Region plans vital big grid connections
29 May 2023

The mantra “there will be no transition without transmission” dominated this year’s World Utility Congress, which was organised by Abu Dhabi National Energy Company (Taqa) and held in the UAE capital on 8-10 May.
“There will be no transition without interconnectivity with our neighbours. If we are not interconnected, we are not using the full capacity of our [electricity] network,” UAE Energy and Infrastructure Minister Suhail bin Mohamed al-Mazrouei said at the congress.
For the GCC states in particular, their ability to procure affordable and large-scale solar energy capacity, and the wide discrepancy in peak demands between the winter and summer months, which often results in substantial idle capacity, make it imperative to connect to other states or regions.
“Links to other GCC states and Central Asia will enable our electricity system to run more efficiently. Some have access to wind, others to solar or hydropower. We also have different peak hours,” Al-Mazrouei said. “We need to consider [these opportunities] and make the investments.”
Boosting transmission
In recent years, there has been a flurry of projects to build or enhance electricity transmission links within the GCC states, as well as with neighbouring countries such as Iraq and Jordan.
Contracts were awarded this year for the construction of overhead transmission lines connecting the GCC grid to Iraq via Kuwait, as well as a link between Iraq and Jordan.
Other projects in the early stages include a second connection between Saudi Arabia and Iraq, Saudi Arabia and the UAE, and the UAE and Oman.
Beyond the GCC, a $1.8bn electricity link between Saudi Arabia and Egypt is under construction. The project will facilitate the exchange of 3,000MW of electricity between the two countries through overhead transmission lines as well as high-voltage, direct current (HVDC) subsea cables.
The most ambitious plans include projects that will pipe electricity from Egypt, Tunisia and Morocco to European countries including Greece, Italy and the UK.
Some have access to wind, others to solar or hydropower. We also have different peak hours … we need to consider [these opportunities] and make the investments
UAE Energy and Infrastructure Minister Suhail bin Mohamed al-Mazrouie
Shifting peaks
Energy security has spurred investments to interconnect electricity grids between national borders and time zones. The pace of development is reminiscent of the advent of data interconnectivity two decades earlier.
Grid interconnections are also critical for the integration and optimisation of renewable energy, according to Jessica Obeid, a partner at New Energy Consult.
“Grid interconnections enable efficient management and mitigations of stability challenges linked to the integration of variable renewable energy such as wind and solar into the grid,” she says.
These interconnections enable the deployment of renewable energy where land is vast and resources are abundant, to be dispatched in energy load centres.
More importantly, they reduce the curtailment of renewable energy systems through electricity exchange, balancing supply and demand at various periods.
UK startup Xlinks aims to connect Morocco to the UK via four HVDC subsea cables stretching 3,800 kilometres across the Atlantic. “Long distance interconnectors solve the intermittency of renewables as the sun is always shining or wind is always blowing elsewhere,” says Simon Morrish, Xlinks’ CEO.
“The idea is to generate clean energy and then move it to meet demand, which is much more economic than relying solely on domestic capacity.”
Xlinks aims to generate 10.5GW through solar and wind farms in Guelmin Oued Noun and pipe about 40 per cent of that energy through subsea cables that will have to pass through Spain, Portugal and France. The UK will receive 3.6GW of clean, affordable energy – equivalent to 8 per cent of its electricity needs – by 2030.
Soaring data demand drives boom
Desertec’s long shadow
The scale of Xlinks’ ambition draws comparison with an earlier project, the Desertec Industrial Initiative (Dii), which launched in 2009, but ironically has yet to see the light of day.
Dii had planned to build renewable energy plants globally, including in Morocco, and supply up to 15 per cent of Europe’s power demand by 2050.
Xlinks’ proponents expect to succeed where Desertec failed, however. “Generation costs are more than 90 per cent lower than they were then, which makes the project economically – as well as politically – attractive,” Morrish says.
Xlinks’ point-to-point design with an exclusive energy supply for the UK is expected to eliminate challenges associated with trying to use third-party transmission networks.
Although the technologies are all mature, Morrish says iterations have led to a much lower levelised cost of transmission over these distances. There is also more expertise for the HVDC system beyond the original equipment manufacturers.
Average electricity prices in Europe have increased significantly over the past 10 years and power delivered from the Middle East and North Africa (Mena) region is competitive with other reliable low-carbon solutions, according to Morrish.
The existence of clear renewable targets in Europe could also benefit Xlinks’ project, as well as similar schemes, such as the EuroAfrica Interconnector, which aims to link Egypt to Cyprus and Greece, and the Elmed Mediterranean project that links Tunisia to Italy.
Morocco’s renewable energy leadership, which includes having implemented legislation designed to facilitate the export of renewable energy, is another positive factor.
“Previous projects have typically focused on the recipient jurisdiction, such as Europe, rather than understanding the drivers for the generation country,” says Morrish. “By focusing on the benefits to the Mena region, in this case Morocco, Xlinks has obtained support from both Morocco and the UK.”
The 13-year gap between Desertec and Xlinks has not necessarily changed the mindset of some industry players, who are just beginning to grasp the complexities involved in other decarbonisation technologies such as green hydrogen and carbon capture and storage.
“It is an excellent concept, but it will be exceptionally difficult, if not impossible, to execute given the high demand for HVDC cables, financing and political considerations,” says a Dubai-based contractor.
Unlike the more reasonably- structured interconnections between the GCC or Mena states, the scale and scope of Xlinks’ scheme and other similar projects will require export credit and multilateral development agency support in combination with project finance debt. Experts say this is critical, but not entirely unprecedented.
For instance, Taqa’s decision to contribute $31m in the startup’s early funding round, which also includes $6.2m from UK-headquartered Octopus Energy, appears to signify investor appetite for the project. The scheme is expected to boost foreign direct investment and create thousands of jobs in Morocco during its construction phase.
Electricity demand is increasing at alarming rates, in direct relation to the impact of climate change and the increases in temperatures, cooling and water demand, which reduces the available supply for exports
Jessica Obeid, New Energy Consult
Political undertones
In December 2022, Saudi Investment Minister Khalid al-Falih said the kingdom is keen to join an agreement between four countries to export clean electricity from Azerbaijan to Europe.
He was referring to an accord signed by Azerbaijan, Georgia, Romania and Hungary to build an undersea cable in the Black Sea transmitting energy from Caspian Sea wind farms to Europe.
The agreement involves a 1,100-kilometre, 1GW cable running from Azerbaijan to Romania. It is part of broader EU efforts to diversify energy resources away from Russia amid the Ukraine war.
This provides an alternative to Saudi Arabia’s grid expansion plans, and to the Saudi-Egypt link, as Egypt itself is involved in negotiations to link its electricity grid to Italy, Cyprus and Greece.
Beyond financing, there are other challenges for both intra-Mena and intercontinental grid connections.
An efficient electricity exchange market is necessary, notes Obeid. Another key issue is the unsustainable increase in demand in Mena states.
Figure1: Saudi-Egypt interconnector route

“Electricity demand is rising alarmingly, in direct relation to the impact of climate change and the increases in temperatures, cooling and water demand, which reduces the available supply for exports,” she says.
Plans to interconnect with Iraq, which has been heavily reliant on Iran for energy imports, can also be tricky. “The incentive is mostly political. Many countries have expressed interest in connecting their grids to Iraq’s, but none of these projects have yet materialised,” says Obeid.
“Linking Iraq to the Saudi grid is bound to be more viable and cheaper for Iraq compared to alternative options such as electricity exports from Jordan. But that is pending a political decision and would get Saudi Arabia and the GCC political and economic influence in Iraq.”
Exclusive from Meed
-
Aramco-backed firm tenders logistics hub expansion9 November 2026
-
Prequalification begins for multibillion-dollar Dubai road9 November 2026
-
Contractor begins early works on Ardara’s AlWadi project9 November 2026
-
Syria in talks for refinery project worth $6bn-8bn9 November 2026
-
Three Libya oil and gas projects see developments9 November 2026
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Aramco-backed firm tenders logistics hub expansion9 November 2026

Asmo, the logistics joint venture of Saudi Aramco and DHL Supply Chain, has set a 15 November deadline for a contract to expand the logistics complex at King Salman Energy Park (Spark) in Saudi Arabia’s Eastern Province.
The logistics hub will add over 124,000 square metres (sq m) at Spark.
Al-Khobar-based engineering firm House of Consulting Office is the project consultant.
The tender for the expansion works comes shortly after Asmo awarded an estimated SR820m ($218m) contract to build the logistics complex’s first phase in May this year.
The overall project will feature a 43,000 sq m, temperature-controlled Grade A warehouse; more than 3,000 sq m of offices and staff amenities; 5,300 sq m dedicated to chemicals storage; and an open yard covering about 1.2 million sq m.
Asmo signed an agreement with Bahrain‑headquartered Arcapita Group Holdings in February to deliver the project at Spark.
Planned for large-scale industrial use, the site is expected to incorporate advanced warehouse and building management systems, end-to-end digital connectivity, automation and robotics.
It will also be developed in line with internationally recognised sustainability standards, featuring solar photovoltaic readiness, electric-vehicle charging infrastructure and a target of Leed Gold certification.
The development aims to support the next stage of Saudi Arabia’s logistics and supply chain expansion.
Under the deal structure, Arcapita will provide funding and retain ownership of the asset, while Asmo will develop the facility and then lease and operate it under a 22-year occupational lease.
According to a statement, “the scheme will be executed via a forward-funding model, underscoring a long-term commitment to national infrastructure”.
Asmo added that this will be its first purpose-built logistics centre and one of four strategic locations planned to anchor its nationwide logistics network, aligned with the National Transport and Logistics Strategy under Saudi Vision 2030.
https://image.digitalinsightresearch.in/uploads/NewsArticle/21267403/main.gif -
Prequalification begins for multibillion-dollar Dubai road9 November 2026

Dubai’s Roads & Transport Authority (RTA) has begun prequalifying contractors for a design-and-build contract for a multibillion-dollar new road that will run parallel to Sheikh Zayed Road.
Contractors have until 30 November to submit their prequalification statements.
The latest development follows contractors’ expressions of interest for the project on 10 October, as MEED reported.
The project’s scope covers about 30 kilometres (km) of works. These include about 15km of viaduct along First Al-Khail Street and more than 14.5km of bridge ramps, along with other associated infrastructure works.
The project is another significant initiative aimed at alleviating pressure on the existing Sheikh Zayed Road section from Hadiqa Street to Hessa Street.
Dubai has previously explored bold concepts to expand capacity on Sheikh Zayed Road, including proposals to introduce double-decker sections to add extra lanes without widening the existing corridor.
The idea was discussed in the context of rising congestion and limited right-of-way along one of the city’s busiest arterial roads, with elevated decks potentially carrying through traffic while existing at-grade lanes served local access.
The plans ultimately became standalone schemes, with subsequent efforts focusing instead on corridor-wide upgrades, interchange improvements and complementary public transport expansions to manage demand more sustainably.
The latest project aligns with Dubai’s continued investment in upgrading and expanding its road network to keep pace with rapid population growth and rising commuting demand.
Planning for growth
Dubai launched the 2040 Urban Master Plan in March 2021, referencing studies indicating that the emirate’s population will reach 5.8 million by 2040, up from 3.3 million in 2020. The daytime population is set to increase from 4.5 million in 2020 to 7.8 million in 2040.
In December 2022, Sheikh Mohammed Bin Rashid Al-Maktoum, Vice President and Prime Minister of the UAE and Ruler of Dubai, approved the 20-Minute City Policy as part of the second phase of the Dubai 2040 Urban Master Plan.
In addition to the road projects, the RTA’s Dubai Metro Blue Line extension and Dubai Metro Gold Line form part of Dubai’s plans to improve residents’ quality of life by cutting journey times, as outlined in the policy.
The policy aims to ensure residents can meet 80% of their daily needs within a 20-minute journey, on foot or by bicycle. This goal will be achieved by developing integrated service centres with all necessary facilities and increasing population density around mass transit stations.
https://image.digitalinsightresearch.in/uploads/NewsArticle/21266194/main.gif -
Contractor begins early works on Ardara’s AlWadi project9 November 2026
Saudi Arabia’s Shibh Al-Jazira Contracting Company (Sajco) has started early construction works on the first cluster of its AlWadi mixed-use development in Abha.
Ardara, backed by the sovereign wealth vehicle the Public Investment Fund (PIF), is developing the AlWadi project.
Sajco will carry out sewerage works, while local engineering firm Dar Al-Riyadh will provide project management and supervision services for the infrastructure works.
The AlWadi project will cover 2.5 million square metres (sq m) and will be developed around architectural styles informed by the heritage and character of the Aseer region.
The masterplan has a planned gross floor area of about 2.02 million sq m. It includes 7,306 apartments, 90 villas and townhouses, and 2,783 hotel keys.
The scheme will also provide 154,082 sq m of retail and food and beverage space, 64,161 sq m of offices, and 59,075 sq m of leisure and entertainment facilities.
The wider development will comprise five districts and include 16 kilometres of waterfront assets and 17km of walking, cycling and sports tracks.
US-based Parsons is the infrastructure designer, while Miami-based OBMI is providing architectural and public realm design services.
https://image.digitalinsightresearch.in/uploads/NewsArticle/21265927/main.jpg -
Syria in talks for refinery project worth $6bn-8bn9 November 2026
Register for MEED’s 14-day trial access
Discussions are under way with international companies to develop a refinery in Syria’s Furqlus area, worth $6bn-8bn, according to a senior official at state-owned Syrian Petroleum Company (SPC).
The project will be “very large” and, after completion, will replace Syria’s Homs refinery, according to SPC’s deputy executive president for refining affairs, Tariq Shalash Al-Abdullah, who spoke to Syria’s state-owned daily newspaper Al-Thawra Al-Souriya.
He said the international companies currently involved in talks about the planned refinery project specialise in design work, engineering and technical studies.
He also stated that, for large-scale projects of this type, consortiums are typically formed from a group of companies with complementary interests in study, manufacturing, financing, implementation and operation.
In June, SPC published an invitation for companies to submit proposals to finance, build and operate the refinery under a build-operate-transfer agreement.
The tender document published by SPC said the refinery would have the capacity to process 210,000 barrels a day (b/d).
It also said the facility would be developed with the option to add an “ancillary petrochemical complex”.
Al-Abdullah said the refinery’s total investment value would depend on the equipment's country of origin, adding that the equipment could potentially be procured from the US, Europe or China.
Another factor that could alter the project’s value is the technology licences selected for the project, according to Al-Abdullah.
The refinery project is expected to take around four years to develop from the date of signing the contract and completing other related preparatory activities.
The project will be developed on a site that covers 400 hectares, according to the document that was published by SPC in June.
SPC invited companies to submit three separate documents relating to their proposals.
These were:
- A package outlining the company’s qualifications and legal documents
- A technical proposal
- A financial and investment proposal
According to the tender document, the scope of the refinery project includes developing:
- Three independent atmospheric distillation units, each with a capacity of 70,000 b/d
- Two vacuum distillation units
- Hydrotreating units
- Sulphur recovery units
- A base oil unit
- Power and steam generation facilities
- A grid interconnection substation
- A safe shutdown system
- An environmental water treatment system
- A gas recovery system
- A unit to produce nitrogen and oxygen
- A fire water network
- Maintenance and repair workshops
- Tank farm and storage facilities
Under the plans outlined in SPC’s tender document, at least 85% of the refinery’s products should meet Euro-5 specifications.
SPC is also seeking a “plan for the establishment and integration of an advanced petrochemical complex”, which would be connected to the refinery, according to the document.
Because of this, it said the refinery design must allow diversion of some light and heavy naphtha and liquid petroleum gas (LPG) to be used as feedstock for the future petrochemical complex.
The petrochemical complex is planned to use 20% to 40% of the naphtha and LPG.
https://image.digitalinsightresearch.in/uploads/NewsArticle/21263584/main.png -
Three Libya oil and gas projects see developments9 November 2026

Three key oil and gas projects in Libya have seen developments amid an uptick in activity in the North African country’s hydrocarbon sector.
The contract scopes include seismic work, subsea pipeline development and drilling services.
An invitation to prequalify has been issued for a project to provide two-dimensional (2D) and three-dimensional (3D) offshore seismic surveying services.
The survey area is the Libyan Offshore Area O1, located in the Sirte Basin.
The winner of the contract will be responsible for:
- Acquisition of approximately 6,100 square kilometres (sq km) of 3D full-fold marine seismic data
- Acquisition of approximately 3,000 sq km of 2D full-fold marine seismic data
The client on the project is the Italian oil and gas company Eni.
In a statement posted on the website of Libya’s National Oil Corporation (NOC), it said: “The objective of the survey is to acquire, within the required operational window from September 2027 to March 2028, high-quality broadband seismic data to improve the imaging of Cretaceous reservoir sequences and support future exploration activities.”
The deadline to submit prequalification documents is 2 December 2026.
Deadline extended
Libya’s Mellitah Oil & Gas Company (MOG) has extended the deadline for companies to submit prequalification documents for a major offshore package as part of its Mellitah complex expansion and CO2 management integrated development project, which is estimated to be worth about $8bn.
The previous deadline of 5 November 2026 has been extended to 3 December 2026.
MOG, a joint venture of NOC and Eni, is the project client.
The package, known as WP4B1, focuses on developing offshore pipelines and subsea systems for the E offshore installation and CO2 project.
The turnkey contract will use the engineering, procurement, installation and commissioning (EPIC) model.
As part of the Mellitah complex expansion and CO2 management integrated development project, two offshore structures – Structure A and Structure E – will be developed in Libya’s offshore block NC 41.
Structure A is also known as wellhead production fixed platform A (WHPA) and Structure E is also known as production platform E (PPE).
Structure A is in the central-western part of the area, about 80 kilometres (km) from the Libyan coast, with a water depth of 95-105 metres.
Structure E is located in the central-eastern part of the area, about 130km from the Libyan coast, in a water depth of 205-235 metres.
The scope of the wider project includes:
- A new production platform installed in about 220 metres of water depth as part of the development of Structure E (Package WP1)
- A new wellhead platform installed in 96 metres of water as part of the development of Structure A (Package WP2)
- Modification of the existing Sabratha platform (Package WP3)
- Sealines and subsea systems extending from the Sabratha platform to Structure A (Package WP4A1)
- Sealines and subsea systems for Structure E and the CO2 system (Package WP4B1)
- Supply of seamless carbon steel pipes for CO2 injection from the Mellitah complex to Sabratha platform (Package WP4B2)
- Subsea Production Systems (SPS) for Structure E and CO2 (Package WP4B3)
- Upgrading the existing onshore Mellitah complex (WP5)
The package known as WP4B1 has been broken down into two phases.
The first phase focuses on the installation of the project’s subsea CO2 pipeline and its related system network.
The second phase of WP4B1 is focused on the pipeline to structure E and its related subsea system network.
Monitoring drilling
MOG has also issued a separate invitation for prequalification relating to a contract to provide hydrogen sulphide monitoring services for offshore drilling.
The contract focuses on providing H2S monitoring services for 18 offshore development wells as part of the “Structures A&E” project.
Four of the wells will be subsea wet wells and a further 14 will be dry tree wells.
The deadline for submitting prequalification documents is 3 December 2026.
The work will be carried out in the zone known as Area D, Block NC41.
H2S monitoring in the oil and gas industry involves tracking H2S gas concentrations in the air using electronic sensors and detectors to protect workers, prevent fatal exposures and avoid equipment damage.
https://image.digitalinsightresearch.in/uploads/NewsArticle/21263383/main.jpg