Warming erodes Kuwait’s power and water reserves

14 August 2023

More on Kuwait’s power and water sector: 

> IWPP: Firms respond to Kuwait independent utilities request
> POWERLocal firm wins 250MW Subiya package
> PRIVATISATIONKuwait thermal plant privatisation to go ahead


 

The temperature in Kuwait soared to 51 degrees Celsius on 1 August, sending its electricity load index up to 16,940MW. This breached its maximum expected load this year of 16,830MW by 0.7 per cent.

This year’s projected maximum load is already 4 per cent higher than the previous year's recorded maximum load. It leaves only roughly 8 per cent of reserve capacity against an available capacity understood to stand at 18,250MW.

Similarly, water consumption across the Gulf state on 2 August, when the temperature decreased to 50 degrees, exceeded production by 29 million gallons, prompting the state utility to access its strategic water reserve capacity to plug the shortfall.

The electricity consumption spike reportedly caused two feeders at the country’s main substation south of Surra in the capital to trip, which led to power outages in some parts of Zahra, a district in Kuwait’s Hawalli governorate.

Kuwait’s Electricity & Renewable Energy Ministry (MEWRE) assured the public that the maximum capacity available in the country’s electricity network during the current summer is 18,250MW, as earlier cited, and that it could safely provide up to 17,660MW.

Persistent delays

The following week MEWRE – through the Kuwait Authority for Partnership Projects (Kapp) – received prequalification applications for the contracts to develop Kuwait’s next two independent water and power producer (IWPP) projects.

The two schemes – Al-Zour North 2 & 3 and Al-Khiran 1 – will have a total combined power generation capacity of 4,500MW and a water desalination capacity of over 150 million imperial gallons a day (MIGD), which will go a long way to address Kuwait’s precarious electricity and water supply situation.

Ironically, these two schemes have been in the planning and early procurement stages since 2017 and have suffered significant delays in the intervening period.

It is the second time developers have submitted statements of qualification (SOQs) for the contracts over the preceding 11 months.

The delays have caused major frustration for some developers and contractors. One utility developer that submitted an SOQ in September last year told MEED they did not participate in the latest attempt to start the prequalification process for the IWPP schemes, without elaborating.

Others expect the country’s stakeholders to eventually approve and expedite the procurement process for the integrated power and desalination facilities.

“I’m not very optimistic, but we submitted an SOQ anyway,” another source tells MEED.

EPC projects motoring ahead

The ministry’s conventional power plant projects have been moving at a relatively faster pace. In June this year, the local company Heavy Engineering Industries & Shipbuilding (Heisco) won a contract for the phase 2 upgrade of the Subiya power plant complex in Kuwait.

Heisco saw off competition from two local companies, Alghanim International and Al-Zain United General Trading & Contracting, for the KD114.28m ($372m) contract.

The project aims to convert an existing 250MW simple-cycle plant into a combined-cycle gas-turbine plant.

In April, a consortium comprising Heisco and Japan’s Mitsubishi Power was also awarded a contract to retrofit the main thermal power generation plant at the power complex.

The contract is understood to be valued at KD90.9m. It entails the upgrade of eight steam turbines and electric generators at the Subiya power plant, which is expected to reach a capacity of 2,400MW once the project is complete.

The existing plant at the Subiya power complex was commissioned between 1998 and 2002. This implies that the steam turbines and generators in commercial operation for nearly 20 years require upgrades to continue operating and improve their performance.

Two steps forward

While the country has pledged to become carbon neutral by 2060, the state utility has yet to make any remarkable progress in procuring new renewable energy capacity.

The recent political deadlock has hampered the procurement of the next phases of the Shagaya Renewable Energy Programme (SREP), despite the award 12 months previously of the project’s transaction advisory contract to a team led by London-headquartered consultancy firm EY.

At the time, the advisory contract was understood to cover the Al-Dibdibah solar project, which will comprise SREP’s second phase, and a third phase expected to include a 720MW solar photovoltaic (PV) plant, a 1,150MW concentrated solar power (CSP) facility and a wind power farm.

Notably, two state-backed downstream operators – Kuwait National Petroleum Company and Kuwait Integrated Petroleum Industries Company (Kipic) – have launched a tender for a contract to undertake a pre-feasibility study identifying opportunities to use renewable energy in their operations.

Kuwait is also expected to make some progress on its first utility privatisation scheme, which forms part of the initiative to strengthen private sector participation in the sector.

In December last year, it was revealed that UK-headquartered Deloitte had submitted a low bid of KD1.2m ($3.9m) for the transaction advisory contract in line with the planned privatisation of the $1.26bn North Shuaiba power and water plant in Kuwait.

GCC grid

While working to boost its electricity reserves and make its electricity systems greener, Kuwait stands to benefit from the ongoing upgrade of the GCC electricity grid, through which other GCC states, such as the UAE, may decide to transmit excess clean energy.

The Al-Fadhili high-voltage direct current (HVDC) converter station upgrade in Saudi Arabia is expected to enable the exchange of 1,800MW of electricity between the six states once complete.

In October last year, the GCC Interconnection Authority (GCCIA) awarded India-based KEC International a contract for an overhead transmission line project linking the substations in Wafra in Kuwait and Fadhili in Saudi Arabia.

The estimated $120m project extends an existing double-circuit 400kV line from Al-Zour in Kuwait to Ghunan in Saudi Arabia. The line has an intermediate interconnection at Fadhili, with associated substations completed in 2009 as part of the first phase of the GCCIA network. The new project is expected to complete in 2025.


This month’s special report on Kuwait also includes: 

> ECONOMYStakeholders hope Kuwait can execute spending plans
> ENERGYKuwait’s $300bn energy target is a big test
> BANKINGKuwaiti banks enter bounce-back mode
> INTERVIEWKuwait’s Gulf Centre United sets course for expansion

https://image.digitalinsightresearch.in/uploads/NewsArticle/11069881/main.gif
Jennifer Aguinaldo
Related Articles
  • Bahrain’s economy walks precarious path

    26 November 2025

    Download the PDF


    MEED’s December 2025 report on Bahrain includes:

    > COMMENT: Manama pursues reform amid strain
    > GVT & ECONOMY: Bahrain’s cautious economic evolution

    > BANKING: Mergers loom over Bahrain’s banking system
    > OIL & GAS: Bahrain remains in pursuit of hydrocarbon resources
    > POWER & WATER: Bahrain advances utility reform
    > CONSTRUCTION: Bahrain construction faces major slowdown
    > TRANSPORT: Air Asia aviation deal boosts connectivity

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/15159666/main.gif
    MEED Editorial
  • Rua Al-Madinah signs hotel operations agreement

    26 November 2025

    Saudi Arabia’s Rua Al-Madinah, the Public Investment Fund (PIF) subsidiary tasked with Medina’s tourism and cultural development, has signed a hotel operations and management agreement with Adeera Hospitality for its Rua Al-Madinah project.

    Adeera Hospitality, which PIF also backs, will operate two buildings comprising 250 hotel rooms and 120 residential units under its Alia brand within the Rua Al-Madinah project, which is being developed near the Prophet’s Mosque.

    Adeera joins Rua Al-Madinah’s roster of hotel operators, which includes leading global hospitality brands such as Marriott, Hyatt, Accor and Hilton.

    The Rua Al-Madinah development includes the construction of 18 hotels under three categories – three-star, four-star and five-star – as well as secondary infrastructure.

    The towers will range in height from 11 to 21 storeys.

    Rua Al-Madinah estimates that superblock five will require 430,000 cubic metres of concrete, 875,000 square metres of block wall, 423,000 sq m of drywall, 74,000 tonnes of steel rebar, 215,000 sq m of tiles, and 228,000 sq m of facades, curtain walls and windows.

    The hotels, which will mainly provide accommodation for pilgrims visiting the holy city, will have a built-up area of about 65,000 sq m.

    In February last year, the client awarded two contracts worth SR300m ($80m) to international consulting firms for work on the superblocks four and five components of the Rua Al-Madinah project.

    Rua Al-Madinah signed a contract with US-based engineering firm Jacobs for design consultancy services for 12 hotels and other infrastructure for superblock four of the project.

    Another contract was signed with US-based KEO International Consultants to oversee the implementation of the superblock five project.

    Other consultants working on superblock five include US-based Perkins Eastman and Singapore-based Meinhardt. 

    UAE-based Ema Design is the interior designer.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/15158923/main.jpg
    Yasir Iqbal
  • Meraas confirms $517m The Acres villas contract award

    26 November 2025

    Dubai-based real estate developer Meraas, now part of Dubai Holding Group, has confirmed that it has awarded a AED1.9bn ($517m) contract to build 642 three-, four- and five-bedroom villas as part of the first phase of its residential community, The Acres, in Dubailand.

    The contract was awarded to the local firm United Engineering Construction Company.

    MEED exclusively reported in August that Meraas had awarded the contract for the project.

    The Acres project is designed by local architectural practice U+A Architects.

    The masterplan includes 1,200 villas ranging from three to seven bedrooms.

    It also features a nursery, school, clinic, mosques, clubhouses, a retail zone, a 2,000-square-metre garden, walking and biking trails, an outdoor gym, children’s playgrounds, swimming pools and sports facilities.

    The latest announcement follows Meraas awarding a AED440m ($120m) contract for the construction of the Northline residential project in the Al-Wasl area of Dubai.

    The contract was awarded to the local GCC Contracting Company.

    The project includes the construction of three residential buildings. Construction work is expected to begin shortly, and the project is slated for completion by 2027.

    Meraas’ latest project contract awards in Dubai are backed by heightened real estate activity in the UAE’s construction market. Schemes worth over $323bn are in the execution or planning stages, according to UK analytics firm GlobalData.

    The company forecasts that the output of the UAE’s construction sector will grow by 4.2% in real terms in 2025, supported by developments in infrastructure, energy and utilities, as well as residential construction projects.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/15158561/main.jpg
    Yasir Iqbal
  • December deadline for Riyadh airport fourth runway

    26 November 2025

     

    King Salman International Airport Development Company (KSIADC) has allowed firms until 3 December to bid for the design-and-build contract for the fourth runway at King Salman International airport (KSIA) in Riyadh.

    The tender was first floated on 17 April. The previous bid submission deadline was 28 October.

    It is understood that the third and fourth runways will add to the two existing runways at Riyadh’s King Khalid International airport, which will eventually become part of KSIA.

    KSIADC, which is backed by Saudi Arabia’s Public Investment Fund, prequalified firms in September last year for the main engineering, procurement and construction packages; early and enabling works; specialist systems and integration; specialist systems, materials and equipment; engineering and design; professional services; health, safety, security, environment and wellbeing services; modular installation and prefabrication; local content; and environmental, social, governance and other services.

    The entire scheme is divided into eight assets. These are:

    • Iconic Terminal
    • Terminal 6
    • Private aviation terminal 
    • Central runway and temporary apron
    • Hangars
    • Landside transport
    • Cargo buildings
    • Real estate

    In August last year, KSIADC confirmed it had signed up several architectural and design firms for the various elements of the project.

    US-based firm Bechtel Corporation will manage the delivery of three new terminals, including the terminal for commercial carriers, Terminal 6 for low-cost carriers and a new private aviation terminal with hangars.

    Parsons, also of the US, was chosen as the delivery partner for two packages. One covers the airside infrastructure, including the runways, taxiways, air traffic control towers, fuel farms and fire stations. The other involves the infrastructure connecting the airport to the rest of the city, including utilities and roads.

    UK-based Foster+Partners will design the airport’s masterplan, including the terminals, six runways and a multi-asset real estate area.

    US-based engineering firm Jacobs will provide specialist consultancy services for the masterplan and the design of the new runways.

    UK-based engineering firm Mace was appointed as the project’s delivery partner and local firm Nera was awarded the airspace design consultancy contract.

    Project scale

    The project covers an area of about 57 square kilometres (sq km), allowing for six parallel runways, and will include the existing terminals at King Khalid International airport. It will also include 12 sq km of airport support facilities, residential and recreational facilities, retail outlets and other logistics real estate.

    If the project is completed on time in 2030, it will become the world’s largest operating airport in terms of passenger capacity, according to UK analytics firm GlobalData.

    The airport aims to accommodate up to 120 million passengers by 2030 and 185 million by 2050. The goal for cargo is to process 3.5 million tonnes a year by 2050.

    Saudi Arabia plans to invest $100bn in its aviation sector. Riyadh’s Saudi Aviation Strategy, announced by the General Authority of Civil Aviation (Gaca), aims to triple Saudi Arabia’s annual passenger traffic to 330 million travellers by 2030.

    It also aims to increase air cargo traffic to 4.5 million tonnes and raise the country’s total air connections to more than 250 destinations.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/15158546/main.jpg
    Yasir Iqbal
  • Chinese contractor appointed for Algerian refinery project

    26 November 2025

    China’s Sinopec Guangzhou Engineering Company has signed a contract for the construction of a heavy naphtha catalytic processing unit at the Arzew refinery in Algeria.

    The contract was signed with the Algerian national oil and gas company Sonatrach.

    The contract uses the engineering, procurement, construction and operation model.

    Under the terms of the contract, Sinopec Guangzhou Engineering Company will handle the entire project lifecycle, from initial design to long-term management and operation.

    The project will be completed over 30 months, according to a statement from the Algerian Ministry of Hydrocarbons & Mines.

    The unit will have an annual capacity of 738,000 tonnes of heavy naphtha and will enable the refinery to increase gasoline production from 550,000 tonnes to 1.2 million tonnes a year.

    Algeria’s Ministry of Hydrocarbons & Mines said this represented “a significant step” that will strengthen the national capacity for gasoline production and help meet demand across various regions, particularly in the west and southwest of the country.

    Sinopec Guangzhou Engineering Company is a subsidiary of China Petroleum & Chemical Corporation (Sinopec), which is listed on stock exchanges in Hong Kong, Shanghai and New York.

    The project is part of Sonatrach’s wider programme to modernise and expand national refining capacities.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/15157814/main.jpg
    Wil Crisp