Region plans vital big grid connections

29 May 2023

 

The mantra “there will be no transition without transmission” dominated this year’s World Utility Congress, which was organised by Abu Dhabi National Energy Company (Taqa) and held in the UAE capital on 8-10 May.

“There will be no transition without interconnectivity with our neighbours. If we are not interconnected, we are not using the full capacity of our [electricity] network,” UAE Energy and Infrastructure Minister Suhail bin Mohamed al-Mazrouei said at the congress.

For the GCC states in particular, their ability to procure affordable and large-scale solar energy capacity, and the wide discrepancy in peak demands between the winter and summer months, which often results in substantial idle capacity, make it imperative to connect to other states or regions.

“Links to other GCC states and Central Asia will enable our electricity system to run more efficiently. Some have access to wind, others to solar or hydropower. We also have different peak hours,” Al-Mazrouei said. “We need to consider [these opportunities] and make the investments.”

Boosting transmission

In recent years, there has been a flurry of projects to build or enhance electricity transmission links within the GCC states, as well as with neighbouring countries such as Iraq and Jordan.

Contracts were awarded this year for the construction of overhead transmission lines connecting the GCC grid to Iraq via Kuwait, as well as a link between Iraq and Jordan.

Other projects in the early stages include a second connection between Saudi Arabia and Iraq, Saudi Arabia and the UAE, and the UAE and Oman.

Beyond the GCC, a $1.8bn electricity link between Saudi Arabia and Egypt is under construction. The project will facilitate the exchange of 3,000MW of electricity between the two countries through overhead transmission lines as well as high-voltage, direct current (HVDC) subsea cables.

The most ambitious plans include projects that will pipe electricity from Egypt, Tunisia and Morocco to European countries including Greece, Italy and the UK.

Some have access to wind, others to solar or hydropower. We also have different peak hours … we need to consider [these opportunities] and make the investments
UAE Energy and Infrastructure Minister 
Suhail bin Mohamed al-Mazrouie 

Shifting peaks

Energy security has spurred investments to interconnect electricity grids between national borders and time zones. The pace of development is reminiscent of the advent of data interconnectivity two decades earlier.

Grid interconnections are also critical for the integration and optimisation of renewable energy, according to Jessica Obeid, a partner at New Energy Consult.

“Grid interconnections enable efficient management and mitigations of stability challenges linked to the integration of variable renewable energy such as wind and solar into the grid,” she says.

These interconnections enable the deployment of renewable energy where land is vast and resources are abundant, to be dispatched in energy load centres.

More importantly, they reduce the curtailment of renewable energy systems through electricity exchange, balancing supply and demand at various periods.

UK startup Xlinks aims to connect Morocco to the UK via four HVDC subsea cables stretching 3,800 kilometres across the Atlantic. “Long distance interconnectors solve the intermittency of renewables as the sun is always shining or wind is always blowing elsewhere,” says Simon Morrish, Xlinks’ CEO. 

“The idea is to generate clean energy and then move it to meet demand, which is much more economic than relying solely on domestic capacity.”

Xlinks aims to generate 10.5GW through solar and wind farms in Guelmin Oued Noun and pipe about 40 per cent of that energy through subsea cables that will have to pass through Spain, Portugal and France. The UK will receive 3.6GW of clean, affordable energy – equivalent to 8 per cent of its electricity needs – by 2030.

Soaring data demand drives boom

Desertec’s long shadow

The scale of Xlinks’ ambition draws comparison with an earlier project, the Desertec Industrial Initiative (Dii), which launched in 2009, but ironically has yet to see the light of day.

Dii had planned to build renewable energy plants globally, including in Morocco, and supply up to 15 per cent of Europe’s power demand by 2050.

Xlinks’ proponents expect to succeed where Desertec failed, however. “Generation costs are more than 90 per cent lower than they were then, which makes the project economically – as well as politically – attractive,” Morrish says.

Xlinks’ point-to-point design with an exclusive energy supply for the UK is expected to eliminate challenges associated with trying to use third-party transmission networks.

Although the technologies are all mature, Morrish says iterations have led to a much lower levelised cost of transmission over these distances. There is also more expertise for the HVDC system beyond the original equipment manufacturers.

Average electricity prices in Europe have increased significantly over the past 10 years and power delivered from the Middle East and North Africa (Mena) region is competitive with other reliable low-carbon solutions, according to Morrish.

The existence of clear renewable targets in Europe could also benefit Xlinks’ project, as well as similar schemes, such as the EuroAfrica Interconnector, which aims to link Egypt to Cyprus and Greece, and the Elmed Mediterranean project that links Tunisia to Italy.

Morocco’s renewable energy leadership, which includes having implemented legislation designed to facilitate the export of renewable energy, is another positive factor.

“Previous projects have typically focused on the recipient jurisdiction, such as Europe, rather than understanding the drivers for the generation country,” says Morrish. “By focusing on the benefits to the Mena region, in this case Morocco, Xlinks has obtained support from both Morocco and the UK.”

The 13-year gap between Desertec and Xlinks has not necessarily changed the mindset of some industry players, who are just beginning to grasp the complexities involved in other decarbonisation technologies such as green hydrogen and carbon capture and storage.

“It is an excellent concept, but it will be exceptionally difficult, if not impossible, to execute given the high demand for HVDC cables, financing and political considerations,” says a Dubai-based contractor.

Unlike the more reasonably- structured interconnections between the GCC or Mena states, the scale and scope of Xlinks’ scheme and other similar projects will require export credit and multilateral development agency support in combination with project finance debt. Experts say this is critical, but not entirely unprecedented.

For instance, Taqa’s decision to contribute $31m in the startup’s early funding round, which also includes $6.2m from UK-headquartered Octopus Energy, appears to signify investor appetite for the project. The scheme is expected to boost foreign direct investment and create thousands of jobs in Morocco during its construction phase.

Electricity demand is increasing at alarming rates, in direct relation to the impact of climate change and the increases in temperatures, cooling and water demand, which reduces the available supply for exports
Jessica Obeid, New Energy Consult

Political undertones

In December 2022, Saudi Investment Minister Khalid al-Falih said the kingdom is keen to join an agreement between four countries to export clean electricity from Azerbaijan to Europe.

He was referring to an accord signed by Azerbaijan, Georgia, Romania and Hungary to build an undersea cable in the Black Sea transmitting energy from Caspian Sea wind farms to Europe.

The agreement involves a 1,100-kilometre, 1GW cable running from Azerbaijan to Romania. It is part of broader EU efforts to diversify energy resources away from Russia amid the Ukraine war.

This provides an alternative to Saudi Arabia’s grid expansion plans, and to the Saudi-Egypt link, as Egypt itself is involved in negotiations to link its electricity grid to Italy, Cyprus and Greece.

Beyond financing, there are other challenges for both intra-Mena and intercontinental grid connections.

An efficient electricity exchange market is necessary, notes Obeid. Another key issue is the unsustainable increase in demand in Mena states. 

Figure1: Saudi-Egypt interconnector route

“Electricity demand is rising alarmingly, in direct relation to the impact of climate change and the increases in temperatures, cooling and water demand, which reduces the available supply for exports,” she says.

Plans to interconnect with Iraq, which has been heavily reliant on Iran for energy imports, can also be tricky. “The incentive is mostly political. Many countries have expressed interest in connecting their grids to Iraq’s, but none of these projects have yet materialised,” says Obeid.

“Linking Iraq to the Saudi grid is bound to be more viable and cheaper for Iraq compared to alternative options such as electricity exports from Jordan. But that is pending a political decision and would get Saudi Arabia and the GCC political and economic influence in Iraq.” 

https://image.digitalinsightresearch.in/uploads/NewsArticle/10842129/main.gif
Jennifer Aguinaldo
Related Articles
  • Saudi Arabia battery storage awards provide fresh lift

    24 August 2026

    Commentary
    Mark Dowdall
    Power & water editor

    The latest battery storage awards provide a welcome injection of investment into Saudi Arabia’s power market, which has seen a sharp slowdown in contract awards this year.

    Saudi Power Procurement Company’s four Group 1 storage service agreements, announced last week, are worth more than $1.16bn and cover 2,000MW of capacity.

    That is significant against the wider market. According to regional project tracker MEED Projects, Saudi Arabia recorded $19.7bn in power sector contract awards in the first seven months of 2025, compared with just $2.5bn in new awards in the same period this year.

    The battery energy storage system (bess) awards therefore account for a sizeable share of the activity recorded so far this year and provide a much-needed source of new contracting activity.

    Importantly, this is not a one-off. SPPC issued the request for proposal (RFP) for its second group of bess projects in July, covering six projects with a combined capacity of 3,000MW and 12,000MWh.

    With the Group 1 tender taking around 18 months from RFP to contract award, it is reasonable to expect Group 2 contracts to be signed in 2027.

    At the same time, the awards for six independent renewable plants under Round 7 of Saudi Arabia’s National Renewable Energy Programme (NREP), with a combined capacity of 5,300MW, are also likely to move into next year, with the latest bid deadlines now extending into September.

    Although a substantial pipeline remains in procurement, it is only once these projects move from tender to award and into construction that this pipeline translates into market activity.

    It is important that these tenders continue to progress at the pace established by the early rounds of Saudi Arabia’s renewable energy programme and now also SPPC’s independent storage provider bess scheme.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/18962923/main.jpg
    Mark Dowdall
  • Qatar receives bids for major power grid expansion

    24 August 2026

     

    Qatar General Electricity & Water Corporation (Kahramaa) has received bids for several packages under a major power transmission expansion project tendered in April.

    The project covers new substations at multiple voltage levels, as well as the supply and installation of 400kV extra-high-voltage power cables. The overall scheme is estimated to cost $650m.

    It is being tendered as part of Kahramaa’s 2026 procurement plan, which includes 198 tenders with a total estimated value of QR21.4bn ($5.9bn).

    According to sources, bids were submitted for the following packages on 20 August:

    • Substation packages S1 and S2, covering new 132/11kV substations (estimated cost: $200m)
    • Package S3, covering new 66/11kV substations ($50m)
    • Package S4, including a new 400/220/132kV substation, as well as upgrades and modifications to existing 400kV and 220kV substations ($200m)
    • Package S5, covering new 132/11kV substations and upgrades to existing 132kV and 66kV substations ($100m)
    • Cable packages C1 and C2, covering 400kV cables ($100m)

    Kahramaa previously stated that foreign companies not registered in Qatar would be allowed to participate in the bidding, subject to meeting specified conditions, including registration and certification requirements.

    In June, the electricity and water utility awarded contracts worth more than QR2.2bn ($604m) to expand the electricity transmission network in the country’s western region.

    The engineering, procurement and construction (EPC) works will support the integration of the 2GW Dukhan solar power project into Qatar’s national electricity grid. The scope includes new and upgraded substations, as well as the installation of underground cables and overhead transmission lines.

    Kahramaa said contracts were awarded to local firm Voltage Engineering, Turkiye’s Best & Betas Consortium, India’s Larsen & Toubro and South Korea’s LS Cable.

    Of Kahramaa’s 2026 procurement plan, electricity transmission projects account for QR8.9bn ($2.4bn) and include the construction of new 400/132kV substations in Al-Wukair and Al-Mashaf, as well as the expansion of 400kV substations at Ras Laffan.

    These also cover the installation of 132kV underground cables between Al-Sailiya and Al-Rayyan over a 24-kilometre route, as well as upgrades to the 400kV and 220kV networks.

    Additionally, there are 64 planned electricity distribution projects managed by the Electricity Distribution Department that cover the medium-voltage and low-voltage networks throughout Doha and the regional municipalities. 

    https://image.digitalinsightresearch.in/uploads/NewsArticle/18962223/main.jpg
    Mark Dowdall
  • Maaden closes $1bn term loan and credit facility

    24 August 2026

    Saudi Arabian Mining Company (Maaden) has announced the closing of its inaugural international syndicated term loan and revolving credit facilities, worth a total of $1bn.

    The $500m international term loan facility will support Maaden’s growth agenda and general corporate purposes, including funding growth projects across its portfolio.

    The $500m international revolving credit facility, which is expected to remain undrawn, provides additional committed funding capacity “as Maaden continues to scale its business and execute its long-term growth strategy”.

    The transaction “was met with strong support from the international banking market, attracting participation from a diverse group of leading international banks across key global financial markets”, including the US, Canada, Europe, China and Japan. The facilities were oversubscribed, Maaden said.

    ALSO READ: Maaden and Aramco sign deal to create joint venture

    “The level of demand reflects the global banking community’s confidence in Maaden’s financial strength, strategic direction and ambitious growth plans,” the Saudi state miner said in its statement.

    “The facilities mark another significant milestone in Maaden’s funding journey – further diversifying its sources of funding and broadening its access to global capital providers as the company continues to advance its long-term growth ambitions.

    “Maaden continues to make significant progress across its growth pipeline, expanding production, advancing major projects and accelerating exploration as it builds a world-class mining company at the heart of Saudi Arabia’s economic transformation.”

    https://image.digitalinsightresearch.in/uploads/NewsArticle/18962086/main4516.jpg
    Indrajit Sen
  • Dubai inflation slows to 5.3% in July

    24 August 2026

    Dubai’s annual inflation rate slowed to 5.3% in July, down from 5.7% in June, as a decline in transport costs eased pressure on consumer prices, according to Emirates NBD.

    The bank said the slowdown supported its view that price growth peaked at mid-year, and it expects inflation to continue easing through the rest of 2026. Monthly price growth slowed to 0.1% in July, from 0.4% in June, the weakest pace since February.

    Transport was the clearest sign of the moderation. Annual price growth in the category slowed to 11.9% in July, from 18.1% in June, as transport costs fell 3.7% over the month. Fuel and lubricant inflation eased to 24.1% year on year, from 48.3%, tracking a decline in local petrol prices.

    Petrol remains the main swing factor in the emirate’s inflation. Transport contributed 1.1 percentage points to headline inflation in July, down from 1.7 percentage points in June. Emirates NBD said the relief may prove temporary, with Super 98 petrol prices climbing 5.9% in August to leave them 33.8% higher than a year earlier. The bank expects headline inflation to edge higher in the August figures before easing again later in the year.

    The UAE deregulated petrol and diesel prices in 2015 and reviews them monthly against global prices, meaning changes in global fuel costs pass through to consumers quickly. Transport, which includes fuel, accounts for 9% of Dubai’s consumer price index basket.

    Housing remained the largest contributor to inflation even as its impulse faded. Housing and utilities, which account for about two-fifths of the basket, added 2.8 percentage points to headline inflation. Annual price growth in the category slowed to 7.0%, from 7.4% in January.

    Food inflation edged up to 7.8% year on year, from 7.6% in June, which the bank attributed to lingering supply-chain disruption from the regional conflict. Inflation in restaurants and hotels accelerated to 4.5% year on year, from 1.7% in June.

    Emirates NBD forecasts inflation of 2.9% by year-end but said risks to that projection were tilted to the upside, given lingering pressures in food and housing.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/18961735/main1839.jpg
    Colin Foreman
  • Libya oil project on track for 2027 completion

    24 August 2026

     

    The project to develop a workers’ camp at Libya’s Erawin oil field is on track for completion next year, according to industry sources.

    The project, estimated to be worth about $50m, is being executed by the Libyan oil services company Al-Saraya Al-Hamara, headquartered in the city of Sebha.

    The Libyan company was awarded the contract in February 2025.

    The scope of the project includes:

    • Construction of an accommodation camp
    • Construction of the camp maintenance warehouse
    • Construction of the camp office
    • Construction of a fire brigade shelter
    • Construction of a kitchen and mess hall
    • Construction of a mosque
    • Construction of a laundry room
    • Construction of a clinic
    • Construction of parking facilities
    • Installation of a fire and gas system
    • Installation of a power generator
    • Construction of associated facilities

    The client on the project is Zallaf Libya Oil & Gas Exploration & Production Company.

    Zallaf Libya Oil & Gas Exploration & Production Company was established in Libya in 2013 and is wholly owned by Libya’s state-owned National Oil Corporation.

    The Erawin field development project is located about 800 kilometres south of Tripoli and 100km southwest of the El-Sharara field.

    Libya shipped its first cargo of crude from the Erawin oil field in November 2023.

    The shipment departed from Libya’s Zawiyah port and consisted of 600,000 barrels of crude.

    Australia-based Worley Parsons was appointed as the front-end engineering and design (feed) contractor for the early production facility project in 2019.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/18953632/main.jpg
    Wil Crisp