Warming erodes Kuwait’s power and water reserves
14 August 2023
More on Kuwait’s power and water sector:
> IWPP: Firms respond to Kuwait independent utilities request
> POWER: Local firm wins 250MW Subiya package
> PRIVATISATION: Kuwait thermal plant privatisation to go ahead

The temperature in Kuwait soared to 51 degrees Celsius on 1 August, sending its electricity load index up to 16,940MW. This breached its maximum expected load this year of 16,830MW by 0.7 per cent.
This year’s projected maximum load is already 4 per cent higher than the previous year's recorded maximum load. It leaves only roughly 8 per cent of reserve capacity against an available capacity understood to stand at 18,250MW.
Similarly, water consumption across the Gulf state on 2 August, when the temperature decreased to 50 degrees, exceeded production by 29 million gallons, prompting the state utility to access its strategic water reserve capacity to plug the shortfall.
The electricity consumption spike reportedly caused two feeders at the country’s main substation south of Surra in the capital to trip, which led to power outages in some parts of Zahra, a district in Kuwait’s Hawalli governorate.
Kuwait’s Electricity & Renewable Energy Ministry (MEWRE) assured the public that the maximum capacity available in the country’s electricity network during the current summer is 18,250MW, as earlier cited, and that it could safely provide up to 17,660MW.
Persistent delays
The following week MEWRE – through the Kuwait Authority for Partnership Projects (Kapp) – received prequalification applications for the contracts to develop Kuwait’s next two independent water and power producer (IWPP) projects.
The two schemes – Al-Zour North 2 & 3 and Al-Khiran 1 – will have a total combined power generation capacity of 4,500MW and a water desalination capacity of over 150 million imperial gallons a day (MIGD), which will go a long way to address Kuwait’s precarious electricity and water supply situation.
Ironically, these two schemes have been in the planning and early procurement stages since 2017 and have suffered significant delays in the intervening period.
It is the second time developers have submitted statements of qualification (SOQs) for the contracts over the preceding 11 months.
The delays have caused major frustration for some developers and contractors. One utility developer that submitted an SOQ in September last year told MEED they did not participate in the latest attempt to start the prequalification process for the IWPP schemes, without elaborating.
Others expect the country’s stakeholders to eventually approve and expedite the procurement process for the integrated power and desalination facilities.
“I’m not very optimistic, but we submitted an SOQ anyway,” another source tells MEED.
EPC projects motoring ahead
The ministry’s conventional power plant projects have been moving at a relatively faster pace. In June this year, the local company Heavy Engineering Industries & Shipbuilding (Heisco) won a contract for the phase 2 upgrade of the Subiya power plant complex in Kuwait.
Heisco saw off competition from two local companies, Alghanim International and Al-Zain United General Trading & Contracting, for the KD114.28m ($372m) contract.
The project aims to convert an existing 250MW simple-cycle plant into a combined-cycle gas-turbine plant.
In April, a consortium comprising Heisco and Japan’s Mitsubishi Power was also awarded a contract to retrofit the main thermal power generation plant at the power complex.
The contract is understood to be valued at KD90.9m. It entails the upgrade of eight steam turbines and electric generators at the Subiya power plant, which is expected to reach a capacity of 2,400MW once the project is complete.
The existing plant at the Subiya power complex was commissioned between 1998 and 2002. This implies that the steam turbines and generators in commercial operation for nearly 20 years require upgrades to continue operating and improve their performance.
Two steps forward
While the country has pledged to become carbon neutral by 2060, the state utility has yet to make any remarkable progress in procuring new renewable energy capacity.
The recent political deadlock has hampered the procurement of the next phases of the Shagaya Renewable Energy Programme (SREP), despite the award 12 months previously of the project’s transaction advisory contract to a team led by London-headquartered consultancy firm EY.
At the time, the advisory contract was understood to cover the Al-Dibdibah solar project, which will comprise SREP’s second phase, and a third phase expected to include a 720MW solar photovoltaic (PV) plant, a 1,150MW concentrated solar power (CSP) facility and a wind power farm.
Notably, two state-backed downstream operators – Kuwait National Petroleum Company and Kuwait Integrated Petroleum Industries Company (Kipic) – have launched a tender for a contract to undertake a pre-feasibility study identifying opportunities to use renewable energy in their operations.
Kuwait is also expected to make some progress on its first utility privatisation scheme, which forms part of the initiative to strengthen private sector participation in the sector.
In December last year, it was revealed that UK-headquartered Deloitte had submitted a low bid of KD1.2m ($3.9m) for the transaction advisory contract in line with the planned privatisation of the $1.26bn North Shuaiba power and water plant in Kuwait.
GCC grid
While working to boost its electricity reserves and make its electricity systems greener, Kuwait stands to benefit from the ongoing upgrade of the GCC electricity grid, through which other GCC states, such as the UAE, may decide to transmit excess clean energy.
The Al-Fadhili high-voltage direct current (HVDC) converter station upgrade in Saudi Arabia is expected to enable the exchange of 1,800MW of electricity between the six states once complete.
In October last year, the GCC Interconnection Authority (GCCIA) awarded India-based KEC International a contract for an overhead transmission line project linking the substations in Wafra in Kuwait and Fadhili in Saudi Arabia.
The estimated $120m project extends an existing double-circuit 400kV line from Al-Zour in Kuwait to Ghunan in Saudi Arabia. The line has an intermediate interconnection at Fadhili, with associated substations completed in 2009 as part of the first phase of the GCCIA network. The new project is expected to complete in 2025.
This month’s special report on Kuwait also includes:
> ECONOMY: Stakeholders hope Kuwait can execute spending plans
> ENERGY: Kuwait’s $300bn energy target is a big test
> BANKING: Kuwaiti banks enter bounce-back mode
> INTERVIEW: Kuwait’s Gulf Centre United sets course for expansion
Exclusive from Meed
-
-
-
-
Dubai advances Auto Market construction6 May 2026
-
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Contractor wins $218m Aramco-backed logistics hub deal7 May 2026

Saudi Amana, the local affiliate of UAE-based construction firm Group Amana, has won an estimated SR820m ($218m) contract to build a logistics complex at King Salman Energy Park (Spark) in Saudi Arabia's Eastern Province.
Asmo, the logistics joint venture of Saudi Aramco and DHL Supply Chain, awarded the contract.
Asmo received the main contract bids on 18 March, as MEED reported.
Al-Khobar-based engineering firm House of Consulting Office is the project consultant.
In February, Asmo signed an agreement with Bahrain‑headquartered Arcapita Group Holdings to deliver the project at Spark.
The project will feature a 43,000-square-metre (sq m), temperature-controlled Grade A warehouse; more than 3,000 sq m of offices and staff amenities; 5,300 sq m dedicated to chemicals storage; and an open yard covering about 1.2 million sq m.
Planned for large-scale industrial use, the site is expected to incorporate advanced warehouse and building management systems, end-to-end digital connectivity, automation and robotics.
It will also be developed in line with internationally recognised sustainability standards, featuring solar photovoltaic readiness, electric-vehicle charging infrastructure and a target of Leed Gold certification.
The development aims to support the next stage of Saudi Arabia’s logistics and supply chain expansion.
Under the deal structure, Arcapita will provide funding and retain ownership of the asset, while Asmo will develop the facility and then lease and operate it under a 22-year occupational lease.
According to a statement, “the scheme will be executed via a forward-funding model, underscoring a long-term commitment to national infrastructure”.
Asmo added that this will be its first purpose-built logistics centre and one of four strategic locations planned to anchor its nationwide logistics network, aligned with the National Transport and Logistics Strategy under Saudi Vision 2030.
READ THE MAY 2026 MEED BUSINESS REVIEW – click here to view PDFGlobal energy sector forced to recalibrate; Conflict hits debt issuance and listings activity; UAE’s non-oil sector faces unclear recovery period amid disruption.
Distributed to senior decision-makers in the region and around the world, the May 2026 edition of MEED Business Review includes:
> REGIONAL LNG: War undermines business case for Middle East LNG> CAPITAL MARKETS: Damage avoidance frames debt issuance> MARKET FOCUS: Conflict tests UAE diversificationTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/16715420/main.jpg -
Kuwait postpones bid deadlines for four downstream oil tenders7 May 2026

Kuwait has extended bid deadlines for four tendered contracts that are all focused on the country’s Mina Al-Ahmadi (MAA) refinery.
The contracts include a project that has been tendered by state-owned downstream operator Kuwait National Petroleum Company (KNPC) to upgrade water transmission and storage infrastructure at the refinery.
The contract will use the engineering, procurement and construction model and the tender was originally issued in October 2025 with an initial bid deadline of 4 January 2026.
The tender has already seen several extensions and the latest rescheduling has set the bid deadline back from 19 April 2026 until 10 May 2026.
The project is expected to take two years to complete and its scope is focused on expanding water storage capacity at the facility, either through extending existing tanks or building new tanks.
The winning bidder will also be responsible for developing associated infrastructure and upgrading related systems that transport desalinated water to the refinery, such as pipelines and other infrastructure.
In its 2024-25 annual report, KNPC said the project will help to meet demand for water at the facility’s refining and gas production units.
The other three contracts are all maintenance contracts, which were also tendered by KNPC and have had their bid deadlines extended until 30 June 2026.
The first of these is focused on mechanical maintenance of the Clean Fuel Project (CFP) units at the facility, as well as gas liquid production facilities.
The CFP units were added to the refinery as part of the $16bn CFP, and were brought online in 2021.
The project aimed to increase Kuwait’s capacity to produce low-sulfur fuels and, as part of the project, the MAA refinery was integrated with Kuwait’s Mina Abdulla (MAB) refinery.
The project increased the capacity of MAB to 454,000 barrels a day (b/d) and the MAA refinery to 346,000 b/d.
The second maintenance contract is focused on the mechanical maintenance of refining and production units at the MAA facility. The third contract is focused on workshop maintenance at the facility.
The MAA refinery has been hit in several attacks during the US and Israel's war with Iran, which started on 28 February 2026.
The full extent of the damage to the facility is currently unclear.
Last month, MEED revealed that state-owned oil companies in Kuwait have fast-tracked the award of contracts to repair damage to infrastructure in the oil and gas sector.
To expedite the award of contracts, deals were directly negotiated with trusted contractors without public tenders.
The contracts were negotiated by senior officials at Kuwait Petroleum Corporation subsidiaries including Kuwait Oil Company and KNPC, sources said.
It is not known whether any of these contracts related to repairs at the MAA refinery.
READ THE MAY 2026 MEED BUSINESS REVIEW – click here to view PDFGlobal energy sector forced to recalibrate; Conflict hits debt issuance and listings activity; UAE’s non-oil sector faces unclear recovery period amid disruption.
Distributed to senior decision-makers in the region and around the world, the May 2026 edition of MEED Business Review includes:
> REGIONAL LNG: War undermines business case for Middle East LNG> CAPITAL MARKETS: Damage avoidance frames debt issuance> MARKET FOCUS: Conflict tests UAE diversificationTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/16715383/main.jpg -
Oman signs exploration agreement for methane hydrates7 May 2026
Oman’s Ministry of Energy & Minerals (MEMR) has signed an agreement with Victarens Global Energy for the exploration of methane hydrates in Block 83 in the sultanate.
Under the agreement, Victarens Global Energy will perform a study of Block 83, which spans approximately 11,000 square kilometers onshore Oman, over an initial period of two years, extendable for an additional two years based on the outcomes of the studies.
“This step marks the first initiative of its kind in the sultanate to assess the potential of gas production through non-conventional methods, contributing to the diversification and sustainability of energy sources,” the MEMR said in a statement.
The agreement was signed in Muscat by Salim Bin Nasser Al-Aufi, Oman’s Energy & Minerals Minister, and Kenan Issa, CEO of Victarens Global Energy.
The project will be implemented in two main phases. The initial investment for the first phase is estimated at approximately $20m, while the second phase is expected to require around $200m, “reflecting the strategic importance of this project in exploring non-conventional energy resources”, the MEMR said in a statement.
ALSO READ: Oman awards manganese exploration concession deal
The scope of work on the first phase includes geological studies, analysis and reprocessing of existing geophysical data, and carrying out new seismic surveys to determine the volume and thickness of methane hydrate layers within the study area.
Based on the results of this phase, the project will proceed to the second phase, which involves installing extraction equipment and testing the feasibility of commercial production.
Should the project demonstrate economic viability for methane hydrate production, negotiations will be conducted between the MEMR and the company to establish a long-term agreement, including the commercial terms and profit-sharing mechanisms that ensure mutual benefits for both parties.
“This agreement aims to explore and assess methane hydrate resources, supporting the adoption of advanced technologies in the energy sector and reinforcing the transition toward future energy sources, while promoting innovation and sustainability in the utilisation of natural resources. The agreement aligns with the objectives of Oman Vision 2040, which focuses on economic diversification, the development of the energy sector and strengthening the sultanate’s position as a regional hub for energy and advanced technologies,” the MEMR statement added.
READ THE MAY 2026 MEED BUSINESS REVIEW – click here to view PDFGlobal energy sector forced to recalibrate; Conflict hits debt issuance and listings activity; UAE’s non-oil sector faces unclear recovery period amid disruption.
Distributed to senior decision-makers in the region and around the world, the May 2026 edition of MEED Business Review includes:
> REGIONAL LNG: War undermines business case for Middle East LNG> CAPITAL MARKETS: Damage avoidance frames debt issuance> MARKET FOCUS: Conflict tests UAE diversificationTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/16703851/main1050.jpg -
Dubai advances Auto Market construction6 May 2026

The construction works on the Dubai Auto Market, which is set to become one of the world’s largest and most advanced automotive trading hubs, are progressing.
Enabling works are under way, being carried out by local contractor Rad International Road Construction.
US-based engineering firm Aecom is serving as the project consultant.
In November last year, Dubai Municipality signed a partnership agreement with DP World’s Economic Zones division to establish and manage the market, as MEED reported. Under the agreement, DP World will provide integrated logistics and zone management services, including e-commerce and trade finance solutions.
The Dubai Auto Market will span a 22 million-square-foot complex, to be developed by DP World. It is planned to include more than 1,500 showrooms, clustered workshop zones, warehouses and multi-storey parking facilities, alongside a convention centre, hotel, auction house, retail outlets, and food and beverage areas.
The facility is designed to handle more than 800,000 vehicles a year, including new and used electric, hybrid and conventional models.
The UAE’s construction industry is projected to expand by 5% in real terms in 2026, supported by rising foreign direct investment (FDI), growth in the construction sector and increased oil sector activity.
According to the UAE’s Federal Competitiveness and Statistics Centre, construction value added rose by 8.8% year on year (YoY) in Q2 2025, following YoY growth of 7% in Q1 2025 and 10.8% in Q4 2024.
The commercial construction sector is forecast to grow by 6.4% in 2026 and to record average annual growth of 4.9% from 2027 to 2030, supported by investment in tourism and hotel facilities.
The industrial construction sector is expected to expand by 4.1% in real terms in 2026, then to average 4.4% annually from 2027 to 2030, supported by improved investment in manufacturing facilities.
The infrastructure construction sector is projected to grow by 5.8% in real terms in 2026, before averaging 4.3% annual growth from 2027 to 2030, supported by the government’s focus on improving regional connectivity through road and rail development.
https://image.digitalinsightresearch.in/uploads/NewsArticle/16700367/main.png -
Saudi Arabia extends bid deadline for solar projects6 May 2026

Saudi Arabia’s principal buyer, Saudi Power Procurement Company (SPPC), has extended the deadline for developers bidding for four solar projects under the seventh round of the National Renewable Energy Programme (NREP).
Round seven of the NREP comprises solar photovoltaic (PV) and wind independent power producer (IPP) projects with a combined capacity of 5,300MW. The renewables programme is being led and supervised by the Ministry of Energy.
The four solar PV projects comprise:
- 1,400MW Tabjal 2 solar PV IPP (Tabrijal, Al-Jouf province)
- 600MW Mawqqaq solar PV IPP (Mawqqaq, Hail province)
- 600MW Tathleeth solar PV IPP (Tathleeth, Aseer province)
- 500MW South Al-Ula solar PV IPP (Al-Ula, Medina province)
The projects were tendered in January, with an initial bid submission deadline of 30 April.
The new deadline is 30 June.
The solar projects are the latest in a string of large-scale power and water developments across the region to have bidding extended in recent weeks.
In the UAE, the bid deadline for the seventh phase of Dubai Electricity & Water Authority’s Mohammed Bin Rashid Al-Maktoum Solar Park was recently pushed back to 1 July.
Bids for the 1,300MW Bilgah and 900MW Shagra wind IPPs are currently still due by 14 May, according to a source.
In January, MEED reported that 16 developers qualified to bid as both managing and technical members for the four solar PV projects under the seventh round of the NREP.
These include:
- Abu Dhabi Future Energy Company (Masdar)
- Alfanar Company (Saudi Arabia)
- Al-Gihaz Holding Company (Saudi Arabia)
- EDF Power Solutions (France)
- Kahrabel (Engie) (UAE / France)
- Sembcorp Utilities (Singapore)
- Jinko Power (HK) (China)
- TotalEnergies Renewables (France)
- Al-Jomaih Energy & Water (Saudi Arabia)
- Korea Electric Power Corporation (Kepco) (South Korea)
- Nesma Renewable Energy (Saudi Arabia)
- Korea Western Power (South Korea)
- Marubeni Corporation (Japan)
- SPIC Shanghai Electric Power (China)
- WahajPeak Holdings (Saudi Arabia)
- FAS Energy for Trading Company (Saudi Arabia)
A further six companies qualified to bid as a managing member only for the solar PV projects. These include:
- Saudi Electricity Company (Saudi Arabia)
- Grupo Empresarial Enhol (Spain)
- Power Construction Corporation of China (Power China) (China)
- GD Power Development (China)
- Gulf Development Public Company (Thailand)
- Reliance NU Energies Private (India)
The renewable energy programme aims to supply 50% of the kingdom’s electricity from renewable energy by 2030.
Earlier rounds under the NREP have already put in place large capacities. Last October, SPPC awarded contracts to develop and operate five renewable energy projects under round six of the NREP.
These comprise four solar PV IPP projects and one wind IPP project with a total combined capacity of 4,500MW.
READ THE MAY 2026 MEED BUSINESS REVIEW – click here to view PDFGlobal energy sector forced to recalibrate; Conflict hits debt issuance and listings activity; UAE’s non-oil sector faces unclear recovery period amid disruption.
Distributed to senior decision-makers in the region and around the world, the May 2026 edition of MEED Business Review includes:
> REGIONAL LNG: War undermines business case for Middle East LNG> CAPITAL MARKETS: Damage avoidance frames debt issuance> MARKET FOCUS: Conflict tests UAE diversificationTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/16700361/main.jpg
