalinsightresearch.in/uploads/NewsArticle/15167232/main.gif -
Prequalification begins for Riyadh King Salman Stadium27 November 2025
Register for MEED’s 14-day trial access
Saudi Arabia’s Sports Ministry has issued a notice inviting companies to prequalify for a contract to design and build the King Salman International Stadium in Riyadh.
The notice was issued on 26 November, with a prequalification deadline of 16 February.
The stadium will cover an area of about 660,000 square metres (sq m) and will have a seating capacity of 92,000.
The stadium will feature a 150-seat royal suite, 120 hospitality suites, 300 VIP seats and 2,200 dignitary seats.
The plan also includes several sports facilities covering more than 360,000 sq m, including two training fields and fan zones; a closed sports hall; an Olympic-sized swimming pool; an athletics track; and outdoor courts for volleyball, basketball and padel.
The new stadium will host the final of the 2034 Fifa World Cup and will serve as the Saudi national football team’s main headquarters.
US-based architectural firm Populous is the lead architect for the stadium.
Construction of the stadium is expected to be completed by 2029.
The stadium will be located next to King Abdulaziz Park.
Saudi Arabia stadium plans
In August last year, MEED reported that Saudi Arabia plans to build 11 new stadiums to host the Fifa World Cup in 2034.
Eight stadiums will be located in Riyadh, four in Jeddah and one each in Al-Khobar, Abha and Neom.
An additional 10 cities will host training bases. These are Al-Baha, Jazan, Taif, Medina, Alula, Umluj, Tabuk, Hail, Al-Ahsa and Buraidah.
There are expected to be 134 training sites across the kingdom, including 61 existing facilities and 73 new training venues.
The kingdom was officially selected to host the 2034 Fifa World Cup through an online convention of Fifa member associations at the Fifa Congress on 11 December 2024.
https://image.digitalinsightresearch.in/uploads/NewsArticle/15166460/main.jpg

