Warming erodes Kuwait’s power and water reserves

14 August 2023

More on Kuwait’s power and water sector: 

> IWPP: Firms respond to Kuwait independent utilities request
> POWERLocal firm wins 250MW Subiya package
> PRIVATISATIONKuwait thermal plant privatisation to go ahead


 

The temperature in Kuwait soared to 51 degrees Celsius on 1 August, sending its electricity load index up to 16,940MW. This breached its maximum expected load this year of 16,830MW by 0.7 per cent.

This year’s projected maximum load is already 4 per cent higher than the previous year's recorded maximum load. It leaves only roughly 8 per cent of reserve capacity against an available capacity understood to stand at 18,250MW.

Similarly, water consumption across the Gulf state on 2 August, when the temperature decreased to 50 degrees, exceeded production by 29 million gallons, prompting the state utility to access its strategic water reserve capacity to plug the shortfall.

The electricity consumption spike reportedly caused two feeders at the country’s main substation south of Surra in the capital to trip, which led to power outages in some parts of Zahra, a district in Kuwait’s Hawalli governorate.

Kuwait’s Electricity & Renewable Energy Ministry (MEWRE) assured the public that the maximum capacity available in the country’s electricity network during the current summer is 18,250MW, as earlier cited, and that it could safely provide up to 17,660MW.

Persistent delays

The following week MEWRE – through the Kuwait Authority for Partnership Projects (Kapp) – received prequalification applications for the contracts to develop Kuwait’s next two independent water and power producer (IWPP) projects.

The two schemes – Al-Zour North 2 & 3 and Al-Khiran 1 – will have a total combined power generation capacity of 4,500MW and a water desalination capacity of over 150 million imperial gallons a day (MIGD), which will go a long way to address Kuwait’s precarious electricity and water supply situation.

Ironically, these two schemes have been in the planning and early procurement stages since 2017 and have suffered significant delays in the intervening period.

It is the second time developers have submitted statements of qualification (SOQs) for the contracts over the preceding 11 months.

The delays have caused major frustration for some developers and contractors. One utility developer that submitted an SOQ in September last year told MEED they did not participate in the latest attempt to start the prequalification process for the IWPP schemes, without elaborating.

Others expect the country’s stakeholders to eventually approve and expedite the procurement process for the integrated power and desalination facilities.

“I’m not very optimistic, but we submitted an SOQ anyway,” another source tells MEED.

EPC projects motoring ahead

The ministry’s conventional power plant projects have been moving at a relatively faster pace. In June this year, the local company Heavy Engineering Industries & Shipbuilding (Heisco) won a contract for the phase 2 upgrade of the Subiya power plant complex in Kuwait.

Heisco saw off competition from two local companies, Alghanim International and Al-Zain United General Trading & Contracting, for the KD114.28m ($372m) contract.

The project aims to convert an existing 250MW simple-cycle plant into a combined-cycle gas-turbine plant.

In April, a consortium comprising Heisco and Japan’s Mitsubishi Power was also awarded a contract to retrofit the main thermal power generation plant at the power complex.

The contract is understood to be valued at KD90.9m. It entails the upgrade of eight steam turbines and electric generators at the Subiya power plant, which is expected to reach a capacity of 2,400MW once the project is complete.

The existing plant at the Subiya power complex was commissioned between 1998 and 2002. This implies that the steam turbines and generators in commercial operation for nearly 20 years require upgrades to continue operating and improve their performance.

Two steps forward

While the country has pledged to become carbon neutral by 2060, the state utility has yet to make any remarkable progress in procuring new renewable energy capacity.

The recent political deadlock has hampered the procurement of the next phases of the Shagaya Renewable Energy Programme (SREP), despite the award 12 months previously of the project’s transaction advisory contract to a team led by London-headquartered consultancy firm EY.

At the time, the advisory contract was understood to cover the Al-Dibdibah solar project, which will comprise SREP’s second phase, and a third phase expected to include a 720MW solar photovoltaic (PV) plant, a 1,150MW concentrated solar power (CSP) facility and a wind power farm.

Notably, two state-backed downstream operators – Kuwait National Petroleum Company and Kuwait Integrated Petroleum Industries Company (Kipic) – have launched a tender for a contract to undertake a pre-feasibility study identifying opportunities to use renewable energy in their operations.

Kuwait is also expected to make some progress on its first utility privatisation scheme, which forms part of the initiative to strengthen private sector participation in the sector.

In December last year, it was revealed that UK-headquartered Deloitte had submitted a low bid of KD1.2m ($3.9m) for the transaction advisory contract in line with the planned privatisation of the $1.26bn North Shuaiba power and water plant in Kuwait.

GCC grid

While working to boost its electricity reserves and make its electricity systems greener, Kuwait stands to benefit from the ongoing upgrade of the GCC electricity grid, through which other GCC states, such as the UAE, may decide to transmit excess clean energy.

The Al-Fadhili high-voltage direct current (HVDC) converter station upgrade in Saudi Arabia is expected to enable the exchange of 1,800MW of electricity between the six states once complete.

In October last year, the GCC Interconnection Authority (GCCIA) awarded India-based KEC International a contract for an overhead transmission line project linking the substations in Wafra in Kuwait and Fadhili in Saudi Arabia.

The estimated $120m project extends an existing double-circuit 400kV line from Al-Zour in Kuwait to Ghunan in Saudi Arabia. The line has an intermediate interconnection at Fadhili, with associated substations completed in 2009 as part of the first phase of the GCCIA network. The new project is expected to complete in 2025.


This month’s special report on Kuwait also includes: 

> ECONOMYStakeholders hope Kuwait can execute spending plans
> ENERGYKuwait’s $300bn energy target is a big test
> BANKINGKuwaiti banks enter bounce-back mode
> INTERVIEWKuwait’s Gulf Centre United sets course for expansion

https://image.digitalinsightresearch.in/uploads/NewsArticle/11069881/main.gif
Jennifer Aguinaldo
Related Articles
  • Egypt signs $420m Gabal El-Zeit wind agreements

    10 June 2026

    Egypt has signed agreements worth $420m for the investment, operation and power purchase of the 580MW Gabal El-Zeit wind power complex in the Red Sea region.

    Gabal El-Zeit 1 has a capacity of 240MW, while Gabal El-Zeit 2 and 3 have capacities of 220MW and 120MW, respectively.

    The agreements were signed between Egypt’s New and Renewable Energy Authority (NREA), the Egyptian Electricity Transmission Company (EETC) and Dubai-based Alcazar Energy.

    Under the agreements, Alcazar Energy will invest in, operate and manage the farms through a project company established under Egyptian law.

    The company will be responsible for technical operations, maintenance and efficiency upgrades while maintaining a minimum capacity of 580MW throughout the contract period.

    The Egyptian Electricity Transmission Company will purchase the electricity generated by the plant.

    The agreements follow earlier efforts to privatise the Gabal El-Zeit wind complex, involving a deal with UK-headquartered private equity firm Actis.

    According to the Egyptian government, the project supports the country’s state ownership policy and national energy strategy, which aim to increase the share of renewable energy in the electricity mix to 45%.

    The Gabal El-Zeit area on Egypt’s Red Sea coast is one of the country’s most established wind power development zones. The latest Gabal El-Zeit wind farm was completed in 2014, according to MEED Projects data. Germany’s Siemens Gamesa was the main contractor. 


    > Be recognised among the best in the industry at the MEED Projects Awards 2026 …

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17170360/main.jpg
    Mark Dowdall
  • Majid Al-Futtaim awards $545m Ghaf Woods contract to ECC

    10 June 2026

    Majid Al-Futtaim Properties has appointed Engineering Contracting Company (ECC) as the main contractor for the Capria East, Capria West and Maravelle Residences developments at its Ghaf Woods community in Dubai, in a deal valued at AED2bn ($545m).

    The contract covers the construction of one-, two- and three-bedroom apartments and duplex residences across the two Capria clusters.

    The award adds to a series of major construction contracts Majid Al-Futtaim has issued across its Dubai communities in recent years.

    In May, local contractor Al-Sahel Contracting was awarded a AED700m contract for the Distrikt development, also at Ghaf Woods.

    In 2024, Majid Al-Futtaim awarded AED3bn in contracts for its Tilal Al-Ghaf community, appointing Innovo Build to build 94 waterfront villas at Elysian Mansions and United Engineering Construction (Unec) to deliver 130 villas at the Alaya development.


    > Be recognised among the best in the industry at the MEED Projects Awards 2026 …

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17170744/main.jpg
    Colin Foreman
  • Saudi Arabia and Turkiye sign railway agreements

    10 June 2026

    Register for MEED’s 14-day trial access 

    Saudi Arabia and Turkiye have signed two memorandums of understanding (MoUs) to strengthen bilateral cooperation in the railway and logistics sectors, advancing Riyadh’s ambitions to become a global logistics hub.

    Transport and Logistics Services Minister Saleh Al-Jasser and Turkish Transport and Infrastructure Minister Abdulkadir Uraloglu signed the agreements at the ministry’s headquarters in Riyadh on 9 June, following ministerial talks held with a high-level Turkish delegation. Transport General Authority president Fawaz Al-Sahli and officials from the kingdom’s transport and logistics sector were also present.

    Agreement scope

    The first MoU covers logistics services and operations, including the exchange of expertise, policies and regulations. The second focuses on railway technologies, signalling and communication systems, railway digitalisation, human capacity development, the localisation of the railway industry and measures to reduce the sector’s environmental impact.

    More broadly, the agreements cover cooperation on railway standards and related innovations, the exchange of expertise on the design, operation and maintenance of rail projects, and engineering, infrastructure and safety standards.

    The two sides will also cooperate on research and development, with provision for joint workforce training through specialist railway academies.

    Riyadh said the agreements will help support its National Strategy for Transport and Logistics Services and Saudi Vision 2030, which seeks to position the kingdom as a logistics bridge connecting three continents.

    Turkish projects

    Turkish contractors have already established themselves as key players in the region’s rail sector. In 2012, Yapi Merkezi secured a $2.1bn contract for work on the Haramain high-speed rail network in Saudi Arabia, while Turkish firms Mapa and Limak are leading the ongoing civil works on Dubai’s $5.5bn Metro Blue Line project as part of a China Railway Rolling Stock Corporation (CRRC) consortium. Turkish consultancy Proyapi Muhendislik ve Musavirlik Anonim Sirketi has also won design contracts for the 111km Kuwait National Rail Road project.

    The agreements signed by Saudi Arabia and Turkiye may also give momentum to longstanding discussions around a rail corridor linking the GCC with Turkiye. The route, which has been discussed for years, has gained renewed impetus in recent months as the effective closure of the Strait of Hormuz has pushed regional governments to accelerate the development of overland trade alternatives.


    READ THE JUNE 2026 MEED BUSINESS REVIEW – click here to view PDF

    GCC looks beyond the Strait; Iraq’s reform window narrows as fiscal assumptions shatter; MEED Top 100 companies.

    Distributed to senior decision-makers in the region and around the world, the June 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/17169958/main.gif
    Colin Foreman
  • Joint venture tenders Algeria field development contract

    10 June 2026

     

    Register for MEED’s 14-day trial access 

    Hassi Bir Rekaiz Group (GHBR), which operates Algeria’s Hassi Bir Rekaiz field, has issued a tender for phase 2A of the asset’s field development project.

    GHBR is a joint venture of Algeria’s national oil and gas company Sonatrach and Thailand’s national exploration and production company PTTEP.

    The scope of the contract focuses on the “provision of engineering and supervision services”, according to documents published by Sonatrach.

    The tender has been issued with a bid deadline of 16 June 2026.

    In May, GHBR signed a $1.1bn contract for phase two of the Hassi Bir Rekaiz development project.

    The contract was won by a consortium of Egypt’s Petrojet and Italian engineering and contracting company Arkad.

    Petrojet’s portion of the project was estimated to be worth around $600m, and Arkad’s portion was estimated to be worth $500m.

    The contract used the engineering, procurement, construction and commissioning model.

    The scope of the project contract is focused on the construction of a central processing facility (CPF) capable of processing crude oil and associated gas.

    It also includes developing off-plot pipelines, as well as related utilities and infrastructure.

    The CPF will have the capacity to process 32,000 barrels a day (b/d) and will be designed to support future expansions.

    The related infrastructure will include an extensive pipeline network spanning approximately 217 kilometres, as well as a road network.


    READ THE JUNE 2026 MEED BUSINESS REVIEW – click here to view PDF

    GCC looks beyond the Strait; Iraq’s reform window narrows as fiscal assumptions shatter; MEED Top 100 companies.

    Distributed to senior decision-makers in the region and around the world, the June 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/17163750/main3325.jpg
    Wil Crisp
  • Algeria extends deadline for urea-formaldehyde project

    10 June 2026

     

    Algeria’s national oil and gas company Sonatrach has extended the bid deadline for a project to develop a new concentrated urea-formaldehyde unit in its Arzew industrial zone.

    The latest bid deadline is 15 June.  

    The contract uses the engineering, procurement, construction and commissioning model, and the bid deadline for technical tender submissions was originally set for early April.

    The condensed urea-formaldehyde unit will be located at the CP1-Z facility.

    The CP1-Z facility began operations in 1975 and has a capacity of 152,000 tonnes a year. It produces products including methanol, resin and formol.

    It is a two-phase tender. The first phase is a technical bid submission, and the second phase is a commercial bid submission.

    To be eligible to win this contract, companies must specialise in petrochemical industrial installation projects.

    They also need to have a share capital of at least $7m and more than 15 years of relevant experience.

    The new unit, UFC85, will have the capacity to produce 40,000 metric tonnes of concentrated and condensed urea-formaldehyde annually.

    The project’s scope also includes the development of auxiliary equipment and installations.

    Urea-formaldehyde has a wide range of uses, including the production of laminates, textiles and paper.

    In the wood industry, it is used as a thermosetting adhesive to bond wood to create plywood and particleboard. In agriculture, urea-formaldehyde is widely used as a slow-release fertiliser.


    READ THE JUNE 2026 MEED BUSINESS REVIEW – click here to view PDF

    GCC looks beyond the Strait; Iraq’s reform window narrows as fiscal assumptions shatter; MEED Top 100 companies.

    Distributed to senior decision-makers in the region and around the world, the June 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/17163657/main.jpg
    Wil Crisp