Warming erodes Kuwait’s power and water reserves
14 August 2023
More on Kuwait’s power and water sector:
> IWPP: Firms respond to Kuwait independent utilities request
> POWER: Local firm wins 250MW Subiya package
> PRIVATISATION: Kuwait thermal plant privatisation to go ahead

The temperature in Kuwait soared to 51 degrees Celsius on 1 August, sending its electricity load index up to 16,940MW. This breached its maximum expected load this year of 16,830MW by 0.7 per cent.
This year’s projected maximum load is already 4 per cent higher than the previous year's recorded maximum load. It leaves only roughly 8 per cent of reserve capacity against an available capacity understood to stand at 18,250MW.
Similarly, water consumption across the Gulf state on 2 August, when the temperature decreased to 50 degrees, exceeded production by 29 million gallons, prompting the state utility to access its strategic water reserve capacity to plug the shortfall.
The electricity consumption spike reportedly caused two feeders at the country’s main substation south of Surra in the capital to trip, which led to power outages in some parts of Zahra, a district in Kuwait’s Hawalli governorate.
Kuwait’s Electricity & Renewable Energy Ministry (MEWRE) assured the public that the maximum capacity available in the country’s electricity network during the current summer is 18,250MW, as earlier cited, and that it could safely provide up to 17,660MW.
Persistent delays
The following week MEWRE – through the Kuwait Authority for Partnership Projects (Kapp) – received prequalification applications for the contracts to develop Kuwait’s next two independent water and power producer (IWPP) projects.
The two schemes – Al-Zour North 2 & 3 and Al-Khiran 1 – will have a total combined power generation capacity of 4,500MW and a water desalination capacity of over 150 million imperial gallons a day (MIGD), which will go a long way to address Kuwait’s precarious electricity and water supply situation.
Ironically, these two schemes have been in the planning and early procurement stages since 2017 and have suffered significant delays in the intervening period.
It is the second time developers have submitted statements of qualification (SOQs) for the contracts over the preceding 11 months.
The delays have caused major frustration for some developers and contractors. One utility developer that submitted an SOQ in September last year told MEED they did not participate in the latest attempt to start the prequalification process for the IWPP schemes, without elaborating.
Others expect the country’s stakeholders to eventually approve and expedite the procurement process for the integrated power and desalination facilities.
“I’m not very optimistic, but we submitted an SOQ anyway,” another source tells MEED.
EPC projects motoring ahead
The ministry’s conventional power plant projects have been moving at a relatively faster pace. In June this year, the local company Heavy Engineering Industries & Shipbuilding (Heisco) won a contract for the phase 2 upgrade of the Subiya power plant complex in Kuwait.
Heisco saw off competition from two local companies, Alghanim International and Al-Zain United General Trading & Contracting, for the KD114.28m ($372m) contract.
The project aims to convert an existing 250MW simple-cycle plant into a combined-cycle gas-turbine plant.
In April, a consortium comprising Heisco and Japan’s Mitsubishi Power was also awarded a contract to retrofit the main thermal power generation plant at the power complex.
The contract is understood to be valued at KD90.9m. It entails the upgrade of eight steam turbines and electric generators at the Subiya power plant, which is expected to reach a capacity of 2,400MW once the project is complete.
The existing plant at the Subiya power complex was commissioned between 1998 and 2002. This implies that the steam turbines and generators in commercial operation for nearly 20 years require upgrades to continue operating and improve their performance.
Two steps forward
While the country has pledged to become carbon neutral by 2060, the state utility has yet to make any remarkable progress in procuring new renewable energy capacity.
The recent political deadlock has hampered the procurement of the next phases of the Shagaya Renewable Energy Programme (SREP), despite the award 12 months previously of the project’s transaction advisory contract to a team led by London-headquartered consultancy firm EY.
At the time, the advisory contract was understood to cover the Al-Dibdibah solar project, which will comprise SREP’s second phase, and a third phase expected to include a 720MW solar photovoltaic (PV) plant, a 1,150MW concentrated solar power (CSP) facility and a wind power farm.
Notably, two state-backed downstream operators – Kuwait National Petroleum Company and Kuwait Integrated Petroleum Industries Company (Kipic) – have launched a tender for a contract to undertake a pre-feasibility study identifying opportunities to use renewable energy in their operations.
Kuwait is also expected to make some progress on its first utility privatisation scheme, which forms part of the initiative to strengthen private sector participation in the sector.
In December last year, it was revealed that UK-headquartered Deloitte had submitted a low bid of KD1.2m ($3.9m) for the transaction advisory contract in line with the planned privatisation of the $1.26bn North Shuaiba power and water plant in Kuwait.
GCC grid
While working to boost its electricity reserves and make its electricity systems greener, Kuwait stands to benefit from the ongoing upgrade of the GCC electricity grid, through which other GCC states, such as the UAE, may decide to transmit excess clean energy.
The Al-Fadhili high-voltage direct current (HVDC) converter station upgrade in Saudi Arabia is expected to enable the exchange of 1,800MW of electricity between the six states once complete.
In October last year, the GCC Interconnection Authority (GCCIA) awarded India-based KEC International a contract for an overhead transmission line project linking the substations in Wafra in Kuwait and Fadhili in Saudi Arabia.
The estimated $120m project extends an existing double-circuit 400kV line from Al-Zour in Kuwait to Ghunan in Saudi Arabia. The line has an intermediate interconnection at Fadhili, with associated substations completed in 2009 as part of the first phase of the GCCIA network. The new project is expected to complete in 2025.
This month’s special report on Kuwait also includes:
> ECONOMY: Stakeholders hope Kuwait can execute spending plans
> ENERGY: Kuwait’s $300bn energy target is a big test
> BANKING: Kuwaiti banks enter bounce-back mode
> INTERVIEW: Kuwait’s Gulf Centre United sets course for expansion
Exclusive from Meed
-
Kuwait tenders oil manifold project24 June 2026
-
-
Consortium wins $1bn Saudi healthcare PPP project23 June 2026
-
Morocco approves Khalladi wind farm expansion23 June 2026
-
Libya plans to distribute oil budget in July23 June 2026
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Kuwait tenders oil manifold project24 June 2026
State-owned upstream operator Kuwait Oil Company (KOC) has tendered a contract to construct remote header manifolds and associated works in the southern and eastern regions of Kuwait.
A meeting with prospective contractors has been scheduled for 21 July 2026, and bids are due to be submitted ahead of a deadline on 20 September 2026.
Manifolds are devices used in the oil sector to divide the flow of liquids from a single source to several outlets, or to collect liquids, or vice versa.
Previously, a project with a similar scope in the same region was awarded to the Kuwaiti contractor Al-Ghanim International General Trading & Contracting.
In 2016, it signed a contract worth $435m to construct remote header manifolds and associated works in the south and east Kuwait areas.
The scope of that contract included design, procurement, construction and commissioning of 25 remote manifold stations and associated pipelines in south and east Kuwait using multi-phase pumps to deliver liquids to gathering centres.
Kuwait’s oil fields are connected to more than 25 gathering centres, which serve as collection points for crude oil produced by several wells connected by flowlines, providing initial treatment by separating associated gas and removing salt.
READ THE JUNE 2026 MEED BUSINESS REVIEW – click here to view PDFGCC looks beyond the Strait; Iraq’s reform window narrows as fiscal assumptions shatter; MEED Top 100 companies.
Distributed to senior decision-makers in the region and around the world, the June 2026 edition of MEED Business Review includes:
> AGENDA: Gulf races to reroute trade> EXPORT ROUTES: Regional war boosts oil and gas pipeline project activity> CURRENT AFFAIRS: UAE’s Opec departure fulfils multiple ends> MEED TOP 100: Middle East stocks recover unevenly> LEADERSHIP: Building the infrastructure that makes net zero possible> TRADE DEAL: UK-GCC trade deal talks concludeTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/17409564/main.jpg -
Contractors win deals for Saudi Energy transmission projects23 June 2026

Saudi Arabia-based Haif Company has won contracts for two separate substation projects in Saudi Arabia, according to sources.
The first involves the construction of a 132/33/13.8kV substation for Saudi Energy, formerly Saudi Electricity Company, which will replace the existing Tabuk substation 2 in Tabuk, northwestern Saudi Arabia.
The works include the construction of a new substation, along with GIS, transformers, switchgear, capacitor banks, MV/LV cable systems and protection infrastructure.
Ten firms submitted bids for the project last December. The bidders included:
- Al-Babtain Contracting (Saudi Arabia)
- Alfanar Projects (Saudi Arabia)
- Al-Gihaz Holding (Saudi Arabia)
- Al-Osais International Holding (Saudi Arabia)
- Danway Electrical & Mechanical Engineering (UAE)
- Haif Company (Saudi Arabia)
- Mohammed Al-Ojaimi Group (Saudi Arabia)
- Nesma Infrastructure & Technology (Saudi Arabia)
- Saudi Services for Electro Mechanic Works (Saudi Arabia)
- Tareg Al-Jaafari Contracting Est (Saudi Arabia)
In addition to Tabuk, Saudi Energy is planning several power transmission projects in Al-Jouf, Medina and the Eastern Province as part of the kingdom’s push to upgrade its electricity transmission and distribution infrastructure
The second Haif contract involves a 132/33kV substation project at Hail to support the integration of solar generation from the Al-Kahfah photovoltaic facility into the network. Together, the projects are valued at about $90m.
Elsewhere, the local Trading & Development Partnership has been appointed to build a 132/33kV substation at Al-Jouf, in Al-Jouf Province.
The facility will deliver a transmission capacity of about 168 MVA to the Al-Busitaa agricultural site, supporting the Liquid Fuel Displacement Programme, which aims to reduce reliance on diesel generators and fuel oil for power generation.
Nine bids were submitted for the project last year.
According to MEED Projects, Saudi Energy has almost $2.3bn-worth of projects currently under bid evaluation, including the 500kV overhead transmission line, approximately 466km long, for the Eastern Operating Area and the Central Operating Area in the Eastern Province. The main contract is expected to be awarded later in 2026.
https://image.digitalinsightresearch.in/uploads/NewsArticle/17397346/main.jpg -
Consortium wins $1bn Saudi healthcare PPP project23 June 2026
Saudi Arabia’s Ministry of Health and the National Centre for Privatisation & PPP (NCP) have awarded a public-private partnership (PPP) contract for the operation and management of the Sabic Specialised Behavioural Healthcare Hospital in Riyadh.
The contract was awarded to SEH Healthcare, a consortium comprising local firms Specialised Medical Company (SMC Healthcare) and Health Gates Complex, and Germany’s Dr Ebel Fachkliniken.
In a stock exchange filing on the Tadawul, SMC Healthcare said the total estimated project value is about SR3.8bn ($1bn).
“The scope of the contract includes medical and non-medical operations and maintenance, facility management, equipment management, and specialised clinical and non-clinical services in mental health and addiction treatment,” the statement added.
The contract term is 15 years.
The facility spans about 62,500 square metres and includes 150 beds, 19 outpatient clinics and six dedicated day-care rooms, as well as specialised services in mental health, addiction treatment, rehabilitation and aftercare.
The project is the latest healthcare project to be procured on a PPP basis in the kingdom. In May, Saudi Arabia’s Ministry of Health, the Ministry of Defence and the NCP issued an expression of interest and request for qualification notice for the Chronic Kidney Disease Care and National Dialysis Services project.
The NCP said the initiative supports Saudi Vision 2030 by increasing private sector participation in the healthcare sector.
In January, Saudi Arabia launched a National Privatisation Strategy, which aims to mobilise $64bn in private sector capital by 2030.
The strategy builds on the privatisation programme first introduced in 2018. It will focus on unlocking state-owned assets for private investment and privatising selected government services.
In a statement, NCP said the new strategy comprises 147 opportunities drawn from a broader pipeline of more than 500 projects across 18 sectors.
https://image.digitalinsightresearch.in/uploads/NewsArticle/17396605/main.jpg -
Morocco approves Khalladi wind farm expansion23 June 2026
Acwa Maroc, a subsidiary of Saudi developer Acwa, has secured approval to expand the Khalladi wind independent power project (IPP) in northern Morocco by 40MW.
The extension will increase the project’s total installed capacity from 120MW to 160MW. The Khalladi wind farm is located at Djebel Sendouq, about 50 kilometres from Tangier. The existing facility comprises 40 wind turbines rated at 3MW each.
The project operates under Morocco’s Law 13.09 renewable energy framework, which allows private renewable energy firms to develop generation assets and supply electricity directly to industrial consumers.
According to Acwa’s website, the facility entered commercial operation in 2018 and supplies electricity to Morocco’s state-owned utility Onee and large industrial customers under a 20-year power-purchase agreement.
Acwa holds a 51% stake in the project alongside Participation Khalladi SA (24%) and ARIF North Africa Investment SARL, an infrastructure investment fund managed by France’s Amundi (25%).
The engineering, procurement and construction contract was executed by Denmark’s Vestas, France’s Cegelec and Morocco’s Stam and AGTT.
Morocco is targeting renewables to account for 52% of its installed power generation capacity by 2030.
The operational wind farm generates about 397GWh of electricity a year. It is understood that the expansion project has already entered the development phase.
https://image.digitalinsightresearch.in/uploads/NewsArticle/17394999/main5046.jpg -
Libya plans to distribute oil budget in July23 June 2026

Libya’s National Oil Corporation (NOC) has communicated to contractors in the country that it is expecting funds from the country’s budget to be distributed to state-owned oil companies in July, according to industry sources.
Earlier this year, the country’s rival legislative bodies approved a unified state budget for the first time in more than 13 years.
The Central Bank of Libya confirmed on 11 April that both chambers had endorsed the budget, calling it a key step towards restoring financial stability after prolonged division.
The total budget was valued at LD190bn ($29.95bn), and LD12bn ($1.9bn) was allocated to the country’s NOC.
An additional LD40bn ($6.3bn) was allocated for “development projects”.
At the time, Libya stated that a joint committee had been formed to help prioritise development projects, and the projects had been listed in the budget.
Over the past decade, the country has had two rival governments; the last time the country operated under a single national budget was in 2013.
The country’s two legislatures are the eastern-based House of Representatives and the Tripoli-based High Council of State.
As a result of the US and Israel’s war with Israel, there has been significant disruption to shipping through the Strait of Hormuz, which normally transports around 20% of the world’s oil and gas exports.
This has driven global energy prices higher, with Brent hitting more than $114 a barrel in May this year.
The price of Brent remains 10% higher than prior to the US and Israel attacking Iran on 28 February.
Libya is well-positioned to capitalise on the ongoing uncertainty around exports via the Strait of Hormuz, as energy-importing nations seek reliable oil and gas supplies.
The North African country is located near Europe, with several large oil and gas export ports and a pipeline that transports gas to Italy.
Libya has the largest oil reserves in Africa, but has struggled to implement projects to develop them over recent years due to political infighting and security problems.
READ THE JUNE 2026 MEED BUSINESS REVIEW – click here to view PDFGCC looks beyond the Strait; Iraq’s reform window narrows as fiscal assumptions shatter; MEED Top 100 companies.
Distributed to senior decision-makers in the region and around the world, the June 2026 edition of MEED Business Review includes:
> AGENDA: Gulf races to reroute trade> EXPORT ROUTES: Regional war boosts oil and gas pipeline project activity> CURRENT AFFAIRS: UAE’s Opec departure fulfils multiple ends> MEED TOP 100: Middle East stocks recover unevenly> LEADERSHIP: Building the infrastructure that makes net zero possible> TRADE DEAL: UK-GCC trade deal talks concludeTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/17389246/main2010.jpg
