Warming erodes Kuwait’s power and water reserves

14 August 2023

More on Kuwait’s power and water sector: 

> IWPP: Firms respond to Kuwait independent utilities request
> POWERLocal firm wins 250MW Subiya package
> PRIVATISATIONKuwait thermal plant privatisation to go ahead


 

The temperature in Kuwait soared to 51 degrees Celsius on 1 August, sending its electricity load index up to 16,940MW. This breached its maximum expected load this year of 16,830MW by 0.7 per cent.

This year’s projected maximum load is already 4 per cent higher than the previous year's recorded maximum load. It leaves only roughly 8 per cent of reserve capacity against an available capacity understood to stand at 18,250MW.

Similarly, water consumption across the Gulf state on 2 August, when the temperature decreased to 50 degrees, exceeded production by 29 million gallons, prompting the state utility to access its strategic water reserve capacity to plug the shortfall.

The electricity consumption spike reportedly caused two feeders at the country’s main substation south of Surra in the capital to trip, which led to power outages in some parts of Zahra, a district in Kuwait’s Hawalli governorate.

Kuwait’s Electricity & Renewable Energy Ministry (MEWRE) assured the public that the maximum capacity available in the country’s electricity network during the current summer is 18,250MW, as earlier cited, and that it could safely provide up to 17,660MW.

Persistent delays

The following week MEWRE – through the Kuwait Authority for Partnership Projects (Kapp) – received prequalification applications for the contracts to develop Kuwait’s next two independent water and power producer (IWPP) projects.

The two schemes – Al-Zour North 2 & 3 and Al-Khiran 1 – will have a total combined power generation capacity of 4,500MW and a water desalination capacity of over 150 million imperial gallons a day (MIGD), which will go a long way to address Kuwait’s precarious electricity and water supply situation.

Ironically, these two schemes have been in the planning and early procurement stages since 2017 and have suffered significant delays in the intervening period.

It is the second time developers have submitted statements of qualification (SOQs) for the contracts over the preceding 11 months.

The delays have caused major frustration for some developers and contractors. One utility developer that submitted an SOQ in September last year told MEED they did not participate in the latest attempt to start the prequalification process for the IWPP schemes, without elaborating.

Others expect the country’s stakeholders to eventually approve and expedite the procurement process for the integrated power and desalination facilities.

“I’m not very optimistic, but we submitted an SOQ anyway,” another source tells MEED.

EPC projects motoring ahead

The ministry’s conventional power plant projects have been moving at a relatively faster pace. In June this year, the local company Heavy Engineering Industries & Shipbuilding (Heisco) won a contract for the phase 2 upgrade of the Subiya power plant complex in Kuwait.

Heisco saw off competition from two local companies, Alghanim International and Al-Zain United General Trading & Contracting, for the KD114.28m ($372m) contract.

The project aims to convert an existing 250MW simple-cycle plant into a combined-cycle gas-turbine plant.

In April, a consortium comprising Heisco and Japan’s Mitsubishi Power was also awarded a contract to retrofit the main thermal power generation plant at the power complex.

The contract is understood to be valued at KD90.9m. It entails the upgrade of eight steam turbines and electric generators at the Subiya power plant, which is expected to reach a capacity of 2,400MW once the project is complete.

The existing plant at the Subiya power complex was commissioned between 1998 and 2002. This implies that the steam turbines and generators in commercial operation for nearly 20 years require upgrades to continue operating and improve their performance.

Two steps forward

While the country has pledged to become carbon neutral by 2060, the state utility has yet to make any remarkable progress in procuring new renewable energy capacity.

The recent political deadlock has hampered the procurement of the next phases of the Shagaya Renewable Energy Programme (SREP), despite the award 12 months previously of the project’s transaction advisory contract to a team led by London-headquartered consultancy firm EY.

At the time, the advisory contract was understood to cover the Al-Dibdibah solar project, which will comprise SREP’s second phase, and a third phase expected to include a 720MW solar photovoltaic (PV) plant, a 1,150MW concentrated solar power (CSP) facility and a wind power farm.

Notably, two state-backed downstream operators – Kuwait National Petroleum Company and Kuwait Integrated Petroleum Industries Company (Kipic) – have launched a tender for a contract to undertake a pre-feasibility study identifying opportunities to use renewable energy in their operations.

Kuwait is also expected to make some progress on its first utility privatisation scheme, which forms part of the initiative to strengthen private sector participation in the sector.

In December last year, it was revealed that UK-headquartered Deloitte had submitted a low bid of KD1.2m ($3.9m) for the transaction advisory contract in line with the planned privatisation of the $1.26bn North Shuaiba power and water plant in Kuwait.

GCC grid

While working to boost its electricity reserves and make its electricity systems greener, Kuwait stands to benefit from the ongoing upgrade of the GCC electricity grid, through which other GCC states, such as the UAE, may decide to transmit excess clean energy.

The Al-Fadhili high-voltage direct current (HVDC) converter station upgrade in Saudi Arabia is expected to enable the exchange of 1,800MW of electricity between the six states once complete.

In October last year, the GCC Interconnection Authority (GCCIA) awarded India-based KEC International a contract for an overhead transmission line project linking the substations in Wafra in Kuwait and Fadhili in Saudi Arabia.

The estimated $120m project extends an existing double-circuit 400kV line from Al-Zour in Kuwait to Ghunan in Saudi Arabia. The line has an intermediate interconnection at Fadhili, with associated substations completed in 2009 as part of the first phase of the GCCIA network. The new project is expected to complete in 2025.


This month’s special report on Kuwait also includes: 

> ECONOMYStakeholders hope Kuwait can execute spending plans
> ENERGYKuwait’s $300bn energy target is a big test
> BANKINGKuwaiti banks enter bounce-back mode
> INTERVIEWKuwait’s Gulf Centre United sets course for expansion

https://image.digitalinsightresearch.in/uploads/NewsArticle/11069881/main.gif
Jennifer Aguinaldo
Related Articles
  • Kuwait receives bids for Al-Khairan phase one IWPP

    2 June 2026

     

    Two developer consortiums have submitted bids for the first phase of Kuwait’s Al-Khairan independent water and power producer (IWPP) project, according to a source.

    Bids were received by the Kuwait Authority for Partnership Projects (Kapp) on 1 June.

    The facility will have a capacity of 1,800MW and 150,000 cubic metres a day of desalinated water. It will be located in Al-Khairan, adjacent to the Al-Zour South thermal plant. 

    The bidders include:

    • Abu Dhabi National Energy Company (Taqa) / A H Al-Sagar & Brothers (Saudi Arabia) 
    • Acwa (Saudi Arabia) / Gulf Investment Corporation (Kuwait)

    The Al-Khairan IWPP is being procured by Kapp in partnership with the Ministry of Electricity, Water & Renewable Energy (MEWRE).

    The main contract was tendered last September. Three consortiums and two individual companies were previously prequalified to participate in the tender.

    Ernst & Young, BNP Paribas, AtkinsRealis and Addleshaw Goddard are financial advisers on the project. Chadbourne & Parke is acting as legal adviser.

    The winning bidder will sign a set of public-private partnership agreements covering financing, design, construction, operation and transfer of the project. The energy conversion and water-purchase agreement is expected to cover a 25-year supply period.

    Future phases

    The Al-Khairan IWPP project is expected to run on low-sulphur fuel oil as the primary fuel and to accommodate crude oil, gas oil and natural gas as backup fuels. Future phases will further expand capacity.

    It is understood that the estimated $750m second phase of the Al-Khairan IWPP project will add a further 1,800MW of generation capacity through a combined-cycle gas-fired power plant.

    The project, first mooted over a decade ago, remains in the early development stages, with no plans currently to advance to procurement in 2026, a source said.

    According to the source, the immediate focus is on advancing plans for the 3,600MW Nuwaiseeb power and water desalination IWPP project.

    The Nuwaiseeb IWPP plant will have a desalination capacity of 75 million imperial gallons a day.

    Kapp plans to release a transaction advisory tender for the project by the end of the year.


    > Be recognised among the best in the industry at the MEED Projects Awards 2026 …

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17072685/main.jpg
    Mark Dowdall
  • Doosan confirms Saudi Jafurah 2 cogen contract

    2 June 2026

    South Korea’s Doosan Enerbility has confirmed it has signed an engineering, procurement and construction (EPC) contract worth about $556m for the second phase of the Jafurah combined heat and power (CHP) plant in Saudi Arabia.

    The project is being developed by Korea Electric Power Corporation (Kepco) in partnership with Saudi Aramco.

    Doosan said the contract covers design, equipment supply, installation, construction and commissioning of the facility.

    The Jafurah CHP phase 2 project will be built near the Jafurah gas field, about 400 kilometres east of Riyadh. Once operational, it will generate 330MW of electricity and produce 465 tonnes of steam an hour for the nearby gas field.

    According to the firm, the project’s main steam turbine will be supplied by Doosan Skoda Power, a subsidiary of Doosan Enerbility.

    WSP is acting as the project management consultant for the project, which is scheduled for completion in 2029.

    The Jafurah gas development is part of Aramco’s $3.2bn unconventional resources programme, which aims to develop shale gas in three areas. Jafurah lies southeast of Ghawar, the world’s largest conventional oil field.

    The programme is part of Riyadh’s plans under Vision 20230 to ensure the kingdom remains self-sufficient in gas supply amid rising demand from the residential and industrial power sectors.

    Jafurah phase one

    In February 2025, MEED exclusively reported that talks were under way to expand the capacity of the $500m Jafurah cogeneration independent steam and power plant (ISPP).

    Construction works were completed on the facility last November.

    At the time of its procurement, the plant’s first phase was to have a power capacity of 270-320MW, and a low-pressure (LP) steam demand of 77-166 thousand pounds an hour (klb/hr) and high-pressure (HP) steam demand of 29-126 klb/hour by 2023.

    The LP and HP steam demand will increase to 283-373 klb/hr and 66-321 klb/hr by 2027, respectively.

    The oil giant issued the letter of award to Kepco for the contract to develop the Jafurah ISPP scheme in July 2022.

    Kepco subsequently awarded South Korea’s Doosan Heavy Industries & Construction the project’s EPC contract.

    US/India-based Synergy Consulting provided financial advisory services to Kepco on its bid.

    Sumitomo Mitsui Banking Corporation (SMBC) served as the client’s financial adviser for the project. Germany’s Fichtner Consulting Engineers is technical consultant, while the UK’s Wood Group is project management consultant.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17072199/main.jpg
    Mark Dowdall
  • Al-Mabanee submits lowest bids for Kuwait infrastructure

    2 June 2026

    Kuwait’s Public Authority for Housing Welfare (PAHW) has opened commercial bids for two major infrastructure and public buildings packages at South Al-Mutlaa Residential City.

    Local firm Al-Mabanee United Company has emerged as the lowest bidder for both contracts, submitting combined offers worth KD44m. Both packages entail the construction, completion and maintenance of services, infrastructure works and public buildings for different district centres within the city.

    The first contract covers the infrastructure and public buildings for the N3 District Centre. PAHW received proposals from eight bidders, with Al-Mabanee United Company submitting the lowest price at KD20.9m. The second-lowest offer was submitted by The Contractor General Trading & Contracting Company at KD22.4m, followed by Golden Engineering Group for General Trading & Contracting at KD22.7m, though Golden Engineering Group was flagged for not providing a bid bond.

    Al-Khonaini General Trading & Contracting Company, operating as Inshat Al-Khonaini, ranked fourth with a bid of KD22.7m, followed closely by Kuwait Industrial Centre Company at KD22.8m. Combined Group Contracting Company submitted a bid of KD23.8m, Al-Dar Engineering & Construction Company bid KD25.7m, and China’s Sichuan Road & Bridge Group Corporation submitted the highest active proposal at KD29m. 

    The second contract is for identical infrastructure and public building works at the N1 District Centre. Al-Mabanee United Company submitted the lowest bid of KD22.8m. Its closest competitor was The Contractor General Trading & Contracting Company, which submitted an offer of KD23.9m.

    Al-Khonaini General Trading & Contracting Company came in third with a bid of KD24.2m, followed by Kuwait Industrial Centre Company at KD24.4m and Golden Engineering Group for General Trading & Contracting at KD24.4m. Combined Group Contracting Company placed a bid of KD26m, Al-Dar Engineering & Construction Company bid KD26.5m, and United Construction Company, known as Al-Inshat Al-Muttahida, submitted an offer of KD 30.9m. Al-Ghanim International General Trading & Contracting filed the highest bid at KD344m and was also noted for lacking a bid bond.

    South Mutlaa Residential City is a large-scale planned development designed to accommodate around 400,000 residents in a modern, fully serviced urban environment. Once completed, it will offer contemporary housing alongside extensive logistical services and a wide range of public and commercial areas, including hospitals, schools and other social services.

    The project also includes major infrastructure works such as approximately 150 kilometres of roads and related structures, lighting and other public works, as well as integrated systems for water distribution, rainwater collection and sewage. In addition, it will provide the civil infrastructure needed for electricity distribution, telecommunications networks and traffic control to support a well-connected, functional city.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17071938/main.gif
    Colin Foreman
  • Local developer secures finance for three Riyadh projects

    2 June 2026

    Qimam Noshoz for Real Estate Development Company, a subsidiary of Saudi Arabia’s Banan Real Estate Company, has signed a sharia-compliant credit facility agreement worth SR84m ($22.4m) with Riyad Bank to fund three commercial, hospitality and sports developments in the kingdom.

    The financing agreement is split into two distinct tranches to align with the projects’ development timelines. The first tranche consists of SR49m with a maturity duration of seven years, while the remaining SR35m has been secured for an eight-year term.

    Qimam Noshoz will utilise the capital to fund construction works for the Al-Rahmaniyah Gem and Al-Wadi District Gem projects. Both of these projects are already leased to the fitness operator Armah Sports Company. The other project is an independent hotel located within the Al-Wadi District.

    The Al-Wadi development is designed as an integrated commercial complex spanning approximately 7,818.5 square metres of land, with a built-up area of about 975 square metres. It includes a men’s gym, a women’s gym and a hotel building.

    The Al-Rahmaniyah project is an integrated commercial development combining fitness facilities with retail. The asset features men’s and women’s gyms operating alongside an independent commercial zone.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17071628/main.jpg
    Colin Foreman
  • SLB wins $385m contract for Kuwait oil research centre

    2 June 2026

    Schlumberger Oilfield Eastern, a unit of the US-headquartered oilfield services company SLB, has been awarded a KD118m ($385m) contract to develop an oil and gas research centre in Kuwait.

    The contract was awarded by the state-owned upstream operator Kuwait Oil Company (KOC), according to a report by Kuwait’s Al-Rai newspaper.

    The Ahmadi Innovation Valley (AIV) project is planned as an advanced research and innovation hub equipped with specialised facilities and technical teams focused on applied research for Kuwait’s oil and gas sector.

    The contract was awarded after the Higher Purchase Committee (HPC) of Kuwait’s national oil and gas company Kuwait Petroleum Corporation (KPC) determined the bid to be compliant with the project’s technical and commercial requirements.

    In February 2025, KOC signed memorandums of understanding (MoUs) with five international oilfield service companies to support the development of the AIV initiative.

    These companies were:

    • SLB (US)
    • Baker Hughes (US)
    • Weatherford (US)
    • Halliburton (US)
    • National Energy Services Reunited (US)

    Under the preliminary agreements, each of the five companies agreed to establish a world-class research and development centre at the project site, focused on helping KOC meet challenges in the upstream sector.

    KOC’s CEO Ahmad Jaber Al-Eidan had said in February 2025 that the project will enable Kuwait to keep pace with global transformations while investing in advanced technologies to ensure the sector’s sustainability and achieve operational excellence.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17063475/main.gif
    Wil Crisp