Region plans vital big grid connections
29 May 2023

The mantra “there will be no transition without transmission” dominated this year’s World Utility Congress, which was organised by Abu Dhabi National Energy Company (Taqa) and held in the UAE capital on 8-10 May.
“There will be no transition without interconnectivity with our neighbours. If we are not interconnected, we are not using the full capacity of our [electricity] network,” UAE Energy and Infrastructure Minister Suhail bin Mohamed al-Mazrouei said at the congress.
For the GCC states in particular, their ability to procure affordable and large-scale solar energy capacity, and the wide discrepancy in peak demands between the winter and summer months, which often results in substantial idle capacity, make it imperative to connect to other states or regions.
“Links to other GCC states and Central Asia will enable our electricity system to run more efficiently. Some have access to wind, others to solar or hydropower. We also have different peak hours,” Al-Mazrouei said. “We need to consider [these opportunities] and make the investments.”
Boosting transmission
In recent years, there has been a flurry of projects to build or enhance electricity transmission links within the GCC states, as well as with neighbouring countries such as Iraq and Jordan.
Contracts were awarded this year for the construction of overhead transmission lines connecting the GCC grid to Iraq via Kuwait, as well as a link between Iraq and Jordan.
Other projects in the early stages include a second connection between Saudi Arabia and Iraq, Saudi Arabia and the UAE, and the UAE and Oman.
Beyond the GCC, a $1.8bn electricity link between Saudi Arabia and Egypt is under construction. The project will facilitate the exchange of 3,000MW of electricity between the two countries through overhead transmission lines as well as high-voltage, direct current (HVDC) subsea cables.
The most ambitious plans include projects that will pipe electricity from Egypt, Tunisia and Morocco to European countries including Greece, Italy and the UK.
Some have access to wind, others to solar or hydropower. We also have different peak hours … we need to consider [these opportunities] and make the investments
UAE Energy and Infrastructure Minister Suhail bin Mohamed al-Mazrouie
Shifting peaks
Energy security has spurred investments to interconnect electricity grids between national borders and time zones. The pace of development is reminiscent of the advent of data interconnectivity two decades earlier.
Grid interconnections are also critical for the integration and optimisation of renewable energy, according to Jessica Obeid, a partner at New Energy Consult.
“Grid interconnections enable efficient management and mitigations of stability challenges linked to the integration of variable renewable energy such as wind and solar into the grid,” she says.
These interconnections enable the deployment of renewable energy where land is vast and resources are abundant, to be dispatched in energy load centres.
More importantly, they reduce the curtailment of renewable energy systems through electricity exchange, balancing supply and demand at various periods.
UK startup Xlinks aims to connect Morocco to the UK via four HVDC subsea cables stretching 3,800 kilometres across the Atlantic. “Long distance interconnectors solve the intermittency of renewables as the sun is always shining or wind is always blowing elsewhere,” says Simon Morrish, Xlinks’ CEO.
“The idea is to generate clean energy and then move it to meet demand, which is much more economic than relying solely on domestic capacity.”
Xlinks aims to generate 10.5GW through solar and wind farms in Guelmin Oued Noun and pipe about 40 per cent of that energy through subsea cables that will have to pass through Spain, Portugal and France. The UK will receive 3.6GW of clean, affordable energy – equivalent to 8 per cent of its electricity needs – by 2030.
Soaring data demand drives boom
Desertec’s long shadow
The scale of Xlinks’ ambition draws comparison with an earlier project, the Desertec Industrial Initiative (Dii), which launched in 2009, but ironically has yet to see the light of day.
Dii had planned to build renewable energy plants globally, including in Morocco, and supply up to 15 per cent of Europe’s power demand by 2050.
Xlinks’ proponents expect to succeed where Desertec failed, however. “Generation costs are more than 90 per cent lower than they were then, which makes the project economically – as well as politically – attractive,” Morrish says.
Xlinks’ point-to-point design with an exclusive energy supply for the UK is expected to eliminate challenges associated with trying to use third-party transmission networks.
Although the technologies are all mature, Morrish says iterations have led to a much lower levelised cost of transmission over these distances. There is also more expertise for the HVDC system beyond the original equipment manufacturers.
Average electricity prices in Europe have increased significantly over the past 10 years and power delivered from the Middle East and North Africa (Mena) region is competitive with other reliable low-carbon solutions, according to Morrish.
The existence of clear renewable targets in Europe could also benefit Xlinks’ project, as well as similar schemes, such as the EuroAfrica Interconnector, which aims to link Egypt to Cyprus and Greece, and the Elmed Mediterranean project that links Tunisia to Italy.
Morocco’s renewable energy leadership, which includes having implemented legislation designed to facilitate the export of renewable energy, is another positive factor.
“Previous projects have typically focused on the recipient jurisdiction, such as Europe, rather than understanding the drivers for the generation country,” says Morrish. “By focusing on the benefits to the Mena region, in this case Morocco, Xlinks has obtained support from both Morocco and the UK.”
The 13-year gap between Desertec and Xlinks has not necessarily changed the mindset of some industry players, who are just beginning to grasp the complexities involved in other decarbonisation technologies such as green hydrogen and carbon capture and storage.
“It is an excellent concept, but it will be exceptionally difficult, if not impossible, to execute given the high demand for HVDC cables, financing and political considerations,” says a Dubai-based contractor.
Unlike the more reasonably- structured interconnections between the GCC or Mena states, the scale and scope of Xlinks’ scheme and other similar projects will require export credit and multilateral development agency support in combination with project finance debt. Experts say this is critical, but not entirely unprecedented.
For instance, Taqa’s decision to contribute $31m in the startup’s early funding round, which also includes $6.2m from UK-headquartered Octopus Energy, appears to signify investor appetite for the project. The scheme is expected to boost foreign direct investment and create thousands of jobs in Morocco during its construction phase.
Electricity demand is increasing at alarming rates, in direct relation to the impact of climate change and the increases in temperatures, cooling and water demand, which reduces the available supply for exports
Jessica Obeid, New Energy Consult
Political undertones
In December 2022, Saudi Investment Minister Khalid al-Falih said the kingdom is keen to join an agreement between four countries to export clean electricity from Azerbaijan to Europe.
He was referring to an accord signed by Azerbaijan, Georgia, Romania and Hungary to build an undersea cable in the Black Sea transmitting energy from Caspian Sea wind farms to Europe.
The agreement involves a 1,100-kilometre, 1GW cable running from Azerbaijan to Romania. It is part of broader EU efforts to diversify energy resources away from Russia amid the Ukraine war.
This provides an alternative to Saudi Arabia’s grid expansion plans, and to the Saudi-Egypt link, as Egypt itself is involved in negotiations to link its electricity grid to Italy, Cyprus and Greece.
Beyond financing, there are other challenges for both intra-Mena and intercontinental grid connections.
An efficient electricity exchange market is necessary, notes Obeid. Another key issue is the unsustainable increase in demand in Mena states.
Figure1: Saudi-Egypt interconnector route

“Electricity demand is rising alarmingly, in direct relation to the impact of climate change and the increases in temperatures, cooling and water demand, which reduces the available supply for exports,” she says.
Plans to interconnect with Iraq, which has been heavily reliant on Iran for energy imports, can also be tricky. “The incentive is mostly political. Many countries have expressed interest in connecting their grids to Iraq’s, but none of these projects have yet materialised,” says Obeid.
“Linking Iraq to the Saudi grid is bound to be more viable and cheaper for Iraq compared to alternative options such as electricity exports from Jordan. But that is pending a political decision and would get Saudi Arabia and the GCC political and economic influence in Iraq.”
Exclusive from Meed
-
Hydrom targets hyperscalers in round four19 November 2026
-
Contractors submit best offers for Oxagon Highway 5519 November 2026
-
Construction starts on Damascus hotel and mall19 November 2026
-
Kuwait discusses retender of $7.7bn of oil projects19 November 2026
-
Saudi Arabia cancels more water tenders19 November 2026
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Hydrom targets hyperscalers in round four19 November 2026

Oman’s green hydrogen company Hydrom is turning to domestic demand to support the sector as export markets slow, says managing director Abdulaziz Al-Shidhani.
Speaking to MEED after Hydrom awarded two projects under its third auction round and launched a fourth round linked to data centres at UN climate change conference Cop31 in Antalya, Al-Shidhani says interest in the third round had been satisfactory but below earlier levels.
“There was a good interest, satisfactory to the auction itself, but it was not as big as it was in round one specifically,” he says. “[That is] reflecting the overall market sentiment when it comes to green hydrogen.”
Hydrom does not disclose the number of auction bids it receives.
Domestic demand
According to Al-Shidhani, regulatory slowdowns in Europe and slower progress in markets such as South Korea and Japan prompted Hydrom to look for buyers at home.“We decided last year to start exploring each and every avenue domestically to support decarbonising our industries and introducing green solutions for expanding the industrial base within Oman itself,” he says.
Steel, methanol, mobility, hydrogen-to-power and data centres are among the applications that are under review. A natural gas supply agreement was recently signed for a green direct reduced iron (DRI) plant, which carries a mandate to replace natural gas with green hydrogen in the early 2030s. Hydrom is helping first-round developers in Duqm reach a commercial agreement with the DRI investor.
Data centres
The fourth round, the Green-Powered Data Centre Hydrogen Auction, will be held in Dhofar Governorate. The city of Salalah was chosen for its connectivity, cooler climate and seawater cooling.
Al-Shidhani says the national grid is not yet in a position to supply hyperscalers requiring 100MW or more. The Energy & Minerals Ministry and the Transport, Communications & Information Technology Ministry mandated Hydrom to design a captive power solution.
“Our work yielded that the best techno-commercial proposition is a blend of renewable electrons supported by batteries and supported by up to 20% firming power through hydrogen gensets,” he says.
The auction is designed for integrated consortiums covering power, hydrogen and data centre hubs. Hydrom will also offer matchmaking for investors that want a partner to supply the energy.
Registration for expressions of interest is open until February 2027. Al-Shidhani says a market sounding exercise had given “a very positive signal”. Hydrom plans to issue the request for qualification by the end of the first quarter of 2027, with requests for proposals expected around mid-year.
Round three
The awards went to a consortium of Petrogas E&P and Italy’s Bio3Energy, which plans to produce about 625,000 tonnes a year (t/y) of green ammonium nitrate, and a consortium of PLN Indonesia Power Renewables, Alawi Enterprises and HBA Offshore International, which plans to produce about 400,000 t/y of green ammonia. Combined green hydrogen output is expected to reach about 121,000 t/y by 2032.
The block offered covers 300 square kilometres and could accommodate up to three projects. One winner has an option on a further 100 square kilometres, which would use the full block.
Al-Shidhani says the land usufruct agreements will be registered with Oman’s Housing Ministry within two to three weeks. Developers then have three and a half years for development work, with a final investment decision expected by the end of year three and financial close six months later. Construction is allotted three and a half years, followed by 40 years of operations.
He says the 2032 production date does not represent a delay to Oman’s 2030 target.
“It is a rolling process,” he says. “The 2030 [projects] were signed in 2023 and 2024. It is a moving target.”
One of the new projects has opted for solar power only at the outset. Hydrom does not specify generation or electrolyser technology. Project finance remains the most common funding route, although Al-Shidhani says export credit agencies could also play a role.
This is a demonstration that Oman is able to produce [some of] the lowest-cost hydrogen
First production
The first phase of India-based Acme Group’s project in Duqm, which will produce 100,000 t/y of green ammonia, is expected to start production in Q2 2027. Al-Shidhani, who visited the site in October, says major components were almost complete.
“This is a demonstration that Oman is able to produce [some of] the lowest-cost hydrogen and deliver it competitively to markets, and we are not talking about small quantities,” he says.
He expects the first export cargo to convince sceptical investors that Oman can produce hydrogen for less than $3 a kilogram. Other first- and second-round developers are still negotiating offtake before moving to front-end engineering and design.
Further rounds
Al-Shidhani says the awarded projects use approximately 4% of the land available to Hydrom, and that further auctions are certain. Oman’s strategy targets 8.5 million t/y of green hydrogen by 2050.
Hydrom paused for almost a year after the second auction round, and the timing of future rounds will depend on the market.
“It is all about selecting the right time to go to the market,” he says. “In terms of whether there would be round five or round six, the answer is definitely there would be.”
https://image.digitalinsightresearch.in/uploads/NewsArticle/21573009/main.gif -
Contractors submit best offers for Oxagon Highway 5519 November 2026

Contractors have submitted their best and final offers for a design-and-build contract to upgrade Highway 55 in Saudi Arabia’s Oxagon region.
The first phase of the project includes the construction of 14 kilometres of road, with two lanes in each direction, as well as one bridge and three interchanges.
The project is expected to take 22 months to complete.
Contractors initially submitted bids on 28 September, as MEED exclusively reported.
Highway 55 connects the Red Sea coast with the mainland in northwestern Saudi Arabia. It is currently the only road providing north-south connectivity between Duba and the Neom region.
MEED reported exclusively in August last year that contractors had submitted responses to an expression of interest notice that Neom had issued earlier that month.
The project is expected to support cargo movement from Duba Port to other parts of the kingdom and the wider region.
Last year, Neom tested a pilot initiative by handling a shipment that travelled from Cairo via the Port of Safaga, across the Red Sea to the Port of Neom, and then inland to Erbil, Iraq.
In a statement, Neom said: “The shipment travelled through an intermodal corridor spanning over 900 kilometres, marking a significant milestone in the kingdom’s transformation into a regional and global logistics hub.”
READ THE NOVEMBER 2026 MEED BUSINESS REVIEW – click here to view PDFGulf projects keep moving amid conflict; UAE's state spending and oil output flexibility cushion Iran war shock; Project finance lenders weigh risk against infrastructure needs.
Distributed to senior decision-makers in the region and around the world, the November 2026 edition of MEED Business Review includes:
> AGENDA: GCC projects market holds its nerve> MARKET FOCUS: UAE economy shows resilience> INDUSTRY REPORT: Project financiers hold the line> STADIUMS: Stadium spending set to jump 39% in 2027> CONFLICT: Hormuz closure wipes out growth in 2026> INTERVIEW: WSP regional president Dean McGrail> INTERVIEW: Ministry of Energy & InfrastructureTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/21556022/main.jpg -
Construction starts on Damascus hotel and mall19 November 2026
Construction has started on the Movenpick Hotel and Arab Mall development in the Kafr Sousa district of Damascus.
Rotana Star Holding and Sankari Holding are backing the project, which Syria’s Ministry of Tourism is developing under its patronage.
The project marks Accor’s entry into the Syrian market. The France-based hotel group signed an agreement earlier this year to manage the project’s Movenpick Hotel component.
The integrated development will cover more than 90,000 square metres (sq m) and combine hotel, retail, entertainment and supporting facilities.
The Movenpick Hotel will occupy more than 25,000 sq m and include 300 accommodation units. Facilities will include event and celebration halls, restaurants with panoramic views, and health and fitness amenities.
Arab Mall will cover more than 65,000 sq m across seven levels. It will include retail units, entertainment facilities and service areas.
The developers expect Arab Mall to open in the first quarter of 2028, followed by the hotel in the first quarter of 2029.
Accor acquired the Swiss-founded Movenpick brand in 2018. Under the management agreement, Accor will operate the hotel and provide access to its global reservation, distribution and marketing platforms.
The development is expected to create direct and indirect employment across construction, engineering, hospitality, retail and services.
The project is being advanced as Syria seeks to expand its tourism and hospitality capacity.
Syria’s Ministry of Tourism has reported that the country received 3.52 million visitors in the first half of 2026, 111% more than in the same period of 2025.
The ministry said foreign tourist arrivals increased by 448%, while Arab visitor numbers rose by 107%.
READ THE NOVEMBER 2026 MEED BUSINESS REVIEW – click here to view PDFGulf projects keep moving amid conflict; UAE's state spending and oil output flexibility cushion Iran war shock; Project finance lenders weigh risk against infrastructure needs.
Distributed to senior decision-makers in the region and around the world, the November 2026 edition of MEED Business Review includes:
> AGENDA: GCC projects market holds its nerve> MARKET FOCUS: UAE economy shows resilience> INDUSTRY REPORT: Project financiers hold the line> STADIUMS: Stadium spending set to jump 39% in 2027> CONFLICT: Hormuz closure wipes out growth in 2026> INTERVIEW: WSP regional president Dean McGrail> INTERVIEW: Ministry of Energy & InfrastructureTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/21555695/main.jpeg -
Kuwait discusses retender of $7.7bn of oil projects19 November 2026

State-owned upstream operator Kuwait Oil Company (KOC) is discussing the retendering of upstream projects worth an estimated $7.7bn, according to industry sources.
The tender processes for all four contracts were cancelled earlier this year after the lowest bids exceeded the projects’ approved budgets.
The projects are:
- Separation Gathering Centre 1 (SGC-I) and Water Injection Plant (WIP-1)
Previous low bidder: Tecnicas Reunidas (Spain) – $2.47bn - Separation Gathering Centre 3 (SGC-3) and Water Injection Plant (WIP-3)
Previous low bidder: Larsen & Toubro (India) – $2.48bn - Installation of Water Injection Plant (WIP-4)
Previous low bidder: Petrofac (UK) – $1.48bn - Effluent Water Disposal Plants 1 & 2 expansion project (EWDP 1&2)
Previous low bidder: Larsen & Toubro (India) – $1.30bn
KOC is considering a strategy under which pipeline and network installation work would be removed from the main contract scopes and tendered separately, the sources said.
The company is also planning to relaunch the four main packages under a build-own-operate model rather than the engineering, procurement and construction (EPC) model used previously.
KOC is expected to tender the pipeline and network packages on an EPC basis, or under a similar delivery model.
In addition, KOC is discussing increases to the projects’ approved budgets to enable contractors to submit compliant bids, the sources said.
Since KOC cancelled the four tenders in January, Kuwait’s oil and gas sector and the wider economy have faced disruption linked to the regional conflict that began after the US and Israel attacked Iran on 28 February.
The conflict has reduced shipping through the Strait of Hormuz, limiting Kuwait’s ability to export crude oil.
READ THE NOVEMBER 2026 MEED BUSINESS REVIEW – click here to view PDFGulf projects keep moving amid conflict; UAE's state spending and oil output flexibility cushion Iran war shock; Project finance lenders weigh risk against infrastructure needs.
Distributed to senior decision-makers in the region and around the world, the November 2026 edition of MEED Business Review includes:
> AGENDA: GCC projects market holds its nerve> MARKET FOCUS: UAE economy shows resilience> INDUSTRY REPORT: Project financiers hold the line> STADIUMS: Stadium spending set to jump 39% in 2027> CONFLICT: Hormuz closure wipes out growth in 2026> INTERVIEW: WSP regional president Dean McGrail> INTERVIEW: Ministry of Energy & InfrastructureTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/21532374/main.jpg - Separation Gathering Centre 1 (SGC-I) and Water Injection Plant (WIP-1)
-
Saudi Arabia cancels more water tenders19 November 2026

Two tenders for a major water pipeline project in Saudi Arabia have been cancelled, marking the second major water infrastructure project in the kingdom to have its tender process called off this month.
The tenders cover Package B and the combined Packages C1 and C3 of the New Water Pipeline to Feed Riyadh City 2 project, being developed by Water Transmission Company (WTCO).
A source close to the project told MEED that bidders were notified of the decision earlier in November.
The three packages have a combined value of about $556m and involve the construction of a long-distance potable-water transmission system to strengthen supplies to Riyadh.
The wider masterplan includes approximately 136 kilometres of pipeline, with diameters ranging from 64 inches to 100 inches. The scope also includes 10 steel storage tanks with capacities ranging from 100,000 cubic metres to 170,000 cubic metres.
According to regional tracker MEED Projects, Saudi Services for Electro-Mechanic Works was appointed as the main contractor for Package B in 2025, with a reported contract value of $279.6m. Another local firm, Al-Rawaf Trading & Contracting, was appointed for Packages C1 and C3, with a combined contract value of $276m. Multiple other contractors submitted bids for the three packages.
As MEED understands, construction was expected to start earlier this year.
The cancellations follow the withdrawal of a tender for a 300-million-litres-a-day seawater reverse osmosis desalination plant at Yanbu, valued at $272m.
As reported by MEED on 16 November, Saudi Water Authority cancelled the Yanbu tender despite India’s VA Tech Wabag receiving the contract award in July 2025.
The contractor disclosed the decision in a filing to Indian stock exchanges, saying the tender was cancelled due to “internal reasons” on the authority’s side.
It is the second time a tender has been cancelled for the project at the final award stage.
It is unclear whether the desalination or transmission-pipeline projects will be retendered and, if so, whether their scopes will remain unchanged. MEED has contacted WTCO for comment.
READ THE NOVEMBER 2026 MEED BUSINESS REVIEW – click here to view PDFGulf projects keep moving amid conflict; UAE's state spending and oil output flexibility cushion Iran war shock; Project finance lenders weigh risk against infrastructure needs.
Distributed to senior decision-makers in the region and around the world, the November 2026 edition of MEED Business Review includes:
> AGENDA: GCC projects market holds its nerve> MARKET FOCUS: UAE economy shows resilience> INDUSTRY REPORT: Project financiers hold the line> STADIUMS: Stadium spending set to jump 39% in 2027> CONFLICT: Hormuz closure wipes out growth in 2026> INTERVIEW: WSP regional president Dean McGrail> INTERVIEW: Ministry of Energy & InfrastructureTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/21527730/main.jpg