Region plans vital big grid connections
29 May 2023

The mantra “there will be no transition without transmission” dominated this year’s World Utility Congress, which was organised by Abu Dhabi National Energy Company (Taqa) and held in the UAE capital on 8-10 May.
“There will be no transition without interconnectivity with our neighbours. If we are not interconnected, we are not using the full capacity of our [electricity] network,” UAE Energy and Infrastructure Minister Suhail bin Mohamed al-Mazrouei said at the congress.
For the GCC states in particular, their ability to procure affordable and large-scale solar energy capacity, and the wide discrepancy in peak demands between the winter and summer months, which often results in substantial idle capacity, make it imperative to connect to other states or regions.
“Links to other GCC states and Central Asia will enable our electricity system to run more efficiently. Some have access to wind, others to solar or hydropower. We also have different peak hours,” Al-Mazrouei said. “We need to consider [these opportunities] and make the investments.”
Boosting transmission
In recent years, there has been a flurry of projects to build or enhance electricity transmission links within the GCC states, as well as with neighbouring countries such as Iraq and Jordan.
Contracts were awarded this year for the construction of overhead transmission lines connecting the GCC grid to Iraq via Kuwait, as well as a link between Iraq and Jordan.
Other projects in the early stages include a second connection between Saudi Arabia and Iraq, Saudi Arabia and the UAE, and the UAE and Oman.
Beyond the GCC, a $1.8bn electricity link between Saudi Arabia and Egypt is under construction. The project will facilitate the exchange of 3,000MW of electricity between the two countries through overhead transmission lines as well as high-voltage, direct current (HVDC) subsea cables.
The most ambitious plans include projects that will pipe electricity from Egypt, Tunisia and Morocco to European countries including Greece, Italy and the UK.
Some have access to wind, others to solar or hydropower. We also have different peak hours … we need to consider [these opportunities] and make the investments
UAE Energy and Infrastructure Minister Suhail bin Mohamed al-Mazrouie
Shifting peaks
Energy security has spurred investments to interconnect electricity grids between national borders and time zones. The pace of development is reminiscent of the advent of data interconnectivity two decades earlier.
Grid interconnections are also critical for the integration and optimisation of renewable energy, according to Jessica Obeid, a partner at New Energy Consult.
“Grid interconnections enable efficient management and mitigations of stability challenges linked to the integration of variable renewable energy such as wind and solar into the grid,” she says.
These interconnections enable the deployment of renewable energy where land is vast and resources are abundant, to be dispatched in energy load centres.
More importantly, they reduce the curtailment of renewable energy systems through electricity exchange, balancing supply and demand at various periods.
UK startup Xlinks aims to connect Morocco to the UK via four HVDC subsea cables stretching 3,800 kilometres across the Atlantic. “Long distance interconnectors solve the intermittency of renewables as the sun is always shining or wind is always blowing elsewhere,” says Simon Morrish, Xlinks’ CEO.
“The idea is to generate clean energy and then move it to meet demand, which is much more economic than relying solely on domestic capacity.”
Xlinks aims to generate 10.5GW through solar and wind farms in Guelmin Oued Noun and pipe about 40 per cent of that energy through subsea cables that will have to pass through Spain, Portugal and France. The UK will receive 3.6GW of clean, affordable energy – equivalent to 8 per cent of its electricity needs – by 2030.
Soaring data demand drives boom
Desertec’s long shadow
The scale of Xlinks’ ambition draws comparison with an earlier project, the Desertec Industrial Initiative (Dii), which launched in 2009, but ironically has yet to see the light of day.
Dii had planned to build renewable energy plants globally, including in Morocco, and supply up to 15 per cent of Europe’s power demand by 2050.
Xlinks’ proponents expect to succeed where Desertec failed, however. “Generation costs are more than 90 per cent lower than they were then, which makes the project economically – as well as politically – attractive,” Morrish says.
Xlinks’ point-to-point design with an exclusive energy supply for the UK is expected to eliminate challenges associated with trying to use third-party transmission networks.
Although the technologies are all mature, Morrish says iterations have led to a much lower levelised cost of transmission over these distances. There is also more expertise for the HVDC system beyond the original equipment manufacturers.
Average electricity prices in Europe have increased significantly over the past 10 years and power delivered from the Middle East and North Africa (Mena) region is competitive with other reliable low-carbon solutions, according to Morrish.
The existence of clear renewable targets in Europe could also benefit Xlinks’ project, as well as similar schemes, such as the EuroAfrica Interconnector, which aims to link Egypt to Cyprus and Greece, and the Elmed Mediterranean project that links Tunisia to Italy.
Morocco’s renewable energy leadership, which includes having implemented legislation designed to facilitate the export of renewable energy, is another positive factor.
“Previous projects have typically focused on the recipient jurisdiction, such as Europe, rather than understanding the drivers for the generation country,” says Morrish. “By focusing on the benefits to the Mena region, in this case Morocco, Xlinks has obtained support from both Morocco and the UK.”
The 13-year gap between Desertec and Xlinks has not necessarily changed the mindset of some industry players, who are just beginning to grasp the complexities involved in other decarbonisation technologies such as green hydrogen and carbon capture and storage.
“It is an excellent concept, but it will be exceptionally difficult, if not impossible, to execute given the high demand for HVDC cables, financing and political considerations,” says a Dubai-based contractor.
Unlike the more reasonably- structured interconnections between the GCC or Mena states, the scale and scope of Xlinks’ scheme and other similar projects will require export credit and multilateral development agency support in combination with project finance debt. Experts say this is critical, but not entirely unprecedented.
For instance, Taqa’s decision to contribute $31m in the startup’s early funding round, which also includes $6.2m from UK-headquartered Octopus Energy, appears to signify investor appetite for the project. The scheme is expected to boost foreign direct investment and create thousands of jobs in Morocco during its construction phase.
Electricity demand is increasing at alarming rates, in direct relation to the impact of climate change and the increases in temperatures, cooling and water demand, which reduces the available supply for exports
Jessica Obeid, New Energy Consult
Political undertones
In December 2022, Saudi Investment Minister Khalid al-Falih said the kingdom is keen to join an agreement between four countries to export clean electricity from Azerbaijan to Europe.
He was referring to an accord signed by Azerbaijan, Georgia, Romania and Hungary to build an undersea cable in the Black Sea transmitting energy from Caspian Sea wind farms to Europe.
The agreement involves a 1,100-kilometre, 1GW cable running from Azerbaijan to Romania. It is part of broader EU efforts to diversify energy resources away from Russia amid the Ukraine war.
This provides an alternative to Saudi Arabia’s grid expansion plans, and to the Saudi-Egypt link, as Egypt itself is involved in negotiations to link its electricity grid to Italy, Cyprus and Greece.
Beyond financing, there are other challenges for both intra-Mena and intercontinental grid connections.
An efficient electricity exchange market is necessary, notes Obeid. Another key issue is the unsustainable increase in demand in Mena states.
Figure1: Saudi-Egypt interconnector route

“Electricity demand is rising alarmingly, in direct relation to the impact of climate change and the increases in temperatures, cooling and water demand, which reduces the available supply for exports,” she says.
Plans to interconnect with Iraq, which has been heavily reliant on Iran for energy imports, can also be tricky. “The incentive is mostly political. Many countries have expressed interest in connecting their grids to Iraq’s, but none of these projects have yet materialised,” says Obeid.
“Linking Iraq to the Saudi grid is bound to be more viable and cheaper for Iraq compared to alternative options such as electricity exports from Jordan. But that is pending a political decision and would get Saudi Arabia and the GCC political and economic influence in Iraq.”
Exclusive from Meed
-
Qiddiya plans $7bn theme park hub near Paris25 August 2026
-
Masdar shelves Abu Dhabi green hydrogen project25 August 2026
-
Oman invites bids for Musandam renewables study25 August 2026
-
US launches sanctions campaign against Iran25 August 2026
-
Kuwait tenders $3.3bn gas processing facility25 August 2026
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Qiddiya plans $7bn theme park hub near Paris25 August 2026
Saudi Arabia’s Qiddiya Investment Company plans to develop a mixed-use leisure destination worth about €6bn ($7bn) at Cergy-Pontoise in the Ile-de-France region, in one of the largest Saudi investments in French tourism infrastructure to date.
The plan was set out in a joint statement issued on 24 August at the close of a state visit to France by Crown Prince and Prime Minister Mohammed Bin Salman Bin Abdulaziz Al-Saud. France and Saudi Arabia signed a memorandum of understanding (MoU) covering the project during the two-day visit.
The destination will bring together entertainment, leisure, hospitality, culture and sport, according to the joint statement. Current plans envisage up to three major entertainment anchors, hotels and complementary leisure experiences, with the €6bn figure covering the full development lifecycle.
One of the three parks is expected to be manga-themed, according to the French presidency. The themes of the other two have not been disclosed. The parks will be built and opened in stages, with construction expected to take several years. No opening date has been given.
The parks are expected to create about 22,000 direct jobs, according to the French presidency, compared with about 20,000 at Disneyland Paris. Cergy-Pontoise lies about 30 kilometres northwest of Paris.
Qiddiya is a subsidiary of the Public Investment Fund, Saudi Arabia’s sovereign wealth fund. Its flagship project is a giga-scale entertainment, sports and cultural city on the outskirts of Riyadh, one of several gigaprojects under Vision 2030.
The theme park plan was among a wider set of agreements reached during the visit. Both sides welcomed the announcement of 21 agreements and MoUs at a French-Saudi investment roundtable, spanning energy, industry, financial services, transport and logistics, health, culture, tourism and artificial intelligence. Bilateral trade reached about $11.8bn in 2025.
It is not the first time Saudi capital has backed a French theme park. Kingdom Holding Company was a longstanding investor in the operator of Disneyland Paris, first taking a stake in 1994 and participating in successive recapitalisations before Walt Disney Company moved to near-full ownership in 2017.
https://image.digitalinsightresearch.in/uploads/NewsArticle/18987274/main.png -
Masdar shelves Abu Dhabi green hydrogen project25 August 2026

Abu Dhabi Future Energy Company (Masdar) has decided to cancel a planned project to build a green hydrogen plant in Abu Dhabi that would have supplied up to 100MW of renewable hydrogen to local steelmaker Emsteel for green steel production.
After contractors submitted bids for the project last year, Masdar asked bidders in the first quarter of this year to extend the validity of their proposals until the end of August to allow “more time to study and evaluate bids”, according to one source.
However, Masdar issued a notification to all bidders on 1 August stating that it had decided to cancel the project, sources told MEED.
Contractors that submitted bids for the Masdar green hydrogen project included:
- Envision (China)
- Larsen & Toubro (India)
- PowerChina (China)
- Samsung E&A (South Korea)
- Sinopec (China)
Masdar did not respond to MEED’s request for comment on the information.
In its current steelmaking process, Emsteel uses hydrogen produced by steam reforming of natural gas as a reducing agent to extract iron from iron ore. The core objective of Masdar’s planned project was to install a 100MW electrolyser at Emsteel’s main manufacturing hub in Musaffah, Abu Dhabi, to supply green hydrogen for future clean steel production.
Masdar initiated work on the project in 2024 by awarding a front-end engineering and design (feed) contract to locally based NT Energies, a joint venture of Abu Dhabi’s NMDC Energy and France-based Technip Energies.
Masdar then sought proposals last year for engineering, procurement, construction, demolition (if needed for brownfield activities), pre-commissioning, commissioning, start-up, and two years of operations and maintenance (extendable up to 20 years) at the planned facility.
Contractors submitted bids by the end of the year, according to sources.
The project involved green hydrogen production using alkaline water electrolysis, with a total installed electrolyser capacity of 100MW.
The scope of work involved building electrolyser stacks and modules, hydrogen separation and compression units, associated utilities and storage systems, and electrical, instrumentation and control systems.
It also included tie-ins to pre-defined interface points, including (but not limited to):
- a grid power supply connection to the MOSF substation in Musaffah that exists within the Emsteel complex and is operated by Taqa Transmission
- a water supply connection to a nearby Taqa Distribution network
Supporting infrastructure included a substation, a motor control centre, and ancillary plant buildings and facilities.
Masdar’s planned 100MW electrolyser project at the Emsteel facility would have represented a step up from a previous pilot project by the two Abu Dhabi-owned companies.
The partners inaugurated a pilot green hydrogen plant at Emsteel’s manufacturing complex in Musaffah in October 2024. It incorporates a 2.1MW electrolyser and is designed to support the production of up to 5,000 tonnes of green steel a year.
This made Emsteel the only steelmaker in the Middle East to use green hydrogen to produce green steel on a pilot basis.
“Sustainability is central to Emsteel’s innovation, competitiveness and long-term growth. Today, approximately 89% of our steel business electricity consumption comes from clean sources, and our steel carbon emissions intensity is around 40% lower than the World Steel Association global average,” Michael Rion, chief commercial officer of Emirates Steel, part of Emsteel Group, told MEED in a recent interview.
READ THE AUGUST 2026 MEED BUSINESS REVIEW – click here to view PDFSaudi Arabia builds for the global stage; Rising uncertainty creates fresh set of challenges in the Maghreb; Gulf banks remain robust in the face of geopolitical tensions.
Distributed to senior decision-makers in the region and around the world, the August 2026 edition of MEED Business Review includes:
> WORLD CUP: What the 2026 World Cup means for Saudi Arabia 2034> MARKET FOCUS: Maghreb fortunes diverge> INDUSTRY REPORT: GCC banks prove resilient amid turmoil> LEADERSHIP: Private capital and the GCC infrastructure inflection> INTERVIEW: Developers look beyond standalone solarTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/18911651/main0611.jpg -
Oman invites bids for Musandam renewables study25 August 2026
Oman’s Nama Power & Water Procurement Company (PWP) has issued a request for proposals (RFP) for techno-economic consultancy services to assess the feasibility of renewable energy options in Musandam Governorate.
The study will examine solar photovoltaic (PV), wind and hybrid renewable energy configurations. It will also assess battery energy storage systems (bess) and other renewable energy and energy storage technologies.
The consultant will be required to determine which technologies are technically and economically justified for the governorate.
The bid submission deadline is 24 September.
The Musandam power system is served primarily by the 123MW Musandam independent power plant (IPP), which began operating in 2017. The governorate has historically relied on small diesel-fired units, but has been seeking to move away from diesel-fired power generation for several years.
Nama PWP has previously said it was exploring renewable energy options in Musandam to meet future additional capacity requirements.
Its latest seven-year statement, released in March, forecasts peak electricity demand in Musandam to rise from 91MW in 2024 to 130MW in 2031, an average annual increase of 5%. Average demand is forecast to rise from 52MW to 73MW over the same period.
The plan says demand growth is being driven by distribution-level load and projects aimed at boosting tourism, economic and commercial activity.
Separately, the utility recently invited bids for financial and commercial consultancy services covering three 1GW solar IPPs targeted for commercial operation by the second quarter of 2030.
The bid submissions deadline is 10 September.
The three projects covered by the financial and commercial consultancy tender are understood to also be part of the 4GW programme, for which a technical advisory tender was issued on 15 July.
Bidding for this tender closes on 26 August.
READ THE AUGUST 2026 MEED BUSINESS REVIEW – click here to view PDFSaudi Arabia builds for the global stage; Rising uncertainty creates fresh set of challenges in the Maghreb; Gulf banks remain robust in the face of geopolitical tensions.
Distributed to senior decision-makers in the region and around the world, the August 2026 edition of MEED Business Review includes:
> WORLD CUP: What the 2026 World Cup means for Saudi Arabia 2034> MARKET FOCUS: Maghreb fortunes diverge> INDUSTRY REPORT: GCC banks prove resilient amid turmoil> LEADERSHIP: Private capital and the GCC infrastructure inflection> INTERVIEW: Developers look beyond standalone solarTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/18983679/main.jpg -
US launches sanctions campaign against Iran25 August 2026
The US has launched a sweeping sanctions campaign against Iran and the entities that trade with it, imposing measures on almost 60 individuals, companies and vessels while expanding the reach of secondary sanctions across five sectors of the Iranian economy.
The campaign, named Operation Economic Outcast, was announced on 24 August by US treasury secretary Scott Bessent, who described it as an economic D-Day for Iran. He said Washington’s objective was to sever every economic lifeline sustaining the Iranian regime.
The treasury’s Office of Foreign Assets Control (Ofac) issued five sectoral sanctions determinations under Executive Order 13902, covering digital assets, technology, gold, aviation and shipping. The determinations allow Ofac to sanction any person operating in those sectors, regardless of location. Washington said Iran uses cryptocurrency for sanctions evasion, seeks advanced technology for its weapons programmes, uses gold to stabilise the rial, and relies on commercial aviation and shipping networks to move fighters, weapons and oil revenue.
The measures build on earlier determinations targeting Iran’s financial, petroleum and petrochemical sectors.
Ofac also sanctioned close to 60 entities, individuals and vessels across multiple jurisdictions, including UAE-based entities, over alleged involvement in nuclear and missile procurement, cyber operations and oil revenue networks. The designations named a network of brokers, companies and shadow fleet vessels operating across the UAE, Hong Kong, China, Singapore, Switzerland and other regions to transport Iranian oil and channel revenue to the Islamic Revolutionary Guard Corps.
Among those designated were shipping brokers and bunkering firms based in the UAE that Washington said facilitated Iranian oil shipments and provided services to sanctioned vessels. The treasury also identified several shadow fleet tankers as blocked property, saying they had moved millions of barrels of Iranian crude and petroleum products, mainly to China.
Separately, the treasury targeted a procurement network spanning the Middle East and East Asia that it said supported Iran’s acquisition of proliferation-sensitive equipment, along with a cyber group directed by Iran’s Ministry of Intelligence & Security.
Bessent said Washington was pressing governments to shut down Iran-related activity within defined timelines, warning that entities facilitating money laundering or sanctions evasion for Iran risked being cut off from the US financial system. He declined to name specific countries.
The campaign follows the UAE’s own move against Tehran. On 19 August, the UAE suspended all trade, commercial exchanges and financial transactions with Iran with immediate effect, citing regional escalation. The UAE has historically been one of Iran’s most significant trading partners, with much of the relationship built on re-export trade routed through Dubai.
https://image.digitalinsightresearch.in/uploads/NewsArticle/18983152/main.jpg -
Kuwait tenders $3.3bn gas processing facility25 August 2026

State-owned Kuwait Gulf Oil Company (KGOC) has issued the tender for the development of an onshore gas plant next to the Al-Zour refinery, according to industry sources.
The project budget is estimated at $3.3bn, and the bid deadline is 29 December, with a meeting for contractors scheduled for 14 September.
The tender was issued on 23 August.
The proposed plant will have the capacity to process up to 632 million cubic feet a day of gas and 60,000 b/d a day of condensates from the Dorra offshore field, located in Gulf waters in the Saudi-Kuwait Neutral Zone.
In February, MEED reported that at least seven companies had shown interest in participating in the tender.
Contractors that sent representatives to previous meetings to discuss the project include:
- Samsung E&A (South Korea)
- Larsen & Toubro (India)
- Tecnicas Reunidas (Spain)
- Saipem (Italy)
- Hyundai Engineering & Construction (South Korea)
- Hyundai Engineering Company (South Korea)
- JGC (Japan)
The tender process is using a fast-track model, which means that Kuwait’s Central Agency for Public Tenders (Capt) will not be involved in the tender process.
Capt typically reviews the technical and commercial evaluations of bids and verifies that the bidding process is competitive.
It is understood that not requiring Capt to approve this tender is expected to speed up the tender process.
Iran disputes ownership of the field, referring to it as Arash.
Iran claims the field partially extends into Iranian territory and asserts that Tehran should be a stakeholder in its development.
The Dorra field’s close proximity to Iran could make development difficult due to current security concerns.
The offshore elements of the wider Dorra field development project are expected to be especially difficult to protect from attacks from Iran.
Earlier this month, MEED revealed that Al-Khafji Joint Operations (KJO) had selected contractors for two major offshore packages under the Dorra field facilities development project.
KJO, which is jointly owned by Aramco subsidiary Aramco Gulf Operations Company and Kuwait Petroleum Corporation subsidiary KGOC, has divided the engineering, procurement and construction (EPC) scope for the Dorra gas production project into four packages: three offshore and one onshore.
US-based McDermott International has secured offshore package 2A, valued at about $1.5bn, according to sources.
A consortium of India’s Larsen & Toubro Energy Hydrocarbon (LTEH) and Italian contractor Saipem has secured package 2B, sources told MEED.
Estimated at about $3.7bn, package 2B is the largest of the three offshore EPC packages under the Dorra field facilities project.
MEED reported in March that the LTEH/Saipem consortium had emerged as the lowest bidder for offshore package 2B.
Contractors submitted bids for offshore packages 2A and 2B by the 9 March deadline, MEED previously reported. Bid validity was understood to expire on 15 August, prompting KJO to issue letters of intent to the selected contractors earlier this month, sources said.
https://image.digitalinsightresearch.in/uploads/NewsArticle/18964461/main.png