Warming erodes Kuwait’s power and water reserves

14 August 2023

More on Kuwait’s power and water sector: 

> IWPP: Firms respond to Kuwait independent utilities request
> POWERLocal firm wins 250MW Subiya package
> PRIVATISATIONKuwait thermal plant privatisation to go ahead


 

The temperature in Kuwait soared to 51 degrees Celsius on 1 August, sending its electricity load index up to 16,940MW. This breached its maximum expected load this year of 16,830MW by 0.7 per cent.

This year’s projected maximum load is already 4 per cent higher than the previous year's recorded maximum load. It leaves only roughly 8 per cent of reserve capacity against an available capacity understood to stand at 18,250MW.

Similarly, water consumption across the Gulf state on 2 August, when the temperature decreased to 50 degrees, exceeded production by 29 million gallons, prompting the state utility to access its strategic water reserve capacity to plug the shortfall.

The electricity consumption spike reportedly caused two feeders at the country’s main substation south of Surra in the capital to trip, which led to power outages in some parts of Zahra, a district in Kuwait’s Hawalli governorate.

Kuwait’s Electricity & Renewable Energy Ministry (MEWRE) assured the public that the maximum capacity available in the country’s electricity network during the current summer is 18,250MW, as earlier cited, and that it could safely provide up to 17,660MW.

Persistent delays

The following week MEWRE – through the Kuwait Authority for Partnership Projects (Kapp) – received prequalification applications for the contracts to develop Kuwait’s next two independent water and power producer (IWPP) projects.

The two schemes – Al-Zour North 2 & 3 and Al-Khiran 1 – will have a total combined power generation capacity of 4,500MW and a water desalination capacity of over 150 million imperial gallons a day (MIGD), which will go a long way to address Kuwait’s precarious electricity and water supply situation.

Ironically, these two schemes have been in the planning and early procurement stages since 2017 and have suffered significant delays in the intervening period.

It is the second time developers have submitted statements of qualification (SOQs) for the contracts over the preceding 11 months.

The delays have caused major frustration for some developers and contractors. One utility developer that submitted an SOQ in September last year told MEED they did not participate in the latest attempt to start the prequalification process for the IWPP schemes, without elaborating.

Others expect the country’s stakeholders to eventually approve and expedite the procurement process for the integrated power and desalination facilities.

“I’m not very optimistic, but we submitted an SOQ anyway,” another source tells MEED.

EPC projects motoring ahead

The ministry’s conventional power plant projects have been moving at a relatively faster pace. In June this year, the local company Heavy Engineering Industries & Shipbuilding (Heisco) won a contract for the phase 2 upgrade of the Subiya power plant complex in Kuwait.

Heisco saw off competition from two local companies, Alghanim International and Al-Zain United General Trading & Contracting, for the KD114.28m ($372m) contract.

The project aims to convert an existing 250MW simple-cycle plant into a combined-cycle gas-turbine plant.

In April, a consortium comprising Heisco and Japan’s Mitsubishi Power was also awarded a contract to retrofit the main thermal power generation plant at the power complex.

The contract is understood to be valued at KD90.9m. It entails the upgrade of eight steam turbines and electric generators at the Subiya power plant, which is expected to reach a capacity of 2,400MW once the project is complete.

The existing plant at the Subiya power complex was commissioned between 1998 and 2002. This implies that the steam turbines and generators in commercial operation for nearly 20 years require upgrades to continue operating and improve their performance.

Two steps forward

While the country has pledged to become carbon neutral by 2060, the state utility has yet to make any remarkable progress in procuring new renewable energy capacity.

The recent political deadlock has hampered the procurement of the next phases of the Shagaya Renewable Energy Programme (SREP), despite the award 12 months previously of the project’s transaction advisory contract to a team led by London-headquartered consultancy firm EY.

At the time, the advisory contract was understood to cover the Al-Dibdibah solar project, which will comprise SREP’s second phase, and a third phase expected to include a 720MW solar photovoltaic (PV) plant, a 1,150MW concentrated solar power (CSP) facility and a wind power farm.

Notably, two state-backed downstream operators – Kuwait National Petroleum Company and Kuwait Integrated Petroleum Industries Company (Kipic) – have launched a tender for a contract to undertake a pre-feasibility study identifying opportunities to use renewable energy in their operations.

Kuwait is also expected to make some progress on its first utility privatisation scheme, which forms part of the initiative to strengthen private sector participation in the sector.

In December last year, it was revealed that UK-headquartered Deloitte had submitted a low bid of KD1.2m ($3.9m) for the transaction advisory contract in line with the planned privatisation of the $1.26bn North Shuaiba power and water plant in Kuwait.

GCC grid

While working to boost its electricity reserves and make its electricity systems greener, Kuwait stands to benefit from the ongoing upgrade of the GCC electricity grid, through which other GCC states, such as the UAE, may decide to transmit excess clean energy.

The Al-Fadhili high-voltage direct current (HVDC) converter station upgrade in Saudi Arabia is expected to enable the exchange of 1,800MW of electricity between the six states once complete.

In October last year, the GCC Interconnection Authority (GCCIA) awarded India-based KEC International a contract for an overhead transmission line project linking the substations in Wafra in Kuwait and Fadhili in Saudi Arabia.

The estimated $120m project extends an existing double-circuit 400kV line from Al-Zour in Kuwait to Ghunan in Saudi Arabia. The line has an intermediate interconnection at Fadhili, with associated substations completed in 2009 as part of the first phase of the GCCIA network. The new project is expected to complete in 2025.


This month’s special report on Kuwait also includes: 

> ECONOMYStakeholders hope Kuwait can execute spending plans
> ENERGYKuwait’s $300bn energy target is a big test
> BANKINGKuwaiti banks enter bounce-back mode
> INTERVIEWKuwait’s Gulf Centre United sets course for expansion

https://image.digitalinsightresearch.in/uploads/NewsArticle/11069881/main.gif
Jennifer Aguinaldo
Related Articles
  • Bahrain extends deadline for Hawar Island water station

    25 November 2025

    Bahrain’s Electricity & Water Authority (Ewa) has extended the bid submission deadline for the main contract to build a new water distribution station on Hawar Island.

    The deadline, initially set for 23 November, has been moved to 7 December. 

    The $15m project covers the construction of two steel ground storage tanks with a capacity of one million gallons each, pumping stations, motors, pipelines and associated facilities.

    The scheme forms a key part of Bahrain’s wider plans to develop Hawar Island, which currently has limited utility infrastructure and relies on water transported from the mainland.

    The government is advancing tourism-led investment on the island, including eco-resorts and hospitality developments that require reliable potable water supplies.

    The tender is linked to Ewa’s ongoing procurement for a new seawater reverse osmosis (SWRO) desalination plant on Hawar.

    The engineering, procurement and construction contract for the SWRO facility, designed to produce one million imperial gallons a day, is currently out to tender, with bids due on 30 November.

    According to Ewa, the desalination plant will connect with two related contracts.

    One of these covers the construction of the new water distribution station, while the second covers offshore seawater intake and outfall systems.

    The main desalination contractor will be required to ensure its design and construction align with these works so that all three components function together as one integrated system.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/15149229/main.jpg
    Mark Dowdall
  • November 2025: Data drives regional projects

    25 November 2025

    Click here to download the PDF

    Includes: Top 10 global contractors | Brent Spot Price | Construction output

     MEED's 2025 EPC contractor ranking


    MEED’s December 2025 report on Bahrain includes:

    > COMMENT: Manama pursues reform amid strain
    > GVT & ECONOMY: Bahrain’s cautious economic evolution

    > BANKING: Mergers loom over Bahrain’s banking system
    > OIL & GAS: Bahrain remains in pursuit of hydrocarbon resources
    > POWER & WATER: Bahrain advances utility reform
    > CONSTRUCTION: Bahrain construction faces major slowdown
    > TRANSPORT: Air Asia aviation deal boosts connectivity

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/15149339/main.gif
    MEED Editorial
  • Bahrain pursues reform amid strain

    25 November 2025

    Commentary
    John Bambridge
    Analysis editor

    Cautious optimism defines Bahrain’s current economic moment as the country presses ahead with a broad agenda of diversification, reform and targeted investment. Yet the more assertively Manama moves to reshape its future, the more the tension between its ambition and its fiscal constraints becomes evident as the defining feature of its policymaking.

    Bahrain’s projects sector, which has now been shrinking for the past seven years, is emblematic of the country’s constricted spending. This year, contract awards have fallen to their lowest value in a decade. This signals a decisive shift to a more disciplined investment strategy aligned with fiscal realities and a more selective approach to forward-looking capital spending. 

    The diminished projects market is in turn a challenge for the financial sector, which now faces a receding pool of project financing and other contracting loans. This is giving further impetus to the potential consolidation of local lenders in the overbanked market, which is also beset by thinning margins, rising compliance costs and pressure to scale amid financial system modernisation. While it could create short-term pain, consolidation should boost the financial health of legacy lenders and provide stability in a sector increasingly being defined by new digital banking models and innovation.

    Yet even as some sectors change, Bahrain’s government remains deeply reliant on hydrocarbons, which continues to drive exploration, including in the technically complex Khaleej Al-Bahrain basin. These activities reflect the practical need to maintain oil revenues in the medium term and, should additional recoverable reserves be discovered, a potent source of optimism.

    Manana is meanwhile looking to overhaul the utilities sector by creating a dedicated regulator and new national operator. The reforms should make space for greater private participation, drawing more capital into power and water projects while improving efficiency and reducing state expenditure in an aspirationally positive step towards greater long-term sustainability.

    Even as fiscal concerns narrow Manama’s policy options, it continues to secure strategic wins. A new aviation agreement with Air Asia establishes Bahrain as a regional hub for one of Asia’s largest low-cost carriers. This move opens new connectivity corridors and, alongside the renewal of direct Gulf Air routes to the US, reinforces Bahrain’s position as a gateway between regions, promising benefits for tourism, logistics and services.

    Overall, Bahrain’s economic trajectory remains delicately balanced – marked by reform-driven progress yet tempered by fiscal constraint. But in threading this needle, Manama shows that cautious optimism can still be a powerful catalyst for change.

     


    MEED’s December 2025 report on Bahrain includes:

    > GVT & ECONOMY: Bahrain’s cautious economic evolution
    > BANKING: Mergers loom over Bahrain’s banking system
    > OIL & GAS: Bahrain remains in pursuit of hydrocarbon resources
    > POWER & WATER: Bahrain advances utility reform
    > CONSTRUCTION: Bahrain construction faces major slowdown
    > AVIATION: Bahrain signs game-changer aviation deal with Air Asia

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/15109785/main.gif
    John Bambridge
  • Chinese firms expand oil and gas presence

    25 November 2025

     

    > This package also includes: Larsen & Toubro climbs EPC contractor ranking


    Chinese contractors have been present in the oil and gas projects market in the Middle East and North Africa (Mena) region since the turn of this century, but largely remained on the fringes. In a hydrocarbons market that has traditionally been dominated by European and American contractors, and those from Japan and South Korea, Chinese firms have become a rising force, especially since the start of the decade.

    Economic competitiveness in bid battles, significant improvement in engineering and technological capabilities and commitment to execution schedules have been primary factors behind the success of Chinese contractors in the regional oil and gas projects market since 2020.

    Competitive edge

    Traditionally, Chinese engineering, procurement and construction (EPC) contractors have enjoyed a lower cost base than their international competitors. This comes from lower manpower costs, access to cheaper materials and equipment, and financial support from state banks. 

    In addition, Chinese firms have typically had a different attitude to risk than many other contractors. Instead of seeking to turn a profit on specific projects, Chinese firms have entered markets cautiously and, as their knowledge of the local market grew, built a commanding long-term position.

    More recently, the edge that Chinese contractors enjoy has come from the technical experience they have gained from delivering large-scale, complex projects in their domestic market. While in the past Chinese contractors were only considered capable of delivering basic construction work, they now have some of the best project references in the world.

    Regional leaders

    Chinese EPC contractors have strengthened their performance in the Mena oil and gas projects market, particularly since the end of the Covid-19 pandemic. Since 2023, the combined value of projects won by Chinese firms has consistently remained well over $13bn, with them winning key contracts on major projects.

    The largest EPC scheme under execution by a Chinese contractor in the region is on a project to maintain and increase the oil production potential of the Bul Hanine offshore oil field development in Qatar. China Offshore Oil Engineering Company won contracts worth $4bn for the two main EPC packages of the project in the third quarter of 2025.

    Also this year, Abu Dhabi’s Taziz awarded the main EPC contract to build a complex of specialty chemicals plants in the Taziz Industrial Chemicals Zone at Ruwais Industrial City to China National Chemical Engineering & Construction Corporation Seven (CC7). 

    The EPC contract is valued at $1.99bn, with work expected to be completed by Q4 2028. The chemicals cluster, known as Project Salt, will produce 1.9 million tonnes a year of marketable polyvinyl chloride (PVC), ethylene dichloride (EDC), vinyl chloride monomer (VCM) and caustic soda.

    Chinese contractors have also enjoyed success in Saudi Arabia, with Aramco having awarded several key EPC contracts to Chinese firms since 2023. China Petroleum Engineering & Construction Company, Sepco and Sinopec Petroleum Services are executing EPC works on four out of the 17 packages of the third expansion phase of Aramco’s Master Gas System project.

    Sinopec Group has played a significant role in Aramco’s Jafurah unconventional gas development in Saudi Arabia. In a consortium with Spanish contractor Tecnicas Reunidas, in 2024 Sinopec won packages one and two of the Riyas natural gas liquids scheme, part of the second Jafurah unconventional gas expansion phase. The combined value of the two EPC contracts was $3.2bn.

    Just weeks after securing these EPC contracts, the consortium also won the contract to deliver the entire scope of work on the scheme’s third expansion phase, valued at $2.24bn.

    In Iraq, China Petroleum Engineering (CPE) won a major contract in August to carry out EPC works on a package covering a major seawater transmission pipeline to be built in Basra as part of the larger Common Seawater Supply Project, which is one of four main components of the estimated $10bn Gas Growth Integrated Project masterplan.

    Work on the $2.52bn contract will be carried out by CPE’s engineering arm, China Petroleum Pipeline Engineering.

    China has built up extensive resources, from skilled personnel to technical know-how. As the domestic market shows signs of slowing, these resources are being deployed internationally, supporting the growing presence of Chinese contractors in the Mena region.

    MEED's 2025 EPC contractor ranking

    https://image.digitalinsightresearch.in/uploads/NewsArticle/15149182/main.gif
    Indrajit Sen
  • Ineco appointed for Spain-Morocco tunnel study

    25 November 2025

    Spanish engineering firm Ineco has been commissioned to conduct an exploratory tunnel study to validate the feasibility of the railway connection linking Spain and Morocco.

    According to reports in Spanish media, the $1m contract will establish a detailed technical roadmap for the project.

    Ineco’s scope of work includes the preliminary design of the exploratory tunnel, revisions to previous studies, and a comprehensive update of the route, geology, geotechnical conditions, security systems, terminals and associated installations.

    Ineco will validate the critical geological conditions of the Strait, particularly in the areas where the project’s greatest risks are located.

    The study is expected to be completed by August next year.

    The latest development comes after German company Herrenknecht completed its study in October. Herrenknecht said it found the project feasible to undertake due to the availability of the technology needed to execute it.

    The media reports added that clients will further study the project and make a final decision in 2027 regarding tendering.

    Recent developments

    MEED reported in August that Ineco had secured an estimated €350,000 ($409,000) contract to carry out a financial feasibility study for the proposed infrastructure.

    UK-based Vodafone also won a contract to provide advanced telecommunications support to teams working on the project.

    These developments followed the appointment of Herrenknecht in January for a €296,400 ($307,483) contract to conduct a drilling feasibility study.

    The Spanish government revived the Morocco-Spain undersea rail link in June last year, after allocating about $2.5m for a renewed design study.

    Project background

    The project, originally launched in 2003, was put on hold following the 2008 financial crisis. It has undergone several rounds of feasibility studies, but remains in the planning phase after nearly two decades of funding-related delays.

    The proposed design includes a double-track railway and a service tunnel extending 38.5 kilometres (km) between Tarifa in Spain and Tangier in Morocco. Of this, 28km will run beneath the Mediterranean Sea at a maximum depth of 475 metres.

    Each single-track tunnel will have an inner diameter of 7.9 metres, while the service gallery will be 6 metres in diameter.

    The project is being jointly developed by Morocco’s National Society for Strait of Gibraltar Studies and Spain’s Sociedad Espanola de Estudios para la Comunicacion Fija a Traves del Estrecho de Gibraltar.

    In 2006, Swiss engineering firm Lombardi Engineering was selected to design the tunnel. Preliminary studies were completed two years later.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/15148660/main.jpg
    Yasir Iqbal