Warming erodes Kuwait’s power and water reserves
14 August 2023
More on Kuwait’s power and water sector:
> IWPP: Firms respond to Kuwait independent utilities request
> POWER: Local firm wins 250MW Subiya package
> PRIVATISATION: Kuwait thermal plant privatisation to go ahead

The temperature in Kuwait soared to 51 degrees Celsius on 1 August, sending its electricity load index up to 16,940MW. This breached its maximum expected load this year of 16,830MW by 0.7 per cent.
This year’s projected maximum load is already 4 per cent higher than the previous year's recorded maximum load. It leaves only roughly 8 per cent of reserve capacity against an available capacity understood to stand at 18,250MW.
Similarly, water consumption across the Gulf state on 2 August, when the temperature decreased to 50 degrees, exceeded production by 29 million gallons, prompting the state utility to access its strategic water reserve capacity to plug the shortfall.
The electricity consumption spike reportedly caused two feeders at the country’s main substation south of Surra in the capital to trip, which led to power outages in some parts of Zahra, a district in Kuwait’s Hawalli governorate.
Kuwait’s Electricity & Renewable Energy Ministry (MEWRE) assured the public that the maximum capacity available in the country’s electricity network during the current summer is 18,250MW, as earlier cited, and that it could safely provide up to 17,660MW.
Persistent delays
The following week MEWRE – through the Kuwait Authority for Partnership Projects (Kapp) – received prequalification applications for the contracts to develop Kuwait’s next two independent water and power producer (IWPP) projects.
The two schemes – Al-Zour North 2 & 3 and Al-Khiran 1 – will have a total combined power generation capacity of 4,500MW and a water desalination capacity of over 150 million imperial gallons a day (MIGD), which will go a long way to address Kuwait’s precarious electricity and water supply situation.
Ironically, these two schemes have been in the planning and early procurement stages since 2017 and have suffered significant delays in the intervening period.
It is the second time developers have submitted statements of qualification (SOQs) for the contracts over the preceding 11 months.
The delays have caused major frustration for some developers and contractors. One utility developer that submitted an SOQ in September last year told MEED they did not participate in the latest attempt to start the prequalification process for the IWPP schemes, without elaborating.
Others expect the country’s stakeholders to eventually approve and expedite the procurement process for the integrated power and desalination facilities.
“I’m not very optimistic, but we submitted an SOQ anyway,” another source tells MEED.
EPC projects motoring ahead
The ministry’s conventional power plant projects have been moving at a relatively faster pace. In June this year, the local company Heavy Engineering Industries & Shipbuilding (Heisco) won a contract for the phase 2 upgrade of the Subiya power plant complex in Kuwait.
Heisco saw off competition from two local companies, Alghanim International and Al-Zain United General Trading & Contracting, for the KD114.28m ($372m) contract.
The project aims to convert an existing 250MW simple-cycle plant into a combined-cycle gas-turbine plant.
In April, a consortium comprising Heisco and Japan’s Mitsubishi Power was also awarded a contract to retrofit the main thermal power generation plant at the power complex.
The contract is understood to be valued at KD90.9m. It entails the upgrade of eight steam turbines and electric generators at the Subiya power plant, which is expected to reach a capacity of 2,400MW once the project is complete.
The existing plant at the Subiya power complex was commissioned between 1998 and 2002. This implies that the steam turbines and generators in commercial operation for nearly 20 years require upgrades to continue operating and improve their performance.
Two steps forward
While the country has pledged to become carbon neutral by 2060, the state utility has yet to make any remarkable progress in procuring new renewable energy capacity.
The recent political deadlock has hampered the procurement of the next phases of the Shagaya Renewable Energy Programme (SREP), despite the award 12 months previously of the project’s transaction advisory contract to a team led by London-headquartered consultancy firm EY.
At the time, the advisory contract was understood to cover the Al-Dibdibah solar project, which will comprise SREP’s second phase, and a third phase expected to include a 720MW solar photovoltaic (PV) plant, a 1,150MW concentrated solar power (CSP) facility and a wind power farm.
Notably, two state-backed downstream operators – Kuwait National Petroleum Company and Kuwait Integrated Petroleum Industries Company (Kipic) – have launched a tender for a contract to undertake a pre-feasibility study identifying opportunities to use renewable energy in their operations.
Kuwait is also expected to make some progress on its first utility privatisation scheme, which forms part of the initiative to strengthen private sector participation in the sector.
In December last year, it was revealed that UK-headquartered Deloitte had submitted a low bid of KD1.2m ($3.9m) for the transaction advisory contract in line with the planned privatisation of the $1.26bn North Shuaiba power and water plant in Kuwait.
GCC grid
While working to boost its electricity reserves and make its electricity systems greener, Kuwait stands to benefit from the ongoing upgrade of the GCC electricity grid, through which other GCC states, such as the UAE, may decide to transmit excess clean energy.
The Al-Fadhili high-voltage direct current (HVDC) converter station upgrade in Saudi Arabia is expected to enable the exchange of 1,800MW of electricity between the six states once complete.
In October last year, the GCC Interconnection Authority (GCCIA) awarded India-based KEC International a contract for an overhead transmission line project linking the substations in Wafra in Kuwait and Fadhili in Saudi Arabia.
The estimated $120m project extends an existing double-circuit 400kV line from Al-Zour in Kuwait to Ghunan in Saudi Arabia. The line has an intermediate interconnection at Fadhili, with associated substations completed in 2009 as part of the first phase of the GCCIA network. The new project is expected to complete in 2025.
This month’s special report on Kuwait also includes:
> ECONOMY: Stakeholders hope Kuwait can execute spending plans
> ENERGY: Kuwait’s $300bn energy target is a big test
> BANKING: Kuwaiti banks enter bounce-back mode
> INTERVIEW: Kuwait’s Gulf Centre United sets course for expansion
Exclusive from Meed
-
Iraq sets up commission for $5bn pipeline project30 April 2026
-
Construction begins on Dubai Healthcare City projects30 April 2026
-
Bahrain extends bid deadline for 1.2GW Sitra IWPP30 April 2026
-
Bidders get more time for Jebel Ali sewage EPC contract29 April 2026
-
UAE’s departure from Opec marks a tectonic shift29 April 2026
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Iraq sets up commission for $5bn pipeline project30 April 2026
Iraq is setting up a high-level commission to oversee the development of the planned $5bn Basra-Haditha crude oil pipeline project.
The decision was made at a meeting held on 26 April, attended by Prime Minister Mohammed Shia Al-Sudani and the Minister of Petroleum Hayyan Abdul Ghani Al-Sawad, as well as other officials and consultants.
The commission will be chaired by the undersecretary of the Oil Ministry and include advisers to the prime minister, along with director-generals from the Oil Ministry and the Industry & Minerals Ministry.
Al-Sudani said the pipeline project will increase flexibility in transporting crude oil to the Turkish port of Ceyhan, as well as the Syrian port of Baniyas and Jordan’s port of Aqaba.
The pipeline is also expected to strengthen supply to refineries in central and northern Iraq and support higher domestic refining output.
The meeting also approved allocating $1.5bn to the project this year, with funding provided through the Iraq-China oil-for-infrastructure mechanism, according to a statement issued by the Petroleum Ministry.
Earlier this month, Iraq’s Council of Ministers approved amendments allowing the Oil Ministry to directly invite specialised companies to bid for the 685-kilometre pipeline.
The pipeline is expected to have a capacity of up to 2.25 million barrels a day.
https://image.digitalinsightresearch.in/uploads/NewsArticle/16621546/main.jpg -
Construction begins on Dubai Healthcare City projects30 April 2026
Dubai Healthcare City Authority (DHCA) has begun construction on Pixel DHCC and Ibn Sina+, two flagship developments in Dubai Healthcare City.
Local contractor International Foundation Group has been appointed to carry out the enabling works.
The two projects form part of Phase 1 of DHCA’s AED1.3bn ($354m) development programme and are scheduled for completion in November 2027.
Pixel DHCC, designed by Hong Kong-based P&T Architects and Engineers, is planned as Dubai Healthcare City’s first LEED Platinum-certified office building. The nine-storey commercial development will cover 13,000 sq m.
Ibn Sina+, designed by Dubai’s Design and Architecture Bureau, will be a five-storey medical complex spanning 5,800 sq m.
— Dubai Media Office (@DXBMediaOffice) April 27, 2026
https://image.digitalinsightresearch.in/uploads/NewsArticle/16611156/main.jpg -
Bahrain extends bid deadline for 1.2GW Sitra IWPP30 April 2026

Bahrain’s Electricity & Water Authority (EWA) has extended the developer bidding deadline for the Sitra independent water and power plant (IWPP).
The new deadline is 17 May.
The Sitra IWPP is a combined-cycle gas turbine plant expected to have a generation capacity of about 1,200MW of electricity.
The project’s seawater reverse osmosis desalination facility will have a production capacity of 30 million imperial gallons a day (MIGD).
It is the second deadline extension on the main works package since the tender was released in August 2025.
Lebanon-headquartered Khatib & Alami was recently awarded a consulting contract for the project, worth $1.91m. This was despite the consultancy submitting only the third-lowest bid behind Spain’s Ayesa ($1.25m) and WSP Middle East Architectural & Engineering ($1.27m).
EWA’s transaction advisory team for the project comprises KPMG Fakhro as the financial consultant and Trowers & Hamlins as the legal consultant.
MEED previously reported that seven international companies and consortiums had prequalified to bid. These are:
- Abu Dhabi National Energy Company (Taqa, UAE)
- Acwa Power (Saudi Arabia)
- China Energy Engineering Corporation / China Datang (Overseas Hong Kong, China)
- Gulf Investment Corporation (Kuwait)
- Jera (Japan)
- Korea Electric Power Corporation (Kepco, South Korea)
- Sumitomo Corporation (Japan)
EWA first received statements of qualifications from nine interested firms in December 2024.
The build-own-operate (BOO) project is being procured under a public-private partnership framework for 20-25 years.
It is Bahrain’s fourth IWPP, replacing the previously planned Al-Dur 3. The Sitra IWPP is expected to be fully operational by the second quarter of 2029.
The project is in line with EWA’s plan to replace old plants with new, more efficient ones that reduce natural gas consumption.
Procurement for the Sitra IWPP is advancing in parallel to other EWA initiatives, including the planned 60MIGD Al-Hidd independent water plant (IWP), for which two bids were submitted earlier this year.
The contract to develop and operate the state’s first IWP remains under bid evaluation, a source said.
https://image.digitalinsightresearch.in/uploads/NewsArticle/16611117/main.jpg -
Bidders get more time for Jebel Ali sewage EPC contract29 April 2026

Dubai Municipality has extended the deadline for contractors to submit bids for a contract covering the expansion of the Jebel Ali sewage treatment plant (STP) phases one and two.
Contractors now have until June to submit offers, a source told MEED. Bidding had been expected to close on 30 April.
The upgraded facility will be capable of treating an additional sewage flow of 100,000 cubic metres a day (cm/d), with the expansion estimated to cost $300m.
The scope includes the design, construction and commissioning of infrastructure and systems required to support the increased capacity.
Located on a 670-hectare site in Jebel Ali, the original wastewater facility has a treatment capacity of about 675,000 cm/d following the completion of phase two in 2019, combining approximately 300,000 cm/d from phase one and 375,000 cm/d from phase two.
The main element of the expansion involves modifications to the secondary treatment process at Jebel Ali STP phase two.
UK-headquartered KPMG and UAE-based Tribe Infrastructure are serving as financial advisers on the project.
Future expansion
It is understood that the project is part of long-term plans to treat about 1.05 million cm/d once all future phases are completed.
According to sources, this includes a Jebel Ali-based build-operate-transfer (BOT) project to be developed under a public-private partnership (PPP) model.
It is understood that the prequalification process for this will begin in the coming months.
In February, MEED exclusively revealed that the municipality is preparing to tender the main construction package for the Warsan STP by the end of the year.
As MEED understands, the Warsan STP had previously been planned as a PPP project.
The main package will now be procured as an engineering, procurement and construction contract, a source said.
The project involves the construction of a sewage treatment plant with a capacity of about 175,000 cm/d, including treatment units, sludge handling systems and associated infrastructure.
https://image.digitalinsightresearch.in/uploads/NewsArticle/16608027/main.jpg -
UAE’s departure from Opec marks a tectonic shift29 April 2026
Commentary
Indrajit Sen
Oil & gas editorRegister for MEED’s 14-day trial access
The UAE’s decision to leave Opec and the Opec+ grouping marks a significant turning point in global oil markets and highlights shifting geopolitical dynamics and evolving supply expectations.
The UAE announced it will leave the producer alliance effective 1 May, ending nearly six decades of membership. The move reflects a broader strategic shift, as the country seeks greater flexibility over its production policy amid rising capacity and changing market conditions.
For oil markets, this is about more than one country wanting to pump more oil. Abu Dhabi National Oil Company (Adnoc) has spent billions of dollars over the years to raise crude production capacity to 5 million barrels a day.
Opec+ quotas had increasingly looked as though they were stifling Abu Dhabi’s growing desire to maximise revenues by tapping into its expanded spare capacity. Leaving the Opec+ coalition gives Abu Dhabi more room to monetise those investments.
The timing also matters. It comes against a backdrop of regional security concerns, tensions around Iran and the Strait of Hormuz, and a sense that consumers are once again being squeezed by high energy costs and depleted strategic reserves.
The immediate dip in the price of global benchmark Brent crude following the announcement of the UAE’s decision on 28 April showed the market’s first instinct: more UAE barrels could mean more supply and lower prices. However, the price rebound on 29 April, with Brent trading around $111 a barrel, also tells the other half of the story: extra capacity does not instantly become risk-free supply when regional bottlenecks and security threats remain front and centre.
For Opec+, this is a blow to unity and to Saudi Arabia’s ability to marshal producer discipline. It does not mean that a price war will start tomorrow, but it raises the risk of other member states choosing to abandon the alliance’s cooperation mechanism and pursue a higher market share. In trading terms, this adds a new volatility premium: more potential supply, less cartel discipline and a Gulf energy landscape that looks significantly less predictable.
The announcement comes at a time of heightened uncertainty in global energy markets, with geopolitical tensions, supply chain constraints and demand recovery trends all contributing to price volatility. The UAE’s exit is expected to reshape market expectations around supply flexibility and producer coordination.
https://image.digitalinsightresearch.in/uploads/NewsArticle/16608006/main.gif