Warming erodes Kuwait’s power and water reserves

14 August 2023

More on Kuwait’s power and water sector: 

> IWPP: Firms respond to Kuwait independent utilities request
> POWERLocal firm wins 250MW Subiya package
> PRIVATISATIONKuwait thermal plant privatisation to go ahead


 

The temperature in Kuwait soared to 51 degrees Celsius on 1 August, sending its electricity load index up to 16,940MW. This breached its maximum expected load this year of 16,830MW by 0.7 per cent.

This year’s projected maximum load is already 4 per cent higher than the previous year's recorded maximum load. It leaves only roughly 8 per cent of reserve capacity against an available capacity understood to stand at 18,250MW.

Similarly, water consumption across the Gulf state on 2 August, when the temperature decreased to 50 degrees, exceeded production by 29 million gallons, prompting the state utility to access its strategic water reserve capacity to plug the shortfall.

The electricity consumption spike reportedly caused two feeders at the country’s main substation south of Surra in the capital to trip, which led to power outages in some parts of Zahra, a district in Kuwait’s Hawalli governorate.

Kuwait’s Electricity & Renewable Energy Ministry (MEWRE) assured the public that the maximum capacity available in the country’s electricity network during the current summer is 18,250MW, as earlier cited, and that it could safely provide up to 17,660MW.

Persistent delays

The following week MEWRE – through the Kuwait Authority for Partnership Projects (Kapp) – received prequalification applications for the contracts to develop Kuwait’s next two independent water and power producer (IWPP) projects.

The two schemes – Al-Zour North 2 & 3 and Al-Khiran 1 – will have a total combined power generation capacity of 4,500MW and a water desalination capacity of over 150 million imperial gallons a day (MIGD), which will go a long way to address Kuwait’s precarious electricity and water supply situation.

Ironically, these two schemes have been in the planning and early procurement stages since 2017 and have suffered significant delays in the intervening period.

It is the second time developers have submitted statements of qualification (SOQs) for the contracts over the preceding 11 months.

The delays have caused major frustration for some developers and contractors. One utility developer that submitted an SOQ in September last year told MEED they did not participate in the latest attempt to start the prequalification process for the IWPP schemes, without elaborating.

Others expect the country’s stakeholders to eventually approve and expedite the procurement process for the integrated power and desalination facilities.

“I’m not very optimistic, but we submitted an SOQ anyway,” another source tells MEED.

EPC projects motoring ahead

The ministry’s conventional power plant projects have been moving at a relatively faster pace. In June this year, the local company Heavy Engineering Industries & Shipbuilding (Heisco) won a contract for the phase 2 upgrade of the Subiya power plant complex in Kuwait.

Heisco saw off competition from two local companies, Alghanim International and Al-Zain United General Trading & Contracting, for the KD114.28m ($372m) contract.

The project aims to convert an existing 250MW simple-cycle plant into a combined-cycle gas-turbine plant.

In April, a consortium comprising Heisco and Japan’s Mitsubishi Power was also awarded a contract to retrofit the main thermal power generation plant at the power complex.

The contract is understood to be valued at KD90.9m. It entails the upgrade of eight steam turbines and electric generators at the Subiya power plant, which is expected to reach a capacity of 2,400MW once the project is complete.

The existing plant at the Subiya power complex was commissioned between 1998 and 2002. This implies that the steam turbines and generators in commercial operation for nearly 20 years require upgrades to continue operating and improve their performance.

Two steps forward

While the country has pledged to become carbon neutral by 2060, the state utility has yet to make any remarkable progress in procuring new renewable energy capacity.

The recent political deadlock has hampered the procurement of the next phases of the Shagaya Renewable Energy Programme (SREP), despite the award 12 months previously of the project’s transaction advisory contract to a team led by London-headquartered consultancy firm EY.

At the time, the advisory contract was understood to cover the Al-Dibdibah solar project, which will comprise SREP’s second phase, and a third phase expected to include a 720MW solar photovoltaic (PV) plant, a 1,150MW concentrated solar power (CSP) facility and a wind power farm.

Notably, two state-backed downstream operators – Kuwait National Petroleum Company and Kuwait Integrated Petroleum Industries Company (Kipic) – have launched a tender for a contract to undertake a pre-feasibility study identifying opportunities to use renewable energy in their operations.

Kuwait is also expected to make some progress on its first utility privatisation scheme, which forms part of the initiative to strengthen private sector participation in the sector.

In December last year, it was revealed that UK-headquartered Deloitte had submitted a low bid of KD1.2m ($3.9m) for the transaction advisory contract in line with the planned privatisation of the $1.26bn North Shuaiba power and water plant in Kuwait.

GCC grid

While working to boost its electricity reserves and make its electricity systems greener, Kuwait stands to benefit from the ongoing upgrade of the GCC electricity grid, through which other GCC states, such as the UAE, may decide to transmit excess clean energy.

The Al-Fadhili high-voltage direct current (HVDC) converter station upgrade in Saudi Arabia is expected to enable the exchange of 1,800MW of electricity between the six states once complete.

In October last year, the GCC Interconnection Authority (GCCIA) awarded India-based KEC International a contract for an overhead transmission line project linking the substations in Wafra in Kuwait and Fadhili in Saudi Arabia.

The estimated $120m project extends an existing double-circuit 400kV line from Al-Zour in Kuwait to Ghunan in Saudi Arabia. The line has an intermediate interconnection at Fadhili, with associated substations completed in 2009 as part of the first phase of the GCCIA network. The new project is expected to complete in 2025.


This month’s special report on Kuwait also includes: 

> ECONOMYStakeholders hope Kuwait can execute spending plans
> ENERGYKuwait’s $300bn energy target is a big test
> BANKINGKuwaiti banks enter bounce-back mode
> INTERVIEWKuwait’s Gulf Centre United sets course for expansion

https://image.digitalinsightresearch.in/uploads/NewsArticle/11069881/main.gif
Jennifer Aguinaldo
Related Articles
  • Dubai scales up its metro ambitions

    23 April 2026

     

    Dubai’s rail sector has rarely seen such a concentrated burst of procurement activity as it has in the past year.

    Within the space of a few months, Dubai’s Roads & Transport Authority (RTA) has moved simultaneously on three distinct fronts: tendering design consultancy for the Route 2020 extension that will connect the Expo 2020 metro station to Al-Maktoum International airport; inviting study-and-design bids for a 55-kilometre Airport Express Line linking Dubai International airport to Al-Maktoum International airport; and culminating in Dubai Ruler Sheikh Mohammed Bin Rashid Al-Maktoum’s approval of the AED34bn ($9.2bn) Gold Line, a 42km fully underground route that the emirate is calling the largest transportation project in its history.

    These projects form a key part of the Dubai Rail Network Plan 2032, which outlines the development of six public transportation schemes comprising a mix of metro, passenger and high-speed rail lines.

    The most prominent feature of the plan is the addition of new lines to Dubai Metro’s existing network, representing a systematic effort to support the shift of Dubai’s economic centre of gravity towards Dubai South and the vast development corridors in between.

    The city is also seeking to stay ahead of the curve by investing heavily in infrastructure. Data from regional projects tracker MEED Projects shows that the emirate has awarded over $14bn-worth of transport projects in the past two years alone, with several other multibillion-dollar schemes still moving through the planning stages.

    All of this work is being carried out in line with the Dubai 2040 Urban Master Plan, which forecasts the emirate’s population will reach 5.8 million by 2040 – a clear indication of the scale of daily movement the city must accommodate.

    Project progress

    Dubai Metro Gold Line

    On 21 April, Sheikh Mohammed officially announced the launch of the new AED34bn ($9.2bn) Gold Line project.

    The line will be a fully underground network spanning over 42 kilometres, with 18 stations.

    It will run from Al-Ghubaiba in Bur Dubai to Jumeirah Golf Estates.

    The Gold Line will connect with Dubai Metro’s existing Red and Green lines and integrate with the Etihad Rail passenger network.

    In October last year, MEED exclusively reported that the RTA had selected US-based engineering firm Aecom to provide consultancy services for the project.

    Stage one covers concept design; stage two, preliminary design; stage three, preparation of tender documents; stage four, construction supervision; and stage five, the defects liability period.

    Airport Express Line

    Procurement has started for another metro line extending from Dubai International airport (DXB) in Al-Garhoud to Al-Maktoum International airport (DWC) in Jebel Ali.

    Earlier this month, the RTA invited consultants to bid for a contract to study and design what is referred to as the Airport Express Line.

    The proposed line will stretch about 55km and include five stations that will provide passengers with facilities such as remote airline check-in, baggage drop-off and security screening.

    The new line will run from the Red Line metro station at DXB through Al-Jaddaf, along Al-Khail Road to a new station at Jumeirah Village Circle (JVC), before continuing on to DWC.

    There will be two spur lines. The first will run from the new JVC station to Al-Fardan Exchange metro station at Emirates Golf Club, while the second will branch toward Business Bay, where another station will be built.

    Expo 2020 route extension

    Dubai is also undertaking the Route 2020 extension of its metro system, which will start from the Expo 2020 metro station and connect with Al-Maktoum International airport’s West Terminal.

    Consultants submitted their bids earlier this month for the design contract.

    The extension will run for about 3km and feature two stations.

    The existing Route 2020 metro link is a 15km line that branches off the Red Line at Jebel Ali metro station. The line comprises 11.8km of elevated tracks and 3.2km of tunnels, and has five elevated stations and two underground stations.

    Dubai Metro Blue Line extension

    Construction progress on the Dubai Metro Blue Line extension is expected to reach 30% by the end of 2026, according to official accounts.

    In December 2024, the RTA awarded a AED20.5bn ($5.5bn) main contract for the construction of the project.

    The contract was awarded to a consortium of Turkiye’s Limak Holding, Mapa Group, also of Turkiye, and the Hong Kong office of China Railway Rolling Stock Corporation (CRRC).

    The Blue Line will connect the existing Red and Green lines. It will be 30km long, with 15.5km underground and 14.5km above ground.

    The line will have 14 stations, seven of which will be elevated. There will be five underground stations, including one interchange station, and two elevated transfer stations connected to the existing Centrepoint and Creek stations.

    The project is scheduled for completion in September 2029.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16534887/main.png
    Yasir Iqbal
  • Sports Boulevard tenders Wadi Hanifa road works

    23 April 2026

     

    Register for MEED’s 14-day trial access 

    Saudi Arabia’s Sports Boulevard Foundation has issued a tender inviting firms to bid for a contract to build a road and associated infrastructure in the Wadi Hanifa area of Riyadh.

    The bid submission deadline is 27 April.

    The scope includes construction of an 11.4-kilometre road and associated infrastructure, including public realm works, utilities and security systems.

    The scheme is the latest package to progress on Riyadh’s Sports Boulevard project.

    The Sports Boulevard Foundation is also evaluating bids for its Global Sports Tower in the development’s Athletics District.

    The 130-metre-tall Global Sports Tower will have a gross floor area of 84,000 square metres (sq m) and will include more than 30 sports facilities. The tower will feature what is billed as the world’s tallest indoor climbing wall, at 98 metres, and a 250-metre running track.

    Sports Boulevard will run across Riyadh from east to west. Once complete, it is intended to be the world’s longest park, stretching more than 135 kilometres.

    The project is divided into multiple districts, including the Wadi Hanifah, Arts, Urban Wadi, Entertainment, Athletics and Eco districts, as well as Sands Sports Park.

    The large-scale development aims to transform central Riyadh – currently dominated by major highways – into a recreational corridor.

    Sports Boulevard will include 4.4 million sq m of public realm and landmark buildings. Along with the Global Sports Tower, there will be a Centre for Cinematic Arts and a 2,000-seat amphitheatre.

    It will also deliver more than 2.3 million sq m of mixed-use commercial, residential and retail space, alongside sports facilities, around the park, known as the Linear Park.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16534345/main.jpg
    Yasir Iqbal
  • Masdar to develop renewables projects in Montenegro

    23 April 2026

    Abu Dhabi Future Energy Company (Masdar) and Elektroprivreda Crne Gore (EPCG) have agreed to establish a 50:50 joint venture to develop and operate renewable energy projects in Montenegro.

    The planned projects include solar photovoltaic (PV), wind, hydropower, pumped-hydro storage and battery energy storage systems.

    The joint venture will be headquartered in Niksic in western Montenegro and is intended to support Montenegro’s domestic energy needs while also enabling the export of renewable electricity to the Western Balkans and Southern Europe, Masdar said in a statement.

    The companies plan to leverage an existing sub-sea interconnection with Italy. Montenegro is connected to Italy via a 600MW HVDC submarine cable, enabling electricity exports to the Italian market.

    Masdar has an existing presence in Montenegro through its investment in the 72MW Krnovo wind farm.

    The developer has recently accelerated foreign investment plans as part of its broader expansion. In April, it signed a binding agreement with France’s TotalEnergies to establish a $2.2bn joint venture to develop, build and operate renewable energy projects across Asia.

    The combined business will have 3GW of operational capacity and 6GW of projects in advanced development, targeted for commissioning by 2030.

    Masdar is targeting a global renewable energy portfolio of 100GW by 2030. It recently reached 65GW, two-thirds of the way to that target.

    The company plans to deploy an additional $30bn-$35bn in equity and project finance by 2030, adding an average of 10GW of new capacity each year.

    This expansion will be funded through a mix of equity, green bonds and long-term project financing.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16534112/main.jpg
    Mark Dowdall
  • Qiddiya sets new deadline for infrastructure package

    23 April 2026

     

    Saudi gigaproject developer Qiddiya Investment Company (QIC) has set a 13 May deadline for bids for a contract covering new infrastructure works at Qiddiya Entertainment City.

    The scope comprises two infrastructure development packages for District 0 of Qiddiya Entertainment City, including the construction of four event park-and-ride facilities.

    The tender was issued on 11 March, with an initial bid submission deadline of 22 April.

    Lebanese firm Dar Al-Handasah and Saudi-based Sets International are serving as project consultants.

    QIC is accelerating plans to develop additional assets at Qiddiya City. Earlier this month, the company received prequalification statements from firms for the engineering, procurement, construction and finance package for the Qiddiya high-speed rail project.

    MEED has also reported that QIC received bids from contractors on 23 February for a SR980m ($261m) contract covering the construction of staff accommodation at Qiddiya Entertainment City.

    The project will cover an area of more than 105,000 square metres (sq m).

    Also in February, QIC started the main construction works on its performing arts centre at the entertainment hub.

    The Qiddiya City performing arts centre is one of several major projects within the greater Qiddiya development. Other projects include an e-games arena, Prince Mohammed Bin Salman Stadium, a motorsports track, the Dragon Ball and Six Flags theme parks, and Aquarabia.

    QIC officially opened the Six Flags theme park to the public in December last year.

    The park covers 320,000 sq m and features 28 rides and attractions, including 10 thrill rides and 18 aimed at families and young children.

    The Qiddiya project is a key part of Riyadh’s strategy to boost leisure tourism in the kingdom. According to UK analytics firm GlobalData, leisure tourism in Saudi Arabia has experienced significant growth in recent years.

    Saudi Arabia’s tourism sector posted record figures last year, with more than 130 million domestic and international visitors – a 6% increase on 2024.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16533776/main.jpg
    Yasir Iqbal
  • Detailed design progressing for major Iraqi oil project

    23 April 2026

     

    Detailed design work is progressing on Iraq’s 950-kilometre seawater pipeline network under the Common Seawater Supply Project (CSSP), according to industry sources.

    They added that on-site construction would begin only after the detailed design is complete.

    Iraq’s state-owned Basra Oil Company (BOC) and China Petroleum Pipeline Engineering (CPP) signed a $2.5bn contract for the pipeline package in September last year.

    The project is being supervised by Austria’s ILF Consulting Engineers.

    The pipeline package is one of two main CSSP packages.

    The second focuses on a seawater treatment facility, expected to have a capacity of 5 million barrels a day (b/d), potentially rising to 7-8 million b/d in later phases.

    Processed water will be injected into some of Iraq’s largest oil fields – Rumaila, Zubair, West Qurna 1, West Qurna 2 and Majnoon – and also used in the Maysan and Dhi Qar fields.

    Iraq’s Oil Ministry said the injected water will help maintain reservoir pressure and sustain crude production.

    CPP is a subsidiary of state-owned China National Petroleum Corporation.

    TotalEnergies is responsible for the CSSP as part of the larger $27bn Gas Growth Integrated Project.

    Iraq approved a $2.45bn contract with South Korea’s Hyundai Engineering & Construction (Hyundai E&C) in August last year for the engineering, procurement and construction of the seawater treatment plant.

    Over recent weeks, Iraq’s oil exports have collapsed by about 80% due to fallout from the US and Israel’s war with Iran.


    READ THE APRIL 2026 MEED BUSINESS REVIEW – click here to view PDF

    Economic shock threatens long-term outlook; Riyadh adjusts to fiscal and geopolitical risk; GCC contractor ranking reflects gigaprojects slowdown.

    Distributed to senior decision-makers in the region and around the world, the April 2026 edition of MEED Business Review includes:

    > GCC CONTRACTOR RANKING: Construction guard undergoes a shift
    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/16527404/main.jpg
    Wil Crisp